DETAILS OF ONGOING LINES UNDER … of the firm M/s Maharashtra Power Transmission Structures Ltd....

42
Length Est. cost km crores Agency LOI SCh comp Survey Foundation Erection Stringing 1 765 kV s/s Anpara D (Areva) 400 kV dc q Anpara B-Anpara D ETD8 05/09 5.03 28.72 13.10.09 22.01.10 24.02.10 REC- 047- 2010-3769 MPTL/ Local 11.10.10 28.02.11/ 30.06.13 (Extn.) Comp 23/23 21/23 3/ 5.032 88.17 Contract of the firm M/s Maharashtra Power Transmission Structures Ltd. has been terminated on 20.05.2014 and LOI no. 2879/ETC(M)T-Tender issued by the SE, Mirzapur on 30.12.14 for the balance work. Work in progress. 2 765 kV s/s Unano (CG) 765 kV Anpara D- Unnao (up to Jhusi) ETD8 03/09 187.0 03.05.08 29.01.09 03.02.09 Jyoti 02.02.10 01.02.12 187/ 187 362/542 318/542 72.563/ 187 67.09 1.forest clearance 2. Railway Crossing 3. Power Line Crossing 4.Foundation 765 kV Anpara D- Unnao (Jhusi onwards) ETD8 03/09 238.8 03.05.08 29.01.09 03.02.09 Gammon 02.02.10 01.02.12 239/ 239 672/673 671/673 227.395/ 238.833 98.71 1.forest clearance 2. Railway Crossing 3. Power Line Crossing 1 400 kV s/s Aurai (PPP I) 220 kV sc Aurai400- Phoolpur TD-329 71.2 35.60 SEW 26.10.10 25.10.11 Comp 210/216 195/216 48.054/ 71.2 89.2 1. Termination point at 400KV S/S Aurai not yet decided,last 02 section work held up due to this. 2. ROW at location 2/1, 3/0 , 4/0, 5/0, 12/0, 12/1,12/ 2,17/ 5,39/3,53/0, 53/1, 53/3 being persued. 220 kV sc Aurai400- Mirzapur TD-329 42 21.00 SEW 26.10.10 25.10.11 Comp 129/147 82/147 0/42 62.9 1.Termination point at 400KV S/s Aurai not yet decided. 2. River crossing work to be taken up. 3.Severe ROW at 15 locations being persued. Progress ED % Prog. Plan /Remarks 751.61 676.44 DETAILS OF ONGOING LINES UNDER TRANSMISSION EAST Sl. no Name of work Tender No. TWC BOD ETF Loan (in Cr.) Work

Transcript of DETAILS OF ONGOING LINES UNDER … of the firm M/s Maharashtra Power Transmission Structures Ltd....

Length Est. cost

km crores Agency LOI SCh comp Survey Foundation Erection Stringing

1765 kV s/s Anpara D (Areva)

400 kV dc q Anpara B-Anpara D

ETD8 05/09

5.03 28.72 13.10.09 22.01.10 24.02.10REC- 047-2010-3769

MPTL/ Local

11.10.1028.02.11/ 30.06.13 (Extn.)

Comp 23/23 21/233/

5.03288.17

Contract of the firm M/s Maharashtra Power

Transmission Structures Ltd. has been terminated

on 20.05.2014 and LOI no. 2879/ETC(M)T-Tender

issued by the SE, Mirzapur on 30.12.14 for the

balance work. Work in progress.

2765 kV s/s Unano (CG)

765 kV Anpara D-Unnao (up to Jhusi)

ETD8 03/09

187.0 03.05.08 29.01.09 03.02.09 Jyoti 02.02.10 01.02.12187/ 187

362/542 318/54272.563/

18767.09

1.forest clearance 2. Railway Crossing

3. Power Line Crossing 4.Foundation

765 kV Anpara D-Unnao (Jhusi onwards)

ETD8 03/09

238.8 03.05.08 29.01.09 03.02.09 Gammon 02.02.10 01.02.12239/ 239

672/673 671/673227.395/ 238.833

98.711.forest clearance

2. Railway Crossing 3. Power Line Crossing

1400 kV s/s Aurai (PPP I)

220 kV sc Aurai400-Phoolpur

TD-329 71.2 35.60 SEW 26.10.10 25.10.11 Comp 210/216 195/21648.054/

71.289.2

1. Termination point at 400KV S/S Aurai not yet decided,last 02 section

work held up due to this.2. ROW at location 2/1,

3/0 , 4/0, 5/0, 12/0, 12/1,12/ 2,17/

5,39/3,53/0, 53/1, 53/3 being persued.

220 kV sc Aurai400-Mirzapur

TD-329 42 21.00 SEW 26.10.10 25.10.11 Comp 129/147 82/147 0/42 62.9

1.Termination point at 400KV S/s Aurai not yet

decided. 2. River crossing work to

be taken up. 3.Severe ROW at 15

locations being persued.

ProgressED

% Prog.

Plan /Remarks

751.61 676.44

DETAILS OF ONGOING LINES UNDER TRANSMISSION EAST

Sl. no

Name of workTender

No.TWC BOD ETF

Loan (in Cr.)

Work

132 kV DC Aurai400-Aurai132

TD-348 5.99 4.39 Archon 18.06.11 17.06.12 Comp 30/35 23/35 0/5.99 64.6

Construction of 400 KV Aurai not yet started,

gantry of both ends not finalised, no gang

deployed by firm, as per local unit firm is not working even on locs

where reach is available.The proposed

date of complition is 31.12.15.

132 kV dc Aurai4oo-Gopiganj

TD-348 12.37 4.82 Archon 18.06.11 17.06.12 Comp 38/57 36/57 0/12.4 59.30 do

132 kV dc Aurai4oo-Rajakatalab

TD-348 35.49 13.84 Archon 18.06.11 17.06.12 Comp 106/126 96/12612.52/ 35.49

75.09 do

LILO of132 kV Bhadohi-Jaunpur line @ Aurai400

TD-348 30.48 11.89 Archon 18.06.11 17.06.12 Comp 93/109 86/1091.35/ 30.48

67.6

Rly xing approval received, agreement with Rly to be done, no gang present at site.The proposed date of

complition is 31.12.15.

132 kV dc Gopiganj-Gyanpur

TD-348 23.9 7.41 Archon 18.06.11 17.06.12 Comp 73/83 68/835.98/ 23.9

74.6

Major ROW at 10 locs, letter written from MD to District Administration for

resolving of ROW, gang not deployed by the firm,

Rly xing approval & demand note awaited, Rly

being persued at local level

2 400 kV S/s Masauli

LILO of one ckt of Meja - Rewa Road 400kV DC Line (Q) at Masauli

30 5018.07.14/ 02.01.15

22.07.14 26.07.14

Maan Structures, Jaipur & Shyama Power

27/30 0/90 0/90 0/30 9

132 kV LILO of Karchana- Naini SC Line @Masauli

35 17.518.07.14/ 02.01.15

22.07.14 26.07.14Archon/ Monte carlo

08.09.15 07.08.16

Line withdrawn from M/s Archon Engicon and

allotted to M/s MonteCarlo on 08.09.15,

firm is in process of taking up work. The proposed

date of complition is 07.08.16.

132 KV LILO Meja road- Rewa Road SC Line @Masauli

30 7.418.07.14/ 02.01.15

22.07.14Archon/ Monte carlo

08.09.15 07.08.16

Line withdrawn from M/s Archon Engicon and

allotted to M/s MonteCarlo on 08.09.15,

firm is in process of taking up work. The proposed

date of complition is 07.08.16.

1220 kV s/s Rasra (Ballia) (TKSAS)

220 kv sc Deoria-Rasra

TD-329 83.0 41.50 SEW 23.03.10 22.03.11 Comp 253/253 252/253 82/83 99.62

1. Rly crossing approved, fund Released from HQ

2. Shifting of 11 KV line to be done by Distribution

wing awaited, estimate for shifting already deposited,

matter being persued.3. River Xing work to be

taken up.

LILO of 132 kv Deoria - Salempur line @ 220KV Deoria

3.0 2.66 21.05.12 18.07.12 2.4 Local Comp 0/12 0/12 0/3 12th

132 kv SC Rasra220-Haldharpur

TD-348 20.3 6.29 Archon 18.06.11 17.06.12 Comp 76/77 70/7715.9/ 20.3

92.44Estimate from Railways of

Rly xing awaited, WIP, Er(1gang), Str(1 gang).

132 kv SC Dighar-Rasra220

TD-348 65.86 20.40 Archon 18.06.11 17.06.12 Comp 200/210 160/2103.5/

65.8670.38

Estimate for 2 no Rly xing submitted, WIP, Fdn (1

gang).The proposed date of complition is 31.12.15.

2 220 Kv Ghazipur s/s

IInd Interconnector 132 kV sc Gazipur 220-Gazipur132

5.43 1.27 Umawalla 2/12 2/12 Comp 100% 100% 100% 99

Foundation completed erection 14 was

completed out of 16 Nos. 99%.

132 kv sc Gazipur220-Gazipur132

7.4 1.27 Local 31.03.10 31.10.10 5.4 14/16 12/16 3.5/5.4

3220 kv s/s Sirathu (TKSAS)

132 kv sc Sirathu220-Khaga

TD-348 33.6 10.42 Trading 23.12.11 22.12.12 Comp 75/102 50/102 0/33.6 58.2

1.Erection in progress. 2.Tower diverted to Kunda-Manikapur and Sarai Aquil

line. Same is being arranged by local unit. 3.Profile under revision

from both the ends due to DFCC. 4.One Erection, Foundation & Stringing

gang to be deployed after revision of profile.

The proposed date of complition 29.02.16.

4220 kv s/s Pratapgarh (RNN)

LILO of220 kV Sultanpur-Phoolpur line @Pratapgarh

TD-329 23.78 15.22 PNC 27.04.10 26.04.11 Comp 80/80 80/8023.08/ 23.78

99.26Str ROW 76-78, being

persued

5220 kv s/s Bansi (TKSAS)

220 kv LILO Gorakhour(PG)-Basti@Bansi

TD-329 50.0 6.20 Archon 18.06.11 17.06.12 Comp 53/155 12/155 0/50 40.10

Work stopped due to rain as low lying area due to

Terai region. The proposed date of

complition is 31.12.15.

132 kv SC Bansi-Dumariaganj

TD-348 35.67 11.56 Archon 18.06.11 17.06.12 Comp 36/115 12/115 0/35.67 39.9

Work stopped due to rain as low lying area due to

Terai region. The proposed date of

complition is 31.12.15.

132 kv SC Bansi-Mehdawal

TD-348 31.18 9.67 Archon 18.06.11 17.06.12 Comp 83/110 72/110 0/31.18 62

Work stopped due to rain as low lying area due to

Terai region. The proposed date of

complition is 31.12.15.

6220 kv s/s Robertsganj (TKSAS)

220 kv LILO Obra-Sahupuri I Ckt.@Rbj

TD-348 4.5 0.9926.08.10/ 31.10.14/ 30.09.15

M/S J.P. Associates on Depsoit

15/15 14/152.0/

3.190

TWC has been approved new proposal for

construction of LILO line. WIP.

220 kv LILO Obra-Sahupuri II Ckt. @Rbj

4.531.10.14/ 30.09.15

132KV LILO of 132KV Roertsganj-Sahupri Ckt-I at 132KV S/S Mughalsarai by under ground cable.

1.5

Eagle construction

, Mughalsarai

14.03.14 WIP 15/15 0/11 0/1.5

Tower part awaited. LT lines are to be shifted. (Overhead line is being

constructed at field level instead of underground

cable line)

7220 kv s/s Bhelupur (Dept)

220 kv dc Sahupuri-Bhelupur(O/H-15)

TD-313 8.94 5.72

Scantec/ Marut

Construction Company, Jaunpur

19.01.09 18.11.09 Comp 39/39 38/397.326/

9.0990.9

Higher water level of river (river crossing).

220 kv dc Sahupuri-Bhelupur( U/G-5)

TD-317 5.36 Universal5.36/ 5.36

100

8220 kv s/s Gajokhar (Dept)

220 kV SC Gajokhar- Jaunpur line

TD-313 37.62 18.06 PNC 23.08.08 22.08.09 Comp 132/132 132/13231.75/ 37.62

98.8

3 Rly Xing & one section of gantry side remaining, Rly

block awaited, firm has been requested to

intimate the date for block, 03 Str gangs

present at site

132 kV SC Gajokhar-Raja ka talab line

TD-313 40.627 11.63 PNC 23.08.08 22.08.09 Comp 122/122 122/12240/

40.62799.61

2 Rly Xing & one section stringing work remaining,

Rly block awaited, firm has been requested to

intimate the date for block

2*220 Kv bays@ Sarnath400 & Jaunpur

3.34 Dept 25/48

9 220 kv s/s Harhua

Cable laying 100% completed. (37.5km/37.5 km Cable laid)

220 kv LILO Sarnath-Azamgarh@ Harhua

TD-348 20.8 13.1 A2Z 23.08.11 22.08.12 Comp 75/75 69/7510.17/ 21.85

85

1 Stringing gang working at site , 1 no Er gang

present at site, firm asked to increase str gang and

deploy erection gang immediately.

10220 kv s/s Bhadaura

LILO of 220kv Sarnath- Sahupuri line @ Bhadaura

52.57

31.6417.05.13/ 30.09.15

17.05.13Archon/E

MC31.07.15 30.11.16

Survey to being completed by 10.10.15. The proposed

date of competion is 30.11.16

LILO of 132kv Ghazipur- Jamania line @ Bhadaura

20.91

6.26 17.05.13 17.05.13Archon/E

MC31.07.15 30.06.16 Comp 01/62 0/62 10.4

Profile approved, 01 no. Fdn under progress.

The proposed date of competion is 30.06.16

132kv SC Bhadaura-Kundesar line

20.66 5.82 17.05.13 17.05.13Archon/E

MC31.07.15 30.06.16 Comp 0/66 0/66 10

Profile approved, 01 no. Fdn under progress.

The proposed date of competion is 30.06.16

11220 kv s/s Azamgarh -II

220kV SC Sarnath(400kV) - Azamgarh -II(220kV) Line on DC Tower

60 32 18.07.14 22.07.14 26.07.14Archon/ Monte carlo

08.09.15 07.11.16

Line withdrawn from M/s Archon Engicon and

allotted to M/s MonteCarlo on 08.09.15,

firm is in process of taking up work. The proposed

date of complition is 07.12.16.

220 kV SC Auraui(400)- Azamgarh -II (220kV) Line on DC Tower

74.8 62 18.07.14 22.07.14 26.07.14 Trading 74.8

1.Stubs & Templates delivered at site.

2. 6 nos. FDN gangs to be deployed shortly. The

proposed date of complition is 31.10.16.

132 kV SC Azamgarh-II (220kV) - Azamgarh(sidhari) Line on DC Tower

46 16 18.07.14 22.07.14 26.07.14Archon/ Monte carlo

08.09.15 07.08.16

Line withdrawn from M/s Archon Engicon and

allotted to M/s MonteCarlo on 08.09.15,

firm is in process of taking up work. The proposed

date of complition is 07.08.16.

132 kV SC Kerakat - Azamgarh-II(220kV) Line on DC Tower

20.18 12 18.07.14 22.07.14 26.07.14Archon/ Monte carlo

08.09.15 07.08.16

Line withdrawn from M/s Archon Engicon and

allotted to M/s MonteCarlo on 08.09.15,

firm is in process of taking up work. The proposed

date of complition is 07.08.16.

132 kV SC Phulpur - Azamgarh-II(220kV) Line on DC Tower

45 15.5 18.07.14 22.07.14 26.07.14Archon/ Monte carlo

08.09.15 07.08.16

Line withdrawn from M/s Archon Engicon and

allotted to M/s MonteCarlo on 08.09.15,

firm is in process of taking up work. The proposed

date of complition is 07.08.16.

132KV DC Azamgarh (220)-II- Lalganj line

20 01.04.15

12220 kv s/s Raja ka Talab

220 kV SC Line Raja ka Talab- 400 kV Aurai on DC Tower

11.5 16.718.07.14/ 02.01.15

22.07.14 26.07.14 Trading 11.5 0/38 0/38 0/11.5 10

1.Stubs & Templates delivered at site.

2. 2 nos. FDN gangs to be deployed shortly. The

proposed date of complition is 30.04.16.

220 kV SC Line Raja ka Talab- 220 kV Sahupuri on DC Tower

60.8 19.818.07.14/ 02.01.15

22.07.14 26.07.14 Trading 60.8 0/188 0/188 0/60.8 10

1.Stubs & Templates delivered at site.

2. 3 nos. FDN gangs to be deployed shortly. The

proposed date of complition is 31.08.16.

LILO of 132 kV SC Raja ka talab(132)- Aurai(400) Line @Raja Ka Talab (220)

4.5 218.07.14/ 02.01.15

22.07.14 26.07.14 Trading 4.5 0/17 0/17 0/4.5 10

1.Stubs & Templates delivered at site.

2. 1 nos. FDN gangs to be deployed shortly. The

proposed date of complition is 31.12.15.

132 KV SC line Raja ka Talab(220)- Kursato on DC Tower

25 8.1518.07.14/ 02.01.15

22.07.14 26.07.14 Trading 25 0/54 0/54 0/25 10

1.Stubs & Templates delivered at site.

2. 2 nos. FDN gangs to be deployed from 01.10.15.

The proposed date of complition is 30.04.16.

1 132kV S/s Kursato

LILO of 132kV SC line Raja ka talab(132)-Gajokhar @ Kursato S/s

1.5 1.518.07.14/ 02.01.15

22.07.14 26.07.14 Trading 1.5 0/9 0/9 0/1.5 10

1.Stubs & Templates delivered at site.

2. 1 nos. FDN gangs to be deployed shortly. The

proposed date of complition is 31.12.15.

3132 kv s/s Chakia (TKSAS)

132 kv LILO Sahupuri-Robertsganj@Chakia

TD-329 21.7 8.08 Aravali 28.04.10 27.04.11 Comp 78/81 76/81 5/21.7 78

Forest clearance approved, firm has started

Fdn work. The proposed date of completion is

30.11.15.

4132 kv s/s Mubarakpur

132 kv SC Azamgarh(220)-Mubarakpur line

15.0 5.37

(Old 17.05.13)

(New 23.01.09)

11.07.1310.5527

(With S/S)Varrsana 07.11.14 06.11.15 Comp 16

Profile approved, inspection of stubs waived

off, fdn work to start immediately.

5132 kv s/s Rudrapur (TKSAS)

132 kv sc Deoria220-Rudrapur

20 7.09Archon/E

MC31.07.15 30.06.16

Survey to start from 05.10.2015. The proposed

date of competion is 30.06.16

6132 kv s/s Nathnagar (TK Techno)

LILO of132 kv Basti-Khalilabad line @ Nathnagar

TD-329 15.55 6.06 Aravali/

Jyoti01.04.11 01.04.12 Comp 50/57 43/57 0/15.55 67.02

WIP, material received, 1 Fdn & 1 Ere gang at site.

The expected date for energisation is 23.12.15

7 132 kv s/s DLW132 kV SC DLW(UPPTCL)-DLW(Deposit)

0.2 7.26 UPPTCL

8132 kv s/s Allahabad Old PH (GIS)

LILO of 220 kV Reewa Road - Cantt Line at 132 kV GIS Old P/H Allahabad(77)

10 48.4 26.10.12 11.12.12 12.12.12 UPRNN 25.6.12 Comp 0 0 76

9 Kms cable laying completed out of 10 Kms.

12 joint out of 14 completed. WIP. The

proposed date of complition is 31.10.15.

9132 kv s/s ChitbadagaonLILO of 132 kv Rasra-Ballia Line @ Chitbadagaon

20 15.3476 17.05.13 10.74332 Archon 0/27 0/27 0/20 Survey started.

10 132 kv s/s Bharwari

132 kV Dc Sirathu-Bharwari

16.06 14.13 15.02.12 18.7.12 12.12.12Archon/E

MC31.07.15 30.06.16 Comp 05/52 0/52 12.4

Fdn WIP. The proposed date of competion is

29.02.2016

11 132 kv s/s Lalganj

LILO of 132 kv Mirzapur-Jigan ckt II @ 132 kV Lalganj

30.79 16.14 07.09.11 12.12.12Archon/E

MC31.07.15 30.06.16

Route survey to start on 30.09.2015. The proposed

date of competion is 30.06.16

12 132kV S/s Jari

132kV DC Masauli (400) - Jari line

55 13.5718.07.14/ 02.01.15

22.07.14 26.07.14Archon/ Monte carlo

08.09.15 07.11.16

Line withdrawn from M/s Archon Engicon and

allotted to M/s MonteCarlo on 08.09.15,

firm is in process of taking up work. The proposed

date of complition is 07.12.16.

132 kV SC Jari - Shankargarh line on DC Tower

45 15.318.07.14/ 02.01.15

22.07.14 26.07.14Archon/ Monte carlo

08.09.15 07.08.16

Line withdrawn from M/s Archon Engicon and

allotted to M/s MonteCarlo on 08.09.15,

firm is in process of taking up work. The proposed

date of complition is 07.08.16.

13132kV S/s Salai Khurd

132kV DC Masauli(400) - Salai Khurd Line

30 7.5118.07.14/ 02.01.15/ 30.09.15

22.07.14 26.07.14 Trading 25.33 0/94 0/94 0/25.33 10

1.Stubs & Templates delivered at site.

2. 3 nos. FDN gangs to be deployed shortly. The

proposed date of complition is 30.05.16.

LILO of single ckt of 132 kV DC Reewa Rd- Korawan line @ Salai khurd S/s

2.4 1.1618.07.14/ 02.01.15/ 30.09.15

22.07.14 Trading

The line put on hold till alternative is finalized

(UPPTCL letter Ref. 1996/ETDC/1/TD-388/14

dt. 29.05.15).

6132 kv s/s Purnachhpar,Bhatni132 kv SC Deoria(220)-Purnachhpar (Bhatni) Line

40Archon/E

MC31.07.15 30.06.16

Survey work to start from 05.10.15.The proposed

date of competion is 30.06.16

1132 kv sc 2PH Basti-Govindnagar

TD-313 21.6 6.71Aravali/

Jyoti 03.10.08 03,10,09 Comp 72/72 72/72

21.6/ 21.6

100

On 22.05.2014 Agency with drawn. Alloted to M/S Jyoti Allahabad.

Completed in Feb.-15, but Rly TSS is not ready.

2

Height raising of 132 kv Barhua FCI line for Railways under deposit work

1.0East India

Udyog4/4 4/4 0/1

Railway block applied wef 10.10.2014.

3132 kv sc Lalganj-Kunda

TD-348 35.29 10.94 Hythro 23.12.11 23.12.12 Comp 22/116 0/116 0/35.29 34.74

Work stopped from several Months. Proposal

for withdrawal of line moved.

4132 kV SC Anandnagar-Naugarh

TD-348 38.27 11.86 Trading 23.12.11 23.12.12 Comp 45/128 0/128 0/38.27 38.79

1. Line route falls in Terai region so area is mostly submerged in water &

work can be executed only 3-4 months in a year.

2. At present team cannot be deployed due to

standing rice crop & water logged area. 3. 01 no Foundation & Erection

gang to be deployed by 25.10.15.

The proposed date of complition 31.03.16.

5132 kV SC Anandnagar-Maharajganj

TD-348 35.72 11.07 Trading 23.12.11 23.12.12 Comp 98/113 45/113 0/35.72 59.65

1. Line route falls in Terai region so area is mostly submerged in water &

work can be executed only 3-4 months in a year.

2. At present team cannot be deployed due to

standing rice crop & water logged area. 3. 01 no Foundation & Erection

gang to be deployed by 25.10.15.

The proposed date of complition 31.03.16.

6

Replacement by AAAC 132 kv dc Sarnath400-Sarnath132

16.12 4..25 Apar WIP.The proposed date of complition 31.10.15.

7132 kv sc Phoolpur-Handia

40

8132 kv sc Chunar-Mirzapur220

45

92*132 kv bays@Chunar&Mirzapur220

10construction of 2 nos. 132kv 'bays' @ 220kv s/s deoria

12th

11

Replacement of Panther Conductor by HTLS ACCC Conductor at Varanasi

132 Kv Sarnath- Maduadih SC line

29.164 Sterlite 14.08.15 13.08.16 NA NA NALOI issued on 14.08.15. The proposed date of

complition is 13.08.16.

132 Kv Gajokhar-maduadih SC line

33.308 Sterlite 14.08.15 13.08.16 NA NA NALOI issued on 14.08.15. The proposed date of

complition is 13.08.16.