Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site...

43
Demolition of the Former Dartmouth Refinery RemTech 2017 Ramy Rahbani - Imperial Chris Ptak- Tervita

Transcript of Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site...

Page 1: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

Demolition of the Former Dartmouth Refinery

RemTech 2017

Ramy Rahbani - Imperial

Chris Ptak- Tervita

Page 2: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

Agenda

• Background

• Project Overview

• High Level Approach

• Demolition Summary

• Challenging Scope

• Lessons Learned

• Project Closure

• Questions2

Page 3: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

Background

Page 4: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

• Extensive global experience

• Imperial/ExxonMobil Global Demolition Centre ofExcellence

• Imperial and ExxonMobilhave executed manydemolition projects throughout the world

• Canada

• United States

• Australia

• Germany

• Italy

• France

Who we are – Imperial

4

Page 5: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

• Tervita Environmental Services is an industry leader in Remediation, Demolition and Environmental Construction Services leveraging the largest waste management infrastructure in Canada to service oil and gas, industrial and government clients.

• Major Demolition Projects Include

• Mildred Lake Mine Replacement

• Giant Mine Roaster Decontamination and Dismantlement

• Kitimat Industrial Facility

Who we are – Tervita

5

Page 6: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

Site Background

• Refinery overview• Located in Dartmouth, NS

• Start of operations - 1918

• Refinery shut down - 2013

• Refining capacity – 88 KBD

• Property area – ~700 acres

• Marine Terminal operated by Canadian Fuels Operations (CFO)

• Surplus areas transferred to ES in Q4 2014

• Neighbors/surrounding land use

• Water bodies: marine and freshwater

• Residential: 210 houses within 100 m

• Commercial/Industrial

• Superior Propane, CN Rail

• Shearwater – military base and airstrip

Page 7: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

Project Overview

Page 8: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

Project Scope

8

Page 9: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

Project Scope

9

Page 10: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

“Nobody gets hurt”

• Minimize disruptionto the surrounding community

• Regulatorycompliance

• Timely execution of project scope

Project Objectives

10

• Project Safety Credos• “Machine before

human”• “Own your zone”• “Clarify, Simplify, Focus”• “It’s not mean to

intervene”

Page 11: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

• Project Timeline • Q4 2015- Q4 2017

• Site is divided into :• 8 areas (Block 1 to 8)

• ~ 85 sub-areas

• ~37,000 metric tons of steel

• ~18,000 m3 of residual hazardous and non hazardous material

• Extensive asbestos abatement

• 73 tanks (spherical, concrete, steel, etc.) Surplus Area

Scope of Work Highlights

Page 12: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

High Level Approach

Page 13: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

13

Where…How…do you begin?

Page 14: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

14

Site Division, Block Definition

Page 15: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

15

3 phase approach: Verification and Validation, Asbestos Abatement, Demolition

High Level Approach

Verification of zeros

Asbestos Abatemen

t

Demolition of

structures

V&V TeamAbatemen

t TeamDemolitio

n Team

Page 16: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

Demolition Summary

Page 17: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

Sept 2015Contract awarded to Tervita

Sept-Nov 2015Pre-planning activities

Nov 2015 Mobilization and start of demolition activities

Nov 2015 - PresentProgressive demolition ofin-scope areas and debris removal

Dec 2017Demolition completion and demobilization

High Level Timeline

17

Page 18: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

• Workforce consists of 70-80 workers

• 80% of the workforce is local

• Workforce consists of five major contracting organizations

• Extensive safety planning, documentation, and engagement

A day on-site…

18

Page 19: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

• Up to 15 excavators/skid steers/rock trucks

• Up to 3-5 vacuum trucks

• Water trucks and other dust suppression activities executed daily

• Specialty demolition excavator attachments

• Extensive controls that restrict access to

Heavy Machinery

19

Page 20: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

20

• Work Hours: ~300,000 LTD

• 80-90 people on-site daily at peak

• Zero recordable spills/regulatory violations

• Strong focus on machine/human interface (HEEZ/ADZ), zone control, hand protection and JSAs

• 74 Work Execution Plans

• 65 JSAs

Safety Summary

Page 21: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

21

• Cleaning and removal of > 70 Tanks Higher complexity

Steel EFR, Spherical, and concrete tanks

• Successful execution of 72 controlled drops

• ~37,000T of steel processed and shipped

~400 railcars

• ~ 18,000m3 of liquid waste disposed

• ~23,000T of construction debris

• ~1,500T of asbestos abated

Milestones Achieved

Preparation of Steel –Processing

Critical Lift – Stack Removal

Page 22: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

Challenging Scope

Page 23: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

23

• All types IFRs, EFRs, Hard shell

Spherical Tanks

Concrete Tanks

• All sizes and contents 10,000 to 900,000 bbl

Diameters of 5 – 250 feet

Contained crude, sludge, refined

• Different methodologies: Shearing

Torching

Tanks…73 Removed

Page 24: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

24

Tanks 453-454

• 250’ D, 54’ H, ~472,000 bbl

• 2 identical tanks

• Collapsed roof

• Sludge and water

• Methodology

Pump water/sludge mixture out

Pressure water cut door

Drive excavator in, shear roof

Collect remaining sludge

Clean tank

Torch walls

Page 25: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

25

Concrete Tanks

Page 26: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

26

Brick Stack

• 150 feet, structurally compromised

• Methodologies considered Engineered drop via blasting

Top down mechanical via cricket unit

Top down mechanical via crane

Ultra-high reach excavator

Engineered drop via cable pull

Page 27: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

27

• 72 drops: towers, furnaces, stacks

• Height Range: 36 – 200 feet

• Different methodologies: Torching of base structure

Push or pull

Guide wire cutting

• Engineering of drop plans • Protect 3rd parties and live equipment

Drops…72

Page 28: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

28

Process Plant

• Extensive network of vessels and piping

• Major focus of V&V program

• Multiple Engineered Drops

Page 29: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

29

Process Plant Demolition

Page 30: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

30

Engineered Drops – D202

Page 31: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

31

Engineered Drops – T102

Page 32: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

Processing Steel

32

Page 33: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

Lessons Learned

Page 34: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

34

Lessons Learned• Regulatory approval received <1 month before execution Ensure all regulatory approvals and demolition permits are

received ahead of time to avoid potential delays and large financial implications

• Major ACM equipment vulnerable to deteriorate Abate deteriorating ACM during decommissioning stages

• Many different color systems between business units Have a color code system for the different states of remaining

surplus equipment. Implement within site orientation.

• Third party expert consultant conducting QA/QC confirming abatement completion allowed for a transparent removal and straightforward process

Have the consultant who conducted the HAZMAT assessment on-site for QA/QC purposes Full circle

• Lesson Recommendatio

n

Page 35: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

35

Lessons Learned

• Leaks can occur from improperly decommissioned lines Identify every line, cross reference P&IDs, drill all low points,

and use a level when uncertain. Implement spill mitigation control measures

• Residual product easier to pump out during warmer weather Recover product during summer months to reduce waste

removal costs in both tanks and lines

• ACM suspect materials encountered during demolition were at times treated as ACM and shipped to expedite process

Be prepared to abate during short duration jobs when ACM suspect materials are unexpectedly encountered.

• Successful relationship with community resulted in smooth execution

Ensure to have a pre-established schedule for community meetings, and plans to deal with any inquiries in a timely and effective manner.

• Lesson Recommendatio

n

Page 36: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

Project Completion

Page 37: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

• Active terminal

• Continued terminaloptimization

• Environmental siteassessmentactivities

• No plans for future development

• Annual communitymeetings

• Continue to play an activerole in the community

Post Demolition

37

Page 38: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

Post Demolition

38

Page 39: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

39

Process Plant – Before and After

Page 40: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

40

Marine Area – Before and After

Page 41: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

41

East Tankfield – Before and After

Page 42: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric

New Tenants

Page 43: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric