10/31/2013
1
Demystifying LEED for Homes
v4.0
Jay Hall
Jay Hall & Associates, Inc.
October 31, 2013
Overview
1. Process Changes
2. Rating System Changes
3. Examples
10/31/2013
2
Process V4 Roll-Out Schedule
1. Immediately Can begin to use V4
2. Nov/Dec 2013 v4 Resources Available
3. Jan 2014 EA 1 Ballot (HERS 70 max.)
4. Spring 2014 EA 1 Required
5. Summer 2015 V4 Required (2008 phased out)
1.
2013 2014 2015
2. 3. 4. 5.
Process Admin.
Fees See checklist
Registration https://www.usgbc.org/leedonline/homes/
Green Raters http://www.usgbc.org/people/green-raters
Providers http://www.usgbc.org/organizations/members/homes-providers
Certification
10/31/2013
3
Process Tools
Checklist www.usgbc.org/resources/homes-v2008-checklist-xls
Rating System http://www.usgbc.org/resources/leed-homes-v2008-current-version
http://www.usgbc.org/sites/default/files/LEED%20v4%20for%20Homes%20and%20Midrise_Ballot%20Version.pdf
CIRs http://www.usgbc.org/leed-interpretations
Reference Guide http://www.usgbc.org/resources/leed-homes-reference-guide
USGBC LEED v4 Webinars http://usgbc.peachnewmedia.com/store/seminar/seminar.php?seminar=21420
10/31/2013
4
Rating System Basic Structure
General Changes
1. 110 Points Total (from 136)
2. Credit names are familiar
3. Order (numbering) is very different
a. Prereqs are pulled out front (p1, p2, etc.)
b. Credits follow (c1, c2, etc.)
4. Single Family, Low-Rise and Mid-Rise are Combined.
5. Bottom Line: Projects will lose one certification level.
10/31/2013
5
Rating System Basic Structure
Certification Levels (% of Total Points) 2008 V 4.0 S / M / L S / M / L
Certified 26%/33%/40% 27%/36%/45%
Silver 36%/43%/51% 36%/45%/54%
Gold 48%/55%/62% 45%/54%/63%
Platinum 59%/66%/73% 63%/72%/82%
S = 950 Sq. Ft., 2 Bedroom
M = 1,900 Sq. Ft., 3 Bedroom
L = 3,820 Sq. Ft., 4 Bedroom
Rating System Basic Structure
Credit Categories
2008 v 4.0 Pts/Prereq/Min Pts/Prereq/Min
ID 11 / 3 / Moved LL 10 / / LT 15 / / 8 (LT+EA) SS 22 / 2 / 5 SS 7 / 2 / WE 15 / / 3 WE 12 / 1 / 3 EA 38 / 2 / EA 38 / 4 / MR 16 / 3 / 2 MR 10 / 2 / EQ 21 / 7 / 6 EQ 16 / 7 / 3 AE 3 / 1 / Gone Innov. 6 / 1 / RP 4 / / Total 136 / 18 / 16 110 / 17 / 14
10/31/2013
6
How Many Changes? Credit
Category 2008 Removed Version 4.0
Total # Measures
Same Moved Changed New Total #
Measures
ID (IN) 11 1 6 2 (Top,EA) 3 7
LL (LT) 10 2 5 3 1 7
SS 15 2 3 (LT,WE) 5
WE 8 4 1 3 1 4
EA 6 2 3 5 9
MR 9 4 4 1 (EQ) 1 6
EQ 25 9 10 6 3 14
AE 4 3 1(EA) 0
Total 107 27 29 7 16 10 60
ID (IN/RP) 2008 Version 4
# Name # Comment
1.1 Preliminary Rating IN p1 MOVED
1.2 Integrated Project Team
IP c1 (1) SAME / COMBINED
1.4 Design Charrette
NEW Trades Training
1.3 LEED AP Homes IN c2 MOVED
1.5 Building Orientation for Solar EA c5 MOVED / CHANGED
2.1 Durability Planning REMOVED
2.2 Durability Management MR p2 MR c1
MOVED / CHANGED ESH v3 2.3 Third Party Durability Verif’n
3 Innovation #1 - 4 IN c1 MOVED (5 pts.)
RP 1-4 NEW Regional Priority (4 pts.)
10/31/2013
7
LT (LL) 2008 Version 4
# Name # Comment
1 LEED ND LT c1 (1) CHANGE: 15 Points
2 Site Selection
LT C2
COMBINED PATH 2: (8 pts)
ADDED: Street Network
3.1 Edge Development REMOVED
3.2 Infill ADDED: Bicycle Network/Storage
3.3 Previously Developed PATH 1: (4 pts.)
4 Existing Infrastructure REMOVED
5.1 Basic Community Resources
LT c4 COMBINED 5.2 Extensive Community Resources
5.3 Outstanding Community Resources
6 Access To Open Space
LT c5 NEW: Access to Public Transit
SS 6 Compact Development LT c3 SAME (3 pts.)
SS 2008 Version 4
# Name # Comment
1.1 Erosion Controls – Construction SS p1 SAME (except > 1 acre)
1.2 Minimized Disturbed Area REMOVED
2.1 No Invasive Plants SS p2 SAME
2.2 Landscaping REMOVED
2.3 Limit Turf WE c3
MOVED / COMBINED (Reduced from 5 to 4 pts.)
2.4 Drought Tolerant Plants
2.5 Outdoor Water Demand Calc. WE c1 MOVED / CHANGED
3 Local Heat Island Effects SS c1 CHANGED: Includes Roof
10/31/2013
8
SS (cont’d) 2008 Version 4
# Name # Comment
4.1 Permeable Lot
SS c2 COMBINED / CHANGED: Includes Area under Roof (Reduced 7 to 3 pts max.)
4.2 Permanent Erosion Controls
4.3 Roof-Run-Off (Quality Control)
5 Non-Toxic Pest Control SS c3 SAME
6 .1 Moderate Density
LL c3 Moved (Reduced from 4 to 3 pts.)
6.2 High Density
6.3 Very High Density
WE
2008 Version 4
# Name # Comment
1.1 Rainwater Harvesting
MOVED: to c1 (below) 1.2 Graywater Reuse System
1.3 Municipal Recycled Water
2.1 High Efficiency Irrigation System REMOVED
2.2 Third Party Inspection
2.3 Reduce Overall Irrig’n Demand MOVED: to c1 (below)
3.1 High Efficiency Fixtures c2
CHANGED WaterSense 3.2 Very High Efficiency Fixtures
p1 NEW: Water Metering
c1 NEW: Total Water Use (Reduced from 16 to 12 pts.)
SS 2 Landscaping (Turf / Plants) c3
CHANGED: Outdoor Water Use (≤ 60% Turf & ≥ 25% Native Plants) (Reduced from 9 to 4 pts. Including Irrigation)
10/31/2013
9
EA Prereqs
2008 Version 4
# Name # Comment
1.1 Meet ENERGY STAR Homes v2 EA p1 CHANGED: ESH v3
1.2 Exceed ENERGY STAR Homes v2 EA c1 CHANGED: ESH v3
EA p2 Energy Metering (MF: every unit)
EA p3 MOVED: from AE 1.1 Education of Homeowner
EA Performance Path
Option 1: LEED Energy Budget (MBtu/yr) Modeled annual energy usage < LEED Energy Budget
where: LEED Energy Budget is based on the ENERGY STAR for Homes version 3 (with several modifications).
1 Point per 1-3% < ESH v3
Option 2: HERS Index w/ Home Size Adj. Modeled annual energy usage < HERS 75
1 Point per 1-3 HERS Index Points < 75 Home Size Adjuster:
+1 point per 4% decrease in CFA < ESH v3 benchmark home
-1 point per 4% increase in CFA > ESH v3 benchmark home
10/31/2013
10
EA (cont’d) for Both Performance and Prescriptive Paths
2008 Version 4
# Name # Comment
EA 7.1 Hot Water Distribution
EA c2
CHANGED: New PERF. Test Option
COMBINED: (5 pts.)
EA 7.2 Pipe Insulation
EA c3 Active Solar Ready Design (not available if PV installed)
EA 11.2 Refrigerant Charge Testing EA c4 HVAC Start-up Credentialing (ESH v3 HVAC Checklist) (+1 Pt.)
EA c5 Advanced Utility Tracking (Option 2: BPP)
EA (cont’d) Prescriptive Path
2008 Version 4
# Name # Comment
ID 1.5 Building Orientation for Passive Solar
EA c5 NEW (3 pts.)
2. Insulation EA c7 CHANGED 10/20% > IECC 2012; Grade I
3 Air Infiltration EA c6 SAME (ACH50 or CFM50/SF)
4 Windows EA c8 CHANGED
5 Duct Leakage EA c10 SAME Small AND Large Home Criteria
6 HVAC Equipment EA c9 SAME Pts for EE Heating OR EE Cooling
10/31/2013
11
EA (cont’d) Prescriptive Path
2008 Version 4
# Name # Comment
7.3 Water Heating Equipment EA c11 SAME
8 Lighting EA c12 CHANGED Calcs Required (W/SF, or % Red’n) All Exterior – Dark Sky Qualified
9 Appliances EA c13 SAME Clothes Washer moved to WE c2
10 Renewables EA c14 CHANGED 1 pt per 50 KWh (Reduced from 10 to 4 pts. max.)
11.1 Refrigerant Charge Test EA p1 COMBINED: ESH v3
11.2 Refrigerant – R 410a (Puron) DELETED
MR 2008 Version 4
# Name # Comment
1.1 Framing Order Waste Limit DELETED
1.2 Detailed Framing Docs DELETED
1.3 Detail Cut List & Lumber Order DELETED
1.4 Framing Efficiencies MR c2 CHANGED (Reduced: 4 to 2 pts.)
1.5 Off-Site Fabrication DELETED
2.1 FSC Tropical Wood MRp1 SAME
2.2 Envir. Preferable Products MRc3 CHANGED Fewer Options (4 pts.)
Low Emitting Products MOVED EQ c7 (3 pts.)
3.1 Construction Waste Management DELETED
3.2 Construction Waste Reduction MR c4 CHANGED Tied to Home Size
ID 2.2 Durability Management MR p2 CHANGED ESH v3 Water Mgmt.
ID 2.3 3rd Party Durability Verification MR C1 MOVED Durability Verification (+1 pt.)
10/31/2013
12
EQ 2008 Version 4
# Name # Comment
1 ENERGY STAR with IAP REMOVED
2.1 Basic Combustion Venting EQ p2 CHANGED: Fireplace - Closed Combustion OR Combustion Safety Test
2.2 Enhanced Combustion Venting EQ c5 Same (EPA Qualified 1 Pt.; None 2 Pts.)
3 Moisture Control REMOVED
4.1 Basic Outdoor Air Ventilation EQ p1 CHANGED ASHRAE 62.2-2010
4.2 Enhanced Outdoor Air Vent’n EQ c1 CHANGED Balanced OR HRV/ERV
4.3 Third Party Performance Testing EA p1 MOVED / COMBINED ESH v3
EQ (cont’d)
2008 Version 4
# Name # Comment
5.1 Basic Local Exhaust EQ p1 COMBINED: 4.1
5.2 Enhanced Local Exhaust EQ c5 COMBINED: 4.2
5.3 Third Party Performance Testing EA p1 MOVED / COMBINED ESH v3
6.1 Room by Room Load Calcs EA p1 MOVED / COMBINED ESH v3
6.2 Return Air /Controls EA p1 MOVED / COMBINED ESH v3
6.3 Air Balancing EQ c3 ESH v3 (+3 Pts.)
10/31/2013
13
EQ (cont’d)
2008 Version 4
# Name # Comment
7.1 Good Filters EQ p5 SAME (MERV 8)
7.2 Better Filters REMOVED
7.3 Best Filters REMOVED
8.1 Contaminant Control – Ducts REMOVED
8.2 Indoor Contaminant Control EQ c2
COMBINED: (0.5 Pt. Each)
8.3 Pre-Occcupancy Flush
EQ (cont’d)
2008 Version 4
# Name # Comment
9.1 Radon Resistant (Zone 1) EQ p4 SAME
9.2 Radon Resistant (Zone 2-3) REMOVED
10.1 No HVAC in Garage EQ p3 COMBINED
10.2 Minimize Pollutants – Garage
10.3 Exhaust Fan Garage EQ c6 COMBINED (1 or 2 pts.)
10.4 Detached / No Garage
11 ETS Control EQ p6 (LR and MR Multi-family only)
12 Compartmentalization EQ p7 EQ c4
CHANGED: 0.23 cfm50 / SF 0.15 cfm50 / SF
MR 2.2 Low Emission Products EQ c7 MOVED
10/31/2013
14
AE / IN / RP
2008 Version 4
# Name # Comment
1.1 Homeowner Education O&M Manual and Training
EA p3 MOVED
1.2 Enhanced Training REMOVED
1.3 Public Awareness REMOVED
2 Education of Building Mgr. MOVED / COMBINED EA p3 (above)
IN MOVED (5 Pts. + 1 Pt. LEED AP Homes)
RP NEW (4 Pts.)
Example Regional Points Vary Regionally
LT c2 Site Selection > 5 / 8 pts. LT c3 Compact Development LT c5 Access to Transit > 1 / 2 pts. SS c3 No Toxic Pest Control EA c1 Exceed ESH v3 > 15 / 29 pts. EA c3 Advanced Energy Tracking EA c6 Building Orientation for Solar
10/31/2013
15
Rating System Major Changes
Removed Prereqs
MR 1.1 Framing Order Waste Factor Limit
MR 3.1 Construction Waste Planning
Rating System Major Changes
New Prereqs
LTp1 Floodplain Avoidance
WEp1 Water Metering
EA p2 Energy Metering
MRp2 Durability Management (ESH v3 Water Management)
EQ p6 ETS (Multi-Family only)
EQ p7 Compartmentalization (0.23 cfm50 / Sq. Ft.)
10/31/2013
16
Rating System Major Changes
Removed Credits (-21 Points) LL 3.1 Edge Development
LL 4 Existing Infrastructure
SS 2.2 Basic Landscape Design
WE 2 High Efficiency Irrigation System
MR 1.2/1.3 Detail Framing Docs / Cut List
EQ 3 Moisture Load Control
EQ 7.2/.3 Better / Best Air Filters
EQ 8.1 Indoor Contaminants at Construction
EQ 10.2 Minimize Pollutants from Garage
AE 1.2/1.3 Enhanced Training / Public Awareness
AE 2 Education of the Building Manager
Rating System Major Changes
ESH V3 Related Changes (-3 pts. net) EA p1 Includes:
EA 11.1 Refrig Charge Testing
EQ 4.3 OA Testing
EQ 5.3 Exhaust Testing
EQ 6.1 Manual D
And Three New Credits:
EA c4 HVAC Start-Up Credentials
MR p2/c1 Durability Mgmnt & Verification
EQ 6.3 Air Balancing (EQ c3: 3 pts)
10/31/2013
17
Rating System Major Changes
New Credits
LTc2 Bicycle Network/Storage (1 Pt.)
WEc1 Total Water Use (12 Pts.)
EA c3 Solar Ready Design (1 Pt.)
EA c4 HVAC Start Up Credentialing (1 Pt.)
EAc5 Advanced Utility Tracking (1 Pt.)
RP Regional Priority (4 Pts.)
Rating System Major Changes
New Credits: Low-Rise Multi-Family Up Front Trade Training (1 Pt.)
LTc5 Access to Transit (2 Pts.)
EQ p6 ETS
EQc4 Enhanced Compartmentalization (1 Pt.)
10/31/2013
18
Example
Scenarios
Rating System Examples
High Level Comparisons (Normalized Scores)
Building Type Market Location 2008 v4
Single Family
Affordable Sub-Urban Gold 55/60
Production Sub-Urban Silver 37/50
Custom Rural Gold 43/60
Low-Rise Multi-Family
Affordable Urban Gold 63/60
Market Urban Gold 51/60
Mid-Rise Multi-Family
Affordable Urban Gold 47/60
Market Urban Gold 48/60
* V4 Certification Thresholds: 40 / 50 / 60 / 80
** Red Text indicates more than one cert level drop.
10/31/2013
19
Example Good News
Small (Affordable) Urban Project Prereqs 17
LT 15 Pts.
SS c3 1 Pt. (Pest Control: 2/12)
WE c2 5 Pts. (Low Flow)
EA p4 10 Pts. (Home Size)
EA c4 1 Pt. (HVAC Credential, ESH)
EA c12/13 4 Pts. (ENERGY STAR L&A)
EQ c2 2 Pts. (No Fireplace)
EQ c6 2 Pts. (No Garage)
Total 40 Pts. (Certified)
Rating System A Little Scary
Large (Custom) Non-Urban Project Prereqs 17
LT 3 Pts. (Avoid Sensitive Sites)
SS c3 1 Pt. (Pest Control: 2/12)
WE c2 5 Pts. (Low Flow)
EA p4 - 10 Pts. (Home Size)
EA c4 1 Pt. (HVAC Credential, ESH)
EA c12/13 4 Pts. (ENERGY STAR L&A)
EQ c2 0 Pts. (Fireplace)
EQ c6 0 Pts. (Garage)
Total 1 Pt. (Not Certified)
10/31/2013
20
Summary Credit
Category 2008 Removed Version 4.0
Total # Measures
Same Moved Changed New Total #
Measures
ID (IN) 11 1 6 2 (Top,EA) 3 7
LL (LT) 10 2 5 3 1 7
SS 15 2 3 (LT,WE) 5
WE 8 4 1 3 1 4
EA 6 2 3 5 9
MR 9 4 4 1 (EQ) 1 6
EQ 25 9 10 6 3 14
AE 4 3 1(EA) 0
Total 107 27 29 7 16 10 60
Summary (cont’d)
Most Beneficial Changes (Points)
LT 1-5 15 Points Available (+5 pts.)
RP 1-4 Regional Priority Points (+4 pts.)
EA c2 DHW Distribution (+3 pts.)
Most Challenging Changes (Extra Effort)
EA p1 ENERGY STAR for Homes (documentation)
EA c1 < HERS 75 for Low-Rise Multifamily Projects
WE c1 Calculation Required for “Total Water Use”
EA c12 Calculation Required EE Lighting