Design & Maintenance Guide 22

download Design & Maintenance Guide 22

of 64

Transcript of Design & Maintenance Guide 22

  • 7/24/2019 Design & Maintenance Guide 22

    1/64

  • 7/24/2019 Design & Maintenance Guide 22

    2/64

    Building energymanagement systems

    SPECIALIST SERVICES, FUELS AND MECHANICAL

    DEFENCE ESTATESMINISTRY OF DEFENCELONDON: The Stationery Office

    January 2001

    Design & Maintenance Guide 22

  • 7/24/2019 Design & Maintenance Guide 22

    3/64

    DMG 22Building Energy Management

    Crown Copyright 2001

    Published with the permission of the Ministry of Defenceon behalf of the Controller of Her Majesty's Stationery Office

    Applications for reproduction should be made to

    The Copyright Unit,Her Majesty's Stationery Office,St. Clements House,2-16 Colegate,Norwich NR3 1BQ

    ISBN 0 11 772934 5

    First Published 2001

    Printed in the United Kingdom for the Stationary Office

    TJ 3543 C1 O 05/01

    January 2001

  • 7/24/2019 Design & Maintenance Guide 22

    4/64

    DMG 22Building Energy ManagementSystems

    Foreword

    This Guide has been produced by Defence Estates (DE), Central Business Unit,

    Specialist Services, under the patronage of the Defence Utilities Working Group.

    The purpose of this Guide is to provide assistance to Project Sponsors, Property

    Managers, specifiers, designers, energy managers and operators in the

    procurement, use and maintenance of Building Energy Management Systems(BEMS). Due to the wide potential readership, a chart has been prepared

    overleaf showing topics likely to be of specific interest to particular readership

    groups.

    Whilst this Guide was commissioned by the DE for use on Ministry of Defence

    (MOD) contracts, it is acknowledged that it could be usefully applied to other

    contracts. DE commends the use of this document by other Government

    Departments. It may also be used by non-government organisations. However, no

    warranty is given as to the accuracy of the content of this Guide, or its fitness for

    any purpose.

    When this Guide is used in connection with a Defence contract then it shall be

    read in conjunction with further documents setting out particular contractualrequirements.

    This Guide has been compiled for the use of the Crown, its technical advisors

    and contractors in execution of contracts for the Crown. The Crown hereby

    excludes all liability (other than liability for death or personal injury)

    whatsoever and howsoever arising (including, but without limitation, negligence

    on the part of the Crown, its servants or agents) for any loss or damage however

    caused where the Guide is used for any other purpose.

    January 2001 iii

  • 7/24/2019 Design & Maintenance Guide 22

    5/64

    DMG 22

    Building Energy Management ForewordSystems

    The following table provides guidance to the reader on which sections of the

    Guide are most likely to be of particular relevance to each type of reader:

    Executive Summary

    1 Introduction

    2 Feasibility, design,procurement

    3 Installation, commissioningperformance testing

    4 BEMS operation

    5 BEMS maintenance

    6 Energy monitoring

    and targeting

    Analysis of requirements

    Tender summary

    Energy consumption

    benchmarks

    Glossary of Terms

    Bibliography

    Very significant

    General interest

    Background information

    January 2001

  • 7/24/2019 Design & Maintenance Guide 22

    6/64

    DMG 22Building Energy ManagementSystems

    Acknowledgements

    This Guide has been compiled by consulting engineers Ove Arup & Partners.

    The authors would like to record their gratitude to the staff at the following

    seven sites within the MOD Estate for their time and co-operation in

    researching the study:

    R N Ensleigh, Bath

    RNAS Yeovilton

    RAF Brampton

    RAC Centre Bovington, Wareham

    RSS Blandford

    RAF Coningsby

    Defence Procurement Executive, Abbey Wood, Bristol

    Gratitude is also extended to the Building Services Research and Information

    Association (BSRIA) whose published guidance has been used in the production

    of this document.

    CONTACT FOR QUERIES

    Specialist Services

    Defence Estates

    Blakemore Drive

    Sutton Coldfield

    West Midlands B75 7RLTel No: 0121 311 2294

    January 2001

  • 7/24/2019 Design & Maintenance Guide 22

    7/64

    January 2001

  • 7/24/2019 Design & Maintenance Guide 22

    8/64

    DMG 22Building Energy ManagementSystems

    Abbreviations

    Building Energy Management System

    Building Management System

    Building Services Research and Information Association

    Chartered Institution of Building Services Engineers

    Central Processing Unit

    Direct Digital Control

    Defence Estates (Formerly Defence Estates Organisation)

    Defence Estates Organisation

    Establishment Works Consultant

    Heating, Ventilation and Air Conditioning

    Heating and Ventilating Contractors Association

    Information Technology

    Monitoring and Targeting

    Original Equipment Manufacturer

    Personal Computer

    Private Finance Initiative

    Planned Preventive Maintenance

    Public Private Partnership

    Structured Cabling System

    Variable Air Volume

    January 2001 vii

    BEMS

    BMS

    BSRIA

    CIBSE

    CPU

    DDC

    DE

    DEO

    EWC

    HVAC

    HVCA

    IT

    M&T

    OEM

    PC

    PFI

    PPM

    PPP

    scs

    VAV

  • 7/24/2019 Design & Maintenance Guide 22

    9/64

    viii 2001

  • 7/24/2019 Design & Maintenance Guide 22

    10/64

    DMG 22

    Building Energy ManagementSystems

    Contents

    Section 1

    1.1

    1.2

    1.3

    1.4

    1.5

    1.6

    Section 2

    2.1

    2.2

    2.3

    2.4

    2.5

    2.6

    2.6.1

    2.6.2

    2.6.3

    2.7

    2.8

    2.9

    2.10

    2.11

    Section 3

    3.1

    3.2

    3.3

    FOREWORD

    ACKNOWLEDGEMENTS

    ABBREVIATIONS

    CONTENTS

    EXECUTIVE SUMMARY

    INTRODUCTION

    AIMS AND OBJECTIVES

    TERMINOLOGY

    WHAT IS A BEMS?

    HISTORY

    ADVANTAGES AND DISADVANTAGES

    OPTIONS AND FUTURE DEVELOPMENTS

    FEASIBILITY, DESIGN AND PROCUREMENT

    GENERALFINANCIAL APPRAISAL

    INDICATIVE COSTS

    JUSTIFICATION

    FEASIBILITY

    DESIGN AND SPECIFICATION

    Design

    Specification

    Types of Specification

    PROCUREMENT

    COMMUNICATIONS

    SOFTWARE

    STANDARDS AND REGULATIONS

    COPYRIGHT

    INSTALLATION, COMMISSIONING, PERFORMANCE TESTING

    INSTALLATION

    COMMISSIONING

    DRAWINGS AND DOCUMENTATION

    iii

    V

    vii

    ix

    xi

    1

    1

    1

    2

    4

    6

    7

    9

    99

    10

    10

    13

    13

    13

    14

    14

    15

    16

    17

    17

    18

    19

    19

    20

    22

    January 2001

  • 7/24/2019 Design & Maintenance Guide 22

    11/64

    DMG 22

    Building Energy ManagementSystems

    Contents

    Section 4

    4.1

    4.1.1

    4.1.2

    4.2

    4.3

    4.4

    4.5

    Section 5

    5.1

    5.2

    5.3

    5.3.1

    5.45.5

    Section 6

    6.1

    6.2

    6.3

    BEMS OPERATION

    OPTIONS FOR MANAGING BEMS

    Examples of the functions of staff who operate and manage BEMS

    Other Options

    OUTLINE SPECIFICATION FOR LEVELS OF BEMS OPERATOR

    TRAINING

    COSTS OF OPERATING BEMS

    UPGRADING AND REFUBISHMENT OF BEMS

    BEMS MAINTENANCE

    PREAMBLE

    MAINTENANCE COSTS

    CONTRACT ARRANGEMENTS

    Operating and Maintenance Documentation

    SPARES AND CONSUMABLESRECOMMISSIONING

    ENERGY MONITORING AND TARGETING

    REVIEW AND RELATIONSHIP WITH BEMS

    ADVANTAGES AND POTENTIAL COST SAVINGS

    COST IMPLICATIONS

    ANNEX A - TYPICAL COSTS AND SAVINGS ASSOCIATED WITH BEMS

    ANNEX B - ANALYSIS OF REQUIREMENTS

    ANNEX C - TENDER SUMMARY

    ANNEX D - ENERGY CONSUMPTION BENCHMARKINGFOR MOD BUILDINGS

    GLOSSARY OF TERMS ASSOCIATED WITH BEMS

    BIBLIOGRAPHY

    23

    23

    24

    25

    25

    27

    27

    27

    29

    29

    29

    29

    30

    3031

    33

    33

    34

    35

    37

    39

    43

    45

    47

    49

    January 2001

  • 7/24/2019 Design & Maintenance Guide 22

    12/64

    DMG 22

    Building Energy ManagementSystems

    Executive Summary

    A Building Energy Management System (BEMS) is a computer based centralised

    system that helps to manage, control and monitor particular engineering

    services within a building or group of buildings. Use of a BEMS can limit energy

    costs and labour requirements by improving plant efficiency and effectiveness. It

    can also provide a more comfortable environment for the building occupants and

    act as a focal point for alarms.

    BEMS have evolved from being a simple supervisory control tool to a totally

    integrated computerised control and monitoring system.

    Some advantages that a BEMS can provide are:

    simple operation with routine and repetitive functions programmed for

    automatic response

    flexible time scheduling of plant and heating to meet site changes such as

    holidays, training exercises and operational requirements

    remote switching of plant and adjustment of set points

    faster and better response to occupant needs

    reduced energy costs through centralised control, monitoring and energy

    management programmes

    ability to cycle/control site electrical demands

    better management through automatic alarm reporting, historical records

    and maintenance programmes

    graphical representation of plant operating conditions

    improved operation through integration of sub-systems (eg. lighting and

    access)

    improved plant performance and life expectancyreal time collection and recording of data for improved analysis of

    equipment or energy uses.

    To obtain a successful BEMS installation:

    provision needs to be made for ongoing operation and maintenance

    operators must be skilled and fully trained on the use and operation of

    BEMS

    existing plant (when being overlaid with a new BEMS) must be capable of

    performing its required functions

    the system needs to be correctly specified, installed, commissioned andoperated.

    January 2001

  • 7/24/2019 Design & Maintenance Guide 22

    13/64

    DMG 22

    Building Energy Management Executive SummarySystems

    the functions of a BEMS

    how to justify a BEMS

    information required for a feasibility assessment

    design and specification aspects

    guidance on procurement

    pointers for satisfactory installation and commissioning

    the importance of record documentation

    the need for ongoing operation and maintenance

    the key role played by trained personnel.

    xii January 2001

    This Guide sets out:

  • 7/24/2019 Design & Maintenance Guide 22

    14/64

    DMG 22Building Energy ManagementSystems

    1 Introduction

    1.2 TERMINOLOGY

    BEMS is a generic term used to describe computer-based control systems for

    engineering and building services such as air conditioning, lighting, access,

    security, monitoring etc. Other titles used for such equipment are Building

    Management System (BMS) and Energy Management System (EMS). The term

    BEMS has been identified as the normal acronym for such systems and adoptedthroughout this Guide. Other terms are synonymous with this.

    January 2001

    provide a history of BEMS

    list their advantages and disadvantages

    address how to justify the application of BEMS

    assess feasibility at a specific location

    identify requirements for installation, testing and commissioning

    explain the importance of operation and maintenance

    demonstrate their potential for energy monitoring and targeting.

    It provides background information, particularly for those who have little

    detailed knowledge of such systems.

    Further guidance is given in Specification 47 - Building Energy Management

    Systems, due to be published in 2001.

    This Guide is intended to:

    selection

    design

    installation

    testing

    commissioning

    use

    maintenance.

    1.1 AIMS AND OBJECTIVES

    The principal purpose of this Guide is to provide a single source of information

    regarding BEMS for those involved with:

  • 7/24/2019 Design & Maintenance Guide 22

    15/64

    DMG22Building Energy ManagementSystems

    Section 1Introduction

    1.3 WHAT IS A BEMS?

    A BEMS is a computer-based system that helps to manage, control and monitor

    building engineering services within a single building or a group of buildings.

    Such a system, when properly designed, installed, commissioned and operated

    will significantly improve the operational efficiency of the engineering

    installation and its cost effectiveness in terms of labour and energy costs. It can

    also help to provide a more comfortable environment for the building occupants.

    A BEMS typically has at least one principal operator position (or central

    station), connected via a communication network to remote outstations (or

    controllers), which can function independently and provide local control to the

    plant to which they are connected. They can also collect and respond to data

    from the central station or other outstations. The central station is a user

    interface at which various functions can be available depending on the client's

    requirements. It may be located remotely eg. at a headquarters building or works

    department.

    Figure 1 demonstrates the components of a BEMS.

    Figure 1Components of a BEMS

    BEMS Central Station(Personal Computer)

    Other OperatorInterface

    Remote OperatorInterface

    SITE DATA NETWORK

    Controllers Hanger Group HQAccommodationBlock

    Unitary controllersserving dedicated plant

    Roomchillerunit

    VAVterminal- box

    AHU Standbygenerator

    Heating pipework

    January 2001

  • 7/24/2019 Design & Maintenance Guide 22

    16/64

    DMG22Building Energy ManagementSystems

    Section 1Introduction

    Figure 2 illustrates how the BEMS controller functions.

    Figure 2Example of BEMS inoperation

    Temperaturesensor

    Humiditysensor

    Velocitysensor

    Sensorinputs

    Time schedules(contained withinthe controller)

    Elements of building engineering services with potential for control or

    monitoring by a BEMS are:

    heating

    ventilation

    air conditioning

    domestic hot and cold water

    lighting

    electrical supply/distribution

    electrical standby services

    energy consumption (ie. reading electricity, gas, water meters)

    January 2001 3

  • 7/24/2019 Design & Maintenance Guide 22

    17/64

    DWG 22Building Energy Management Section 1 IntroductionSystems

    There is no reason, however, why any system needing to be monitored remotely

    could not be integrated into a BEMS to provide a central focus point.

    Most current generation BEMS provide the management interface at the central

    station through a personal computer (PC). The operating system for the centralstation is likely to be Microsoft Windows, since this has become an industry

    leader. The component structure below the central station comprises a

    communication network, local controllers and field devices (eg. sensors, actuators

    and meters). Different suppliers use different communication protocols to

    transfer data, and within different generations of equipment from a single

    supplier there may be variations in communication standards. Where different

    suppliers equipment exist, or different generations of the same supplier, it may

    be possible to integrate the control components, but due to different

    communication standards and operating criteria this may not be a

    straightforward process. As this integration can be expensive, costs should be

    compared to replacement with directly compatible equipment.

    CIBSE note in their Energy Efficiency in Buildings Guide (published in 1998),

    that energy savings of between 10% and 20% can be achieved through the use of

    a BEMS, compared with independent controllers for each system, though

    opportunities for savings of this size will not always be available.

    1.4 HISTORY

    The development and processing power of computers, and in particular

    microprocessors, has enabled a steady growth since the late 1960s from separate,

    independent and dedicated control equipment to increasing degrees of

    automation, control and communication. One driving force was to reduce theamount of cabling by the use of data networks.

    Early systems were structured around a central computer called the 'head end'

    or 'front end' which contained the processing capability, linked by fixed wiring to

    each sensor or actuator device (eg. a room thermostat or a motorised valve).

    Although the processing capability was limited, only providing start/stop control

    and system monitoring, a central facility became available where all control and

    performance information could be accessed such as alarms, room temperatures

    and on-off switching times. This reduced the need for frequent site visits and

    hence offered more efficient use of maintenance operatives.

    Because the central processor carried out all the functions, the system capabilitywas limited by the available capacity. Such systems were generally very

    inflexible and not user friendly.

    January 2001

    electrical maximum demand

    security/access equipment

    fire detection/alarm systems

    vertical transportation

    specialist equipment (eg. standby facilities, smoke control and fume

    cupboards etc.)

    catering services (eg. ventilation, electricity and water usage)

  • 7/24/2019 Design & Maintenance Guide 22

    18/64

    DMG 22

    Building Energy ManagementSystems

    Section 1 Introduction

    The next development was the introduction of direct digital control (DDC) and

    the reduction of the dependence on the central computer by distributing the

    computing power round the building or estate within local microprocessors, each

    with a limited input/output capacity. This style of system became known as

    'distributed intelligence'. System design and operational requirements

    determined the need for a central computer. This was not essential because thesystem 'intelligence' was provided by the outstations. Provision of a

    communication network to link the outstations and allow data to be passed

    between them promoted the stand-alone outstations to a BEMS.

    Use of BEMS for control and monitoring of building services significantly

    increased over the decade from 1980. Interest increased also in the potential to

    link Heating, Ventilation and Air Conditioning (HVAC) equipment controls using

    BEMS for at least alarm monitoring from other stand alone systems such as

    lighting, lifts, fire and security and providing a single point for alarms to be

    registered.

    As computer processing power increased and costs reduced, the capabilities and

    applications of BEMS grew, though on occasions the installations became

    difficult to manage. Installation standards were not always followed,

    commissioning became difficult and not always effective, which resulted in

    systems that failed to achieve their original expectations.

    Building owners and operators became disenchanted with "automated systems"

    which failed to deliver the promised solution. However, they accepted that if the

    systems could be simplified, designed properly, installed correctly and fully

    commissioned, they would be a useful tool for running properties.

    As microprocessor technology developed, stand-alone controllers becameoperated alone or linked through a communication network to other controllers

    and a central point of information access. Such units, where they serve terminal

    units such as fan coil units or Variable Air Volume (VAV) boxes have become

    known as unitary controllers. Plant manufacturers or Original Equipment

    Manufacturers (OEMs), purchase unitary controllers and fit them to their own

    products. These can provide an opportunity for later integration into a BEMS

    through a communication network. Computer power has now become fully

    distributed, with the central computer becoming the 'host' for loading

    programmes, interrogating performance and recovering data. Systems have also

    become more user friendly and easier to programme.

    Figure 3Summary of changes inBEMS technology

    BEMS with outstations

    1970 1980 1990 2000

    January 2001

  • 7/24/2019 Design & Maintenance Guide 22

    19/64

    DMG 22Building Energy Management Section 1 IntroductionSystems

    1.5 ADVANTAGES AND DISADVANTAGES

    The use of a BEMS provides an integrated computer based facility for the

    control and monitoring of the building engineering services.

    Advantages are:

    routine and repetitive functions are programmed and responded to

    automatically (eg. daily on and off times, holiday scheduling, operational

    programming for different buildings, periodic testing of standby plant)

    relatively simple operation for trained users (eg. access to detailed

    information such as room temperatures to monitor plant performance;

    modifying operating times to match changes to building use)

    quick response to occupant complaints about environmental conditions

    (the sensitivity of BEMS can highlight potential problems and allow

    adjustments to be made before occupants initiate complaints)

    reduced energy consumption and hence costs by central monitoring and

    control (savings may be up to 10% by constant fine tuning to match

    occupational needs)

    ability to cycle or control site electrical demand

    improved management information such as historical records, alarm logs

    and hours run can demonstrate that environmental criteria have been

    achieved; alarms have been actioned and plant maintenance can be more

    precisely managed

    graphical representation of plant operating conditions and internal

    environment, providing quick and simple understanding of the

    information presented

    integration of system control and operation through software links

    (allowing increased opportunities for fine-tuning of controls to the

    particular application)

    improved plant performance and life expectancy (eg. by establishing key

    operating criteria and monitoring performance efficiency).

    Disadvantages that can apply include:

    any BEMS installation will have costs associated with it. These will not

    only be the initial design and installation, but also the subsequent

    operation and maintenance (see para 2.1)

    possible disruption to normal plant operation during BEMS installation

    need for a skilled operator to ensure maximum use is made of the system

    the effective potential of a BEMS can be very sensitive to proper

    specification, full consideration of condition and ability of plant to be

    controlled, commissioning by a skilled BEMS specialist and continued

    maintenance

    difficulty in integrating with existing equipment especially regardingcommunication protocol or the need for new controls or sensors to allow

    integration

    January 2001

  • 7/24/2019 Design & Maintenance Guide 22

    20/64

    DMG 22

    Building Energy Management Section 1 IntroductionSystems

    requires commitment at all levels throughout its operational life to

    maintain maximum effectiveness

    unless carefully chosen, certain aspects of BEMS can become obsolete

    relatively quickly

    unless correctly specified, installed, maintained and operated BEMS canincrease costs and environmental impacts.

    1.6 OPTIONS AND FUTURE DEVELOPMENTS

    The processing power of electronic equipment being used within a BEMS means

    that any system needing to be controlled or remotely monitored could be

    accommodated, providing the cost of the initial installation and ongoing

    operation and maintenance can be justified.

    Greater integration between different systems such as lighting, fire alarms,

    security and BEMS is likely to develop as the full capabilities become

    recognised. The links at present tend to be for monitoring and alarm reporting.As users investigate different options and the potential of the full equipment,

    greater confidence will be developed.

    Whilst communication standards do exist, different suppliers and manufacturers

    still have their own for their respective systems. As clients begin to demand

    system integration to allow data from different components and systems to be

    viewed and managed centrally, and control functions to be enhanced by sharing

    data, greater flexibility will be achieved. The components of BEMS from different

    suppliers are expected to become more compatible.

    Unitary controllers are likely to become standard items of plant and equipment.

    This may also influence the move towards communication standards, as greater

    integration between suppliers equipment will be required. Unitary controllerscan provide programmable memories for field devices such as temperature

    sensors or valve actuators, allowing them to be programmed and commissioned

    before delivery to site. On-site commissioning will, however, always be required.

    The costs of outstations and central stations will be influenced by the continuous

    developments of IT equipment, with the expectation that greater processing

    capability will be obtained for less cost. The cost element of a BEMS taken up

    with the installation of the communication network may be reduced where an IT

    network is available. Alternatively, the use of radio communications for both

    internal and external links has considerable potential to grow and develop,

    particularly between field devices and their associated outstations. Overall costs

    of BEMS are unlikely to reduce. Whilst some components such as electronicequipment may become cheaper, other hardware costs and the system design and

    engineering will continue to be the major proportion of the price and not provide

    opportunities for savings.

    As the volume of data increases, the levels of management information will rise.

    Exception reporting, to show potential problem areas with likely causes and

    possible solutions, may be developed to enable full use to be made of the

    available information.

    January 2001

  • 7/24/2019 Design & Maintenance Guide 22

    21/64

    DMG 22

    Building Energy Management Section 1 IntroductionSystems

    January 2001

  • 7/24/2019 Design & Maintenance Guide 22

    22/64

    DMG 22Building Energy ManagementSystems

    2 Feasibility, design and

    procurement

    GENERAL

    This section helps to identify the factors for choosing a BEMS and provides

    guidance in establishing the feasibility and requirements for a BEMS. The most

    common reasons for considering the use of BEMS are:

    for new builds where costs are comparable to other forms of control

    to replace existing old or failing controls where the difference in costs are

    outweighed by the benefits provided by the BEMS

    to improve the system where the benefits outweigh the costs

    where there is a need for stringent control and monitoring levels of

    building services.

    2.2 FINANCIAL APPRAISAL

    A key factor in building a business case for a BEMS will be a financial appraisal

    over the proposed life of the system. Annex A is a simple table to help provide

    initial indications of the likely costs and savings associated with BEMS. MOD

    Guidance and Policy for carrying out full financial appraisals is given in:

    JSP 414 Part 4 Chapter 16 Investment Appraisal and Post Project

    Evaluation

    DEO (Works) 1996 DEO Technical Bulletin 96/04 - Through Life Costing

    DEO (Works) 1996 DEO Technical Bulletin 96/03 - Value Engineering

    MOD Guide to Investment Appraisal and Evaluation.

    Further guidance is also given in:

    Appraisal and Evaluation in Central Government (Treasury Guidance

    1997)

    Appropriate local guidelines should also be followed.

    January 2001

  • 7/24/2019 Design & Maintenance Guide 22

    23/64

    DMG 22Building Energy Management Section 2Feasibility, design and procurementSystems

    2.3 INDICATIVE COSTS

    As general background information, three generic types of installation are

    considered with outline cost information based on Quarter One year 2000. These

    are not intended to be used for budget purposes, only to provide outline guidance

    of the order of costs for the different types of properties. The particularrequirements for a specific location may result in significant variations from

    these figures.

    Total installed

    cost of BEMS

    (new greenfield

    site)*

    Property Type One

    Very large major site with numerous buildings and facilities 300,000

    eg. Naval Dockyard; RAF Operational Site

    Total utilities cost per annum (electricity, oil, gas, water)

    1 million.

    Property Type Two

    Medium to large 75,000

    eg. Large single building or complex of buildings

    Total utilities cost per annum

    200,000.

    Property Type Three

    Small to medium single building or small complex of 30,000

    buildings

    Total utilities cost per annum

    (electricity, oil, gas, water)50,000

    * Installation in existing buildings will require an increase of

    10% to allow for additional design and installation costs.

    2.4 JUSTIFICATION

    All building services need controls. BEMS can be cheaper than individual

    controls, particularly for new buildings where they can be justified on first costs

    for almost all types of buildings. For refurbishment or replacement situations,

    first costs alone may not indicate that a BEMS is appropriate. Whole life costs

    should also be investigated when system flexibility, monitoring and centralcontrol capability can be taken into account. Upgrading costs will need to be

    compared with potential energy savings.

    CIBSE indicate energy cost savings between 10% and 20% by use of BEMS in

    their 1998 Energy Efficiency in Buildings Guide. As a rule of thumb, a retrofit

    BEMS can yield a 10% direct fuel cost saving against a reasonably well

    maintained conventional control system when properly designed, installed and

    commissioned.

    The benefits of using a BEMS are the flexibility of the controls available,

    communications capability (particularly for operational data between plant and

    system) and overall performance monitoring.

    10 January 2001

  • 7/24/2019 Design & Maintenance Guide 22

    24/64

    DMG 22Building Energy Management Section 2Feasibility, design and procurementSystems

    A BEMS can provide three key advantages over stand alone control:

    provision of management information

    remote operation, interrogation and alarm monitoring

    greater flexibility and range of control strategies.

    BEMS will not compensate for fundamentally inefficient buildings and plant.

    Benefits of a BEMS can include:

    improved environmental (eg. temperature) and time control from central

    location

    rapid communication (system monitoring, operation and control) with

    remote sites, without physical visits

    improved comfort for building occupants

    automatic fault reporting at central location (with predetermined levels of

    action)

    monitoring and targeting of energy consumption

    allows easy trial and monitoring of building response characteristics and

    related energy saving proposals such as lunch time set back of heating.

    graphical representation of plant performance and environmental

    conditions.

    Examples of specific capabilities of BEMS are:

    scheduling plant start / stop times

    fuel consumption recording / energy metering

    plant sequencing / optimisation

    filter condition monitoring

    electrical maximum demand limiting

    lift monitoring

    lighting control

    hours run recording and trend logging

    security management

    alarm handling

    'at a glance' information presentation.

    Whilst these are also available using stand-alone controls, integration into a

    BEMS provides the opportunity for achieving the greatest savings and operating

    efficiency.

    January 2001 11

  • 7/24/2019 Design & Maintenance Guide 22

    25/64

    DMG 22Building Energy Management Section 2 Feasibility, design and procurementSystems

    In addition to the technical capabilities listed above, BEMS can provide the

    opportunity for improved financial control, for example, by billing sub-tenants

    where suitable metering is provided. Close monitoring of occupancy times and

    adjusting BEMS settings can produce energy savings. Reduced maintenance

    attendance by scheduling work on an hours run basis can lead to manpower

    savings.

    Before purchasing such a system, it is important to consider what the controls

    are intended to do and how they will achieve this.

    To provide a framework for this, Annex B - Analysis of Requirements provides a

    series of questions to help analyse requirements at a specific location, including

    a pro forma to identify which plant and services are to be covered by the BEMS.

    The particular plant or system will generally determine the type of control

    required. Each control requirement should be considered separately and the

    details listed. It is important to avoid an over specified or unnecessarily complex

    control system for the particular application. Advice on what is necessary and

    appropriate, and help on completion of the check list can be obtained from the

    Establishment Works Consultant (EWC) through the Property Manager or

    through the Establishment Energy Focal Point.

    The larger the number of systems or plant items listed for the project, and the

    larger the number of control or monitoring requirements, then the greater is the

    likelihood for a BEMS to be the appropriate choice for controlling the building

    services.

    For an existing installation, a list of questions to consider is given below:

    is there an operational requirement for central monitoring or control?

    do the existing controls meet current good practice? (eg. time control,weather compensation, optimum start/stop)

    can the existing control be adequately operated and maintained?

    does energy use compare well with published guidelines? (see Annex D -

    Energy consumption benchmarks for existing MOD buildings)

    is there a need to attribute responsibility for utilities to specific users?

    (eg. billing of non-entitled users and resource accounting)

    are consumption records needed for tariff/consumption profile analysis?

    is there an opportunity to integrate control of different engineeringservices?

    has the building function changed?

    have good housekeeping measures to reduce energy consumption been

    carried out.

    are the building occupants satisfied with their environment?

    These questions are included in Annex B - Analysis of Requirements

    Once a decision in principle has been taken to consider a BEMS, the full

    potential benefits and costs of achieving them need to be examined.

    12 January 2001

  • 7/24/2019 Design & Maintenance Guide 22

    26/64

    DMG 22Building Energy Management Section 2Feasibility, design and procurementSystems

    2.5 FEASIBILITY

    BEMS are becoming the norm in many larger new buildings, as their first cost is

    similar to stand alone controllers.

    In existing buildings, assessing the feasibility of a BEMS can be more difficult.

    Where existing stand alone control equipment is available, the suitability,practicality and cost of retaining and incorporating components of it into a larger

    BEMS needs to be assessed.

    The following considerations are aimed at existing buildings, but could also be

    applied to new buildings.

    Zoning of Building Services

    Are these adequate for energy efficient operation and match current

    and proposed occupant requirements?

    Primary Plant

    Does this have stand alone control, could it be linked with a BEMS?

    Existing stand alone controls

    Are they still supported by manufacturers? Can they be

    economically integrated into a new BEMS? Control equipment

    installed in the late 80s, early 90s or earlier may have limited

    functions available and be difficult to reprogramme.

    Existing BEMS

    Is there an existing BEMS available that could be used?

    2.6 DESIGN AND SPECIFICATION

    2.6.1 Design

    A BEMS is a powerful tool that allows building owners, operators, and managers

    to understand the function and control the operation of engineering plant and

    services for which they have responsibility. It is important to note that however

    a BEMS is designed or specified it can only control within the limits and

    accuracy of the equipment to which it is connected.

    There are a wide variety of systems available that can provide control or simply

    monitor the status of plant. A purchaser needs to be clear and unambiguous

    about the plant and equipment to be served by the BEMS and the degree of

    control required.

    The extent and method of design will depend on the size and complexity of the

    installation and its controls, the technical competence of the client and any

    relationship which exists with a preferred supplier.

    Where the BEMS is being overlaid on existing plant and equipment, control

    devices such as sensors and actuators may not be compatible or suitable for

    connection to the BEMS. Allowance for this will need to be included in the costs

    of the work.

    January 2001 13

  • 7/24/2019 Design & Maintenance Guide 22

    27/64

    DMG 22

    Building Energy ManagementSystems

    Section 2Feasibility, design and procurement

    Control of different engineering systems such as HVAC, lighting, major plant

    items such as chillers, and life safety (eg. fire) has traditionally been kept

    independent. BEMS can provide opportunities for a degree of integration, but

    this is likely to be limited to alarm monitoring or sequence initiation. The extent

    of integration will be governed by the risks involved. Plant that is safety critical,

    has military operational implications or operates under its own dedicated controlsystem may not be appropriate for integration.

    2.6.2 Specification

    The objectives of a specification are to:

    14 January 2001

    provide a firm basis tor a tender

    identify required performance criteria

    minimise misunderstanding

    define responsibilities

    provide like for like comparisons between different proposals.

    The specification provides basic information together with exact functional

    requirements, where appropriate, for the specific application. Further detailed

    guidance regarding this is provided in Specification 47 - Building Energy

    Management Systems to be published in 2001.

    The initial step when preparing a specification is to define the building

    management strategy from which a specification can be developed. To achieve

    maximum benefit the strategy must take account of the function of each building

    and the existing or proposed operation and maintenance manpower availability.

    For large, complex applications it may be appropriate to appoint a professional

    advisor for this role. Advice on this can be obtained from the EWC through the

    Property Manager, or through the Establishment Energy Focal Point.

    2.6.3 Types of Specif ication

    Two generic types of specification can be identified:

    Performance

    Functional

    states how the system will operate in strategic terms, with an

    outline description of what is to be controlled and monitored.

    gives detailed requirements for the system, including control

    and monitoring strategies and the devices included, such as

    controllers, sensors and actuators.

    Both types of specification should describe the features to be provided, standards

    to be met including materials and workmanship, testing and commissioning

    requirements, training to be carried out and guarantees to be provided.

    The type of specification will be dictated by the particular application and

    intended procurement strategy. Where a specialist controls contractor is to be

    used and competence has been demonstrated and proved on similar work, a

    performance specification may suffice. The same type of specification may also be

    appropriate for buildings with relatively simple engineering services and no need

    for elaborate control. However, where a building has complex plant such as full

    air conditioning, or where environmental conditions have to be closely controlled

    within strict limits and there are considerable inter-relationships between the

    control sequences, a functional specification will be required to ensure the

    client's requirements are fully defined and able to be interpreted by the supplier

  • 7/24/2019 Design & Maintenance Guide 22

    28/64

    DMG 22Building Energy Management Section 2Feasibility, design and procurementSystems

    and installer. Care must be taken to ensure BEMS equipment is compatible with

    all systems and its operation does not allow plant to operate outside

    manufactures parameters, normal duty ranges or operational limits.

    In 1998 The Building Services Research and Information Association (BSRIA)

    published a Library of Control Strategies (Application Guide AG7/98) as a

    reference document for when the controls are being developed, specified and

    configured. The strategies can be used when specifying control systems as an

    independent source of control solutions. The provision of this Library does not

    remove the onus from designers to ensure that an appropriate working solution

    is produced.

    To create a specification for a particular installation from the strategies within

    AG7/98 the designer needs to:

    decide which 'plant functions' are required to make up the whole system

    decide for each plant function which of the available plant modulesoptions is to be used

    forstrategieswhichofferalternativesoroptions, decide whichare

    required in the specific application.

    2.7 PROCUREMENT

    A number of options are available. These include:

    January 2001 15

    direct purchase from a specialist supplier of controls equipment

    direct purchase from a systems integrator (who obtains components such

    as controls equipment from a specialist supplier and designs, installs and

    commissions the system to meet the user's requirements)

    use of a controls specialist to design the system, tender the work and

    oversee installation and commissioning

    produce in-house, an outline brief of requirements and tender the work

    for purchase

    produce in-house, an outline brief of requirements and tender for leasing

    an installed BEMS (where such a leasing agreement is deemed

    appropriate). The lease agreement may include upgrades to the BEMSover the stated period of the lease agreement.

    incorporate the BEMS installation within a Private Finance Initiative

    (PFI)/Public Private Partnership (PPP) arrangement.

    lease the BEMS through the Facilities Management Contractor.

  • 7/24/2019 Design & Maintenance Guide 22

    29/64

    DMG 22Building Energy Management Section 2 Feasibility, design and procurementSystems

    2.8 COMMUNICATIONS

    Two aspects of communications need to be considered:

    1. The information being communicated.

    Computers need precise, rigidly defined rules and protocols for successful

    communication.

    Typically, translation problems occur when trying to connect products

    made by different manufacturers, or in some cases, different versions of

    products made by the same manufacturer.

    Traditionally, different systems such as lighting, HVAC and life safety (eg.

    fire) have had separate, dedicated controls. Relevant specialists should

    be fully consulted where safety critical systems are to be connected to a

    BEMS.

    Communication standards allow transfer and interpretation of data

    between different parts of the BEMS and integration of equipment from

    different suppliers. There is no single agreed communications standard,

    at present, followed by all BEMS suppliers. Several exist and are being

    used by different suppliers.

    2. Physical communication system between all parts of the BEMS (eg. data

    cabling).

    The elements of a BEMS need to be linked together to transfer data

    through a communication network. The most common method is data

    cabling using shielded or unshielded twisted pair. Other options include

    fibre optics, which can provide increased security, radio links, which may

    be more appropriate when long distances (eg. across an operational RAFsite) are involved, mains borne signalling, where the electrical

    distribution system is suitable and modem links to public or private

    telephone networks.

    Existing communication network cabling may be available, eg. redundant

    voice systems, but will need to be checked and proved suitable before

    inclusion into the project scheme. Dedicated voice networks using

    modems, can provide a basic communication infrastructure, particularly

    on extensive sites where buildings are spread over a large area. This

    application can result in prolonged times for data transfer and problems

    with data accuracy which may have implications if used for generating

    energy bills.

    Alternatively, an existing IT cabling system may be available. Office

    accommodation in particular is increasingly likely to have a structured

    cabling system providing an infrastructure on each floor, with a grid of

    outlet connections allowing connection of IT equipment such as PC's and

    printers. BEMS may be able to use this to link major components directly

    together (eg. controllers and the central station). The cost of integrating a

    BEMS with an IT structured cabling systems (SCS) will depend on how

    much of the SCS is required.

    Where it is proposed to use an existing or proposed general use cabling

    system for a BEMS, application for this must be made in sufficient time

    to ensure its availability when required. The continuing availability ofshared access to the system also needs to be confirmed.

    16 January 2001

  • 7/24/2019 Design & Maintenance Guide 22

    30/64

    DMG 22Building Energy Management Section 2 Feasibility, design and procurementSystems

    If the SCS is installed at the same time as the BEMS (eg. on a green field

    development) it can be designed to accommodate the BEMS requirements

    and installed by the SCS installer.

    Other benefits of using the IT network are shared network maintenance

    costs, access to a robust and industry recognised communication network

    and an enhanced network security (faults detected and rectified more

    quickly than normal BEMS network).

    Use of an IT network is likely to be for the major data interconnections such as

    between controllers and the central station. Use of a local BEMS network is

    more likely to be cost effective for individual plant controllers.

    Radio communications applied to BEMS are very limited but offer potential for

    future growth. It has been successfully adopted on large MOD sites such as

    operational RAF stations with considerable distances between buildings, to

    reduce the need for cable links. The technology can be applied both internally

    between field devices and associated outstations and externally over a campus

    type environment for communications between remote buildings. Security of

    radio communication systems may not be satisfactory for particular locations.

    2.9 SOFTWARE

    The software elements of a BEMS determine how the controls and monitoring

    functions built into it will operate and communicate. This level of software may

    be termed the 'firmware' since they can be fixed components of the system whose

    operating parameters and characteristics are set up to match the specific

    requirements. The BSRIA Library of Control Strategies provides a set of

    standards. Individual suppliers may opt for particular ways to achieve each

    strategy.

    BEMS software imposed above the control strategies provides the monitoring

    and reporting structure of the system, including how and what reports, alarms

    and historical logs are generated.

    Documentation for both the firmware and software is critical because it will

    define how each controller and control parameter has been configured, how

    information is stored and reports are generated.

    Software protection in terms of licence agreements needs to be resolved at an

    early stage of the project. Copies of the software should be held in secure

    locations, ideally both on and off site.

    2.10 STANDARDS AND REGULATIONS

    BEMS installations must comply with all relevant statutory regulations. Other

    guidance in terms of standards and codes of practice should also be noted.

    Examples of these are British Standards Codes of Practice and MOD guidance.

    The following is a general list of some areas that should be addressed when

    installing a BEMS:

    January 2001 17

    a safe means of access for maintenance

    all BEMS panels are secured to prevent unauthorised access

    the central station and controllers are password protected to prevent

    unauthorised access

  • 7/24/2019 Design & Maintenance Guide 22

    31/64

    DMG 22

    Building Energy Management Section 2 Feasibility, design and procurementSystems

    sufficient illumination is provided as required for user operation of BEMS

    where they are situated in plant rooms. This may require additional task

    lighting.

    electrical installations comply with BS7671 1992 - Requirements for

    Electrical Installations (IEE Wiring Regulations 16th Edition). Commonly

    known as the Wiring Reg's

    all equipment complies with the standards relating to electromagnetic

    interference and is suitable for the particular application

    workstations comply with the Health and Safety (Display Screen

    Equipment) Regulations 1992

    specific security needs for the particular application relating to hardware,

    software, sensors and other electronic and IT equipment are followed.

    2.11 COPYRIGHT

    For a particular application, the detailed BEMS specification, software

    configuration, operating parameters and reporting structures established for thespecific application will all be covered by MOD copyright and not, therefore,

    available to others without authorised agreement.

    18 January 2001

  • 7/24/2019 Design & Maintenance Guide 22

    32/64

    DMG 22

    Building Energy ManagementSystems

    3 Installation, Commissioning,

    Performance Testing

    3.1 INSTALLATION

    This is the process of translating the requirements set out in the specification

    into a physically completed system (static completion). It requires labour,

    materials, supervision, inspection, testing and documentation.

    In a new installation the plant and equipment needing interconnection with the

    BEMS should have suitable facilities already available. For existing plant and

    equipment, where a new BEMS is being installed, there may be a need to replace

    or refurbish existing control devices such as sensors, actuators and analogue

    controls.

    Installation standards should be defined in the specification, including those for

    data cabling, programming, testing, documentation and cable identification.

    The installation of a BEMS can be critical to its effective and efficient

    performance. It is advised that installation should only be carried out, or closely

    managed, by specialist BEMS installers, or organisations who can demonstrate

    their particular expertise in this field.

    Safety and operational interlocks are likely to be included within the specific

    control strategies. These need to be identified in schedule format and proved to

    be working in a safe and correct manner. The BEMS would normally only

    monitor the action of such interlocks, particularly for critical operations.

    Tests to confirm an installation has been completed and approved to the

    satisfaction of the Project Manager should include:

    an audit of the cabling and hardware

    demonstration of the physical and logical integrity of the system

    demonstration of all the control actions

    demonstration of all the sensor calibrations

    demonstration of the system software

    demonstration of the system graphics

    all documentation including drawings and operating and maintenance

    manuals have been provided.

    January 2001 19

  • 7/24/2019 Design & Maintenance Guide 22

    33/64

    DMG 22 Section 3 Installation, Commissio ning, Performa nce TestingBuilding Energy ManagementSystems

    3.2 COMMISSIONING

    Commissioning is the process of turning a physically completed system into a

    fully operational working system that meets the designed requirements. Poor

    commissioning is the most common cause of BEMS failing to meet the initial

    performance expectations. This in turn can lead to unstable and underperforming plant. Suppliers can benefit from good commissioning since

    subsequent warranty costs are likely to be less than for a poorly commissioned

    installation.

    A comprehensive specification supplemented with flow diagrams can form the

    basis of the commissioning checklist and serve as a yardstick to test the BEMS

    control strategies. It is beneficial to specify as much off-site testing as possible

    (eg. control panels, application software and graphics) when conditions are more

    suitable for testing and remedial work.

    Once installed, the BEMS should be fully pre-commissioned as far as

    possible,(eg. data cabling interconnections, validity of sensor readings, actuator

    performance). All controls are likely to be needed in 'manual' operation duringfull commissioning of the engineering services. The BEMS can then be

    integrated with the building services and finally commissioned and put into

    operation. Adequate time needs to be allowed for this, as a guide 30 minutes for

    each BEMS sensing point should be anticipated. Attendance will also be required

    by other trades and this should be reflected in the tender figures as part of the

    commissioning costs.

    On sites where the BEMS is commissioned and handed over in stages, the

    sensors in the earliest stages may have drifted from the calibration setting by

    the time that later stages are commissioned.

    Where the BEMS is being installed in an operational building, careful planningis needed to maintain all services so that they continue to function during the

    commissioning process.

    Whilst the initial commissioning will be carried out to the original design data, it

    is likely that fine tuning of the system will be required over the first full year of

    building occupation to fully meet the requirements of the building operator and

    the occupants. It may be appropriate to include this in the original contract cost,

    particularly for more complex installations. This will lead to greater savings as

    the BEMS operation and performance parameters can be optimised. Liaison

    between the building user/operator and the installation contractor during the

    period of fine tuning is important to ensure a full understanding of how the

    building is required to function.

    BSRIA Application Handbook AH 2/92, Commissioning of BEMS, provides a code

    of practice including detailed check lists. Other relevant publications are:

    20 January 2001

    Commissioning HVAC Systems - Divisions of Responsibilities.

    The Commissioning of Air Systems in Buildings

    The Commissioning of Water Systems in Buildings

    A Procedure for Commissioning VAV Systems

    Commissioning of VAV systems in buildings

    Commissioning Code C Automatic Control

    TM1/88

    AG3/89.1

    AG2/89.1

    TM2/88

    AG1/91

    BSRIA

    CIBSE

  • 7/24/2019 Design & Maintenance Guide 22

    34/64

    DMG 22

    Building Energy ManagementSystems

    Performance testing addresses the operation of the BEMS and the associated

    plant. It is aimed at ensuring both are operating in an optimum manner in

    terms of energy and internal environmental performance.

    The BEMS operator should be trained to monitor the BEMS performance and to

    note and respond to feedback from the building occupants.

    Many BEMS receive little or no maintenance. Possibly this is because a BEMS is

    perceived as microprocessor based and not requiring attention. A BEMS is more

    than the central station or controllers. Sensors can go out of calibration,

    actuators can fail to operate. Building use will change over time, needing set

    points to be revised. Performance testing will detect changes to the BEMS level

    of performance and faults due to incomplete commissioning.

    Reasons for performance testing include:

    January 2001 21

    occupant complaints about the environment

    energy performance is unsatisfactory

    system neglect

    little information may be available about the installed control regimes

    BEMS performance is inadequate/not satisfactory

    unsatisfactory environmental performance

    significant change to energy consumption

    to evaluate BEMS performance

    repeated failures or alarms need to be investigated.

    fits ofperformancetestingare:

    improved occupant comfort

    prevents complaints arising from occupants

    energy savings

    reduced false alarms

    improved awareness of BEMS and control strategies

    confidence in BEMS records.

    BSRIA Application Guide AG2/94 - BEMS, Performance Testing, provides

    guidance on a general performance audit and help in resolving particular BEMS

    problems.

    Guidance on energy consumption benchmarks for MOD buildings can be found

    in the DETR Energy Conservation Guide 75 - Energy Use in Ministry of Defence

    Establishments. A copy of the summary page giving the benchmark figures from

    this document is given in Annex D.

    Section 3 Installation, Commissioning, Performance Testing

  • 7/24/2019 Design & Maintenance Guide 22

    35/64

    Section 3 Installation, Commissioning, Performance Testing

    3.3 DRAWINGS AND DOCUMENTATION

    Comprehensive and accurate record drawings and documentation are essential

    for the satisfactory operation and maintenance of a BEMS. These should include:

    BEMS Performance Specification

    written description of plant and how it is controlled

    control strategy, including diagrams

    operating and maintenance manual

    maintenance schedules

    central station software manual

    points list (all analogue and digital inputs and outputs)

    flow diagram

    specifications for sensors and actuators

    schematic wiring diagrams for outstations, field devices and control panels

    controls design specification

    details of set points, alarm levels, time schedules, overload settings

    commissioning data

    plant diagrams showing locations of field devices

    software back-up copies

    emergency procedures

    handover/acceptance documentation

    log book - to record incidents, operational information and all changes

    made to the system (para 5.3.1 gives more information about this).

    22 January 2001

    Building Energy ManagementSystems

    DMG 22

  • 7/24/2019 Design & Maintenance Guide 22

    36/64

    DMG 22Building Energy ManagementSystems

    4 BEMS Operation

    4.1 OPTIONS FOR MANAGING BEMS

    To achieve the full benefit of a BEMS installation it will need to be monitored,

    used and properly maintained rather than simply installed and ignored. The

    man/machine interface of a BEMS provides ready access to plant operating data,

    allows better understanding of the performance of the systems being controlled

    and helps improve decision making. As such, this interface is a key element of

    any BEMS.

    Due to the complexities of modern BEMS systems a common problem is

    identifying just who is responsible for what and in what context. To help

    eliminate this it is recommended that this is agreed and documented at the

    design stage, include operation, access, maintenance and communication

    responsibilities.

    It is essential that all personnel authorised to access or use a BEMS are

    adequately trained to ensure safe and efficient operation of the system. Where

    personnel have the ability to control or effect equipment or plant controlled bythe BEMS, they must be competent to do so. Risk Assessments and Safety

    Method Statements should be produced and used to ensure safe and correct

    operation and use of the BEMS. Individuals with the appropriate authority

    should be able to demonstrate their understanding of the areas within the

    BEMS to which they have access, and any implications their actions may have

    relating to the Health and Safety of both themselves and others.

    Authorisation for access to the BEMS or plant rooms in which they may be sited,

    especially where plant/equipment settings and controls are involved, should be

    approved through the Property Manager and managed throughout by the

    Authorised Person. In turn the Property Manager should confirm with the

    Establishment Works Consultant (EWC) and Works Services Manager (WSM), or

    relevant service provider, that the individual requesting use/control of the BEMS

    is deemed competent for their specific requirements. The EWC and WSM should

    also be able to confirm if there are any other implications regarding existing

    maintenance and operation contracts.

    It would be beneficial for the main operators of BEMS to be longer term

    personnel who have a good understanding of the site and any necessary

    conditions or concerns. Where this is not appropriate/possible operators can help

    by keeping records to pass on. Each new operator should receive full training for

    the system.

    Having regard to the above, Site Energy Managers would typically be included

    in those with access to BEMS at the highest level. This will help ensure

    January 2001 23

  • 7/24/2019 Design & Maintenance Guide 22

    37/64

    DMG22

    Building Energy ManagementSystems

    maximum benefit from the BEMS in terms of energy management, efficiency

    and savings. Potential overlap between Site Energy Managers and the WSM

    must be discussed and agreed at the earliest stage in the BEMS design. This

    may, for example, lead to siting of BEMS controllers out of plant rooms to

    facilitate safe access by the Site Energy Manager.

    4.1.1 Examples of the functions of staff who operate and manage BEMS

    The hours noted overleaf are illustrative only and will depend on the particular

    site and application. Hours do not include for energy Monitoring and Targeting

    (M&T), or interpretation of consumption information. A BEMS is a tool to aid

    the staff listed overleaf. As such, the installation and use of a BEMS, within the

    roles described, should represent savings in human resources, not demands on

    them. This is based on the principle that the BEMS should allow existing tasks

    to be done in less time. In addition, the improved quality and quantity of

    information and rapid and flexible control of plant will allow much greater

    effectiveness of these tasks.Site Energy Manager

    The typical emphasis of this role regarding BEMS is on improved energy

    efficiency and management. Typical BEMS use for this role is seven

    hours per week. The role may typically include an understanding of how

    the engineering plant functions and be aware of the complexities,

    capabilities and design philosophy of the BEMS. The post holder 's

    functions could include regular checking of plant performance and

    environmental conditions, adjustment of environmental conditions to

    meet changes in weather, occupancy or usage and bringing any other

    areas of concern to the attention of the Property Manager. The level of

    potential achieved from the BEMS in this role will strongly depend on thelevel of training, understanding, experience and delegated authority to

    take necessary action.

    Site Maintenance Staff/Consultants (Other Service Providers)

    The typical emphasis of this role regarding BEMS is on maintenance and

    operation of the site infrastructure, without necessarily having any

    specific direction on energy management. Typical BEMS use for this role

    is three hours per week. The principle use of the BEMS in this role is to

    confirm plant is operating correctly, identify and respond to plant failure

    alarms and use information for proactive maintenance management. In

    many cases, it will also include operation of plant and equipment. This

    role requires detailed understanding of how the engineering plantfunctions and all aspects of the BEMS.

    Energy Warden (or Building Custodian)

    This is often a supporting role to the Site Energy Manager or Property

    Manager, normally associated with a single building or small group of

    buildings. Typical BEMS use for this role is up to two hours per week.

    The role requires ready access to information from the BEMS such as

    time / environmental settings and actual conditions for the relevant

    area(s). Any anomalies can then be manually verified or investigated as

    required and recommendations made or action taken using local

    knowledge. A basic understanding of the relevant functions and

    capabilities of the BEMS would be beneficial. This role does not normallyhave authority for any control function but may have access for limited

    adjustment to environmental set points.

    24 January 2001

    Section 4 BEMS Operation

  • 7/24/2019 Design & Maintenance Guide 22

    38/64

    DMG 22

    Building Energy ManagementSystems

    Property Manager/EWC (Management)

    This role primarily requires access to information from the BEMS to aid

    in the management role or provide clear and rapid understanding of

    relevant systems through the schematics. Use is dependent on

    requirement. Typical BEMS use would be up to one hour a week. Only a

    basic understanding of the plant or BEMS function or capability is

    required. This role would not normally access the control functions. Full

    understanding of plant or BEMS functions or access to the control

    functions would be achieved through the Site Energy Manager, WSM or

    EWC, as required.

    4.1.2 Other Options

    A Bureau Service could be used to provide 24 hour monitoring of BEMS alarms

    remote from the site. There may be scope for this function to be provided by the

    site security organisation when the main tenance contractor is not in attendance.

    Instructions on how to respond to each alarm type or priority level would need tobe established along with contact details for unexpected situations. Maintenance

    contractors and other commercial organisations often provide such a facility, at a

    cost, if required.

    A more effective use of a Bureau Service would be to audit the BEMS

    performance, rather than only provide a reactive alarm monitoring function.

    This would require the Bureau Service to have skilled and experienced staff who

    could interrogate the BEMS, interpret the results and monitor that appropriate

    action had been taken. As such, this role would not be suitable for site security

    staff.

    Use of a Bureau Service would need to be considered in relation to the existing

    contractual arrangements to determine whether scope is available for this.

    Another option would be to use the enthusiasm and expertise of existing Site

    Energy Managers by extending their role and responsibility across a number of

    sites. Dependent on site sizes, one Site Energy Manager could potentially have

    responsibility for several sites if linked through a suitable communication

    network. The BEMS at each location would provide local control and reporting.

    The Site Energy Manager would interpret the data and, from intimate

    knowledge of the sites, be able to initiate the appropriate action. This role

    would be further enhanced by access to a comprehensive energy M&T system.

    4.2 OUTLINE SPECIFICATION FOR LEVELS OF BEMS OPERATOR

    To provide a better understanding of the different potential operating roles of

    BEMS, the following four categories show typical aspects of various levels and

    typical posts in which they would be suited. Important Note: Any adjustments,

    control function or accessibility to BEMS plant should be approved in writing by

    the Property Manager. This should detail the specific tasks and level of

    controlability to be authorised including the name(s) of the individual(s) being

    given the authority. These levels are generic and actual allocation of roles and

    responsibilities would benefit from input by experienced personnel.

    Level One- typically fits within the role of Energy Warden and may include/

    require:

    basic understanding of BEMS purpose and method of beneficial operation

    January 2001 25

    Section 4BEMS Operation

  • 7/24/2019 Design & Maintenance Guide 22

    39/64

    DMG 22Building Energy ManagementSystems

    no or very limited permission to make alterations to set points

    ability to call-up and view data from schematics and points list

    ability and access to view and interpret trend logs for relevant areas

    access to pertinent limited areas of the site only.

    Level Two - typically fits within the role of the Property Manager or other

    Managers and may include/require:

    as Level One above but also requires access to information and data for

    the whole site. Not normally permitted to make alterations to set points.

    Level Three- typically fits within the role of the WSM, EWC or other similar

    service provider organisations and may include/require:

    a detailed understanding and knowledge of all aspects of the BEMS required

    a detailed understanding and knowledge of all plant integrated with the

    BEMS. Able to call up and view point data from schematics and pointslist for whole site

    full access to all control functions, liaison with Site Energy Manager,

    advised if environmental set points or time setting to be altered

    ability and access to acknowledge system alarms

    ability and access to add analogue and digital inputs and outputs to the

    system

    ability and access to change control strategies

    ability and access to view trend logs.

    Level Four- typically fits within the role of the Site Energy Manager and may

    include/require:

    a full understanding of the BEMS architecture, design philosophy and

    capabilities

    a full understanding of the functions of the engineering systems

    controlled by the BEMS

    access and ability to call up and view point data from schematics and

    points lists for the whole site

    access and ability to view all system data and set up trend logs or

    exception alarms

    visibility of all system alarms for relay on to relevant maintenance

    personnel

    access and ability to make changes to time and occupancy controls and

    set points and alarms

    ability and access to add or change graphics

    ability to change control strategies and add analogue and digital inputs

    and outputs to the system.

    These four levels are only indicative and the particular site and its requirements

    will dictate those appropriate. In some instances, levels may be combined, inothers, sub-levels within those shown may be created.

    26 January 2001

    Section 4 BEMS Operation

  • 7/24/2019 Design & Maintenance Guide 22

    40/64

    DMG 22Building Energy ManagementSystems

    4.3 TRAINING

    To obtain the full benefit of a BEMS it is essential that people who are

    authorised to use, operate and maintain it, are trained to allow them to have a

    good understanding of its capabilities, purpose and potential. Such training

    needs to be an ongoing process.

    Operators need to understand the prime function of the BEMS, which may have

    changed since the original design specification was produced. They also need to

    be trained in the operating method of the system. Problems that may arise when

    established procedures are not followed should be part of the training

    programme. The procedure for making changes, alterations or additions to the

    BEMS should already be defined, but will need to be explained, together with

    how to record system malfunctions or concerns about incorrect performance to

    enable them to be resolved by the maintainer.

    BEMS operators will need to be trained to understand the displays, how to

    monitor and change time schedules, set points and environmental control

    settings, acknowledge and cancel alarms and take action following alarmmessages. They should also be able to carry out routine maintenance of the

    system central station hardware (eg. replace printer cartridge).

    Maintenance staff require training in any specialist procedures related to the

    specific installation. They also need to understand the generic requirements set

    out in the HVCA maintenance schedules for BEMS. (See Section 5.3).

    4.4 COSTS OF OPERATING BEMS

    These can be divided into two elements. The first is maintenance of the installed

    equipment. An indicative annual cost for this is some 7% of the original installed

    cost for the complete controls installation. However, the controls components(sensors, actuators, controllers etc.) will need to be maintained in any event. The

    cost of maintenance of the BEMS components (ie. control operator station and

    communications network) should be identified separately. In the absence of

    other information, a value of 0.5% of the total installed cost could be considered.

    This value is included within the 7% stated above (see 5.2 Maintenance Costs).

    The second element is the operator cost for the system. This will depend on the

    role of the person acting in this capacity, and whether energy M&T is included.

    For BEMS operation, an indicative figure of 10% - 20% full time attendance

    would need to be available for this role. Should energy M&T also be included,

    the time proportion increases to 30% - 40%.

    4.5 UPGRADING AND REFURBISHMENT OF BEMS

    The cost of upgrading or refurbishment of BEMS will need to be demonstrated to

    be cost effective. Anticipated energy savings are likely to be the principle

    jus tification, though other potential advantages, listed in para 1.5, may also be

    appropriate. A life cycle cost analysis showing anticipated operating,

    maintenance and repair costs of the existing equipment, compared with the cost

    of upgrade or refurbishment, over say 15 years, can help to make the case.

    At the design stage, adequate spare capacity should be provided in the system

    for known or anticipated system expansion. This extra capacity needs to be

    available at the central station, outstations and the communications network.

    January 2001 27

    Section 4BEMS Operation

  • 7/24/2019 Design & Maintenance Guide 22

    41/64

    DMG 22Building Energy ManagementSystems

    Specific site requirements and known proposals should be used as the basis for

    expansion planning. However, in the absence of detailed information an

    allowance of 20% should be made in each of the component elements with

    potential for expansion such as the central station, outstations and

    communication network.

    If the BEMS is a modular system, it may be reasonable to provide minimal

    expansion capability during the initial installation and provide additional

    modules when required.

    When upgrading an existing system, the initial consideration is likely to be to

    use the same equipment supplier. This should avoid problems with the

    communication standards protocols and interfaces between different suppliers'

    equipment. The age, reliability and performance of an existing system may

    influence the decision to continue with the same supplier.

    When an existing BEMS has insufficient capacity to upgrade to meet current

    requirements, it may be practical to retain field devices and the communication

    network to limit the project cost. It is possible that the existing equipment from

    a particular supplier may not be compatible with their current product range.

    BEMS equipment suppliers claim to be able to interface with the majority of

    competitors equipment. Careful programming of the project will be required to

    ensure all systems are operational during the upgrading.

    CIBSE have published the following economic life factors for BEMS components,

    which may be useful when considering upgrading or refurbishment. The specific

    applications and quality of maintenance will dictate the remaining life of

    existing components.

    Equipment Item Typical Life

    Factors (Years)

    BEMS operating system 5-10

    AutoDial modem 5-10

    Communication network (hardwiring) 25-30

    Network communications services 10-15

    Damper actuators 10-15

    Outstations 5-15

    Sensors 3-10

    Control valves 15-20

    Control dampers 15-20

    Utility sub-metering 10-20

    Electronic controls 12-18

    Hydraulic valve actuators 10-15

    Pneumatic valve actuators 15-20

    28 January 2001

    Section 4BEMS Operation

  • 7/24/2019 Design & Maintenance Guide 22

    42/64

    DMG 22

    Building Energy ManagementSystems

    5 BEMS Maintenance

    5.1 PREAMBLE

    With the increasing complexity of BEMS it is essential that their integrity

    (including software and applications) is checked and the requirements reviewed

    at regular intervals. Ignorance of a system's capabilities, coupled with poor

    commissioning and lack of client commitment can result in a BEMS becoming an

    expensive time clock.

    If the equipment is not correctly and fully commissioned and maintained by

    specialist, trained personnel and supported by the manufacturers, the benefits of

    the investment will be lost, energy wasted and operational costs will rise.

    Where a BEMS is installed, the client should be aware of the need for

    continuous monitoring of performance. Switching off because of a malfunction or

    lack of data update can negate the considerable investment and give rise to

    unacceptable environmental conditions and energy wastage.

    Building operators with a BEMS should ensure that the operators have had

    appropriate training to understand the equipment and carry out routine daily

    and weekly maintenance tasks, such as monitoring and changing time

    schedules, set points, environmental control settings and simple computer

    hardware maintenance (eg. changing printer cartridges). Such training needs to

    be an ongoing process.

    5.2 MAINTENANCE COSTS

    It is essential to make provision for the ongoing maintenance of a BEMS once it

    is installed. As a budget indicator, an annual cost of 7% of the installed cost (ie.

    the hardware, software, outstations, sensors and actuators, and communication

    interfaces) should be allowed for the complete controls installation. This figurehas been obtained from suppliers, BEMS specialist maintenance contractors and

    MOD users. This would cover, depending on the size of the installation,

    maintenance of the central operator station, data communications, controllers

    and software functions, calibration of sensors, and operational checks of

    actuators. Spare parts and replacements would be additional costs. As noted in

    para 4.4, Costs of Operating BEMS, the maintenance of the BEMS components

    is a small proportion of the 7% figure.

    5.3 CONTRACT ARRANGEMENTS

    The HVCA have produced a series of standard maintenance specifications for

    mechanical services in buildings. Volume III covers Control, Energy and

    January 2001 29

  • 7/24/2019 Design & Maintenance Guide 22

    43/64

    DMG 22Building Energy Management Section 5 BEMS MaintenanceSystems

    Building Energy Management Systems. The HVCA Standard can be used as a

    means of checking that work has been carried out and conforms to the

    requirements. It is essential that the specialist engineer appointed for BEMS

    maintenance is familiar with the equipment and the manufacturer's

    maintenance manual.

    Maintenance schedule or contract needs to be in place from the date the BEMS

    is handed over to the client. One option for the initial twelve month period is to

    include the cost in the supply contract. If this is done, the cost details need to be

    separately identified in the tender document.

    Contract options are:

    direct contract to specialist or equipment supplier

    arrange call-out facility only with specialist or supplier

    place BEMS maintenance through main M&E maintenance contractor.

    Details of the arrangement also need to be addressed, such as minimum call-out

    response time, whether a fully comprehensive contract is required (ie. costs

    include all spares, consumables, and replacement following breakdown).

    Maintenance contractors undertaking BEMS maintenance should have

    specialists with:

    necessary training

    knowledge of the installed system

    up-to-date awareness of manufacturers equipment

    access to up-to-date diagnostic equipment

    good technical support

    access to good stocks of spares.

    5.3.1 Operat ing and Maintenance Documentat ion

    It is essential that a detailed manual be kept on site. This site manual records

    the responsibilities of all parties involved with the BEMS, together with the

    installed equipment, normal settings, control diagrams and location of theOperating and Maintenance manual relating to the specific plant and control

    equipment. This site manual can also serve as a service log to record faults and

    observed by the BEMS operator, changes to control parameters, set

    points, program algorithms plus reasons why the change was necessary. It can

    also be used to check when each entry is resolved.

    5.4 SPARES AND CONSUMABLES

    Investigation of typical BEMS installations at various MOD locations indicated

    that spares and consumables may not need to be stored on site, as they are often

    readily available from manufacturers and could be charged for on an 'as

    required' basis.

    30 January 2001

  • 7/24/2019 Design & Maintenance Guide 22

    44/64

    DMG 22Building Energy Management Section 5 BEMS MaintenanceSystems

    Therefore, it is not recommended that BEMS spares be held on site unless

    particular requirements such as equipment serving a strategically essential

    system justify this.

    Items which are known to be regularly replaced such as sensors, valves and

    actuators, which are common throughout the site, would justify being held at

    minimum levels to allow replacement to be carried out.

    5.5 RECOMMISSIONING

    Over time, BEMS settings, performance and operating parameters will change

    as items become worn, electrical items drift and other circumstances change.

    Regular recommissioning of the BEMS can help ensure it is operating at its full

    potential, maximum energy savings are being achieved and plant performance

    and expected life is maximised. The frequency and areas of the BEMS for

    recommissioning should be based on regular monitoring of the BEMS

    performance and any major changes in the use or layout of the areas being

    managed by it.

    An indicative cost for recommissioning should be based on around 30 minutes

    per point to be covered.

    January 2001 31

  • 7/24/2019 Design & Maintenance Guide 22

    45/64

    32 January 2001

  • 7/24/2019 Design & Maintenance Guide 22

    46/64

    DMG22Building Energy ManagementSystems

    Figure 4

    Energy monitoring andtargeting

    6 Energy monitoring and targeting

    6.1 REVIEW AND RELATIONSHIP WITH BEMS

    A target can be defined as a measurable objective to be achieved in a given time.

    In terms of energy management, it may be a forecast over a twelve month period

    of the expected utility consumption eg. electricity, gas, oil, water. For heating,cooling and lighting loads, there will be fluctuations over the twelve month

    period due to variations in external weather conditions and the available hours

    of daylight. This is in addition to the specific building requirements such as

    changes in the hours of occupancy.

    Figure 4 shows an exampletargetconsumption for an officetype building, with a

    tolerance margin around the target line of 10% to show acceptable performance

    criteria.

    7000

    6000

    5000

    4000

    3000

    2000

    1000

    0

    By plotting the actual consumption on the target graph on say, a monthly basis,

    a good indication of performance against target can be obtained, as shown by the

    white line. As weather conditions are never the same year to year, or even month

    to month, the results may need to be normalised by the use of degree-day

    information. This provides detailed meteorological information of the days when

    heating (or cooling) would have been required, which allows target information

    to be modified to actual local weather conditions.

    January 2001 33

    Target ConsumptionTarget 10%

    Actual Consumption

  • 7/24/20