Delhi Metro Rail

13
Delhi Metro Rail Project Presented By Raghu

description

Project Management,

Transcript of Delhi Metro Rail

Page 1: Delhi Metro Rail

Delhi Metro Rail Project

Presented By Raghu & Saurabh

Page 2: Delhi Metro Rail

AGENDA

The Metro Project -An Overview

Project Highlight

Operation Highlight

Challenges in Implementation

Project Management at All Stage

Page 3: Delhi Metro Rail

THE METRO PROJECT AN OVERVIEW……

• Set up in May’95 under the Indian Companies Act.

• A joint venture between the Federal Government of India and the Provincial Government of Delhi State, with equal equity.

• DMRC has the responsibility for construction and operation of Delhi Metro

• A Master Plan had been drawn up for Delhi Metro expansion, consisting of 12 lines, covering 420 kms. to be completed by 2021 in four Phases.

Page 4: Delhi Metro Rail

THE METRO PROJECT AN OVERVIEW …….

• Works started on Phase I on 1st October, 1998 and completed in December, 2005.

• Phase-I – 65 kms. Cost US $ 2.5 billion. Completed in 7 years and 3 months (2 years & 9 months ahead of schedule)

• Phase-II covers 124 kms. This also includes a high speed

Metro connection from center of the city to the new

airport in 18 minutes.

Page 5: Delhi Metro Rail

………THE METRO PROJECT AN OVERVIEW

• Phase-II works commenced in January 2006 and

completed in October, 2010 – 5 months ahead of

schedule.

• Phase-III will consist of about 140 km at a cost of US $ 8.6

billion. The works commenced in June, 2012 and

expected to be completed by 2016.

Page 6: Delhi Metro Rail

PROJECT HIGHLIGHTPhase

No of Lines

Length (Km)

Elevated Length (Km)

Underground Section (Km)

At grade Length (Km)

No of Stations

I 3 65

47.43 13.17

4.50 59

II 15 128

94.13 29.83

4.10 81

III 11 140 N/A N/A N/A

N/A

IV 8

100 N/A N/A N/A

N/A

Page 7: Delhi Metro Rail

OPERATION HIGHLIGHT 2500 train trips with 200 train sets on 6 lines. 

Each train used to consist of 4 coaches. Trains progressively being lengthened to 6 coaches and finally to 8 coaches.

Average daily ridership - About 16.5 lakh passengers with average lead of 14 kms.

Frequency during peak hours – 2 m 30 sec.

System fully Barrier Free for Physically challenged.

DMRC has introduced feeder bus short loop services

Page 8: Delhi Metro Rail

CHALLENGES IN IMPLEMENTATION Delhi Metro Project is the biggest urban intervention since

Independence.

Project is to be executed in very difficult urban environment.

Being in the capital city all actions under close scrutiny of VVIPs.

Project approved on completion cost.

The Project implementation period extremely compressed and strict completion targets.

Metro being constructed to world class standards with frontline technologies.

Page 9: Delhi Metro Rail

PROJECT MANAGEMENT

Each activity of testing identified and duration of all these activities pre-determined

Trials conducted as per schedule pre-determined jointly by System Contracts

Service trial schedules also laid out in advance

Sufficient time provided before actual commissioning

Page 10: Delhi Metro Rail

INTERFACE MANAGEMENT

•Interface Management - “Access dates” and “Key dates”

listed in contract document itself.

• The important items which require interface with other contractors are clearly identified and indicated in contracts.

• Other contractors with whom the contractor has to interface are also clearly defined.

Page 11: Delhi Metro Rail

MONITORING DURING EXECUTION Contractors prepare detailed Base – line work

schedule for execution including duration of activities and identification of critical activities/path

Close monitoring of work schedule, mobilization of ‘Manpower’, ‘Machinery & Plant’ and ‘Materials’

Weakly meetings with Contractors for planning the work and solving their problems.

Practical approach to solve the genuine problems of contractors.

Streamlined prompt payment procedure and quick decision-making.

Page 12: Delhi Metro Rail

MONITORING DURING EXECUTION ………• Stringent penalties for failures to deliver.

• Prompt resolution of claims.

• Round the clock supervision guaranteed

• Strict independent quality & safety audit.

• Monthly progress presentations by the contractors

• DMRC directly handles works pertaining to other Government and Civic Departments to speed up.

Page 13: Delhi Metro Rail

Thank You