Delta System Limited

download Delta System Limited

of 81

Transcript of Delta System Limited

  • 7/30/2019 Delta System Limited

    1/81

    APPLICATION FOR FINANCIAL ASSISTANCEFROM

    EQUITY AND ENTREPRENEURSHIP FUND (EEF)

    BANGLADESH BANK

    DELTA SYSTEMS LIMITED

    CORPORATE OFFICE :

    8 Panthapath, Level-14

    Unique Trade Center (UTC)

    Tejgaon, Dhaka.

  • 7/30/2019 Delta System Limited

    2/81

    GENERAL CONTENTS

    PART I : APPLICATION FOR FINANCIAL

    ASSISTANCE FROM THE EEF UNIT,

    BANGLADESH BANK

    PART II : FEASIBILITY REPORT ON DELTASYSTEMS LIMITED

    PART III : MEMORANDUM & ARTICLES OF

    ASSOCIATION OF DELTA SYSTEMS

    LIMITED

  • 7/30/2019 Delta System Limited

    3/81

    PART I

    APPLICATION FOR FINANCIAL ASSISTANCEFROM

    THE EQUITY & ENTREPRENEURSHIP FUND (EEF)BANGLADESH BANK

  • 7/30/2019 Delta System Limited

    4/81

    Bank/DFI/EEF Unit

    Application Form For Financial Assistance For a New Project

    1.0 Proposed Project :

    1.1 Name of the Project : Delta Systems Limited

    1.2 Address :

    a. Corporate Office : 8 Panthapath, Level-14

    Unique Trade Center (UTC)

    Tejgaon, Dhaka.

    b. Project Office : 153/1, Green Road.

    Dhaka-1205.

    2.0 Promoters :

    2.1 Particulars of the Promoters :

    Name Address Status

    Engr. Bellal HossainShikder

    House # 8, Road # 12Dhanmondi, Dhaka.

    ManagingDirector

    Engr. Faizul Hoque

    Shikder

    7D, House # 5/Kha, Shatmosjid

    Road, Mohammadpur, Dhaka.Director

  • 7/30/2019 Delta System Limited

    5/81

    2.2 Bio-data of the Promoters

    (Sponsors/Directors)

    : Furnished as per

    Form1 (enclosed)

    2.3 Personal Networth Statement

    of the Promoters

    : Furnished as per

    Form2 (enclosed)

    2.4 Declaration of particulars of

    sister/allied concern (s)

    : Furnished as per

    Form3 (enclosed)

    2.5 Specimen of the letters addressed

    to the bankers of the Promoters

    : Enclosed.

    3.0 TESTS OF PROJECTS VIABILITY:

    In appraising the project, the viability tests have been made, as

    follows, on the basis of the factors and/or aspects prescribed inForm5:

    3.1 Appraisal of the Sponsors/Entrepreneurs :

    The overall management and operation of the project will be under

    the joint supervision and guidance of the promoters as mentionedearlier. A brief description of background and experience of all the

    sponsors is furnished hereunder :

  • 7/30/2019 Delta System Limited

    6/81

    Engr. Bellal Hossain Shikder :

    The Managing Director of the Company Engr. Bellal Hossain Shikder,

    aged 39, is a B. Sc. in Civil Engineering from BUET and also an MBA

    form the University of Dhaka.

    He is a well experienced in Information Technology (both hardware &

    software). He has been running business in this sector for more than

    one year and has already achieved remarkable success. His success

    in the relevant sector made him confident enough to take up a

    venture in larger shape.

    Engr. Bellal Hossain is a social worker and he is engaged in various

    socio-cultural activities.

    Engr. Faizul Hoque Shikder :

    Engr. Faizul Hoque Shikder, aged 27 is a B. Sc. in Agricultural

    Engineering and an M. Sc. in Food Technology. He is a Director of the

    Company. He is an experienced businessman in IT sector, who has

    been doing this business for more than one year.

    Engr. Faizul Hoque is a young, dynamic person who is devoted to

    business in IT sectors. He is very much enthusiastic and confident

    about success in IT related businesses.

    Engr. Faizul Hoque is a good organizer and social worker. He is a

    popular person in his community and spends time to do social well

    being.

  • 7/30/2019 Delta System Limited

    7/81

    3.2 Technical, Technological and Environment Tests :

    The project has been designed mainly for developing computer

    software and selling the same at both local and foreign

    markets/buyers. The software have been getting an increasing

    demand day by day, but the supply situation (production of software)

    has not been at a level in relation to demand. For this reason, there

    prevails a demand-supply gap (i.e. supply deficiency) in this sector,

    especially in the western countries.

    The main and the most valuable component of the software industry

    is the IT professionals. Fortunately, Bangladesh is enriched with this

    type of professionals who possess the highest brilliance and excellent

    ideas/innovations. But this is yet to be focused in the international

    arena. And if this can be highlighted before the world, it could be a

    great source of foreign currency for the country.

    The project is environment friendly. So, it will put no adverse effect

    on the environment. Rather, it is likely to create employment for a

    good number of educated people and thus will play a satisfactory

    socio-economic role.

    The project is of utmost priority set by the present Government with

    a view to developing the software sector, which will ultimately

    contribute significantly in the economic development of the country.

  • 7/30/2019 Delta System Limited

    8/81

    3.3 Financial Feasibility:

    The project is financially feasible. This is indicated by the following

    evaluating factors:

    Breakeven point : 60% of

    assumed capacity.

    Internal Rate of Return (IRR) :

    25 %

    Payback period : 5 years

    and 3 months.

    Margin of safety : 40%

    3.4 Projects Return :

    The after-tax return of the project are shown as follows:

    Return on sponsors

    Paid-up capital : 10% (4th year)

    Return on total

    Capital outlay : 5% (4th year)

    Return on assets : 6% (4th

    year)

    So the projects return can be considered to be satisfactory.

    3.5 Ratio Analysis:

    All financial ratios of the project show a comparatively better picture,

    as follows, than the minimum standards set by the EEF Unit of

    Bangladesh Bank :

    FactorsProjects Ratios

    Year-1 Year-2 Year-3 Year-4 Year-5

    Gross profitto sales (%)

    51 40 39 38 38

  • 7/30/2019 Delta System Limited

    9/81

    Operating profitto sales (%)

    18 10 10 12 14

    Net Profitto sales (%)

    13 07 08 09 10

    Debt-service CoverageRatio (times) 2.95 2.57 2.65 2.81 2.99

    Fixed Assets CoverageRatio (times)

    1.83 1.81 1.77 1.72 1.64

    3.6 SWOT Analysis:

    Strengths:

    The project location is an excellent one and it enjoys a good

    communication network with all infrastructure facilities being

    available.

    All the promoters are financially sound and have the affordability

    of equity participation against their respective shareholdings in

    the company.

    The promoters of the project are all highly educated with bright

    academic records. So the project is enriched with the persons

    who are quite sound and capable in business management and

    operational aspects.

    Weakness:

    The software industry in Bangladesh is still at its infant stage.

    People do not come forward to develop this sector mainly due

    to financial incapability and some sort of confusion about its

    prospect.

  • 7/30/2019 Delta System Limited

    10/81

    For competing in the international market, volume and quality

    should be significantly high to achieve the acceptability.

    Opportunities:

    There is a vast market demand of the software, especially in

    the western countries of the world, which is getting an

    increasing shape day by day. So the software developingprojects of the country have a lot to exploit it.

    Talented professionals required to run this type of venture can

    be obtained locally. This will enable the project to have a cost-

    benefit advantage.

    The software project will be socially and economically wellaccepted and environment friendly having no adverse effect on

    the surrounding areas.

    Threats:

    The resourceful brilliant professionals may leave the country forbetter prospect and living standard in absence of their desired

    placement.

    The software project may face struggle to survive in absence of

    vigorous marketing efforts.

  • 7/30/2019 Delta System Limited

    11/81

    Political unrest may cause some problem in case of the

    projects desired progression.

  • 7/30/2019 Delta System Limited

    12/81

    4.0 CORPORATE SET-UP/CONSTITUTION:

    4.1 Corporate Set-up : Private Limited Company4.2 Date of incorporation : 27.01.01

    4.3 Certificate of incorporation : Copy enclosed, duly certified by theManaging Director of the company.

    4.4 Memorandum & Articles ofAssociation of the Company

    : Copy enclosed, duly certified by theManaging Director of the Company.

    4.5 TIN of Directors of theCompany and sister concerns

    : Copy of certificates enclosed.

    5.0 PARTICULARS OF THE PROJECT:

    Feasibility Report on the project containing the particulars prescribed

    in the Application Form of the EEF Unit of Bangladesh Bank has beenprepared and enclosed hereto.

    We do hereby solemnly declare and affirm that the statement andinformation furnished in this Application and the Forms and the

    Feasibility Report enclosed herewith are correct and true, and nothinghas been concealed therefrom, and if at any time it transpires that

    we have suppressed any fact and/or supplied wrong information, weshall be held liable therefor. We agree to furnish you any further

    information as may be required by the Bank/DFI.

    Name and Designation Signature

    1. Engr. Bellal Hossain Shikder ___________________

    Managing Director

    2. Engr. Faizul Haque Shikder ___________________

    Director

    Date :____________

  • 7/30/2019 Delta System Limited

    13/81

    Form-1(a)

    Name of company:

    BIO-DATA OF THE SPONSORS/DIRECTORS

    01. Name : Engr. Bellal Hossain Shikder

    02. Fathers Name : Late Shyad Ali Shikder

    03. Mothers Name : Nurzahan Begum

    04. Nationality : Bangladeshi

    05. Age/Date of birth : 01.03.1964

    06. Address :

    a) Present : House # 8, Road # 12

    Dhanmondi, Dhaka.

    b) Permanent : House # 8, Road # 12

    Dhanmondi, Dhaka.

    07. Home district : Bagerhat.

    08. Educational Qualification : B. Sc. in Civil Engineering from BUET.

    MBA from the University of Dhaka.

    PHOTO

  • 7/30/2019 Delta System Limited

    14/81

    Form-1(b)

    09. Technical or any other qualifications :

    (a) Information Technology enabled knowledge in both hardware and

    software.(b) Teaching.10. Industrial/Business/Other experience :

    Name ofCompany

    Nature ofBusiness

    Location/Address

    MainProducts

    Position/Jobs

    Durationwith date

    Delta SystemsLtd.

    InformationTechnology

    House # 83/A,Road # 11A,Dhanmondi, Dhaka

    Brand PCi-friend &software

    ManagingDirector

    Since27.01.01

    Delta School ofMathematics

    PrivateEducation

    House # 83/A,Road # 11A,Dhanmondi, Dhaka

    Education Chairman 16 years

    11. Whether associated with any projects financed by Bank/DFI : N/A.

    12. Any other information :

    (a) Earned wide reputation in teaching profession.

    (b) Engaged in various other social & religious activities.

    D E C L A R A T I O N

    I do hereby declare that-

    i) I am a bonafide national of Bangladesh;

    ii) I am not a minor;iii) neither I am nor my spouse is serving with any Government/Semi-

    Government/Autonomous Body; and

    iv) the particulars furnished above are true and correct.

    (Engr. Bellal Hossain Shikder)

    Date :______________ Signature of the Sponsor/Director

  • 7/30/2019 Delta System Limited

    15/81

    Form-1(a)

    Name of company :Delta Systems Limited

    BIO-DATA OF THE SPONSORS/DIRECTORS

    01. Name : Engr. Faizul Hoque Shikder

    02. Fathers Name : Late Shyad Ali Shikder

    03. Mothers Name : Nurzahan Begum

    04. Nationality : Bangladeshi

    05. Age/Date of birth : 01.01.1976

    06. Address :

    a) Present : 7D, House # 5/Kha, Satmasjid Road

    Mohammadpur, Dhaka.

    b) Permanent : Vill + PO: Barabaria

    Chitalmari, Bagerhat.

    07. Home district : Bagerhat.

    08. Educational Qualification : B. Sc. in Agricultural Engineering.

    M. Sc. in Food Technology.

    PHOTO

  • 7/30/2019 Delta System Limited

    16/81

    Form-1(b)

    09. Technical or any other qualifications :

    (a) Diploma in Information Technology from Bhuiyan Academy, Dhaka.

    (b) Information Technology enabled knowledge in both hardware andsoftware.

    10. Industrial/Business/Other experience :

    Name ofCompany

    Nature ofBusiness

    Location/Address

    MainProducts

    Position/Jobs

    Durationwith date

    Delta SystemsLtd.

    InformationTechnology

    House # 83/A,Road # 11A,

    Dhanmondi, Dhaka

    Brand PCi-friend &

    software

    Director Since27.01.01

    Delta School ofMathematics

    PrivateEducation

    House # 83/A,Road # 11A,Dhanmondi, Dhaka

    Education Partner 2 years

    11. Whether associated with any projects financed by Bank/DFI : N/A.

    12. Any other information :

    a) A good social organizer.

    b) Earned reputation in teaching profession.

    c) Engaged in various other social and religious activities.

    D E C L A R A T I O N

    I do hereby declare that-

    i) I am a bonafide national of Bangladesh;

    ii) I am not a minor;

    iii) neither I am nor my spouse is serving with any Government/Semi-

    Government/Autonomous Body; and

    iv) the particulars furnished above are true and correct.

    (Engr. Faizul Hoque Shikder)

    Date :______________ Signature of the Sponsor/Director

  • 7/30/2019 Delta System Limited

    17/81

    Form-2(a)

    PERSONAL NETWORTH STATEMENT

    Name : Engr. Bellal HossainShikder S/O : Late Shyad Ali Shikder

    Address : House # 8, Road # 12Flat # B-5

    Dhanmondi, Dhaka.

    Age :

    Profession :

    Position :

    Marital Status :

    Children :

    39 years

    Business

    Managing Director

    Married

    Male 01 Female --

    For the purpose of obtaining financial assistance from time to time in any form

    whatsoever from the Bank/DFI/EEF, the undersigned submits the following as

    being a true and accurate statement of his financial condition on the date

    mentioned herein and also agree that if any change occurs, the undersigned will

    immediately notify the same to the Bank/DFI/EEF :

    NETWORTH STATEMENT AS ON 10.04.2003

    ASSETS Amount (Tk) LIABILITIES : Amount(Tk)

    CASH :

    a) In hand

    b) With other Banks

    INVESTMENT :

    Government securities,

    Shares, Debenture, Bonds,etc. (Private Investment)

    Debtors

    Real estate (encumbered)

    (Schedule-B)

    Real estate (unencumbered)

    (Schedule-C)

    Cash surrender value forLife Policy

    Others

    7,56,000

    12,00,000

    15,00,000

    20,00,000

    -

    1,20,00,000

    2,50,000

    75,00,000

    Loan from Banks/Financial

    Institutions

    (Schedule-A) :

    SecuredUnsecured

    Other Creditors

    Unpaid Taxes

    Other liabilities

    5,00,000-

    -

    -

    -

    Total : 2,52,06,000 Total : 5,00,000

    Net Worth (Total Assets Total Liabilities) :Tk. 2,47,06,000

  • 7/30/2019 Delta System Limited

    18/81

    Form-2(b)

    Name of company :

    SCHEDULEA : LIABILITIES TO BANKS/FINANCIAL INSTITUTIONS :

    Name & address ofthe Bank/Financial

    Institution

    Date of availing ofthe loan

    Limit with validity Present outstanding Secured with natureof security

    Pubali BankSatmosjid Road,Dhaka

    Dec-2001 Tk 8,00,000 Tk 5,00,00040% of SavingsCertificates held

    SCHEDULEB : REAL ESTATES (ENCUMBERED) : N/A

    Location and

    tenure of

    ownership

    Area of land Description and

    Schedule of the Property

    and type of building

    Mortgage and

    mortgage amount

    Market Price

    Land Building Total

    SCHEDULEC REAL ESTATES (UNENCUMBERED) :

    Location and tenure of

    ownership

    Area

    of land

    Description and Schedule of the

    Property and type of building

    Market Price (Tk in 000)

    Land Building TotalHouse # 8, Road # 12

    Flat # B-5,Dhanmondi, Dhaka.

    1400sft Apartment Building. - 3000 3000

    8 Panthapath, Level-14Green Road, Dhaka.

    2844sft Commercial Building - 8000 8000

    9C, Concord CentreFramgate, Dhaka

    550 sft Commercial Building - 1000 1000

    Total : - - 12000 12000

  • 7/30/2019 Delta System Limited

    19/81

    Form2(c)

    DECLARATION

    (a) I do hereby declare that I do not have liabilities to any Banks/DFIs in

    my name or in the name of any company/concern in which I hold

    interests;

    (b) I do hereby declare that the above named assets are owned by me; and

    (c) I do hereby declare that my Income Tax (Payers) Identification Number

    (TIN) is/are ________________________ and Income Tax liabilities is/are

    cleared up to the assessment year ____________________ (photo copies

    of tax payment documents is/are enclosed).

    The undersigned certifies that the information furnished herein is true and correct.

    (Engr. Bellal Hossain Shikder)Date :_____________ Signature of the Sponsor/Director

  • 7/30/2019 Delta System Limited

    20/81

    Form-2(a)

    PERSONAL NETWORTH STATEMENT

    Name : Engr. Faizul HoqueShikder S/O : Late Shyad Ali Shikder

    Address : 7D, House # 5/KhaSatmasjid Road

    Mohammadpur

    Dhaka.

    Age :

    Profession :

    Position :

    Marital Status :

    Children :

    27 years

    Business

    Director

    Unmarried

    Male -- Female --

    For the purpose of obtaining financial assistance from time to time in any form

    whatsoever from the Bank/DFI/EEF, the undersigned submits the following as

    being a true and accurate statement of his financial condition on the date

    mentioned herein and also agree that if any change occurs, the undersigned will

    immediately notify the same to the Bank/DFI/EEF :

    NETWORTH STATEMENT AS ON 10.04.2003

    ASSETS Amount (Tk) LIABILITIES : Amount(Tk)

    CASH :

    a) In hand

    b) With other Banks

    INVESTMENT :

    Government securities,

    Shares, Debenture, Bonds,etc. (Private Investment)

    Debtors

    Real estate (encumbered)

    (Schedule-B)

    Real estate (unencumbered)

    (Schedule-C)

    Cash surrender value forLife Policy

    Others

    5,00,000

    3,00,000

    5,00,000

    5,00,000

    -

    -

    10,00,000

    Loan from Banks/Financial

    Institutions

    (Schedule-A) :

    SecuredUnsecured

    Other Creditors

    Unpaid Taxes

    Other liabilities

    --

    -

    -

    -

    Total : 28,00,000 Total : -

    Net Worth (Total Assets Total Liabilities) :Tk 28,00,000

  • 7/30/2019 Delta System Limited

    21/81

    Form-2(b)

    Name of company : Delta Systems Limited

    SCHEDULEA : LIABILITIES TO BANKS/FINANCIAL INSTITUTIONS : N/A

    Name & address ofthe Bank/FinancialInstitution

    Date of availing ofthe loan

    Limit with validity Present outstanding Secured with natureof security

    SCHEDULEB : REAL ESTATES (ENCUMBERED) : N/A

    Location and

    tenure ofownership

    Area of land Description and

    Schedule of the Propertyand type of building

    Mortgage and

    mortgage amount

    Market Price

    Land Building Total

    SCHEDULEC REAL ESTATES (UNENCUMBERED) :

    Location and tenure ofownership

    Area ofland

    Description and Schedule of theProperty and type of building

    Market Price (000 Tk)

    Land Building Total

    Total : - -

  • 7/30/2019 Delta System Limited

    22/81

    Form2(c)

    DECLARATION

    (a) I do hereby declare that I do not have liabilities to any Banks/DFIs in

    my name or in the name of any company/concern in which I hold

    interests;

    (b) I do hereby declare that the above named assets are owned by me; and

    (c) I do hereby declare that my Income Tax (Payers) Identification Number

    (TIN) is/are ________________________ and Income Tax liabilities is/are

    cleared up to the assessment year ____________________ (photo copies

    of tax payment documents is/are enclosed).

    The undersigned certifies that the information furnished herein is true and correct.

    (Engr. Faizul Hoque Shikder)

    Date :_____________ Signature of the Sponsor/Director

  • 7/30/2019 Delta System Limited

    23/81

    Form-3Name of the Company : Delta System LimitedBank/DFI/EEF

    Sub : Declaration of particulars of my sister/allied concern(s).

    Dear Sir,

    I do hereby declare that the particulars of my sister/allied concern(s) is/are as

    follows:

    (1) Name of business concern(s) : Delta School of Mathematics

    (2) Name, Fathers Name & Address :

    of the proprietor/partners/Directors : Engr. Bellal Hossain ShikderS/O. Late Shyad Ali Shikder

    House # 8, Road # 12Dhanmondi, Dhaka.

    Engr. Faizul Hoque ShikderS/O. Late Shyad Ali Shikder7D, House # 5/Kha

    Satmasjid Road, MohammadpurDhaka.

    (3) Business address : House # 83/A, Road # 11/A

    Dhanmondi, Dhaka.

    (4) Name of the Banker :

    (5) Position of loans/liabilities : N/A

    Name of loan Amount Present outstanding Security

    - - - -

    I confirm that I have no other sister/allied concern and liabilities beyond those as

    declared herein.

    (Engr. Bellal Hossain Shikder)Date : _____________________ Signature of the Sponsors/Director

  • 7/30/2019 Delta System Limited

    24/81

    Form-3Name of the Company : Delta System LimitedBank/DFI/EEF

    Sub : Declaration of particulars of my sister/allied concern(s).

    Dear Sir,

    I do hereby declare that the particulars of my sister/allied concern(s) is/are as

    follows:

    (1) Name of business concern(s) : Delta School of Mathematics

    (2) Name, Fathers Name & Address :

    of the proprietor/partners/Directors : Engr. Bellal Hossain ShikderS/O. Late Shyad Ali Shikder

    House # 8, Road # 12Dhanmondi, Dhaka.

    Engr. Faizul Hoque ShikderS/O. Late Shyad Ali Shikder7D, House # 5/Kha

    Satmasjid Road, MohammadpurDhaka.

    (3) Business address : House # 83/A, Road # 11/A

    Dhanmondi, Dhaka.

    (4) Name of the Banker :

    (5) Position of loans/liabilities : N/A

    Name of loan Amount Present outstanding Security

    - - - -

    I confirm that I have no other sister/allied concern and liabilities beyond those as

    declared herein.

    (Engr. Faizul Hoque Shikder)Date : _____________________ Signature of the Sponsors/Director

  • 7/30/2019 Delta System Limited

    25/81

    Form-4

    The Manager

    ..................................

    ..................................

    ..................................

    Dear Sir,

    Account No.

    I/We have applied to the EEF Unit, Bangladesh Bank, Dhaka, for financial

    assistance.

    In this connection, I/we hereby authorize you to furnish to them any

    information they may request from you regarding the conduct of the

    account and loans/facilities that have been extended to me/us by your

    Bank.

    (Engr. Bellal Hossain Shikder)

    Signature of Account Holder

  • 7/30/2019 Delta System Limited

    26/81

    Form-4

    The Manager

    ..................................

    ..................................

    ..................................

    Dear Sir,

    Account No.

    I/We have applied to the EEF Unit, Bangladesh Bank, Dhaka, for financial

    assistance.

    In this connection, I/we hereby authorize you to furnish to them any

    information they may request from you regarding the conduct of the

    account and loans/facilities that have been extended to me/us by your

    Bank.

    (Engr. Faizul Hoque Shikder)

    Signature of Account Holder

  • 7/30/2019 Delta System Limited

    27/81

    PART II

    FEASIBILITY REPORTON

    DELTA SYSTEMS LIMITED

  • 7/30/2019 Delta System Limited

    28/81

    CORPORATE OFFICE :

    8, Panthapath, Level-14Unique Trade Center (UTC)

    Tejgaon, Dhaka.

    APRIL, 2003

  • 7/30/2019 Delta System Limited

    29/81

    FEASIBILITY REPORTON

    DELTA SYSTEMS LIMITED

    TABLE OF CONTENTS PART-II

    PROJECT SUMMERY iii

    01. INTRODUCTION 1

    02. ORGANIZATION & MANAGEMENT 3

    03. TECHNICAL ASPECTS 6

    04. MARKETING ASPECTS 12

    05. SOCIO- ECONOMIC ASPECTS 15

    06. FINANCIAL ASPECTS 17

    ANNEXURE :

    I. Cost of the Project 19

    II. Cost of machinery & equipment 21

    Iii. Cost of furniture, fixture & office equipment 22

    IV. Preliminary expenses 23

    V. Working capital 24

    VI. Earning forecast 25

    VII. Sales forecast 26

    VIII. Cost of goods sold 27

    IX. Administrative & selling expenses 30

    X. Break- even analysis 32

    XI. Cashflow statement 33

    XII. Projected balance sheet 34

    XIII. Internal rate of return (IRR) 35

    XIV. Debt- service coverage ratio (DSCR) 36

    XV. Pay- back period 37

    XVI. Margin of Safety 38

  • 7/30/2019 Delta System Limited

    30/81

    PROJECT SUMMARY

    01. Name of the Project : Delta Systems Limited

    02. Location of the Project : The proposed project will be located at

    153/1, Green Road, Dhaka-1205. The

    project site is very much suitable from

    different perspectives and enjoys all

    infrastructure and very good

    communication facilities.

    03. Address : Corporate Office :

    8, Panthapath, Level-14

    Unique Trade Center (UTC)

    Tejgaon, Dhaka.

    Project :153/1 Green Road

    Dhaka-1205.

    04. Project brief : The project envisages setting up of a

    software industry for the development

    and marketing of computer software and

    ICT enabled services, which are of high

    demand both at home and abroad.

    The implementation of the project will

    increase national earnings, make

    significant contribution to GDP and create

    employment opportunity considerably.

  • 7/30/2019 Delta System Limited

    31/81

    05. Corporate setup / status : Private Limited Company.

    06. Name & Address of the sponsors :

    Name Address Status

    Engr. Bellal HossainShikder

    House # 8, Road # 12Dhanmondi, Dhaka

    ManagingDirector

    Engr. Faizul HoqueShikder

    7D, House # 5/Kha, SatmasjidRoad, Mohammadpur, Dhaka

    Director

    07. Cost of the project & Means of finance :

    (Tk. in 000)

    Financing Cost incurred To be incurred Total

    B. B. equity - 17961 17961

    Sponsors equity 5620 13074 18694

    Total capital outlay: 5620 31035 36655

    08. Financial Performance :(Tk. in 000)

    Year-1 Year-2 Year-3 Year-4 Year-5

    Sales revenue

    Gross profit

    Operating profit

    Net profit

    16500

    8408

    3015

    2182

    18150

    7301

    1830

    1325

    19800

    7625

    2075

    1502

    21450

    8218

    2585

    1871

    23100

    8842

    3124

    2262

  • 7/30/2019 Delta System Limited

    32/81

    09. RATIO ANALYSIS :

    FactorsProjects Ratios

    Year-1 Year-2 Year-3 Year-4 Year-5

    Gross profitto sales (%)

    51 40 39 38 38

    Operating profit

    to sales (%)18 10 10 12 14

    Net Profit

    to sales (%)13 07 08 09 10

    Debt-service CoverageRatio (times)

    2.95 2.57 2.65 2.81 2.99

    Fixed Assets Coverage

    Ratio (times)1.83 1.81 1.77 1.72 1.64

    10. BREAK-EVEN POINT : 60 % of assumed capacity.

    11. INTERNAL RATE OF

    RETURN (IRR) : %

    12. PAY-BACK PERIOD : 5 years and 3 months.

    13. MARGIN OF SAFETY : 40 %

    14. Market Outlook :

    The computer software and other IT enabled services have got a vast

    market worldwide. This is getting an increasing trend with the change

    in livelihood and faster job requirements. But there prevails a huge

    demand-supply gap (supply-deficiency) in this sector. So the

    software projects have a lot to exploit this opportunity.

    15. Conclusion :

    From feasibility report of the project it appears that the project is

    technically feasible, commercially viable, financially profitable and

    acceptable from the marketing point of view. And as such it is found

    to be worthwhile and desirable for investment.

  • 7/30/2019 Delta System Limited

    33/81

    FEASIBILITY REPORT

    ONDELTA SYSTEMS LIMITED

    1.0 INTRODUCTION

    1.1 Background :

    Bangladesh is a developing country which is facing numerous

    problems. Among them, unemployment and poverty are the two

    major ones. To solve these problems, we have to look for ways and

    means and also to think of our strengths, weaknesses, opportunities

    and threats.

    If our strengths are first considered, it is evident that our human

    resources, among all others, can be mentioned first. Again, if we talk

    about the ICT Sector, we will be certainly boasted of our brilliant

    professionals.

    But these ICT Professionals and their capabilities are yet to be

    focused in the international arena. If we can properly illuminate them

    before the world, it could be a great source of foreign currency forthe country. To earn foreign currency, we must display the products

    before the world, which our brilliant ICT Professionals can produce

    and which will have worldwide demandofcourse, this is the Software

    and ICT enabled services.

  • 7/30/2019 Delta System Limited

    34/81

    Bangladesh is enriched with so many ICT Professionals who possess

    the highest level of brilliance and excellent ideas and innovations.

    These professionals are certainly the wealth of the nation who have

    the ability to produce different software of international standard to

    suit the customers need and thus can contribute to the economic

    development of the country to a great extent.

    1.2 The Project :

    The proposed project is an attempt to make use of some of these ICT

    Professionals in producing Software for both local and foreign

    markets. The project is also aimed at contributing to the economic

    development of the country.

  • 7/30/2019 Delta System Limited

    35/81

    2.0 ORGANIZATION & MANAGEMENT

    2.1 Name & Location of the Project :

    The proposed project will be established under the name and style of

    Delta Systems Limited to be located at 153/1, Green Road,

    Dhaka-1215 having its corporate office at 8, Panthapath, Level-14,

    Unique Trade Center (UTC), Tejgaon, Dhaka.

    The location of the project is an excellent one from different

    perspectives with all infrastructure and communication facilities being

    available.

    2.2 Nature of the Project :

    The project, by nature, will be a software developing firm. However,

    it will also go on with ICT enabled products/services.

    The software and services to be developed will be sold in foreign as

    well as local markets.

    2.3 Organizational Setup :

    The project is a Private Limited Company formed by the sponsors

    having incorporation from the Registrar of Joint Stock Companies &

    Firms, Government of Bangladesh.

  • 7/30/2019 Delta System Limited

    36/81

    2.4 Particulars of the Sponsors :

    The project will be promoted by the following sponsors :

    Name & Address Status

    Engr. Bellal Hossain ShikerHouse # 8, Road # 12

    Dhanmondi, Dhaka-1205

    Managing Director

    Engr. Faizul Hoque Shikder7D, House # 5/KhaSatmasjid Road, Mohammadpur, Dhaka.

    Director

    2.5 Background & experience of the promoters :

    A brief description of education, technical knowhow & skills,

    experience, etc. of all the promoters of the project are given

    hereunder:

    Engr. Bellal Hossain Shikder :

    The Managing Director of the Company Engr. Bellal Hossain Shikder,

    aged 39, is a B. Sc. in Civil Engineering.

    He is a well experienced in Information Technology (both hardware &

    software). He has been running business in this sector for more than

    one year and has already achieved remarkable success. His success

    in the relevant sector made him confident enough to take up a

    venture in larger shape.

    Engr. Bellal Hossain is a social worker and he is engaged in various

    socio-cultural activities.

  • 7/30/2019 Delta System Limited

    37/81

    Engr. Faizul Hoque Shikder :

    Engr. Faizul Hoque Shikder, aged 27 is a B. Sc. in Agricultural

    Engineering and a Director of the Company. He is an experienced

    businessman in IT sector, who has been doing this business for more

    than one year.

    Engr. Faizul Hoque is a young, dynamic person who is devoted to

    business in IT sectors. He is very much enthusiastic and confident

    about success in IT related businesses.

    Engr. Faizul Hoque is a good organizer and social worker. He is a

    popular person in his community and spends time to do social well

    being.

    2.6 Management :

    The overall management and supervision of the project will be vested

    with the Board of Directors. The Board of Directors will formulate

    policies and will provide necessary guidelines for the day to day

    operation of the project.

    The managing Directors will be responsible to the Board of Directors.

    He will look after the overall business affairs and administration of theproject and will provide all required logistic supports.

    The Managing Director will be assisted by other directors of the

    company. Besides, locally recruited managerial and technical

    personnel will assist hi to run the management and operation of the

    project.

  • 7/30/2019 Delta System Limited

    38/81

    3.0 TECHNICAL ASPECTS

    3.1 Project Purpose and Design :

    The project envisages for setting up of a Software Development

    Industry producing and marketing computer software and ICT related

    products/services.

    The project will be equipped with machinery and equipments to be

    procured from reputed suppliers/manufacturers.

    While designing the project, the requirement of physical facilities has

    been considered in such a manner so that the project can operate at

    its optimum capacity.

    The sales revenue of the project will include mainly the sales of

    computer software. Besides, the project has the plan to make earning

    by way of :

    Software development training.

    Software outsourcing.

    Providing ICT services.

    The fixed cost of the project has been estimated at Tk 332.55 lacs,

    while the total cost thereof at Tk 366.55 lacs.

  • 7/30/2019 Delta System Limited

    39/81

    3.2 Product mix & Production Plan :

    The production plan of the project is as under :

    Products/Services Yr-1 Yr-2 Yr-3 Yr-4 Yr-5

    Capacity utilization 50% 55% 60% 65% 70%

    Software :

    a. Clinic management

    b. Banking

    c. Accounting

    Web Solution :

    a. Domain registration

    b. Web page development &

    designing

    25

    5

    50

    200

    2000

    28

    6

    55

    220

    2200

    30

    6

    60

    240

    2400

    33

    7

    65

    260

    2600

    35

    7

    70

    280

    2800

    3.3 Technology & Process :

    The steps involved in developing software including different phases.

    Every phase demands its own point of view and technology-based

    insight into the matter. The execution begins with the study of the

    requirement, which is also called the system study. After the initial

    thoughts have been gathered, they are put on paper and a final

    logical checkup is performed. Once the logical system is developed,the system is designed and created by programming language.

    Comprehensive testing is done at the end of each subsection of the

    procedure. Once the system is built, proper documentation support

    and help file is provided with the system.

  • 7/30/2019 Delta System Limited

    40/81

    The following diagram shows the technical development steps of

    software products :

    Figure : Typical Development of Software

    Initiation Use

    Requirement

    Specification

    Acceptance

    Tested System

    V & V V & V

    System Integration &System Tested

    System

    V & V V & V

    Code

  • 7/30/2019 Delta System Limited

    41/81

    Since a software product has large number users, it must be properly

    designed, carefully implemented and thoroughly tested. Also, a

    software product consists not only of the program code but also of all

    the associated documents such as requirement specification

    document, design document, test document and user manuals, etc.

    Further, software products are often too large to be developed by any

    individual programmer. Therefore, software products are usually

    developed by a Software Development Team.

    The team consists of different types of personnel with different

    responsibilities like Analyst, Designer, Programmer, ester and the

    Project Manager. The team is led by a Tem Leader and he/she must

    be an active member of the team. Typically the size of the team

    depends on the versatility of the software and the deadline to be met

    by the team. The team members must include a representative from

    the customer side or a domain expert to guide the team in every

    phase of development.

    3.4 Machinery & Equipments :

    A list of the machinery and equipment required for he project has

    been provided in Annexure-II, the total value of which stands at

    Tk 50.00 lacs.

    3.5 Store & Spares :

    The annual requirement of store and spares has been estimated @

    0.5%, 1.0%, 1.5%, 2.0% and 2.5% of the cost of machinery &

    equipment for 1st, 2nd, 3rd, 4th and 5th year of operation

    respectively.

  • 7/30/2019 Delta System Limited

    42/81

    3.6 Repairs & Maintenance :

    The annual cost of repairs and maintenance has been estimated

    @ 0.5%, 1%, 1.5%, 2% & 2.5% from 1st to 5th year of operation,

    respectively, on the value of buildings, machinery and transport/

    vehicles.

    3.7 Materials & Supplies :

    The annual requirement of materials & supplies has been roughly

    estimated at a lump sum of Tk 4.50 lacs per annum to be incurred

    100% capacity level. The above cost includes some materials and

    office supplies such as paper, pens, pencils, erasers, rubber stamps,

    staples, stapler pins, envelopes, scotch-tapes, toners, cartridges,

    printer ribbons, floppy diskettes, CD ROMs, etc.

    3.8 Transport :

    Provision has been kept for a sum of Tk 10.00 lacs of purchase a

    microbus (9-seater) to facilitate transportation of the projects

    personnel.

    3.9 Furniture & Fixture :

    A sum of Tk 35.00 lacs has been estimated to be incurred topurchase required furniture & fixture (setup cost), as shown in

    Annesure-III

    3.10 Erection & Installation :

    The cost of erection & installation of the projects machinery has been

    roughly estimated to be Tk. 10.00 lacs.

  • 7/30/2019 Delta System Limited

    43/81

    3.11 Utilities :

    Water : There will be free supply of water at the project premises.

    Power : A sum of Tk 3.00 lacs has been estimated to be incurred

    annually for the electricity to be consume at 100% capacity

    utilization.

    Fuel & Lubricants : For this purpose, a roughly estimated amount of

    Tk 1.20 lacs has been considered to be incurred.

    3.12 Insurance Coverage :

    The main assets of the project will have insurance coverage @ 1% of

    the total cost thereof.

    3.13 Manpower Requirements :

    On implementation, the project will require the services of 41 hired

    people and for them, a total of Tk 6.33 lacs has been estimated to be

    incurred per month as shown in Annexure-VIII.

    3.14 Preliminary Expenses :

    A sum of Tk 152.40 lacs will need to be incurred to meet up the

    primary and startup expenses as shown in Annexure-IV.

    3.15 Environment & Pollution Control :

    The project will have no polluting no polluting effect on the

    environment. Being environment friendly in nature, it will not require

    incurring any cost to have pollution control.

  • 7/30/2019 Delta System Limited

    44/81

    4.0 MARKETING ASPECTS

    4.1 Product-mix:

    The project has been designed to produce/develop mainly the

    computer software. However, it will also produce and/or provide

    some IT related products and services. A list of the product-mix of

    the project is given below :

    Software :

    a. Clinic management

    b. Banking

    c. Accounting

    Web Solution :

    a. Domain registration

    b. Web page development & designing.

    4.2 Demand Analysis :

    As stated earlier, the project is envisaged mainly to develop

    computer software and market the same both at home and abroad.

    Nowadays the computer software is becoming popular all over the

    world and the demand for software is rapidly increasing day by day.

    The people of the western countries are accustomed with Net

    Shopping.

    Software is also well known to and used by the non-resident

    Bangladeshi buyers living in the western countries. The software to

    be developed can be brought before these target people through Net.

    In Bangladesh too, different target groups, especially the

  • 7/30/2019 Delta System Limited

    45/81

    Government Departments, Banks, Hospitals, Clinics, Departmental

    Stores and other business organizations have been showing interests

    and desires for relevant software. So the demand for software is

    quite apparent which is showing a rapid growth as a whole.

    4.3 Pricing :

    The prices of the product-mix of the project are primarily determined

    as follows :

    Sl. Product-Mix Price (Tk)

    01.

    02.

    Software :

    a. Clinic management

    b. Banking

    c. Accounting

    Web solution :

    a. Domain registration

    b. Web page development & designing

    1,00,000

    5,00,000

    70,000

    20,000

    2,000

    The prices of the products are changeable depending on the market

    situation. The sponsors will put much emphasis on the competitive

    market prices and take all possible measures to gain maximum

    market share.

  • 7/30/2019 Delta System Limited

    46/81

    4.4 Sales Promotion :

    To market the products/services of the project, the following

    promotional activities will take place :

    Introducing the products/services and their utilities through

    seminar .

    Aggressive marketing through talented trained and motivatedmarketing professionals.

    Spread the word of ICT and its impact through expert and

    renowned personalities of our country and abroad.

    Advertisement through IT magazines, magazines, and daily

    newspapers.

    Corporate selling/direct marketing.

    Word of mouth/personal selling.

    4.5 Distribution Channel :

    Distribution through web technology.

    Direct implementation.

    Distribution through software incubator BASIS/BCS.

    Liaison office abroad.

  • 7/30/2019 Delta System Limited

    47/81

    5.0 SOCIO-ECONOMIC ASPECT

    5.1 Employment Generation :

    Upon implementation, the project will generate employment for 41

    people of different categories. Thus, on the one hand, the project will

    play a significant role to lessen the unemployment problem of the

    country and improve the living standard of the employed people. On

    the other hand, additional employment opportunity will be created for

    production, supply and distribution of materials and supplies.

    5.2 Contribution to GDP :

    The project will contribute a sum of Tk 178.79 lacs of the Gross

    Domestic Product (GDP) of the country as shown below :

    (Tk in 000)

    A. Net Sale revenue (4th year) : 21450

    B. Inter-farm transactions :

    Materials & Supplies : 293

    Travelling & conveyance : 75

    Repairs & maintenance : 1200

    Stores & spares : 1000

    Utilities : 273

    Printing & stationery : 390

    Postage, telephone : 75

    Legal & audit fee : 65

    Ad & sales promotion : 200 : 3571

    C. Contribution to GDP (AB) : 17879

  • 7/30/2019 Delta System Limited

    48/81

    5.3 Foreign Exchange Earning :

    The project, if implemented, will earn foreign exchange for the

    country by way of developing software and exporting the same to

    foreign countries, especially the USA and European countries. Thus

    the project will contribute to the economic development of the

    country.

    5.4 Linkage Effects :

    A considerable development of software & ICT services in the country

    will certainly encourage some other groups to produce and supply

    materials required to provide support services in this sector.

  • 7/30/2019 Delta System Limited

    49/81

    6.0 FINANCIAL ASPECTS

    6.1 Assumptions for Financial Analysis :

    The following assumptions have been made to conduct relevant

    financial analyses :

    1) The economic life of the project has been considered to be 10 years

    without major replacement.

    2) The software producing/developing unit will work throughout the

    year.

    3) The cost of inputs/materials as well as sales have been assumed

    to remain constant throughout the project years on the

    assumption that the increase in prices of inputs/materials will be

    offset by the proportionate increase in the selling price of output.

    4) There will be 5% increase in salary and wages per year and one

    months salary will be given as bonus every year.

    5) Deprecations are charged at the rate of 10% on machinery &

    equipments and 20% on vehicles & other assets on straight-line

    method.

  • 7/30/2019 Delta System Limited

    50/81

    6.2 Cost of the Project :

    The total cost of the project has been estimated at Tk 366.55 lacs

    which includes the projects fixed cost of Tk 332.55 lacs and total

    working capital of Tk 34.00 lacs.

    Out of the projects fixed cost, an amount of Tk 56.20 lacs has

    already been incurred by the sponsors. The detailed description of the

    project cost has been shown in AnnuxureI.

    6.3 Means of finance :

    (Tk. in 000)

    Financing Cost incurred To be incurred Total

    B. B. equity - 17961 17961

    Sponsors equity 5620 13074 18694

    Total capital outlay: 5620 31035 36655

    6.4 Financial Performance :(Tk. in 000)

    Year-1 Year-2 Year-3 Year-4 Year-5

    Sales revenue

    Gross profit

    Operating profit

    Net profit

    16500

    8408

    3015

    2182

    18150

    7301

    1830

    1325

    19800

    7625

    2075

    1502

    21450

    8218

    2585

    1871

    23100

    8842

    3124

    2262

  • 7/30/2019 Delta System Limited

    51/81

    Annexure-I

    COST OF THE PROJECT

    &

    MEANS OF FINANCE

    (Tk. in "000")

    A. COST OF THE PROJECT

    Sl. ItemsCost already

    incurred

    Cost to beTotal

    01.

    02.

    03.

    04.

    05.

    06.

    07.

    08.

    09.

    Rent advance for 5 years (50%) :a) Corporate office (2844 sft)

    b) Software laboratory (4500 sft)

    Machinery & equipments

    Freight & other charges (L.S)

    Erection & installation (L.S)

    Furniture & fixture

    Transport/vehicles

    Security deposits (Telephone)

    Preliminary expenses(primary + startup expenses)

    Contingencies

    (5% on the costs to be incurred)

    18000

    1500

    200

    400

    1500

    -

    20

    200

    -

    3839

    3500

    300

    600

    2000

    1000

    40

    15040

    1316

    5639

    5000

    500

    1000

    3500

    1000

    60

    15240

    1316

    Fixed Cost of the Project: 5620 27635 33255

    Total Working Capital : - 3400 3400

    Total Cost of the Project : 5620 31035 36655

  • 7/30/2019 Delta System Limited

    52/81

    B. MEANS OF FINANCE / PLAN OF INVESTMENT (PROPOSED)

    Sl. Cost items EEF EquitySponsors

    EquityTotal

    01.

    02.

    03.

    04.

    05.

    06.

    07.

    08.

    09.

    10.

    Rent advance for 5 years (50%) :

    c) Corporate office (2844 sft)

    d) Software laboratory (4500 sft)

    Machinery & equipments

    Freight & other charges (L.S)

    Erection & installation (L.S)

    Furniture & fixture

    Transport/vehicles

    Security deposits (Telephone)

    Preliminary expenses

    (primary + startup expenses)

    Contingencies

    (5% on the costs to be incurred)

    Working Capital

    -

    5000

    458

    490

    1715

    490

    29

    7468

    645

    1666

    5639

    -

    42

    510

    1785

    510

    31

    7772

    671

    1734

    5639

    5000

    500

    1000

    3500

    1000

    60

    15240

    1316

    3400

    Total 17961 18694 36655

    Ratio of investment : 49% 51% 100%

  • 7/30/2019 Delta System Limited

    53/81

    Annexure-II

    MACHINERY & EQUIPMENTS

    Sl. Description of items Qty Rate (Tk.) Total (Tk.)

    01. Server 03 3,75,000 11,25,000

    02. Corporate office PC 12 62,500 7,50,000

    03. Workstation PC 50 46,500 23,25,000

    04. UPS 50 4,000 2,00,000

    05. IPS 1 80,000 80,000

    06. Generator 1 2,66,000 2,66,000

    07. Printer 3

    1,35,000

    25,000

    10,000

    1,70,000

    08. Scanner 3 10,000 30,000

    09. Web camera 3 18,000 54,000

    Total : - - 50,00,000

  • 7/30/2019 Delta System Limited

    54/81

    Annexure-III

    FURNITURE, FIXTURE & OFFICE EQUIPMENT

    Sl. Description of items Qty Rate (Tk.) Total (Tk.)

    01. Corporate office :

    a) Table (Computer)

    b) Computer Chair

    c) Table rack

    d) Executive table

    e) Executive chair

    f) Managing director table

    g) Managing director chair

    h) Director table

    i) Director chair

    j) Thai partition with glass

    k) Reception desk with sofa

    l) Conference table with 20 chairs

    12

    12

    12

    10

    10

    1

    1

    1

    1

    -

    -

    Lot

    8,000

    6,000

    3,000

    15,000

    10,000

    50,000

    20,000

    30,000

    15,000

    L.S.

    L.S.

    L. S.

    96,000

    72,000

    36,000

    1,50,000

    1,00,000

    50,000

    20,000

    30,000

    15,000

    12,00,000

    2,00,000

    3,36,000

    02. Laboratory :

    a) Computer tables and chair

    b) Reception with sofa

    c) A. C

    d) Telephone (mobile)

    e) Fax

    f) Photo copier

    53

    1 set

    10

    10

    2

    2

    5,000

    50,000

    50,000

    12,000

    30,000

    1,00,000

    2,65,000

    50,000

    5,00,000

    1,20,000

    60,000

    2,00,000

    Total : - - 35,00,000

  • 7/30/2019 Delta System Limited

    55/81

    Annexure-IV

    PRELIMINARY EXPENSES

    (TK in ooo)

    Sl. Particulars Total

    01.

    02.

    03.

    04.

    a) Primary Expenses :

    Company incorporation, trade license, consultancy,project appraisal /evaluation, documentation, etc.

    b) Licensing :

    Microsoft Development Network (MSDN) : 150

    OracleDevelopment Suite : 800

    Window

    s 200 Operation System : 400(Server & Professional)

    c) VSAT/Bandwidth/Radio Link

    d) Membership with BASIS (Bangladesh Association ofSoftware Information Service)

    Pre-operating & Startup Expenses :

    a) Salary for 12 months (Ref: Annexure-VIII & IX)

    b) Materials & Supplies for 12 months(Ref: Annexure-VIII)

    c) Bandwidth charges for 12 months(128 kbps @ Tk 2,00,000/month)

    Launching cost (L.S.)

    Others (L.S.)

    300

    1350

    400

    20

    9845

    225

    2400

    500

    200

    Total : 15240

  • 7/30/2019 Delta System Limited

    56/81

  • 7/30/2019 Delta System Limited

    57/81

    Annexure-V

    WORKING CAPITAL

    (Tk. in "000")

    Items Tied-up period Amount

    Materials & Supplies 30 days 19

    Stores & Spares 180 days 125

    Work in Process (WIP) 60 days 1765

    Receivables 60 days 1349

    Other expenses (L. S.) 30 days 142

    Total Working Capital Required : 3400

  • 7/30/2019 Delta System Limited

    58/81

    Annexure-VI

    EARNING FORECAST

    (Tk. in "000")

    Items Yr-1 Yr-2 Yr-3 Yr-4 Yr-5

    Sales Revenue 16500 18150 19800 21450 23100

    Cost of Goods Sold 8092 10849 12175 13232 14258

    Gross Profit 8408 7301 7625 8218 8842

    Admin & Selling Expenses 5393 5471 5551 5633 5718

    Operating Profit 3015 1830 2074 2585 3124

    Financial Expenses - - - - -

    Net Profit before Tax 3015 1830 2074 2585 3124

    Income Tax - - - - -

    Net Profit after Tax 3015 1830 2074 2585 3124

    Bond Purchase (30%) 905 549 622 776 937

    Net Profit after Bond Purchase 2110 1281 1452 1809 2187

    Return on Bond (8%) 72 44 50 62 75

    Net Profit after Return on Bond 2182 1325 1502 1871 2262

    Ratios :

    Gross Profit to Sales (%) 51 40 39 38 38

    Operating Profit to Sales (%) 18 10 10 12 14

    Net Profit to Sales (%) 13 07 08 09 10

  • 7/30/2019 Delta System Limited

    59/81

    Annexure-VII

    SALES FORECAST

    (Tk in 000)Items Yr-1 Yr-2 Yr-3 Yr-4 Yr-5

    Sales at 100% capacity 33000 33000 33000 33000 33000

    Assumed capacity 50% 55% 60% 65% 70%

    Sales at assumed capacity 16500 18150 19800 21450 23100

    Assumption :

    1) From 1st to 5th year of operation of the project, the capacities to

    be utilized have been assumed to be 50%, 55%, 60%. 65% &

    70% respectively.

    2) Products/Services & Sales :

    At 100% capacity, the sales achievement has been estimated as

    follows :

    Items Qty (nos) Rate(Tk) Total (Tk)

    Softwares :

    a. Clinic managementb. Bankingc. Accounting

    Web solution :

    a. Domain registrationb. Web page development &

    designing

    5010100

    4004000

    1,00,0005,00,000

    70,000

    20,0002,000

    50,00,00050,00,00070,00,000

    80,00,00080,00,000

    Total : - - 3,30,00,000

  • 7/30/2019 Delta System Limited

    60/81

    Annexure-VIII

    COST OF GOODS SOLD

    (Tk. in "000")

    Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5

    Materials & Supplies 220 248 270 293 315

    Salary & Wages 7280 7644 8026 8427 8849

    Stores & Spares 250 500 750 1000 1250

    Water, Power, Fuel 210 231 252 273 294

    Repairs & Maintenance 300 600 900 1200 1500

    Rent, Tax, Insurance 333 333 333 333 333

    Depreciation 1814 1814 1814 1814 1814

    Other expenses (L.S.) 180 185 190 195 200

    Total Cost of Production 10592 11555 12535 13535 14555

    Add: Opening WIP (60 days) - 1765 2220 2459 2666

    Total stock of WIP 10592 13320 14755 15994 17221

    Less: Closing WIP (60 days) 1765 2220 2459 2666 2870

    Cost of goods manufactured 8827 11100 12296 13328 14351

    Add: Opening FG (30 days) - 735 986 1107 1203

    Cost goods available for sales 8827 11835 13282 14435 15554

    Less: Closing FG (30 days) 735 986 1107 1203 1296

    Cost of Goods Sold 8092 10849 12175 13232 14258

    ASSUMPTIONS :

    1) A period of 60 days has been considered to determine the work

    in process (WIP) based on the assumption that the development

    of softwares would require 3090 days depending on their

    sizes/types, thus 60 days on an average.

    2) To determine the inventory of finished goods (FG), an average

    period of 30 days has been considered on the assumption that

    any softwares, regardless of their size or types, would require a

    minimum of 30 days to market the same.

  • 7/30/2019 Delta System Limited

    61/81

    3) Capacity Utilization :

    From 1st to 5th year of operation, the capacities to be utilized have

    been assumed to be 50%, 55%, 60%, 65% & 70% respectively.

    4) Cost of Materials and Supplies :

    At 100 percent efficiency, a sum of Tk 4,50,000 has been

    roughly estimated to be incurred annually in this head of

    expenditure. Thus the annual cost of materials and supplies, at

    the assumed capacities, would be Tk 2,25,000; Tk 2,47,500;

    Tk 2,70,000; Tk 2,92,500 and Tk 3,15,000.

    5) Stores and Spares :

    The cost of stores and spares has been considered to be 0.5%, 1%,

    1.5%, 2% & 2.5% on the value of machinery and equipments.

    6) Repairs and Maintenance :

    The costs for repairs and maintenance have been considered to

    be 0.5%, 1%, 1.5%, 2% & 2.5% on the value of

    transport/vehicles and machinery & equipments.

    7) Rent, Tax, Insurance :

    The cost involvement in this head of expenditure has been

    considered to be 1% of the fixed cost of the project.

    8) Depreciation :

    Items Cost Rate Amount

    Machinery & Equipments

    Furniture & Fixture

    Transport/Vehicles

    Intangible assets

    5000

    3500

    1000

    2070

    10%

    20%

    20%

    20%

    500

    700

    200

    414

    Total : - - 1814

  • 7/30/2019 Delta System Limited

    62/81

    9) Water, Power & Fuel :

    a. Water : There will be free supply of water in the office/project

    premises as the cost will be borne by the landlord.

    b. Power : A lump sum of Tk 3,00,000 has been roughly

    estimated to be incurred annual for the electricity to be

    consumed at 100% capacity utilization.

    c. Fuel : For this purpose, a roughly estimated amount of

    Tk 1,20,000 has been considered to be incurred.

    Total (a+b+c) : Tk 4,20,000 per annum at 100% capacity. Therefore

    at the assumed capacities, the annual costs would be Tk 2,10,000;

    Tk 2,31,000; Tk 2,52,000; Tk 2,73,000 and Tk 2,94,000 from 1st to

    5th year of operation respectively.

    10) Salary (Technical Personnel) :

    Category/Designation No.Monthly

    Salary (Tk)

    Annual Salary

    (Tk in 000)

    Software Development :

    Project Manager

    Senior System AnalystSystem Administrator (network)System Analyst

    Business AnalystSenior ProgrammerProgrammer

    01

    010501

    031501

    40,000

    30,0001,00,000

    30,000

    60,0002,25,000

    25,000

    480

    3601200360

    7202700300

    Sub-Total : 27 5,10,000 6120

    Web Solution :Web administratorWe Page Designer

    0102

    20,00030,000

    240360

    Sub-Total : 03 50,000 600Total : 30 5,60,000 6720

    (Tk in 000)

    Yr-1 Yr-2 Yr-3 Yr-4 Yr-5

    SalaryIncrement (5%)Bonus (one months salary)

    6720-

    560

    6720336588

    7056353617

    7409370684

    7779

    389681

    Total : 7280 7644 8026 8427 8849

  • 7/30/2019 Delta System Limited

    63/81

    Annexure-IX

    ADMINISTRATIVE & SELLING EXPENSES

    (Tk. in 000)

    Sl. Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5

    01. Directors remuneration 960 960 960 960 960

    02. Administrative salary 949 997 1047 1099 1154

    03. Depreciation & write-off 2634 2634 2634 2634 2634

    04. Travelling & conveyance 60 65 70 75 80

    05. Printing & stationery 360 370 380 390 400

    06. Postage, telegram & telephone 60 65 70 75 80

    07. Legal & audit fee 50 55 60 65 70

    08. Ad & sales promotion (LS) 200 200 200 200 200

    09. Miscellaneous expenses 120 125 130 135 140

    Total : 5393 5471 5551 5633 5718

    Assumptions :

    01. Directors Remuneration :

    An amount of Tk 80,000 per month has been considered to be

    the Directors remuneration of 2 Directors. Thus, the annual

    remuneration of Directors stands at Tk 12,00,000 annually.

    02. Administrative Salary :

    Category/Designation No.Monthly Salary

    (Tk)Annual Salary

    (Tk 000)

    Administrative :Office Manager

    AccountantReceptionistAttendant/Cleaner/SecurityDriver

    01

    01010401

    10,000

    8,0004,000

    12,0004,000

    120

    9648

    14448

    Sub-Total : 04 38,000 456

    Marketing :Marketing Manager

    Marketing Executive

    01

    02

    15,000

    20,000

    180

    240

    Sub-Total : 08 38,000 456

    Total : 11 73,000 876

  • 7/30/2019 Delta System Limited

    64/81

    (Tk in 000)

    Yr-1 Yr-2 Yr-3 Yr-4 Yr-5

    Salary 876 876 920 966 1014

    Increment (5%) - 44 46 49 51

    Bonus (1 months salary) 73 77 81 85 89

    Total : 949 997 1047 1099 1154

    04. Depreciation and write-off :

    (Tk. in 000)

    Items Cost Rate Deprecation

    Preliminary expenses 13170 20% 2634

    Total : - - 2634

  • 7/30/2019 Delta System Limited

    65/81

    Annexure-X

    BREAK-EVEN ANALYSIS

    (Tk. in 000)

    1.

    2.

    3.

    Sales revenue (4th year)

    Total cost of operation, admin & selling and financial expenses:

    21450

    Analysis of total cost Total cost Fixed cost Variable cost

    Materials & SuppliesSalary and wages (Laboratory)Repairs & maintenanceTax, insurance, etc.

    Water, power, fuelStores & spares

    Administrative salaryPostage, telegram, tel.

    Printing & stationeryConveyance & travellingDepreciation & write-off

    Miscellaneous expensesLegal & audit feeAd & sales promotion

    Financial expense

    29384271200333

    2731000

    205975

    39075

    4448

    33065200

    -

    ---

    333

    --

    107025

    78-

    4448

    6665-

    -

    29384271200

    -

    2731000

    98950

    31275

    -

    264-200

    -

    Total : 19168 5015 13083

    Break-even point (BEP) :

    PV Ratio = (Sales Variable cost) / Sales

    = (21450 13083)/21450 = 0.39

    BEP (Sales) = Fixed cost / PV Ratio

    = 5015 / 0.39

    = Tk 12859 thousand i.e. 60% of assumed capacity.

  • 7/30/2019 Delta System Limited

    66/81

    Annexure-XI

    CASHFLOW STATEMENT

    (Tk. in 000)

    A. Source of fund : Const. Yr Yr-1 Yr-2 Yr-3 Yr-4 Yr-5

    Sponsors equity

    Depr. & write-off

    Operating Profit

    B.B. equity

    Return on bond

    16960

    -

    -

    16295

    -

    1734

    4448

    3015

    1666

    72

    -

    4448

    1830

    -

    44

    -

    4448

    2074

    -

    50

    -

    4448

    2585

    -

    62

    -

    4448

    3124

    -

    75

    Total : 33255 10935 6322 6572 7095 7647

    B. Utilization of Fund :

    Capital expenditure

    (fixed assets)

    Increase in current

    assets

    Buy-back of B.B. equity

    Investment on bond

    33255

    -

    -

    -

    -

    3400

    2245

    905

    -

    -

    2245

    549

    -

    -

    2245

    622

    -

    -

    2245

    776

    -

    -

    2245

    937

    Total : 33255 6550 2794 2867 3021 3182

    Cash surplus (AB)

    Opening cash balance

    Closing cash balance

    -

    -

    -

    4385

    -

    4385

    3528

    4385

    7913

    3705

    7913

    11618

    4074

    11618

    15692

    4465

    15692

    20157

  • 7/30/2019 Delta System Limited

    67/81

    Annexure-XII

    PROJECTED BALANCE SHEET

    (Tk. in 000)

    Items Const. Yr Yr-1 Yr-2 Yr-3 Yr-4 Yr-5

    Properties & Assets:

    Current Assets :

    Cash Balance

    Investment On Bond

    Other current assets

    -

    -

    -

    4385

    905

    3400

    7913

    1454

    3400

    11618

    2076

    3400

    15692

    2852

    3400

    20157

    3789

    3400Sub total : - 8690 12767 17094 21944 27346

    Fixed assets :

    Total Fixed Assets 33255 28807 23459 19911 15463 11015

    Sub-total : 33255 28807 23459 19911 15463 11015

    Total assets : 33255 37497 37126 37005 37407 38361

    LIABILITIES AND

    SPONSORS EQUITY :

    Liabilities :

    B.B. equity/share

    Working capital loanOther current liabs

    126295

    --

    15716

    --

    13471

    --

    11226

    --

    8981

    --

    6736

    --

    Total liabilities : 16295 15716 13471 11226 8981 6736

    Sponsors equity :

    Piad-up capital

    Investment on bond

    Retained earnings

    16960

    -

    -

    18694

    905

    2182

    18694

    1454

    3507

    18694

    2076

    5009

    18694

    2852

    6880

    18694

    3789

    9142

    Total equity : 16960 21781 23655 25779 28426 31625

    Total liabs & equity : 33255 37497 37126 37005 37407 38361

  • 7/30/2019 Delta System Limited

    68/81

    Annexure-XIII

    INTERNAL RATE OF RETURN

    (Tk. in 000)

    Year Net Cash flow NPV disc. @ 15% NPV disc. @ 20%

    0 (33255) (33255) (33255)

    1 7463 6493 6217

    2 6278 4746 4357

    3 6522 4291 3776

    4 7033 4023 3390

    5-10 7572 16378 12153

    11 500 108 68

    Total : 2784 (3294)

    IRR = 15 + (20-15) X 2784/(2784 + 3294)

    = 15 + 5 X 0.4580 = 15 + 2.29

    = 17.29, say 17%

    Assumptions :

    01. The economic life of the project has been considered to be 10 years

    02. Benefit/Net Cash flow :

    (Tk. in 000)

    Year Operating profit Depr. & write-off Total

    1 3015 4448 7463

    2 1830 4448 6278

    3 2074 4448 6522

    4 2585 4448 7033

    5 3124 4448 7572

    03. Salvage Value :

    (Tk. in 000)

    Item Total value % of recovery Recoverable

    Machinery 5000 10% 500

    Total : - - 500

  • 7/30/2019 Delta System Limited

    69/81

    Annexure-XIV

    DEBT-SERVICE COVERAGE RATIO

    (Tk. in 000)

    A. Income Yr-1 Yr-2 Yr-3 Yr-4 Yr-5

    Net profit after

    return on bond2182 1325 1502 1871 2262

    Depreciation &

    write-off4448 4448 4448 4448 4448

    Total : 6630 5773 5950 6319 6710

    B. Liabilities :

    Buy-back of B.B. equity 2245 2245 2245 2245 2245

    Total : 2245 2245 2245 2245 2245

    C. Debt-service coverage

    ratio (times)

    2.95 2.57 2.65 2.81 2.99

  • 7/30/2019 Delta System Limited

    70/81

    Annexure-XV

    PAY-BACK PERIOD

    (Tk. in 000)

    1. Amount to be paid (excluding value of land) : 33255

    2. Amount available for recovery of the value of assets as follows :

    Items Yr-1 Yr-2 Yr-3 Yr-4 Yr-5

    Net profit

    Depr. & write-off

    2182

    4448

    1325

    4448

    1502

    4448

    1871

    4448

    2262

    4448

    Total : 6630 5773 5950 6319 6710

    3. Pay-back Period :

    Year Amount to berecovered

    Amount availablefor recovery

    Balance

    1

    2

    3

    4

    5

    33255

    26625

    20852

    14902

    8583

    6630

    5773

    5950

    6319

    6710

    26625

    20852

    14902

    8583

    1873

    The pay-back period will be 5 years and 3 months.

  • 7/30/2019 Delta System Limited

    71/81

    Annexure-XVI

    MARGIN OF SAFETY

    (Tk. in 000)

    Margin of Safety =Sales

    Point)BreakevenatSales(Sales

    =21450

    12859)-(21450

    =21450

    8591

    = 0.4005, say 40%

  • 7/30/2019 Delta System Limited

    72/81

    Annexure-XVIII

    CONSTRUCTION & CIVIL WORKS

    Sl. Description Area/Qty Rate (Tk) Amount (Tk)

    01. Office building (50 X 30 ) - Pucca 1500 sft 985/sft 14,77,500

    02. Godown (60 X 30 ) Semi-Pucca 1800 sft 535/sft 9,63,000

    03. Hatchery shed (110 X 30 ) 3300 sft 375/sft 12,37,500

    04. Breeding Tank (20 dia) - L.S. 2,25,000

    05. Overhead Tank (15 X 12 X 8 - 6 ) - L.S. 5,50,000

    06. Pump house (20 X 10 ) - Pucca 200 sft 985/sft 1,97,000

    07.Labour Shed (25 X 30 ) Semi-

    750 sft 350/sft 2,62,500

    08.Staff Quarter (54 X 30 )- Semi-

    1620 sft 535/sft 8,66,700

    09. Cistern (12 X 8 ) 10 Nos. 20,000 each 2,00,000

    10. Cistern (8 X 6 ) 08 Nos. 15,000 each 1,20,000

    11. Spawning Tank (10 dia) 02 Nos. 50,000/tank 1,00,000

    12. Incubation Jar 2 - 3 dia (RCC) 06 Nos. 10,000 each 60,000

    13. Incubation Jar 2 - 3 dia (MS sheet) 06 Nos. 8,000 each 48,000

    14. Nursery pond (125 X 80 X 15 ) 04 Nos. 1.25/cft 7,50,000

    15. Fishery Pond (150 X 80 ) 15 depth 16 Nos. 2,00,000 32,00,000

    16. Deep tube-well 01 No. 9,50,000 9,50,000

    17. Boundary with barbed fencing - L.S. 8,00,000

    18. Guard/Reception Room (10 X 8 ) 80 sft 985/sft 78,800

    19. Miscellaneous - - 2,55,000

    Total : 1,23,41,000

  • 7/30/2019 Delta System Limited

    73/81

    PART III

    MEMORANDUM & ARTICLES OF ASSOCIATIONOF

    DELTA SYSTEMS LIMITED

  • 7/30/2019 Delta System Limited

    74/81

  • 7/30/2019 Delta System Limited

    75/81

    SALES ESTIMATE

    (Tk. in "000")

    Items Yr-1 Yr-2 Yr-3 Yr-4 Yr-5

    Sales at rated capacity

    Assumed capacity

    Sales at assumed capacity

    ASSUMPTIONS:

    1. At 100% capacity, the projects annual production at different stages will be

    as follows:

    Production of fish spawn:

    a) Crap fish (200 pcs X 0.50 kg / fish / year) = 100 kg

    b) Sarputi (2,000 pcs X 0.050kg / fish / year) = 100 kg

    Production of fish fry:

    From fish spawn, 50% will be sold out directly to the fish farmers while 50% will be kept for fry

    production as follows:

    a) Crap fish (50 kg spawn X 1,00,000 pcs of fry per kg) = 50,00,000 pcs

    b) Sarputi (50 kg spawn X 1,00,000 pcs of fry per kg) = 50,00,000 pcs

    Production of fish:

    From fish fry, the production of fish will be made as follows:

    a) Crap fish (50,00,000 pcs less sale of 47,00,000 pcs) = 3,00,000 pcs of 0.750 kg body wt.

    each.

    c) Sarputi (50,00,000 pcs less sale of 40,00,000 pcs) = 10,00,000 pcs of 0.200 kg body wt. each.

    The above production of fish will be made under the arrangement that there will be two production

    cycles in a year- each having 3000 pcs of Crap fish per pond (thus 3,00,000 pcs of fish in 50

  • 7/30/2019 Delta System Limited

    76/81

    ponds), with which a joint cultivation of 10,000 pcs of Sarputi per pond (thus 10,00,000 ocs in 50

    ponds) will also be made.

    2. Estimate of sales:

    At 100% capacity, the sales of different products of the project have been summarized and

    estimated as follows:

    Production unit Fish variety Product-mix Quality Rate (Tk) Ammount

    Hatchery Crap

    Sarputi

    Fish spawn

    Fish fry

    Fish spawn

    Fish fry

    50 kg

    47,00,000 pcs

    50 kg

    40,00,000 pcs

    3500/kg

    2.50/pc.

    3500/kg

    0.50/pc.

    Sub-Total: - - - -Fishery Crap

    Sarputi

    Fish

    Fish

    2,25,000 kg

    2,00,000 kg

    55/kg

    60/kg

    Sub-Total: - - - -

    Total: - - - -

    3. From 1st to 5th year of operation, the production capacity to be achieved have been assumed to be

    70%, 75%, 80%, 85% & 90% respectively.

  • 7/30/2019 Delta System Limited

    77/81

    Annexure-VIII

    COST OF GOODS SOLD

    (Tk. in "000")

    Particulars Yr-1 Yr-2 Yr-3 Yr-4 Yr-5

    Raw Materials & Supplies

    Wages and Salaries

    Stores and Spares

    Water, Power, Fuel

    Repairs & Maintenance

    Rent, Tax, Insurance

    Depreciation

    Other expenses

    Cost of goods sold

    ASSUMPTIONS:

    1. At 100% capacity, the annual production is 2,70,000 kg of fish (Carp & Sarputi) and 52,00,000 pcs

    of fish fry (Carp & Sarputi).

    2. Cost of raw materials and supply:

    a) Fish feed:

    For fish = 2 kg feed/kg fish X 2,70,000 kg fish X Tk 17/kg feed

    = Tk 91,80,000

    For fish fry = 3 kg feed / 1000 pcs fish fry X 52,00,000 pcs fish fry X Tk 15/ kg feed

  • 7/30/2019 Delta System Limited

    78/81

    Total = Tk 94,14,000

    b) Medicine & Supply:

    For 50 Bigha = Tk 900 / bigha X 50 Bigha X 3 times / year

    (Total pond area) = Tk 1,35,000

    Total (a + b) = Tk 95,49,000

    Therefore, at 70%, 75%, 80%, 85% & 90% capacity utilization from 1st to 5th year of operation,

    the cost of raw materials & supplies would stand at Tk 66,84,300; Tk 71,61,750;

    Tk 76,39,200; Tk 81,16,650 and Tk 85,94,100 respectively.

    4. Salaries & Wages:

    Designation No. Monthly Salary (Tk)Annual Salary

    (Tk "000")

    Hatchery Officer 01 10,000 120

    Hatchery Assistant 02 8,000 96

    Laboratory Assistant 02 8,000 96

    Feed Assistant 02 8,000 96

    Water Control Assistant 02 6,000 72

    Machine operator 01 3,000 36

    Unskilled worker 10 20,000 240

    Total: 20 63,000 756

    (Tk. "000")

    Yr-1 Yr-2 Yr-3 Yr-4 Yr-5

    Salary 756 756 794 834 876

    Increment (5%) - 38 40 42 44

    Bonus (1 Month's Salary) 63 66 70 73 77

    Total: 819 860 904 949 997

    5. Stores & Spares:

  • 7/30/2019 Delta System Limited

    79/81

    Cost considered @ 0.5%, 1%, 1.5%, 2% & 2.5% on value of Machinery form 1st to 5th year

    respectively.

    6. Repairs & Maintenance:

    Cost for repair & maintenance of machinery and bldg. estimated at 0.5%, 1%, 1.5%, 2% &

    2.5% in 1st, 2nd, 3rd, 4th & 5th yearrespectively as follows:

    Items Yr-1 Yr-2 Yr-3 Yr-4 Yr-5

    Buildings

    Machinery

    Total:

    7. Rent, Tax & Insurance:

    It has been estimated at 1% of the total Fixed Cost of the Project (excluding the value of land).

    8. Depreciation:

    (Tk. in "000")

    Items Cost Rate Amount

    Building 5%

    Machinery 10%

    Transport 20%

    Total: - -

    9. Water, Power & Fuel:

    (a) Water: Supply will be met up by sinking a submersible pump and deep tube well.

    (b) Power: Supply will be obtained from PDB/REB.

  • 7/30/2019 Delta System Limited

    80/81

    Cost:

    For water pump : 12 kw X 8hrs X365 days X Tk 4.10 = Tk 1,43,644

    For lighting : 10 kw X 8hrs X365 days X Tk 4.10 = Tk 1,19,720

    Total power cost = Tk 2, 63, 384

    (d) Fuel/Lubricant: Tk 1,20,000/ Year (L.S.)

    Total (a+b+c) = Tk 3,83,384 annually at 100% capacity utilization.

    Therefore, at 70%, 75%, 80%, 85% & 90% capacity utilization, the costs would take place as

    follows:

    1st Year

    2nd Year

    3rd Year

    4th Year

    5th Year

  • 7/30/2019 Delta System Limited

    81/81

    Annexure-X

    BREAK-EVEN ANALYSIS

    (Tk. in 000)

    1.

    2.

    Sales revenue (4th year)

    Total cost of operation, admin & selling and financial expenses

    Analysis of total cost Total cost Fixed cost Variable cost

    Raw materials

    Salary and wages

    Repairs & maintenance

    Tax, insurance, etc.

    Water, power, fuel

    Stores & spares

    Administrative salary

    Postage, telegram, tel.

    Printing & stationery

    Conveyance & traveling

    Depreciation & write-off

    Miscellaneous expenses

    Legal & audit fee

    Ad & sales promotion

    Financial expense -

    -

    -

    -

    -

    -

    -

    -

    -

    -

    -

    -

    -

    Total:

    Break-even point (BEP):PV Ratio = (Sales Variable cost) / Sales