DESIGN AND PERFORMANCE ANALYSIS OF MICRO HYDRO …
Transcript of DESIGN AND PERFORMANCE ANALYSIS OF MICRO HYDRO …
DSpace Institution
DSpace Repository http://dspace.org
Power Systems Engineering Thesis
2020-05-05
DESIGN AND PERFORMANCE
ANALYSIS OF MICRO HYDRO
ELECTRIC POWER SYSTEM AT
DIVERSION WEIR IRRIGATION PROJECT
Baye, Tilahun
http://hdl.handle.net/123456789/10806
Downloaded from DSpace Repository, DSpace Institution's institutional repository
i
BAHIR DAR UNIVERSITY
BAHIR DAR INSTITUTE OF TECHNOLOGY
SCHOOL OF RESEARCH AND POSTGRADUATE
STUDIES
FACULTY OF ELECTRICAL AND COMPUTING ENGINEERING
DESIGN AND PERFORMANCE ANALYSIS OF MICRO HYDRO
ELECTRIC POWER SYSTEM AT DIVERSION WEIR IRRIGATION
PROJECT
[Case study - River Fetam at Zalima Village Bure Woreda]
By
Tilahun Baye
Bahir Dar, Ethiopia
October 20, 2017
ii
DESIGN AND PERFORMANCE ANALYSIS OF MICRO HYDRO ELECTRIC POWER
SYSTEM AT DIVERSION WEIR IRRIGATION PROJECT
[Case study - River Fetam at Zalima Village Bure Woreda]
By
Tilahun Baye
A thesis submitted to the school of Research and Graduate Studies of Bahir Dar
Institute of Technology, BDU in partial fulfillment of the requirements for the degree
of
Master of Science in the electrical power system in the faculty of engineering
.
Advisor Name: Dr. Tassew Tadiwose
Bahir Dar, Ethiopia
October 20, 2017
i
DECLARATION
I, the undersigned declare that this thesis is my original work, and has not been
presented for a degree in this or any other university, and all sources of materials used
for the thesis have been fully acknowledged.
Name of the student Tilahun Baye Signature _________
Date of submission: 10/10/2017
Place: Bahir Dar
This thesis has been submitted for examination with my approval as a university
advisor.
Advisor Name: Dr. Tassew Tadiwose
Advisor‟s Signature: ______________
ii
© 2017
By: Tilahun Baye (as it appears on the title page)
ALL RIGHTS RESERVED
iii
Bahir Dar University
Bahir Dar Institute of Technology-
School of Research and Graduate Studies
Faculty of Electrical and Computing Engineering
THESIS APPROVAL SHEET
Student:
……………………… ….………………… …………………..
Name Signature Date
The following graduate faculty members certify that this student has successfully
presented the necessary written final thesis and oral presentation for partial fulfillment of
the thesis requirements for the Degree of Master of Science in Electrical Power System
Engineering
Approved By:
Advisor:
……………………… ….………………… ………………….. Name Signature Date
External Examiner:
Getachew Biru (Dr.-Ing) 09/10/2017
………………………… …………………… ………………...
Name Signature Date
Chair Holder:
…………………………. …………………… …………………
Name Signature Date
Faculty Dean:
……………………….... …………………… ………………….
Name Signature Date
iv
ACKNOWLEDGEMENTS
First and foremost, a lot of thanks and glory to almighty God who made me a person I am
today and for His blessing for me to complete my MSC Project and this thesis is the
symbolic of the support and guidance that I get from all my family specially my mother
Father Baye and my beloved wife Slenat Brehan
Next, I would like to express my heart-felt appreciation and special gratitude to all persons
who, in one way or another contributed to the accomplishment of the study. Special
appreciation and deepest thanks go to the project research advisor Dr. Tassew Tadiwose
(Bahir Dar Institute of Technology) for his continued guidance, inspiration,
encouragement and support throughout the study period, which made the successful
completion of this study smoothly.
My appreciation also goes to my family who has been so tolerant and supports me all
these years. Special thanks for their encouragement, love and emotional supports that they
had given to me. Besides, I would like take this opportunity to thank all my friends Abiye
Wogayew, Habtamu Mamu & BoB for their close support and help.
v
ABSTRACT
Ethiopia is a developing country with a total access to electricity not exceeding 58% (in
2017) and the number of household connected to this access is 25%. About 85% of the
population lives in places where access to electricity is less than 5%. The village for this
study, Zalima rural Village (11.610 N, 28.400 E) has a total population of 2035 and 275
households. The village is about 1.2km from Fetam Irrigation canal power house
substation; which makes the extension of the grid not yet practical and off grid
electrification is the best option for the village. The community in the Zalima Village uses
Kerosene for lighting, water for milling and biomass for cooking and dry cells for radios.
Nothing has been done so far in developing the renewable energy resources, such as
micro hydro energy in the village.
In this study, finical and economic feasibility of micro hydro power electric supply system
to the village is analyzed using HOMER software as complete sensitivity analysis tool.
Hydro potential of the village is analyzed by measuring the gross head of the irrigation
canal with the help of serving data and stream flow irrigation canal data obtained from
Bureau of Water, Irrigation and Energy of Development of Amhara. Electric load for the
basic needs of the community, such as, for lighting, radio, water pumps, and flour mills is
estimated. One primary school and one health posts are also considered for the
community. Additionally one Orthodox churches also considered. As a result, many
feasible standalone the system was then optimized and determined the best configuration
result using the Homer software. For primary load of 203 kwh/d and 18.9 KW hydro
turbines backup Generator 7KW. Micro-hydro system combinations are generated, and
accordingly, total net present cost (NPC) of the micro hydro configuration and cost of
energy (COE) for micro hydro system is $67,044 and $0.07/kWh, respectively. Further
HOMER calculates the emissions of the following six pollutants CO2, CO, UHC, PM, SO2,
& NO2 as a result the system is environmentally friendly and free from greenhouse gases.
These facts indicate that electrifying rural villages using micro hydro systems is beneficial
and suitable for long-term investments.
Index terms: Micro - hydro, off - grid system, Backup Generator, HOMER
vi
TABLE OF CONTENTS
DECLARATION .............................................................................................. i
ACKNOWLEDGEMENTS .......................................................................... iv
ABSTRACT ..................................................................................................... v
TABLE OF CONTENTS .............................................................................. vi
LIST OF ABBREVATIONS .......................................................................... x
LIST OF SYMBOLYS .................................................................................. xi
1. INTRODUCTION ....................................................................................... 1
1.1 Background ................................................................................................................................................ 1
1.2 Problem Statement ..................................................................................................................................... 2
1.3 Objective of the study ................................................................................................................................ 3
1.4 Scope of the study ...................................................................................................................................... 3
1.5 Significance of the study ............................................................................................................................ 4
1.6 Thesis Outline ............................................................................................................................................ 4
2. LITERATURE REVIEW .......................................................................... 5
2.1 Micro-Hydropower Generation System ..................................................................................................... 7
2.2 Classification of hydro power based on the demand for electrical power................................................ 10
2.3 Civil Work Components of Micro Hydro power unit .............................................................................. 11
2.4 Powerhouse Components ......................................................................................................................... 13
2.5 Types of Hydraulic Turbines ................................................................................................................... 15
2.4.1 Impulse Turbines .................................................................................................................................... 15
2.4.2 Reaction Turbine .................................................................................................................................... 17
3. METHODOLOGY.................................................................................... 20
4. ENERGY DEMAND ASSESSMENT OF THE STUDY VILLAGE ... 22
4.1 Profile of the Village under study ............................................................................................................ 22
4.2 Primary and Secondary Data Collection .................................................................................................. 22
4.2.1 Primary data ........................................................................................................................................... 22
4.2.2 Secondary data ....................................................................................................................................... 23
4.3 Energy Demand Assessment and Load Scheduling of the Village .......................................................... 24
4.3.1Load projection for the village ................................................................................................................ 26
5. SYSTEM DESIGN AND PERFORMANCE ANALYSIS OF MICRO
HYDRO ELECTRIC POWER.................................................................... 29
5.1 Study design and Selection of System Components MHP....................................................................... 29
5.1.1 Intake water way .................................................................................................................................... 30
5.1.2 Inlet and Outlet Zone ............................................................................................................................. 34
5.1.3 Head race Canal ..................................................................................................................................... 35
vii
5.1.4 Forebay..... ............................................................................................................................................. 36
5.1.5 Factors to be considered in Penstock Selection and Design ................................................................... 38
5.2 Electromechanical Equipment ................................................................................................................. 40
5.2.1 Turbine Selection ................................................................................................................................... 40
5.2.2 Selection of Generator............................................................................................................................ 42
6. RESULTS AND DISCUSSION ............................................................... 45
6.1 Overview of HOMER Software ............................................................................................................... 45
6.2 Simulation Result of HOMER Software (compere analytical method) ................................................... 46
6.3 Sensitivity simulation result ..................................................................................................................... 49
7. COUNCLUSIONS AND RECOMMMENATIONS .............................. 53
7.1 Conclusions .............................................................................................................................................. 53
7.2 Recommendations .................................................................................................................................... 54
REFERENCES.. ............................................................................................................................................ 56
APPENDIX....... ............................................................................................................................................. 58
Appendix 1: Secondary data Year Stream flow Irrigation canal ..................................................................... 58
Appendix 2: Study area location (source document BoWIERD Amhara) ...................................................... 59
Appendix 3: Fetam Tajet irrigation system (source BoWIERDA) ................................................................. 60
viii
LIST OF FIGURES Figure 2-1 Cross –flow turbine ................................................................................................................................... 17
Figure 2-2 Turbine application chart Source [source: st. onge environmental engineering]....................................... 19
Figure 3-1 Flow Chart of the Research Methodology ................................................................................................. 20
Figure 5-1Flood discharge position of diversion canal ............................................................................................... 29
Figure 5-2Inlet and Outlet Zone .................................................................................................................................. 35
Figure 5-3Design of forebay tank ............................................................................................................................... 38
Figure 5-4 Design of penstock pipe ............................................................................................................................ 39
Figure 5-5 net design head .......................................................................................................................................... 40
Figure 5-6 Design of net head ..................................................................................................................................... 40
Figure 6-1 Diagram of the project with HOMER ....................................................................................................... 46
Figure 6-2 Hydro resource of Fetam River left side irrigation canal [AWIEB] .......................................................... 47
Figure 6-3 Hourly & Monthly/Seasonal primary load demand data of Zalima Shenbekuma Village upper
steram ................................................................................................................................................................. 48
Figure 6-4 Cost summary of renewable system components ...................................................................................... 49
Figure 6-5 Cash flow Summary by cost category for project life time ....................................................................... 50
Figure 6-6 Annual electric energy production by Hydro system ................................................................................ 51
Figure 6-7 State of backup of generation system ........................................................................................................ 52
Figure 6-8 Emission of system generation .................................................................................................................. 52
ix
LIST OF TABLES
Table 2-1 Hydro power category (source Lecture Notes) ........................................................................................... 10
Table 2-2 Efficiency of different turbines ................................................................................................................... 18
Table 5-1Design of Headrace and Left side Irrigation Transferring Canal ................................................................. 36
Table 5-2Selection of T-14 cross flow turbine plan .................................................................................................... 42
Table 5-3Design of Micro Hydropower by Irrigation Canal Fetam River output data ............................................... 43
Table 6-1Economic input of HOMER ........................................................................................................................ 45
Table 6-2 Categorized simulation result for the proposed renewable system ............................................................. 48
x
LIST OF ABBREVATIONS
MHP Micro hydro power
EREDPC Ethiopian Rural Energy Development and Promotion Center
ESCOs Energy Service Companies
IAEA International Atomic Energy Agency
IHA International Hydropower Association
COE Cost of energy
MoWIE Ministry of Water, Irrigation and Energy
EEU Ethiopian Electric Utility
AC Alternating current
REF Rural Electrification Fund
UEAP Universal Electricity Access Program
UF Utilization Factor
m.a.s.l Meter above Sea Level
HPP Hydro Power Plant
ANRS Amhara National Regional State
BoWIERD Bureau of Water Irrigation and Energy Resource Development
HRC Headrace canal,
ITC Irrigation Transfer Canal
HDP High density politely
COE Level zed cost of energy/useful electrical energy produced by the system.
NPC Net Present Cost
xi
LIST OF SYMBOLYS
KV Kilo Volt
MWh Mega Watt Hour
rpm revolution per minute
v Velocity
W Width
OD Outside diameter
PN Nominal pressure
g gravity
1
CHAPTER ONE
1. INTRODUCTION
Now, life without energy is unimaginable. The access to electricity has proven to be a key
factor necessary for socioeconomic development, both for the peoples and infrastructure
of a country. It is a basis for urbanization and industrialization in the current modern
times. With electricity, lines being confined to large cities and towns, developing
countries lag far behind in many sectors when compared to industrialized countries.
Ethiopia, despite being the one of Eastern African country, has a very poor electricity
penetration rate. Electricity is available for 58% of the population and only 25% of the
households are connected to the central grid; even the above coverage is confined to
major towns and cities [26].
Since the Ethiopian Government advocates Green Economy Renewable energy sources
(solar, wind, hydropower etc.) are attracting and got more attention as an alternative
energy sources than conventional biomass based energy system it accounts 90 % of the
total primary energy consumption in the country [26].
1.1 Background
According to EEU, current data with only 25% of households connected and 58% of the
he population is estimated to have access to electricity and the per capital energy
consumption is100kWh, which is the lowest in the sub-Sahara average, that is 510kWh.
Most of the non-electrified regions are found in rural part of the countries. These regions
can be electrified either by extending the grids of the existing power systems or by
constructing isolated (standalone) power systems. In general, it is preferred to go for the
extension of the existing grids but they are not always affordable the fact that most of the
non-electrified parts are located in remote and difficult areas, like hilly regions, forests,
and they are scattered, which demand enormous investment for grid. [26]
Hence off-grid electrification for remote place is nowadays become attractive and
alternative option for remote villages, which are detached from the central grid. There is a
2
huge potential for utilizing renewable energy sources, for example solar energy, wind
energy, or micro-hydropower to provide a quality power supply to remote areas. The
abundant energy available in nature can be harnessed and converted to electricity in a
sustainable way to supply the necessary power demand and thus to elevate the living
standards of the people isolated from the central grid. The Ethiopia Government is now
aware the national utility alone through Continuous grid extension cannot accelerate rural
access to electricity. To improve rural access to electricity, the government has recently
updated its strategies and improved any obstacle and constraints to accelerated off-grid
rural electrification.
Therefore; Bure woreda, is a small town having many rural villages far from the central
grid, of which Zalima Village is one of the village that does not have access to electricity,
in spite of having year round flowing river crossing and near left side irrigation canal, the
name of the river is Fetam River.
1.2 Problem Statement
In Amhara region off grid electrification for remote place is nowadays become attractive
and alternative option for Zalima Shenbekuma village and dwell around the site which are
detached from the central grid. There is a huge potential for utilizing renewable energy
sources, for example solar energy, wind energy, or micro-hydropower to provide a quality
power supply to remote areas. One of the reasons to have low electricity access in
Ethiopia is the costs of extending the electric grid and the scarcity of energy becomes
greater due to the high rate of population growth and weak energy supply system. The
pace of energy supply has been out stripped by that of energy demand.
The generally backward infrastructural development in Ethiopia radically limits the pace
of economic growth. Particularly the rural communities are adversely affected. This has a
negative impact on the overall economy of the nation, as the rural communities are the
basis for agricultural development, which is the backbone of the economy of the nation.
Out of many infrastructural facilities that the small communities lack, the absence of
appropriate form of energy is the most obvious one. Lack of energy has a detrimental
3
effect on the growth of the nation since energy is the driving engine of economic
development.
1.3 Objective of the study
General Objective:-The main objective of this research is to study of micro-hydropower
system and energy storage for electrification at Fetam Rive irrigation canal of remote
villages for Zalima Village to sustainably and efficiently satisfy the energy demand of
remote village, where central grid electricity has not reached yet due to many
geographical and economic constraints.
Specific Objective
To assess and analyze daily/monthly/annually primary data of load demand
(such as Energy, power and light sources) for the technical and financial
feasibility of the site.
To perform analysis the average stream flow of daily/monthly/annually
secondary data (such as irrigation canal flow) for the technical feasibility of
micro hydropower energy potentials of the site.
To simulate complete sensitivity analysis of total net present cost/NPC/,
Levied CEO $/kWh and operation and maintenance cost $/yr. considering the
system life time using NREL Homer energy software/ Microsoft excel/.
1.4 Scope of the study
The scope of this study shall collect and analyze relevant data and information to examine
and select the most suitable systems configuration, recommend necessary action,
necessary measures that configure a system to accommodate the current and near future
electrical energy demand for the village. The study only focuses a micro-hydro resource
assessment of among different renewable energy resource in the village, like solar, wind
biogas and biomass. In doing so, we shall recommend for further production of a model by
other researchers and the limitations of this research shall then clearly be told as to give a
way to next coming researchers and those who are interested in the area.
4
1.5 Significance of the study
Ethiopian government has uncompromised policy in generating power from renewable
energy sources in GTP-2, similarly this thesis work focuses on renewable energy which is
assessment of a remote area Micro hydropower energy system to supply the rural
community detached village electrification energy system.
Policy makers and concerned bodies can use this study as a real problem solving approach
for similar and related studies.
Furthermore, this study gives answer to the site viability for the proposed system if there
is a concerned body /governmental or non-governmental organizations/ who can work on
the practical implementation.
1.6 Thesis Outline
This thesis contains seven chapters organized as follows. Chapter one provides a general
overview of about, steam flow and energy consumption. It also describes the background
information of the country under investigation, sets the objectives, formulation of
the problem statement, gives limitations, the scope of the study and purpose and
describes. In chapter two different literatures using of micro hydro energy in the rural
electrification purpose are presented and reviewed.
Chapter three: This section of the thesis is methodology section. In chapter four it
introduces about the case study area and energy consumption.
Chapter five: the designing steps in analysis method of micro hydro energy at diversion
weir of irrigation canal systems are presented and also include HOMER software and
simulation of hydro turbine system. Chapter six includes the result and discussion of the
designed system HOMER software.
The conclusion of the thesis has been taken by summing up all the findings and
summarizes them in chapter seven.
5
CHAPTER TWO
2. LITERATURE REVIEW
Several researches have been conducted in hybrid/micro hydro off-grid power generation
all over the world and in Ethiopia. Different scholars used different Technology option
and approaches to evaluate the various configurations of renewable energy resources, such
as solar energy, wind energy, micro hydropower and their hybrid configurations. A
number of studies results have been published some of the thesis paper are reviewed and
evaluated in the following paragraph.
Yohannes .T presented a case study of rural area in Ethiopia entitled “Application of
Micro-hydro pv/battery off- grid hybrid energy system for Ethiopian rural area‟
Simulating of a Micro Hydro-Wind hybrid power generation system for rural area of
Ethiopia” of Guder River His objective was to develop a hybrid system cost competitive
to supply energy for remote villages for a model community of 874 households with three
Protestant churches and two Orthodox churches also considered. He discussed many
feasible hybrid system combinations are generated, and accordingly, total net present cost
(NPC) of the hybrid configuration and cost of energy (COE) for PV/ micro hydro/ battery
hybrid system is $394,819 and $0.044/kWh, respectively, which is much lower than
previously studied Micro hydro/wind hybrid system and PV/hydro/wind hybrid systems,
and this value is less than the current grid price of Ethiopian ($0.06) [EEU]. [29]
Berihun G. presented a case study of rural area in Ethiopia entitled “Modeling and
Simulating of a Micro Hydro-Wind hybrid power generation system for rural area of
Ethiopia” by using HOMER & Matlab software. His objective was to develop a hybrid
system cost competitive to supply energy for remote villages for a model community of
660 households with, one primary school two churches one mosque and one health center.
He discussed two option, Wind/Micro hydro hybrid and Standalone Micro hydro system
by comparing the cost of energy to identify cost competitive for the remote village
compared to extending the existing grid to the area since the break even grid extension is
23.6km which is less an the extension of the grid, so grid extension can be an option.
According to him, the COE most favorable Wind/Micro hydro hybrid system is
6
$0.112/kWh. Moreover, COE of standalone Micro-hydro system is $0.035/kWh. He
concluded micro hydro system is the most economical and can only satisfy the energy
demand of the village and technically feasible option. [28]
As per GIZ report, Ethiopia is one of the lowest electrification levels in the sub-Saharan
Africa. The rural electrification level is less than 1.5 percent which is the lowest in the
world. After more than a century of history, the benefits of electricity are still limited to a
small section of the population in urban areas. In the Southern Nations, Nationalities and
Peoples‟ Regional State (SNNPR) Of Ethiopia, there exist three smaller hydropower
schemes in Yadot (350 kW), Dembi (750 kW) and Sor (5 MW). Currently GIZ is
supporting 4 off-grid sites (7, 30, 35, and 50 kW) and one grid-connected site (200 kW).
For example, the Gobecho I micro hydropower plant is built on a small river in Bona
Zuriaworeda of the Sidama zone in SNNP state with over 50,000 Euro; this project can
generate about 7 kilowatts of energy and provides electric power to more than 160
residents of the woreda. Form this report I understand in Amhara region there is no
implemented project there for I will make the design then interested company will work
on it. [30]
All most all of the above scholar‟s paper shows the hybrid system either only PV/wind
excluding hydro or PV/Wind/Hydro include wind turbine. But in this study only Micro-
Hydro. This system is best of all due to the reason Ethiopia have plenty of Huge amount of
Hydro potential in almost many parts of the country
In addition from the above literature reviews, it is observed that no researcher use RET Screen
or other simulation software for the design of hybrid micro power and almost all of them
dedicated to feasibility studies. Hence, HOMER is widely used for most of the RES based
systems. Thus, based on the above literature reviews, HOMER software is taken for the
purposes of this study to carry the feasibility assessment..
7
2.1 Micro-Hydropower Generation System
Water is the most common source of energy in Ethiopia. It accounts 97.65 percent of the
total energy mix [14]. Hydropower engineering refers to the technology involved in
converting the pressure and kinetic energy of water in to more easily used electrical
energy. The prime mover in the cost of hydropower is a water wheel or hydraulic turbines,
which transform the energy of the water in to mechanical energy [27].
Micro-Hydropower basics:- A micro-hydropower system is a small system in the range
of 5-100 KW. The simplest micro-hydropower plant is based on a run-of-river design,
which means it does not have water storage capability. It will produce power only when
water is running or it might have relatively small water storage capability. Micro-
hydropower is an interesting prospect for providing electricity for rural communities. [9]
General Principal of MHP: - Power generation from water depends upon a combination
of head and flow. Both must be available to produce electricity. Water is diverted from a
stream into a pipeline, where it is directed downhill and through the turbine (flow). The
vertical drop (head) creates pressure at the bottom end of the pipeline. The pressurized
water emerging from the end of the pipe creates the force that drives the turbine. The
turbine in turn drives the generator where electrical power is produced. More flow or more
head produces more electricity. Electrical power output will always be slightly less than
waterpower input due to turbine and system inefficiencies.
Water pressure or Head created by the difference in elevation between the water intake
and the turbine. Head can be expressed as vertical distance (feet or meters), or as pressure,
such as pounds per square inch (psi). Net head is the pressure available at the turbine when
water is flowing, which will always be less than the pressure when the water flow is
turned off (static head), due to the friction between the water and the pipe. Pipeline
diameter also has an effect on net head.
Flow is quantity of water available, and is expressed as „volume per unit of time‟, such as
gallons per minute (gpm), cubic meters per second (m3/s), or liters per second (l/s). Design
flow is the maximum flow for which the hydro system is designed. It will likely be less
8
than the maximum flow of the stream (especially during the rainy season), more than the
minimum flow, and a compromise between potential electrical output and system cost.
Sites where the gross head is less than 15m would normally be classed as “low head”.
From 10-50m would typically be called “medium head”. Above 50m would be classed as
“high head”.
Figure2 1Using a head drop structure of existing irrigation canal (Source Micro Hydro
Power Resource Assessment Handbook)
To determine the power potential of water in a stream it is necessary to know the flow
quantity of water available from the stream and the available head. The quantity of water
available for power generation is the amount of water (in m3 or liters) which can be
diverted through an intake into the pipeline (penstock) in a certain amount of time. This is
normally expressed in cubic meters per second (m3/s) or in liters per second (l/s)
Head is the vertical difference in level (in meters) through which the water falls down.
The theoretical power (p) available from a given head of water is in exact proportion to
the head and the quantity of water available [9].
9
* * *P Q H g (2.1)
Where, P= power at the generator terminal, in kilowatts (kW)
H= the gross head from the pipeline intake to the tail water in meters (m)
Q= flow in pipeline, in cubic meters per second (m3/s)
= The efficiency of the plant, considering head loss in the pipeline and the
efficiency of the turbine and generator 9.81 is a constant and is the product of
the density of water and the acceleration due to gravity (g)
This available power will be converted by the hydro turbine in mechanical power.
In studying the subject of hydropower engineering, it is important to understand the
different types of Hydro power plant development. The flowing classification system is
used in this text:
Run-of-river developments. A dam with a short penstock (supply pipe) directs
the water to the turbines, using the natural flow of the river with very little
alteration to the terrain stream channel at the site and little impoundment of the
water.
Diversion and canal developments. The water is diverted from the natural
channel into s canal or a leg penstock, thus changing the flow of the water in the
stream for a considerable distance.
Storage regulation developments. An extensive impoundment at the power plant
or at reservoirs upstream of the power plant permits changing the flow of the river
by storing water during high –flow periods to augment the water available during
the low-flow periods, the supplying the demand for energy in a more efficient
manner. The word storage is used for long-time impounding of water to meet the
seasonal fluctuation in water, availability and the fluctuations in energy demand.
While the word pondage refers to short-time (daily) impounding of water to meet
the short-time changes of energy demand [8].
10
Pumped Storage Developments. Water is pumped from a lower reservoir to a
higher reservoir using inexpensive dump power during periods of low energy
demand. The water is then run down through the turbines to produce power to
meet peak demand [9].
2.2 Classification of hydro power based on the demand for electrical
power.
Based-load developments: - When the energy from a hydropower plant is used to
meet all or part of the sustained and essentially constant portion of the electrical
load or firm power requirements, it is called a base-load plant. Energy available
essentially at all times is referred to firm power.
Peak-load developments: - Peak demands for electric power occur daily, weekly,
and seasonally, plants in which the electrical production capacity is relatively high
and the volume of water discharged through the units can be changed readily are
used to meet peak demands. Storage or pondage of the water supply necessary [9].
Classification of hydro power by installed capacity
Classification of hydropower according to installed capacity is different from different
scholars. However, here with the most common classification source hydropower
engineering lecture notes in BDUIT). Table 2.1 Hydropower classification by installed
capacity (source Lecture Notes)
Table 2-1 Hydro power category (source Lecture Notes)
S.no. Types of plant Installed capacity in
(KW)
1 Pico < 5
2 Micro < 100 3 Mini < 1000 4 Small to medium < 6000
5 Large > 6000
11
Classification of hydro power by head: - Hydraulic head is a key site-specific factor
affecting the turbines type selection, equipment, and construction costs of an SHP. Hence,
a set of representative reference models should developed for different head ranges and
corresponding turbine types:
Low head (2-25m): axial flow (AF) Kaplan/propeller, cross-flow
Medium head (25-70m): conventional Kaplan/propeller, Francis
High head (>70 m): Francis, Turgo, Pelton
2.3 Civil Work Components of Micro Hydro power unit
The civil components described in this section are those major components such as the
intake, headrace canal, de-Sanding basin, spillway, forebay tank, penstock pipes and
tailrace (BPC Hydro consult, 2006).
Operating reserve/Head Storage/:
Operating reserve provides a safety margin that helps ensure reliable electricity
supply despite variability in the electric load and the renewable power supply.
Virtually every real power system must always provide some amount of operating
reserve, because otherwise, the electric load would sometimes fluctuate above the
operating capacity of the system, and an outage would result.
Intake
Intake is the primary means of passage of water from the source of water. Intake
could be of side intake type or the bottom intake type. Usually, trash racks have to
be placed at the intake, which acts as the filter to prevent large water born objects
to enter the waterway of Micro Hydro Project. [15]
Headrace Canal
Headrace canal conveys the water to the fore bay. Sometimes, pipes can also be
used in place of the canals. [20]
Settling Basin
In order to reduce the sediment density, which has negative impact to other
components of the MHS (Micro Hydropower System) de-sanding basins are used
to capture sediments by letting the particles settle by reducing the speed of the
12
water and clearing them out before they enter the canal. Therefore, they are usually
built at the head of the canal. They are equipped with gate valves for flushing the
settled undesirable sediments. De sanding basin is capable of settling particles
above 0.2-0.3 mm of size [9].
Spillway
Spillways need to be designed to remove the excess water due to floods, in order to
minimize the adverse effects to the other components of the MHS (Micro
Hydropower System) spillways are often constructed in de-sanding basin and the
fore bay, from which the excess water is safely diverted to the water source.
Fore bay tank
The fore bay tank serves the purpose of providing steady and continuous flow into
the turbine through the penstocks. For bay also acts as the last settling basin and
allows the last particles to settle down before the water enters the penstock.
Forebay can also be a reservoir to store water-depending on it size (large dams or
reservoirs in large hydropower schemes are technically forebay). A sluice will
make it possible to close the entrance to the penstock. In front of the penstock a
trash rack need to be installed to prevent large particles to enter the penstock. A
spillway competes the forebay tank [8].
Penstock
The penstock is the pipe, which conveys water under pressure from the forebay tan
to the turbine. Penstock is a significant component of the MHP scheme and needs
to be designed and selected carefully as it represents a major expense in the total
budget (for some high head installations this alone could cost as much as 30% of
the total costs). Here the main aspects to consider are head loss and capital cost.
Head loss due to friction in the pipe decreases dramatically with increasing pipe
diameter. Conversely, pipe costs increase steeply with diameter. Therefore a
compromise between cost and performance is considered for design and selection
of pipe diameter and material.
Tailrace
Tailrace is very similar to headrace canal described previously in this section. The
only difference with that of the headrace canal is that it is situated at the end of the
13
civil components and is used to convey the water back to the source after use in the
micro hydro plant.
2.4 Powerhouse Components
The powerhouse components of Micro-Hydropower are used to the conversion of
mechanical energy of water into electrical energy takes place. Powerhouse consists of
electro-mechanical equipment such as turbines, generator and drive systems.
Turbine
In a Micro Hydropower System, hydraulic turbine is the primary component,
which converts the energy of the flowing water into mechanical energy through the
rotation of the runner. The choice of particular turbine depends upon technical
parameters such as design head and discharge at which the turbine is to operate as
well as other practical considerations such as the availability and cost of
maintenance personnel. The optimum speed of the turbine is the particular speed of
its rotor at which the turbine performs its best. The turbine needs to operate at this
optimum speed in order to get maximum possible output at all loading conditions.
Generators
Although this study is not overly concerned with the selection, and uses of
generators in the micro hydropower system it is, however, relevant to describe the
basic types of generators and how they are integrated in the micro hydropower
system. There are two types of generators in use for hydroelectricity generation;
either synchronous or induction generators. Synchronous generators are the
primary types of generators, which are used extensively in large-scale power
generation. When the power output levels are generally low (less than 10 MW),
induction generators are extensively used. Induction generators are also the
preferred type of generators in MHP (Micro Hydro Project) because they can
operate at variable speeds with constant frequency, are available cheaply and
requires less maintenance than the synchronous generators. Both of these
generators have the possibility to be used connected to the grid or just standalone
operation (Upadhayay, 2009).Advantage of synchronous generators are of high
efficiency even in partial loading, independent control of real and reactive powered
14
frequency, reliable power source with stable frequency and voltage for
independent network.
Drive Systems
The main purpose of the drive systems is to transmit the power from turbine to the
generators at a stable voltage and frequency at a required direction and required
speed. Like any normal drive systems, in a MHS also, drive systems comprise of
generator shaft, turbine shaft, bearings, couplings, gearboxes, belts, and pulleys.
The different types of drive systems common in MHS (Micro Hydropower
System) are direct drive, “V” or wedge belts and pulleys, timing belt and sprocket
pulley and gearbox drive systems. A direct drive system is one in which the turbine
shaft is connected directly to the generator shaft. In contrast, “V” or wedge belts
and pulleys are the most commonly used type of drive systems in MHS (Micro
Hydropower System). However, in very small systems (less than 3 kW) where
efficiency is critical, timing belt and sprocket pulley are commonly used.
Gearboxes are suitable in large machine where drive belts are not efficient. Due to
high maintenance and alignment costs of gearboxes, they are less frequently used
in MHS (Micro Hydropower System) (Upadhayay, 2009).
Electrical Load Controllers
All MHS (Micro Hydropower System) will have to have switchgear in order to
separate the power flow when necessary and to control the electrical power flow.
There are several different kinds of switches used in an MHS (Micro Hydropower
System) such as isolators, which are manually operated, switch fuses which
additionally can provide fuse for current limiting, MCCB (Molded Case Circuit
Breakers) which are used for protection from over current or short circuits and also
on. The choice of electronic load controller is largely dependent upon the type of
generator installed in MHS. For instance,when the induction generator is used in
the MHS. It is necessary to install induction generator controllers (IGC) [9].
Hydraulic Turbines: - The device, which converts hydraulic energy into mechanical
energy or vice versa, is known as Hydraulic Machines. The hydraulic machines, which
convert hydraulic energy into mechanical energy, are known as hydraulic turbines.
15
2.5 Types of Hydraulic Turbines
Turbines can be categorized mainly in two types: Impulse turbine and Reaction turbine.
Turbine is the heart of hydro system, as they transform the hydraulic energy in the
mechanical one, which is a more easily usable form of energy.
2.4.1 Impulse Turbines
The impulse turbine generally uses the velocity of the water to move the runner and
discharges to atmospheric pressure. The water stream hits each bucket on the runner.
There is no suction on the down side of the turbine, and the water flows out the bottom of
the turbine housing after hitting the runner. An impulse turbine is generally suitable for
high head, low flow applications.
There are three basic types of impulse turbines, which distinguished and which have
different physical principles and characteristics. These are the Pelton turbines, the Turgo-
turbine and the Cross flow-turbine (also known as Banki-Mitchell or Ossberger-turbine).
Pelton Turbinen
Pelton turbines are impulse turbines where one or more jets impinge on a wheel
carrying on its periphery a large number of buckets. Each jet issues water through
a nozzle with a needle valve to control the flow they are only used for high heads
from 60m to more than 1000m. The axes of the nozzles are in the plan of the
runner. In case of an emergency stop of the turbine (e.g. in case of load rejection),
the jet may be diverted by a deflector so that it does not impinge on the buckets
and the runner cannot reach runaway speed. In this way the needle valve can be
closed very slowly, so that overpressure surge in the pipeline is kept to an
acceptable level (max1.15 static pressure) [17].
Turgo turbines
The Turgo turbine can operate under a head in the range of 30-300m. Its buckets
areshaped differently from the Pelton turbine and the jet of water strikes the plane
of its runner at an angle of about 200. Water enters the runner through one side of
the runner disk and emerges from the other whereas the volume of water
16
decreases. Pelton turbine can admit is limited because the water leaving each
bucket interferes with the adjacent ones, the Turgo runner does not present this
problem. The resulting higher runner speed of the Turgo makes direct coupling of
turbine and generator more likely, improving overall efficiency and decreasing
maintenance cot. Despite the advantages, Turgo turbines are seldom build today
and are only applied in very small MHPs.
Cross-Flow Turbine
A cross flow turbine gets its name from the way the water flows through, or more
correctly „across‟ the rotor as shown in Figure 2.4 below (hence across flow or
cross flow). The water flows over and under the inlet guide-vane which directs
flow to ensure that the water hits the rotor at the correct angle for maximum
efficiency. The water then flows over the upper rotor blades, producing a torque on
the rotor, then through the center of the rotor and back across the low rotor blades
producing more torque on the rotor. Most of the power is extracted by the upper
blades (roughly 75%) and the remaining 25% by the lower blades. Obviously the
rotor is rotating, so what are the upper blades one moment will be the lower blades
the next [20]. The cross flow turbine is also named as Banki turbine. Its structure is
simple, but the Efficiency is low, used for small power stations with o Water head
of 4m-150m Output power could be up to 300 KW The advantage of cross-flow
turbines is they can be easily manufactured, cheap compare to other turbine type,
easy to repair. It can generate power even during low flow rate period
17
Figure 2-1 Cross –flow turbine
2.4.2 Reaction Turbine
A reaction turbine develops power from the combined action of pressure and moving
water. The runner is placed directly in the water stream flowing over the blades rather
than striking each individually. Reaction turbines tare generally used for sites with lower
head and higher flows than compared with the impulse turbines [17].
Kaplan and Propeller turbines
Kaplan and propeller turbines are axial-flow reaction turbines; generally used
for low heads from 2m to 40m. The Kaplan turbine has adjustable runner
blades and may or may not have adjustable guide-vanes. If both blades and
guide-vanes are adjustable, it is described as “double-regulated”. If the guide –
vanes are fixed it is “single-regulated”. Fixed runner blade Kaplan turbines are
called propeller turbines. They are used when both flow and head remain
practically constant, which is a characteristic that makes them unusual in small
hydropower schemes [17].
Francis turbines
The Francis turbine is a reaction turbine where water changes pressure as it
moves through the turbine, transferring its energy. A watertight casement is
needed to contain the water flow. Generally, such turbines are suitable for
18
sites such as dams where they are located between the high-pressure water
source and the low-pressure water exit. Francis turbines can be designed for a
wide range of heads and flows and along with their high efficiency makes
them one of the most widely used turbines in the world. Large Francis turbines
are usually designed specifically for each site so as to gain highest levels of
efficiencies (these are typically in the range of over 90%). Francis turbines
cover a wide range of head- from 20 meters to 700 meters, and can be
designed for outputs power ranging from just a few kilowatts to one Gig watt.
Hydro Turbine Efficiency
It is important to remember that the efficiency characterizes not only the ability of a
turbine to exploit a site in an optimal manner but also its hydrodynamic behavior.
Average efficiency means that the hydraulic design is not optimum and that some
important problems may occur (as for instance cavitations, vibration, etc). That can
strongly reduce the yearly production and damage the turbine.
Each power plant operator should ask the manufacturer for an efficiency guarantee (not
output guarantees) based on laboratory developments. It is the only way to get insurance
that the turbine will work properly. The origin of the guarantees should be known, even
for very small hydro turbines.
Table 2-2 Efficiency of different turbines [31]
Turbine type Best efficiency
Kaplan single regulated 0.91
Kaplan double regulated 0.93
Francis 0.94
Pelton multi-jet 0.90
Pelton single jet 0.89
Turgo 0.85
Cross-flow 0.80
19
Figure 2-2 Turbine application chart Source [source: st. onge environmental engineering]
20
CHAPTER THREE
3. METHODOLOGY
The methodology to accomplish this thesis work block diagram is as shown below:
Figure 3-1 Flow Chart of the Research Methodology
21
Literature Review: - Published Journals, different energy books, different literatures
related to problem statement and micro hydro power energy efficient rural electrification
system and load estimation, potential assessment techniques of micro hydropower
resources and optimization system components software guides like Homer Energy has
been reviewed.
Data Collected: - Primary and secondary data has been collected from the site and
concerned bodies.
Primary data collection such as needs for electricity system daily, monthly &
annually power load (kW)/Energy (kWh). Demand and consumption ($/kWh) from
the field and by interview of responsible bodies.
Secondary data collection such as max & minimum flow rate data and assessment
of micro hydro energy potentials of the site from river and irrigation canal has
been made.
Materials required for the study:-
Google Earth & Google Map
Software: HOMER for micro hydropower optimization and sensitivity analysis
tool, and MS Excel for load data estimation processing
Digital Camera: important photos related to the study will be taken and
documented.
Standard tables and charts: to determine flow of stream in the study area.
GPS
22
CHAPTER FOUR
4. ENERGY DEMAND ASSESSMENT OF THE STUDY VILLAGE
4.1 Profile of the Village under study
The selected off-grid remote rural village for this thesis is Fetam River Tajet diversion
weir irrigation project of left side main canal. The project area is located in Bure zuria
woreda, Zalima Shenbekuma village in specific location called Tajet. It can be accessed
by 180km asphalted road that runs from Bahir dar to Addis Ababa and 20km, gravel road
along the route, which joins Bure and Wolega.
4.2 Primary and Secondary Data Collection
4.2.1 Primary data
Primary dates are those data that are collected by the researcher his/herself by conducting
field survey. During the field survey, the primary data necessary for this study are the
selection of site river diversion weir irrigation canal available head of the diversion of
irrigation canal, the number of religious institutes and type of community services, such
as, school and health post. The gross head is measured by sit survey, of irrigation canal to
diversion weir canal elevation with approximately of 5.4m; whereas the number of
Churches, Community services is collected from Zalima Shenbekuma village
Administration, Zalima Shenbekuma village health office, Zalima Shenbekuma village
Education office and the local people live near to the selected River diversion weir left
side irrigation canal. Accordingly the primary data collected are listed below in Table 3.1
23
Table3. 1 Primary data
Data Collected Value Data Source
Left Side Irrigation Canal
Gross Head of storge
1 Field survey direct Measurement with
GPS and Irrigation project designe
docment.
Distance from power house to
village
1.2Km Filed surivey direct Measurement with
GPS
Number of Primary school 1 Zalima Shenbekuma village Education
Offices
Number of Health Post 1 Zalima Shenbekuma village Health
Offices
Number of Churches
- Orthodox Churches
2
Zalima Shenbekuma village
Administration Office
Number of Population
I. 2007 Census
II. Current Population
6124
8104
2007 Census and Burea Woreda
Administration. (25% total number of
Population living Zalima rural village and
the other Shenbekuma rural village )
4.2.2 Secondary data
Is a data that is not collected by the researcher for his purpose; others collect it for other
purpose. Secondary data more appropriate for this study are, stream flow of the river,
irrigation canal , population size & number of households, energy equipment cost related
to the proposed Steam flow is collected from Bureau of Water, Irrigation and Energy
Development of Amhara; whereas the population size & number of households and token
from Central Statics Agency and Zalima Shenbekuma village administration
respectively. [CSA, 2007] The following table show secondary data collected for the
village under study:
24
Table3. 2Secondary data
Secondary Data Collected
Value Data Source
Fetam river Stream flow(From
1980-2009)
20 year ANRS Bureau of water
Irrigation and energy
left side Irrigation Canal Stream
flow
436l/s ANRS Bureau of water
Irrigation and energy
(Irrigation Design document)
4.3 Energy Demand Assessment and Load Scheduling of the Village
To improve the life of the society energy is very important and crucial. Due to the low
income of the society, scattered placement, the house hold energy demand of the village is
lower than that of in the urban area.
The electrical energy produced from the proposed Micro hydropower system is supplied
to home appliances, community service, and religious institute. Home appliances include
lighting. Radio receiver, community services energy requirement includes lighting, power
for office equipment‟s and water pumping .The primary load is residential with some load
for health post, religious institute and schools. The load of the village is composed of the
household devices such as lights radios and batter charges and that of refrigerators; water
heater devices are included in the calculation for health post. Table 5. The table shows
estimation of each appliance‟s rated power, its quantity and the hours of use by each house
health post, churches and school in a single day.
According to Burea Woreda Administration., the population living area in the selected
village is divided in to two classes based on their geographical area upper /downstream.
Based on geographical area the Wereda Administration selected 275 households‟ Zalima
kebel and 545 households Shenbekuma Keble the study selected upper stream (Zalima
Keble) for load planning, the current population size described in the above paragraph is
considered
25
Table3. 3Summary of energy demand of the village
No End Use Device Unit end use
Power[W]
Qty. Operating hours Daily Energy
Demand[kWh/d] Period hr/d
Small House Loads(275)
1 Lighting 11 3 18:00-23:00 5 45.375
2 Radio at Weekday 30 1 18:00-20:00 2 16.5
3 Battery charge 30 1 09:00-12:00 3 24.75
Sub total 86.625
Health Post
1 Vaccine
Refrigerator
60 1 00;00-23:00 24 1.44
2 Small Refrigerator 200 1 00:00-23:00 24 4.8
3 Microscope 15 1 09:00-12:00
18:00-23:00
6 0.09
4 Lighting 11 5 09:00-17:00 8 0.44
5 Water Heater 1000 1 08:00-11:00 3 3
6 Miscellaneous 20 1 00:00-23:00 24 0.48
Sub total 10.25
Schools
1 Lighting 15 32 18:00-20:00 2 0.96
2 Computer 100 4 08:00-12:00 4 1.6
3 Different office
lighting
15 6 18:00-20:00 2 0.18
4 Miscellaneous 20 1 00:00-23:00 24 0.48
Sub total 3.22
Church
1 Lighting 11 25 18:00-20:00 2 0.55
2 Megaphone 15 10 06:00-08:00 2 0.3
3 Miscellaneous 20 1 00:00-23:00 24 0.48
Sub total 1.33
Others
1 Pump 6000 1 01:00-04:00 3 18
2 Flour Mill 7000 2 04:00-07:00
11:00-14:00
6 84
Sub total 102
System daily total
energy Demand
203.425
26
4.3.1Load projection for the village
Predictions of future events and conditions are called forecasts, and the act of making such
predictions is called forecasting. Forecasting is a key element of decision-making. . Its
purpose is to reduce the risk in decision making and reduce unexpected cost [9].
Energy Consumption in the Future across the residential, commercial and industrial
sectors in the Village will be strongly influenced by economic growth. Increasing personal
income, capital investment and housing starts are major contributors in continued growth
in electricity demand.
For this study, Load, projection for the village is considered from the country average. The
electricity demand forecast considers both the peak demand for electricity and average
demand throughout the year. Peak demand refers to the highest level of electricity
consumption that the utility can supply at any one time. According to EEU the Target
Scenario electricity, demand will be expected to grow by 30% for the period 2017-2020
EEU. From this Forecasting Estimation we assume the village Energy Demand also will
increases by 25% because village Energy Demand is lower than urban Demand.
Therefore, for the village under study the current energy Demand is 203.4kWh/d, peak
energy demand is 24kW and 74,241kWh/year. However, From Simulation Result 53% of
the Energy is Excess energy, for the time being this excess energy will be damped by
damping resistor, when the demand increases the excess energy can be utilized. Hence, the
Village future Energy Demand Growth will be satisfied by this excess energy Generated
by the designed hybrid system.
27
Table3. 4 Load demand
Figure4 1 Load demand
The total estimated peak load is not the actual peak load that will be seen by the system,
because not all the loads allocated for a certain period might be operated on at the same
time. Therefore, a demand factor is applied to the load data. Based on experience on
electrical engineering and engineering judgment, the demand factor is assumed 0.8.
Additionally a 10% spinning reserve is assumed in the system as well. To import the load
data into HOMER hourly load profile for the whole year is required. A load profile of
8,760 hours was thus created for a year based on hourly estimated load for different
months.
End
Time
Load
demand
[kwh/day]
1 0.32
2 6.32
3 6.32
4 6.32
5 14.32
6 14.32
7 14.47
8 0.47
9 9.97
10 10.04
11 10.04
12 14.79
13 14.375
14 14.375
15 0.375
16 0.375
17 0.375
18 0.32
19 18.49
20 18.49
21 9.395
22 9.395
23 9.395
24 0.32
Total 203.38
28
The average daily energy demand of the village after assuming demand factor of 0.8 and
becomes 163kWh, hence the yearly energy demand is estimated as:
Annual Average Energy=163KWh*365day=59,393KWh/year
29
CHAPTER FIVE
5. SYSTEM DESIGN AND PERFORMANCE ANALYSIS OF MICRO HYDRO ELECTRIC POWER
The off-grid power generation system studied in this thesis is standalone micro hydro
power generation and diesel generator backup purposes of station.
Advantages of the system are the stability and immobility of the system and a lower
maintenance requirement, thus reducing downtime during repairs or routine maintenance.
Besides this, as well as being indigenous and free, renewable energy resources also
contribute to the reduction of emissions and pollution.
The Micro hydro power generation system makes use of hydro turbine to produce
electricity as the primary source to supply the load. The micro hydropower system is with
including a diesel generator as a standby system.
5.1 Study design and Selection of System Components MHP
The study of conveyance facilities are provided to guide the diverted Irrigation water
from the power intake to a penstock and removing surplus water back to the irrigation
channel and includes the headrace, the head pond or forebay, the side spillway and
flushing channel.
Figure 5-1Flood discharge position of diversion canal
30
Design Flood discharge of Diversion canal and level
i. Diversion Irrigation canal bed elevation at site of weir =1976.50masl
ii. F.S.L of the headrace canal at the head =1979.80masl
iii. Minimum driving head for full supply discharge = 0.5masl
iv. Pond level require to be maintained assuming 0.1m
Head loss in the weir intake and settling basin = 1980.4masl
Thus the total minimum height of weir required is 1980.4-1976.50 = 3.9 m
The crest level/ floor level of the scouring canal free bored has been fixed 0.3m higher
than the lowest average irrigation canal bed level at 1976.80masl. So that any deposited
silt in front of intake structure shall be disposed of easily .The downstream profile of the
scouring sluice has been kept at a slope of 2.5H to 1V and that of the weir proper at a
slope of 2H to 1V.
Similarly the crest level of the weir of diversion canal has been fixed at 1980.7masl
considering the head required to transfer the flow to headrace canal and a downstream
profile kept at a slope of 2.5H to 1V . The deepest diversion canal bed level at the weir site
is around 1979.0masl.
5.1.1 Intake water way
The water way of the intake to discharge or draw 0.436cum can be determined by using
the discharge formula.
2dQ C A gh (5.1)
Where, Q: Design discharge = 0.436m3/sec
Cd: discharge coefficient =0.6
A: Area of the water way
h: net head or water depth = design intake water level – inlet apron elevation
g: Gravity of
Pond level 1980.40masl
31
Inlet apron level 1978.90masl
The head available above the inlet apron 1.5m but assuming that the available head above
the center of the intake to be 0.5m the area of the water way to pass the required discharge
is computed as:
For the design purpose the velocity of water to pass through the orifice is taken as, V = 1.3
m/s. This value was so taken because for MHS (Micro Hydropower System) the
recommended velocity through the orifice during normal flow is 1.0 - 1.5 m/s). Based on
this premise, it is possible now to calculate the, Area of orifice, (A)
2.436
0.331.3
QA m
V (5.2)
However it is also necessary to consider, whether this design will work during the
monsoon season when the water floods by taking into consideration the value of discharge
through the orifice during flood flow (Q flood).
. 2 r hQ AV AC g h h (5.3)
Letting C=0.6 (for roughly finished masonry)
3
0.33*0.6 2*9.8 1.4 0.5 0.83floodmQ
s
This value will be important at the later stage when designing the spillway since the
orifice is only designed to take 0.436 m3/s.
Design of spillway
It was already pointed out in the section discussing design parameters that the design of
the spillway can be made with calculations of its different dimensions.
The dimension of the spillway are given by,
32
For the design of the spillway it is first necessary to consider what would be the length
required if the design flow was 0m3/s.
Because the material for spillway was chosen as crested weir with round edges C w = 1.6
Q flood = 0.832 m3/s
Q design = 0.436 m3/s
H overtop (h flood – h sp) = 100 mm by convention,
In this case the length of the spillway would be,
1.5
flood design
spillway
w flood
Q QL
C h hsp
(5.4)
1.5
flood design
spillway
w flood
Q QL
C h hsp
= 7.1 m
Settling basin
The water drawn from Fetam River Tajet diversion weir left side irrigation canal for
power generation may carry suspended sediment particles. This silt load may be composed
of hard abrasive materials such as quartz and will cause damage or wear to the hydro-
mechanical elements like turbine runners, valves, gates and penstocks. To remove this
material a structure called settling basin should be constructed, where the velocity of the
flow will be reduced resulting in settling out of the material, which has to be periodically
or continuously flushed out. In order to satisfy the requirement for a good hydraulic
performance the basin is divided into three main zones: inlet zone, settling zone, and
outlet zone.
33
Determination of the design grain size limit
The hydraulic design of a settling basin is normally begins with analyzing the quantity and
quality of sediment carried by the river and determining the necessary degree of removal
on the basis of theory and practical experience but in the absence of the enough sediment
data the limiting size of the suspended matter allowed to deposit is determined from the
low head plants: d limit = 0.2 to 0.5mm
Thus considering the available head, the turbine type (Cross flow) and the size of the
project a limiting size of 0.2mm is adopted for the design of the basin.
/lV a d m s =0.197m/s (5.5)
Where, dl: diameter of the smallest sediment particle to be settled in 0.2mm
„a‟ constant given as a = 0.44 for d = 0.2mm.
V: Settling velocity (m/s)
Settling velocity
The fall velocity of a spherical particle of diameter 0.2mm and relative density of 2.65 is
found to be around 3.1cm/s at around 250 temperatures.
Now assuming the width of the basin to be 1.6 m the depth of flow D can be computed
from the continuity equation as:
0.436
1.6*.2
QD
WV =1.36 says 1.4m (5.6)
Where W: Width of the basin (assuming 1.6m)
D: depth of flow (m)
V: Settling velocity (m/s)
34
During a turbulent flow settling is slower in a flowing water due to the retarding effect of
turbulent flow on subsiding particles, thus the settling velocity is need to be adjust as:
0
mvs
0.1320.111
D
0.031 (0.111*0.2) 0.0086ms
Where; : adjusts settling velocity
: settling velocity of subsiding particles
: Coefficient of subsiding particles
t: adjusts settling time
Using adjusts settling velocity the settling time is computed using the formula:
1.4
162.750.0086
Dt s
(5.7)
The length of the basin is thus,
162.5*0.2 32.55 33L Vt m m (5.8)
Therefore a study design of stilling basin which has a depth of 1.4m, width of 1.6m and
length of 33.0m is provided.
5.1.2 Inlet and Outlet Zone
The main function of the inlet is to decrease gradually the turbulence and avoid all
secondary currents in the basin. This is achieved by decreasing the flow velocity through
gradually increasing the flow cross-section, i.e., by providing gradual expansion of the
width and depth.
In order to achieve a uniform approach of water over the whole chamber width, the
transition is designed using the formula:
35
2 tan 3
B b LI
11m (5.9)
Where I: transition length
B: stilling basin width = 1.6m
b: width of intake = 0.8m
Ѳ: expansion angle = 14.5o
1.6 .8
2 112 tan14.5
I
, hence the design is save.
Outlet Zone
This is a kind of transition provided following the settling zone to facilitate getting back
the flow into the conveyance system with the design velocity by gradually narrowing the
width and depth. The outlet transition wall is designed to Converge 2.5:1
Figure 5-2Inlet and Outlet Zone
5.1.3 Head race Canal
The head race is a conveyance for the diverted left side irrigation canal water from the
weir intake to the forebay and can be provided in the form of a canal, The general
topography of the project area is characterized by a moderate gentle slopes and a very
steep slope terrain that extends downward to left side irrigation canal. Thus, the headrace
36
canal is aligned to run parallel to the left side irrigation canal and closely follow the line of
the terrain that corresponds to the full supply level of the canal. The total length of the
headrace canal is around 50m.the cross section is designed as a concrete lined rectangle
canal up to the full supply depth and a free board of 0.3m vertical masonry wall is
provided. To prevent the interference of animals and humans the power canal is provided
with a top cover concrete slab. The details of the study design are shown in table.
Table 5-1Design of Headrace and Left side Irrigation Transferring Canal
Canal
ID
Required
discharge
Manning's
roughness
Bed
slope
Side
slope
Bed
width
Water
depth
b/d
rati
o
Free
boar
d
Velocity Design
discharge
(Qr) m3/s 'n' (s)
b (m) d (m) m V (m/s) (Qd)
HRC* 0.436 0.015 0.0016 0.75 0.8 0.55 1.7 0.3 1.01 0.447
ITC** 0.436 0.015 0.0016 0 0.8 0.55 1.7 0.3 1.01 0.447
5.1.4 Forebay
A sufficient covering water depth should be provided for preventing the occurrence of a
vortex at the mouth the penstock and air movement to the penstock. The minimum
submergence depth is
1.707*s
vY
gd (5.10)
Where Y s: the minimum submergence depth
v: velocity at the inlet to the conduit( m/s)
d: depth of the conduit(m)
g: 9.81 is a constant and is the product of the density of water and the acceleration
due to gravity (m/s2
)
2.8
1.707* 2.19.81*0.5
sY m
To avoid the inflow of sediment to the penstock, the bottom of the inlet basin of the
penstock is raised by 0.5m from the lowest portion of the forbay resulting to a total water
37
depth of 3.1m i.e. 0.5m depth of inlet conduit plus 2.1m submergence depth plus 0.5m
dead storage depth.
Therefore the study design of forebay will have a final size of 17m length, 1.6m width and
3.1m depth.
A gradual transition section should be provided between the power canal and the forebay
basin and the total length of the transition is determined using the formula:
2 5.62 tan 3
B b LI m
Where I: transition length
B: forebay width = 1.6m
b: bottom width of head race canal = 0.8m
Ѳ: expansion angle = 14.5o
The study design capacity of the forebay tank
* *FV W D L (5.11)
31.6*3.1*17 84.3FV m
Where VF: Volume of forebay (m3)
W: Width of forebay (m)
D: Depth of forebay (m)
L: Length of forebay (m)
38
Figure 5-3Design of forebay tank
5.1.5 Factors to be considered in Penstock Selection and Design
After selecting the material for the penstock pipe, it is necessary to determine its diameter.
The most important design parameter in this selection is that the velocity of the water
should be in between 2.5 m/s to 3.5 m/s. If the velocity is lower or higher it can cause loss
in the power output and thus be uneconomical in the longer run. In study selected
HDP pipe OD 500 PN16 because low cost and high flexible pipe.
4*
*p
Qd
V
(5.12)
Where, d pipe = inside diameter of the pipe (m)
Q = design flow (m3/s)
V = average velocity in the pipe (m/s)
39
Figure 5-4 Design of penstock pipe
40
5.2 Electromechanical Equipment
5.2.1 Turbine Selection
Hydrological Data
i. Design discharge (Qd) = 0.447m3/s which was taken 90% minimum reliable
discharge (after deducting the total loss). So as to sustain the minimum
guaranteed power available with minimum initial investment.
ii. Net design head (H) = 4.42 which is calculated from the following parameters
(at design value)
Figure 5-5 net design head
Figure 5-6 Design of net head
2 3netH H H (5.13)
1977.5 1973.09 4.4netH masl masl m
Where
H net – Effective head
41
Hg - Gross Head of Elevation (1980.4masl)
HL1 - Elevation of intake to forebay (1979.6masl)
HL2 - Elevation of penstock (1977.5masl)
HL3 - Elevation of installation head (1973.09masl)
Turbine performance Analysis T-14 Model values in design are as follows;
Formula (1): Inlet width
11max
1.
.o
net
Qb
q D H (5.14)
Where ob In let width
11maxq Unit discharge (flow) =0.80 (for T-14 Turbine model no)
D Rotor diameter =0.3 m
4.9o
net
Qb
H =887m
Formula (2): Shaft power output
max max9.8* * *e tP H Q =15.47 KW (5.15)
Where t Turbine efficiency 0.80 (for T-14 Turbine model no)
Formula (3) Turbine speed (rpm)
11t net
nn H
D =266rpm (5.16)
Where tn Turbine speeds
11n Unit Speed 38 (for T-14 Turbine model no)
42
Table 5-2Selection of T-14 cross flow turbine plan
5.2.2 Selection of Generator
Considering the facts that the synchronous generators are of high efficiency even in partial
loading, independent control of real and reactive powered frequency, reliable power
source with stable frequency and voltage for independent network and since it can be
designed and manufactured for any actual site condition.
The unit generator input power is same as the turbine output power 14.3kw from
mechanical design. Taking the efficiency of a generator as 95%, the output power of the
generator is calculated as 14.3x0.95=13.58kw.
365 24
1000
KWh days houersAnnulyAvergeEnergy power
year year
(5.17)
Item Unit Parameter
Net head/Design head/ m 4.41
Design discharge m3/s 0.447
Diameter of runner m 0.3
Unit speed (opt) rpm 38
Unit flow (opt) m3/s 0.8
Efficiency of turbine % 74
Unit flow (max) m3/s 0.94
Efficiency of turbine(max) % 73
Width of runner mm 887
Shaft power output kw 14.3
Shaft power output(max) kw 15.47
Turbine speed rpm 266
If turbine width is determined
Width of runner mm 900
Discharge m3/s 0.45
Turbine speed rpm 266
Run away speed rpm 478
43
13.58*365*24 118,961AnnulyAvergeEnergy KWh year
Based on the above mathematical analysis the total energy produced by the micro
hydropower is 118,961kWh/year. From this discussion, the Micro-hydropower system
totally meets the energy demand of the village
Table 5-3Design of Micro Hydropower by Irrigation Canal Fetam River output data
Description Unit
Diversion Weir type for Irrigation Canal Trench and Sharp crested weir
Number of diversion weir 1
Design Flood (Q f) 0.83m3/s
Weir Crest Level 1980.4masl
Bed Level 1976.5masl
Height of Weir (P) 3.9m
Length of Weir (L) 7.1m (including under sluice)
Intake with Trash rack/Gate Rectangular channel
Design Discharge 0.447 m3/s
Intake sill level 1979masl
Water level 1980.4masl
Scouring sluice invert level 1976.8masl
Power conduit type Closed conduit Rectangular canal
Canal height, H 0.85m
Canal width (W b) 0.8 m
Canal Length (L) 50m
Forebay type Rectangular
Area of forebay (17.5 x 1.6) 28m2
Water Level 1979.6masl
Flushing conduit invert level 1976.5masl
Penstock Inlet Invert level 1977.0masl
Penstock type Mild Steel pipe
Penstock diameter 0.9 m
Total length of penstock (L) 66 m
Powerhouse Surface type
Powerhouse area (W x L) (4 x 5) m2 Including control room
Floor Level 1972.755masl
Power production
Gross Head (Hg) 5.4 m
Net Head (H n) 4.41m
Plant discharge 0.447m3/s
Output power 13.5Kw
Turbine type horizontal shaft cross flow turbine
44
Description Unit
Turbine output power 14.3 kW
Rated speed 266 rpm
Turbine max efficiency 0.80
Turbine Coupling type Belt
Energy production 118 M W h/year
Electrical system Standalone type
Voltage level 400/230v
45
CHAPTER SIX
6. RESULTS AND DISCUSSION
6.1 Overview of HOMER Software
Renewable Optimization Model for Electric Renewable (HOMER) is a free computer
model developed originally by the National Renewable Energy Laboratory (NREL) in the
United States. This software application is used to design and evaluate technically and
financially the options for off-grid and on-grid power systems for remote, stand-alone and
distributed generation applications. It allows considering a large number of technology
options to account for energy resource availability and other variables. Since then
HOMER has remained a free software application which has evolved in to a very robust
tool for modeling both conventional and renewable energy technologies.
Table 6-1Economic input of HOMER
No. Hydro turbine Diesel Generator Size of energy equipment 1 KW 1 KW Capital Cost ($) 2000 256 Replacement cost ($) 1750 243 O& M Cost ($/Yr.) 57 0.05$/hr Life time 25yr 10yr(3.2hr./day)
46
6.2 Simulation Result of HOMER Software (compere analytical method)
Figure 6-1 Diagram of the project with HOMER
The inputted data fed for the HOMER simulation software described the primary load, and
micro hydro system components and its costs (Hydro turbine and Generator 1) and
different sizes as mentioned in the previous sections. The system‟s simulations are
performed by HOMER for each of the 8,760 hours in a year. The simulation output
consists of several combinations of each source, with initial capital and net present cost of
each of them.
47
Then monthly average data left side irrigation canal were fed to HOMER software. The
software calculated stream flow values for months of the year.
Figure 6-2 Hydro resource of Fetam River left side irrigation canal [AWIEB]
48
Figure 6-3 Hourly & Monthly/Seasonal primary load demand data of Zalima Shenbekuma Village upper
steram
Table 6-2 Categorized simulation result for the proposed renewable system
49
6.3 Sensitivity simulation result
This model shows how micro-hydro systems integrate with backup Generator system a
stand-alone application.
Sensitivity analysis was carried out and Figure 4.3 shows the variation of stream flow
against at fixed diesel price, the most cost effective set up for a particular set of hydro
generation system is also included.
Figure 6-4 Cost summary of renewable system components
As shown in figure 6.4.the largest capital cost is hydro $28600 and the lowest is for
Generator $2000
50
Figure 6-5 Cash flow Summary by cost category for project life time
As depicted in figure 6.5 the larger cost is expended in the first year and which is capital
cost of the project. Salvage value is calculated at the end of 25th year.
51
Figure 6-6 Annual electric energy production by Hydro system
Figure 6.6 depicts the constant of stream flow available throughout the hours of the day,
month and year b/c constant input load447m3/s.
52
Figure 6-7 State of backup of generation system
Figure 6.7 depicts participate of backup generation of the system almost none black color.
Figure 6-8 Emission of system generation
Figure 6.8 depicts the large Emission is use backup generation and no emission defect
hydro
53
CHAPTER SEVEN
7. COUNCLUSIONS AND RECOMMMENATIONS
7.1 Conclusions
This thesis aimed to investigate and design a micro hydro power generation system and
power conditioning to answer the research questions raised in the begging of the thesis, is
the micro hydro system technically feasible? The micro hydro system Designed to supply
electricity to the village, which equipped with residential loads, a health post and primary
school, and some commercial use, to improve the life of people as well the infrastructure
in the village where they are detached from the central grid. The study of the renewable
potentials of the site is based on the recently recorded data of 20 years average stream
flow and irrigation canal flow data obtained from ANRS Bureau of water Irrigation and
energy. HOMER does the analysis of the renewable energy resources. From the results,
the micro hydro potential of the site is found to be considerably high, and sufficient for
supplying the village in the current and near future energy demand of the village. In
General, this study relates the technical and environmental impact of the off-grid system.
The Overall Conclusion of the research work reported in this thesis is summarized as
follows:
1 From Technical point of view, Micro Hydro system is proposed in the Thesis.
From the simulation result the majority of the energy is obtained from
hydropower, which accounts 98% and backup generators 2% of the total load
consumption. Hence the backup generators should be avoided it only incurs
and increase the project cost.
2 From Environmental Stand point, the renewable energy fraction of the project
is 98%, which implies the total energy almost obtained from Renewable
Energy Resources. Due to this study promoting clean energy and its
contribution to the reduction of Pollutant emission released to the environment.
3 Finally the Author proposed that Off-grid Micro-Hydro system is technically
and economically feasible and Environmentally Friendly Configuration. Thus
the government, non-governmental organizations and private sectors should
54
make combined efforts to improve the quality of life of the communities living
in rural areas.
7.2 Recommendations
The following recommendations are made out of this research; some of them are directed
to other researchers while the others are directed to decision makers. Ethiopia has a huge
potential of renewable energy resources, which can be used for rural electrification
through the off-grid system. There are, however, many challenges like low purchasing
capacity of the rural community, unfavorable conditions towards the utilization of
renewable energies, absence of awareness how to use these resources, etc.
Thus the government, non-governmental organizations and private sectors should make
combined efforts to improve the low rate of rural electrification in Ethiopia.
The implementation for this micro hydro system in the village can serve as a pilot
system for the whole country. This will build for more research, study and
analysis.
As far as the environmental aspects are concerned, this kind of micro hydro energy
systems have to be wide spread in order to cover the energy demands of rural
communities, and in that support Ethiopian Government Green Economic Police as
well way to help reduce the greenhouse gases emission and the deforestation of the
environment in general.
The study done is on one randomly selected village of Bure Woreda administration
in Amahra region and it does not cover all around Amahra region. Future
researchers should extend such a research work in other potential sites and make
the rural people beneficial with renewable energy resource.
In spite of the huge hydroelectric potential of Ethiopia, sever power cuts in recent
years have a heavy impact on the country‟s economy. Micro hydro system
recommended to be built in for the future application to crate sustainable energy
supply of the country.
55
Finally the software used in this study used are free trial version, Used licensed
software for more reliable analysis.
56
REFERENCES
[1] W. Ministry, "Ministry of Mines and Energy (Nov. 2008), Ethiopia Energy Resources
Potential and Current Status.Addis Ababa," 2008.
[2] EEPCo, "EEPCo. Gibe III HEP Office (August 2010) , Environmental and Social
Issus Related to Gibe III Hydroelectric Project.Addis Ababa," 2010.
[3] A. Rajavanshi, "Strtegy for Rural Electrification, HOME,30 December 2005, Nepal,"
2005.
[4] Ministry Water , Guideline for design of small hydropower plant ,2000,Ireland, 2008.
[5] W. M. Organization, World Metrological Organization ,2008 "Manual on Low-Flow
Estimation and Perdiction",Operation Hydrology Report No.50,WMO-NO. 1029,
2008.
[6] U.S Department of Interior Offce, "U.S Department of I Designe of Small Dams. U.S
Department of Interior Supt. of Documents, U.S. Government Printing office,
Washington DC20402".
[7] World Metrological Organization, ""Manual on Law-Flow Estimation and
Predication"Operationnal Hydrology Report No. 50, WMO-NO. 1029," 2008.
[8] Q.F (Katherine) Zhang, " "Small Hydropower Cost Reference Model"," vol.
http://inf.oml.gov/sites/publications/files/pub 39663.pdf., May 2015.
[9] IEA-ETSAP, ""Technology Brief E12"," http://www.estap.org/, 2010.
[10] G. B. B. Plam, ""Feasibility study for astandalone solar -wind-based hybrid energy
system for application in Ethiopia"," Vols. Applied energy ,vol 87, pp. pp487-495,
2010 Addiss Abeba.
[11] ESHA, Guide on Howe to Develop Asmall Hydropower plant, 2004.
[12] IRENA Haarvey, Micro hydro design manual, IEA201b;Block & Veatch2012 &
IRENA/GIZ Haarvey, 1983.
[13] K. M. Katti P.K, "Alternative energy facilities based on site matching and generation
unity sizing for remote area power supply," in Renewable Energy 32, 2007, p.
pp1346.
[14] G. Lambert.T, "'Micro-power system modeling with Homer' in Farret F.A Godoy
Simoes M.(eds)," vol. Integration of alternative source of energy, pp. pp379-417.
[15] World Bank Africa Region Sustainable Development Unit, "Power traiff caught
between cost recovery and affordabillity," Cecilia Brice no-Gamedia maria shkatar,
December 2011.
[16] T. M.C, ""Feasibility assessment of hydroelectric power plant in Ungauged river
basin a case study "," Arabian Journal for Science and Engineering, Vols.
vol.38,no.6, pp. pp. 1359-1367, 2013.
57
[17] R. a. C. R. S.KSingal, ""Analysis for cost estimtion of low head run -of-river small
hydrpower schemes'," vol. vol. 14, no. Energy for sustainable Development, pp.
pp.117-126, 2010.
[18] D.Pappantonis, Small Hydro Power Stations,, Simeon Athens Greece, 2001.
[19] Alliance for Rural Electrification, "Hybrid power systems based on renewble energies
a suitable and cost competitive solution for ruralelectrification".
[20] ESHA, "Guide on How to Develop a small hydropower plant," 2004.
[21] Japanese Embassy in Ethiopia, Study on the Energy Sector in Ethiopia, Addiss Abeba
Ethiopia, 2008.
[22] Mekuria.L, "Power Africa Geothermal Road show," September,28 2014.
[23] H. P. V. 3.7, "User Manual All rights reserved," August 2016.
[24] H. p. system, "www.eepco.gov.et/," strategic management and programming office,
2011/2012. [Online].
[25] "http://www.eere.Avaible energy.gov/water/hydro turbine type," US department of
Energy Water power program. [Online].
[26] Federal Democratic Republic of Ethiopia Ministry of Water Irrigation and Electricity,
"www.mowie.gov.et," 21 06 2017. [Online].
[27] IRENA,Renwable Energy Technologies: , " Cost Analysis Series,
Hydropower,Volum Power Sector Issu 3/5 , International Renewable Energy
Agency.," Masdar city ,United Arab Emirates, 2012.
[28] Berihun.G, "Modeling and Simulating of a micro hydro wind hybrid power
generation system for rural area of Ethiopia," no. Master thesis in Addiss Ababa,
2013.
[29] Yohannes.T, "Modeling and Simulating of a micro hydro solar hybridy power
generation system for rural area of Ethiopia," no. Masters thesis in Addis Ababa
University, 2014.
[30] "http://www.Renewable Energy Potential in giz Ethiopia," [Online].
[31] "http://www.teriin.org/eveents/micro/NF-S3-RevA.pdf," [Online].
58
APPENDIX
Appendix 1: Secondary data Year Stream flow Irrigation canal
Month Stream flow (l/s)
January 447
February 447
March 447
April 447
May 447
June 447
July 447
August 447
September 447
October 447
November 447
December 447
Average 447
59
Appendix 2: Study area location (source document BoWIERD Amhara)
60
Appendix 3: Fetam Tajet irrigation system (source BoWIERDA)