DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume...

100
DESIGN-BUILD OF NORTH TORRANCE WELLFIELD PROJECT FOR: PUBLICS WORKS DEPARTMENT CITY OF TORRANCE 20500 MADRONA AVENUE TORRANCE, CA 90503 REQUEST FOR PROPOSALS Volume III Design Criteria / Contract Appendices May 2017

Transcript of DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume...

Page 1: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

DESIGN-BUILD

OF NORTH TORRANCE WELLFIELD PROJECT

FOR:

PUBLICS WORKS DEPARTMENT CITY OF TORRANCE

20500 MADRONA AVENUE TORRANCE, CA 90503

REQUEST FOR PROPOSALS

Volume III – Design Criteria / Contract Appendices

May 2017

Page 2: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

2 May 2017

TABLE OF CONTENTS

VOLUME III

VOLUME IIIA - CONTRACT APPENDICES

Appendix A – Section A-1: Design Requirements (to be supplemented with design

information provided by Selected Proposer)

Section A-2: Conceptual Design Level Drawings (to be replaced or

supplemented with plans submitted by Selected Proposer)

Section A-3 Environmental Mitigation Measures

Section A-4: Agency Coordination and Permitting

Appendix B – Required Insurance

Appendix C – Project Specifications for:

– Design (Section C-1)

– Construction (Section C-2)

– Operational Testing and Training (Section C-3)

Appendix D – Governmental Approvals and Responsibility Matrix

Appendix E – Quality Management Plan [draft to be provided with proposal and finalized

based on final technical proposals]

Appendix F – Start-up and Operational Testing Plan [draft to be provided with proposal and

finalized based on final technical proposals]

Appendix G – Milestone Schedule [draft to be provided with proposal and finalized based

on final proposals]

Appendix H – Subcontractors [draft to be provided with proposal and finalized based on

final business proposals]

Appendix I – Safety Plan [draft to be provided with proposal and finalized based on final

technical proposals]

Appendix J – SCADA Pre-Negotiated Scope and Fee

Appendix K – Minimum Required Technical Specifications

VOLUME III-B – REFERENCE DOCUMENTS

Page 3: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

3 May 2017

Appendix 1 – SCE Application

Electrical Service Requirements

Appendix 2 – City of Torrance North Torrance Well Field Project C.I.P. No. I-108

Preliminary Design Report

Well 9 Installation Report

Well 10 Preliminary Information Report

Appendix 3 – Corrosion Control Study

Appendix 4 – Torrance Municipal Code Sections 22.3.20 – 22.2.24

Appendix 5 – Record of Utilities, Pothole Data

Appendix 6 – Project Site Survey by Bush & Associates Inc.

Appendix 7 – Legal Description, by Floyd Huber

Appendix 8 – Easements

TUSD Access Agreement

TUSD Utility Easement

SCE Right-of-Way Lease

Appendix 9 – Geotechnical Study Report (Converse Consultants)

Appendix 10 – CEQA Documents

Mitigated Negative Declaration

Air Quality Study

Noise and Vibration Study

Mitigated Monitoring Plan (MMP)

Tank Failure Inundation Study Report

Statement of No Historical Significance

Appendix 11 – Not Used

Appendix 12 – Preliminary Calculations

Appendix 13 – Sample Specifications

Appendix 14 – State and Federal Grant Agreements

Notice to Proceed for Grant Agreement No. R16AP00141

Page 4: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

4 May 2017

Volume III-A - Contract Appendices

Page 5: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

5 May 2017

Appendix A

Section A-1: Design Requirements (to be supplemented with design information provided by Selected

Proposer)

Section A-2: Conceptual Design Level Plans (to be replaced or supplemented with plans submitted by

Selected Proposer)

Section A-3: Environmental Mitigation Measures

Section A-4: Agency Coordination and Permitting

Page 6: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

6 May 2017

Section A-1 – Design Requirements Overview

The following are the design requirements for the project. Further reference information can be found

in the Preliminary Design Report (PDR) attached as Appendix 2 of Volume III-B.

1.1 Well Field

Three groundwater wells will be included in the NTWFP (Well Nos. 9, 10, and 11). The design of the

wells and construction details are discussed in the following sections. The design flow from the well

field is 9,000 gpm, or 14,510 af/yr.

1.1.1 Well No. 9

Geoscience Support Services, Inc. (Geoscience) designed and observed the construction. Well

construction details are summarized in a report entitled Results of Drilling, Construction, Development

and Testing by Geoscience, May 2009 (Appendix 2). This well has the following characteristics:

Specific capacity = 39 gpm/foot.

Sustainable well yield = 3,000 gpm (4,840 af/yr).

18-inch-diameter casing.

Screen intervals: 190 to 310 feet, 330 to 470 feet, and 500 to 550 feet below ground surface (bgs).

Well depth = 594 feet bgs.

Discharge from Well No. 9 will be rerouted southerly on Yukon Avenue to the project site.

1.1.2 Well No. 10

The pilot hole for proposed Well No. 10 was drilled at the project site in June 2009 to determine water

quality parameters and develop the design for the well. Geoscience observed the construction of the pilot

hole and prepared a report recommending the well design (Appendix 2). As described in the PDR, the

well was drilled to a depth of 904 feet bgs and backfilled to a depth of 46 feet bgs. The conductor casing

was installed and grouted in place. See Drawing M-501 in Appendix A, Section A-2 of Volume III-A for

the well design diagram. The well will be completed as part of this project at this location. The required

well yield is 3,000 gpm.

1.1.3 Well No. 11

Well No. 11 is proposed to be constructed just west of Yukon Avenue, north of the I-405 Freeway within

the old Yukon Avenue right-of-way dedicated to the City, and is expected to be similar to existing Well

No. 9. The required well yield is 3,000 gpm.

Discharge from Well No. 11 will join the pipeline from Well No. 9 and proceed to the plant site.

1.1.4 Well Construction Requirements

All work is to be in accordance with the City of Torrance, California Department of Water Resources and

California Division of Drinking Water (DDW) standards. Prepare source water assessments for each new

Page 7: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

7 May 2017

well per DDW requirements. Obtain and comply with requirements of a National Pollution Discharge

Elimination System (NPDES) Permit. Provide required tanks and means for disposal of test water.

Construction of the new Wells 10 and 11 shall include, at a minimum, the following tasks:

Erection of temporary sound walls (Well No. 11 only).

Installation of a grouted conductor casing (task completed for Well 10).

Drill pilot hole. Take geophysical logs (resistivity, spontaneous potential, gamma ray, guard

resistivity, and acoustic with variable density log and porosity). Run caliper, gyroscopic, and video

surveys (Task has been completed for Well 10).

Submit report with recommended screen intervals and filter pack design for City review (task has

been completed for Well 10).

Obtain water samples for zone testing and test for water quality (task has been completed for Well

10).

Install well casing/screen (Type 316 stainless steel), one 2-inch stainless steel sounding tube, and

two 3-inch gravel feed tubes (mild steel). Install filter pack.

Develop well by airlifting and swabbing.

Install test pump for final development by pumping and surging. Measure flow rate and

groundwater level.

Conduct step drawdown and constant rates pumping tests.

At the end of the constant rate test, obtain water samples and test for constituents required by the

California Code of Regulations, Title 22 Rule.

Disinfect well.

Provide downhole color video of the well casing and screen.

Prepare and submit the well completion report to the California Department of Water Resources.

Prepare a report summarizing the well construction. Follow the format of the Well No. 9 report.

1.1.6 Well Nos. 10 and 11 Buildings

Buildings similar to those for Well No. 9 shall be provided. See Drawing A-102 of Appendix A, Section

A-2 of Volume III-A for floor plans. Buildings for Wells No. 10 and 11 shall be masonry, grouted solid,

and architecturally match Well No. 9.

Building shall be designed to be vandal-resistant with no exterior windows (except one in the utility

building control room). All doors shall be constructed of steel. Vandal-resistant door shall be used,

including heavy-duty locksets with deadbolts and tamper-proof door hinges with non-removable pins.

Doors and frames shall be primed and painted insulated galvanized steel; 1-3/4-inch thick 16 gage doors

and 12 gage frames. Finish hardware shall be Type 316 stainless steel and shall include lever handle

heavy-duty mortise locks, heavy-duty mortise hinges, and overhead closers protected by separate heavy-

duty stops. Accessories shall be aluminum and shall include continuous replaceable weather stripping and

thermal-break thresholds.

Provide removable skylights over each booster and well pump.

Tasks completed for Well No. 10.

Page 8: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

8 May 2017

Floors shall be constructed of reinforced concrete, 6-inch minimum thickness, with a light broom finish to

provide a slip-resistant surface. Floors shall be sloped a minimum of 1 percent to floor drains. Floor slab

of new buildings shall have a moisture barrier and be treated with a chemical hardener.

1.2 Reservoir

A reservoir is to be provided as a forebay for the BPS and for emergency storage.

1.2.1 Capacity

The reservoir capacity shall be 3.0 MG. The site will allow a tank with a maximum diameter of about 115

feet.

1.2.2 Configuration and Material

A single circular reservoir shall be provided with the following characteristics:

Provide 3 feet of freeboard below the reservoir roof.

For a prestressed concrete tank and 40-foot height, the side water depth would be 37 feet and

diameter 118 feet.

The bottom of the reservoir will be 20 feet below grade.

Design the reservoir per Section 64585, CCR Title 22, and AWWA D110, Type I standards and the

following criteria:

Current site-specific seismic data will be used for the design.

The minimum floor thickness will be 6.5 inches for durability and reinforcement clearances per

ACI 350, Code Requirements for Environmental Engineering Concrete Structures.

The roof will be a geodesic aluminum dome design.

Roof access hatch and vents will be provided.

The reservoir will be fitted with interior washdown connections and lighting at the roof entrance.

The reservoir layout will include inlet, outlet, overflow, and drain piping.

Provide stairway access to the top of the reservoir. Bottom is to be secured to prevent unauthorized

access. Stairway shall be free-standing, with stability connections to the reservoir only at the

landings.

1.3 Booster Pump Station (BPS)

The BPS is to discharge treated water to the City’s distribution system.

1.3.1 Capacity

The station capacity is to be equal to the total project design inflow capacity of 9,000 gpm. Because the

well flow will be variable, due to fluctuating groundwater conditions and water system gradient, and

operational flexibility is required, two pumps will be provided with a variable frequency drive (VFD) to

provide a means of matching total inflow.

Select vertical turbine booster pumps as follows:

Page 9: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

9 May 2017

Two pumps could run at full speed.

Pump design flow rate = 4,500 gpm.

Pump shall be capable of pumping from the reservoir with five feet of water depth to the first

piping connection in Yukon Avenue. At this point, the HGL will vary from 353 feet (minimum

day system demand) to 303 feet (peak hour system demand).

For pipeline friction, assume HW coefficient (C) of 120.

Consider valve and fitting head losses.

See Section 6.5 of the PDR for preferred manufacturers.

1.3.2 Layout

Three vertical turbine pumps are to be provided (two to run plus one standby), each with a capacity of

4,500 gpm; preliminary estimate of 291-ft head and 450 HP which needs to be analyzed and designed by

the Company. A representative pump selection may be a Peerless 18HXB three-stage pump operating at

1,760 revolutions per minute (rpm).

1.3.3 Discharge Pipeline

A 24-inch pipeline from the BPS will be connected to two points within the distribution system:

To the existing 12-inch line in Yukon Avenue, and,

Extend an 18-inch line southerly in Yukon to connect to a 12-inch line in 182nd

Street.

Appendix A, Section A-2 of Volume III-A includes Drawing C-104 for the yard piping plan, Drawing C-

10 for offsite piping in the utility easement and northerly along Yukon, and Drawing C-202 for offsite

piping crossing the I-405 Freeway.

1.3.4 Surge

1.4 Drain Lines

Several drain lines are required for disposal of project waste flows, as follows.

1.4.1 Reservoir Overflow and Drain

Under a worst-case scenario (failure of the wells to shut down on high reservoir level), the overflow line

must be designed to dispose of the full 9,000-gpm well inflow. This will require a 30/24-inch gravity

pipeline and connection to an existing manhole in Yukon Avenue north of 182nd

Street, which is

connected to a 9-foot by 10-foot reinforced concrete box (RCB) culvert in 182nd

Street. To maintain

gravity flow, the pipeline must cross the I-405 Freeway via a jacked steel casing westerly of and parallel

to Yukon Avenue. Discharge from two freeway drain lines will be diverted to this line. See Appendix A,

Section A-2 of Volume III-A Drawings C-107, C-201, C-202, and C-204 for the plan and Drawings C-

203 and C-204 for the profile. If constructed early, this line could be used for disposal of well

development water.

Page 10: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

10 May 2017

1.4.2 Drain to Sewer

The rest room, laboratory, and chemical room drains will require a connection to the sewer for disposal.

The point of connection will be an existing manhole in front of the school. This line is shown in Drawings

C-104 and C-107; the profile is in Drawing C-205 in Appendix A, Section A-2 of Volume III-A.

1.4.3 Well Flush Lines

Flush water from Well Nos. 10 and 11 will be routed to connections to the reservoir overflow drain line.

Flush water from Well No. 9 will be discharged at Well No. 11.

1.4.4 Blending

A blend line has been provided for future blending or treatment to meet TDS or other treatment

requirements. Future blending may be required should imported water meet TDS levels well below 500

ppm. A future RO treatment process will generate a waste concentrate flow which will be disposed of to

the existing 6” VCP sewer system. A holding tank could be required to regulate concentrate flow. The

blend line can also be used as a potable water line for the site. The blend line is currently stubbed out to

Yukon Avenue, but is not connected.

1.5 Utility and Access Road Easements

A 24-foot wide utility easement has been obtained (Appendix 8 of Volume III-B) from the TUSD. It

will carry the well water pipeline into the plant, water from the plant to the distribution system, the

sewer for the rest room, future blending, the reservoir overflow storm drain, electrical conduit, and

fiber-optic cable conduit, as shown in Drawings C-104 and C-107 of Appendix A, Section A-2 of

Volume III-A.

The utility easement is overlaid with a 15-foot wide access road easement. The access road has been

installed. A six-foot chain-link fence and automated access gates with car reader will be required

between the school playground and access road and school parking lot and access road.

1.6 School Parking Lot Improvements

To provide for large vehicle access to the project site, the existing school parking lot was modified, per

Drawing C-108 found in Appendix A, Section A-2 of Volume III-A. The access road driveway will be

re-striped across the AC playground area and new gates installed for school access to the playground

and access road. This is being coordinated with TUSD.

1.7 Water Treatment

The water treatment system shall be designed for a flow of 9,000 gpm and provide treatment for the

bacteriological and virus disinfection as required by DDW.

The water treatment requirements are to be based on water quality analysis from Well No. 9. The

general chemistry results are summarized in Table 3.1, which show that the water from Well No. 9

meets all maximum contaminant levels (MCLs) established by the DPH based upon the initial sampling.

The complete analysis is provided as Appendix A in the PDR.

Provisions in the design shall include for treatment for fluoridation, hydrogen sulfide, iron and

manganese, and total dissolved solids (TDS). Treatment systems for fluoridation and hydrogen sulfide

Page 11: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

11 May 2017

are included in this project. If treatment systems for iron and manganese are determined to be required

through water quality testing, they would be extra work. A discussion of these constituents and their

treatment methodology is provided in the sections below.

1.7.1 Disinfection

The City practices disinfection by chloramination to maintain compatibility with imported water

supplies (the Metropolitan Water District chloraminates water treated at its treatment plants).

It is intended to inject both chlorine and ammonia into the water upstream of the reservoir to form

chloramine prior to storage and minimize the time the water experiences a free chlorine residual. An

additional chlorine residual analyzer and hypochlorite metering pumps will monitor reservoir effluent

combined chlorine residual and add hypochlorite if necessary to maintain the desired concentration.

To maintain compatibility with imported water, the chloramine concentration should be maintained at

about 2.2 milligrams per liter (mg/L) as total chlorine. Because there is some chlorine demand in the

water (assumed to be about 1.3 mg/L), this will require addition of about 3.5 mg/L of chlorine and 0.6

mg/L ammonia. Actual chlorine dose to maintain 2.2 mg/L in the reservoir effluent will be determined

by bench testing and operating experience. Based upon these doses and assuming a maximum well field

production rate of 9,000 gpm, the disinfection system will need to be able to supply about 378 pounds

of chlorine and 64 pounds of ammonia per day. Chemical requirements are summarized in Table 3.2.

Chlorine will be added as sodium hypochlorite, which will be purchased as a nominal 12.5 percent

solution, containing about 1 pound of effective chlorine per gallon. It will be stored in a 5,000-gallon

fiberglass storage tank, which will provide about 14 days of storage plus working volume to allow

receipt of a full truckload of hypochlorite.

Ammonia will be purchased as aqueous ammonia at a nominal concentration of 19 percent, containing

about 1.54 pounds of ammonia per gallon. Ammonia will be stored in a 500-gallon steel tank, which

provides 14 days of storage plus working volume. This volume is less than a full tank load (6,000

gallons). Due to its volatility and pungent odor, ammonia storage systems require installation of a

scrubber on the tank vent to capture ammonia fumes. The scrubber will be a small tank, 18 inches in

diameter, and filled with water to absorb the ammonia fumes. The tank will occasionally be manually

drained and refilled with fresh water.

Table 3.1 – Well No. 9 Water Quality

Constituent Unit MCL Value

Calcium mg/L — 80

Magnesium mg/L — 25

Sodium mg/L — 64

Potassium mg/L — 6.3

Bicarbonate mg/L — 220

Chloride mg/L — 180

Sulfate mg/L 250 46

Nitrate mg/L 45 ND

Fluoride mg/L 2 0.29

Hardness mg/L — 300

Alkalinity mg/L — 200

TDS mg/L 1,000 540

Specific Conductance µS/cm — 950

Page 12: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

12 May 2017

pH — 6 to 9 7.88

Odor TON — 1.0

Boron µg/L 1,000 120

Langelier Index — — 0.595

Bromide µg/L — 580

Copper µg/L 1,300 1.9

Lead µg/L 15 0.47

Iron µg/L 300 18

Manganese µg/L 50 41

Sulfide mg/L — ND

1.7.2 Fluoridation

The City of Torrance currently practices fluoridation to be consistent with MWD water.

As seen in Table 3.1, the well water contains about 0.3 mg/L of fluoride. The U.S. Department of

Health and Human Services has recently issued a statement advising that water systems target a fluoride

concentration of about 0.7 mg/L to minimize dental cavity formation and avoid dental fluorosis.

Therefore, the fluoride feed system should be capable of providing about 0.4 mg/L of fluoride, or about

42 pounds per day.

Fluoride will be purchased as hydrofluosilicic acid, with a nominal concentration of 24 percent,

containing about 2 pounds of fluoride per gallon. It will be stored in a 500-gallon high-density

polyethylene (HDPE) tank, providing 14 days’ storage plus working volume. As fluoride vapors are

very corrosive, the tank will need to be ventilated through the roof.

1.7.3 Hydrogen Sulfide

(H2S) is seen in a number of Torrance wells. Spray nozzles shall be designed at the top of the reservoir

similar to other Torrance locations, so that well water is discharged into the reservoir through these

nozzles.

To address the possibility that H2S released from the water might lead to odor complaints from

populations near the reservoir, means shall be provided to add a scrubber capable of removing H2S

from air vented from the reservoir, should it be needed. To provide for this future scrubber, the reservoir

roof shall be designed and provided with a 2-foot diameter flanged outlet, located opposite the vent. In

the future, a 2-foot diameter duct should be extended to a blower and scrubber located on the ground

adjacent to the reservoir. A 10-foot by 15-foot space shall be required for this blower and scrubber.

1.7.4 Corrosivity

The design shall include corrosion control analysis and facility design and installation to meet DDW

requirements and address requirements described in the Corrosion Control Study Report (see Appendix

3).

1.8 Additional Treatment Requirements

While existing water quality information does not indicate the need for treatment beyond disinfection,

the City’s other wells in the vicinity of Well No. 9 experience a number of water quality issues that

Page 13: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

13 May 2017

require treatment. It is likely that, as the NTWFP begins to produce significant quantities of water, these

water quality issues may begin to appear. It is prudent, therefore, to include design for additional

treatment should it be required.

1.8.1 Iron and Manganese

As seen in Table 3.1, iron and manganese are present at concentrations below their secondary MCLs.

The manganese concentration of 41 µg/L is close to the MCL of 50 µg/L, and it may therefore be

possible that some manganese may accumulate in distribution system piping over time. This could lead

to occasional instances of black water if these deposits were disturbed, as might happen during flushing

operations. It is important to note that the black water would not be hazardous to health but would be

very displeasing aesthetically.

Iron and manganese are present at similar concentrations in other City wells, where they are

successfully dealt with by addition of a phosphate sequestrant/corrosion inhibitor (Carus 8500). This

sequestrant prevents precipitation and settling of the manganese, thus preventing accumulation of

manganese sediment in the distribution system. If manganese concentration should exceed 50 µg/L,

additional treatment may be required. This treatment would most likely consist of oxidation using

potassium permanganate or ozone and filtration through manganese greensand or other media filtration.

The design for these future facilities shall be provided.

The Carus 8500 product is an aqueous solution of phosphates with specific gravity of 1.35 to 1.41. It is

typically fed into the well water at a dose of 5 mg/L, which requires about 47 gallons per day. It will be

stored in a 1,000-gallon HDPE tank, which provides 14 days of storage plus working volume.

1.8.2 TDS Reduction

At the present time, groundwater at the NTWFP meets water quality requirements, however, the

groundwater basin has been impacted by seawater intrusion that occurred in the past. Based on this

information, future installation of a reverse osmosis (RO) system shall be designed as a part of this

project. Drawing C-101 found in Appendix A, Section A-2 of Volume III-A presents a conceptual

layout of the RO system.

1.8.3 Chemical System – Preliminary Sizing

Table 3.2 – Chemical Systems

Chemical Systems Dose

(mg/L) Pounds per Day

Concentration (lb/gal)

Gallons per Day

Storage Tank (gallons)

Sodium hypochlorite 3.5 378 1 378 6,000

Ammonia 0.6 64 1.54 42 700

Fluoride 0.4 42 2 21 500

Sequestrant 5 540 11.7 47 1,000

1.9 Electrical Service

The electrical service shall include a new electrical transformer. The utility requirements shall be per

Southern California Edison (SCE) standards. The SCE transformer for the plant facilities shall be located

in the northeast corner of the site. A separate transformer for Well No. 11 shall be located adjacent to the

well building.

Page 14: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

14 May 2017

As shown in Drawing C-101 found in Appendix A, Section A-2 of Volume III-A, there is space at the

plant site for storage of two portable generator units for Well Nos. 9 and 11.

1.9.1 Main Switchboard

The power to the station shall be 480/277 volts, 3 phase, 4 wire. The main switchboard shall consist of

an underground pull section and one section with both the utility meter and the main circuit breaker.

The main circuit breaker shall have ground fault protection. The main electrical service shall have the

capability of powering a lead pump, a lag pump, and the pump for Well No. 10. The third booster pump

does not need to be included in the electrical load calculations as it shall be strictly a standby pump. The

main switchboard shall also include an automatic transfer switch, two VFDs for the booster pumps, one

solid-state starter for a booster pump, and one solid-state starter for Well No. 10. The main control

panel (MCC) will also include a 120/208-volt step-down transformer and panelboard for lighting and

auxiliary loads and a circuit breaker for the electrical room air-conditioning unit. Refer to Drawing E-

601 found in Appendix A, Section A-2 of Volume III-A.

Well No. 11 will not be fed from the BPS main switchboard; this well will require its own service.

Refer to the single-line diagram in Drawing E-602 found in Appendix A, Section A-2 of Volume III-A.

The future RO treatment process will require significant electrical loads (as outlined in Section 3.4 of

the PDR), which will not be included at this time. There are no provisions in the main switchboard to

feed the future RO treatment facility.

1.9.2 Emergency Power

A standby engine/generator (E/G) shall be provided to allow continued operation during a power

outage. The following features (motor) will be supported simultaneously:

Well No. 10. Well No. 11 will require its own electrical service because of the distance from the

plant site transformer. To provide required flows during an emergency, it is assumed that both

Well Nos. 9 and 11 will operate with a portable generator. This project will provide the two

generators and pre-built metal buildings for storage at the Site.

BPS. Two pumps, operating simultaneously.

Chemical pumps.

Air conditioning.

Miscellaneous electrical load.

An E/G unit shall be provided. Per City criteria, the fuel tank will be sized for a 48-hour run time during

a power outage. The fuel tank will be double-walled with leak detection alarms. The leak detection

alarm will have local and remote annunciation. The remote annunciation will be via the site

programmable logic controller (PLC) to City of Torrance Public Works Central Control via the

supervisory control and data acquisition (SCADA) system.

An above-grade diesel fuel tank shall be provided, to be located just outside the E/G room.

Approximate volume will be 5,000 gallons.

1.9.3 Utility Building Interior Lighting

Interior lighting shall consist of surface-mounted fluorescent, 1-foot by 4-foot enclosed and gasketed

fixtures. Lighting fixtures and lamps shall be California Title 24 compliant. Lighting fixtures with

Page 15: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

15 May 2017

emergency battery packs will be used to provide egress lighting during the transition from normal

power to emergency generator power. Lights will have generator backup power.

1.9.4 Chemical Room Lighting

The chemical room lighting shall consist of surface-mounted fluorescent, 1-foot by 4-foot enclosed and

gasketed fixtures and will be corrosion resistant. Lighting fixtures with emergency battery packs will be

used to provide egress lighting during the transition from normal power to emergency generator power.

Lights will have generator backup power.

1.9.5 Site Exterior (Security) Lighting

Exterior site lighting (security lighting) shall consist of metal halide wall packs mounted on the exterior

walls and metal halide fixtures mounted on 20-foot-high lighting poles. The exterior lighting will be

controlled via photocell controls to turn on at dusk and turn off at dawn. The site lighting levels shall be

kept within the property and shall not spill to the neighboring properties nor interfere with freeway

drivers.

The Caltrans right-of-way between the Caltrans block wall and the NTWFP Site block wall is a security

concern. Caltrans has requested this area be secured with chain-link gates and security cameras and

lights.

1.10 Security

1.10.1 Utility Building Intrusion Alarm

The building intrusion alarm shall consist of motion sensors located in the building interior. The motion

sensors will be deactivated when the vehicle electrical gate is opened via the proximity cards. Proximity

cards shall match the existing City’s cards. The system is monitored by a 3rd

-party firm via POTS phone

lines. The intrusion system shall be as follows:

Bosch 7412-GV4 control unit

Bosch D1255 keypad

Exterior Door Contacts GE 1076D concealed GE 2507 Surface mounted DPDT

Interior Protection will be detailed as the building design becomes finalized.

1.10.2 Security Closed Circuit Television (CCTV)

Cameras shall be used to monitor the perimeter and the interior of the NTWFP Site. The cameras shall

be as manufactured by Panasonic to match the City’s existing cameras. A Photometric plan shall be

provided to assess lighting levels for camera placement. The video will be sent via the communication

media to central control.

1.10.3 Site Electric Gates

Access to the site shall consist of two electrically actuated gates, one gate will be installed in the main

entry at the school parking lot and another gate will be located at the project site. Refer to Civil

drawings found in Appendix A, Section A-2 of Volume III-A for location of the gates. The gates shall

operate as follows:

Page 16: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

16 May 2017

The personnel use a proximity card to open the gate.

Security is disabled and the gate opens and then automatically closes after a time delay.

Upon exiting, personnel use proximity card or key switch to close gate.

If a photo sensor detects an object in the path of the gate while closing, the gate shall open and

remain open.

The gate shall have an adjustable time delay to close after the last valid card user exits.

Security shall then be enabled after the time delay has expired after the last valid card user exits.

A Knox switch shall be provided for the fire department to open the gates at any time.

Two days of operator training shall be provided.

1.11 Facility SCADA System Overview

Treatment facilities and Well Nos. 9, 10, and 11 shall be designed to allow for automatic operation with

remote monitoring and supervision.

Each well shall be controlled by a local PLC. All PLCs shall be tied together with the NTWFP plant

SCADA workstations via a fiber-optic network. Controls of existing Well No. 9 shall be modified to

interface it to the new facility via fiber-optic cable installed with the new pipeline.

The plant SCADA system shall include Wonderware software.

A design objective is to have all PLCs by Allen-Bradley Logix platform (ControlLogix and/or

CompactLogix).

The plant shall communicate with the City SCADA system using a DSL connection, which will be

ordered by the City.

The plant shall be equipped with an Ethernet spread spectrum radio, to be used as a backup

communications media. The radio will be tied to the City’s existing water system SCADA at City

Yard.

Plant control system shall be stand-alone and will be integrated by the design-build team. Design-build

team will contract control system integrator designated by the City (“City’s Integrator”) to expand

existing City’s Water SCADA system to accommodate the plant.

City has pre-negotiated the existing SCADA modifications and cost with the City’s Integrator

(Appendix J of Volume III-A).

Upgrade of the existing City of Torrance SCADA system, including new radio system infrastructure, is

not in the DB scope.

1.12 Site Work

1.12.1 Site Layout

A layout of the project site is included as Drawing C-101 found in Appendix A, Section A-2 of Volume

III-A. The layout includes adequate space around each feature for access and maintenance and turn-

around by a fire engine.

Page 17: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

17 May 2017

With the exception of the access road along the existing east block wall, the Site is to be lowered an

average of one-foot as a mitigation measure for reservoir failure.

Due to the quantity of hazardous materials in the Chemical Room, the Utility Building is classified as H-

Occupancy. This will probably require sprinklers for fire protection in at least the chemical room.

Coordination with the City Fire Prevention Department is required by the Company.

1.12.2 Utility Building

A utility building shall be provided near the reservoir with the following minimum number of rooms:

E/G set.

Electrical.

Control.

Booster pumps. A removable skylight shall be provided over each pump for equipment removal.

Chemical storage and feed equipment. An eyewash/shower will be provided.

A unisex rest room will consist of a toilet and lavatory. Handicapped access shall be provided.

A laboratory, which shall include counter space with a sink, cabinets above, and an undercounter

refrigerator. Sample lines shall be extended into the room. Countertop shall be solid surface

Corian, cabinets shall be plastic (HDPE).

The building shall be concrete block, fully grouted, with architectural treatment. See Drawing M-

101 of Appendix A, Section A-2 of Volume III-A for a proposed building floor plan. The utility

building will be split-face block to match the appearance of the existing Well No. 9 building. The

interior clearance will be 12 feet high to accommodate the chemical storage tanks. The roof will be

flat, with a minimum 3-foot 6-inch parapet to screen exhaust fans and the air conditioner, and act

as a means of fall-prevention for workers on the roof. Roof openings with removable covers will

be provided over each chemical storage tank.

Building shall be designed to be vandal-resistant with no exterior windows (except one in the

utility building control room). All doors shall be constructed of steel. Vandal-resistant door shall

be used, including heavy-duty locksets with deadbolts and tamper-proof door hinges with non-

removable pins. Doors and frames shall be primed and painted insulated galvanized steel; 1-3/4-

inch thick 16 gage doors and 12 gage frames. Finish hardware shall be Type 316 stainless steel

and shall include lever handle heavy-duty mortise locks, heavy-duty mortise hinges, and overhead

closers protected by separate heavy-duty stops. Accessories shall be aluminum and shall include

continuous replaceable weather stripping and thermal-break thresholds.

Hardware for the building shall include the following:

o Manufacturer: Schlage

o Cylindrical lockset: ND80 JTD 626 x RHO

o Electrical Cylindrical Lockset: ND 80 JTDEURX 626 x RHO

o Mortise Lockset: L9080 JT 06 626

o Electrified Mortise Lockset: L9092EURX JT 06 626

o VON DUPRIN

Page 18: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

18 May 2017

Panic Bar: XP99 NL 996L 06 626 (Provide FSIC Primus Housing)

Electrified: XP99RX NL E996L 06 626 (Provide FSIC Primus Housing)

Provide removable skylights over each booster and well pump.

Provide an overhead bridge crane with hoist inside the booster pump room / building, with 3-ton

capacity. The crane rails shall either be supported by the building or be a free-standing structure

inside the room. Should the rails be support by the building, the building shall be designed to

support the rated load, while meeting all structural and seismic requirements. The crane / hoist

system shall be capable of lifting each of the booster pump motors and pumps from their

respective pump cans and transporting to the building entrance for loading onto a flat-bed truck for

off-site service.

Floors shall be constructed of reinforced concrete, 6-inch minimum thickness, with a light broom

finish to provide a slip-resistant surface. Floors shall be sloped a minimum of 1 percent to floor

drains. Floor slab of new buildings shall have a moisture barrier and be treated with a chemical

hardener.

Provide a roof parapet, minimum 3-foot 8-inch height, to conceal roof-mounted equipment

including roof hatches, ventilation fans, and air conditioners.

Building shall have metal roof decking covered by built-up roofing, which shall be warranted for

20 years, minimum (full value, nonprorated, no dollar limit guarantee). Metal roof decking shall

be supported by structural steel roof framing. Steel roof framing shall be supported by the masonry

walls. No interior columns shall be allowed. Bottom of roof framing shall be at least 24 inches

above the top of any electrical or mechanical equipment.

Each chemical tank (except the scrubber) will be provided with a roof opening for tank removal.

An interior wall-mounted ladder and roof scuttle shall be provided for access to roof equipment.

Building roof shall drain to wall-mounted roof scuppers or to roof drains. Parapet shall be

provided with roof overflow openings near the scuppers or roof drains.

The floor in the chemical room will be depressed to provide containment of the full volume of

each chemical storage tank, plus freeboard.

1.12.3 Chemical Treatment Vaults

A vault shall be provided just ahead of the inlet connection to the reservoir for application of chlorine,

ammonia, and polyphosphate. A second vault shall be located between the reservoir and the BPS for

application of chlorine and ammonia.

1.12.4 Fencing and Gates

The project site has been provided with a concrete masonry block wall along the east property line (school

side) and concrete masonry walls are proposed on the north and west property lines (SCE and Caltrans

sides). Rolling gates shall be provided at the entry to the access easement near Yukon Avenue and at the

site entrance. This shall be operated by an electric actuator; City standard is Elite Model SL-3000. An

access gate shall also be provided along the north wall line, for entry of emergency vehicles. Flood gates

manufactured by FloodBreak shall be provided at site entrances.

Page 19: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

19 May 2017

1.12.5 Site Drainage

The site drainage shall incorporate low impact design (LID) elements pursuant to current NPDES MS4

Permit requirements. This will involve providing onsite storage and/or minimizing impermeable surfaces

(using gravel or porous pavement, for example). The County of Los Angeles Low Impact Development

Standards Manual will be used as a guideline.

1.13 Work at McMaster Park

After completion of the project, all of the existing water facilities at McMaster Park except Well No. 9

shall be demolished; see Drawing C-106 found in Appendix A, Section A-2 of Volume III-A. Work

shall include the following:

Removal and reinstallation of a portion of the Well No. 9 discharge piping and electrical conduits.

Demolition of the steel reservoir, including all appurtenances, piping, and concrete ringwall. Lead

in the coating will need to be addressed.

Removal of perimeter chain link fencing, including posts and concrete.

Removal of well and booster pumps, including motors.

Removal of all piping.

Removal of chemical storage and feed equipment.

Removal of electrical panels and wiring in underground conduits. Conduits may be abandoned in

place.

Demolition of Well No. 6 per state and local requirements.

Demolition of the building.

Abandonment of the booster pump station discharge piping. This will require removal of the tee

connection in Yukon Avenue and reconnection of a service line.

Removal of buried concrete structures, including the BPS and transformer pad. If the structure is 4

feet or less deep, remove the structure. If greater than 4 feet, remove the structure to a depth of 3

feet, core weep holes in the floor, and backfill with compacted structural fill material.

After completion of demolition and removals, repair any damaged pavement or gutters and grade the

site for proper drainage. Provide grass sod over the bare areas and extend the existing park irrigation

system to cover the new grass. Coordinate these design and construction activities with the City

Community Services Department.

Page 20: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

20 May 2017

Section A-2 – Conceptual Design Level Drawings

(1) Print outs (11” x 17”) of the current conceptual drawings follow.

(2) This includes data files for these drawings, along with the topographic survey data files and

be uploaded from the City’s website at www.ntwfp.torranceprojects.city.

(3) This section shall be replaced (or supplemented) with drawings provided by the Company.

(4) Proposals shall include refinements to these drawings:

Provide a higher level of detail, enabling the City and its Technical Review Panel to

better understand the Facility that is proposed, including specific items of equipment.

Indicate finishes, materials, access and operational features.

Prior to construction, final drawings, specifications, and other documents shall be submitted for review

and approval, as described in Volume II.

Page 21: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

21 May 2017

Section A-3 – Environmental Mitigation Measures

The following are mitigation measures from the Project’s Mitigated Negative Declaration. These

mitigation measures must be complied with and implemented by the Company in execution of the

project.

Mitigated Negative Declaration

Air Quality Study

Noise and Vibration Study

Mitigation Monitoring Plan (MMP), as required by the CEQA documents

The above list documents can be found in Appendix 10 and can be uploaded from the City’s website.

Page 22: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

22 May 2017

Section A-4 – Agency Coordination and Permitting

The following sections include a summary of required agency coordination and permitting the design-

build contractor is expected to perform.

4.1 Caltrans

Coordination and permitting shall be required by the Company from Caltrans for modification to the

Caltrans right-of-way between the 405 Freeway and Site. The trees and irrigation system are to be

removed within a 50-foot radius of Well No. 10. Chain-link fences with gates are to be installed

between Caltrans and City block walls at the west and east end of the City’s property, and security

lights installed. Grass is to be removed and open spaces covered with mulch.

4.2 TUSD

Coordination shall be conducted by the Company with the TUSD to discuss and mitigate impacts to the

Yukon Elementary School or property both during construction and from operation and maintenance

activities. Mitigation measures and procedures shall be incorporated into the design-build documents so

that selected contractor incorporates them into their work. Among the issues that will be covered

include public safety during construction, working hours and workday restrictions, traffic control, and

modification of the existing parking area to accommodate new infrastructure while maintaining or

improving parking and traffic flow and new landscaping along Yukon Avenue parkway in front of

Yukon Elementary School.

4.3 SCE

The site shall require new 480-volt 3-phase electric service to operate electric motors for the well

pumps for Well Nos. 10 and 11 in addition to operation of the BPS. Other 110-volt electrical

components will be instruments and controls, site lighting, and electrical demand associated with the

rest room.

An application shall be submitted for new electric service from SCE. A load schedule will be required

for submittal to SCE along with a site plan and description of the facility.

Demand for a future RO treatment facility is not included at this time.

4.4 State Water Resources Control Board (SWRCB)

A general permit to discharge storm water associated with construction activity including clearing,

grading, and excavation activities that disturb greater than 1 acre of total land area is required to be

obtained by the Contractor for the City. The site encompasses an area of approximately 1.5 acres. . The

new General Construction Storm Water Discharge Permit requires the “Legally Responsible Party”

(LRP) to file permit registration documents (PRDs) electronically prior to starting construction activity.

The Contractor shall prepare the permit on the State’s SMARTS system for the City’s LRP to certify.

The PRDs consist of:

Notice of Intent (NOI)

Risk Assessment

Site Map

Page 23: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

23 May 2017

Storm Water Pollution Prevention Plan (SWPPP)

Annual Fee (mail no later than seven days before the start of construction)

Signed Certification Statement

Notice of Termination (at Project completion)

Permit coverage does not begin until the PRDs and annual fee are received by the SWRCB and a WDID

number is assigned and sent via Storm Water Multi-Application and Report Tracking System

(SMARTS).

Development and implementation of an SWPPP and monitoring program are required to be in place by

the start of construction. Notice must be filed prior to the start of construction. There is a filing fee of

$317 (also the annual fee) for 1-acre sized projects and $200 plus a surcharge for projects that qualify

for the low erosivity waiver. These fees are subject to change by the SWRCB; processing time is

approximately one month. Contractor shall provide Qualified Stormwater Developer (QSD) and

Qualified Stormwater Practioner (QSP), as required to prepare SWPPP and inspect BMPs.

The PRDs are to be submitted to SWRCB SMARTS database, located at

https://smarts.waterboards.ca.gov/smarts/faces/SwSmartsLogin.jsp.

4.5 Regional Water Quality Control Board (RWQCB)

The City’s water system NPDES permit will be amended for discharge associated with water produced

from the overflow and drain from the reservoir and future well flush discharge.

The Company shall prepare and the City of Torrance will submit the required permit application and

documentation to the RWQCB to obtain the NPDES permit (Appendix 11 of Volume III-B):

Regional Water Quality Control Board, Los Angeles Region

320 West Fourth Street, Suite 200

Los Angeles, CA 90013

Discharges from well development, well purging, or dewatering during construction of the wells may be

covered under Order R4-2008-0032, “Discharges of Groundwater from Construction and Project

Dewatering to Surface Waters.” At least 45 days before the start of a new discharge, an application

needs to be submitted to the RWQCB that includes an NOI and a site characterization study defining the

presence of contaminated groundwater. The report must include a list of constituents and discharge

concentration of each constituent submitted in spreadsheet form (volatile organic compounds, metals,

pesticides and PCBs, and semi-volatile organics).

The Contractor will prepare and the City of Torrance LRP will certify the required NPDES permit

application and NOI to be covered under the existing order to the RWQCB, which is located at:

Regional Water Quality Control Board, Los Angeles Region

320 West Fourth Street, Suite 200

Los Angeles, CA 90013

4.6 City Plan Checking and Permit Process

When completed, the plans need to be submitted by the selected design-build contractor to the City of

Torrance for plan-check approval. Approvals will be obtained from the Public Works, Building and Fire

Departments in addition to other departments that the City deems appropriate. The City Public Works

Department will resolve potential conflicts in comments provided by different City departments. Upon

Page 24: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

24 May 2017

receipt of approved plans by the City, permits can then be obtained by the construction contractor prior

to the start of construction. Permits will include encroachment, building, plumbing, mechanical,

electrical, and fire.

Plans will need to be submitted to the Public Works Department including the Public Works

Engineering and Water Operations Division of the City of Torrance for plan-check processing and

approval. Once approved, encroachment and other related permits are then obtained by the contractor.

4.7 AT&T

The Company shall work with AT&T to bring a phone and data line to the Site. AT&T will bring a line

overhead to the pole (1319282E) at the southeast corner of the school property. A conduit will need to

be brought from the existing pull box at the school parking lot to the pole (See Figure E-

101).(Information per Craig Chinen of AT&T (310) 515-2429, [email protected] and per email dated

March 22, 2016).

4.8 Los Angeles County Sanitation District (LACSD)

A permit from the LACSD shall be obtained by Company for the sewer from the utility building; the

discharge line for the future RO system concentrate will not be addressed at this time. Initially only the

permit for connection to the sewer line in Yukon Avenue for the utility building will be required. If in

the future, the RO system in installed, it will be necessary to connect to a different sewer line with a

larger capacity, and thus a separate permit will be required at that time.

4.9 Division of Drinking Water (DDW)

DDW approval is required for reservoir and well designs. DDW staff will be included as part of the

City’s plan check and permit process.

4.10 Public Outreach to Stakeholders

Contractor shall participate in meetings with stakeholders to discuss design aspects of the project. The

meeting will include:

Water Commission meeting

City Council meeting

At least one public outreach meeting

Contractor shall prepare PowerPoint presentation for each meeting, which will include at least one site

rendering showing visual aspects of the project. Contractor shall assume that each meeting will be held

in or nearby the Torrance area and that each meeting will last for two hours. Meetings will be held

during evening hours.

Page 25: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

25 May 2017

Appendix B - Required Insurance

A. CONTRACTOR must maintain at its sole expense the following insurance, which will be full

coverage not subject to self-insurance provisions:

1. Automobile Liability, including owned, non-owned and hired vehicles, with at least the

following limits of liability:

a. Primary Bodily Injury with limits of at least $500,000 per person, $1,000,000 per

occurrence; and

b. Primary Property Damage of at least $250,000 per occurrence; or

c. Combined single limits of $1,000,000 per occurrence.

2. General Liability including coverage for premises, products and completed operations,

independent contractors/vendors, personal injury and contractual obligations with combined

single limits of coverage of at least $5,000,000 per occurrence.

3. Workers Compensation with limits as required by the State of California and Employers

Liability with limits of at least $1,000,000.

4. CONTRACTOR hereby grants to CITY a waiver of any right to subrogation which any

insurer of CONTRACTOR may acquire against the CITY by virtue of the payment of any

loss under such insurance. CONTRACTOR agrees to obtain any endorsement that may be

necessary to affect this waiver of subrogation, but this provision applies regardless of

whether or not the CITY has received a waiver of subrogation endorsement from the insurer.

B. The insurance provided by CONTRACTOR will be primary and non-contributory. Any

insurance or self-insurance maintained by the CITY, its officers, officials, employees, or

volunteers shall be excess of the CONTRACTOR’s insurance and shall not contribute with it.

C. CITY (“City of Torrance”), the Successor Agency to the former Redevelopment Agency of the

City of Torrance, the City Council and each member thereof, members of boards and

commissions, every officer, agent, official, employee and volunteer must be named as additional

insured under the automobile and general liability policies. Coverage can be provided in the

form of an endorsement to the CONTRACTOR’s insurance or applicable policy language.

D. CITY (“City of Torrance”), the Successor Agency to the former Redevelopment Agency of the

City of Torrance, the City Council and each member thereof, members of boards and

commissions, every officer, agent, official, employee and volunteer must be named as additional

insured under the automobile and general liability policies. Coverage can be provided in the

form of an endorsement to the CONTRACTOR’s insurance or applicable policy language.

Page 26: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

26 May 2017

E. CITY (“City of Torrance”), the Successor Agency to the former Redevelopment Agency of the

City of Torrance, the City Council and each member thereof, members of boards and

commissions, every officer, agent, official, employee and volunteer must be named as additional

insured under the automobile and general liability policies. Coverage can be provided in the

form of an endorsement to the CONTRACTOR’s insurance or applicable policy language.

F. CITY (“City of Torrance”), the Successor Agency to the former Redevelopment Agency of the

City of Torrance, the City Council and each member thereof, members of boards and

commissions, every officer, agent, official, employee and volunteer must be named as additional

insured under the automobile and general liability policies. Coverage can be provided in the

form of an endorsement to the CONTRACTOR’s insurance or applicable policy language.

G. CITY (“City of Torrance”), the Successor Agency to the former Redevelopment Agency of the

City of Torrance, the City Council and each member thereof, members of boards and

commissions, every officer, agent, official, employee and volunteer must be named as additional

insured under the automobile and general liability policies. Coverage can be provided in the

form of an endorsement to the CONTRACTOR’s insurance or applicable policy language.

Page 27: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

27 May 2017

Appendix C - Project Specifications

Section C-1 – Design Specifications

The Company shall provide a professionally engineered facility conforming to the requirements

specified herein this RFP document inclusive of: Appendix A Section A-1,the concepts depicted on the

drawings found in Appendix A Section A-2, Appendix A Section A-3 Appendix J – Minimum

Required Technical Specification. The Company shall prepare construction documents, consisting of

drawings, specifications, and equipment submittals, as described later in this section.

General Site Improvements and Site Work

Unless noted otherwise, site work shall meet the minimum requirements specified in the “Standard

Specifications for Public Works Construction, 2012 Edition” (SSPWC).

Structural and Architectural Design Requirements

The following design criteria shall be utilized in preparing construction drawings and specifications for

the utility and well buildings, which will house electrical equipment, pumps, an E/G unit, chemical

storage and feed equipment, and other rooms. The buildings shall comply with the following structural

and architectural requirements:

General

Buildings shall be designed in accordance with the California Building Code, latest

edition. Seismic design parameters shall be established by geotechnical analysis. The

"essential facility" seismic importance factor shall be used for determining seismic

forces for building design and equipment design and anchorage.

Structural Design Requirements

All structural design work shall be prepared under the direct supervision of a registered

professional engineer with a structural emphasis licensed in the State of California. The

Company shall design all structures for a service life of not less than 50 years, in

accordance with the most current applicable codes and standards. The specifications in

this structural section define the general quality of the Facility; variation from any

standards shall be identified by the Company in a PDR and provided to the City. City

acceptance shall be obtained prior to implementing such variations, and shall be

provided at the sole discretion of the City.

All new structures shall be designed in accordance with the conditions and

specifications contained in the following sections.

Design Loads

The structural design loads shall conform to the CBC latest edition unless a generally

accepted specialized code or standard applies to the design of the given structural

component. The CBC shall apply to all general building structures and components not

Page 28: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

28 May 2017

covered by other codes and standards. ACI 318-02/350-01/350R-01: Code Requirements

for Environmental Engineering Concrete Structures and Commentary shall apply to the

design of concrete building structures and their components. The seismic design shall be in

accordance with ACI 350.3-01/350.3R-01: Seismic design of Liquid-Containing Concrete

Structures and Commentary. The seismic zone considered in the structural design shall be

in Zone 4 with site specific data developed by the City’s geotechnical engineer. Steel

structures design shall be supplemented by AISC Allowable Stress Design (ASD) latest

edition or Load and Resistance Factor Design (LRFD) latest edition. CBC shall be the

primary code governing the design of masonry and timber structures.

The recommendations of ACI 350R Environmental Engineering Concrete Structures shall

become requirements for the design of: concrete water-containing structures; buildings

with high humidity; concrete structures exposed to repeated washdown of chemical or

process spills; concrete structures below ground and concrete structures built or placed in

the water.

Load Combinations. The Company shall design new structures for all loads including

but not limited to, dead, live, wind, impact, temperature variations, moving, seismic,

and liquid loads. The design shall also include all equipment and process loads. The

distribution, concentration, and combination of design loads and forces possible,

during construction or operation, shall be included in the design in accordance with the

applicable codes. Where codes and standards have conflicts regarding loads or

combinations, each code shall be applied consistently. The applicable code or standard

that gives the most conservative loading and combination shall be used.

Live Loads. Minimum live loads shall conform to CBC with traffic loads per

AASHTO. The Company shall use minimum live loads for structures that will allow

equipment to be moved to other locations or additional equipment to be added. Floor

live loads in equipment rooms, pump rooms, electrical rooms and areas where

equipment may be moved to various locations shall be not less than those given in

ASCE-7 for light manufacturing: 150 pounds per square foot (psf) uniform load and

2,000 pound concentrated load. Where the loads of specific equipment give higher

design forces and stress for a specific area, the higher loading shall be used. Any given

floor area shall be designed for the loads from the specific equipment used or the 75

psf uniform load and 2,000 pound concentrated load minimums, whichever is greater.

No live load reduction for floors may be used. For heavy equipment greater than five

tons, floor live loads shall be designed for the higher of a 250 psf uniform load or the

load of the specific equipment.

Wind Loads. The wind load requirements for the Facility include meeting the CBC

requirements and other provisions for local codes applicable to this project. CBC wind

load design forces and wind load detailing requirements shall apply for all buildings,

equipment anchorage and hydraulic or water-holding structures.

Seismic Loads. The general seismic requirements for the Facility include meeting the

CBC requirements and other provisions by local codes applicable to the project.

Page 29: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

29 May 2017

Water-containing Structures

The walls of water-containing structures, including tanks and basins, shall be designed for

the following conditions:

Tank or basin at full liquid level without soil backfill.

Empty tank or basin with soil backfill and maximum ground water.

Basin or tank cells in any combination of empty and full.

Increased soil backfill pressures and liquid pressures due to seismic conditions.

Seismic impulsive and convective loading under operating conditions.

Operational level shall include maximum flooded condition unless passive methods are

provided to prevent flooding. Passive methods include; overflow weirs; upstream or

downstream hydraulic controls not dependent on pumps, monitors, electronic controlled

valves, or operators. If passive level controls are present, then the maximum operational

level is defined as the liquid elevation when those controls are in effect.

Water-containing structures shall not be backfilled until the basin passes the water-

tightness testing.

Uplift Loads. Tanks and basins shall be designed for uplift based on the following

safety factors and groundwater conditions:

1. Maximum groundwater levels expected during a 100-year storm and/or 199-

year flood events in the structure area, as a minimum, with basins empty and a

minimum safety factor of 1.2.

2. Groundwater at normal levels with basins empty and a minimum safety factor of

1.5.

3. In all cases side friction shall not be considered as resisting uplift.

Maximum ground water level is the level that can be obtained adjacent to the structure

being evaluated. Drain systems, external to the structure, may be provided to reduce the

maximum ground water level. The reduced level shall only be used in uplift calculation

when the drain system is entirely passive, i.e. relying only on gravity or where

groundwater pressure relief valves installed in the walls and floor are utilized. The reduced

ground water levels from drain systems that rely on pumping, monitoring, or operator

intervention shall not be substituted for the maximum ground water level obtainable if

components of such a drains system did not operate.

Deflections

The Company design shall be in accordance with adopted building codes and standards to

minimize deflections causing adverse functional or aesthetic effects over the life of the

Facility. The live load and total load deflections criteria given in CBC for general loading

combination and specific to the various design material (concrete, steel, timber and such)

shall be the minimum for buildings, building-like structures, and for structural and material

types not specifically covered elsewhere.

Page 30: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

30 May 2017

Concrete Design

Concrete structures, including tanks and buildings, shall be designed and constructed in

accordance with all applicable codes. The concrete mix design shall meet the requirements

of ACI 318-02 and ACI 350

01. Ground water shall be sampled and tested for salinity and sulfate levels. The concrete

mix design shall be adjusted to provide appropriate sulfate resistance per ACI 318-02 and

ACI 350-01.

Structural Steel

Structural steel shall be designed, fabricated and erected according to the latest applicable

CBC Chapter 22. The methods shall be according to either CBC Chapter 22 Division III

for Allowable Stress Design (ASD) or CBC Chapter 22 Division II for Load and

Resistance Factor Design (LRFD).

Connections

As much as practicable, structural connections shall be shop welded and field bolted.

Welds shall be designed and executed in accordance to ANSI/AWS D1.1 (latest edition)

Structural Welding Code – Steel from American Welding Society. Welding procedures

shall be qualified in accordance to ANSI/AWS D1.1 Section 5. Welders, Welding

Operators and Tack Welders shall be currently qualified in accordance to ANSI/AWS

D1.1 Section 5. Welders’ certifications should be made available to City. Welding

inspectors shall have current certification as an AWS Certified Welding Inspector (CWI)

in accordance with AWS QC1 Standard and Guide for Qualification and Certification of

Welding Inspectors.

Bolted connections for steel building, building like structures, and platforms that enclose

for support process equipment, shall be designed as snug tightened connections with the

threads included in the shear plane. The actual bolts provided for the connection shall have

the threads excluded from the shear plane. Bolted connections shall conform to AISC

Specifications for Structural Joints Using ASTM A325 or A490 Bolts (latest edition).

Fabrication and Erection

Steel shall be fabricated and erected according AISC Code of Standard Practice for Steel

Buildings and Bridges (latest edition). Steel fabricators shall be certified according to

AISC Quality Certification Program.

Metal Roof Deck

Design and fabrication of metal roof deck shall be in accordance with the latest

specifications of the Steel Deck Institute. Steel used in the fabrication of deck units shall

conform to the requirements of the AISI “Light Gage Cold-Formed Steel Design Manual.”

Miscellaneous Metals

Miscellaneous metals shall include such items as gratings, metal floor plates, railings and

toe plates, loose lintels and miscellaneous framing and ladders. Materials of construction

shall be selected to provide maximum service life for the expected environmental

Page 31: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

31 May 2017

conditions, including exposure to marine conditions. Any metal item that is submerged

shall be 316 stainless steel unless the corrosivity of the environment requires different.

Any metal item located in a corrosive atmosphere shall be 316 stainless steel, unless noted

otherwise in this Appendix or if aluminum or another material is suitable and complies

with the reference standards. 304 stainless can be used in non-corrosive areas. No

dissimilar metal items what would result in corrosion if connected together shall be used.

Miscellaneous metal shall be fabricated in accordance with the most recent applicable

CBC, OSHA, or ASTM standards. All metal fabrications exposed in the finished

construction, both interior and exterior, whether painted or not, shall be hot-dip galvanized

(heavy duty type coating) except in aluminum only for railings, toe plates and stairways.

Galvanizing of miscellaneous metal after fabrication shall be in conformance with ASTM

A 123 and A 153. Cadmium plating of miscellaneous metals shall be in accordance with

ASTM A 165, Type TS.

All anchor bolts shall be stainless steel type 316 in corrosive areas, stainless steel type 304

in all other areas unless high strength steels are required.

Cages and ladders shall conform to applicable OSHA regulations. Ladder fall prevention

devices shall be DBI/SALA, Inc., flexible cable system using all type 316 stainless steel

parts with a RM-0397 cable without substitution, unless specified herein.

Attachment 3B provides additional Design Requirements for structural features.

Structural concrete materials shall have certification of compliance for meeting ASTM

specifications and test reports certifying that no material contains asbestos, and that all

aggregates are non-reactive or present ASR reactivity. All certifications, submittals, and

reports shall be current within three months of use and shall be identifiable to the materials

supplied for both fine and coarse aggregate.

Precast concrete vaults will be in conformance with ASTM C858.

Mechanical Requirements

The following design criteria shall be utilized in preparing construction drawings and specifications for

equipment, piping, valves, and appurtenances.

General

Facilities shall be designed with the following capabilities and features:

Equipment and materials selected to provide long-term trouble-free operation.

Equipment selected to provide required performance and minimize energy

consumption.

All equipment and systems shall be capable of continuous operation.

All equipment and systems shall be capable of manual and automatic operation.

Provided with control and monitoring safeguards to protect equipment and facilities

from damage.

Provided with adequate access and space for maintenance.

Page 32: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

32 May 2017

Provided with unobstructed access to all equipment.

Provided with protective features to maintain personnel safety.

Provided with equipment and materials to minimize noise impacts to operations

personnel and adjacent property.

Secure from trespass and vandalism, including all pumping units, ancillary equipment,

appurtenances, controls, and instrumentation.

Mechanical Layout

The layout of mechanical facilities shall take into account access space for maintenance,

ease of removal/replacement, personnel safety, and noise control. Confined spaces shall be

avoided where possible. Facilities requiring access shall be located above grade.

Equipment

Equipment arrangements and layouts shall satisfy the requirements of

applicable local, state, and national codes, including state and federal OSHA

requirements. Equipment layouts shall comply with the following

requirements:

Equipment shall be located to provide easy access for service, repair,

removal, and replacement.

Electrical panels (including main control panel) shall face the pumping

units, unless electrical panels are located in a separate room.

Equipment components requiring routine maintenance shall be located at a

convenient height above the floor or be provided with a permanent platform

for access.

Equipment shall be located so that access for repair does not require

removal or disassembly of adjacent equipment.

A minimum of 36 inches of clearance shall be provided adjacent to

mechanical and electrical components that need periodic adjustment or

service (e.g., pump seals, valves, instrumentation, grease fittings, and oil

reservoirs).

Walking areas shall be free of tripping hazards and overhead obstructions

to a minimum height of 7 feet.

Chemical storage facilities shall be located to provide easy access for

chemical delivery trucks.

A minimum of 48-inch clearance shall be provided in front of all electrical

panels, including electrical service panel and MCC.

Piping and Valves

The following pipe materials are to be used:

Page 33: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

33 May 2017

Drain line to sewer: Vitrified clay pipe (extra strength) per ASTM C700 or

PVC pipe per ASTM D 3034.

Overflow drain line: Reinforced concrete pipe per ASTM C 76 or

C 655 or HDPE per ASTM F 894.

Water mains: Diameters 16 inches and less – Class 350 ductile-iron pipe

per ASTM C151. Diameters greater than 16 inches – Either ductile iron or

cement mortar lined and coated steel per requirements of AWWA C200,

C205, C209, C214, and C602.

Water piping at wellheads and BPS: Steel pipe, fusion-bonded epoxy lined

and coated.

Chemical feed piping shall be Schedule 80 chlorinated PVC (CPVC) per

ASTM D 1784 and F 441, or PE ASTM 100RC.

Piping and valves shall be located to provide easy access for service, repair,

removal, and replacement. Piping and valve layouts shall comply with the

following requirements:

Piping shall be provided with strategically placed break-out joints, such as

flexible couplings or grooved-end couplings, to permit the easy removal of

pumps, valves, meters, etc.

Each flowmeter shall be provided with the appropriate length of straight

piping on the upstream and downstream sides of the meter. As a minimum,

provide five pipe diameters of straight piping upstream and two pipe

diameters downstream of each flowmeter.

Provide conveniently located hose bibbs adjacent to areas or equipment

requiring wash down, such as the pump room, chemical room, and

chemical delivery area.

Pipe supports shall be located to eliminate transfer of pipe loads to

equipment, to minimize piping removal when removing connected valves

and appurtenances, and to minimize pipe stresses.

Provide a drain line with funnel strainer adjacent to the chlorine residual

analyzer and ammonia analyzer.

Appurtenances

Appurtenances shall be located to provide easy access for service, repair, removal, and

replacement.

Flowmeters

Flowmeters shall be propeller-type. Meter tubes shall be constructed of carbon

steel with flanged end connections and be suitable for a working pressure of

Page 34: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

34 May 2017

150 psi. Each flowmeter shall be equipped with a local readout/totalizer and a

remote signal transmitter (4 to 20 milliampere [mA]). The meter shall display

the flow rate in gpm and total flow in acre-feet.

Pressure Gauges

Pressure gauges shall be liquid filled, weatherproof, and provided with 4-1/2-

inch dials, 1/2-inch threaded connections, epoxy-coated aluminum cases with

safety glass windows, and Type 316 stainless steel needle valves. Pressure

gauge range shall be selected such that the normal operating pressure is near

the middle of the range. Pressure gauge accuracy shall be ±1 percent.

Pressure Transmitters

Pressure transmitters shall be electronic two-wire devices with adjustable span,

integral display scaled in engineering units, solid-state circuitry, and 4- to 20-

mA output. Process connection shall be 1/2-inch NPT and shall be provided

with Type 316 stainless steel isolation ball valve. Transmitter housing shall be

epoxy-coated low copper aluminum alloy and rated NEMA 4X.

Pipe Supports

All piping and valves shall be adequately supported. Pipe supports shall consist

of cast-iron or fabricated steel saddles with adjustable stanchions and fully

welded floor mounting plates. Pipe supports shall be provided with hot-dipped

galvanized coating and painted to match adjacent piping.

Building Mechanical

Mechanical equipment shall comply with the following requirements:

Heating, Ventilation, and Air Conditioning (HVAC)

HVAC system design shall be in accordance with the guidelines and standards

of the American Society of Heating, Refrigerating and Air Conditioning

Engineers (ASHRAE) and the Air Movement Control Association (AMCA).

HVAC system components, including louvers, ductwork, registers, ventilators,

and air conditioners, shall be sized and selected to provide the required

performance and minimize room noise levels. Noise generated by HVAC

system components shall not exceed levels recommended for light

industrial/commercial occupancy. HVAC ductwork shall not be routed over

electrical equipment unless an appropriate pan and drain system is provided per

ASHRAE guidelines and standards.

Wall Louvers

Louvers shall be supply or exhaust with a blade width of 8 inches and sized to

fit the wall opening. Louvers shall be fixed, adjustable, automatic gravity, or

acoustical type depending upon the application. Louvers shall be constructed of

Page 35: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

35 May 2017

aluminum Alloy 6063-T5 and shall be provided with 18 by 14 mesh bronze

insect screens.

Acoustical louver free field noise reduction shall be:

Hz 63 125 25 500 1K 2K 4K 8K

dB 11 13 17 18 19 20 18 15

Ventilators

Exhaust ventilators shall be sized to remove heat generated by the housed

equipment operating at full capacity. A maximum temperature differential of

10°F above the outdoor ambient temperature shall be used when determining

the required airflow for the ventilators. Airflow determined for heat removal

shall not be less than that required to provide 12 room volume air changes per

hour.

Roof exhaust ventilators shall be low profile, centrifugal, belt-driven type, with

aluminum hoods. A single-stage (or two-stage if two-speed ventilator) cooling

thermostat shall be provided for automatic operation.

Roof Scuttles

Roof scuttles shall be constructed of galvanized steel with single door leaf.

Door leaf shall be provided with automatic hold-open arm, padlockable latch,

and compression springs sized for easy opening and to retard downward

motion when closing.

Floor and Roof Drains

Floor drains shall be cast iron with 8-inch-diameter (minimum) bronze strainers

and p-traps, or channel drains with cast-iron channel grates and p-traps, where

appropriate.

Roof and floor drains shall be provided with clean-outs.

Utility Building Fire Protection

Due to the quantity of hazardous materials in the Chemical Room, the Utility

Building is classified as H-Occupancy. This will require sprinklers for fire

protection in at least the Chemical Room. Coordinate with the City Fire

Prevention Department for possible alternatives for other rooms.

Electrical Requirements

General

Electrical design and components shall be in strict accordance with all applicable national,

state, and local codes (e.g., NEC, CEC, NEMA, and IEEE) and SCE requirements.

Page 36: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

36 May 2017

Electrical equipment and components shall be sized for existing conditions and loads.

These items may include main switchboard, generator, automatic transfer switch, VFDs,

reduced voltage solid-state starters, transformers, lighting panels, conduit, and conductors.

Electrical equipment specifications shall include requirements for performance of an arc

flash hazard study to determine potential arc flash incident energies, arc flash boundaries,

shock hazard boundaries, and required personal protective equipment (PPE) for all

energized electrical equipment and arc flash and shock hazard warning labels. The study

shall include all electrical equipment from the normal power source or sources to and

including all electrical panels with voltage greater than 24 volts. Electrical equipment shall

be provided with warning labels in accordance with study recommendations.

Utility Power

Three-phase, 277/480-volt, 4-wire power is required from SCE. Electrical plans shall

include all SCE-related facilities required to be constructed, such as conduit and pull boxes

for primary and secondary conductors, transformer pad, electrical service panel, grounding

system(s), and protective guard posts. All electrical service equipment, materials, and

components shall conform to SCE requirements and comply with the following:

Full height (90 inches high), 277/480-volt, 3-phase, 4 wire main switchboard in a

NEMA 1A, gasketed enclosure.

Main disconnect shall be a molded case circuit breaker with inverse time and

instantaneous tripping characteristics and ground fault protection system. Main circuit

breaker shall have a minimum interrupting capacity matching the main switchboard l

rating. Circuit breaker shall be 100 percent rated, capable of carrying continuous loads

to 100 percent of its rating.

Transient Voltage Surge Suppressor (TVSS)

A TVSS shall be provided on the load side of the main circuit breaker and shall be

mounted in the main switchboard. The TVSS shall be provided with an integral disconnect

switch which has been tested to the surge current rating of the TVSS. The TVSS shall be

UL tested and labeled as a complete system to a symmetrical fault current rating of 200

KA, minimum. The TVSS shall provide protection for L-L and L-G modes, and each

mode shall be fused and incorporate a thermal cutout device. The minimum surge current

capability of the TVSS shall be 150 KA per mode and 300 KA per phase. The TVSS shall

be provided with status indicating lights, surge counter, and dry contacts for remote

monitoring.

Emergency Generator

The emergency generator shall comply with the following requirements:

Select the unit to start and run two booster pumps, Well No. 10, air conditioning, and

miscellaneous loads for lighting and SCADA.

Particulate filter to comply with South Coast Air Quality Maintenance Board

(SCAQMB) requirements for a generator located within 500 feet from a school.

Page 37: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

37 May 2017

Maximum voltage dip shall be 20 percent when starting and running all of the loads.

Emissions shall comply with SCAQMD requirements.

If the engine fuel pump cannot provide adequate pump lift to supply the engine from the

fuel tank, provide a day tank.

Diesel Fuel Tank

The aboveground diesel fuel tank shall comply with the following requirements:

Provide storage capacity for 48 hours of run time at full load.

High/low level monitoring and leakage alarms.

Steel primary tank.

Reinforced concrete exterior.

Concrete slab overfill containment.

Internal bracing support legs.

Level indicator.

Emergency vent.

Access ladder.

Motor Control

All motor control shall include the following:

Motor Controllers (Motor Starters)

Equipment with motor horsepower ratings of 40 or less shall be provided with

full voltage combination starters. Equipment with motor horsepower ratings

greater than 40 shall be provided with solid-state reduced voltage starters or

VFDs.

Each starter or VFD shall be equipped with control relays, timers, selector

switches, indicating lights, elapsed time meter, and auxiliary contacts as

required to provide manual and automatic equipment operation. As a

minimum, each starter or VFD shall be provided with manual stop momentary

pushbutton, manual start momentary push button, a hand-off-auto (HOA)

switch, elapsed time meter, and the following status and alarm lights. Status

lights shall be provided for "Control Power On" and "Run." Alarm lights shall

be provided for "Motor Overload" and "Phase Loss." A warning light shall be

provided for "Motor High Temperature" (only for motors greater than 50

horsepower), “high/low pressure fail,” “solid-state starter fail.” Alarm

conditions shall open the respective motor starter and activate a corresponding

alarm light, which shall be latched "on." Alarm conditions shall require a

manual reset to clear. Warning lights shall be latched "on" and require a

manual reset to deactivate the light but shall not open the motor starter. All

status and alarm lights shall be push-to-test type and shall be heavy duty, oil

tight (NEMA 13). All control power shall be 120 volts, single phase.

Page 38: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

38 May 2017

Reduced Voltage Solid-State Starters

Reduced voltage solid-state starters shall have built-in overload protection

and built-in run bypass contactor.

The starters shall have soft-start and soft- stop capabilities and be rated for

3-phase 1.15 service motor factor.

The starter shall have a digital interface module with LCD display and

keypad. Monitoring shall allow accessing real time process and diagnostic

data. Data shall be viewable at the module or through communications

network.

VFDs

VFD shall comply with the following requirements:

VFD shall be as manufactured by Cuttler Hammer or ABB, no equal.

Controller shall consist of an 18-pulse minimum converter section.

Controller shall be pulse width modulated design.

Controller shall be voltage/variable frequency (constant volts per hertz)

input power surge protection.

115 percent overload rating for 100 seconds, 100 percent rated current

continuous.

Power loss ride through: Controller shall be capable of a minimum three-

cycle power loss ride-through without fault activation.

Voltage dip ride through: controller shall be capable of sustaining

continued operation with a 40 percent dip in nominal voltage. Output may

decline only if current limit rating controller is exceeded.

Separately adjustable acceleration and deceleration rates.

Comprehensive microprocessor-based digital diagnostic system that

monitors its own control functions and displays faults and operating

conditions in English without the use of codes.

Minimum controller efficiency shall be 96 percent at 100 percent speed and

100 percent torque, 88 percent at 50 percent speed and 25 percent torque

based on nominal 1,800-rpm motor with load horsepower to vary as cube

of speed.

The controller shall include protective circuitry that initiates as orderly

shutdown of the inverter without component failure.

Integral capability to be able to communicate with PLC EMI/RFI filters.

Meet requirements outlined in the current edition of IEEE 519 for each

individual VFD and total harmonic distortion. Total demand distortion

(TDD) as defined by IEEE 519, caused by the simultaneous operation of

the VFDs shall not exceed 5 percent at the main switchboard while

Page 39: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

39 May 2017

operating from the utility source or 5 percent while operation from the

standby generator.

Resistance Temperature Detector (RTD) Temperature Monitoring and Alarm System

The alarm system shall comply with the following requirements:

Microprocessor-based motor protection system.

Monitor electrical current and temperature sensors, giving commands to the

motor starter and other devices under its control, and communication by

alphanumeric display with the operator.

Capable of being connected to motor winding and bearing RTDs.

Provide digital display and motor protection for stator and motor bearings.

Motors

All electric motors shall be high efficiency and shall be provided with a minimum service

factor of 1.15. Motor horsepower, not including motor service factor, shall equal or exceed

the horsepower requirements of the driven equipment over its full range of operation.

Motors shall comply with the following requirements:

Motors shall be nameplate rated, 3 phase, 60 hertz, 460 volts.

Motors for VFDs shall have VFD rating.

Motors for wells shall have non-reverse ratchets.

Motors shall have a no load speed of 1,800 rpm or less.

Motors greater than 50 hp shall be equipped with 120-volt thermal sensors, one for

each phase, affixed to or embedded in the motor windings, set to open the motor

control circuit at 135°C. Thermal sensor leads shall terminate in the motor terminal

box.

Motors greater than 50 hp shall have a 120-volt heating elements.

Motors 200 hp and larger shall have 120-ohm nickel or 100-ohm platinum resistance

temperature detectors (RTDs), with two RTDs in each winding and one RTD in each

bearing for a total of eight. Design the RTDs to function in two temperature steps: the

first to indicate an alarm and the second to stop the motor.

All motors shall be premium efficiency in accordance with NEMA Standards. Motors

shall be sized to a maximum of 95% of the motor rating used at 100 percent of driven

load rating.

Conduit and Conductors

Conduit shall be of adequate size to carry conductors required for ultimate electrical loads.

Page 40: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

40 May 2017

Conduit

Exposed conduit shall be minimum 3/4 inch.

Below-grade conduit shall be PVC, Schedule 40, UL listed, and sunlight

resistant.

Above-grade conduit shall be galvanized rigid metal steel conduit.

Conduit in corrosive areas shall be PVC-coated galvanized rigid steel

conduit.

Below-grade conduit shall be installed with a minimum of 24-inch cover

and shall be encased in red-colored concrete.

Transition from below-grade PVC conduit to above-grade hot-dipped

galvanized conduit shall be made at the horizontal leg of the below-grade

conduit bend.

Above-grade conduit shall be run exposed.

Connection from junction box or conduit to motor or equipment terminal

box shall be with PVC-coated liquid-tight flexible metallic conduit.

Conductors

Conductors 250 KCMIL or smaller shall be stranded copper with 75°C

THWN insulation. Conductors larger than 250 KCMIL shall be stranded

copper with 75°C XHHW insulation.

Minimum power conductor size shall be No. 12 AWG. Minimum control

conductor size shall be No. 14 AWG.

Grounding

All grounding shall be in accordance with the NEC, latest edition. Under no circumstances

shall electrical grounding systems utilize metallic piping.

Lighting and Receptacles

Fluorescent lights shall be provided in each room/building.

Vapor-proof fluorescent lights shall be installed in pump room.

Corrosive resistant fluorescent lights shall be installed in corrosive areas.

Security and area lighting shall be provided.

Convenience receptacles of the ground fault interrupter type shall be provided

throughout each room/building.

Security Requirements

Each project facility will be provided with a security system, which will be connected to

the PLC for alarming City security personnel via the City's telemetry system. For the wells,

Page 41: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

41 May 2017

the minimum security system components will include limit switches to signal an

"intrusion alarm" to the PLC. The security system shall have the following requirements:

Site access gate control.

Site access building exterior doors.

Building interior motion detection.

Closed circuit television (CCTV).

The CCTV system shall be able to be viewed via network.

Additional security system components shall include outdoor security cameras and motion

detectors, card readers for gate operators, card readers for building doors, and motion

detectors inside the buildings. CCTV and card readers shall be consistent with existing

City systems. Construction drawings shall show conduit and junction boxes between the

remote terminal unit (RTU) and/or security system cabinet (if applicable) and the

respective device.

Control Software, Video Software, and Video Storage Requirements

Provide AMAG Symmetry Security Management Software Pro Version 8.0,

with the server AMAG network video record (NVR) software, camera

integration license and concurrent AMAG web client licenses.

Secure access to control software based on assigned privileges. To be

compatible with Microsoft Active Directory security and group access

control.

Secure database of information regarding access key distribution and

logging of access information. Must be able to generate reports from

database.

Video viewing must be delivered directly from the video storage device to

the requesting client. IT must not be rerouted back to the AMAG control

server before distribution to the requestor.

Secure access to cameras and stored video.

Must have ability to manage and add cameras, access control devices

(doors, gates) and other IP security devices.

Set retention requirements for stored video from a designated group of

devices.

Ability to add storage as video data grows.

Ability to add storage devices at various locations with control from a

centralized control software server.

Ability to search video by date and time, and to export portions to disk or

mobile media such as DVD or flash memory.

Ability to display a single or multiple cameras on a computer screen or

centralized large screen display.

Page 42: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

42 May 2017

Browser and local client based client access to control software functions,

video software, and stored video.

Provide all hardware and software specification sheets, including annual

maintenance/support costs, and estimated useful life of hardware.

Technical Standards

Provide the following:

Cisco wireless and network devices.

Dell computer and servers.

Windows operating system.

Microsoft SQL MSDE database installed on the AMAG control server.

Internet Explorer Browser.

AMAG Symmetry Security Management Software.

Fluke DTX 1800 cable analyzer tester.

Fluke DTX 1800 cable analyzer Linkware PC software.

Page 43: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

43 May 2017

Minimum Specifications

Camera PTZ (Outdoor) Panasonic WV-NW964

Outdoor camera casing/element resistant, IP66 ingress protection rating

Mounting accessories

Pan, Tilt, Zoom (PTZ), Sweep, and automatic tracking by remote control and/or by setting

Color image

30 fps @ VGA resolution

Auto focus

Day/Night/Low light capabilities:

o Minimum illumination-automatic switching to black and white while depending on natural illumination

o Color: 0.5 lux

o Color w/enhancement 0.02 lux

o Black and white 0.04 lux

o Black and white w/enhancement 0.0012 lux

Motion detection

Auto image stabilization

30x optical zoom/10x electronic

Scene change alarm

100 base-TX (RJ45)

UPS not required on cameras

Page 44: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

44 May 2017

Camera Fixed (Outdoor) Panasonic WV-NW502S

Outdoor camera casing/element resistant, IP66 ingress protection rating

Mounting accessories

Fixed lens

Color image

30 fps @ VGA resolution

Auto focus

Day/Night/Low light capabilities:

o Minimum illumination-automatic switching to black and white while depending on natural illumination

o Color: 1.5 lux

o Color w/enhancement 0.046 lux

o Black and white 0.16 lux

o Black and white w/enhancement 0.005 lux

Motion detection

Auto image stabilization

2x optical zoom/4x electronic

Scene change alarm

100 base-TX (RJ45)

UPS not required on cameras

Page 45: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

45 May 2017

Camera Fixed (Indoor) Panasonic WV-NF302

Indoor casing to prevent tampering

Mounting accessories

Fixed lens

Color image

30 fps @ VGA resolution

Auto focus

Day/Night/Low light capabilities:

o Minimum illumination

o Color: 1.5 lux

o Color w/enhancement 0.046 lux

o Black and white 0.16 lux

o Black and white w/enhancement 0.005 lux

Motion detection

Auto image stabilization

3.6x optical zoom/4x electronic

100 base-TX (RJ45)

UPS not required on cameras

Page 46: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

46 May 2017

Centrally managed security system with distributed network based

video recording system AMAG Symmetry Security Management Software-Video modules

and camera device licensing.

AMAG Symmetry Network Video recording software.

Concurrent AMAG web client licenses.

Compatible with the City’s existing AMAG security control software and Microsoft SQL MSDE database. The City will provide Microsoft SQL licensing as needed.

Capable of recording at 15 fps minimum.

Ability to add cameras and data storage for additional security camera sites.

The system must integrate seamlessly with the cameras described herein.

The system must record all video feeds in a standard digital file format for playback compatibility on any desktop or server computer without any special proprietary video player software required.

Ability to save video file(s) onto portable media (CD-R, DVD-R, flash drive).

The system must be securely accessible both locally and remotely via the City’s network to search and play back video files and perform administrative functions. No client software install required for web clients.

Ability to manage all aspects of camera controls and recording.

Ability to place video storage device either locally or centrally based on configured storage destination.

Ability to view multiple cameras at a time from both live feed and recorded video.

Page 47: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

47 May 2017

Control Room NVR server and storage Dell Poweredge R330 rack server with 5 year warranty.

Intel Xeon 12403.5GHz, 8M cache, turbo.

16.4GB (2x8GB), UDIMM.

Two 200 GB SSD hard drive (Raid 1).

PERC H330/H730 (SAS/SATA controller) 2 hard drives Raid 1.

PERC H330 RAID Controller.

PERCH830 Raid Adapter for external MD1420.

On-board dual Gigabit Ethernet.

DVD-ROM drive.

Power supply redundant 400W.

Sliding ready rails with cable management arm.

Windows Server 2012 R2

MD1420 power vault with 24 x 2Tb 7.2K rpm NLSAS 12 Gbps 2.5-inch hotplug hard drives, rapid rails for square hole racks.

Standard power cords for all power supplies, NEMA 5-15p to C13.

5 years ProSupport 4HR 7x24 onsite: Non mission critical for all equipment.

Must record and store video from all cameras for thirteen (13) months of video running 24 hours/day, 7 days/week recording when activated by motion detection. No file archive is required.

Page 48: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

48 May 2017

Control Room Terminal/Web Server Dell R330 rack server.

Intel Xeon 1240,3.5GHz, 8M cache, turbo.

16.4GB (2x8GB), UDIMM.

WindowsServer 2012 R2.

Windows terminal server license.

Six terminal server Microsoft terminal server client access licenses.

Two 200 GB SSD hard drive (Raid 1).

PERC H330/H730 (SAS/SATA controller) 2 hard drives Raid 1.

PERC H330 RAID Controller

PERCH830 Raid Adapter for external MD1420.

On-board dual Gigabit Ethernet.

DVD-ROM drive.

Power supply redundant 400W.

Standard power cords for all power supplies, NEMA 5-15p to C13.

Sliding ready rails with cable management arm.

Five years ProSupport 4HR 7x24 onsite: Non mission critical for all equipment.

SCADA, Controls, and Telemetry Requirements

Facility SCADA System Overview

Facilities and wells shall be designed to allow for automatic operation with remote

monitoring and supervision.

Each well will be controlled by a local PLC. All PLCs shall be tied together with the

SCADA workstations via a fiber-optic network. Controls of existing Well No. 9 will be

modified to interface it to the new facility via fiber-optic cable.

SCADA system shall be Wonderware.

Provisions shall be made allowing the City’s existing SCADA system to access the

NTWFP plant SCADA via radio, which shall be compatible with City’s existing radio

system (spread spectrum, serial interface) project SCADA via fiber-optic network, new

and existing. The fiber-optic cable demarcation point between the plant site and existing

networks shall be a fiber-optic cable pull box near the property line. The location of the

Page 49: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

49 May 2017

demarcation pull box needs to be coordinated with the City. Modifications to the existing

City SCADA system are included in this the current project. See Appendix J of Volume

III-A for the pre-negotiated Scope-of-Work and fee to be incorporated in to the DB effort.

A design objective is to have all PLCs by Allen-Bradley Logix platform (ControlLogix

and/or CompactLogix).

Controls

Controls for manual and automatic equipment operation will be located in the MCC

compartment containing switchgear for the respective equipment. Minimum requirements

for equipment control are described herein under the section entitled "MCC."

Pumping units operating in the "auto" mode will receive the start/stop and speed signals

from the plant control system. PLCs will transmit alarm and status signals from remote

locations to the treatment plant SCADA and will receive control signals and set points for

pumping unit operation. All alarm, status, and control signal wires will be terminated on a

terminal block within the instrument control panel. If the PLC fails, the only mode of

pump operation will be manual via the pump HOA switch.

PLC

PLCs will receive all alarm and status signals and all analog signals from field

instrumentation. In addition, PLCs will provide output signals to the respective MCC

pump starter which will start/stop pumping units and cause pumping unit shutdown under

various alarm conditions (e.g., low flow rate, high discharge pressure, and low discharge

pressure).

Page 50: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

50 May 2017

Preferred Manufacturers

The following manufacturers have been preapproved by the City. Any proposed alternatives are subject

to City approval:

Equipment Approved Manufacturer

Well or booster pump Flowserve, Goulds, Peerless

Pump motor US (no equals)

Propeller flowmeter McCrometer (no equals)

Resilient wedge gate valve Mueller

Butterfly valve Mueller

Air/vacuum valve APCO, Crispin, Val-Matic

Wafer check valve K-F Industries

VFD ABB, Cutler-Hammer

MCC Allen Bradley, Cutler-Hammer, General Electric, Siemens

PLC Allen Bradley (no equals)

E/G unit Caterpillar, Cummins-Onan

Chemical feed pump Prominent, Pulsafeeder

Chlorine residual analyzer Hach (no equals)

Ammonia residual analyzer Hach (no equals)

Signage

The Company shall include in its design, the location and types of signage including, but not limited to,

entrance sign to the facility, descriptive signs for each building and process, chemical classification and

safety signs, plus any required OSHA safety signs, and pipe labeling.

Fire Alarm System

The Company shall provide a plant-wide fire detection and alarm system, with audible as well as visual

alarm signals, conforming to the requirements of the local fire marshall, NFPA, and Factory Mutual

requirements. Fire extinguishers rated for A, B and C type fires shall be located in all buildings. System

shall be connected to SCADA and through the SCADA System, be capable of calling the City’s security

service.

Geotechnical Analysis and Recommendation Requirements

The Company shall provide a geotechnical engineering report, which provides specific

recommendations for the design and construction of the structures, pipelines, and other facilities

proposed by the Company. The geotechnical report shall address the subjects outlined in the

Preliminary Geotechnical Report (Appendix 9), and may utilize data taken from the preliminary report.

The Geotechnical Report shall also utilize data obtained from supplementary site exploration and testing

performed by the Company, if such data are needed.

Page 51: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

51 May 2017

The recommendations of the Geotechnical Report shall be used in the design of grading, foundations,

backfill, retaining walls, and subgrade remediation. Settlement calculations from the Geotechnical

Report shall be used when setting the hydraulic profile and in the design of structures and pipelines.

The Geotechnical Report shall address specifically how the risk of seismically induced settlement is to

be mitigated. The Report shall be signed by a California licensed geotechnical engineer, and shall be

submitted to the City for its review.

Construction Documents (Plans, Specifications, and Equipment Submittals)

The Company shall generate and maintain lists showing the status of the documents. The Company

shall generate a drawing list, specification list, and an equipment list and submit to the City monthly.

Six copies of the construction documents shall be submitted to the City, signed and sealed by a

registered engineer in the state of California, for review of compliance with codes, regulations and

conformance to the contract. The City will review the documents within 30 working days after receipt.

Comments, if any, will be provided to the Company. The lack of any comments by the City does not

relieve the Company of responsibility for accuracy and content.

Drawings shall be prepared full-size (22” x 34”), but shall be submitted as half-size (11” x 17”), unless

full-size is needed for legibility. Drawings shall be prepared using scales that are typical for the type of

drawing that is provided. Plan, specifications and equipment submittals shall be submitted to the City at

50% design, 95% design, released for construction stages and record documents. The released for

construction and record documents shall be signed and sealed by the Engineer of Record.

No construction activities shall be performed prior to the concurrence and approval that the associated

plan, specifications, and equipment submittals have been released for construction.

Design Quality Control and Quality Assurance Requirements

Company shall submit, no later than 30 days after award of contract, six (6) copies of a plan for design

QA/QC. Minimum requirements are:

Who is the QA/QC manager for the project

Provide a log showing review and approval process

Provide log and description of how design revisions, RFIs, and Shop Drawings are to be

tracked, reviewed, and distributed

Include in the process City review and approval of drawings, drawing revisions, and

RFIs.

Every submittal to the City shall be accompanied by the QC checklists compiled during

the Company’s review process.

Equipment Submittal Document

The Company shall submit to the City, drawings, diagrams, schematics of all significant equipment

associated with the operation of the project. Those drawings will be reviewed by the City for

conformance with the contract. The submittal of these drawings shall precede any submittals of

construction documents for plan check. The City will review all equipment submittal documents within

10 working days, and submit comments, if any, related to the drawings. At the completion of

construction the Company shall submit to the City, complete set of operations and maintenance manuals

Page 52: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

52 May 2017

which shall include, as a minimum, all certified equipment drawings, descriptive information on the

equipment’s operation, maintenance schedules, maintenance instructions and parts list.

Page 53: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

53 May 2017

Section C-2 – Construction Specifications

Site Security

The Company shall secure the site and the Company’s equipment against loss from theft, weather or

vandalism. Company shall also provide safety protection at open excavations as required by local, state,

or federal law and good industrial practice. Company shall furnish, install, and maintain all fencing and

gates necessary for the safe execution of the work.

Construction QA/QC

The Company is responsible for providing a Quality Assurance/Quality Control (QA/QC) Program for

all quality control testing and inspections necessary for completion of the work. As part of the QA/QC

Program, the Company shall submit a QA/QC Plan, no later than 60 days after award of contract, which

establishes the protocols to be used to maintain an effective construction quality control program. The

QA/QC Plan shall identify the personnel, their qualifications, inspection procedures and documentation,

sampling and test procedures, frequency and number of tests, laboratory and field test standards, and

materials requiring testing that will be used to ensure an end product that complies with the approved

design and specifications. The QA/QC Program shall address all construction and manufacturing

operations, both on-site and off-site, and shall be keyed to the proposed construction sequence. The

QA/QC Program shall be submitted for review and the Company shall modify the QA/QC Program as

necessary to address the comments and requests of the City. The City will provide comments to the

Contractor within 30 days. The City shall be notified of the inspection and testing schedule in advance

and reserves the right to perform inspections and verification testing in addition to the Company’s

QA/QC Program, to confirm contract compliance requirements. The Company shall thoroughly test

and inspect materials, equipment, and work in order to assure that the requirements of the approved

design and specifications are met. The Company shall remove and replace all materials, equipment, and

work which are defective or which do not meet the requirements of the approved design and

specifications.

Work Area

Company shall clearly identify in the field the extent of the work area and provide signage. Company

shall maintain all activities within the work area, staging area, and access corridors as identified.

Survey

Company shall perform a topographic survey of both the Southern California Edison (SCE) and City-

owned sites adjacent to the Yukon Elementary School

Grading Plan

Company shall perform both a construction and final grading plan, as required by SCE lease for use of

SCE right-of-way.

Existing Utilities

The utilities shown on the drawings have been located with the best available recorded information.

Generally, utility locations have not been field surveyed. The Company shall call the local utility

service alert agency and coordinate field locations of all facilities. One exception is the sewer pipeline

and associated manholes along the south property line. Additionally, the Company shall pothole all

Page 54: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

54 May 2017

buried utilities prior to excavating trenches in the area of the utility. Any and all utilities damaged

during construction shall be immediately repaired at the Company’s expense.

Compaction

The term relative compaction as used in these specifications is defined as the ratio of in-place field dry

density to maximum laboratory dry density of the soil expressed as a percentage. The laboratory

maximum dry density shall be determined in accordance with ASTM D1557. The in-place field dry

density shall be determined in accordance with ASTM D1556 or ASTM D2922.

Corrosion Protection and Cathodic Protection Systems

Level of corrosion protection is to be determined by the Company, to provide the required service life in

the environment to which the piping and equipment will be exposed. As a minimum, conform to

manufacturer’s recommendations for service lives specified as follows:

50 years for concrete structures

50 years for buried pipelines

50 years for above-grade structures, with periodic recoating every 10 years

50 years for equipment cabinets, shrouds and housings, with periodic recoating every 20

years

10 years for the wearing surfaces of pumps and other mechanical equipment

Construction Staking

The Company shall furnish and set all construction stakes, points, nails, and marks to establish the lines

and grades required for the completion of the work. The Company may substitute laser control for

grading, trenching and pipe placement staking. All survey work shall be conducted under the direct

supervision of a CA licensed land surveyor.

Trench and Excavation Shoring Plan

The Company shall submit to the City in accordance with Section 6500 of the Labor Code of the State

of California, in advance of excavation, a detailed plan for excavations 5 feet or more in depth showing

the design of shoring, bracing, sloping, or other provisions to be made for worker protection from the

hazard of caving ground during the excavation of such excavations. This plan shall also show how

shoring protects existing structures influenced by the adjacent excavation. The plan shall be prepared by

a California-registered Civil or Structural Engineer.

Dewatering Plan

If required by site conditions, the Company shall develop a dewatering plan that will meet NPDES

discharge requirements. The Company shall also develop a SWPPP and obtain approval from the City.

Materials On-Site

The Company may use excavated materials such as stone, gravel, sand, or other materials within the

area of construction, if such materials meet the requirements of the geotechnical recommendations.

Page 55: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

55 May 2017

As-Built Drawings

The Company shall prepare and submit as-built drawings showing all installed equipment and facilities

as designed and constructed. All drawings shall be stamped by a California-registered Professional

Engineer (PE). The horizontal and vertical locations of all the constructed facilities shall be included.

All as-builts, upon completion, shall be submitted to the City both on Mylar and in electronic (CD)

format, AutoCad’s latest version.

Equipment Startup and Testing

Equipment testing and startup are required for satisfactory completion of the construction phase of the

contract and therefore shall be completed prior to operation of the facility.

a. Definitions. For purposes of equipment startup and testing, the following

definitions shall apply:

Manufacturer’s Representative. Employee of manufacturer who is factory

trained and knowledgeable in the technical aspects of the products and

systems.

Functional Testing. Tests necessary to demonstrate that the installed

equipment and systems function as specified and operate in the manner

intended.

Startup Period. Startup of any portion of the entire facility will be considered

complete when the facility or designated portion has properly operated

without interruption. This period is in addition to specified functional or

performance testing and training.

Acceptance Testing. The operation of the entire facility to demonstrate the

successful operation and integration of all the elements, including but not

limited to: wastewater treatment, generator set, solids handling, pump

stations, instrumentation and control system and PRV control valves. This is

covered in Section C-3.

b. Equipment Testing:

The Company shall furnish the services of a manufacturer’s representative for

each piece of major equipment, to inspect, to check, and to adjust, if

necessary, the equipment installation. In each case, the Company shall

arrange to have the manufacturer’s representative revisit the jobsite as often

as necessary until any and all trouble is corrected and the equipment

installation and operation is acceptable to the manufacturer’s representative.

The Company shall furnish the manufacturer’s representative a written report,

certifying that the equipment has been properly installed and lubricated, is in

accurate alignment, is free from any undue stress imposed by connecting

piping or anchor bolts, and has been operated satisfactorily under full-load

conditions.

Page 56: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

56 May 2017

The Company shall schedule all equipment testing. The manufacturer’s

representative and the operating personnel and the owner’s representative will

witness equipment testing.

c. Functional Testing: Functional (or run) testing shall be required for meters,

generator sets, pumps, and equipment control systems. The Company shall

furnish the services of a manufacturer’s representative to assist with the test.

Testing shall include checking for proper rotation, alignment, speed, excessive

vibration, quiet operation, and full capability of all required functions. The

Company shall perform initial equipment and system adjustment and calibrations

in the presence and with the assistance of the manufacturer’s representative. Prior

to treatment plant operational testing, unit processes shall be tested using plain

water.

d. Startup: The Company shall conduct, with the assistance of the manufacturer’s

representative, startup and field tests of equipment, systems, and subsystems.

e. Other construction testing shall include, but is not limited to:

Verify instrument signals are received properly at wire terminal cabinet

by manual stimulation.

Verify PLC ladder logic is simulated and proven to respond as designated

(e.g., alarm failure conditions and trip signals).

Verify that simulated signals, including alarms, are received and properly

indicated at the Operations Control Station.

Verify that software displays the screens for each of the unit processes

and for the overall treatment process.

f. Acceptance Testing: After all functional and equipment tests have been

performed and all equipment has successfully met startup requirements, the

facility shall be operated as a complete system for commissioning, to demonstrate

overall plant performance for the performance test plan, as described in Section

C.3.

Page 57: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

57 May 2017

Section C-3 – Operational Testing and Training

3.1 Acceptance Test Procedure

The acceptance test shall demonstrate the ability of the Facility to reliable produce and distribute a

maximum of 9,000 gpm of potable water to the City’s distribution system.

The Company shall prepare an acceptance test plan and protocol which shall define the procedures to be

used.

The specific measurements that will be made, including identification of permanent and

temporary measurement devices.

Calibration procedures for measuring devices.

Redundancy of any measuring device to demonstrate accuracy.

Organization of the testing team, including responsibilities.

The testing schedule.

Operations and maintenance schedule during the test period and first 90 days of operation..

Specific detailed sampling protocols to be used in conducting the acceptance test.

The acceptance test shall not be conducted until the acceptance test plan is approved by the City and

regulatory agencies, and authorization is received from the City.

All labor, materials, and equipment necessary to perform the test, shall be provided by the Company.

During the acceptance test, the Company will operate, and be responsible for, all costs for all systems

under normal operating conditions, including but not limited to, routine equipment operation,

maintenance services, and chemical usage. Electricity will be paid by the City. The City will also

provide certified plant operators who will work under the direction of the Company for 90 days. At least

one operator will be provided for eight hours per day, during the acceptance test period (5 continuous

days).

The acceptance test shall also demonstrate the Plant’s ability to operate on the emergency generator, in

the event of total plant power failure, including automatic transfer to the emergency generator. The

system should demonstrate that the quality of water produced is not diminished due to an automatic

transfer to the emergency generator.

The acceptance test should demonstrate the UPS for PLCS and SCADA controls performing without

loss of data and control.

The acceptance test shall demonstrate manual shutdown, manual start-up, automatic shutdown,

automatic start-up, and automatic transfer of equipment that requires any or all of those functions,

without interruption of flow, or quality of effluent.

3.1.1 Pretest Activities

Preparations for testing shall include:

Page 58: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

58 May 2017

Successful pressure testing and disinfection of all components.

Arrange with the City to have suitable, certified operators present as needed

Operate the new Facility for at least 24 hours of continuous operation, with all equipment and

processes fully functional, prior to starting the Acceptance Test.

3.2 Acceptance Test Reports

The Company shall provide reports in accordance with the requirements of regulatory agencies, with

certification of the results demonstrating performance, all relevant data measured and recorded during

the test(s), any calculations that were used in determining test results, any certifications from equipment

manufacturers that equipment was operated according to manufacturer’s recommendations, any other

available documentation reasonably requested by the City.

3.3 Duration of Acceptance Test

In addition to demonstrating successful operation of equipment and process start-up, shutdown, and

transfer, the Plant shall demonstrate performance and quantity of flow for a minimum of 24 continuous

hours at the maximum flow. Failure to achieve 100 percent successful operation will require a retest

after corrections and adjustments for the problems have been implemented.

3.4 Reserved

3.5 Operator Training

During the first 90 days, the Company shall provide training for the City’s personnel in the operations

of the new facility. Training shall be conducted by the process engineer who is chiefly in charge of the

design of the facility, or an appropriate designee.

Six days of training shall be provided, either at the plant site, or at the City’s headquarters in Torrance.

A syllabus for the training shall be prepared and submitted for review and approval, prior to the start of

training. The classes will be held in two 3-day sessions. Training shall be scheduled at a mutually

agreeable date, prior to facility acceptance.

Session 1 will cover operation of the well pumps, booster pumps, process equipment, operations and

maintenance of mechanical equipment, electrical equipment, O&M manual contents, and optimization.

Session 2 will cover controls, instrumentation, communications, automation, computer equipment, and

programming, and is described in Appendix J.

Page 59: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

59 May 2017

Appendix D – Governmental Approvals and Responsibility Matrix

The following matrix delineates responsibilities for regulatory compliance, permits, and other activities

needed to complete the project and commission the facility:

Table D-1 Responsibility Matrix

Description City Company

CEQA compliance City has completed an MND and an Addendum to the MND.

Comply with MND requirements and mitigations measures.

Permits - Construction City will provide plan check for grading permit and building and safety permits.

City will file Notice of Intent (NOI) with RWQCB for storm water discharge during construction.

Company shall procure permits required for construction, including: (1) storm water (construction)

(2) Building and Safety

Permit – Plant Operating City will be responsible for Drinking Water Permit and/or modification by the DDW.

City will be responsible for NPDES permit

Company will assist by providing technical information

Permit – Air Quality City will pay fee and sign permit application Company shall prepare and process permit application and provide compliant equipment

Geotechnical investigation City is responsible for providing a preliminary geotechnical report for the Facility

Company responsible for review of data, final geotechnical report and design recommendations, and stating key assumptions

Utilities A preliminary title report is provided and preliminary investigation via Underground Service Alert has been started. Available information is shown on the site plan. Other utility maps will be provided, as they become available.

Company is responsible for completing the utility research and designing the facility accordingly. Should unanticipated utility relocations be required, this would be covered as a change order.

Electricity City will enter into any required electrical power service agreement for the Facility with SCE, including payment any fees or charges. Preliminary contact has been made with SCE regarding the loads shown in the concept drawings.

Company responsible for coordination of design and construction of the electrical power for the facility including providing any required construction needed for the electrical power for the Facility.

Telephone and Telecommunications

City responsible for entering into and telephone service agreement, including payment of any fees or charges.

Company responsible for design and construction of any facilities to provide telephone service for the Facility, and for making necessary contacts and arrangements.

Page 60: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

60 May 2017

Table D-1 Responsibility Matrix

Description City Company

Water No potable water is currently available on site.

Company responsible for design and construction of on-site storage, pumping and distribution system, including provisions for connecting a possible future well.

Company to furnish all water needed for construction and testing.

Land Acquisition City to purchase all property required for the Facility and to clear all easements not currently in use, that will conflict with the Facility’s construction

Company responsible for any property needed for construction that is not part of the Facility site provided by the City

Survey City responsible for initial site survey and placement of temporary property monuments. City responsible for legal description.

Company responsible for any additional design and construction required surveys

Design City to provide minimum design requirements and conceptual drawings in RFP. City will provide timely reviews of design submittals.

Company responsible for all Facility design & construction documents. Company responsible for submission of

Construction City will respond to RFIs and will review shop drawings and other technical submittals for general conformance. City will provide general oversight.

Company responsible for all Facility construction based on design documents included in the contract, including management

Quality assurance and quality control

At its discretion, City will provide occasional construction observation and verification testing.

Company responsible for establishing and implementing QA/QC procedures, including: (1) independent review of design products, and (2) inspection/testing of construction. Company shall provide documentation of QA/QC results.

Site Security City to adhere to Company rules regarding ingress and egress.

Company responsible for construction site security.

SCADA programming of New Facility

City will provide input regarding preferences Company to provide hardware, software, and programming

Sewer at the facility City responsible for providing approximate location of existing sewer manhole and proposed sewer line routing. City also responsible for payment of sewer connection fees and application for new sewer service.

Company is responsible for the design and construction of the connection to the existing sewer manhole and maintaining sufficient distances from water infrastructure to satisfy regulatory requirements.

Construction Safety plan Company is solely responsible

Construction Schedule Company is solely responsible

Page 61: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

61 May 2017

Appendix E – Quality Management Plan

Page 62: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

62 May 2017

Appendix F – Start-Up and Operational Testing Plan

Page 63: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

63 May 2017

Appendix G – Milestone Schedule

Page 64: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

64 May 2017

Appendix H – Subcontractors

Page 65: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

65 May 2017

Appendix I – Safety Plan

Page 66: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

66 May 2017

Appendix J – SCADA Pre-Negotiated Scope and Fee

Page 67: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

67 May 2017

Appendix K – Minimum Required Technical Specifications

DIVISION 01 - GENERAL REQUIREMENTS

011100 COORDINATION OF WORK, PERMITS, AND REGULATIONS

012000* MEASUREMENT AND PAYMENT

013101 PROGRESS SCHEDULES

013216 CPM CONSTRUCTION SCHEDULE

013300 SUBMITTALS

014210 GENERAL ABBREVIATIONS

015100 CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

015526* TRAFFIC REGULATION

015721* STORM WATER RUNOFF CONTROL FOR SITES

015210 TEMPORARY OFFICE BUILDING

017000 CONTRACT CLOSEOUT

017410 CLEANING DURING CONSTRUCTION AND FINAL CLEANING

019310 OPERATION AND MAINTENANCE MANUALS

DIVISION 02 - EXISTING CONDITIONS

020120 PROTECTING EXISTING UNDERGROUND UTILITIES

020130* CONNECTIONS TO EXISTING BURIED PIPELINES

DIVISION 03 - CONCRETE

030500 GENERAL CONCRETE CONSTRUCTION

031510* CONCRETE WATER STOPS

034220* PRECAST CONCRETE VAULTS

DIVISION 04 - MASONRY

042223 CONCRETE UNIT MASONRY

DIVISION 05 - METALS

050520 BOLTS, WASHERS, AND ANCHORS

051210* MISCELLANEOUS METAL AND STRUCTURAL STEEL

053120* METAL ROOF DECKING

Page 68: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

68 May 2017

055100* LADDERS, STAIRS, AND STAIR NOSINGS

055200* HANDRAILS

055300* GRATING, COVER PLATES, AND ACCESS HATCHES

DIVISION 06 – WOOD AND PLASTICS

061110 WOOD FRAMING AND SHEATHING

061753 PREFABRICATED WOOD TRUSSES

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

071119 VAPOR BARRIER DAMPPROOFING MEMBRANE

072100 FIBERGLASS BULDING INSULATION

073113 ASPHALT SHINGLE ROOFING

075200* BUILT-UP BITUMINOUS ROOFING

076000 FLASHING AND SHEET METAL

077200 ROOF SCUTTLES, SKYLIGHTS, AND CURBS

079200 ARCHITECTURAL CAULKING AND SEALANTS

DIVISION 08 - OPENINGS

081110* METAL DOORS AND FRAMES

083323* COILING DOORS

083473 SOUND CONTROL DOORS AND FRAMES

087110 DOOR FINISH HARDWARE

089119 FIXED LOUVERS

DIVISION 09 - FINISHES

099000 PAINTING AND COATING

099752 COLD-APPLIED WAX TAPE COATING

099754 POLYETHYLENE SHEET ENCASEMENT

099761 FUSION-BONDED EPOXY LININGS AND COATINGS

DIVISION 10 - SPECIALTIES

104416 FIRE EXTINGUISHERS

DIVISION 13 – SPECIAL CONSTRUCTION

0133310* ALUMINIM GEODESIC DOMES

Page 69: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

69 May 2017

DIVISION 22 - PLUMBING

221319* PLUMBING PIPING SPECIALTIES

224210* PLUMBING FIXTURES AND TRIM

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING

230933 ELECTRIC/ELECTRONIC HVAC CONTROLS

233410 FANS

238114* CUSTOM PACKAGED ROOFTOP AIR CONDITIONERS

DIVISION 26 - ELECTRICAL

260500 GENERAL ELECTRICAL REQUIREMENTS

260519 WIRES AND CABLES LESS THAN 600 VOLTS

260526 GROUNDING AND BONDING

260534 CONDUITS, BOXES, AND FITTINGS

260548 SEISMIC RESTRAINT FOR ELECTRICAL EQUIPMENT

260573 ARC-FLASH HAZARD ANALYSIS

260590* MISCELLANEOUS ELECTRICAL DEVICES

261216 DRY-TYPE TRANSFORMERS

262410 PANELBOARDS

262419 LOW-VOLTAGE MOTOR CONTROL

262650 ELECTRIC MOTORS

262726 WIRING DEVICES

262913 LOW-VOLTAGE SWITCHBOARDS

262923 VARIABLE FREQUENCY DRIVE

263212* STANDBY ENGINE-GENERATORS

264313 TRANSIENT VOLTAGE SURGE SUPPRESSORS (TVSS)

265000 LIGHTING

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

282318* CLOSED CIRCUIT TELEVISION SYSTEM

DIVISION 31 - EARTHWORK

312300 EARTHWORK

Page 70: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

70 May 2017

312316 TRENCHING, BACKFILLING, AND COMPACTING

312323 CRUSHED ROCK BASE FOR STRUCTURES

DIVISION 32 - EXTERIOR IMPROVEMENTS

321216 ASPHALT CONCRETE PAVING

DIVISION 33 - UTILITIES

331220* BACKFLOW PREVENTERS

331300 DISINFECTION OF PIPING AND WELL

331620* PRESTRESSED CIRCULAR CONCRETE RESERVOIRS

332110* TEMPORARY WELL CONSTRUCTION FACILITIES

332112* CONDUCTOR CASINGS

332116* WELL GEOPHYSICAL LOGGING AND CALIPER SURVEY

332118* ISOLATED AQUIFER SAMPLING

332120* TEMPORARY STABILIZATION OF PILOT HOLE

332122* PILOT HOLE DRILLING, DOWNHOLE TESTING AND REAMING

332124* WELL CASINGS, SCREENS AND ACCESSORIES

332126* GRAVEL PACK AND GROUT SEAL FOR WELLS

332128* WELL DEVELOPMENT

332130* WELL TESTING

332132* VIDEO CAMERA SURVEY OF WELL

333110* VITRIFIED CLAY PIPE

333112* PVC GRAVITY SEWER PIPE

333118* HDPE PROFILE WALL GRAVITY DRAIN PIPE

DIVISION 40 - PROCESS INTEGRATION

400500 GENERAL PIPING REQUIREMENTS

400515 PRESSURE TESTING OF PIPING

400520 MANUAL, CHECK, AND PROCESS VALVES

400560 AIR-RELEASE AND VACUUM-RELIEF VALVES

400570* GLOBE PATTERN CONTROL VALVES

Page 71: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

71 May 2017

400722 FLEXIBLE PIPE COUPLINGS

400764* PIPE HANGERS AND SUPPORTS

400775* EQUIPMENT, PIPING, DUCT, AND VALVE IDENTIFICATION

402001 GENERAL REQUIREMENTS FOR STEEL PIPING

402020* COPPER TUBING

402035* PLASTIC TUBING

402040* DUCTILE-IRON PIPE

402050 FABRICATED STEEL SPECIALS

402057 FUSION EPOXY-LINED AND –COATED STEEL PIPE

402066 CML&C STEEL PIPE

402076* STAINLESS STEEL PIPE

402078 STAINLESS STEEL TUBING

402094* CPVC PIPE, 3 INCHES AND SMALLER

402350* DRAINAGE AND PLUMBING PIPING

402468* CLEAR PVC SECONDARY CONTAINMENT PIPING

402717* PULSATION DAMPENERS

405000 PROCESS CONTROL AND INSTRUMENTATION SYSTEM (PCIS) GENERAL

REQUIREMENTS

405010 PROCESS CONTROL AND INSTRUMENTATION SYSTEM LOOP

DESCRIPTIONS

405020 INSTRUMENTATION EQUIPMENT

405030* ANALYTICAL INSTRUMENTS

405040 PROGRAMMABLE LOGIC CONTROLLER (PLC) CONTROL SYSTEM

405050* DATA RADIO SYSTEM

405080 INSTRUMENT CONTROL PANEL

405085* FIELD INSTRUMENT PANELS

409117* MAGNETIC LEVEL INDICATOR

409715 PRESSURE GAUGES AND PRESSURE SWITCHES

409726 PROPELLER METERS

Page 72: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

72 May 2017

DIVISION 43 - PROCESS GAS AND LIQUID HANDLING, PURIFICATION, AND STORAGE

EQUIPMENT

432148* SUMP PUMPS

432150* VERTICAL TURBINE PUMPS

432154 VERTICAL TURBINE PUMPS-WATER WELLS

432182* PROGRESSING CAVITY PUMPS

434126* FRP CHEMICAL STORAGE TANKS

434217* POLYETHYLENE STORAGE TANKS

* = Draft specs not included.

Page 73: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

73 May 2017

Volume III-B – Reference Documents

Page 74: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

74 May 2017

Page 75: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

75 May 2017

Appendix 1 – SCE Information

SCE Application

Electrical Service Requirements

Page 76: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

76 May 2017

Page 77: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

77 May 2017

Appendix 2 – Preliminary Design Report by AECOM

Well 9 Installation Report

Well 10 Preliminary Information Report

Page 78: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

78 May 2017

Page 79: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

79 May 2017

Appendix 3 – Corrosion Control Study

Page 80: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

80 May 2017

Page 81: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

81 May 2017

Appendix 4 – Torrance Municipal Code Sections 22.3.20 – 22.2.24

Page 82: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

82 May 2017

Page 83: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

83 May 2017

Appendix 5 – Record of Utilities, Pothole Data

Page 84: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

84 May 2017

Page 85: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

85 May 2017

Appendix 6 – Project Site Survey by Bush & Associates Inc.

Page 86: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

86 May 2017

Appendix 7 – Legal Description, by Floyd Huber

Page 87: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

87 May 2017

Page 88: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

88 May 2017

Appendix 8 – Easements

Page 89: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

89 May 2017

Page 90: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

90 May 2017

Appendix 9 – Preliminary Geotechnical Study, Converse Consultants

Page 91: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

91 May 2017

Page 92: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

92 May 2017

Appendix 10 – CEQA Documents

Mitigated Negative Declaration

Air Quality Study

Noise and Vibration Study

Traffic Study

Tank Failure Inundation Study Report

Letter Stating no Historical Significance

Page 93: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

93 May 2017

Page 94: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

94 May 2017

Appendix 11 – Not Used

Page 95: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

95 May 2017

Page 96: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

96 May 2017

Appendix 12 – Preliminary Calculations

Page 97: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

97 May 2017

Page 98: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

98 May 2017

Appendix 13 – Sample Specifications

Page 99: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

99 May 2017

Page 100: DESIGN-BUILD OF NORTH TORRANCE WELLFIELD …ntwfp.torranceprojects.city/Shared Documents/Volume III/NTWF... · Design-Build of North Torrance Wellfield Project Volume III ... (NPDES)

Design-Build of North Torrance Wellfield Project Volume III – Contract Appendices

100 May 2017

Appendix 14 – State and Federal Grant Agreements

State Grant Agreement

Federal Grant Agreement