Delivering the Rehabilitation of the F.G. Gardiner Expressway
-
Upload
toronto-public-consultation-unit -
Category
Government & Nonprofit
-
view
996 -
download
0
Transcript of Delivering the Rehabilitation of the F.G. Gardiner Expressway
Public Consultation
427
Kipl
ing
Islin
gton
Park
Law
n
Duf
feri
n
Stra
chan
Bath
urst
Spad
ina
York
Yong
e
Jarv
is
Lake
Sho
re
“Anatomy” of Gardiner Expressway
– “At-grade” section: Hwy. 427 to Dufferin Street (1955 to 1958)
– “Elevated” section: Dufferin Street to Logan Avenue (1959 to 1966)
“At Grade” - 11 km - 32 bridges/ structures
“Elevated” - 7 km - 335 spans
Don
Val
ley
2
Public Consultation
Rehabilitation Strategic Plan
3
In 2013 the Strategic Plan for the rehabilitation of the Gardiner Expressway (developed by McCormick Rankin ) the plan:o identified immediate, short and long term rehabilitation needs of Gardiner;o developed an implementation schedule for the necessary rehabilitation works
to maintain the Gardiner in a safe and serviceable condition; and,o Took into consideration:
• previous rehabilitation work;• User impacts and associated costs;• Capital costs, Life cycle costs, Cash Flow requirements; and• Assumed traffic restrictions of no more than a single lane closure in each
direction.
Public Consultation4
In 2014, Staff presented the Strategic Rehabilitation plan to the
Public Works Committee and City Council.
On April 2, 2014 City Council:o approved the “Accelerated Construction” approach for Gardiner
Rehabilitation reducing the traffic impacts for the anticipated work from 20
years to 12 years
o directed to report back with analysis of project delivery models and
procurement options.
On June 10, 2014, Council authorized retention of Infrastructure
Ontario for the purposes of preparing a procurement options
analysis in support of the implementation of the Strategic Plan
Rehabilitation Strategic Plan
Public Consultation
Accelerated Rehabilitation Approach
Placing Prefabricated Deck-Girder Section
Montreal: Jacques Cartier Bridge Rehabilitation
Prefabrication Facility
5
Public Consultation
Evaluating Project Delivery
Various methods of project delivery includingo Traditional project delivery
Multiple contracts with private sector for design and construction of various project components
o Public private partnership (P3) One large contract with private sector consortium
for design, construction, operations and life cycle maintenance.
Public Consultation
Federal Funding Requests P3 Canada Fundo P3 Canada funding for projects delivered as P3so Business case must demonstrate positive Value for
Money for project delivery as P3 compared with traditional delivery methods
New Building Canada Fundo Projects with capital costs >$100 million must be
screened for potential delivery as P3o Business case and procurement options analysis
to be submitted
7
Public Consultation
Models of PPP in Canada
Degree of Private Sector Involvement
Deg
ree
of
Pri
vate
Sec
tor
Ris
k
Design – Build
PP
P M
odel
s
Operation & Maintenance
Build – Finance
Build – Finance – Maintain
Lease – Develop – Operate
Design – Build – Operate
Design – Build – Finance – Maintain
Design – Build – Finance – Operate
Design – Build – Finance – Operate - Maintain
Build – Own – Operate
Concession
Privatization
Public Consultation
Key Features of P3
Risk Transfer from public sector to private sector, including:o Project Delivery on time and on budgeto Long term maintenance risk
Innovationo Project structured so as to promote innovation in design and construction
Integrated Project Deliveryo Design, Construction undertaken by one consortium enhances asset
delivery meeting/exceeding expectations
Life Cycle Accountability for the Worko Maintenance of constructed work is responsibility of private sector, post
construction, over long-term concession period (eg 30 year) o ensures that asset will be maintained in good condition, and handed back to the City in
good condition at end of contract
Public Consultation
P3 Risk Transference
Traditional: Design-Bid-Build (DBB)
Owner’s Risks Bidder’s Risks
Design
Financing
HighwayMaintenance
Lifecycle
HighwayAvailability,
Performance & Asset Value
Construction
P3: Design-Build-Finance-Operate-Maintain (DBFOM)
Bidder’s Risks
Output Specifications
Design
Financing
Construction
Lifecycle
HighwayAvailability,
Maintenance Performance &
Asset Value
Owner’s Risks
Risks are transferred to the party best able to manage them.
Public Consultation
Defining Value for Money (VfM)
11
• Base Costs: Design, Construction,
Operations (summer and winter maintenance)
and Rehabilitation over the concession term
• Financing Costs: Costs associated with
funding the project
• Ancillary Costs: includes additional 3rd party
advisory, legal, delivery costs etc
• Risk Retained: Risks best managed by Public
sector stay with Public sector
• The risk adjusted cost difference between
PSC and AFP is the estimated Value for
Money
• If the AFP costs are less than the PSC cost,
there is positive Value for Money by
procuring a project using AFP.
Value for Money assessment compares the cost of delivering the same project under two different delivery models, Traditional or Public Sector Comparator (PSC) to Alternative Financing and Procurement (AFP) to determine which provides a lower estimated total project cost.
Base Costs (Lower under AFP as a result of Innovation Factor set off by higher Lifecycle Costs)
Risks Retained
+ Value for Money
PSC AFP
Ancillary CostsFinancing Costs
Public Consultation
Other Canadian Transportation P3 Projects
• Winnipeg- Chief Peguis Trail
• Saskatoon North Commuter Parkway and Traffic Bridge Replacement
• Alberta- Stoney Trail (various projects)
• Quebec- Autoroutes 25 and 30• Montreal- Rebuild of Turcott Interchange• Federal- Montreal- Champlain Bridge• New Brunswick- Fredricton-Moncton Highway
• Federal- New Brunswick- Trans Canada Highway
12