Design and development of first MW-level microgrid in Thailand
Transcript of Design and development of first MW-level microgrid in Thailand
International Journal of Smart Grid and Clean Energy
Design and development of first MW-level microgrid in
Thailand
Xianwen Zhu a, c
, Suttichai Premrudeepreechacharn a
, Tirapong Kasirawat b
,
Chakphed Madtharad b
a Faculty of Engineering, Chiang Mai University, Chiang Mai, 50200, Thailand b Provincial Electricity Authority (PEA), Chiang Mai, 50200, Thailand
c NR Electric Co.,Ltd, Nanjing, 211102, China
Abstract
This paper presents the design and development of a MW-level Microgrid project at Mae Sariang District Mae Hon
Son province in northern of Thailand. The Microgrid project coverage area get power supply by a 110 km 22kV
distribution line which also pass the forest area. Thus the power supply is not stable, and the power quality is not
good, the weak power system has limited the local society development. To improve the power system in the
mentioned area, the Microgrid project has decided to build which include four local resources: 1.2MW hydro-power
plant, 4MWp solar PV, 5MW diesel generator and 3MW/1.5MWh battery energy storage system (BESS).Moreover,
Power flow study, short circuit study, dynamic study and protection system design based on various combinations of
RE systems are calculated using DIgSILENT PowerFactory software in achieving the most optimal design. The
obtained solution shows that a hybrid combination of solar/ hydro/battery/diesel is cost effective, sustainable, social-
economically and environmentally [1]. Additionally, the result shows that the Microgrid system could significantly
increase the power system stability and reliability in the Microgrid coverage area. Moreover, after lost power supply
from the main grid, by automatically black start function, the Microgrid system can supply power locally to the
customer and can reduce the outage time from at least 20 minutes to within 1 minute.
Keywords: Microgrid, BESS
1. Introduction
Mae Sariang District is about 110 km away from HOT substation.A long(110 km) 22 kV distribution
line which also pass through the forest area is the only link between the main grid and Mae Sariang
District, to reduce the power loss of the long distribution line , a 4MWp solar farm and 1.2MW hydro-
power plant are built to supply power locally, but there are still remain following main issues: The
energy loss from long distribution line is about 19% or about 6.7 million kWh per year; the number of
outage is more than 20 times per year caused by damaged equipment, maintenance, or weather related;
during peak load, diesel generator has to run to support the voltage in the area; solar farm cannot connect
to the grid in some cases caused by voltage sag, over voltage, or unbalance voltage; the operation in this
area still depends on the local operator due to the reliability of controlled equipment in SCADA system
which are sometime low battery or loss of communication. Therefore, when the outage occurs, it will take
about 20 minutes to connect and disconnect equipment before diesel generator is able to supply to the
load.Hence, the Provincial Electricity Authority (PEA) decided to build a smart microgrid by integrating
PV generation, BESS, hydro-power plant and diesel generator to enhance the local power supply, the
stability and resiliency of the power system.
Fig. 1 illustrates the power system single line diagram. It has 11 circuit breaks at substation for all
* Manuscript received August 13, 2020; revised July 7, 2020.
Corresponding author’s Tel.: +8613776540931; E-mail address: [email protected]
doi: 10.12720/sgce.10.2.133-141
feeders which is included incoming feeder from HOA08 and HOA09(22kV source) and 1BVB(future
115kV source) . The feeder from solar farm connect to the same bus with battery in order to use battery in
many operations such as PV smoothing, peak shaving, energy management, etc. 15 load break switches
installed in this project to provide the function of load shedding, load recovery and Fault Location,
Isolation, and Service Restoration(FLISR).
Fig. 1. Power system single line diagram
Fig. 2 has been shown the typical load profile of the microgrid coverage area, the most load is come
from the residential electricity consumption, thus the peak load is happen at 6:30AM when people wake
up and start to cooking and 6:30PM when people start to use lighting and air-conditioner. And during
those peak time, PV already cannot generate power at that time , power supply is not enough, the system
voltage will drop , without microgrid system, PEA has to start Diesel generator to maintain system
voltage despite the cost of diesel oil is quite high, after microgrid system set up, it will use BESS to
discharge during the peak time. The microgrid system also can be used for voltage and frequency
dynamic regulation function when system has some disturbance .In case that there is some internal fault
happen, the Fault Location, Isolation, and Service Restoration(FLISR) function will operate to
locate ,isolate and restore the fault area automatically to reduce the outage duration. In addition, in case
the distribution line is interrupted, the coverage area will be supplied by energy sources from battery,
diesel generator, Solar farm, or hydro power plant to form as islanding area in order to increase the
reliability of the system.
Fig. 2. Typical load profile of Microgrid coverage area
134 International Journal of Smart Grid and Clean Energy, vol. 10, no. 2, April 2021
Zhu Xianwen et al.: Design and development of first MW-level microgrid in Thailand
2. System Components
Microgrid control & protection system adopts the layered and distributed design, which is divided into
local control level, coordinative control level and optimal control level. [2-4]
The topology as shown in Fig. 3:
Fig. 3. Layered Microgrid control and protection system
2.1. Local control level
The Local control level includes DGs, PCS, local controller and protection IEDs. Our automated local
control system with independent communication can provide fast response speed between equipment
during minor disturbances or short-circuit faults, and stabilize power-supply by the self-regulation of
converter or the fast action of protection equipment.
2.2. Coordinative control level
The coordinative control level includes the Microgrid controller, which acquires the information of
DGs, energy storage, diesel generators and important load via the control communication network. When
Microgrid operates in the islanded mode and large disturbance occurs (such as non-scheduled grid outage,
large-capacity DG trip, etc.), the Microgrid controller coordinates the operating modes of energy storage
and diesel generator as well as the output power of DGs to maintain the voltage and frequency within the
allowable ranges and guarantee the stable and safe operation of Microgrid system.
2.3. Optimal control level
The optimal control level includes the Microgrid EMS and depends on the data supplied by SCADA
system, dispatching & schedule system, load forecast system, etc. It realizes the functions of data analysis,
energy prediction, load management, optimal operation, economic dispatching for the specified
applications to maximize the comprehensive utilization rate of the DGs within Microgrid.
3. System Modeling
According to the problems, DIgSILENT PowerFactory software is used to show ability of the MGDP
in any case or scenario studies defined by PEA, the power system study result has also been used for
function design and relay setting calculation.
135
3.1. System modelling
The system modelling as shown in Fig. 4:
Hydro
Diesel
PV System
Battery
DC Batt 0 .000 .000 .00
LV(6)0 .411 .0317.29
22.361 .02
-13.81
22.161 .01
-13.24
22.411 .02
-13.73
22.661 .03
-12.99
LV(4)0 .390 .9819.91
LV(3)0 .390 .9819.91
LV(2)0 .390 .9819.91
LV(1)0 .390 .9819.91
TDiesel0 .000 .000 .00
M SR _ D _ 1 ( 4 )
0 .000 .000 .00
M SR _ D _ 1 ( 2 )
0 .000 .000 .00
M SR _ D _ 1 ( 1 )
0 .000 .000 .00
22.741 .03-3 .90
22.941 .04
-12.26
22.661 .03
-12.99
Terminal LF5(1)22.401.02-13.60
T F1
Terminal LF4(1)22.461.02-13.66
MAA115 .001 .000 .00
HOA0 .000 .000 .00
22.441 .02
-13.6922.451 .02
-13.67
22.421 .02
-13.72
21.010 .96
-12.25
21.650 .98-3 .90
23.061 .05-5 .96
22.761 .03-2 .46
Hydro_13 .301 .000 .00
M SR _ D _ 1
0 .000 .000 .00
MAA Bus 1
22.501.02
-13.60
21.120 .96-5 .95
21.400 .97-2 .45
MAA Bus 222.501 .02
-13.60
23.101 .050 .00
23.101 .050 .00
22.531 .02
-13.25 22.741 .03-3 .90
PowerFactory 15.1.2
Project:
Graphic: Grid
Date: 10/7/2018
Annex:
Load Flow Balanced
Nodes
Line-Line Voltage, Magnitude [kV]
Voltage, Magnitude [p.u.]
Voltage, Angle [deg]
Branches
Active Power [MW]
Reactive Power [Mvar]
Current, Magnitude [kA]
~
BESS PQ Droop Mode
P 1...Q 0...I 1...
V
DC - Batt
BESS VF Mode
LoadHOA08(3)
P 0 .9 ..Q 0.0 ..I 0 .02..
LoadHOA09(3)
P 1 .2 ..Q 0.6 ..I 0 .03..
Lin
eS
WC
ap_
a
SWCap
P 0 .0 ..Q 0.0 ..I 0 .00..
1
LoadHOA09(2)
P 1 .6 ..Q 0.8 ..I 0 .04..
LoadHOA09(1)
P 1 .1 ..Q 0.5 ..I 0 .03..
LoadHOA08(2)
P 1 .3 ..Q -0.0..I 0 .03..
LoadHOA08(1)
P 1 .1 ..Q 0.0 ..I 0 .02..
Lin
eF
4_
en
d
Load LF4(4)
P 0 .3 ..Q 0.2 ..I 0 .00..
Load F5(2)
P 0 .4 ..Q 0.2 ..I 0 .01..
Lin
eF
5_
en
d
Load LF1(3)
P 0 .2 ..Q 0.1 ..I 0 .00..
Load LF1(1)
P 0 .6 ..Q 0.3 ..I 0 .01..
Lin
eF
1_
en
d
Lin
eC
ap
_a
P 0 .0 ..Q -5.0..I 0 .12..
Capacitor MAA1CVB-01
P 0 .0 ..Q -5.0..I 0 .12..
2
Line
HO
A09
_a
Line
HO
A08
_a
PV
_T
R1
P -1 .0 ..Q 0.1 ..I 0 .02..
P 1 .0 ..Q -0.0..I 1 .47..
P 1.0 ..Q -0.0..I 1.47..
2
Load F5(1)
P 0 .5 ..Q 0.3 ..I 0 .01..
Load LF1(2)
P 0 .3 ..Q 0.2 ..I 0 .00..
SW
15Li
neF
1_a
Load LF4(1)
P 0 .6 ..Q 0.3 ..I 0 .01..
SW
14
P 0 .3 ..Q 0.1 ..I 0 .00..
PV04
P 1 .0 ..Q -0.0..I 1 .47..
PV03
P 1 .0 ..Q -0.0..I 1 .47..
PV02
P 1 .0 ..Q -0.0..I 1 .47..
PV01
P 1 .0 ..Q -0.0..I 1 .47..
Lin
eH
OA
08
_0
P -2 .0 ..Q 1.0 ..I 0 .05..
Lin
eH
OA
09
_0
P 0 .3 ..Q 0.1 ..I 0 .00..
Lin
eG
en
_a
Lin
eG
en
_a
Lin
eP
V_
0 P -4 .0 ..Q 0.2 ..I 0 .10..
Lin
eB
ES
S_
0
P -1.0 MWQ -0.4 MvarI 0.028 kA
Lin
eF
5_
0P 1 .0 ..Q 1.4 ..I 0 .04..L
ine
F1
_0
P 1 .4 ..Q 0.6 ..I 0 .03..
Lin
eF
4_
0P 1 .4 ..Q 0.6 ..I 0 .03..
Line
F3_
a
Lin
eF
2_
0
P 1 .3 ..Q 0.6 ..I 0 .03..
LineF3_bP 0 .4 ..Q 0.2 ..I 0 .01..
Line(9)
Lin
eP
V_b
Tie Bus Cable
P -4 .1 ..Q -2.8..I 0 .12..
P 4 .1 ..Q 2.8 ..I 0 .12..
Lin
eG
en
Tr4
Lin
eG
en
Tr4
Lin
eG
en
Tr3
Lin
eG
en
Tr3
Lin
eG
en
Tr2
Lin
eG
en
Tr2
Lin
eG
en
Tr1
Lin
eG
en
Tr1
L Load HOA09
P 0 .3 ..Q 0.2 ..I 0 .00..
L Load HOA08
P 0 .2 ..Q 0.9 ..I 0 .02..
G~
STAMFORD 2
G~
STAMFORD 4
Die
sel_
GS
UT
(4)
P 0 .0 ..Q 0.0 ..I 0 .00..
5
Die
sel_
GS
UT
(4)
P 0 .0 ..Q 0.0 ..I 0 .00..
5
G~
STAMFORD 5
Die
sel_
GS
UT
(2)
P 0 .0 ..Q 0.0 ..I 0 .00..
5
Die
sel_
GS
UT
(2)
P 0 .0 ..Q 0.0 ..I 0 .00..
5
G~
STAMFORD 3
Grid MAA115kV
0 .00 MW0.00 Mvar
1 .00
HOA09Grid
4 .07 MW2.17 Mvar
0 .88
SW13
SW
7
SW
6
SW
11 SW
12
SW
2
SW
1
SW
4
SW
3P 0 .7 ..Q 0.3 ..I 0 .02..
2-W
ind
ing
..
P 0 .0 ..Q 0.0 ..I 0 .00..
P -0 .0 ..Q -0.0..I 0 .00..
P 0.0 ..Q 0.0 ..I 0.00..
8
Lin
e
Grid HOT115kV
Load LF3(3)
P 0 .4 ..Q 0.2 ..I 0 .01..
SW10
SW5
Load LF3(2)
P 0 .5 ..Q 0.3 ..I 0 .01..
SW9P 0 .9 ..Q 0.5 ..I 0 .02..
SW
8Li
neF
2_b
P -0 .5 ..Q -0.3..I 0 .01..
Load LF2(2)
P 0 .5 ..Q 0.3 ..I 0 .01..
Line
F2_
a
Die
sel_
GS
UT
(1)
P 0 .0 ..Q 0.0 ..I 0 .00..
5
Die
sel_
GS
UT
(1)
P 0 .0 ..Q 0.0 ..I 0 .00..
5
Die
sel_
GS
UT
P 0 .0 ..Q 0.0 ..I 0 .00..
5
Die
sel_
GS
UT
P 0 .0 ..Q 0.0 ..I 0 .00..
5
HOA08Grid
6 .27 MW0.98 Mvar
0 .99
Line
BE
SS
_a
Lin
eP
V_a
Lin
e(
5)
Lin
e(
5)
P 0 .0 ..Q -0.0..I 0 .00..
G~
MITSU 1
P 0 .0 ..Q 0.0 ..I 0 .00..
G~
STAMFORD 1
Lin
eF
1_
b
Line
F5_
a
Lin
eF
3_
0
P 1 .7 ..Q 0.8 ..I 0 .04..
Line
F4_
a
PV
_T
R4
P -1 .0 ..Q 0.1 ..I 0 .02..
P 1 .0 ..Q -0.0..I 1 .47..
P 1.0 ..Q -0.0..I 1.47..
2
PV
_T
R3
P -1 .0 ..Q 0.1 ..I 0 .02..
P 1 .0 ..Q -0.0..I 1 .47..
P 1.0 ..Q -0.0..I 1.47..
2PV
_T
R2
P -1 .0 ..Q 0.1 ..I 0 .02..
P 1 .0 ..Q -0.0..I 1 .47..
P 1.0 ..Q -0.0..I 1.47..
2
Hy
dro
_G
SU
T
P -0 .0 ..Q -0.0..I 0 .00..
P 0 .0 ..Q 0.0 ..I 0 .00..
P 0.0 ..Q 0.0 ..I 0.00..
2
HO
A0
9 A
VR
2
P 2 .8 ..Q 1.4 ..I 0 .08..
P -2 .8 ..Q -1.4..I 0 .08..
P 2.8 ..Q 1.4 ..I 0.08..
6
HO
A0
8 A
VR
2
P 4 .8 ..Q 0.4 ..I 0 .13..
P -4 .8 ..Q -0.4..I 0 .12..
P 4.8 ..Q 0.4 ..I 0.13..
8
HO
A0
8 A
VR
1
P 2 .3 ..Q 0.0 ..I 0 .06..
P -2 .3 ..Q -0.0..I 0 .05..
P 2.3 ..Q 0.0 ..I 0.06..
8
HO
A0
9 A
VR
1
P 0 .0 ..Q -0.0..I 0 .00..
P -0 .0 ..Q 0.0 ..I 0 .00..
P 0.0 ..Q -0.0..I 0.00..
5
Load F5(3)
P 0 .1 ..Q 1.0 ..I 0 .02..
Load LF1(4)
P 0 .2 ..Q 0.1 ..I 0 .00..
Load LF2(1)
P 0 .7 ..Q 0.4 ..I 0 .02..
Load LF3(1)
P 0 .7 ..Q 0.4 ..I 0 .02..
Load LF4(2)
P 0 .4 ..Q 0.2 ..I 0 .01..
F in e F1 _ c
Line
F4_
b
2-W
ind
ing
..
P 1.0 ..Q 0.4 ..I 1.53..
0
Ze
qZ
pu
-0
-1
(1
)
P 1 .2 ..Q 0.6 ..I 0 .03..
P -1 .2 ..Q -0.6..I 0 .03..
Ze
qZ
pu
-0
-1
(3
)
P 0 .0 ..Q -0.0..I 0 .00..
P -0 .0 ..Q 0.0 ..I 0 .00..
Zeq
Zp
u-
0-
1
P 3 .0 ..Q 1.6 ..I 0 .08..
Ze
qZ
pu
-0
-1
(7
)
P 2 .3 ..Q 0.0 ..I 0 .05..
P -2 .2 ..Q 0.0 ..I 0 .05..
Ze
qZ
pu
-0
-1
(6
)
Ze
qZ
pu
-0-1
(5)
DIg
SIL
EN
T
Fig. 4. The all power system modelling in DIgSILENT PowerFactory software
3.2. Cases definition
All the case definition as shown in Table 1.
Table 1.Case definition
Case
No.
Grid-connected
Islanding PV BESS Diesel Hydro 115kV HOA08 HOA09
1081 0 1 0 0 1 1 1 1
1082 0 1 0 0 1 1 0 0
1083 0 1 0 0 0 0 1 0
1091 0 0 1 0 1 1 1 1
1092 0 0 1 0 1 1 0 0
1093 0 0 1 0 0 0 1 0
1151 1 0 0 0 1 1 1 1
1152 1 0 0 0 1 1 0 0
1153 1 0 0 0 0 0 1 0
0001 0 0 0 1 1 1 1 1
0002 0 0 0 1 1 1 0 0
0003 0 0 0 1 0 0 1 0
Remark: Status 1: Connected Status 0: Disconnected
For example, Case No. 1081: The power system connect to 22kV system at HOA08 together with
BESS, PV power plant, Diesel generators, and Hydro power plant. The simulation result of case 1081 has
been shown on Fig. 5., Fig. 6. and Fig. 7..
136 International Journal of Smart Grid and Clean Energy, vol. 10, no. 2, April 2021
Zhu Xianwen et al.: Design and development of first MW-level microgrid in Thailand
(a) (b)
Fig.5. Case 1081: (a)Voltage profile and (b) Active power profile
Fig. 6. Dynamic study of case 1081without BESS
In this case without BESS, voltage and frequency deviation may not comply with PEA regulation.
Fig. 7. Dynamic study of case 1081 with BESS
In this case with BESS, the BESS discharge/charge active power (-1.96 or -2.54 MW) and reactive
power (-0.24 or 1.41 Mvar) to regulate the voltage and frequency, can comply with the PEA regulation
without any outage.
4.
System Function Design
The design follows the connection standard IEEE 1547[5]. The Microgrid system is designed to
137
operate in both grid connecting and islanding mode [6] and more detail can be explained as following:
4.1. Scenario definition
Scenario 1 Before islanding
Scenario 1A grid connecting with 115kV incoming; Scenario 1B grid connecting with both HOA08
and HOA09 with tie breaker 0BVB open; Scenario 1C grid connecting with HOA08 with tie breaker
0BVB close; Scenario 1D grid connecting with HOA09 with tie breaker 0BVB close
Scenario 2 Preventive islanding if a supply interruption is planned, or an outage is expected
Intentional switching from grid connecting to islanding
Scenario 3 Automated islanding in case of unplanned grid failure
This project not have scenario 3
Scenario 4 Black start recovery to re-supply loads after grid failure
Automatic black start
Scenario 5 Maintaining the islanding
Islanding status control
Secnario 6 Reconnection to the main grid
Automatic connect back to grid
4.2. System operation mode for only have 22kV incoming:
The system will have 4 operation mode: Grid connecting open loop operation mode 1 (Scenario 1B,
0BVB open), grid connecting close loop opearation mode 2 (Scenario 1D,0BVB close), grid connecting
close loop opearation mode 3 (Scenario 1C, 0BVB close), island operation mode 4 (Scenario 5, 0BVB
close).
4.3. System operation mode for 115kV incoming:
After Mae Sariang substation 115kV incoming finished construction, the bus tie breaker will work as
normally close, 1VB 10VB will work as both feeder and back up power source in case 115kV power
source has been lost, then PCC point will have three which are 115kV incoming, HOA08 and HOA09.
4.4. System operation mode switching for 22kV incoming only
The operation mode switching as shown in Fig. 8.
Mode 2 grid connecting close loop operation
Mode 3 grid connecting close loop operation
Mode 1 grid connecting open loop operation
Trip 1VBclose 0BVB
Trip 0BVBclose 1VB
Trip 0BVBclose 10VB
Trip 10VBClose 0BVB
Mode 4 island close loop operation
Trip 1VB Close 1VBClose 10VB Trip 10VB
Fig. 8. System operation mode switching
138 International Journal of Smart Grid and Clean Energy, vol. 10, no. 2, April 2021
Zhu Xianwen et al.: Design and development of first MW-level microgrid in Thailand
Below Incoming 1 indicate for HOA08, Incoming 2 indicate for HOA09
The operation mode switching:
Logic 1: When system work in mode 1, incoming 1 lost power, bus I lost voltage, trip 1VB, PV and
BESS will stop asthmatically, close 0BVB, bus I lost power short time, go to mode 2; Switching from
Scenario 1B to 1D
Logic 2: When system work in mode 1, Incoming 2 lost power, bus II lost voltage, trip 10VB, close
0BVB, but II lost power short time, go to mode 3; Switching from Scenario 1B to 1C
Logic 3: When system work in mode 2: Incoming 2 supply to load, after that the voltage of incoming 1
has been recovered, it will trip 0BVB, then PV BESS stop automatically, bus I close 1VB, bus I lost
power short time. Switching from 1D to 1B.
Logic 4: When system work in mode 3: incoming 1 supply to load, after that the voltage of incoming 2
has been recovered, it will trip 0VBV, the diesel engine will stop, close 10VB, but II lost power for short
time, Switching from 1C to 1B
Logic 5: In case both incoming lost power, bus I and bus II both lost voltage, it will trip 1VB and
10VB, close 0BVB, go to black start mode, Scenario 4.
4.5. Function of mode 1
The function are: 1, Peak Shaving and Valley Filling, 2, Stabilize Fluctuation,3, frequency regulation,
4, voltage regulation
4.5.1. Peak shaving and valley filling
Because of its fast response and its superior peaking performance of the large-scale battery energy
storage system, in the electricity trough as the load store electrical energy, in the peak period as the power
to release energy, thereby reducing the peak valley load difference, improve the economy and safety of
power grid operation. This function can be set as “Local” or “Remote” mode. In remote mode, according
to the power plan curve transmitted by the main station (EMS), the energy storage charge and discharge
power are controlled. In local mode, the stored charge and discharge power are controlled in accordance
with the planned curve value set by this controller. The local planning curve can be formulated according
to the peak and valley price. [7-8]
4.5.2. Stabilize fluctuation
Photovoltaic output is affected by light intensity and has fluctuation characteristics. Especially in the
grid connected state, it is always in the MPPT control mode, and the change of light intensity has a great
influence on the PV output. The fast charging and discharging characteristics of the energy storage
battery can be used to stabilize the fluctuation of PV output. The fluctuation control is divided into first
order filtering control method and average filter control method according to the algorithm.
4.5.3. Frequency regulation
The Microgrid controller will detect the frequency of power grid, it will based on the offset of the
frequency, and calculate the power output of BESS bessP according to the Droop characteristic equation
and SOC of BESS, and send the power control command to BESS.
4.5.4. Voltage regulation
Voltage regulation use the controller to detect the voltage of power grid, according to the offset of the
voltage, and calculate the reactive power output of BESS bessQ
according to the Droop characteristic
equation , and send the reactive power control command to BESS.
4.6. Black start
Microgrid controller detect the open position of 1VB and 10VB, MGCC trip SW6 and SW7, limit the
139
load within 3MW via load shedding which the trip matrix is provided in the setting, the above process
will finish in 1 minute.
And then start the BESS via VSG mode, after the system voltage has been set up, then start the diesel
generator via parallel mode, after diesel generator start finish , BESS switch to PQ mode,diesel
generator check the voltage and frequency fluctuation and switching to main source mode. Then it will
automatic connect the load which has been shedding by black start.
4.7. Load recovery
In Microgrid controller will have the setting for control prohibit, when manually open or close the LBS,
and not allow Microgrid controller to automatically open and close the LBS, need control in the
Microgrid EMS to prohibit the control for LBS. Local switch at the LBS panel should be one of the input
of prohibit the control for LBS
When FLISR function isolate the fault via trip the LBS will automatically prohibit automatic control
for Microgrid controller, when the fault recover by operator, need cancel the prohibit control command in
the HMI.
Load recovery time will be set in the Microgrid controller, after the time (since it has been shedding)
finish the load will not recover to ensure the safety consideration. The maximum setting of this time will
be consider as 10 minutes.
4.8. Intentional grid connecting to island (Scenario 2)
The control center or Microgrid EMS issues the island instruction. Then the MGCC receives the island
instruction. It will start the diesel generator via parallel mode first to be ready for island mode. it will
limited the tie line power to ensure that the tie line active power and reactive power is restricted in the
allowable range via control the diesel generator and BESS, In case BESS and diesel power output is
lower than the load, need shed some load and send trip command for the LBS and send mode switching
commands to switch the diesel generator to island mode. [9-10]
4.9. Island to grid connecting
In case the island is from the intentional island command, it will not automatically connect back the
grid even the voltage of grid side is normal. In case the island is not from the intentional island command,
after the Microgrid controller detect the voltage of power grid side has recovered, it will control the
voltage and frequency of diesel generator, the voltage and frequency of Microgrid side to synchronize
close the LBS to connect back the power grid. After connect back to grid, change the diesel generator
back to parallel mode.
5. Conclusions
The key issue for access for big scale distributed renewable energy is the voltage stability and power
quality issue due to the unstable of the power generation of distributed renewable energy such as PV or
wind farm. Microgrid is a locally controllable power system composed of distributed generation
(Wind/Solar/Diesel, etc), energy storage and load, which can be connected to bulk power system and
islanding operation and it is also an autonomous system to realize control, protection and management by
itself, further more it is an efficient way to make full use of distributed generation. This paper introduces
the background of Thailand first MW level smart Microgrid project at Mae Sariang, Chiang Mai Thailand.
A typical topology and function design for Microgrid project at rural area also has been proposed in this
paper which is possible to use in other similar Microgrid project. DIgSILENT PowerFactory is used to
simulate the power system study of the area for the purpose of function design and relay setting
calculation. Finally, the microgrid system can increase reliability and stability, reduce SAIDI and SAIFI
and reduce greenhouse gas emission. Consequently, Mae Sariang district becomes green community.
140 International Journal of Smart Grid and Clean Energy, vol. 10, no. 2, April 2021
Zhu Xianwen et al.: Design and development of first MW-level microgrid in Thailand
Conflict of Interest
The authors declare no conflict of interest.
Author Contributions
A, C conducted the research; B analyzed the data; A, C wrote the paper; all authors had approved the
final version.
Acknowledgements
First and foremost, I would like to show my deepest gratitude to my adviser, Dr. Suttichai
Premrudeepreechacharna, a respectable, responsible and resourceful scholar, who has provided me with
valuable guidance in every stage of the writing of this paper. Without his enlightening instruction,
impressive kindness and patience, could not have completed my paper. His keen and vigorous academic
observation enlightens me not only in this paper but also in my future study. Last but not least, I' d like to
thank all my friends for their encouragement and support.
References
[1] Tirapong K, Patompong B, Titti B. PEA Microgrid design for coexistence with local community and environment: Case study
at Khun Pae village Thailand. IEEE Innovative Smart Grid Technologies-Asia (ISGT-Asia), 2017; (1-5).
[2] Suttichai P . Microgrid controller: Control and operation- Thailand IEEE,Session 3.2 13 Sep 2018.
[3] Haobin Z, Guangfu X, Xianwen Z, Qunbing Y, Jun C, Xu L. Microgrid coordinated control system with VSG-CIRED
Workshop - Ljubljana, 7-8 June 2018.
[4] NR Electric Co., Ltd. PCS-9617MG Microgrid controller, 2017.
[5] IEEE Standard for Interconnecting Distributed Resources with Electric Power Systems, IEEE std 1547-2003-2014.
[6] Li FS, Li RS, Zhou FQ. Microgrid Technology and Engineering Application, Academic Press, 2016.
[7] Moghimi M, Leskarac D, Panchal C, Lu J, Stegen S. Energy management system for peak shaving in an experimental
microgrid employing MILP optimization. International Journal of Engineering and Innovative Technology (IJEIT), January
2018.
[8] Estefanía P, Jon A, José IG, Iñigo Martínez de A, Edorta I. AC and DC technology in Microgrids: A review. Renewable and
Sustainable Energy Reviews, Mar, 2015; 43: 726- 749.
[9] Loh PC, Ding L. Chai Y, and Blaabjerg F. Autonomous operation of hybrid microgrid with AC and DC subgrids. IEEE Trans.
Power Electron., May 2013; 28(5): 2214-2223.
[10] Cho C, Jeon JH, Kim JY et al. Active synchronizing control of a microgrid. IEEE Trans. Power Electronics. 2011; 26(12):
3707-3719.
Copyright © 2021 by the authors. This is an open access article distributed under the Creative Commons Attribution License (CC
BY-NC-ND 4.0), which permits use, distribution and reproduction in any medium, provided that the article is properly cited, the use
is non-commercial and no modifications or adaptations are made.
141