DEKOTEC -MTS · DEKOTEC®-MTS Recommendation for processing All work steps must be performed...

1
DEKOTEC ® -MTS Recommendation for processing All work steps must be performed wearing personal protective equipment such as safety shoes, helmet, protection goggles and welder gloves in accordance with the local occupational health and safety regulations. It is strongly recom- mended to train the personnel inexperienced in the processing of shrink sleeves before the application. Adjacent factory coating must be roughened (e.g. emery cloth #40) and beveled with an angle ≤30°. The use of 2 applicators is recommended for pipe diameters > 400mm (16“). Required surface cleanliness: The surface must be dry, free of grease, oil, dust and other contaminations. Steel surfaces have to be cleaned to a degree of at least St 2 or Sa 2,5 (ISO 8501-1). 1. Preparation General work steps: General work steps: Clean the surface with a lint-free cloth - The cleaned surface must not be touched with unprotected hands. 2. Cleaning 4. DEKOTEC ® -DI Mastic Cut DEKOTEC ® -DI Mastic to length in such a way that a closed ring is created in front of the bell. Firmly press DEKOTEC ® -DI Mastic with the self-adhesive side on to the pipe and the front of the bell. Afterwards, smooth with a hot palette-knife. Prevent protrusion at the bell. 4. DEKOTEC ® -MTS Sleeve installation step 1 Heat the adhesion side of the sleeve at the side with the 45° bevel on a lengths of approximately 200 mm (8“). When using master rolls, the sleeves must be cut to the required lengths (see table) and must be covered on one side with 45° bevels. Press heated side of DEKOTEC ® - MTS55 DI on to the bell in such a way that the center marking lays on the bell edge. Heat the lose end of the sleeve at a length of app. 100 mm and press on to the already installed end (100 mm overlap). 7. Sleeve installation step 2 Heat the adhesion side of the sleeve at the side with the 45° bevel on a lengths of approximately 200mm (8”). Caution: Only heat sleeve for the width of the bell (supporting surface) 6. Sleeve installation step 1 Heat the adhesive side (silver) of the DEKOTEC ® -CLP closure patch until the surface is glossy. Apply the DEKOTEC ® -CLP in the overlapping area of the sleeve by firmly pressing it to the surface, with center markings that lay on top of each other. Support free standing sleeve form the inside while pressing (only with clean gloves)”. 8. DEKOTEC ® -CLP Attaching the closure patch Heat the sleeve from the bell to the edge of the bell pipe in the direction of the circumference with even motions. Heat the sleeve from the bell to the edge of the plug-in pipe in the direction of the circumference with even motions. 9. Sleeve installation shrinking When using master rolls, the sleeves must be cut to the required lengths and must be covered with 45° bevels. The cutting length of DEKOTEC ® - MTS55 DI is equivalent to the largest circumference of the bell plus 100 mm The circumference of the plug-in pipe must be ≥ 0.65 multiplied by the largest circumference at the bell. 5. Cutting 1. Press the DEKOTEC ® -MTS in the 2 o’clock position on the dried sur- face in such a way that the center marking of the sleeve is positioned above the welding seam. Remove the trapped air with a roller as shown in the image. 5. DEKOTEC ® -MTS Sleeve installation step 2 2. 1. 1. 2. 2. At the loose end of the DEKOTEC ® -MTS, heat the adhesive side on a lengths of approximately 100 mm (4“). Press the lose end on to the end that is already installed in such a way that the center markings are on top of each other. The overlap is approximately 100 mm (4“). 6. DEKOTEC ® -MTS Sleeve installation step 3 100 mm (4“) 2. Heat the closure patch DEKOTEC ® -CLP on the adhesive side (silver) until it becomes glossy. Firmly press DEKOTEC ® -CLP in the overlapping range of the sleeves The center markings should be on top of each other. Prevent extensive stretching of the lock strap. 7. DEKOTEC ® -CLP Attaching the closure patch 2. 2. Use a burner flame of average intensity to shrink DEKOTEC ® -MTS. Starting in the middle, heat the sleeve with even motions in the direction of the circumference. Move gradually to the edges 8. DEKOTEC ® -MTS Sleeve installation shrinking DN >400 2 Burners Heat the entire DEKOTEC ® -MTS sleeve evenly with a strong flame intensity The “DEKOTEC“ imprinting disap- pears when introducing adequate heat. The adhesive must be visible at both sleeve sides around the entire circumference. 9. DEKOTEC ® -MTS Sleeve installation post heating The surface to be encased must be thoroughly dried (steel and adjacent work coating). The surface temperature must be ≥ +23°C (≥ +73°F) and must be +3°C (+5.4°F) above the dew point. 3. Drying Pipe diameter Sleeve length Length DEKOTEC ® -CLP DN (mm) inch mm mm 75 3“ 425 75 100 4“ 510 100 150 6“ 685 100 200 8“ 850 100 300 12“ 1195 150 400 16“ 1465 150 500 20“ 1800 150 600 24“ 2135 200 700 28“ 2470 200 800 32“ 2800 200 900 36“ 3135 200 1000 40“ 3470 200 1200 48“ 4135 200 1400 56“ 4805 200 2. 2. 1. 1. A roller must be used to remove the trapped air. Initially, rolling takes place in the direction of the circumference towards the overlapping of the sleeve. In the overlapping area, roll from the center to the edges Move the roller in zigzag to drive the air forward. After the application, the sleeve must cool down for at least 2 hours to reach ambient temperature before the filling of the pipe trench can be started. 11. DEKOTEC ® -MTS Sleeve installation Cooling time 10. DEKOTEC ® -MTS Sleeve installationSmoothing Work steps for DEKOTEC ® -MTS30 and DEKOTEC ® -MTS55: Work steps for DEKOTEC ® -MTS55 DI: Cutting lengths for welding encasements 1. 1. DENSO GmbH P.O. Box 150120 | 51344 Leverkusen | Germany Phone +49 214 26 02-0 | Fax +49 214 2602-217 www.denso.de | [email protected] Our product information, our application recommendations and other product related documents are made for your convenience only. Since many installation factors are beyond our control, the user shall determine the suitability of the products for the intended use and assume all risks and liabilities in connection therewith. All information contained in this document is to be used as a guide and does not constitute a warranty of specification. The information contained in the document is subject to change without notice. For this reason, no liability can be accepted for inaccurate advice or any failure to provide advice. The user is responsible for checking the applications of the product and verifying its suitability for the intended use. Our General Terms of Sale, which are available at www.denso.de, shall be decisive without any exception. 11.2017 This is a translation from the original German product information. In case of any discrepancy or any dispute arising on the interpretation of this product information, the German text of the respective German product information, which is available at www.denso.de, shall be decisive. The legal relationship shall be governed by German law.

Transcript of DEKOTEC -MTS · DEKOTEC®-MTS Recommendation for processing All work steps must be performed...

DEKOTEC®-MTS

Recommendation for processing

■ All work steps must be performed wearing personal protective equipment such as safety shoes, helmet, protection goggles and welder gloves in accordance with the local occupational health and safety regulations. It is strongly recom-mended to train the personnel inexperienced in the processing of shrink sleeves before the application.

■ Adjacent factory coating must be roughened (e.g. emery cloth #40) and beveled with an angle ≤30°.

■ The use of 2 applicators is recommended for pipe diameters > 400mm (16“).■ Required surface cleanliness: The surface must be dry, free of grease, oil, dust

and other contaminations. Steel surfaces have to be cleaned to a degree of at least St 2 or Sa 2,5 (ISO 8501-1).

1. Preparation

General work steps:

General work steps:

■ Clean the surface with a lint-free cloth - The cleaned surface must not be touched with unprotected hands.

2. Cleaning

4. DEKOTEC®-DI Mastic

■ Cut DEKOTEC®-DI Mastic to length in such a way that a closed ring is created in front of the bell. Firmly press DEKOTEC®-DI Mastic with the self-adhesive side on to the pipe and the front of the bell. Afterwards, smooth with a hot palette-knife. Prevent protrusion at the bell.

4. DEKOTEC®-MTS Sleeve installation step 1

■ Heat the adhesion side of the sleeve at the side with the 45° bevel on a lengths of approximately 200 mm (8“).

■ When using master rolls, the sleeves must be cut to the required lengths (see table) and must be covered on one side with 45° bevels.

■ Press heated side of DEKOTEC®-MTS55 DI on to the bell in such a way that the center marking lays on the bell edge.

■ Heat the lose end of the sleeve at a length of app. 100 mm and press on to the already installed end (100 mm overlap).

7. Sleeve installation step 2

■ Heat the adhesion side of the sleeve at the side with the 45° bevel on a lengths of approximately 200mm (8”). Caution: Only heat sleeve for the width of the bell (supporting surface)

6. Sleeve installation step 1

■ Heat the adhesive side (silver) of the DEKOTEC®-CLP closure patch until the surface is glossy.

■ Apply the DEKOTEC®-CLP in the overlapping area of the sleeve by firmly pressing it to the surface, with center markings that lay on top of each other. Support free standing sleeve form the inside while pressing (only with clean gloves)”.

8. DEKOTEC®-CLP Attaching the closure patch

■ Heat the sleeve from the bell to the edge of the bell pipe in the direction of the circumference with even motions.

■ Heat the sleeve from the bell to the edge of the plug-in pipe in the direction of the circumference with even motions.

9. Sleeve installation shrinking

■ When using master rolls, the sleeves must be cut to the required lengths and must be covered with 45° bevels.

■ The cutting length of DEKOTEC®-MTS55 DI is equivalent to the largest circumference of the bell plus 100 mm

■ The circumference of the plug-in pipe must be ≥ 0.65 multiplied by the largest circumference at the bell.

5. Cutting

1.

■ Press the DEKOTEC®-MTS in the 2 o’clock position on the dried sur-face in such a way that the center marking of the sleeve is positioned above the welding seam.

■ Remove the trapped air with a roller as shown in the image.

5. DEKOTEC®-MTS Sleeve installation step 2

2. 1.1.

2.

2.

■ At the loose end of the DEKOTEC®-MTS, heat the adhesive side on a lengths of approximately 100 mm (4“).

■ Press the lose end on to the end that is already installed in such a way that the center markings are on top of each other. The overlap is approximately 100 mm (4“).

6. DEKOTEC®-MTS Sleeve installation step 3

100 mm (4“)

2.

■ Heat the closure patch DEKOTEC®-CLP on the adhesive side (silver) until it becomes glossy.

■ Firmly press DEKOTEC®-CLP in the overlapping range of the sleeves The center markings should be on top of each other.

■ Prevent extensive stretching of the lock strap.

7. DEKOTEC®-CLP Attaching the closure patch

2.2.

■ Use a burner flame of average intensity to shrink DEKOTEC®-MTS.

■ Starting in the middle, heat the sleeve with even motions in the direction of the circumference. Move gradually to the edges

8. DEKOTEC®-MTS Sleeve installation shrinking

DN >400 2 Burners

■ Heat the entire DEKOTEC®-MTS sleeve evenly with a strong flame intensity

■ The “DEKOTEC“ imprinting disap-pears when introducing adequate heat.

■ The adhesive must be visible at both sleeve sides around the entire circumference.

9. DEKOTEC®-MTS Sleeve installation post heating

■ The surface to be encased must be thoroughly dried (steel and adjacent work coating).

■ The surface temperature must be ≥ +23°C (≥ +73°F) and must be +3°C (+5.4°F) above the dew point.

3. Drying

Pipe diameter Sleeve length Length DEKOTEC®-CLP

DN (mm) inch mm mm

75 3“ 425 75

100 4“ 510 100

150 6“ 685 100

200 8“ 850 100

300 12“ 1195 150

400 16“ 1465 150

500 20“ 1800 150

600 24“ 2135 200

700 28“ 2470 200

800 32“ 2800 200

900 36“ 3135 200

1000 40“ 3470 200

1200 48“ 4135 200

1400 56“ 4805 200

2.

2.

1.1.

■ A roller must be used to remove the trapped air. Initially, rolling takes place in the direction of the circumference towards the overlapping of the sleeve.

■ In the overlapping area, roll from the center to the edges Move the roller in zigzag to drive the air forward.

■ After the application, the sleeve must cool down for at least 2 hours to reach ambient temperature before the filling of the pipe trench can be started.

11. DEKOTEC®-MTS Sleeve installation Cooling time10. DEKOTEC®-MTS Sleeve installationSmoothing

Work steps for DEKOTEC®-MTS30 and DEKOTEC®-MTS55:

Work steps for DEKOTEC®-MTS55 DI:

Cutting lengths for welding encasements

1.1.

DENSO GmbHP.O. Box 150120 | 51344 Leverkusen | Germany Phone +49 214 26 02-0 | Fax +49 214 2602-217www.denso.de | [email protected]

Our product information, our application recommendations and other product related documents are made for your convenience only. Since many installation factors are beyond our control, the user shall determine the suitability of the products for the intended use and assume all risks and liabilities in connection therewith. All information contained in this document is to be used as a guide and does not constitute a warranty of specification. The information containedin the document is subject to change without notice. For this reason, no liability

can be accepted for inaccurate advice or any failure to provide advice. The user is responsible for checking the applications of the product and verifying its suitability for the intended use. Our General Terms of Sale, which are available at www.denso.de, shall be decisive without any exception. 11.2017This is a translation from the original German product information. In case of any discrepancy or any dispute arising on the interpretation of this product information, the German text of the respective German productinformation, which is available at www.denso.de, shall be decisive. The legal relationship shall be governed by German law.