This presentation was given during the Spring, 2012 Data Center World Conference and Expo. Contents contained are owned by AFCOM and Data Center World and can only be reused with the express permission of ACOM. Questions or for permission contact: [email protected] . Interested in data center management? Learn about the data center management sessions offered at the upcoming Fall 2012 Data Center World Conference at: www.datacenterworld.com .

Transcript of Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

Page 1: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

This presentation was given during the Spring, 2012 Data Center World Conference and Expo. Contents contained are owned by AFCOM and Data Center World and can only be reused with the express permission of ACOM. Questions or for permission contact: [email protected].

Interested in data center management?

Learn about the data center management sessions offered at the upcoming Fall 2012 Data Center World Conference at:

www.datacenterworld.com.

Page 2: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

Protocols and Procedures for Proven Success

Sean Roome, Site Manager, Technisource

Page 3: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success
Page 4: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success
Page 5: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

Not just tapes anymore Expand their Capabilities

◦Proven Procedures◦Clear Responsibilities

Expand Responsibilities◦Extensive Knowledge Base

Enable 24/7 Shops◦Security Benefits◦Extend the Helpdesks hours

Hands on Learning / Training Go getters move up the chain Promote from within

Page 6: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

Dropped Balls◦ Mistakes made in general◦ Dead lines missed◦ Tasks slip through the cracks

Failure to follow procedures Lack of communication between Ops Failure to communicate with management Lack of knowledge Needless support calls Blame game

Page 7: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

Guarantee updated procedures Proper ticket logging Accountability Unambiguous turnover Less Support calls Ever-increasing knowledge database Operator confidence Self policing A+ on operational audits

Page 8: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

Procedures Turnover Email Handling Ticket System Knowledge Base Support Calls

Page 9: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

Dwight Schrute

Page 10: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

Nothing done without procedures◦ Must contain all tasks◦ No procedures = STOP◦ Indexed◦ Hyperlinked◦ Hard and Soft copies◦ Separate Helpdesk and Operations◦ Putting in the time now will pay off later◦ Training is a breeze◦ Consistency◦ Accountably◦ Reliability

Page 11: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

Accuracy◦Must be up to date◦Operators must email inaccuracies to

management◦Audit by the Operators is mandatory◦Confidence builder

Page 12: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

Reverse Turnover

◦Check first, ask questions later◦Gather information via a checklist◦Review the last 24 hours Emails Moved Room is neat / organized Check for any outstanding warnings /

failures Ticket system checked for accuracy and

completeness Checklist from other shifts checked

Page 13: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

Accountable for shift when complete

◦What you will get: New shifts asking questions from prior shifts –

increased communication Operations Auditing previous work Operations awareness of ongoing and

previous issues

◦What you won’t get: “I told them” “I forgot to tell them” “I Don’t know about that”

Page 14: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

Clean Inbox◦Only current or near future action items◦Distant action items can go into the

Ticket System◦No clutter, no confusion◦Important tasks not overlooked◦Constant maintenance Task is done, move it Ticket created, move it Not pertinent, move it

Page 15: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

Limited amount of folders◦Completed / Acknowledged◦Warnings and Failures◦Informational

Nothing gets deleted Archive system in Place

Page 16: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

All tasks performed All issues encountered Complete listing of all actions taken Big or Small – Ticket System should have

it all Invaluable turnover tool The tickets need to be consistently written

and leave no room for question Who, Conversation, Times No surprises

100% Accurate Managers job to audit Helps current issues to be resolved

sooner using past events

Page 17: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

Tracks changes to the procedure book Great for external audits Knowledge Gets better and better

overtime, more and more reliable Used also as a knowledge base

Page 18: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

Built over time Limit locations – no duplicate information

◦Procedure book Routine tasks Specific Instructions DR Procedures Server Reboot instructions

Default Special

Page 19: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

◦Ticket System Auto generation / integration

capabilities Past Issue handling details Knowledge built with every event Tracks Issues / Trends

“Top Ten” Establish weekly meeting to review

Used to create metrics Separate Ops & Helpdesk tasks with

categories Audited by Ops and management

Page 20: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

Establish a flow chart◦Initiation◦Management awareness◦Follow-up

Perform pre-call trouble shooting ◦Prior events and solutions Reference the procedure book Reference the Knowledge database

◦Present all the facts to support personnel Current failure Past Failure and resolution

Page 21: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

◦All facts and the solution must be logged in the ticketing system

◦Follow up with emails to support staff to better build the DB Future failure instructions

◦Establish weekly meetings, review the “Top Ten”

Off-hour support calendar◦Preferred numbers◦Backup person◦Establish an escalation policy

Page 22: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

Procedures Turnover Email Handling Ticket System Knowledge Base Support Calls

Page 23: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

◦All tasks◦Accurate◦Followed, no deviation◦Stop if wrong or unclear◦Nothing done without them◦Audited

Page 24: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

◦Reverse - gather first, questions later◦24 hour review◦Accountable when done

Page 25: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

◦Keep it clean◦Limit the amount of folders◦Move it◦Nothing gets deleted◦Archive system in place

Page 26: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

◦Everything goes in◦Details, details, details◦Invaluable “Top Ten” tracking tool ◦Manager audits

Page 27: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

◦Built over time◦Referenced frequently

Page 28: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

◦Establish a clear and concise Flow Chart◦Gather facts before the call◦Off-hour support calendar◦Establish a clear escalation policy

Page 29: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

Expanded Capabilities Greater Responsibilities Hybrid Ops/Helpdesk Extended HD hours At hand Job Pool Promote from within

Page 30: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success
Page 31: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success
Page 32: Develop an Elite Data Center Operations Staff: Protocols and Procedure for Proven Success

This presentation was given during the Spring, 2012 Data Center World Conference and Expo. Contents contained are owned by AFCOM and Data Center World and can only be reused with the express permission of ACOM. Questions or for permission contact: [email protected].

Interested in data center management?

Learn about the data center management sessions offered at the upcoming Fall 2012 Data Center World Conference at:

www.datacenterworld.com.