DESIGN DEVELOPMENT NOT FOR CONSTRUCTION
Transcript of DESIGN DEVELOPMENT NOT FOR CONSTRUCTION
eckersleyGarden Architecture
Eckersley Garden Architecture Pty LtdPO Box 5004 Burnley 3121 Victoria Australia T +61 3 9421 5537 F +61 3 9421 [email protected] www.e-ga.com.au
All measurements must be verifi ed on site before commencing any construction.All works requiring engineering specifi cations must be independently designed by consultant engineers. Levels and step numbers to be verifi ed on site. Details and listings to follow on A4 format.
Additional Information
This drawing is copyright and remains the property of Eckersley Garden Architecture.
Date 23.JAN.13
Scale 1:300 (A1)
Rev D
Drawn KE
Project Hotel & Conference CentreMurchison StreetMarysville
Client METIER 3
Drawing Title LANDSCAPE PLAN
Drawing No. MET-0113-05-03
DESIGN DEVELOPMENT
414000Surface Level
413000Surface Level
416000Surface Level
NPW (x1430)
NDO (x57)TAS (x40)
UP
ACO (x67)
NPW (x1704)
NPW (x1275)NPW (x49)
NPW (x2432)
CPP (x20)JUS (x20)CPP (x13)
JUS (x13)CPP (x13)JUS (x13)
CPP (x13)JUS (x13)
CPP (x5)JUS (x5)
PNA (x209)TAS (x41)
CPP (x20)JUS (x20) CPP (x13)
JUS (x13)CPP (x7)JUS (x7)
CPP (x6)JUS (x6)
MSG (x339)
NDO (x328)TAS (x101)
PNA (x134)TAS (x26)
CPP (x169)JUS (x169)
NDO (x222)TAS (x68)
NDO (x1955)
MSG (x206)
MSG (x415)
MSG (x358)
MSG (x412)
MSG (x261)TAS (x51)
NDO (x68) NDO (x43)
NDO (x76)
NDO (x76)
NDO (x315)TAS (x219)
LMR (x630)
PNA (x435)
MSG (x1452)
CPP (x224)JUS (x224)
EIV (x70)
EIV (x226)
EIV (x86)
ACO (x99)
ACO (x36)
ACO (x24)
ACO (x45)
ACO (x54)
CPP (x20)JUS (x20)CPP (x13)
JUS (x13)CPP (x13)JUS (x13)
CPP (x13)JUS (x13)
CPP (x5)JUS (x5)
CPP (x17)JUS (x17) CPP (x13)
JUS (x13)CPP (x7)JUS (x7)
CPP (x6)JUS (x6)
CPP (x20)JUS (x20)
CPP (x13)JUS (x13)
CPP (x13)JUS (x13)
CPP (x13)JUS (x13)
CPP (x5)JUS (x5)
CPP (x16)JUS (x16) CPP (x13)
JUS (x13)CPP (x7)JUS (x7)
CPP (x6)JUS (x6)
PNA (x3)PNA (x3) PNA (x3)
NDO (x185)TAS (x94)
414.95
QPA (x1)
BPD (x3)
BPD (x3)
BPD (x2)
BPD (x4)
BPD (x3)
BPD (x1)
BPD (x3)
BPD (x5)
BPD (x5) BPD (x3)
QPA (x5)
BPD (x8)
UPA (x5)
UPA (x5)
UPA (x5)
UPA (x5)
BPD (x3)
UPA (x10)
UPA (x1)
EIV (x198)
EIV (x86)
EIV (x141)
CES (x41)
PQU (x10)
420900Surface Level
RAINGARDEN- To Civil Engineers specification
RAINGARDEN- To Civil Engineers specification
RAINGARDEN- To Civil Engineers specification
RAINGARDEN- To Civil Engineers specification
TJA (x78)
M O W NL A W N
Elms Trees
1:35Slope falls 2m x 70m
UP
UP
UP
UP
M
O
W
N
L
A
W
N
M O W NL A W N
M O W NL A W N
M O W NL A W N
Water Tank
1:20Slope falls 1.25m over 26m
1:400Slope falls 0.1m over 41m
HEAVY VEHICLE ACCESS
BATTER
R O U G HL A W N
1:16
RAM
P
UP
GAS TANK2 X 7000L
HEAVY VEHICLE ACCESS
CARPARK
P O O L
1:16
WATER TANK
418000Surface Level
417900Surface Level
417500Surface Level
423000Surface Level
421000Surface Level
4230
00S
urfa
ce L
evel
419850Surface Level
418250Surface Level
417100Surface Level
421000Surface Level
421040Surface Level
417590Surface Level
417000Surface Level
416500Surface Level
416000Surface Level
415500Surface Level
414500Surface Level
414300Surface Level
412500Surface Level
410600Surface Level
415250Surface Level
416000Surface Level
415000Surface Level
414500Surface Level
416000Surface Level
415000Surface Level
415370Surface Level
413500Surface Level
414750Surface Level
416000Surface Level
414650Surface Level
415000Surface Level
419000Surface Level 418000
Surface Level417000
Surface Level416000
Surface Level421000
Surface Level420000
Surface Level422000
Surface Level423000
Surface Level
B A T T E R
416915Surface Level
417285Surface Level
417100Surface Level
417200Surface Level
Low Garden Bed- Planting TBC by Council
Low Garden Bed- Planting TBC by Council
Concrete slab for GAS TANK- to Engineers specs- dimensions TBC
P L A N T E D B A T T E R
RAMP
GREASE TRAP- Refer HYD ENG DWGS
SUBSTATION
BINS
423570Surface Level
420960Surface Level
GA
TE
B A T T E R
Cut outs in paving- 1m diam- Planting around tree base
416390Surface Level
417920Surface Level
417800Surface Level
200mm x 200mm cut outs in paving- base of each post, front & back- creeper to grow up
BATTER AROUND COURT EDGES AS REQUIRED
412500Surface Level
411300Surface Level
417000Surface Level
413500Surface Level
WATER TANK
421040Surface Level
420860Surface Level
419500Surface Level
419000Surface Level
417000Surface Level
412000Surface Level
CHAPEL- To Architects Design
Low Garden Bed- Planting TBC by Council
UP
UP421540
Surface Level
420940Surface Level
Raised Planter - to Architects spec
Raised Planter - to Architects spec
Retaining Wall - To Architects specBalustrade
- Timber Frame & Stainless wire- See elevations
Cut Across corner- To Allow Council foot path to be reinstated
Sleeper Retaining Wall- Painted Dulux "NAMADJI"- See elevation
1:26Slope falls 0.5m over 13m
418417
416
416.200
415
414
413
412
B A T T E R
419199Surface Level
414775Surface Level
411250Surface Level
411250Surface Level
414775Surface Level
418725Surface Level
417990Surface Level
417990Surface Level
418530Surface Level
420450Surface Level
420450Surface Level
419900Surface Level
418530Surface Level
420950Surface Level
421430Surface Level
421430Surface Level
421761Surface Level
PLANT SCHEDULE
SYM Botanical Name Common Name Mat. Height Mat. Spread Spacing Pot Size Quantity
Trees
BPD Betula pendula 'Dalecarlica' Silver Birch 11m 6m As plan 30cm 43
CES Cedrela sinensis Chinese Toon Tree 8m 3.5m As plan 14cm 41
QPA Quercus palustris Pin Oak 18m 10m As plan 30cm 6
UPA Ulmus parvifolia Chinese Or Lacebark Elm 10 - 15m 10 - 15m As Plan 30cm 31
Shrubs
EIV Escallonia iveyii White Escallonia 3m 3m 750mm Tube 1305
NDO Nandina domestica Sacred Bamboo 2m 0.8m 500mm Tube 3325
Perennials
NPW Narcissus 'Paper White' White Jonquils 0.5m 0.3m As plan Bulbs 6890
Strap Leaf Plants & Grasses
LMR Liriope muscari 'Royal Purple' Purple Turf Lily 0.3m 0.4m 300mm Tube 630
MSG Miscanthus sinensis 'Gracillimus' Eulalia 1.2 - 2.1m 0.9 - 1.2m 400mm Tube 3918
PNA Pennisetum 'Nafray' Fountain Grass 0.6m 0.6m Tube 787
Ground Covers
ACO Aptenia cordifolia Baby sun rose 0.3m 0.4m 300mm 14cm 325
TAS Trachelospermum asiaticum Creeping Star Jasmine 0.3m 1.2m 500mm Tube 640
Climbers
PQU Parthenocissus quinquefolia Virginian Creeper Structure Size Structure Size Up Wire 14cm 10
TJA Trachelospermum jasminoides Chinese Star Jasmine 8.0m 0.3m Structure Size Tube 78
Aquatic Plants
CPP Carex appressa Tall Sedge 0.9 - 1.5m 0.3 - 0.6m As plan Tube 716
JUS Juncus usitatus Common Rush 0.9 - 1.5m 0.6 - 0.9m As Plan Tube 716
(E) Existing
(T) Transplant
Notes
Plant pot sizes and numbers will be determined by stock availability at the time of installation.
Spacing is indication only. Numbers to be spread evenly over the area indicated on the plan.
* Plants supplied to be hedged should be full and bushy. All to be of similar shape and size
** Trees supplied in 30cm pots should be a minimum of 1.5m high from top of pot and single trunked.
All should be of similar shape and size. Double staking may be required.
*** Trees supplied as Advanced should be a minimum of 2.5m plus high from top of pot and single trunked.
All should be of similar shape and size. Double staking may be required.
SITE SPECIFICATION
Sleeper Walls
Sleeper walling is to be constructed with galvanised steel H beam posts. Treated Pine sleepers set between posts to
required height. Ensure footings and walling are constructed to structural engineers specifications and to Australian Standards.
Planting
Planting shall be carried out using accepted horticultural practices with all plants conforming to the species, size and quantities
indicated on the Landscape Plan and Plant Schedule. Plants shall be thoroughly soaked through immersion in water prior to
planting and if the planting soil is very dry then the planting hole is also to be filled with water and allowed to drain completely.
The root-ball of semi-advanced trees is to be well irrigated rather than immersed.
All plants shall be appropriately hardened off in the nursery. Use plants with the following characteristics: Large healthy root
systems with no evidence of root curl or pot bound restriction or damage, vigorous, well established, free from disease and
pests and of good form, consistent with the species or variety, hardened off – not soft or forced. Plants that do not meet these
requirements will be rejected.
Planting holes for shrubs and groundcovers are to be of minimum size 75mm larger than the planting pot in all directions.
Semi-advanced tree planting holes are to be the same depth as the root-ball and 2-3 times its diameter, with the top of the root-
ball being at grade. Planting holes are not to be excavated using an auger unless the edges of the hole are later broken up
using a spade or similar. The use of augers can smooth the side of the hole and lead to root girdling. A 75mm high berm is to
be constructed at edge of root-ball to hold water.
All plants are to be thoroughly watered after planting and slow release fertiliser added at the quantities specified by the
manufacturer.
SITE SPECIFICATION
Mulching
Organic mulch is to be supplied to all garden beds and is to be of chipped or shredded vegetable material with 80% of particles
in the size range 25 to 50mm in plan and 5 to 10mm in thickness. No particles are to exceed 75mm in plan. Mulch shall be free
of deleterious and extraneous matter such as soil, weeds and sticks. Mulch is to be stockpiled and thoroughly weathered prior
to delivery.
This mulch shall be laid to a minimum depth of 100mm and is to be sloped towards plant stems and kept 100mm back from the
steams of all plants to prevent collar rot.
Irrigation
An approved Netafim irrigation system is to be supplied to all garden beds and planter boxes. It is the responsibility of the
contractor to ensure that all irrigation meets Netafim specifications. This system is to be comprised of drip irrigation to all
garden beds and planter boxes including a rain-shut off device and timer.
Plant Establishment Period
There shall be a 13 week plant Establishment Period following the approval of Practical Completion by the responsible
authority. During this period the landscape contractor shall make good all defects in his / her scope of works.
Maintenance and Establishment means the care and maintenance of the contract area by accepted horticultural practices,
as well as rectifying any defects that become apparent in the work under normal use. This shall include, but shall not
be limited to watering, fertilising, weeding, pruning, pest and disease control, cultivation, re-staking and replacement
of any plants that fail or are damaged with plants of the same species and size.
PLANNING SPECIFICATION LISTS
NOT FOR CONSTRUCTION
Lighting - Ground Mount LED Luminaire- from garden spike
Lighting - 'HANGING LIGHTS' - from tree
Lighting - Recessed Bridge Rectangular Led
Lighting - Ground Mount 2LED Luminaire- from garden spike
Lighting - Car Park - P1
Lighting - Car Park - P1
SURFACES
Regular Coloured Concrete - Colour TBC
Pool
NOTES- All measurements must to be checked and verified on site.- Lighting shown for information only.- For further information, these drawing are to be read in conjunction with AECOM Hydraulic & Fire Engineers and Meinhart Civil Engineers design documentation.
Lawn - fine mown
Asphalt Heavy Vehicle Access - Car Park
Asphalt - Car Park & Hotel Entrance
Pebbles beds - Rain garden river pebbles
Tree Grate - Water drainage
Lawn - rough mown
Garden beds - '5 way blend' with existing soil
Retaining wall - Treated Pine Timber Sleepers
Compact Gravel - Class 4 Brown 5mm - DustCrushed Aggregate with bonding agent
Steps - 'Myrtle' 600x300x35mm Bullnose
Hardstand Coloured Concrete - Colour TBC
Crazy Paving - Kanmantoo Bluestone
UP
Plain Concrete - Colour TBC
Paving - Bluestone 100x100mm grid- tactile treads
Tactile Treads
SITE SPECIFICATION
Sleeper Walls
Sleeper walling is to be constructed with galvanised steel H beam posts. Treated Pine sleepers set between posts to
required height. Ensure footings and walling are constructed to structural engineers specifications and to Australian Standards.
Planting
Planting shall be carried out using accepted horticultural practices with all plants conforming to the species, size and quantities
indicated on the Landscape Plan and Plant Schedule. Plants shall be thoroughly soaked through immersion in water prior to
planting and if the planting soil is very dry then the planting hole is also to be filled with water and allowed to drain completely.
The root-ball of semi-advanced trees is to be well irrigated rather than immersed.
All plants shall be appropriately hardened off in the nursery. Use plants with the following characteristics: Large healthy root
systems with no evidence of root curl or pot bound restriction or damage, vigorous, well established, free from disease and
pests and of good form, consistent with the species or variety, hardened off – not soft or forced. Plants that do not meet these
requirements will be rejected.
Planting holes for shrubs and groundcovers are to be of minimum size 75mm larger than the planting pot in all directions.
Semi-advanced tree planting holes are to be the same depth as the root-ball and 2-3 times its diameter, with the top of the root-
ball being at grade. Planting holes are not to be excavated using an auger unless the edges of the hole are later broken up
using a spade or similar. The use of augers can smooth the side of the hole and lead to root girdling. A 75mm high berm is to
be constructed at edge of root-ball to hold water.
All plants are to be thoroughly watered after planting and slow release fertiliser added at the quantities specified by the
manufacturer.
SITE SPECIFICATION
Mulching
Organic mulch is to be supplied to all garden beds and is to be of chipped or shredded vegetable material with 80% of particles
in the size range 25 to 50mm in plan and 5 to 10mm in thickness. No particles are to exceed 75mm in plan. Mulch shall be free
of deleterious and extraneous matter such as soil, weeds and sticks. Mulch is to be stockpiled and thoroughly weathered prior
to delivery.
This mulch shall be laid to a minimum depth of 100mm and is to be sloped towards plant stems and kept 100mm back from the
steams of all plants to prevent collar rot.
Irrigation
An approved Netafim irrigation system is to be supplied to all garden beds and planter boxes. It is the responsibility of the
contractor to ensure that all irrigation meets Netafim specifications. This system is to be comprised of drip irrigation to all
garden beds and planter boxes including a rain-shut off device and timer.
Plant Establishment Period
There shall be a 13 week plant Establishment Period following the approval of Practical Completion by the responsible
authority. During this period the landscape contractor shall make good all defects in his / her scope of works.
Maintenance and Establishment means the care and maintenance of the contract area by accepted horticultural practices,
as well as rectifying any defects that become apparent in the work under normal use. This shall include, but shall not