DESIGN REPORT ON SITE STORMWATER AND SOIL MANAGEMENT
Transcript of DESIGN REPORT ON SITE STORMWATER AND SOIL MANAGEMENT
www.lp-consulting.com.au
T: +61 2 9223 4444
M: +61 416 256 955
A: Suite 2, Level 8, 15 Castlereagh Street Sydney NSW 2000
P: P.O. Box 814 Kensington NSW 1465
E: [email protected] ACN: 165 018 968 ABN: 61 165 018 968
• DESIGN AND PROJECT MANAGEMENT
• CIVIL ENGINEERING
• WATER AND WASTEWATER ENGINEERING
• BUILDING AND INFRASTRUCTURE
• HYDRAULIC AND FIRE SERVICES
• SYDNEY WATER REGISTERED
WATER SERVICING COORDINATOR,
DESIGNER AND PROJECT MANAGER
• EXPERT TECHNICAL ADVICE
DESIGN REPORT ON SITE STORMWATER AND SOIL MANAGEMENT Ref: 2015-0524 Tuesday, 12 April 2016 EQUITY SITE HOLDINGS PTY TD C/- Lallees Enterprises Pty Ltd 1/108a Irrubel Road NEWPORT NSW 2106 Attention – Mr Leon Fredkin ([email protected]) RE: - 110 ADDISON ROAD, MARRICKVILLE
SITE STORMWATER MANAGEMENT FOR DEVELOPMENT APPLICATION
INTRODUCTION AND OVERVIEW
This design report addresses the Site Stormwater Drainage Management for the proposed Development
Application. LP Consulting Australia (LP Consulting) has prepared the following Drawings in support of the
drawings prepared by Architects Nicholas & Associates (AN & A): -
Site Stormwater Drainage
DA-STW-001 Title Sheet and Locality Plan
DA-STW-002 Legend, Abbreviations and Drawing List
DA-STW-003 General Notes
DA-STW-004 Erosion and Sediment Control Plan
DA-STW-005 Erosion and Sediment Control Details
DA-STW-101 Site Stormwater Drainage - Basement Plan
DA-STW-102 Site Stormwater Drainage - Ground Floor Plan
DA-STW-103 Site Stormwater Drainage - Level 1 Plan
DA-STW-104 Site Stormwater Drainage - Level 2 Plan
www.lp-consulting.com.au
DA-STW-105 Site Stormwater Drainage – Level 3 Plan
DA-STW-106 Site Stormwater Drainage – Loft Plan
DA-STW-107 Site Stormwater Drainage - Roof Plan
DA-STW-201 Site Stormwater Drainage – Basement Pump Out Pit Details
DA-STW-202 Site Stormwater Drainage – Stormwater Treatment and OSD Tank Details
DA-STW-203 Site Stormwater Drainage – Rainwater Reuse Tank Details
The design plans address the following key areas:-
1. Constraints setting the Finished Floor Level (FFL) and the site levels across the proposed
development.
2. The roof stormwater collection system is reticulated separate to the in ground surface drainage and
drains to a rainwater re-use tank.
3. All pavement areas are contained and drained through a Water Sensitive Urban Device (WSUD)
device and into an On-Site Detention (OSD) Tank.
4. Drainage from the site reticulates into the Council stormwater system located in Illawarra Road and
is limited to pre-development flows by the discharge control pit.
We refer to previous studies undertaken and the proposal methodology for the Site Stormwater Management
for the above site.
www.lp-consulting.com.au
THE EXISTING SITE
The existing site is on the corner of Illawarra Road and Addison Road, the site is bounded on the southern
and eastern boundaries by existing two (2) storey residential developments. Handley Street provides an
additional street frontage at the south eastern corner of the site.
The attached Site Plan prepared by AN & A shows that:
Addison Road falls from RL 9.96m to RL 9.71m from west to east along the road frontage;
Illawarra Road falls from RL 9.88m to RL 9.32m from north to south along the road frontage;
Handley Street falls away from the site to the east from RL 8.93 at the south eastern corner of the site
boundary;
The site falls gradually from north western corner to south eastern corner from RL 10.10m to RL 8.93m
N
www.lp-consulting.com.au
FLOOD AFFECTED LAND
Reference is made to the Marrickville Council (Council) Development Control Plan (DCP 2011) Section 2.22
– Flood Management and Flood Mapping which explains the extent of flood affected land.
Figure 1 below shows that the site is located within the flood planning area for overland flow. This requires
local overland flow to be assessed for the 1 in 100 Year storm event round the development.
Figure 1 – Flood Planning Area (Overland Flow) Map
110 Addison Road
www.lp-consulting.com.au
Figure 2 below shows that the proposed development is located within the flood liable land area. Flood
Liable Land is identified as land possibly subject to the Probable Maximum Flood Level (PMF) of the Cooks
River.
Figure 2 – Flood Liable Land Map
The Flood Planning Area requirements are more stringent than the Flood Liable Area requirements and as
such will be referenced throughout this report.
Reference should be made to the previous Flood Study submitted for this site which addresses the flooding
issues and determines appropriate Flood levels for the 100 year Average Recurrence Interval storm, which
has led to the determination of Floor levels.
110 Addison Road
www.lp-consulting.com.au
PROPOSED FINISHED FLOOR LEVELS
The proposed Finished Floor Level (FFL) is required to be set to satisfy Council’s DCP 2011 Section 2.22
Flood Management. Council requires 500mm freeboard between the overland flow levels and the FFL of the
proposed building ground floor. The ground floor is a mixture of retail, commercial and residential space.
The following initiatives are proposed for the development:-
The FFL for the proposed development will be set at RL 10.60m AHD which is 500mm above the
highest boundary level of RL 10.10m AHD at the intersection of Illawarra Road and Addison Road.
The proposed basement carpark entry ramp at the south eastern corner of the development off
Handley Street will have a threshold of RL 9.70m which is greater than 500mm above the boundary
level of RL 8.95m at Handley Street.
www.lp-consulting.com.au
SITE STORMWATER SYSTEM
Refer to the attached information including:-
Drawing DA-STW-102 for site grading and levels
Drawing DA-STW-102 for site stormwater layout
The site in-ground stormwater system has been designed to capture the 1 in 100 Year Annual Recurrence
Interval (ARI) storm event. This system collects and drains all paved areas around the proposed building. A
site grading plan has been prepared and stormwater pits and pipes located to drain the site from north to south
The in-ground site stormwater system drains through a Water Sensitive Urban Design (WSUD) treatment
device into an On-Site Detention (OSD) tank before being discharged from site into Council’s drainage system.
These elements of the site stormwater management plan are discussed in further detail later in the report.
ROOF WATER SYSTEM
Refer to attached information including:-
Drawing DA-STW-102 for site stormwater layout
Drawing DA-STW-106 and 107 for roof drainage layout
The roof of the proposed building is a flat roof with pitched metal sections falling to gutters at the loft level. The
roof water for the proposed development is collected and discharged through Rainwater Outlets in the flat
roofed areas and eaves gutters in the pitched roof areas through a series of DN100mm downpipes to ground
level and draining at the podium level to the proposed rainwater tank located under the external common area.
This system is detailed further on design plans DA-STW-102 to STW-107.
All downpipes and overflows have been designed to accommodate the 1 in 100 year ARI storm event and in
accordance with AS3500 Part 3 and the Building Code of Australia.
www.lp-consulting.com.au
BASEMENT PUMPOUT SYSTEM
Refer to attached information including:-
Drawing DA-STW-101 for Basement Pumpout Pit location
Drawing DA-STW-201 for Basement Pumpout Pit details
All exposed areas of the site that drain to the basement are drained to a central pump-out pit located in the
south western corner of the basement.
The storage volume has been calculated based on the 1 in 100 year ARI storm event for a 2 hour storm
duration with an intensity of 34.6mm/hr. The storage control volume provided between the top and bottom
water levels is 2.8m3.
ON SITE STORMWATER DETENTION (OSD)
Refer to attached information including:-
Drawing DA-STW-102 for OSD tank location
Drawing DA-STW-202 for OSD tank details
Council’s DCP 2011 Section 2.25 states that all multi-unit residential developments require OSD with the pre-
development flow for sites greater than 1000m2 to assume ‘state of nature’ when determining the pre-
development flow.
Storm events ranging from 1 in 5 Year to 1 in 100 Year ARI are to be controlled and limited to the pre-
development Peak Site Discharge (PSD) as outlined in Supplement 2 of the Stormwater and On Site Detention
Code.
www.lp-consulting.com.au
An ILSAX model has been completed using DRAINS, an urban stormwater runoff and routing software
program. The site area has been determined at 1500m2 with a 100% impervious ratio for the post development
catchment. The following design criteria have been included in determining the size of the OSD tank:-
Depth of OSD Tank 0.55m
Volume of OSD Tank 23m3
Orifice Diameter 240mm
High Early Discharge Crest Level RL 9.20m
High Early Discharge Co-efficient 1.6
OSD Overflow Level RL 9.45m
The table below presents a comparison of the pre and post development flows from the DRAINS analysis and
demonstrates that the post development flows are limited to the pre-development flows for storm events
ranging from 1 in 5 Year to 1 in 100 Year ARI:
STORM EVENT
(ARI)
PEAK SITE DISCHARGE (L/sec)
PRE-DEVELOPMENT POST DEVELOPMENT
5 45 43
10 54 44
20 66 46
50 73 49
100 82 59
The OSD Tank has been provide as a suspended reinforced concrete tank in the south western corner of the
basement with an outlet connection to the existing Council kerb entry pit located in Illawarra Road.
www.lp-consulting.com.au
RAINWATER REUSE
Refer to the attached information including:-
Drawing DA-STW-102 for rainwater tank location
Drawing DA-STW-203 for rainwater tank details
Reference is made to Council’s DCP 2011 Section 2.17 Water Sensitive Urban Design in relation to rainwater
reuse. For mixed use developments compliance with BASIX and/or installation of fittings and fixtures to meet
the following Water Efficiency Labelling and Standards (WELS) and rainwater tanks to meet as seen below
www.lp-consulting.com.au
A water balance has been undertaken using the MUSIC Numerical model, to optimise the rainwater usage
for the proposed development while also ensuring compliance with BASIX and/or WELS. Climate statistics
from the Sydney – 6 minute template have been utilised in the analysis.
Rainwater reuse has been allocated to the following:-
Irrigation of landscape gardens and trees in planters;
Car washing;
WC flushing in residential units.
The irrigation will be of the landscape gardens within the common area and the trees located within the
planters. The assumption has been made that garden areas requires irrigation at a rate of 20mm/m2/week
and trees within planters requiring 15L/day/tree. This equates to a total water usage of 400L/day.
Car washing will occur in the washing bay at the south eastern corner of the development. It has been
assumed that 4 cars per day will be washed at 40L/car. This equates to a total of 160L/day allocated to car
washing
In addition to these rainwater reuse has been allocated to WC flushing for all residential properties within the
development. At 4L/flush with a population of 60 people assuming equal numbers male and female the total
usage per day is 700L/day.
The total water usage allocated to rainwater reuse is 1.26kL/day.
The proposed development has a total roof area of 1100m2 which will drain to a 24,000L rainwater tank
located underneath the external common area alongside the OSD tank as seen on drawing DA-STW-102.
When this system is analysed with climate statistics it provides a total rainwater reuse for irrigation of 99%.
The table below presents the water balance results from MUSIC with the reuse demand highlighted.
www.lp-consulting.com.au
www.lp-consulting.com.au
ON SITE STORMWATER TREATMENT
Refer to the attached information including:-
Drawing DA-STW-102 for WSUD treatment device locations
Drawing DA-STW-202 for Stormfilter details
The requirement for On Site Stormwater treatment is discussed in Council’s DCP 2011 Part 2.17. Section
2.17.4 and outlines the percentage reductions required for urban developments:
MUSIC modelling has been conducted to demonstrate that the targets set by Council have been met by the
proposed treatment train.
The stormwater treatment train layout is shown on drawing DA-STW-102 and allows for the following:-
5 off Enviropods at collection pits draining to the OSD tank;
One off 24,000L rainwater tank collecting all roof water from the proposed development for irrigation,
car washing and WC flushing purposes;
A Stormwater 360 Stormfilter with 15 off cartridges.
www.lp-consulting.com.au
The results from the MUSIC analysis are presented below showing the total percentage reduction achieved
by the proposed treatment train described above.
The proposed stormwater quality treatment train as outlined above results in compliance against the
percentage reduction rate required to be achieved by Council.