DETAILS OF ONGOING LINES UNDER … of the firm M/s Maharashtra Power Transmission Structures Ltd....
Transcript of DETAILS OF ONGOING LINES UNDER … of the firm M/s Maharashtra Power Transmission Structures Ltd....
Length Est. cost
km crores Agency LOI SCh comp Survey Foundation Erection Stringing
1765 kV s/s Anpara D (Areva)
400 kV dc q Anpara B-Anpara D
ETD8 05/09
5.03 28.72 13.10.09 22.01.10 24.02.10REC- 047-2010-3769
MPTL/ Local
11.10.1028.02.11/ 30.06.13 (Extn.)
Comp 23/23 21/233/
5.03288.17
Contract of the firm M/s Maharashtra Power
Transmission Structures Ltd. has been terminated
on 20.05.2014 and LOI no. 2879/ETC(M)T-Tender
issued by the SE, Mirzapur on 30.12.14 for the
balance work. Work in progress.
2765 kV s/s Unano (CG)
765 kV Anpara D-Unnao (up to Jhusi)
ETD8 03/09
187.0 03.05.08 29.01.09 03.02.09 Jyoti 02.02.10 01.02.12187/ 187
362/542 318/54272.563/
18767.09
1.forest clearance 2. Railway Crossing
3. Power Line Crossing 4.Foundation
765 kV Anpara D-Unnao (Jhusi onwards)
ETD8 03/09
238.8 03.05.08 29.01.09 03.02.09 Gammon 02.02.10 01.02.12239/ 239
672/673 671/673227.395/ 238.833
98.711.forest clearance
2. Railway Crossing 3. Power Line Crossing
1400 kV s/s Aurai (PPP I)
220 kV sc Aurai400-Phoolpur
TD-329 71.2 35.60 SEW 26.10.10 25.10.11 Comp 210/216 195/21648.054/
71.289.2
1. Termination point at 400KV S/S Aurai not yet decided,last 02 section
work held up due to this.2. ROW at location 2/1,
3/0 , 4/0, 5/0, 12/0, 12/1,12/ 2,17/
5,39/3,53/0, 53/1, 53/3 being persued.
220 kV sc Aurai400-Mirzapur
TD-329 42 21.00 SEW 26.10.10 25.10.11 Comp 129/147 82/147 0/42 62.9
1.Termination point at 400KV S/s Aurai not yet
decided. 2. River crossing work to
be taken up. 3.Severe ROW at 15
locations being persued.
ProgressED
% Prog.
Plan /Remarks
751.61 676.44
DETAILS OF ONGOING LINES UNDER TRANSMISSION EAST
Sl. no
Name of workTender
No.TWC BOD ETF
Loan (in Cr.)
Work
132 kV DC Aurai400-Aurai132
TD-348 5.99 4.39 Archon 18.06.11 17.06.12 Comp 30/35 23/35 0/5.99 64.6
Construction of 400 KV Aurai not yet started,
gantry of both ends not finalised, no gang
deployed by firm, as per local unit firm is not working even on locs
where reach is available.The proposed
date of complition is 31.12.15.
132 kV dc Aurai4oo-Gopiganj
TD-348 12.37 4.82 Archon 18.06.11 17.06.12 Comp 38/57 36/57 0/12.4 59.30 do
132 kV dc Aurai4oo-Rajakatalab
TD-348 35.49 13.84 Archon 18.06.11 17.06.12 Comp 106/126 96/12612.52/ 35.49
75.09 do
LILO of132 kV Bhadohi-Jaunpur line @ Aurai400
TD-348 30.48 11.89 Archon 18.06.11 17.06.12 Comp 93/109 86/1091.35/ 30.48
67.6
Rly xing approval received, agreement with Rly to be done, no gang present at site.The proposed date of
complition is 31.12.15.
132 kV dc Gopiganj-Gyanpur
TD-348 23.9 7.41 Archon 18.06.11 17.06.12 Comp 73/83 68/835.98/ 23.9
74.6
Major ROW at 10 locs, letter written from MD to District Administration for
resolving of ROW, gang not deployed by the firm,
Rly xing approval & demand note awaited, Rly
being persued at local level
2 400 kV S/s Masauli
LILO of one ckt of Meja - Rewa Road 400kV DC Line (Q) at Masauli
30 5018.07.14/ 02.01.15
22.07.14 26.07.14
Maan Structures, Jaipur & Shyama Power
27/30 0/90 0/90 0/30 9
132 kV LILO of Karchana- Naini SC Line @Masauli
35 17.518.07.14/ 02.01.15
22.07.14 26.07.14Archon/ Monte carlo
08.09.15 07.08.16
Line withdrawn from M/s Archon Engicon and
allotted to M/s MonteCarlo on 08.09.15,
firm is in process of taking up work. The proposed
date of complition is 07.08.16.
132 KV LILO Meja road- Rewa Road SC Line @Masauli
30 7.418.07.14/ 02.01.15
22.07.14Archon/ Monte carlo
08.09.15 07.08.16
Line withdrawn from M/s Archon Engicon and
allotted to M/s MonteCarlo on 08.09.15,
firm is in process of taking up work. The proposed
date of complition is 07.08.16.
1220 kV s/s Rasra (Ballia) (TKSAS)
220 kv sc Deoria-Rasra
TD-329 83.0 41.50 SEW 23.03.10 22.03.11 Comp 253/253 252/253 82/83 99.62
1. Rly crossing approved, fund Released from HQ
2. Shifting of 11 KV line to be done by Distribution
wing awaited, estimate for shifting already deposited,
matter being persued.3. River Xing work to be
taken up.
LILO of 132 kv Deoria - Salempur line @ 220KV Deoria
3.0 2.66 21.05.12 18.07.12 2.4 Local Comp 0/12 0/12 0/3 12th
132 kv SC Rasra220-Haldharpur
TD-348 20.3 6.29 Archon 18.06.11 17.06.12 Comp 76/77 70/7715.9/ 20.3
92.44Estimate from Railways of
Rly xing awaited, WIP, Er(1gang), Str(1 gang).
132 kv SC Dighar-Rasra220
TD-348 65.86 20.40 Archon 18.06.11 17.06.12 Comp 200/210 160/2103.5/
65.8670.38
Estimate for 2 no Rly xing submitted, WIP, Fdn (1
gang).The proposed date of complition is 31.12.15.
2 220 Kv Ghazipur s/s
IInd Interconnector 132 kV sc Gazipur 220-Gazipur132
5.43 1.27 Umawalla 2/12 2/12 Comp 100% 100% 100% 99
Foundation completed erection 14 was
completed out of 16 Nos. 99%.
132 kv sc Gazipur220-Gazipur132
7.4 1.27 Local 31.03.10 31.10.10 5.4 14/16 12/16 3.5/5.4
3220 kv s/s Sirathu (TKSAS)
132 kv sc Sirathu220-Khaga
TD-348 33.6 10.42 Trading 23.12.11 22.12.12 Comp 75/102 50/102 0/33.6 58.2
1.Erection in progress. 2.Tower diverted to Kunda-Manikapur and Sarai Aquil
line. Same is being arranged by local unit. 3.Profile under revision
from both the ends due to DFCC. 4.One Erection, Foundation & Stringing
gang to be deployed after revision of profile.
The proposed date of complition 29.02.16.
4220 kv s/s Pratapgarh (RNN)
LILO of220 kV Sultanpur-Phoolpur line @Pratapgarh
TD-329 23.78 15.22 PNC 27.04.10 26.04.11 Comp 80/80 80/8023.08/ 23.78
99.26Str ROW 76-78, being
persued
5220 kv s/s Bansi (TKSAS)
220 kv LILO Gorakhour(PG)-Basti@Bansi
TD-329 50.0 6.20 Archon 18.06.11 17.06.12 Comp 53/155 12/155 0/50 40.10
Work stopped due to rain as low lying area due to
Terai region. The proposed date of
complition is 31.12.15.
132 kv SC Bansi-Dumariaganj
TD-348 35.67 11.56 Archon 18.06.11 17.06.12 Comp 36/115 12/115 0/35.67 39.9
Work stopped due to rain as low lying area due to
Terai region. The proposed date of
complition is 31.12.15.
132 kv SC Bansi-Mehdawal
TD-348 31.18 9.67 Archon 18.06.11 17.06.12 Comp 83/110 72/110 0/31.18 62
Work stopped due to rain as low lying area due to
Terai region. The proposed date of
complition is 31.12.15.
6220 kv s/s Robertsganj (TKSAS)
220 kv LILO Obra-Sahupuri I Ckt.@Rbj
TD-348 4.5 0.9926.08.10/ 31.10.14/ 30.09.15
M/S J.P. Associates on Depsoit
15/15 14/152.0/
3.190
TWC has been approved new proposal for
construction of LILO line. WIP.
220 kv LILO Obra-Sahupuri II Ckt. @Rbj
4.531.10.14/ 30.09.15
132KV LILO of 132KV Roertsganj-Sahupri Ckt-I at 132KV S/S Mughalsarai by under ground cable.
1.5
Eagle construction
, Mughalsarai
14.03.14 WIP 15/15 0/11 0/1.5
Tower part awaited. LT lines are to be shifted. (Overhead line is being
constructed at field level instead of underground
cable line)
7220 kv s/s Bhelupur (Dept)
220 kv dc Sahupuri-Bhelupur(O/H-15)
TD-313 8.94 5.72
Scantec/ Marut
Construction Company, Jaunpur
19.01.09 18.11.09 Comp 39/39 38/397.326/
9.0990.9
Higher water level of river (river crossing).
220 kv dc Sahupuri-Bhelupur( U/G-5)
TD-317 5.36 Universal5.36/ 5.36
100
8220 kv s/s Gajokhar (Dept)
220 kV SC Gajokhar- Jaunpur line
TD-313 37.62 18.06 PNC 23.08.08 22.08.09 Comp 132/132 132/13231.75/ 37.62
98.8
3 Rly Xing & one section of gantry side remaining, Rly
block awaited, firm has been requested to
intimate the date for block, 03 Str gangs
present at site
132 kV SC Gajokhar-Raja ka talab line
TD-313 40.627 11.63 PNC 23.08.08 22.08.09 Comp 122/122 122/12240/
40.62799.61
2 Rly Xing & one section stringing work remaining,
Rly block awaited, firm has been requested to
intimate the date for block
2*220 Kv bays@ Sarnath400 & Jaunpur
3.34 Dept 25/48
9 220 kv s/s Harhua
Cable laying 100% completed. (37.5km/37.5 km Cable laid)
220 kv LILO Sarnath-Azamgarh@ Harhua
TD-348 20.8 13.1 A2Z 23.08.11 22.08.12 Comp 75/75 69/7510.17/ 21.85
85
1 Stringing gang working at site , 1 no Er gang
present at site, firm asked to increase str gang and
deploy erection gang immediately.
10220 kv s/s Bhadaura
LILO of 220kv Sarnath- Sahupuri line @ Bhadaura
52.57
31.6417.05.13/ 30.09.15
17.05.13Archon/E
MC31.07.15 30.11.16
Survey to being completed by 10.10.15. The proposed
date of competion is 30.11.16
LILO of 132kv Ghazipur- Jamania line @ Bhadaura
20.91
6.26 17.05.13 17.05.13Archon/E
MC31.07.15 30.06.16 Comp 01/62 0/62 10.4
Profile approved, 01 no. Fdn under progress.
The proposed date of competion is 30.06.16
132kv SC Bhadaura-Kundesar line
20.66 5.82 17.05.13 17.05.13Archon/E
MC31.07.15 30.06.16 Comp 0/66 0/66 10
Profile approved, 01 no. Fdn under progress.
The proposed date of competion is 30.06.16
11220 kv s/s Azamgarh -II
220kV SC Sarnath(400kV) - Azamgarh -II(220kV) Line on DC Tower
60 32 18.07.14 22.07.14 26.07.14Archon/ Monte carlo
08.09.15 07.11.16
Line withdrawn from M/s Archon Engicon and
allotted to M/s MonteCarlo on 08.09.15,
firm is in process of taking up work. The proposed
date of complition is 07.12.16.
220 kV SC Auraui(400)- Azamgarh -II (220kV) Line on DC Tower
74.8 62 18.07.14 22.07.14 26.07.14 Trading 74.8
1.Stubs & Templates delivered at site.
2. 6 nos. FDN gangs to be deployed shortly. The
proposed date of complition is 31.10.16.
132 kV SC Azamgarh-II (220kV) - Azamgarh(sidhari) Line on DC Tower
46 16 18.07.14 22.07.14 26.07.14Archon/ Monte carlo
08.09.15 07.08.16
Line withdrawn from M/s Archon Engicon and
allotted to M/s MonteCarlo on 08.09.15,
firm is in process of taking up work. The proposed
date of complition is 07.08.16.
132 kV SC Kerakat - Azamgarh-II(220kV) Line on DC Tower
20.18 12 18.07.14 22.07.14 26.07.14Archon/ Monte carlo
08.09.15 07.08.16
Line withdrawn from M/s Archon Engicon and
allotted to M/s MonteCarlo on 08.09.15,
firm is in process of taking up work. The proposed
date of complition is 07.08.16.
132 kV SC Phulpur - Azamgarh-II(220kV) Line on DC Tower
45 15.5 18.07.14 22.07.14 26.07.14Archon/ Monte carlo
08.09.15 07.08.16
Line withdrawn from M/s Archon Engicon and
allotted to M/s MonteCarlo on 08.09.15,
firm is in process of taking up work. The proposed
date of complition is 07.08.16.
132KV DC Azamgarh (220)-II- Lalganj line
20 01.04.15
12220 kv s/s Raja ka Talab
220 kV SC Line Raja ka Talab- 400 kV Aurai on DC Tower
11.5 16.718.07.14/ 02.01.15
22.07.14 26.07.14 Trading 11.5 0/38 0/38 0/11.5 10
1.Stubs & Templates delivered at site.
2. 2 nos. FDN gangs to be deployed shortly. The
proposed date of complition is 30.04.16.
220 kV SC Line Raja ka Talab- 220 kV Sahupuri on DC Tower
60.8 19.818.07.14/ 02.01.15
22.07.14 26.07.14 Trading 60.8 0/188 0/188 0/60.8 10
1.Stubs & Templates delivered at site.
2. 3 nos. FDN gangs to be deployed shortly. The
proposed date of complition is 31.08.16.
LILO of 132 kV SC Raja ka talab(132)- Aurai(400) Line @Raja Ka Talab (220)
4.5 218.07.14/ 02.01.15
22.07.14 26.07.14 Trading 4.5 0/17 0/17 0/4.5 10
1.Stubs & Templates delivered at site.
2. 1 nos. FDN gangs to be deployed shortly. The
proposed date of complition is 31.12.15.
132 KV SC line Raja ka Talab(220)- Kursato on DC Tower
25 8.1518.07.14/ 02.01.15
22.07.14 26.07.14 Trading 25 0/54 0/54 0/25 10
1.Stubs & Templates delivered at site.
2. 2 nos. FDN gangs to be deployed from 01.10.15.
The proposed date of complition is 30.04.16.
1 132kV S/s Kursato
LILO of 132kV SC line Raja ka talab(132)-Gajokhar @ Kursato S/s
1.5 1.518.07.14/ 02.01.15
22.07.14 26.07.14 Trading 1.5 0/9 0/9 0/1.5 10
1.Stubs & Templates delivered at site.
2. 1 nos. FDN gangs to be deployed shortly. The
proposed date of complition is 31.12.15.
3132 kv s/s Chakia (TKSAS)
132 kv LILO Sahupuri-Robertsganj@Chakia
TD-329 21.7 8.08 Aravali 28.04.10 27.04.11 Comp 78/81 76/81 5/21.7 78
Forest clearance approved, firm has started
Fdn work. The proposed date of completion is
30.11.15.
4132 kv s/s Mubarakpur
132 kv SC Azamgarh(220)-Mubarakpur line
15.0 5.37
(Old 17.05.13)
(New 23.01.09)
11.07.1310.5527
(With S/S)Varrsana 07.11.14 06.11.15 Comp 16
Profile approved, inspection of stubs waived
off, fdn work to start immediately.
5132 kv s/s Rudrapur (TKSAS)
132 kv sc Deoria220-Rudrapur
20 7.09Archon/E
MC31.07.15 30.06.16
Survey to start from 05.10.2015. The proposed
date of competion is 30.06.16
6132 kv s/s Nathnagar (TK Techno)
LILO of132 kv Basti-Khalilabad line @ Nathnagar
TD-329 15.55 6.06 Aravali/
Jyoti01.04.11 01.04.12 Comp 50/57 43/57 0/15.55 67.02
WIP, material received, 1 Fdn & 1 Ere gang at site.
The expected date for energisation is 23.12.15
7 132 kv s/s DLW132 kV SC DLW(UPPTCL)-DLW(Deposit)
0.2 7.26 UPPTCL
8132 kv s/s Allahabad Old PH (GIS)
LILO of 220 kV Reewa Road - Cantt Line at 132 kV GIS Old P/H Allahabad(77)
10 48.4 26.10.12 11.12.12 12.12.12 UPRNN 25.6.12 Comp 0 0 76
9 Kms cable laying completed out of 10 Kms.
12 joint out of 14 completed. WIP. The
proposed date of complition is 31.10.15.
9132 kv s/s ChitbadagaonLILO of 132 kv Rasra-Ballia Line @ Chitbadagaon
20 15.3476 17.05.13 10.74332 Archon 0/27 0/27 0/20 Survey started.
10 132 kv s/s Bharwari
132 kV Dc Sirathu-Bharwari
16.06 14.13 15.02.12 18.7.12 12.12.12Archon/E
MC31.07.15 30.06.16 Comp 05/52 0/52 12.4
Fdn WIP. The proposed date of competion is
29.02.2016
11 132 kv s/s Lalganj
LILO of 132 kv Mirzapur-Jigan ckt II @ 132 kV Lalganj
30.79 16.14 07.09.11 12.12.12Archon/E
MC31.07.15 30.06.16
Route survey to start on 30.09.2015. The proposed
date of competion is 30.06.16
12 132kV S/s Jari
132kV DC Masauli (400) - Jari line
55 13.5718.07.14/ 02.01.15
22.07.14 26.07.14Archon/ Monte carlo
08.09.15 07.11.16
Line withdrawn from M/s Archon Engicon and
allotted to M/s MonteCarlo on 08.09.15,
firm is in process of taking up work. The proposed
date of complition is 07.12.16.
132 kV SC Jari - Shankargarh line on DC Tower
45 15.318.07.14/ 02.01.15
22.07.14 26.07.14Archon/ Monte carlo
08.09.15 07.08.16
Line withdrawn from M/s Archon Engicon and
allotted to M/s MonteCarlo on 08.09.15,
firm is in process of taking up work. The proposed
date of complition is 07.08.16.
13132kV S/s Salai Khurd
132kV DC Masauli(400) - Salai Khurd Line
30 7.5118.07.14/ 02.01.15/ 30.09.15
22.07.14 26.07.14 Trading 25.33 0/94 0/94 0/25.33 10
1.Stubs & Templates delivered at site.
2. 3 nos. FDN gangs to be deployed shortly. The
proposed date of complition is 30.05.16.
LILO of single ckt of 132 kV DC Reewa Rd- Korawan line @ Salai khurd S/s
2.4 1.1618.07.14/ 02.01.15/ 30.09.15
22.07.14 Trading
The line put on hold till alternative is finalized
(UPPTCL letter Ref. 1996/ETDC/1/TD-388/14
dt. 29.05.15).
6132 kv s/s Purnachhpar,Bhatni132 kv SC Deoria(220)-Purnachhpar (Bhatni) Line
40Archon/E
MC31.07.15 30.06.16
Survey work to start from 05.10.15.The proposed
date of competion is 30.06.16
1132 kv sc 2PH Basti-Govindnagar
TD-313 21.6 6.71Aravali/
Jyoti 03.10.08 03,10,09 Comp 72/72 72/72
21.6/ 21.6
100
On 22.05.2014 Agency with drawn. Alloted to M/S Jyoti Allahabad.
Completed in Feb.-15, but Rly TSS is not ready.
2
Height raising of 132 kv Barhua FCI line for Railways under deposit work
1.0East India
Udyog4/4 4/4 0/1
Railway block applied wef 10.10.2014.
3132 kv sc Lalganj-Kunda
TD-348 35.29 10.94 Hythro 23.12.11 23.12.12 Comp 22/116 0/116 0/35.29 34.74
Work stopped from several Months. Proposal
for withdrawal of line moved.
4132 kV SC Anandnagar-Naugarh
TD-348 38.27 11.86 Trading 23.12.11 23.12.12 Comp 45/128 0/128 0/38.27 38.79
1. Line route falls in Terai region so area is mostly submerged in water &
work can be executed only 3-4 months in a year.
2. At present team cannot be deployed due to
standing rice crop & water logged area. 3. 01 no Foundation & Erection
gang to be deployed by 25.10.15.
The proposed date of complition 31.03.16.
5132 kV SC Anandnagar-Maharajganj
TD-348 35.72 11.07 Trading 23.12.11 23.12.12 Comp 98/113 45/113 0/35.72 59.65
1. Line route falls in Terai region so area is mostly submerged in water &
work can be executed only 3-4 months in a year.
2. At present team cannot be deployed due to
standing rice crop & water logged area. 3. 01 no Foundation & Erection
gang to be deployed by 25.10.15.
The proposed date of complition 31.03.16.
6
Replacement by AAAC 132 kv dc Sarnath400-Sarnath132
16.12 4..25 Apar WIP.The proposed date of complition 31.10.15.
7132 kv sc Phoolpur-Handia
40
8132 kv sc Chunar-Mirzapur220
45
92*132 kv bays@Chunar&Mirzapur220
10construction of 2 nos. 132kv 'bays' @ 220kv s/s deoria
12th
11
Replacement of Panther Conductor by HTLS ACCC Conductor at Varanasi
132 Kv Sarnath- Maduadih SC line
29.164 Sterlite 14.08.15 13.08.16 NA NA NALOI issued on 14.08.15. The proposed date of
complition is 13.08.16.
132 Kv Gajokhar-maduadih SC line
33.308 Sterlite 14.08.15 13.08.16 NA NA NALOI issued on 14.08.15. The proposed date of
complition is 13.08.16.