DETAILED FEASIBILITY STUDY (DFS) FOR THE …ibn.gov.np/uploads/files/Working...
Transcript of DETAILED FEASIBILITY STUDY (DFS) FOR THE …ibn.gov.np/uploads/files/Working...
1
May, 2018 New Baneshwor,
Kathmandu, Nepal
EXPRESSION OF INTEREST (EOI) FOR
DETAILED FEASIBILITY STUDY (DFS) FOR THE DEVELOPMENT, OPERATION AND
MANAGEMENT OF METRORAIL FROM DHULIKHEL TO NAGDHUNGA
2
Expression of Interest (EOI)
A DETAILED FEASIBILITY STUDY (DFS) FOR THE
DEVELOPMENT, OPERATION AND
MANAGEMENT OF METRORAIL FROM
DHULIKHEL TO NAGDHUNGA
Method of Consulting Service:
International
Project Name : Dhulikhel- Nagdhunga Metrorail Project
EOI: OIBN/CONSULTANTANCY SERVICES/METRO/2074/075-1
Office Name : Office of the Investment Board Nepal
Office Address: New Baneshwor, Kathmandu, Nepal
Phone: 977-1-4475277, 4475278, 4475280
Fax: 977-1-4475281
Issued on: 17/05/2018 AD (03/02/2075 BS)
Financing Agency: Government Budget
3
Abbreviations
CV - Curriculum Vitae
DO - Development Partner
EA - Executive Agency
EOI - Expression of Interest
GON - Government of Nepal
PAN - Permanent Account Number
PPA - Public Procurement Act
PPR - Public Procurement Regulation
TOR - Terms of Reference
VAT - Value Added Tax
4
Contents A. Request for Expression of Interest ............................................................................................... 5
B. Instructions for submission of Expression of Interest ................................................................. 8
C. Objective of Consultancy Services or Brief Terms of Reference (TOR).................................... 9 D. Evaluation of Consultant’s EOI Application .................................................................................. 9 E. EOI Forms & Formats ........................................................................................................................ 11 1. Letter of Application ........................................................................................................................ 12 2. Applicant’s Information Form ....................................................................................................... 14 3. Experience ........................................................................................................................................ 15 4. Capacity ....................................................................................................................................... 18
5. Key Experts (Include details of Key Experts only) ................................................................... 20
6. Project Sheets ............................................................................................................................... 20
7. TERMS OF REFERENCE (TOR) ....................................................................................................... 22
“DETAILED FEASIBILITY STUDY (DFS) FOR THE CONSTRUCTION & OPERATION OF METRORAIL
FROM DHULIKHEL TO NAGDHUNGA” .................................................................................................... 22 1 Background: ..................................................................................................................................... 23 2 Objectives: ........................................................................................................................................ 23 3 Scope of work: .................................................................................................................................. 24 3.1 Route Analysis ..................................................................................................................................... 25
3.2 Baseline Survey and Ridership Forecast ........................................................................................ 25
3.3 Transportation model ........................................................................................................................ 26
3.4 Technical investigations .................................................................................................................... 27
3.5 Review of Data and Documents .................................................................................................... 28
4 Deliverables ....................................................................................................................................... 32 4.1 Drawings .............................................................................................................................................. 32
4.2 Investigation Reports ......................................................................................................................... 33
4.3 Designs of Rail Track, pillar, stations, Maintenance Facilities and depot................................ 33
4.4 Detailed Design and 3D Model ...................................................................................................... 34
4.5 Conclusion and Recommendation ............................................................................................... 35
5 Report Submissions ........................................................................................................................... 35 6 Formation of Technical Advisory Group ...................................................................................... 35 7 Project Timeline ................................................................................................................................ 35 8 Qualification Requirement of consulting firm/organization: ................................................... 36 8.1 Consulting Firm/Organization’s Qualification ............................................................................... 36
8.2 Human Resource requirement: ....................................................................................................... 36
9 Other Requirement: ......................................................................................................................... 37 10 Other Commercial Comparisons: ............................................................................................ 37 11 Land Acquisition: ......................................................................................................................... 38 12 Remuneration: .............................................................................................................................. 38 13 Taxation: ........................................................................................................................................ 38 14 Confidentiality: ............................................................................................................................. 39 15 Preparation of Procurement Documents ............................................................................... 39 16 IBN’s Right to the DFS Document: ............................................................................................. 39 17 Conclusion & Recommendations: ........................................................................................... 39
5
A. Request for Expression of Interest
Government of Nepal
Office of the Investment Board
Date: May 17, 2018
NAME OF PROJECT: A DETAILED FEASIBILITY STUDY OF METRORAIL SYSTEM IN
KATHMANDU VALLEY (DHULIKHEL-NAGDHUNGA)
Office of the Investment Board ("OIBN") is considering to conduct a Detailed Feasibility
Study (DFS) on Metrorail Project from Dhulikhel to Nagdhunga to be developed and
operated through Public Private Partnership (PPP) model. OIBN is in the process of
hiring a Consultant to prepare a Detailed Feasibility Study Report ("DFS"). The study will
be funded by the Government of Nepal (“GoN”).
Objectives and Scope
The objective of this study is to assess the feasibility of constructing and operating
Metrorail from Nagdhunga to Dhullikhel with bus parks adjacent to Nagdhunga and
Dhulikhel stations. The route will serve heavy load of passengers entering the
Kathmandu Valley from eastern Nepal via Dhulikhel and passengers entering the
Kathmandu Valley from western Nepal via Nagdhunga on a daily basis. Additionally,
the route will serve the inner city’s east to west mass transit. The work to be
undertaken under this study will cover five major areas, namely:
Development and Operation of Metrorail System in Katmandu Valley
(Dhulikhel-Nagdhunga)
Technical Feasibility of the project
Financial and economic feasibility of the project
Environmental Impact Assessment and Mitigation Measures
Social Impact Study and Mitigation Measures
Legal Appraisal
OIBN invites Expression of Interest ("EOI") from any interested, qualified, eligible and
experienced domestic/international Firms/Companies ("Consultant or Consultants") to
prepare a DFS of the aforementioned project. Experienced, eligible and willing
Consultants are invited to submit their EOI, either alone or as a joint venture. No
Consultant, either solely or as part of a consortium, shall be represented in more than
one EOI submission. The Consultant shall conduct the study, and provide DFS and
other documents as per the Terms of Reference ("TOR") of the Project within the
specified time frame.
The instruction to the Consultant, prescribed formats, evaluation criteria, scope of
6
work, duration of study, and other details of the project are stated in the Terms of
Reference ("TOR"), as provided below.
1. The selection procedure of the Consultant will be governed by the prevailing laws
of Nepal, namely the Public Procurement Act, 2007 (2063 BS) & Public Procurement
Regulation, 2007 (2064 BS), Investment Board Act 2068 (2011) and Investment
Board Regulations 2069 (2012). The received EOI shall be evaluated based on
financial, experience and availability of key personnel of the consultant or their
joint venture.
2. The EOI documents including the ToR may be downloaded from the website of
Public Procurement Monitoring Office (www.bolpatra.gov.np/egp) or IBN
(www.ibn.gov.np). Required documents should be submitted/uploaded by 21
days (5:00 PM Nepal Standard Time) from the first publication date of the EOI
notice:-
i) Duly completed EOI documents in hard copy should be submitted or
received via registered post in the address below:
Office of the Investment Board
ICC Complex, New Baneshwor, Kathmandu, Nepal
Phone: 977-1-4475277, 4475278, 4475280
And/Or
ii) Receive detailed information regarding the EOI process online for
submission of the EOI document at
www.bolpatra.gov.np/egp
3. In case the day of submission of the EOI falls on a public holiday, it should then be
submitted by 5 pm on the following working day. The EOI documents shall be
opened at 11:00 am of the following day of the last EOI submission date.
4. The maximum number of firm in JV shall not be more than three (3).
5. Only shortlisted Consultants will be invited further to respond to the Request for
Proposal ("RFP’) notice from the IBN. IBN reserves the right to accept or reject any
or all of the received EOI Documents with or without giving any reasons
whatsoever. Up to six (6) top ranked firms obtaining at least sixty (60) marks in the
EOI evaluation process will be listed as pre-qualified firms. Further Information or
clarification can be obtained by visiting the IBN website or by contacting the IBN
office within office hours.
6. Pre-qualified firms will be notified 30 days after the EOI Submission deadline with a
7
request for Technical and Financial proposals (RFP). Further selection during the
RFP process will be in accordance with the Quality and Cost Based Selection
procedure (QCBS).
8
B. Instructions for submission of Expression of Interest
1. Expression of Interest may be submitted by a sole firm or a joint venture of
consulting firms.
2. Interested consultants must provide information indicating that they are qualified
to perform the services (descriptions, organization and employee of the firm or
company, description of assignments of similar nature completed in the last 7 years
and their location, experience in similar conditions, general qualifications and the
key personnel to be involved in the proposed assignment).
3. This expression of interest is open to all eligible consulting firm/company/
organization.
4. The assignment has been scheduled for a period of fifteen (15) months. Expected
date of commencement of the assignment is August 01, 2018.
5. A Consultant will be selected in accordance with the Quality and Cost-Based
Selection (QCBS) process.
6. Expression of Interest should contain the following information:
(i) A Cover Letter addressed to the representative of the client on the official letter
head of the company duly signed by the authorized signatory.
(ii) Applicants shall provide the following information in the respective format
given in the EOI document:
EOI Form: Letter of Application (Form 1)
EOI Form: Applicant’s Information (Form 2)
EOI Form: Work Experience Details (Form 3(A), 3(B) & 3(C))
EOI Form: Capacity Details (Form 4)
EOI Form: Key Experts List (Form 5).
7. Applicants may submit additional information with their application but
shortlisting will be based on the evaluation of information requested and
included in the format provided in the EOI document.
8. The Expression of Interest (EOI) document must be duly completed and
submitted in sealed envelope and should be clearly marked as “EOI Application
for Short-listing for the Detail feasibility study for the construction and operation
of Metrorail Dhulikhel to Nagdhunga Project. The envelope should also clearly
indicate the name and address of the Applicant. Alternatively, applicants can
submit their EOI application through e-GP system by using the forms and
instructions provided by the system.
9. The completed EOI documents must be submitted on or before the date and
should be addressed to the address mentioned in the “Request for Expression of
Interest”. In case the submission falls on a public holiday the submission can be
made on the next working day. Any EOI Document received after the deadline
9
for submission of proposals shall not be considered for evaluation.
C. Objective of Consultancy Services or Brief Terms of Reference
(TOR) [Provide detail objectives of the consultancy services with expected
deliverables or alternatively provide Brief TOR]
D. Evaluation of Consultant’s EOI Application Consultant’s EOI application which meets the eligibility criteria will be ranked on the
basis of the Ranking Criteria
i) Eligibility & Completeness Test Compliance
Copy of Registration of the company/firm
VAT/PAN Registration (for National consulting firm
only)
Tax Clearance/Tax Return Submission/Letter of Time
Extension for Tax Return Submission [insert Fiscal
year] (for National consulting firm only)
Net worth of the Firm should be positive for the last
three consecutive years
EOI Form 1: Letter of Application
EOI Form 2: Applicant’s Information Form
EOI Form 3: Experience (3(A) and 3(B))
EOI Form 4: Capacity
EOI Form 5: Qualification of Key Experts Only those consultants who qualify in eligibility and completeness based on the parameters
above will be considered for further evaluation
SN ii) EOI Evaluation
Criteria
Minimum
Requirement
A. Qualification of Key
Experts
Marks
35
Minimum
experience
in year
after
Bachelor
Degree
Education required
International Experts (23)
1 Team
Leader/Metrorail
Expert
5.5 15 PhD/M.Sc. in
Transportation/Railway
Engineering or
equivalent
10
2 Alignment Engineer 3.5 12 M.Sc. in alignment
Engineering or
equivalent
3 Structural Engineer 3.5 12 M.Sc. in
Structure/Bridge
Engineering
4 Geotechnical
Engineer
3.5 10 M.Sc. in Geotechnical
Engineering
5 Transport Economist 3.5 10 M.Sc. in Transport
Economics or
equivalent
6 Finance Expert 3.5 10 Masters in Finance,
MBA or equivalent
National Expert (12)
7 Structural Engineer 3 10 M.Sc. in
Structure/Bridge
Engineering
8 Environment Expert 3 10 Masters Environment
Engineering
9 Geotechnical
Expert
3 5 Masters in
Geotechnical
Engineering
10 Electrical Engineer 3 5 Masters in Electrical
Engineering
B. Experience of the Firm
General
experience of
Consulting Firm
10
List all projects: Completion of
general civil engineering works more
than USD 1.5 million. The completed
projects should include
Environmental Impact Assessment
(EIA), Social Impact Assessment (SIA)
and soil exploration and testing
component.
Specific experience
of Consulting Firm
within last 7 years
35 List all projects:
1. Completion of Detailed Design or
Feasibility Study of Metrorail projects
(At least 20 km of length/network).
The projects that were implemented
and supervised by the consultant
after detailed feasibility study shall
be given priority.
11
Similar
Geographical
experience of
Consulting Firm
5 List projects completed in same
geographical region
C. Capacity
Annual turnover of
the Consulting Firm
15 List the turnover of last 5 years:
General Consultancy services
turnover of best three years in last 5
years should be US $ 2.5 million.
E. EOI Forms & Formats Form 1. Letter of Application
Form 2. Applicant’s information
Form 3.Experience (General, Specific and Geographical)
Form 4. Capacity
Form 5. Qualification of Key Experts
12
1. Letter of Application
(Letterhead paper of the Applicant or partner responsible for a joint venture,
including full postal address, telephone no., fax and email address)
Date: …………..
To,
Full Name of Client: __________________________
Full Address of Client: ________________________
Telephone No.: ______________________________
Fax No.: ____________________________________
Email Address: _______________________________
Sir/Madam,
1. Being duly authorized to represent and act on behalf of (hereinafter "the
Applicant"), and having reviewed and fully understood all the short-listing
information provided, the undersigned hereby apply to be short-listed by [Insert
name of Client) as Consultant for {Insert brief description of Work/Services}.
2. Attached to this letter are photocopies of original documents defining:
a) the Applicant's legal status;
b) the principal place of business;
3. [Insert name of Client] and its authorized representatives are hereby authorized to
verify the statements, documents, and information submitted in connection with this
application. This Letter of Application will also serve as authorization to any
individual or authorized representative of any institution referred to in the
supporting information, to provide such information deemed necessary and
requested by yourselves to verify statements and information provided in this
application, or with regard to the resources, experience, and competence of the
Applicant.
4. [Insert name of Client) and its authorized representatives are authorized to
contact any of the signatories to this letter for any further information.1
5. All further communication concerning this Application should be addressed to the
following person,
1 Applications by joint ventures should provide on a separate sheet, relevant information for each party to the
Application.
13
[Person]
[Company]
[Address]
[Phone, Fax, Email]
6. We declare that we have no conflict of interest in the proposed procurement
proceedings and we have not been punished for an offense relating to the
concerned profession or business and our Company/firm has not been declared
ineligible.
7. We further confirm that if any of our experts is engaged to prepare the TOR for any
ensuing assignment resulting from our work product under this assignment, our firm,
JV member or sub-consultant, and the expert(s) will be disqualified from short-listing
and participation in the assignment.
8. The undersigned declares that the statements made and the information provided
in the duly completed application are complete, true and correct in every detail.
Signed :
Name :
For and on behalf of (name of Applicant or partner of a joint venture):
14
2. Applicant’s Information Form
(In case of joint venture of two or more firms to be filled separately for each
constituent member)
1. Name of Firm/Company:
2. Type of Constitution (Partnership/ Pvt. Ltd/Public Ltd/ Public Sector/ NGO)
3. Date of Registration / Commencement of Business (Please specify):
4. Country of Registration:
5. Registered Office/Place of Business:
6. Telephone No; Fax No; E-Mail Address
7. Name of Authorized Contact Person / Designation/ Address/Telephone:
8. Name of Authorized Local Agent /Address/Telephone:
9. Consultant’s Organization:
10. Total number of staff:
11. Number of regular professional staff:
(Provide Company Profile with description of the background and
organization of the Consultant and, if applicable, for each joint venture
partner for this assignment.)
15
3. Experience
3(A). General Work Experience
(Details of assignments undertaken. Each consultant or member of a JV
must fill in this form.)
S.
N.
Name of
assignment
Location Value of
Contract
Year
Completed
Client Description of work carried
out
1.
2.
3.
4.
5.
6.
7.
(Please provide CVs of each Consultant)
16
3(B). Specific Experience
Details of similar assignments undertaken in the previous seven years
(In case of joint venture of two or more firms to be filled separately for each
constituent member)
Assignment name:
Approx. value of the contract (in current
NRs; US$ or Euro)2:
Country:
Location within country:
Duration of assignment (months):
Name of Client:
Total No. of person-months of the
assignment:
Address:
Approx. value of the services provided by
your firm under the contract (in current
NRs; US$ or Euro):
Start date (month/year):
Completion date (month/year):
No. of professional person-months
provided by the joint venture partners or
the Sub-Consultants:
Name of joint venture partner or
sub-Consultants, if any:
Narrative description of Project:
Description of actual services provided in the assignment:
Note: Provide highlight on similar services provided by the consultant as
required by the EOI assignment.
Firm’s Name:
2 Consultant should state value in the currency as mentioned in the contract
17
3(C). Geographic Experience
Experience of working in similar geographic region or country
(In case of joint venture of two or more firms to be filled separately for each
constituent member)
No
Name of the Project
Location
(Country/ Region)
Execution Year
and Duration
1.
2.
3.
4.
5.
6.
7.
18
4. Capacity
4(A). Financial Capacity
(In case of joint venture of two or more firms to be filled separately for each constituent
member)
Annual Turnover
Year Amount Currency
- Average Annual Turnover
(Note: Supporting documents for Average Turnover should be submitted for the
above.)
19
4(B). Infrastructure/equipment related to the proposed assignment3 No Infrastructure/equipment
Required
Requirements Description
1.
2.
3.
4.
5.
3 Delete this table if infrastructure/equipment for the proposed assignment is not required.
20
5. Key Experts (Include details of Key Experts only)
(In case of joint venture of two or more firms to be filled separately for each
constituent member)
SN Name Position Highest
Qualification
Work Experience
(in year)
Specific
Work
Experience
(in year)
Nationality
1
2
3
4
5
(Please insert more rows as necessary. Please provide CVs of each Key Experts. )
6. Project Sheets
Indicate up to 10 reference projects from the past 7 years that the
firm/association/joint venture feels are relevant.
Project 1 of __
Project Name
Name of Client
Country Project location within Country
Participation
As lead firm
As associate firm
Value of Services (US$)
Source of Financing
Consultancy Services
(i) No. of key professional staff
(ii) No. of person months
Length of Consultancy Assignment
Start Date (dd/mm/yyyy)
21
Completion Date (dd/mm/yyyy)
Name of Associate Firms (if any)
No. of Person-Months of Professional Staff Provided by Associated Firm(s)
Name of Senior Staff (Project Director/Coordinator, Team Leader) Involved and
Functions Performed
Detailed Narrative Description of the Project
Detailed Description of the Actual Services Provided by your Firm
22
New Baneshwor, Kathmandu, Nepal
Phone: 977-1-4475277, 4475278, 4475280
Fax: 977-1-4475281
TERMS OF REFERENCE (TOR)
For
“DETAILED FEASIBILITY STUDY (DFS) FOR THE DEVELOPMENT,
OPERATION AND MANAGEMENT OF METRORAIL FROM
DHULIKHEL TO NAGDHUNGA”
23
1 Background: The Investment Board Nepal (IBN), established in 2011, is a high-level government
body chaired by the Right Honorable Prime Minister. IBN functions as a central fast-
track government agency established to facilitate economic development in
Nepal by creating an investment-friendly environment, mobilizing and managing
domestic as well as foreign investments.
IBN serves as a one window facility for domestic and foreign investors pursuing
large scale projects. It selects proposals for investment, facilitates investment,
coordinates between various ministries, and monitors the progress of approved
projects. As a private face for the government, it leads the promotion of
investment, supports investors, signs fair and bankable contractual agreements
with developers, and cooperates with Government in facilitating the execution of
these agreements.
The Investment Board Act, 2011 gives the Office of the Investment Board of Nepal
(OIBN) a broad mandate to fulfill the role of a Public Private Partnership (“PPP”), as
well as an Investment Development and Promotion, body.
IBN has been playing a role of an approval agency as well as facilitator especially
for mega investment projects. The Board has till date approved 4 hydropower
projects, 3 cement projects and 2 solid waste management projects and is
facilitating them to come into operation at the earliest.
As per IBN Act, 2011 section 9 (a) Fast track road, Tunnel, Railway line, Rope-way,
Trolleybus as prescribed by Government of Nepal and section 9 (k) Investment
required for any infrastructure or service industry that has a paid-up capital of Rs.
10 billion or a project cost exceeding that amount, are IBN’s mandate.
In this regards, the OIBN is seeking a consulting firm to conduct a Detailed
Feasibility Study for the development and operation of Metrorail system from
Dhulikhel to Nagdhunga to ease out the traffic management.
2 Objectives: The objectives of the proposed DFS aim to examine the economic, financial,
political, social, environmental, and technical viability of the proposed Metrorail
System. The DFS report is required to recommend the sustainability and its
replicability. Any issues related to the recommended routes and sites are to be
24
considered as a part of the DFS report. The study report shall be prepared in a
manner which ensures;
Enhanced safety of the traffic, the road users and the people living close to
the alignment.
Enhanced traffic management of the city.
Enhanced operational efficiency of the urban transit of Kathmandu Valley.
Fulfillment of the mobility needs of the growing population in Kathmandu
Valley
Minimal adverse impact on the road users and the local population due to
construction.
Identification of feasible and constructible options for the project with least
cost options.
Environmental and Social Impact Assessment of the selected option
3 Scope of work:
Scope of services shall include but not limited to the following:
Consultant shall prepare the DFS the development and operation of the Double
track rail System clearly spelling out the feasible Engineering, technological and
management solutions (with detailed design). The Consultant should keep in mind
that the systems are safe, efficient and convenient to the users as well as public
living adjacent to the alignment. The DFS report of the project shall ensure the
following:
The system is safe for the passengers and the public living adjacent to the
alignment
Construction of the project through proven technological solutions
Construction is least disruptive to the road users and the public living near
to the alignment
Operation, management and maintenance of the Metrorail should be
smooth and efficient
Facilities available should be used up to maximum extent.
Within the given constraints, the solutions are sound, sustainable,
economical, and environmentally, socially, financially and technically
viable, constructible and manageable.
Topographic survey, geotechnical investigation and testing are to be
carried out.
25
Hydraulic and hydrographic investigation for all structures are to be carried
out.
Track and viaduct Investigation are to be carried out.
Traffic studies including traffic surveys, demand forecasting, tariff option
studies for next thirty years are to be carried out.
Inventory and Condition surveys for existing road are to be carried out.
Identification of sources of construction materials are to be carried out.
Identification of required number of pillars and stations should be done.
Investigation for new planned structures like underpasses, flyovers and their
design are to be carried out.
Design of stations, depots, pillars and identification of their numbers and
location and office cum residential complex should be carried out.
Design and operation plan of maintenance facilities are to be carried out
Study and design should be carried out considering seismic factor.
Local resources should be used at maximum extent.
Involuntary resettlement particular for depot area.
Preparation of Detailed Design Project Report, Cost Estimate for execution
of work.
Financial, Environment, Social, Technical and Economic Analysis should be
carried out.
Recommendation and Conclusion
Identifying the public and private land required for the civil works and
information on existing land use and valuations
3.1 Route Analysis The Consultant shall carry out below activities:
Identify and carry out detailed analysis of at least three different alignment
joining Dhulikhel and Nagdhunga.
Ensure the proposed rail alignment should not have any adverse impact
on the existing transportation systems.
Recommend the most appropriate alignment joining Dhulikhel and
Nagdhunga with regards to technical, economical, financial,
environmental and social aspects
Identify Rights of Way required to implement the project for all identified
alignment
Identify the sections that should be underground and/or elevated with
justification.
3.2 Baseline Survey and Ridership Forecast
The data to be collected and updated are those required for the purpose of
26
transport strategic planning. These would include both historical and spatial
data. Considering the vast area under Kathmandu Valley its surrounding
municipalities, the population and its distribution over the area, the sample
size for the survey should be determined based on the size and spread of the
geographical sections.
There is no systematic, continuous collection of traffic data within the City and
Valley. For the purposes of the DFS, the Consultant shall review these data and
determine where additional Origin Destination (O+D) Survey , journey time,
and traffic count surveys may be required in order to address key issues
including trip purpose, vehicle type, traffic seasonality as well as turning
movements at key junctions. Also, as no recent data on employment exists,
the Consultant should present a methodology to address this lack of the data
for the model, in the Inception Report. Lastly, the DFS should estimate the
ridership for the proposed Metrorail under different development and tariff
structures and carry out the necessary sensitivity analysis.
3.3 Transportation model
The Consultant shall recommend a model package that would be suitable for
Kathmandu Valley planning needs. The purpose of the travel demand model
is to provide good policy-related and future travel forecasts, and therefore,
should be simple. The conventional approach of developing the 4-stage
model at aggregate level (except the modal choice at disaggregate level)
should be followed.
The model should integrate household activities, land use patterns, traffic flow,
and regional demographics. The core of the proposed model system is a
household activity simulator that determines the locations and travel patterns
of household member’s daily activities by trip purpose. The model should
estimate travel behavior with regard to longer term choices of residential and
employment location, and land use and adaptive behavior in response to
transportation system changes, including fare and pricing policy.
The Consultant should recommend appropriate software package(s) suitable
for the development of the requisite model in the Inception Report. The
Consultant shall undertake an overview of various models such as Trans CAD,
SATURN, CUBE, etc. with their merits and demerits and recommend a model
package that would be suitable for Kathmandu Valley planning needs. The
final decision on the selection of software package (s) will be made by IBN
within 15 days of presentation of options along with merits and demerits. The
software package (s) should in particular be capable of:
27
Modeling mode split, including walk, public transport modes (Metrorail,
Metrorail, bus, taxis, etc.) and private transport (motorcycle, car, etc.),
good's vehicles
Assigning trips to Metrorail taking into account the condition in Metrorail
due to changes in overall traffic volume, and fares
Reflecting the impact of new land use developments and / or control
policies, including truck terminals, truck parking lots, interstate bus terminal
etc.
Responding to traffic demand management measures such as parking
fees, road user charges and congestion pricing as well as the staggering
of working hours, flexi hours and multiple shift work
Using the recommended software and methodology, the Consultant shall
prepare a Multi-modal transport integration plan for this project.
3.4 Technical investigations
The Consultant shall carryout Technical appraisal of Metrorail technology,
worldwide experience (including type of technology and adopted costs) with
recommendation for technology most suited for this alignment. The followings
tasks are to be carried out:
Identify and analyze all the available rail technologies including but not
limited to, Heavy Rail, Light Rail (AGT, Metrorail, Sky rail, Tram)) in detail;
Recommend the most appropriate rail technology systems
Technical feasibility of the alignment and identification of station locations;
Identification of location of depot and depot layout;
Construction Methodology;
Details of power supply options, signaling, information and ticketing
systems;
Operation Plan and Service Details;
Passenger Dispersal and integration facilities with other modes of public
transport;
Safety features, evacuation of passengers and handling emergencies;
Technical Investigations of Park and Ride and other Commercial entities
that would boost Metrorail ridership;
Recommendations on the choice of Metrorail technology and the
specifications to be used;
Train operation plan;
Detailed analysis of rolling stock;
Detailed analysis and design of disaster management plan for metro;
Security and safety measures for a metro systems;
28
Implementation strategy and project implementation plans;
3.5 Review of Data and Documents
The Consultant shall collect the available data and information relevant for
the Study The data and documents of major interest shall include, but not be
limited to, the following:
Climate;
Road inventory
Hydraulic and hydrographic data, drawings and details of existing bridges;
Details of sanctioned / on-going works on the stretch sanctioned by GoN
Survey and evaluation of locally available construction materials;
Historical data on classified traffic volume (preferably for 5 years or more);
Origin-destination and commodity movement characteristics; if available;
Type and location (height and depth) of existing utility services (e.g.
Optical Fiber Cable, O/H and U/G Electric, Telephone line, Water mains,
Sewer, Trees etc.)
3.5.1 Surveys, Study and Investigation
3.5.1.1 Traffic Surveys
The following type of traffic surveys shall be carried out along and in the
vicinity of the Project Road.
Origin-Destination Characteristics
Intersection Volume Count at All Major Intersections
Estimation of Passenger Volume for Next 30 Years
Consultant shall make traffic demand estimates and establish
possible traffic growth rate scenarios based on (i) trend
growth, and (ii) demand elasticity methods in respect of all
categories of passengers. Consultant shall also make
estimates of generated traffic (due to development of the
influence area of the Metrorail). The choice of the traffic
projection models, the inputs to the models and the
assumptions made shall be clearly stated with justification. The
traffic demand estimates shall be done for the period of 30
years.
3.5.1.2 Topographic, Hydraulic and Hydrological surveys and study
Desk study of existing study reports
GPS survey using DGPS instrument, fixing benchmarks pillars at 1.5 km
interval or suitable location
Fixing Temporary Bench Marks at 250 m interval
29
Total Station/ Drone traverse including collection of existing features along
the alignment and within Right of Way at 0.5 contour interval
Carry out leveling including longitudinal section at 25m c/c distance and
cross section at 50m c/c distance from the center line of the alignment
Survey and mapping of major structural components of the projects in
1:1000, 0.5m contour interval.
Topographic survey shall be carried out to 3rd order precision and the
admissible error of closure shall not exceed 12 x k0.5 mm, where k is the
distance in kilometers. The area shall be covered by traverse net,
triangulation net and a few random lines to establish the location of the
items related to the investigation and key structures. Horizontal control
survey shall be tied into the existing geodetic net. Benchmark shall be
adopted for vertical survey control. Coordinates of all stations marked as
triangles shall be provided by the survey. The expatriate trigonometric
points, which are necessary for ground control and for mapping with
stereo plotting machine shall be connected.
Hydraulic and Hydrological study shall consist of;
L-Section and Cross section for bridges for a minimum length of 250 m on
upstream and downstream along the Bridges.
Collection of all Hydrological Data from the all the relevant weather
stations and DHM.
Cross-sections and L-sections shall be taken at intersecting roads at contor
interval of 0.5 m and cross-section at 25 m c/c at the required length.
3.5.1.3 Road Inventory surveys Collect the number and locations of the existing features like bridges,
culverts, ROBs, underpasses, drains, protection works, other amenities
and road furniture, pavement details (e.g. width/thickness of layers),
GAD of bridges, culverts and structures.
3.5.1.4 Geotechnical and Geological Study & Investigation Conduct Geological field survey and geophysical electrical
resistivity tomography (ERT) survey
Conduct Soil Investigation (Drilling, Boring & Report, at least at 200m
interval of the whole alignment (30 m deep)).
Conduct representative boring at Abutment or pier location of
proposed elevated track and conduct necessary testing to assess
foundation type requirement
30
Prepare profiles of different layers at each investigated site (Bore
Log)
Conduct sampling, testing, particle size distribution
3.5.1.5 Construction Material surveys Survey the material sources, collect the sample and carry out tests
for confirming quality to use.
3.6 Design of the Project
Present detailed design of project including but not limited to track, rail,
pillar, tunnel, station, depot, bus parks etc. considering international
standards.
3.7 Signaling & Telecommunications
This shall focus on the following points: -
Defining signaling and telecommunication system based on traffic
forecasts and resulting density of traffic for each section/network
Rules & regulations, local requirements, flexibility for operation etc.
Technical design standards of the proposed systems.
Study of various modern signaling and telecommunication systems and
description of salient design features, broad outline of specifications of
the equipment and power supply system etc. of the recommended
system.
Yard lay outs.
Signaling and telecommunication plans for the selected routes.
Establishment of maintenance workshops and centers, maintenance
structure and organization etc.
3.8 Locomotive and Rolling Stock
The Consultant s shall make a preliminary assessment of appropriate
workshop, maintenance facilities and define the type of rolling stock to be
maintained. The scope of work will include
Study of types of locomotives and recommendation of suitable type of
locomotive.
Define the type of rolling stock to be maintained
Design standards and criteria for the new rolling stock
Requirement of rolling stock (locomotives, coaches, special stock, if any)
based on traffic forecasts, location of Loco Sheds, Sick Lines, and Washing
Lines etc.
31
3.9 Electric Power Study
Electricity requirement for official and residential buildings.
Identification of source of supply and purchase of electricity (voltage &
capacity).
Distribution network for supply to stations, yards, residential/office building,
colonies, pumping stations and signaling equipment etc.
Location/capacity of pumping stations including ground water
exploration.
Electric Power Generation, if required.
Estimation of required electricity for the system
Identification and recommendation of alternative source of electricity.
Details of transformers
3.10 Environmental and Social Impact Assessment
Environmental and Social Impact Assessment should be conducted as per
EPA/ EPR 1997 and laws of Nepal.
The assessment report should include the following:
Legal Framework
Baseline Environmental Condition
Project Impacts (Physical, Biological, Socio-economic & Cultural)
Alternative analysis
Mitigation and Enhancement
Environmental Management Plan
Project Monitoring
Environmental Benefit and Cost Estimates
Environmental auditing
3.11 Implementation
Project implementation plan
Operations, management and maintenance plan
Hazard rescue plan
Coordination with other intuitions concerning with road usages
Detailed metro operations plan
3.12 Cost Estimation
Rate Analysis for various items of works
Work out Bill of Quantities for the project
Estimation of cost for traffic diversion measures
Cost estimation for Environmental Management Plan, Environmental
monitoring and auditing activities
32
Cost estimates of the equipment, recurring expenditure, availability of
spares, cost of training etc.
Cost Estimate for construction of all items of Works
Cost Estimate for the public and private land required for the civil works of
the project
3.13 Financial and Economic Analysis
To workout Commute Cost and Time Savings for 1) With Project and 2)
Without Project
Tariff Rates to be proposed on the Project
To work out Financial Internal Rate of Return (FIRR), Economic Internal Rate
of Return (EIRR), Net Present Value (NPV), Debt Service Coverage Ratio
(DSCR), etc.
To carry out sensitivity analysis and work out FIRR, EIRR, NPV, DSCR for
various options (consider factors including but not limited to, changes in
cost, time, tariff rate, late implementation etc)
To provide Conclusion on Results and recommendation of the project.
4 Deliverables Consultant shall deliver the following in the Detailed Feasibility Study Report (DFS):
4.1 Drawings
A set of drawings such as Plans, L-sections, Cross-sections, and Detailing
etc, showing all the existing features within the ROW (e.g. Metrorail track,
pillar, stations, depots, structures, rails, utilities, adjoining land use,
intersecting roads, road side developments, road furniture, safety features
etc.) with the proposed improvements marked hereon (e.g. new
subways/underpasses/grade separators, arrangements for
merging/diverging, traffic circulation, additional road furniture, relocation
of utilities, etc).
Traffic circulation plan indicating the location of proposed underpasses,
bridges, flyovers and other structures, intersecting roads, and access
roads.
General Arrangement Drawings of large/ major/ minor structures.
General Arrangement Drawings including plan & profile, support systems
for bridges.
A strip plan showing all the existing and proposed features
Junction Improvement Plan for Major and Minor Intersections
Plan for stations and related amenities
33
Plans and typical drawings for drainage.
Detailed drawings identifying the public and private land required for the
civil works and information on existing land use and valuations
Associated changes to the road infrastructure to accommodate the
elevated lines, stations, depots, and transport interchanges
Deatailed drawings of the bus parks at Dhulikhel and Nagdhunga
4.2 Investigation Reports
Topographic survey Report including Coordinates of Benchmark Pillars,
Temporary Bench Marks, Leveling carried out at specified intervals etc.
Geotechnical Investigation Report including earthquake resilience for
boring work executed at all large/ major/ minor pillars, bridges along the
existing and proposed road including recommendation for type of
foundation to be provided for relevant structure.
Material Investigation report including test and conclusion for borrow are
soil, aggregates, sub grade soil etc.
Traffic survey data on:
Traffic study of the alignment.
Detailed Ridership Forecast for next 30 years.
ROW condition survey data on:
Existing utilities
Water supply and sewerage pipeline network
Electricity and communication lines
Environment and Social Impact Assessment
Hydrological and meteorological data collected
4.3 Designs of Rail Track, pillar, stations, Maintenance
Facilities and depot
The consultant is to carryout detailed designs and prepare detailed drawings
for the following:
Metrorail tracks and support structures
Stations and depots at appropriate locations;
Traffic analysis and forecasting
Bridges, viaduct/subways and structures etc.;
At-grade and grade-separated intersections, interchanges (if required);
Prepare alignment plans, longitudinal sections and cross-sections @ 50 m
intervals but @25 m interval;
Designs and drawings for service road/under passes/overpass / tree
planting/fencing at locations where necessary / required
34
Office-cum-residential complex for PIU (one for each civil contract
package)
Drainage design
Maintenance facilities
Traffic amenities (Parking and Ride, etc.).
Design of Major Junctions and Typical Arrangement for Minor Junctions
including the proposed metro lines in Kathmandu Valley.
Design of the bus parks at Dhulikhel and Nagdhunga
4.4 Detailed Design and 3D Model Geometric Design to meet the requirements for constructing an elevated track for
Metrorail. The design shall consist of the following:
Complete layout of the proposed elevated track with all the features
shown there on
Traffic circulation plan indicating the location of proposed stations and
other amenities.
Design of Drainage System
Associated changes to the road infrastructure to accommodate the
elevated lines, stations, depots, and transport interchanges
Hydraulic calculations for bridges based on field and topo sheets
Design of structures like underpasses, flyovers, pedestrian under passes,
indicating the approximate sections and General Arrangement Drawings
(GAD) required for the project
Scheme and design for new bridges proposed along the new alignment
Detailed design for improvement for Junctions
Details of power supply options, signaling, information and ticketing
systems
Detailed analysis of rolling stock
Detailed analysis and design of disaster management plan for Metrorail
(for instance, if one cabin stuck in between two stations)
Security and safety measures for a Metrorail systems
Implementation strategy and project implementation plans
Multi-modal transport integration plan
Detailed drawings identifying the public and private land required for the
civil works and information on existing land use and valuations
Conceptual Design for traffic management during construction
Design of Arboriculture and Landscaping
Preparation of Report of Quality Assurance Plan
Design of mitigation measures on Environmental and Social issues and
preparation of reports.
35
4.5 Conclusion and Recommendation
Summary
Conclusion
Recommendation
5 Report Submissions The Draft Detailed Report and Final Detailed Report containing details specified under
Clause 3 shall be submitted along with soft copy of design, drawings including copy of
Auto-CAD, Cost Estimate, Financial and Economic Analysis
6 Formation of Technical Advisory Group IBN will form an evaluation team comprising all relevant institutions and experts to
evaluate and give comments and feedback to Consultant.
7 Project Timeline
The time-line for the accomplishment of various activities will be as follows:-
The overall DFS period will be for fifteen (15) months beginning from the award
of the consultancy to the selected Consultant after the completion of the RFP
process.
Field visit, data collection and preparation of Inception Report must be
submitted and discussed in the stakeholder meetings two (2) month after the
agreement is signed.
First Draft Report should be submitted to the IBN eight (8) months after the
Inception Report.
First Draft Final Report should be submitted to the IBN three (3) months after the
First Draft Report.
Final reports need to be submitted two (2) months after the Presentation. The
final report must incorporate IBN comments.
Progress report to be submitted each month to the IBN.
(Note: Environmental Assessment and Social Impact Study should be completed
within the DFS timeline)
36
8 Qualification Requirement of consulting
firm/organization:
8.1 Consulting Firm/Organization’s Qualification
Firm Registration Certificate
VAT/PAN Registration Certificate
Tax Clearance Certificate for FY2015/16 (072/73 BS)
Tax Clearance Certificate or Tax Pay Slip for FY2016/17 (073/74 BS)
Minimum 5 years of experience in the related field
The Consultant s submitting EOI in joint venture shall furnish duly signed
Joint Venture Agreement stating responsibility of each partner of Joint
Venture and name of authorized signatories through attorney of power
signed by each Joint Venture firm.
If the proponent is a firm/company the detail of assignment of similar
nature performed in the last five years and their locations of execution
shall be provided.
8.2 Human Resource requirement:
The qualifications of the core team members shall be as follows:
S.
N.
Key Experts Minimum
experience in
the related field
(year
after Master’s
Degree)
Education required
1 Team Leader/Mass
Raipd Transit Expert
15 PhD/M.Sc./equivalent in
Transportation/Railway Engineering
2 Traffic and Transport
Planner
12 M.Sc. in Transportation/Traffic
Engineering
3 Alignment Engineer 12 M.Sc. in Alignment Engineering
4 Structural Engineer 12 M.Sc. in Structure/Bridge
Engineering
5 Hydraulic Expert 12 M.Sc. in Hydraulic Engineering
6 Geotechnical
Engineer
10 M.Sc. in Geotechnical Engineering
7 Railway Rolling
Stock Specialist
10 M.Sc. in Rolling Stock Engineering/
Mechanical or Equivalent
Standard EOI Document
37
Engineering
8 Transport Economist 10 M.Sc. in Transport Economics or
equivalent
9 Finance Expert 10 Masters in Finance, MBA or
equivalent
10 Automated fare
collection expert
10 M.Sc. in
Mechanical/Electrical/Electronic
Engineering
11 Metrorail System
Operator Expert
10 M.Sc. in Transportation/Railway or
equivalent engineering
12 Railway Signaling
and
Communication
Engineer
10 M.Sc. in Signaling and
Communication Engineer
13 Tunnel Engineer 10 M.Sc. in Tunnel Engineering
14 Hydrologist 10 M.Sc. in water resources/hydrology
engineering
15 Structural Engineer 10 Masters in Structural Engineering
16 Electrical Engineer 10 Masters in Electrical Engineering
17 Environment
Engineer
10 Masters in Environment engineering
18 Social Impact
Assessment Expert
10 Masters in Social Science or
equivalent
19 Legal Expert 10 LLM or equivalent
20 Geo-technical
Expert
10 Masters in Geotechnical
Engineering
21 Civil Engineer 5 Bachelors in Civil Engineering
9 Other Requirement: Brief on Rehabilitation and Resettlement (R&R) and local employment issues.
Key issues to be addressed for the project, such as environment and wild life
issues etc.
The Consultant shall weigh the pros & cons of the project and make
recommendation with proper justification to enable IBN to
Make an informed decision on the project proposal.
10 Other Commercial Comparisons: The Consultant will be required to present detailed comparative technical and
financial analysis by conducting a comparison between various development,
operations and management modality including but not limited to government
funding, Government to Government arrangement (G2G), Joint Venture
between private and government and different types of PPP models.
Standard EOI Document
38
Furthermore, the Consultant will be required to examine required Viability Gap
Funding (VGF).
Present the detailed comparison between PPP model and Government
financing and recommend the most suitable approach.
Investigate, analyze and recommend all the possible ways, methods and
strategies to make this project viable and attractive for private sector to
develop and operate under PPP model.
Investigate and recommend the operating schedule of the project with respect
to seasonal and peak/off-peak rates period. Optimize operation to maximize
usages during off-peak hours.
Investigate the optimal headway and operating time taking into consideration
of the resource and passenger volume.
11 Land Acquisition: Identify and recommend the total required land (private, forest and individual)
including Right of Way (ROW) for the project.
Recommend and identify the total land to be acquired for the project.
Key issues to be addressed for land acquisition.
The Consultant shall estimate the total land acquisition cost for the project.
12 Remuneration: IBN shall pay to Consultant a fixed fee to be negotiated and agreed upon with
the selected Consultant. The fee shall be payable in three installments:
20% of the total bid amount after inception report.
50% of the total bid amount after the submission of First Draft Final Report
incorporating IBN’s concerns on the First Draft Report.
Remaining 30% of the total amount after the acceptance of the Final
Report.
13 PERFORMANCE SECURITY Consultant shall produce unconditional performance security of 5% of total
contract amount prior to the agreement. In case of non-performance of the
contractual obligation, IBN shall have the right to confiscate the Performance
Security.
14 Taxation: The consultancy firm is fully responsible for all taxes imposed by the relevant laws
of GoN.
Standard EOI Document
39
15 Confidentiality: The consultancy firm shall not disclose the information collected in this
assignment during the term of this assignment and thereafter to anyone who is
not authorized by IBN.
16 Preparation of Procurement Documents The consultancy firm shall prepare all tender document, including but not
limited to Expression of Interest (EoI), Request For Proposals (RFPs) and
evaluation documents for the procurement of developer/contractor to
develop and operate Metrorail project.
The consultancy firm shall prepare draft Project Development Agreement (PDA)
to be signed with the prospective developer under Public-Private-Partnership
(PPP) considering all relevant laws of Nepal.
17 IBN’s Right to the DFS Document: Once the Consultant completes the DFS work, the DFS and all related materials,
including but not limited to, any intellectual property, design, technology that
may form part or all of the DFS content, shall become the property of IBN.
Consultant will not incorporate anything that would restrict the right of IBN or
the GoN to modify, further develop or otherwise use the materials in any way
IBN or GoN may deem necessary. In addition, the Consultant will warrant that
the provision of the Services and Deliverables will not infringe on any third-party
intellectual property rights.
18 Conclusion & Recommendations: Conclusion and Recommendations shall draw together the findings of the DFS
report. In the conclusion and recommendations section the proponent shall
present, including but not limited to, the following:
Summary of Key Issues
Main Conclusions
Recommendations