Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low...
Transcript of Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low...
![Page 1: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/1.jpg)
Demand Driven Materials Requirements Planning (DDMRP)
Can DDMRP be a game-changer in supply chain planning?
Leo Ducrot and Ehtesham Ahmed. SCMb 2019 Advisors: Dr Tugba Efendigil, Dr Sergio Alex Caballero
![Page 2: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/2.jpg)
Sponsors
Advanced Planning System Provider
Industrial partner (investigating DDMRP)
Institute developing and promoting DDMRP
![Page 3: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/3.jpg)
13%service level
-20%inventory
Motivation: Can DDMRP be a game changer?
-48%leadtime reduction
DDMRP average result :
Can these numbers be achieved in all industries?
![Page 4: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/4.jpg)
Motivation: Can DDMRP be a game changer?
service levelinventory leadtime reduction
Financial impact:
ROI
![Page 5: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/5.jpg)
What is DDRMP?
DDMRP is a multi-echelon supply chain planning approach that combines the best of lean, MRP, six-sigma and the theory of constraints
2 3 4 51Position Protect Pull
Strategic buffer
positioning
Buffer profiles
Dynamic adjustments
Demand driven
planning
Execution and
priorities
![Page 6: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/6.jpg)
What is DDMRP?
DDMRP Leverages decoupling points to make the planning problem easier!
Coupled MRP Decoupled DDMRP
![Page 7: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/7.jpg)
What is DDMRP?: Inventory buffers
Top Of Green
Define the order size and the order frequency
Provides inventory over lead time
Protect against variability
Top Of Yellow
Top Of Red
80
100
50
Buffer levels (in product unit)Order volum
e
![Page 8: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/8.jpg)
What is DDMRP?: Run chartVo
lum
e p
rodu
ct u
nit
Time (days)
Example of DDMRP run chart
Sum of TOPOFGREEN Sum of TOPOFYELLOW Sum of TOPOFRED Sum of NETFLOWPOSITION
![Page 9: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/9.jpg)
What is in for me?
Could that work inmy company?
![Page 10: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/10.jpg)
Problem Setting and Research Question
DDMRP uses decoupled points to create a more stable and suitable environment for MRP. Would that bring better results than a APS?
Capacity Constraint Sourcing decision Shelf-life Constraint
Research Question: What would be the added value of DDMRP in finite capacity planning under uncertainty?
![Page 11: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/11.jpg)
Methodology
Qualitative/ Quantitative part: What was the impact of DDMRP on companies that implemented it?
Simulation analysis: Let’s compare KPIs of plans made with APS and DDMRP
Inventoryturn
Service Level
Interviews: A few companies, in-depth investigation
Survey: Many companies, targeted questions
Simulation: Comparing APS and DDMRP in a controlled environment
![Page 12: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/12.jpg)
Could it work for my company: Size
17% 46%
> $10 BAnnual revenues <= $100 M > $100M <= $500M
Proportion 29%
![Page 13: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/13.jpg)
Could it work for my company: Legacy system
MRP APS
23%
-23%
-55%
7%
-13%
-26%inventory
Customer lead time
service level
![Page 14: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/14.jpg)
Could it work for my company: Maturity level
23%
-22%
-47%inventory
Customer lead time
service level 6%
-16%
-29%
![Page 15: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/15.jpg)
Could it work for my company?
It looks like it is applied everywhere!
![Page 16: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/16.jpg)
Could it work for my company?
Can DDMRP handlemy operational
constraints?
![Page 17: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/17.jpg)
Could it work for my company: Sourcing decisions
Moderately Effective
Effective
All respondentsRespondents with sourcing
decisions
27%54%
38%46%
Sourcing decision
![Page 18: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/18.jpg)
Could it work for my company: shelf-life limitations
Moderately Effective
Effective
All respondentsRespondents with shelf-life
limitations
29%42%
38%46%
Shelf-life Constraint
![Page 19: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/19.jpg)
Could it work for my company: Finite capacity
Capacity Constraint
Moderately Effective
Effective
All respondentsCapacity
constraints respondents
15%58%
18%73%
![Page 20: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/20.jpg)
Could it work for my company: DDMRP or APS
80.0%
85.0%
90.0%
95.0%
100.0%
0 20 40 60 80 100 120
Service Level VS Inventory Turns Scenario 1
APS Heuristic Scenario 1
APS Solver Scenario 1
DDMRP Scenario 1
80.0%
85.0%
90.0%
95.0%
100.0%
0 20 40 60 80 100 120
Service Level VS Inventory Turns Scenario 2
APS Heuristics Scenario 2
APS Solver Scenario 2
DDMRP Scenario 2
DDMRP outperforms the
heuristic-based planning
Results are similar to the
solver
DDMRP is more robust to
capacity constraint than
the heuristic
The solver is overall more
robust
Optimal corner
Less ca
pa
city
![Page 21: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/21.jpg)
80.0%
85.0%
90.0%
95.0%
100.0%
0 20 40 60 80 100 120
Service Level VS Inventory Turns Scenario 4
APS Heuristics Scenario 4
APS Solver Scenario 4
DDMRP Scenario 4
Could it work for my company: DDMRP or APS
80.0%
85.0%
90.0%
95.0%
100.0%
0 20 40 60 80 100 120
Service Level VS Inventory Turns Scenario 3
APS Heuristic Scenario 3
APS Solver Scenario 3
DDMRP Scenario 3
DDMRP outperforms the heuristic-based planning
Results are similar to the solver
The solver is overall more robust
Less capacity
![Page 22: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/22.jpg)
Could it work for my company: DDMRP or APS
KPIsEasy to understand
APS heuristic APS solver DDMRP
Easy to maintainNon-trivial solutions
Operational constraints
![Page 23: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/23.jpg)
DDMRP and the operations
0%20%40%60%
80%100%
PlanningStability
Clearpriorities
Better controlover the
operations
Smootherdependent
requirements
Relevantinformation
Improvements in the operations with DDMRP
Agree Neither Agree nor Disagree Disagree Cannot Say
Graph showing the frequency of the answer
![Page 24: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/24.jpg)
DDMRP streamlines operations
Education program across the company
Educate everyone on the basic of flow
Align objectives
DDMRP implementations lead to streamlined operations across the internal supply chain
![Page 25: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/25.jpg)
Could it work for my company?
It seems like DDMRP can handle complex
operationalconstraints!
![Page 26: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/26.jpg)
Conclusion: What is the added value of DDMRP?
Easy planning method that can have a positive financial impact and provides a competitive edge
Provides results similar to a mathematical solver
Streamline the operations
![Page 28: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/28.jpg)
Literature review: Current state
MRP APS DDMRP
Current literature available
1965 1990’s 2011
Project scope PhD thesis
![Page 29: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/29.jpg)
Problem setting: DDMRP planning principles
80
120
70
0
50
100
150
200
250
300
Quantity toreplenish
Only use Customer order
Adapt the system (Portfolio, capacity, buy-make) to the desired future
Order book Cumulative leadtime Long time future
80
120
70
0
50
100
150
200
250
300
Set up buffers according to anticipated future
Use forecasts
![Page 30: Demand Driven Materials Requirements Planning (DDMRP) · MRP requires stable demand signal and low operational variability. Hypothesis are no longer valid Hypothesis are no longer](https://reader034.fdocuments.in/reader034/viewer/2022042623/5fae98746f947d509974c17a/html5/thumbnails/30.jpg)
Problem setting: Hypothesis of MRP
MRP/APS
1 coupled plan
Long leadtimesVariability passed on between levels
DDMRP
Multiple decoupled plans
Shorter (decoupled) leadtime
Reduced variability
MRP requires stable demand signal and low operational variability.
Hypothesis are no longer valid Hypothesis are no longer valid