Design of Partially Combined Sewerage System

download Design of Partially Combined Sewerage System

of 18

Transcript of Design of Partially Combined Sewerage System

  • 7/24/2019 Design of Partially Combined Sewerage System

    1/18

    1

    PROJECT DESCRIPTION

    IDEA OF FUTURE VISION PROJECT

    The Future Vision housing scheme project is for providing an economical & perfect residential area for

    the people especially of the middle class society with the basic requirements.

    The required sewerage system is to be designed to facilitate the people.

    GENERAL DESCRIPTION:The Future vision housing society is a complete residential neighborhood in all respects. The scheme

    comprises of:

    An English-medium school.

    Two hundred & Eighty one (281) houses divided into different blocks(A To M).

    Three(3) flats & Apartments each.

    a well equipped dispensary, with cooperative staff.

    Parks.

    Graveyard.

    These facilities provide ease to the residents All the basic necessities including electricity, gas,

    telephone and water are available. The scheme also has its own waste water treatment plant.. Being

    adjacent to the Jhelum road, the housing scheme is very easily accessible by road, lying at just 15

    minutes drive from Jhelum city.

    GEOGRAPHICAL LOCATION:

    The Future Vision Society is situated on the west bank of the Upper Chenab canal, 10 km along the

    Jhelum road

    HOUSING PLAN:

    The Future Vision Housing project Housing Plan is divided into: Independent Housing Plots

    Apartments(3)

    Flats (3)

    The independent plots in the society have been divided into 13 housing blocks which are

    named: A to M for distinction.

    The detail of no. of each housing units is given below

    CHAPTER 1

  • 7/24/2019 Design of Partially Combined Sewerage System

    2/18

    2

    RELATED THEORY

    SEWERAGE:It is the liquid waste or waste water produced as a result of water use.

    SEWER:Sewer is a pipe or conduit, generally closed, and flow takes place under gravity.

    SOURCES OF WASTE WATER:Sources of waste water or sewage are commonly encountered are:

    Domestic Wastewater

    It is the waste water from houses, office, other buildings, hotels and institutions.

    Industrial Wastewater

    It is the liquid waste from industrial process.

    Storm water

    It includes surface runoff generated by rainfall and the street wash.

    COMPONENTS OF WASTE WATER ENGINEERING:

    1) Collection system (network of sewer pipes)

    2) Disposal work (sewage pumping stations, outfalls)

    3) Treatment works (for rendering waste water treatment)

    TYPES OF SEWERS: Sanitary sewer

    It carries sanitary sewage i.e. waste water from municipality including domestic and industrial

    waste water.

    Storm sewer

    It carries storm sewage including surface runoff and street wash.

    Combined sewer

    It carries domestic, industrial and storm sewage.

    House sewer

    It is the sewer conveying sewage from plumbing system of a building to common or municipal

    sewer.

    Lateral sewer

    This sewer carries discharge from house sewer.

    Sub main sewer

    Chapter 2

  • 7/24/2019 Design of Partially Combined Sewerage System

    3/18

    3

    This sewer carries discharge from two or more laterals.

    Main / Trunk sewer

    It receives discharge from two or more sub mains.

    Outfall sewerIt receives discharge from all collecting system and conveys it to the point of final disposal.

    TYPES OF SEWER SYSTEMS:

    Separate system

    In this system storm water is carried separately from domestic and industrial waste water.

    Combined systemIn this system sewers carry both sanitary and storm water.

    Partially combined system

    If some portion of storm or surface runoff is allowed to be along with sanitary sewage, the system is

    known as partially combined system.

    The sewerage system of the Future Vision scheme has been designed according to partially combined

    system, being the most economical option in a developing country such as Pakistan.

    DESIGN PERIOD FOR SEWER SYSTEMS:1) Design of Sewer system

    Period of design is indefinite, as the system is designed to care for the maximum development of

    the area.

    2) Design of Sewage pumping station

    Design period is usually 10 years.

    3) Design of sewage treatment plant

    Design period is usually 15-20 years.

    STRENGHT OF RCC PIPES:Three edge bearing test is used to measure the strength of R.C.C pipes. Load is applied on the pipe to

    produce 0.25mm crack. The test defines the load that can be safely supported by the sewer.

    JOINTS IN SEWER PIPES:There are two types of joints in Concrete (up to 300 mm diameter) and R.C.C pipes (greater than 300

    mm diameter)

    Bell and Spigot joint (Employed for sewers from 225 mm to 600 mm diameter)

    Tongue and groove joint (employed for sizes greater than 600 mm diameter)

    SEWER APPURTENANCES:Appurtenances ate those devices, in addition to the pipes and conduits, that all essential for the

    operation of the sewer system. They include:

  • 7/24/2019 Design of Partially Combined Sewerage System

    4/18

    4

    1. Manhole (provided when drop is less than 0.6m)

    2. Drop manholes (provided when drop is more than 0.6m)

    3. Inlets

    An inlet is an opening into a storm or combined sewer for entrance of storm runoff. It is designed to

    permit the passage of water from the street surface into the sewer

    a)

    Curb inletb) Gutter inlet

    c) Catch basins

    4. Flush tanks

    5. Inverted siphon

    6. PUMPING STATIONS:Used to elevate and transport waste water when:

    Continuation of gravity flow is no longer feasible

    Basements are deep

    Any obstacle lies in the path of sewerReceiving stream is higher than the sewer

    Sewage is to be delivered to and above ground treatment plant

    MAIN COMPONENTS OF SEWAGE PUMPING STATION:Screens

    Dry well (for installation of pumps)

    Wet well (for receipt of waste water)

    Pumps (along with valves, force main, motor, control panel etc)

    Design of wet well and pump selection:

    In small pumping stations, where pump is sized to meet the peak the peak or maximum flow, the

    following considerations are made:

    The detention time in the wet well at average flow should preferably be not more than 30

    minutes.

    The pump must run for at least 2 minutes

    Cycle time must not be less than 10 minute.

    DESIGN CRITERIA

    Complete details are given here regarding all aspects of design of waste water disposal system for this

    project.

    The Design procedure aims primarily to determine the:

    Diameters

    Slopes of the pipes to be laid.

    CHAPTER 3

  • 7/24/2019 Design of Partially Combined Sewerage System

    5/18

    5

    THE SEWER SYSTEM:

    For the type of waste water disposal system, three(3 )options were available as shown below:

    TYPE OF SEWER SYSTEMS CHARACTERISTICS

    Separate systemAll sanitary and storm sewage carried in separate

    sewer pipes.

    Combined systemAll sanitary and storm sewage carried in same

    sewer pipe.

    Partially Combined system.

    All sanitary sewage carried with a portion of

    storm sewage or surface runoff in same sewer

    pipe.

    SELECTED SEWER SYSTEM: Partially Combined system.

    DESIGN SEWAGE FLOW CRITERIA

    In general, the design sewage flow for sewer system is calculated using the following equation:

    PEAK SANITARY SEWAGE FLOW:

    The peak sanitary sewage flow is obtained by application of a peak factor to the average sewage

    flow. Relevant equation is as follows:

    Peak sanitary sewage flow = Peak factor Average sanitary sewage flow

    There are two approaches for determination of peak sewage flow i.e. from WASA specifications or byusing the Herman formula.

    USING WASA SPECIFICATIONS:

    For the calculation of peak factor for the design purpose, the 1986 specifications provided by the WASA

    (Water and Sanitation Agency) have been referred.

    AVERAGE SEWAGE FLOW

    (m3/day)PEAK FACTOR TO OBTAIN Qmax

    2500 4.00

    25005000 3.40

    500010,000 3.10

    10,00025,000 2.70

    Design sewage flow = Peak sanitary sewage flow + Storm sewage flow + Infiltration

  • 7/24/2019 Design of Partially Combined Sewerage System

    6/18

    6

    In our case, Peak factor for average sewage flow = 4.0

    USING HERMAN FORMULA:

    An alternative method for determination of peak factor is by using the Herman formula. The formula is

    given below

    P4

    141

    Q

    QM

    AVG

    MAX

    DESIGN EQUATION:

    The Mannings formulais used for design of sewers flowing under gravity.

    2

    1

    3

    2

    S.R.n

    1v

    Where v = Velocity of flow (m/sec)

    R = Hydraulic mean depth = full)halforfullflowingispipe(when4

    D

    perimeterWetted

    Area

    S = Slope of the sewer

    n = Mannings coefficient of roughness for pipes (n = 0.013 for RCC pipes)

    MINIMUM SELF CLEANSING VELOCITY:

    It is the minimum velocity that ensures non settlement of suspended matter in the sewer.For Partially combined sewerage system = 0.7 m/sec

    Maximum velocity:Maximum velocity should not be greater than 2.4 m/sec to avoid excessive sewer abrasion and also to

    avoid steep slopes.

    MINIMUM SEWER SIZE:

    The minimum sewer size is taken as 225mm.

    MINIMUM COVER:1m is taken as the minimum cover over the sewers to avoid damage from live loads coming on the

    sewer.

    25,00050,000 2.50

    50,000100,000 2.30

    100,000250,000 2.15

    250,000500,000 2.08

    > 500,000 2.00

  • 7/24/2019 Design of Partially Combined Sewerage System

    7/18

    7

    SPACING OF MANHOLES

    sewer size spacing

    225mm to 375mm 100m450mm to 750mm 120m

    greater than 750mm 150m

    HYDRAULIC STATEMENT & DETAILED DESIGN

    This chapter deals with the detailed design of future vis ion housing society.

    This chapter includes the following:

    Design of partially combined sewer system (hydraulic statement)

    Design of sewage pumping station (only wet well)

    PREPARATION OF HYDRAULIC STATEMENT

    Hydraulic statement is : Tabular form or a sheet

    Contains information regarding diameters of pipes used, slopes to be maintained, invert levels

    etc.

    REQUIRED DATA FOR THE PREPARATION OF HYDRAULIC STATEMENT

    POPULATION:

    The calculation of population was based on the following data:

    No of Plots = 281

    No of Apartments = 3

    No of Flats (2 storey) = 3

    Persons /plot=ten(10)

    Total population = (281 x 10) + (3 x 600) + (3 x 400)

    = 5810 persons.

    PER CAPITA WATER CONSUMPTION:

    CHAPTER 4

  • 7/24/2019 Design of Partially Combined Sewerage System

    8/18

    8

    The per capita water consumption is calculated in liters per capita per day (lpcd) using the following

    relation

    PER CAPITA WATER CONSUMPTION = 350 + R

    Where, R = Registration number of the student = 142

    Hence, the per capita water consumption came out to be 492 lpcd.

    TOTAL AVERAGE DAILY WATER CONSUMPTION:

    The relation used for the determination of total average daily consumption of water is as follows:

    Total average daily water consumption = Pd Per capita water consumption

    AVERAGE DAILY SEWAGE FLOW

    80% of average daily water consumption

    DESIGN SEWAGE FLOW CRITERIA:

    In general, the design sewage flow for sewer system is calculated using the following equation:

    This design sewage flow value is calculated for each sewer line, by determining each of the

    three parameters given in the equation above. The detail of determination of these parametersfollows:

    Design sewage flow = Peak sanitary sewage flow + Storm sewage flow + Infiltration

    PEAK SANITARY SEWAGE FLOW:

    The peak sanitary sewage flow is obtained by application of a peak factor to the average sewage

    flow. Relevant equation is as follows:

    Peak sanitary sewage flow = Peak factor Average sanitary sewage flow

    Using WASA Specifications,

    Peak factor= 4 for our case.

    INFILTRATION:

    Infiltration refers to the wastewater that enters sewers through poor joints, cracked pipes, walls and

    manhole covers.

    Infiltration rate = 10 % of average sanitary sewage flow

  • 7/24/2019 Design of Partially Combined Sewerage System

    9/18

    9

    DESIGN FLOW:

    IT is given by the following expression:

    Design sewage flow = 2 Peak sanitary sewage flow + Infiltration

    ORDesign sewage flow=8.1*Q(avg.)

    LONGITUDINAL PROFILE OF LONGEST SEWER LINE

    It is always recommended to draw a longitudinal profile of sewer line because:

    Helps in executing the work of water disposal system

    Guides the contractor to execute the work easily & efficiently.

    Longitudinal profile is a section along the length showing invert levels, reduced levels, details ofmanholes, diameter of sewer pipe lines, slope of sewer pipe lines, length of sewer pipe line etc.

    SEWER INVERT LEVELS:The lowest inside level at any cross section of a sewer pipe is known as the Invert Level at that cross

    section.

    IMPORTANCE OF INVERT LEVELS:

    minimum self cleansing velocity are achieved through calculations of invert levels of sewers atvarious manholes.

    Formula for calculation of invert level:

    U/S Invert level = NGSL/Road level Depth of sewer Thickness of sewer Diameter of sewer

    D/S Invert level = U/S Invert level (Sewer slope

    Length of sewer)

  • 7/24/2019 Design of Partially Combined Sewerage System

    10/18

    10

    IMPORTANT CONSIDERATIONS IN INVERT LEVEL CALCULATION:

    When sewers of equal diameter discharge in a manhole and a pipe of same diameter receives

    the total discharge, then the lowest D/S Invert Level among the discharging sewers has been

    taken as U/S Invert Level of the receiving sewer.

    When the diameter of receiving sewer is greater than that of lowest discharging sewer thefollowing rules are observed in the laying of sewer pipes:

    a) The sewer crowns are kept at the same level.

    b) U/S IL of receiving sewer is dropped by the difference in diameter of the two sewers.

    SEWAGE PUMPING STATION:A sewage pumping station is needed to elevate or transport sewage to a higher receiving point in the

    sewerage system.

    Such a need can arise when:

    Continuation of gravity flow is no longer feasibleBuildings in vicinity have deep basements

    An obstacle is present in the path of sewer

    Receiving stream is higher than the sewer

    Sewage is to be delivered to an above ground treatment plan.

    PUMPING CAPACITY & DESIGN SEWAGE FLOW:The sewage pump is design according to the maximum design sewage flow of the total population, and

    for the current case:

    Maximum design sewage flow = 18966.528 m3/day = 13.1712 m3/min

    So, required pumping capacity = 13.1712 m3/min

    AVERAGE SEWAGE FLOW:

    The average sewage flow rate is used along with the minimum rate of sewage flow to calculate the

    corresponding cycle time for the pumping station:

    Average sewage flow = 2341.538 m3

    /day = 1.626 m3

    /min

    MINIMUM SEWAGE FLOW:

    Minimum sewage flow = 50 % of ave rage sewage flow

    Minimum sewage flow= 0.5 x 2341.538 m3/day = 1170.769 m3/day = 0.813m3/min

    CYCLE TIME:

    The cycle time for a sewage pumping station is the time elapsed between 2 successive startups of the

    motor pump.

  • 7/24/2019 Design of Partially Combined Sewerage System

    11/18

    11

    Cycle time = Time to empty the wet well + Time to fill the wet well

    FORMULAfor calculating cycle time

    QQV

    PVt

    VOLUME OF WET WELL:

    Volume of wet well corresponding to a certain cycle time is given by the following formula:

    4

    P.tV min

    The wet well should have a volume such that the cycle time is always greater than the minimum cycle

    time recommended for a motor pump.

    DESIGN CALCULATIONS DESIGN CALCULATIONS DESIGN CALCULATIONS DESIGN CALCULATIONS

    (PUMPING STATION)

    Given data:

    Maximum design sewage flow = Qmax = 9147.26 m3/day

    =6.35 m3/min

    Average sewage flow = Qavg= 2286.82 m3/day

    =1.58 m3/min

    Minimum sewage flow = Qmin= 0.5 * 1.58 m

    3

    /day=0.794 m3/min

    Recommended cycle time for pump = 10 minutes

    SOLUTION:

    Effective volume of wet well = 3min m87.154

    106..35

    4

    tP.

    CHECK FOR RUNNING TIME:

    t= min2>2.84min794.035.6

    87.15

    QP

    V

    min

    ( OK)

    DESIGN

    CALCULATIONS

  • 7/24/2019 Design of Partially Combined Sewerage System

    12/18

    12

    CHECK FOR DETENTION TIME:

    =

    Qavg=

    .

    .= . < 30 min (ok)

    So, Volume of wet well = 15.87 m3

    Assuming Depth = 2.0 m

    Surface Area = 7.935m

    Diameter = 3.18 m

    DRAWINGS

    This chapter deals with the major drawings required for the implementation of the project.

    The following drawings are included in this chapter:

    1. Longitudinal profile of sewer

    2. Manhole

    3. Sewage pumping station

    4. Sewer joints

    LONGITUDINAL PROFILE OF THE SEWER Longitudinal profile of the sewer is:

    The graphical representation of Hydraulic Statement.

    In our design of future vision housing society I have drawn the longest sewer profile.

    The functions of manholes are:

    MANHOLES

    Cleaning, inspection of sewer pipe Maintenances of sewer

    House connections

    DIAMETER SELECTED = 3.18 meters

    CHAPTER 5

  • 7/24/2019 Design of Partially Combined Sewerage System

    13/18

    13

    LOCATION OF MANHOLES

    Manholes should be located where ever there is:

    Change in sewer direction

    Change in slope Change in diameter

    A typical figure of manhole is shown in the below figure.

    DROP MANHOLES

    When lateral or sub main join in a deeper sewer, excavation is saved by keeping the upper

    sewer at a reasonable grade and making the vertical drop at the manhole.

    Drop manhole is constructed when the drop is more than 0.6m.

    A typical figure of drop manhole is shown in the figure.

  • 7/24/2019 Design of Partially Combined Sewerage System

    14/18

    14

    SEWAGE PUMPING STATION:

    A sewage pumping station is needed :

    To elevate or transport sewage to a higher receiving point in the sewerage system.

    Such a need can arise when:

    Continuation of gravity flow is no longer feasible

    Buildings in vicinity have deep basements

    An obstacle is present in the path of sewer

    Receiving stream is higher than the sewer

    Sewage is to be delivered to an above ground treatment plant

    The schematic diagram of the pumping station is given below.

    CYCLE TIME:

    The cycle time for a sewage pumping station is the time elapsed between 2 successive startups of the

    motor pump.

    Cycle time is given by the following formula:

    QQ

    V

    P

    Vt

    VOLUME OF WET WELL:

    4

    P.tV min

    SEWER JOINTS:

    There are two types of joints in Concrete (up to 300 mm diameter) and R.C.C pipes (greater than 300

    mm diameter)

    Bell and Spigot joint (Employed for sewers from 225 mm to 600 mm diameter)

    Tongue and groove joint (employed for sizes greater than 600 mm diameter)

    The figure of bell and spigot joint and tongue and groove joints is given below.

  • 7/24/2019 Design of Partially Combined Sewerage System

    15/18

    15

    BILL OF QUANTITY (BOQ) & BEDDING

    (a) FOR EXCAVATION

    Sr

    No. Sewers Diameter Excavation(meters) Quuantity Rate Amount(RS)

    Description (mm) L(m) W(m) H(m) m3 Rs/C Rupees Millions

    1 M1 - M2 225 106 0.638 1.321 89.27 123 10979.79 0.011

    2 M2M8 225 37 0.638 1.296 30.57 123 3760.04 0.004

    3 M7M8 225 106 0.638 1.321 89.27 123 10979.79 0.011

    4 M8M10 225 37 0.638 1.346 31.75 123 3905.10 0.004

    5 M9M10 225 106 0.638 1.071 72.37 123 8901.86 0.009

    6 M10M11 310 37 0.765 1.598 45.23 123 5563.46 0.006

    7 M13M12 225 89 0.638 1.288 73.08 123 8988.58 0.009

    8 M12M11 310 23 0.765 1.324 23.30 123 2865.38 0.003

    9 M11- M16 380 39 0.870 1.852 62.84 123 7729.12 0.008

    10 M3 - M16 225 110 0.638 1.304 91.44 123 11247.49 0.01111 M16- M17 460 34 0.990 1.925 64.80 123 7969.85 0.008

    12 M4- M17 225 108 0.638 1.275 87.78 123 10797.40 0.011

    13 M17- M18 460 48 0.990 1.736 82.49 123 10146.85 0.010

    CHAPTER 6

  • 7/24/2019 Design of Partially Combined Sewerage System

    16/18

    16

    14 M5- M18 225 110 0.638 1.229 86.18 123 10600.59 0.011

    15 M18M19 530 55 1.095 1.625 97.87 123 12037.47 0.012

    16 M6M19 310 112 0.765 1.495 128.09 123 15755.27 0.016

    17 M19M20 610 42 1.215 1.61 82.16 123 10105.47 0.010

    18 M20M23 610 43 1.215 1.154 60.29 123 7415.76 0.007

    19 M14M15 225 45 0.638 1.004 28.80 123 3542.68 0.00420 M15M21 225 163 0.638 0.754 78.35 123 9637.05 0.010

    21 M24M23 225 150 0.638 1.206 115.32 123 14184.82 0.014

    22 M23M21 310 46 0.765 0.988 34.77 123 4276.43 0.004

    23 M21- M22 310 15 0.765 0.671 7.70 123 947.07 0.001

    24 M22D.S 690 17 1.335 0.859 19.50 123 2397.89 0.002

    194735.19 0.195

    ,

    (B)FOR SEWER MATERIAL

    Sr. No. Description Quantity Unit Rate(RS/m) Amount(RS)

    1 225mm Sewer 1167 Meters886.1 1034078.7

    2 310mm Sewer 236 Meters1354.95 319768.2

    3 380mm Sewer 39 Meters1669.2 65098.8

    4 460mm Sewer 2 Meters

    2104.3 4208.6

    5 530mm Sewer 82 Meters 2573.65 211039.3

    6 610mm Sewer 85 Meters 2992.35 254349.75

    7 690mm Sewer 17 Meters 3575.55 60784.35

    1949327.7

    TOTAL COST OF EXCAVATION=0.195 MILLIONS

    Total cost forsewerage=1.94 Millions

  • 7/24/2019 Design of Partially Combined Sewerage System

    17/18

    17

    BEDDING PROVIDED

    Prov

    Dia

    (m)

    H(m) B(m) C H/B

    Load(kg/m

    Load

    (Lbs/ft/ft

    3 edge

    bearing

    Standardvalue(lb/ft/ft

    3 edge

    bearing

    valuefor prov

    dia.

    Load

    factor

    Bedding

    suggested

    0.2251.321

    0.64 1.66 2.07 1237.65 2722.84 1500 1107.3

    2.46 concrete

    cradle

    0.2251.296

    0.64 1.64 2.03 1219.08 2681.99 1500 1107.3

    2.42 concrete

    cradle

    0.2251.321

    0.64 1.66 2.07 1237.65 2722.84 1500 1107.3

    2.46 concrete

    cradle

    0.2251.346

    0.64 1.69 2.11 1256.06 2763.33 1500 1107.32.50 concrete

    cradle

    0.2251.071

    0.64 1.40 1.68 1044.56 2298.04 1500 1107.3

    2.08 concrete

    cradle

    0.311.598

    0.77 1.67 2.09 1793.56 3945.83 1500 1525.6

    2.59 concrete

    cradle

    0.2251.288

    0.64 1.63 2.02 1213.11 2668.84 1500 1107.3

    2.41 concrete

    cradle

    0.311.324

    0.77 1.44 1.73 1541.50 3391.29 1500 1525.6

    2.22 concrete

    cradle

    0.381.852

    0.87 1.70 2.13 2354.40 5179.68 1500 1870.1

    2.77 concrete

    cradle

    0.2251.304

    0.64 1.65 2.05 1225.04 2695.10 1500 1107.3

    2.43 concrete

    cradle

    0.461.925

    0.99 1.58 1.94 2837.49 6242.49 1500 2263.8

    2.76 concrete

    cradle

    0.2251.275

    0.64 1.62 2.00 1203.36 2647.40 1500 1107.3

    2.39 concrete

    cradle

    0.461.736

    0.99 1.45 1.75 2609.50 5740.90 1500 2263.8

    2.54 concrete

    cradle

    0.2251.229

    0.64 1.57 1.93 1168.53 2570.76 1500 1107.3

    2.32 concrete

    cradle

    0.531.625

    1.1 1.27 1.48 2778.13 6111.89 1500 2608.32.34 concrete

    cradle

    0.311.495

    0.77 1.59 1.95 1701.13 3742.48 1500 1525.6

    2.45 concrete

    cradle

    0.611.61

    1.22 1.15 1.33 3105.20 6831.43 1500 3002.0

    2.28 concrete

    cradle

    0.61 1.154 1.22 0.86 0.95 2315.54 5094.18 1500 3002.0 1.70 Brick Ballast

    0.2251.004

    0.64 1.33 1.57 989.92 2177.83 1500 1107.3

    1.97 Crushed

    Stone

    0.225 0.754 0.64 1.04 1.18 774.51 1703.92 1500 1107.3 1.54 Brick Ballast

    0.225 1.206 0.64 1.55 1.89 1150.90 2531.97 1500 1107.3 2.29 concretecradle

    0.31 0.988 0.77 1.12 1.29 1204.02 2648.84 1500 1525.6 1.74 Brick Ballast

    0.31 0.671 0.77 0.80 0.88 854.30 1879.45 1500 1525.6 1.23 Brick Ballast

    0.69 0.859 1.34 0.60 0.64 1956.82 4305.01 1500 3395.7 1.27 Brick Ballast

  • 7/24/2019 Design of Partially Combined Sewerage System

    18/18

    18

    RECOMMENDATIONS & COMMENTS

    I have Carried out the design of this waste water disposal system for the Future Vision housing

    scheme with great zeal and the design is complete & will work for the betterment of the people.

    Design report is prepared considering all possible features.

    Manhole are provided where they were required.

    Standard diameters of the pipes have been selected.

    Pipes with sufficient length have been provided.

    Prper joints have been suggested based on the diameter provided for the pipes.

    Required cost for laying the pipes has also been calculated.

    The bedding is selected on the basic of required load factor.

    Rats for the sewer pipes & excavation were picked from the finance department website.

    (http://punjab.gov.pk/aug-jan-2013)

    I have also suggested the type of bedding based on the considerations given by WASA LAhORE.

    For the effective utilization of the system cleaning and inspection be conducted after a proper

    time duration.

    I have not provided the flush tank as they were not required.

    Proper maintenances should be provided when required.

    Proper maintenances of pumps are also required at regular interval.

    In the end,I will conclude that this complete design of partially combined sewer improved my

    knowledge the design of this system done by me will work very efficiently.

    .

    CHAPTER 7

    MUHAMMAD USMAN 2009-CIVIL-142

    SECTION C

    http://punjab.gov.pk/aug-jan-2013http://punjab.gov.pk/aug-jan-2013http://punjab.gov.pk/aug-jan-2013http://punjab.gov.pk/aug-jan-2013