Detailed guide: Oil and gas: decommissioning of offshore installations and pipelines Updated: Approval of Close out Report Overview The decommissioning of offshore oil and gas installations and pipelines on the United Kingdom Continental Shelf (UKCS) is controlled through the Petroleum Act 1998 . The responsibility for ensuring that the requirements of the Petroleum Act 1998 are complied with rests with the Offshore Petroleum Regulator for Environment and Decommissioning (OPRED) which sits within the Department for Business, Energy and Industrial Strategy. Owners of oil and gas installations and pipelines are required to decommission their offshore infrastructure at the end of a field’s economic life and the 1998 Act requires owners to set out the measures to decommission disused installations and/or pipelines in a decommissioning programme. A decommissioning programme must identify all the items of equipment, infrastructure and materials that have been installed or drilled and describe the decommissioning solution for each. OPRED aims to be transparent in its consideration of decommissioning programmes. As a result members of the public, other organisations, non- governmental organisations and other government departments or agencies are invited to comment on the proposals set out in a programme. Details of the current programmes under consideration are noted in the table below. OPRED provides guidance on the regulatory requirements for decommissioning, Offshore Oil and Gas Decommissioning Guidance Notes May 2018 (PDF, 1.09MB, 124 pages) . Final guidance on the Environmental Considerations for Decommissioning (section 12) will follow shortly, meantime draft guidance can be found here: Section 12 (MS Word Document, 142KB) .

Transcript of Detailed guide: Oil and gas: decommissioning of offshore ...

Page 1: Detailed guide: Oil and gas: decommissioning of offshore ...

Detailed guide: Oil and gas:decommissioning of offshoreinstallations and pipelines

Updated: Approval of Close out Report

OverviewThe decommissioning of offshore oil and gas installations and pipelines onthe United Kingdom Continental Shelf (UKCS) is controlled through thePetroleum Act 1998.

The responsibility for ensuring that the requirements of the Petroleum Act1998 are complied with rests with the Offshore Petroleum Regulator forEnvironment and Decommissioning (OPRED) which sits within the Department forBusiness, Energy and Industrial Strategy.

Owners of oil and gas installations and pipelines are required todecommission their offshore infrastructure at the end of a field’s economiclife and the 1998 Act requires owners to set out the measures to decommissiondisused installations and/or pipelines in a decommissioning programme.

A decommissioning programme must identify all the items of equipment,infrastructure and materials that have been installed or drilled and describethe decommissioning solution for each.

OPRED aims to be transparent in its consideration of decommissioningprogrammes. As a result members of the public, other organisations, non-governmental organisations and other government departments or agencies areinvited to comment on the proposals set out in a programme.

Details of the current programmes under consideration are noted in the tablebelow.

OPRED provides guidance on the regulatory requirements for decommissioning,Offshore Oil and Gas Decommissioning Guidance Notes May 2018(PDF, 1.09MB, 124 pages)

. Final guidance on the Environmental Considerations for Decommissioning(section 12) will follow shortly, meantime draft guidance can be found here:Section 12(MS Word Document, 142KB)

.

Page 2: Detailed guide: Oil and gas: decommissioning of offshore ...

Table of draft decommissioning programmes underconsideration

Field Name Field Operator Status Main points of theprogramme Details

Viking VDP2(Viking BravoHub, VikingSatellitesKD, LD, ARand Vixen VM)

ConocoPhillips(U.K.) Limited

Draftprogrammesunderconsideration

Removal to shore ofthe Viking BravoHub and VikingSatellites KD, LDand AR topsides andjackets and VictorJM subsea manifoldforrecycling/disposal.Wells to be pluggedand abandoned.Pipelines to bedecommissioned insitu. Allmattresses onpipelines to remainin situ.

VDP2DecommissioningProgrammes(PDF, 3.29MB,80 pages)

VDP2ComparativeAssessment(PDF, 3.09MB,167 pages)

VDP2EnvironmentalStatement(PDF, 13.5MB,420 pages)

Viking VDP3(Victor JDand JM)

ConocoPhillips(U.K.) Limited

Draftprogrammesunderconsideration

Removal to shore ofthe Victor JDtopsides andjackets and VictorJM subsea manifoldforrecycling/disposal.Wells to be pluggedand abandoned.Pipelines to bedecommissioned insitu. Allmattresses onpipelines to remainin situ.

VDP3DecommissioningProgrammes(PDF, 1.78MB,49 pages)

VDP3ComparativeAssessment(PDF, 3.09MB,167 pages)

VDP3EnvironmentalStatement(PDF, 13.5MB,420 pages)

Page 3: Detailed guide: Oil and gas: decommissioning of offshore ...

Dunlin AlphaField

FairfieldBetula Limited

Draftprogrammeunderconsideration

Decommissioning insitu of DunlinAlpha concretegravity basedstructure andstorage cells. Fullremoval of DunlinAlpha topsides forreuse or recycling.

Dunlin AlphaDecommissioningProgramme(PDF, 6.5MB, 77pages)

Dunlin AlphaDecommissioningComparativeAssessmentReport(PDF, 3.66MB,133 pages)

Dunlin AlphaDecommissioningEnvironmentalAppraisal(PDF, 5.04MB,155 pages)

BeatriceField

Repsol SinopecResources UKLimited

Draftprogrammesunderconsideration

Topsides, jacketsand the drillingtemplate will beremoved andrecycled ordisposed onshore.Wells will beplugged andabandoned. Trenchedand buriedpipelines willremain in situ. Anyexposed sectionswill undergotrenching andburial, rockcovering or be cutout and removed toshore. A smallsection of drillcuttings will beleft in situ.Concrete mattressesand grout bags willbe recovered toshore for reuse,recycling ordisposal.

BeatriceDecommissioningProgramme(PDF, 5.13MB,81 pages)

BeatriceComparativeAssessmentReport(PDF, 3.3MB, 98pages)

BeatriceEnvironmentalAssessmentReport(PDF, 15.9MB,255 pages)

Page 4: Detailed guide: Oil and gas: decommissioning of offshore ...

Tyne SouthInstallations

Perenco UKLimited

Draftprogrammesunderconsideration

Removal to shore ofthe Tyne Southtopsides, jacketand subseainstallation forre-use orrecycling.

Tyne SouthInstallationsDecommissioningProgramme(PDF, 1.86MB,40 pages)

Tyne SouthInstallationsEnvironmentalImpactAssessment(PDF, 8.75MB,223 pages)

GuinevereInstallation

Perenco UKLimited

Draftprogrammesunderconsideration

Removal to shore ofthe Guineveretopsides and jacketfor re-use orrecycling.

GuinevereInstallationDecommissioningProgramme(PDF, 1.68MB,41 pages)

GuinevereInstallationEnvironmentalImpactAssessment(PDF, 5.95MB,149 pages)

Page 5: Detailed guide: Oil and gas: decommissioning of offshore ...

Curlew andCurlew CFields

Shell (U.K.)Limited

Draftprogrammesunderconsideration

Removal to shore ofthe Curlew FPSO,mid-water arch andmooring system forrecycling/disposal.Removal to shore ofsubsea manifold,Curlew C WHPS andsubsea pipelinestructures forrecycling/disposal.Subsea wells to beplugged andabandoned. Alltrenched and buriedpipelines will bedecommissioned in-situ with pipelineand umbilical endscut or lowered andcovered. Alljumpers, spools andconcrete mattresseswill be recoveredto shore forrecycling/disposal.

Curlew andCurlew CDecommissioningProgrammes(PDF, 2.49MB,61 pages)

Curlew andCurlew CComparativeAssessment(PDF, 3.08MB,85 pages)

Curlew andCurlew CEnvironmentalStatement(PDF, 7.77MB,196 pages)

WindermereField

INEOS UK SNSLimited

Draftprogrammesunderconsideration

Topsides and jacketwill be removed andrecycled ordisposed onshore.The pipelines willbe partiallyremoved, theexposed sectionsadjacent to theplatforms will beremoved andrecycled ordisposed onshore.The exposed endswill be lowered toachieve adequatedepth of coverage.The existing buriedsections ofumbilical will beleft in situ. Allconcrete mattressesand grout bags willbe recovered toshore for reuse,recycling ordisposal.

WindermereDecommissioningProgramme(PDF, 2.39MB,38 pages)

WindermereComparativeAssessment(PDF, 1.49MB,34 pages)

WindermereEnvironmentalStatement(PDF, 10.2MB,235 pages)

Page 6: Detailed guide: Oil and gas: decommissioning of offshore ...

Bains FieldSpirit EnergyProduction UKLtd

Draftprogrammesunderconsideration

All SubseaInstallations willbe removed. Bothpipelines will beleft in situ exceptfor short exposedsections.

BainsDecommissioningProgrammes(PDF, 1.94MB,30 pages)

BainsComparativeAssessment(PDF, 1.68MB,40 pages)

BainsEnvironmentalAppraisal(PDF, 3.61MB,61 pages)

Jacky Field Ithaca Energy(UK) Limited

Draftprogrammesunderconsideration

Platform & MidlineTee Structure willbe removed andtransported toshore for re-use orrecycling. Subseawells will beplugged andabandoned using adrilling rig.Pipelines aretrenched and buriedand will remain insitu.

JackyDecommissioningProgrammes(PDF, 1.86MB,50 pages)

JackyComparativeAssessment(PDF, 1.32MB,31 pages)

JackyEnvironmentalImpactAssessment(PDF, 8.83MB,135 pages)

Page 7: Detailed guide: Oil and gas: decommissioning of offshore ...

East Brae andBraemar

Marathon OilUK LLC

Draftprogrammesunderconsideration

Removal of EastBrae topsides andremoval of jacketsto the top of thefootings. Removalof Braemar subseainstallations.Pipelines to bedecommissioned bypartial removal andleave in situ.

East Brae AndBraemarDecommissioningProgrammes(PDF, 10.3MB,74 pages)

East Brae andBraemarEnvironmentalStatement –Main Report(PDF, 14.5MB,78 pages)

East Brae andBraemarEnvironmentalStatement –TechnicalAppendices(PDF, 12.8MB,96 pages)

East Brae Sub-structuresComparativeAssessment(PDF, 5.96MB,39 pages)

Brae AreaSubsea AssetsComparativeAssessment(PDF, 6.84MB,43 pages)

Page 8: Detailed guide: Oil and gas: decommissioning of offshore ...

Brae Alpha,Brae Bravo,Central Brae,West Brae andSedgwick

Marathon OilUK LLC

Draftprogrammesunderconsideration

Removal of BraeAlpha and BraeBravo jackets tothe top of thefootings.Removal of CentralBrae, West Brae andSedgwick subseainstallations.Pipelines to bedecommissioned in avariety of waysincluding removal,trenching and leavein situ.

Brae Alpha,Brae Bravo,Central Brae,West Brae andSedgwickDecommissioningProgrammes(PDF, 15.3MB,120 pages)

Brae A etc,EnvironmentalStatement –Main Report(PDF, 14.6MB,80 pages)

Brae A etc.EnvironmentalStatement –TechnicalAppendices(PDF, 13.3MB,96 pages)

Brae A Sub-structureComparativeAssessment(PDF, 5.27MB,34 pages)

Brae B Sub-structureComparativeAssessment(PDF, 5.44MB,34 pages)

Brae AreaSubsea AssetsComparativeAssessment(PDF, 6.84MB,43 pages)

Page 9: Detailed guide: Oil and gas: decommissioning of offshore ...

Ninian NorthPlatform CNR

Draftprogrammeunderconsideration

Topsides will beremoved andrecovered to shore.Partial removal ofthe Jacket tobetween 77.5 and88.5m below LAT.Decommissioning insitu of jacketfootings.

Ninian NorthPlatformDecommissioningProgramme(PDF, 1.8MB, 61pages)

Ninian NorthPlatformEnvironmentalStatement(PDF, 7.82MB,229 pages)

Ninian NorthPlatformComparativeAssessment(PDF, 2.75MB,92 pages)

Page 10: Detailed guide: Oil and gas: decommissioning of offshore ...

Brent Shell U.K.Limited

Draftprogrammesunderconsideration

Removal of upperpart of Brent Alphasteel jacket to84.5m below sealevel.Decommissioning insitu of Brent Alphajacket footings.Decommissioning insitu of BrentBravo, Charlie andDelta concretegravity basedstructures.Pipelines severaldecommissioningoptions.

BrentDecommissioningProgramme(PDF, 12MB, 322pages)

Brent ES(PDF, 12.5MB,475 pages)

Brent EIA(PDF, 5.05MB,429 pages)

Brent ESAppendix(PDF, 2.52MB,45 pages)

A suite ofdetailedTechnicalDocuments whichsupport theDecommissioningProgrammesdocuments areavailable onthe ShellWebsite

Page 11: Detailed guide: Oil and gas: decommissioning of offshore ...

Atlantic andCromarty

BG GlobalEnergy Limitedand HessLimited

Draftprogrammesunderconsideration

Manifold and Wellhead Protectionstructures (WHPS)to be removed forrecycling/disposal.Partial removal ofpipelines andremaining sectionof buried/trenchedpipelines to remainin situ.

Atlantic &CromartyDecommissioningProgrammes(PDF, 1.76MB,50 pages)

Atlantic &CromartyStakeholderReport(PDF, 1.11MB,32 pages)

Atlantic &CromartyEnvironmentalImpactAssessment(PDF, 4.5MB,109 pages)

Atlantic &CromartyComparativeAssessment(PDF, 2.06MB,110 pages)

Table of approved decommissioning programmes

Field Name Operator atapproval

Operatorfollowinglicence /companychange

Main installationsdecommissioned Approved option Year of

approval

Brae BravoTopsides, FlareBridge, FlareTower and FlareJacket andSubstructure(PDF, 4.9MB, 52pages)

Marathon OilUK LLC –

Brae BravoTopsides, FlareBridge, Flare Towerand FlareJacket/Substructure

Removal to shorefor either re-useor recycling

August2018

Page 12: Detailed guide: Oil and gas: decommissioning of offshore ...

Brent Alpha,Bravo andCharlieTopsides(PDF, 3.34MB,81 pages)

Shell U.K.Limited –

Brent Alpha, BrentBravo and BrentCharlie Topsides

Removal to shoreforrecycling/disposal

August2018

Stirling A33WHPSDecommissioningProgramme(PDF, 1.13MB,27 pages)

Premier OilE&P UK Limited – Subsea installation Removal to shore

for recycling May 2018

Ann and Alison(PDF, 2.98MB,60 pages)

Spirit EnergyNorth SeaLimited

Subseainstallations

Removal to shorefor either re-useor recycling

April2018

Pipelines

Buried and stablepipelines left insitu. Surface laidpipelines removedto shore for re-useor recycling

April2018

Saturn(Annabel)(PDF, 2.49MB,47 pages)

Spirit EnergyNorth SeaLimited

Subseainstallations

Removal to shorefor either re-useor recycling

April2018

Pipelines

Buried and stablepipelines left insitu. Surface laidpipelines removedto shore for re-useor recycling

April2018

Audrey(PDF, 2.87MB,58 pages)

Spirit EnergyNorth SeaLimited

2 fixed platforms

Removal of topsidesand jackets toshore for recyclingor disposal

April2018

Pipelines

Buried and stablepipelinesdecommissioned insitu. Surface laidpipelines removedto shore for re-useor recycling

April2018

RevDecommissioningProgramme(PDF, 12MB, 42pages)

Repsol NorgeAS – Pipelines

Fully buried andstable pipeline tobe left in situ.All other pipelinesto be removed. Allmattresses onpipelines to beremoved

April2018

Markham ST-1(PDF, 2.39MB,49 pages)

CentricaProductionNederland B.V.

Fixed PlatformRemoval to shorefor either re-useor recycling

February2018

PipelinesTwo pipelines to bedecommissioned insitu

February2018

Page 13: Detailed guide: Oil and gas: decommissioning of offshore ...

Osprey(PDF, 3.92MB,68 pages)

FairfieldFagus Limited –

Subsea Installation

Removed andrecovered to shoreforrecycling/disposal

December2017

Pipelines

Full removal withthe exception ofthe Bundles,Umbilical Riserswithin the DunlinAlpha ConcreteGravity BasedStructure or thosetrenched and rockdumped

December2017

Merlin(PDF, 2.97MB,56 pages)

FairfieldFagus Limited –

Subsea Installation

Removed andrecovered to shoreforrecycling/disposal

December2017

Pipelines

Full removal withthe exception oftrenched and rockdumped Pipelinesand Umbilicals andUmbilical Riserwithin the DunlinAlpha ConcreteGravity BasedStructure

December2017

Dunlin Fuel GasImport (DFGI)and DunlinPower Import(DPI)(PDF, 3.48MB,54 pages)

FairfieldFagus Limited –

Subsea Installation

Removed andrecovered to shoreforrecycling/disposal

December2017

Pipelines

Full removal withthe exception oftrenched and buriedPipelines and RigidRiser and RiserCable within theDunlin AlphaConcrete GravityBased Structure

December2017

VikingSatellites CD,DD, ED, GD, HDPipelines(PDF, 6.77MB,32 pages)

ConocoPhillips(U.K.) Limited – Pipelines

All pipelines andassociatedmattresses toremain in situ

November2017

LOGGSSatellitesVulcan UR,Viscount VO,Vampire OD –LDP1(PDF, 17.5MB,61 pages)

ConocoPhillips(U.K.) Limited –

3 x fixed platforms– Vulcan UR,Viscount VO andVampire OD

Removal to shore oftopsides andjackets forrecycling/disposal

November2017

Pipelines

All pipelines andassociatedmattresses toremain in situ

November2017

Leman BHDecommissioningProgramme(PDF, 4.66MB,46 pages)

Shell U.K.Limited – 1 x platform

Removal to shorefor either re-useor recycling

April2017

Page 14: Detailed guide: Oil and gas: decommissioning of offshore ...

Ettrick andBlackbird(PDF, 2.1MB, 62pages)

NexenPetroleum UKLimited

FPSORemoval for re-useat differentlocation

March2017

Subsea EquipmentRemoval to shorefor either re-useor recycling

March2017

Pipelines

Removal to shorefor either re-useor recycling;buried pipelines tobe left in-situ

March2017

Ann A4DecommissioningProgramme(PDF, 1.37MB,29 pages)

Centrica NorthSea Limited –

A4 WellheadProtectionStructure

Removal to shorefor either re-useor recycling

February2017

Janice James &Affleck(PDF, 3.8MB,115 pages)

Maersk Oil UKLimited –

FPSO Removal forrecycling

September2016

Subsea EquipmentRemoval to shorefor either re-useor recycling

September2016

Pipelines

Removal to shorefor either re-useor recycling;buried pipelines tobe left in-situ

September2016

AthenaDecommissioningProgrammes(PDF, 3.88MB,70 pages)

Ithaca Energy(UK) Limited –

FPSORemoval for re-useat differentlocation

September2016

Subsea EquipmentRemoval to shorefor either re-useor recycling

September2016

Pipelines

All 32 pipeline tobe removed andreturned to shorefor re-use orrecycling

September2016

VikingPlatforms(PDF, 3.53MB,40 pages)

ConocoPhillips(U.K.) Limited –

5 x fixed platformsViking CD, DD, ED,GD, HD

Removal to shore oftopsides andjackets forrecycling/disposal

September2016

Leadon(PDF, 1.71MB,53 pages)

Maersk OilNorth Sea UKLimited

FPSORemoval for re-useat differentlocation

March2016

Subsea

Removal of 2 xbundle towheads andmid-line structureto shore fordisposal; removalof 2 x drillcentres to shorefor disposal

March2016

Pipelines

2 x Pipelinebundles to be leftin-situ, partialremoval of gasimport pipeline

March2016

Page 15: Detailed guide: Oil and gas: decommissioning of offshore ...

Harding STL(PDF, 2.61MB,73 pages)

Harding STLClose-OutReport(PDF, 1.62MB,26 pages)

TAQA BrataniLimited –

Harding SubmergedTurret Loading(STL) System

Harding SubmergedTurret Loading(STL) System to bereplaced by newOffshore LoadingSystem. STL to beremoved to shoreforrecycling/disposaland shuttle tankermooring and loadingbuoy interfacesreturned to owner

2015

Thames Area –Horne & Wren(PDF, 1.57MB,48 pages)

Tullow Oil SKLimited –

1x fixed platform

Removal of topsidesand jackets toshore forrecycling/disposal

November2015

Pipelines To remain buried insitu

November2015

Thames Area –Orwell(PDF, 828KB, 42pages)

Tullow Oil SKLimited –

SubseaInstallations

Removal to shoreforrecycling/disposal

November2015

Pipelines To remain buried insitu

November2015

Thames Area –Wissey(PDF, 1.26MB,43 pages)

Tullow Oil SKLimited –

SubseaInstallations

Removal to shoreforrecycling/disposal

November2015

Pipelines To remain buried insitu

November2015

Thames Area –Thames Complex(PDF, 15.9MB,76 pages)

Perenco UKLimited –

3x fixed platforms

Removal of topsidesand jackets toshore forrecycling/disposal

October2015

SubseaInstallations

Removal to shoreforrecycling/disposal

October2015

Pipelines To remain buried insitu

October2015

Thames Area –Gawain(PDF, 3.8MB, 47pages)

Perenco UKLimited –

SubseaInstallations

Removal to shoreforrecycling/disposal

October2015

Pipelines To remain buried insitu

October2015

Thames Area –Arthur(PDF, 4.41MB,46 pages)

Perenco UKLimited –

SubseaInstallations

Removal to shoreforrecycling/disposal

October2015

Pipelines To remain buried insitu

October2015

Brent – BrentDelta Topside(PDF, 3.55MB,72 pages)

Shell U.K.Limited – Brent Delta Topside

Removal of topsideto shore forrecycling anddisposal

July 2015

Page 16: Detailed guide: Oil and gas: decommissioning of offshore ...

RoseDecommissioningProgrammes(PDF, 2.87MB,42 pages)

Rose Close OutReport(PDF, 3.31MB,36 pages)

CentricaResourcesLimited

SubseaInstallations

Removal to shoreforrecycling/disposal

May 2015Close OutReportApprovedOctober2018

Pipelines

Removal of sectionsof un-trenchedpipelines; trenchedpipelinesdecommissioned insitu

May 2015Close OutReportApprovedOctober2018

Stamford(PDF, 2.71MB,39 pages)

Centrica NorthSea GasLimited

SubseaInstallations

Removal to shoreforrecycling/disposal

April2015

Pipelines

Removal of sectionsof un-trenchedpipelines; trenchedpipelinesdecommissioned insitu

April2015

Murchison(PDF, 2.37MB,70 pages)

CNR –

Large SteelPlatform

Topsides and jacketto top of footingsto be removed toshore forrecycling/disposal.Footings to remainin situ

August2014

Pipelines

Export pipelinedecommissioned insitu with remedialrock placement.Infield Flowlinesto be removed forrecycling/disposal.

August2014

Rubie & Renee(PDF, 2.47MB,50 pages)

EndeavourEnergy UKLimited

SubseaInstallations

Removal to shoreforrecycling/disposal

April2014

Pipelines Selective Recovery April2014

Miller(PDF, 6.57MB,198 pages)

BP Exploration(Alpha)Limited

Large SteelPlatform

Footings to remainin place, steeltopsides and jacketto top of footingsto be removed toshore

December2013

Schiehallion &Loyal Phase One(PDF, 1.84MB,60 pages)

BritoilLimited –

Schiehallion FPSO Removal forpotential re-use 2013

Pipelines

Recovery wherepossible.Productionflowlines to beleft in situ.

2013

IVRR –decommissoningprogramme(PDF, 1.57MB,102 pages)

IVRR Close OutReport(PDF, 4.74MB,35 pages)

Hess limited –

FPSORemoval for re-useat differentlocation

2013

Subseainstallations

Removal to shoreforrecycling/disposal

2013

Pipelines Selective recovery 2013

Page 17: Detailed guide: Oil and gas: decommissioning of offshore ...

Camelot(PDF, 488KB, 39pages)

Camelot Closeout report(PDF, 2.27MB,41 pages)

EnergyResourceTechnology(UK) Limited

Small SteelPlatform

Removal to shorefor recycling /disposal

2012

PipelinesPipelinesdecommissioned insitu

2012

Fife, Flora,Fergus, Angus:decommissioningprogramme(PDF, 8.36MB,135 pages)

FFFA Close OutReport(PDF, 1.49MB,33 pages)

Hess Limited –

FPSORemoved for re-useat differentlocation

2012

Subseainstallations

Removal to shorefor recycling /disposal

2012

Pipelines

Full removal of un-trenched pipelines;trenched pipelinesdecommissioned insitu

2012

DonBritoil PublicLimitedCompany

Subsea installationRemoval to shorefor recycling /disposal

2011

PipelinesDecommissioned insitu with selectiverecovery

2011

Welland Perenco UKLimited

Perenco UKLimited

Small SteelPlatform

Removal for re-useoutside of UKwaters

2010

PipelinesDecommissioned insitu with selectiverecovery

2010

Tristan NWClose outreport

SilverstoneEnergy Limited

BridgeEnergy UKLimited

Subsea installation Removal to shorefor recycling

2010;close-outreportreceivedJanuary2011

Pipelines

Production pipelinewith piggy-backedumbilical – leavein situ; jumpers,spool pieces andassociated pipelineequipment – removeto shore for re-useor recycling

2010;close-outreportreceivedJanuary2011

Page 18: Detailed guide: Oil and gas: decommissioning of offshore ...

ShelleyClose outreport

Premier Oil –

Sevan Voyageur FPSOTow away for futureuse at anotherlocation

2010;close-outreportreceivedFebruary2012

Manifold andWellhead

Remove to shore forre-use, recyclingor disposal

2010;close-outreportreceivedFebruary2012

Pipelines

Production pipeline– leave in situ;umbilical – removein sections

2010;close-outreportreceivedFebruary2012

Kittiwake SALExport SystemClose outreport

Venture NorthSea OilLimited

Kittiwake SALAssembly

SAL Assembly –removal to shorefor re-use.Revision toapproveddecommissioningprogramme:Completion of theremoval of the SALAssembly extendedto 31 July 2012

2009;close-outreportreceivedJuly 2012

PipelinesPipeline – flexibleflowline removed toshore for re-use

2009;close-outreportreceivedJuly 2012

MCP-01Close outreport

Total E& P UKLimited –

Manifold &CompressionPlatform

Permit granted forthe disposal in-situ of theconcretesubstructure;topsides to beremoved to shorefor re-use,recycling ordisposal

2008;close-outreportreceivedMarch2013

KittiwakeLoading Buoy

Venture NorthSea OilLimited

–Exposed LocationSingle Buoy MooringSystem (ELSBM)

Removals to shorefor recycling ordisposal

2008

Page 19: Detailed guide: Oil and gas: decommissioning of offshore ...

Linnhe(PDF, 2.25MB,66 pages)

</p>Linnhe CloseOut Report(PDF, 1000KB,22 pages)

Mobil NorthSea LLC –

Wellhead ProtectionStructure

Removal to shore.Revision toapproveddecommissioningprogramme:completion of theremoval of theWellhead ProtectionStructure extendedto 30 June 2010

2008;year ofrevisedapproval:2010

Pipelines

Decommissioned insitu; pipelinesections outsidetrenches removed toshore. Revision toapproveddecommissioningprogramme:completion of theabandonment of thepipelines extendedto 30 June 2010

2008;year ofrevisedapproval:2010

Indefatigable(Shell)(PDF, 11.6MB,224 pages)

</p>Close OutReport(PDF, 2.47MB,64 pages)

Shell U.K.Limited –

6 x fixed steelplatforms Removal to shore 2007

Pipelines

2 x hose bundlesremoval to shore; 5x infield + exportdecommissioned insitu

2007

NW Hutton:decommissioningprogramme(PDF, 14.9MB,320 pages)

Close OutReport(PDF, 2.52MB,32 pages)

Amoco (U.K.)ExplorationCompany – nowa subsidiaryof BP plc

Large SteelPlatform

Footings to remainin place, steeltopsides and jacketto top of footingsto be removed toshore

2006

Pipelines Decommissioned insitu 2006

Ardmore

BritishAmericanOffshoreLimited

– Mobile Jack-Up Rig Re-use 2005

Ardmore Ugland NordicShipping AS –

Single AnchorLoading Systems

Re-use/removal toshore 2005

Pipelines Re-use 2005

Ardmore Acorn Oil &Gas Limited –

Subsea equipmentincluding guideframe

Removal to shore 2005

Brent Shell – Brent FlareRemovals to shorefor recycling anddisposal

2004

BeatriceTalismanEnergy (UK)Limited

– Fixed SteelPlatforms Re-use 2004

Page 20: Detailed guide: Oil and gas: decommissioning of offshore ...

Forbes andGordon InfieldPipelines

BHP Billiton – Infield Pipelines

Decommission insitu – retrench anyarea of pipelinewith less than 0.4mdepth of cover

2003;close-outreportreceivedMay 2005

Frigg TP1, QP &CDP1Close outreport

Total E&PNorge AS –

Treatment Platform1 (TP1), QuartersPlatform (QP) andConcrete DrillingPlatform 1 (CDP1)

Concretesubstructures toremain in place;concrete topsidesto be removed toshore; steelinstallations to beremoved to shore;infield pipelinesto be removed toshore

2003

Durward andDauntless Amerada Hess – Pipelines Decommissioned in

situ 2002

Hutton Kerr-McGee –

Tension LegPlatform Re-use

2002;close-outreportreceivedJuly 2004

Pipelines

1 x removal toshore; 1 xdecommissioned insitu (with futuremonitoringprogramme)

2002;close-outreportreceivedJuly 2004

Camelot CB ExxonMobil – Fixed SteelPlatform

Re-use or removalto shore forrecycling. Revisionto approveddecommissioningoption: removal toshore fordismantling andrecycling

2001.Year ofrevisedapproval:2002

Blenheim andBladon Talisman –

FPSO Re-use 2000Pipelines Removal to shore 2000

Durward andDauntless Amerada Hess –

FPSO Re-use 2000Subsea Facilities Removal to shore 2000

Maureen andMoira Phillips –

Large Steel GravityPlatform

Removal to shorefor re-use orrecycling

2000

Concrete LoadingColumn

Removal to shorefor re-use orrecycling

2000

Pipelines

2 x removal toshore;1 xdecommissioned insitu

2000

Brent Spar Shell – Oil Storage andLoading Facility

Re-use as part ofquay extension.Revision toapproveddecommissioningoption: Brent SparAnchor Blocks –removal to shorefor reuse,recycling ordisposal 1998

Year ofrevisedapproval:2004

Page 21: Detailed guide: Oil and gas: decommissioning of offshore ...

Donan BP – FPSO Re-use 1998

Fulmar SALM Shell –

Single Anchor LegMooring Buoy Removal to shore 1998

16” Pipeline Decommissioned insitu 1998

Emerald MSR –FPSO Re-use 1996

Pipeline Decommissioned insitu 1996

Frigg FP Elf Norge TotalFinaElfNorge Flare Column Removal to shore 1996

Leman BK Shell – Fixed SteelPlatform Removal to shore 1996

Staffa Lasmo – Pipelines Removal to shore 1996Viking AC, AD,AP & FD Conoco – 4 x Fixed Steel

Platform Removal to shore 1996

Esmond CP & CW BHP – 2 x Fixed SteelPlatform Removal to shore 1995

Gordon BW BHP – Fixed SteelPlatform Removal to shore 1995

Angus Amerada Hess –

FloatingProduction, Storageand Offloading(FPSO) Vessel

Re-use 1993

Forbes AW Hamilton BHP Fixed SteelPlatform Removal to shore 1993

Argyll, Duncanand Innes Hamilton BHP

FloatingProduction,Facility (FPF)

Removal to shore 1992

Catenary Anchor LegMooring (CALM) Buoy Removal to shore 1992

Pipelines Removal to shore 1992

Blair Sun Oil AGIP Pipelines1 x Re-use; 1 xDecommissioned insitu

1992

Crawford Hamilton Oil BHP

FloatingProduction,Facility (FPF)

Removal to shore 1991

Catenary Anchor LegMooring (CALM) Buoy Removal to shore 1991

Subsea Facilities Removal to shore 1991

Piper Alpha Occidental Talisman Fixed SteelPlatform Toppling 1988

Notification of disused pipelines(the DPN form has been amended – July 2017)

During the course of a field’s life, pipelines/sections of pipelines may betaken out of use, e.g. due to corrosion, problems with reservoir pressure,damage to the pipeline, etc. When this happens, under the Petroleum Act 1998the Secretary of State has the option of immediately calling for a fulldecommissioning programme. This is not always considered an appropriateoption however, and so it has been agreed consideration will be given tohandling suitable pipelines, under an informal decommissioning regime,thereby deferring a formal programme until the end of the field’s life.

If a formal decommissioning programme is not immediately deemed suitable,

Page 22: Detailed guide: Oil and gas: decommissioning of offshore ...

details of the out of use pipeline(s) will be circulated to other governmentdepartments for comment. Following this, OPRED will decide one of thefollowing:

we are content with the proposals for monitoring and maintaining theout-of-use pipelinewe request additional information or further remedial actionwe request a formal decommissioning programme

The Interim Pipeline Regime is intended to ensure out of use lines do notpose a risk to other users of the sea or the environment and that they arecovered by an appropriate surveying and maintenance regime from the pointwhen they are taken out of use until approval of the formal decommissioningprogramme, which is usually at the end of field life. It should be noted thatany interim solution should not prejudice the final decommissioning optionsfor that line, including complete removal. The department expects Operatorsto submit details of out of use pipelines/sections of a pipeline as soon asthey are taken out of use.

Operators are reminded that any works that are proposed on any pipelinesunder the Pipeline Works Authorisation regime, as per their Terms andConditions of the PWA, must have a Legal Consent in place before works cancommence which includes but is not exclusive to any proposed decommissioningworks. Consents are issued by the Oil & Gas Authority and Operators arerequested to contact Claire Grant on any queries that they may have relatingto Legal Consents. Further Guidance can also be found on the Oil & GasAuthority website:https://www.ogauthority.co.uk/licensing-consents/consents/pipeline-works-authorisations/

Once the necessary legal consent has been issued by OGA, Consents &Authorisations Section, Operators are to email a completedDisused pipeline notification form(MS Word Document, 81.7KB)

to The Offshore Decommissioning Unit, OPRED,BEIS.

If you are an Operator, aware of any out of use pipelines that have not beenreferred to the department, please submit a completed DPN form at yourearliest convenience.

Following confirmation a pipeline has been accepted under the InterimPipeline Regime, the Offshore Decommissioning Unit will continue to monitorthe condition of the pipeline by asking the Operator to confirm the status ofthe pipeline remains unchanged following future surveys.

Further informationA list of all installations on the UKCS and their current status is availablefrom the OSPAR Website

At the first ministerial meeting of the Commission for the Protection of the

Page 23: Detailed guide: Oil and gas: decommissioning of offshore ...

Marine Environment of the North East Atlantic (OSPAR) in 1998, a bindingdecision was agreed that set rules for the disposal of offshore installationsat sea. Under the decision the dumping and leaving wholly or partly in placeof offshore installations is prohibited. Decision 98/3 recognises it may bedifficult to remove the ‘footings’ of large steel jackets weighing more than10,000 and concrete installations. As a result there are derogations forthese categories of installations if the internationally agreed assessmentand consultation process shows leaving them in place is justifiable.

OPRED has utilised streamlined decommissioning programme templates forderogation and non-derogation cases, Operators will therefore have a choicewhether to submit a decommissioning programme in the existing format (seeAnnex C of the Guidance Notes ‘Format and Content’) or adopt the streamlineddecommissioning programme template. Operators should discuss individual caseswith OPRED.

AStreamlined Decommissioning Programme Template (Non-Derogation Cases)(PDF, 1.36MB, 33 pages)

is available – (December 2015).

AStreamlined Decommissioning Programme Template (Derogation Cases)(PDF, 1.5MB, 36 pages)

is also available (December 2015).

A word version of these templates can also be requested from OPRED. Pleaseemail The Offshore Decommissioning Unit for further details.

Cost recoveryOPRED will charge a fee in respect of offshore (oil and gas) installationsand pipelines decommissioning programmes under the Petroleum Act 1998.Guidance, including the indicative fee structure, is available inGuidance on charging a fee for offshore (oil and gas) installations andpipelines under the Petroleum Act 1998(PDF, 308KB, 9 pages)