Deepika Final Report

download Deepika Final Report

of 36

Transcript of Deepika Final Report

  • 8/8/2019 Deepika Final Report

    1/36

    A

    Seminar Report

    On

    Practical Training Undergone At

    BHARAT HEAVY ELECTRICALS LIMITED

    Submitted For

    In partial fulfillment for the award of the degree for

    Bachelor of Technology

    In

    Electrical Engineering

    (2009)

    SUBMITTED TO :SUBMITTED BY:

    Er. A.K.DhimanDeepika Mittal (Sr. ENGR.)

    Roll No:12

    Block - IV Electrical

    Engineering

    B.H.E.L. Haridwar

    DEPARTMENT OF ELECTRICAL ENGINEERING

    ARYA INSTITUTE OF ENGINEERING AND TECHNOLOGY

    RAJASTHAN TECHNICAL UNIVERSITY

    PREFACE

  • 8/8/2019 Deepika Final Report

    2/36

    Practical knowledge means the visualization of the

    knowledge, which we read in our books. For this, we perform

    experiments and get observations. Practical knowledge is very

    important in every field. One must be familiar with the problems

    related to that field so that he may solve them and become a

    successful person.

    After achieving the proper goal in life, an engineer has to

    enter in professional life. According to this life, he has to serve an

    industry, may be public or private sector or self-own. For the

    efficient work in the field, he must be well aware of the

    practical knowledge as well as theoretical knowledge.

    To be a good engineer, one must be aware of the industrial

    environment and must know about management, working in such a

    industry, labor problems etc., so that he can tackle them

    successfully.

    Due to all the above reasons and to bridge the gap between

    theory and practical, our engineering curriculum provides a practicaltraining of 30 days. During this period, a student works in the

    industry and gets all type of experience and knowledge about

    the working and maintenance of various types of machinery.

    I have undergone my 30 days training (after VI Semester) at

    BHARAT HEAVY ELECTRICALS LIMITED. This report is

    based on the knowledge, which I acquired during my 30 days

    training period at the plant.

  • 8/8/2019 Deepika Final Report

    3/36

    INDEX

    S.No.

    01. INTRODUCTION

    02. BHEL-A Brief Profile

    03. BHEL - AN OVERVIEW

    04. HEEP: AN OVERVIEW

    05. BRIEF SUMMARY OF THE BAR SHOP

    06. TYPES OF TURBOGENERATORS

    07. MATERIAL CHECKING

    08. CONDUCTOR CUTTING AND END CLEANING

    09. TRANSPOSITION OF CONDUCTORS

    10. CROSSOVER INSULATION

    11. PRESSING

    12. ISS- TEST

    13. FORMING OF BAR

    14. ZERO PICKLING OF BAR END

    15. COIL LUG MOUNTING

    16. MAIN BRAZING

    17. CONDUCTOR CUTTING, DEBBERING AND FACE MILLING

    `18. FIRST PICKLING

  • 8/8/2019 Deepika Final Report

    4/36

  • 8/8/2019 Deepika Final Report

    5/36

    INTRODUCTION

    In 1956, India took a major step towards the

    establishment of its heavy engineering industry when Bharat

    Heavy Electrical Ltd., the first heavy electrical manufacturing

    unit of the country was setup at Bhopal. It progressed rapidly and

    three more factories went into production in 1965. The main aim of

    establishing BHEL was to meet the growing power requirement of the

    country.

    B.H.E.L appeared on the power map of India in 1969 when the

    first unit supplied by it was commissioned at the Basin BridgeThermal Power Station in Tamil Nadu. Within a decade, BHEL

    had commissioned the 100 unit at Santaldih. West Bengal.

    BHEL had taken India from a near total dependence on imports to

    complete self-reliance in this vital area of power plant equipment

    BHEL has supplied 97% of the power generating equipment.

    BHEL has already supplied generating equipment to various

    utilities capable of generating over 18000 MW power. Today

    BHEL can produce annually; equipment capable of generating6000MW. This will grow further to enable BHEL to meet all of

    Indias projected power equipment requirement. As well as sizeable

    portion of export targets.

    Probably the most significant aspect of BHELs

    growth has been its

    diversification. The constant reorientation of the organization to meet

    the varied needs intime with time a philosophy that has led to the development of

    a total capability from concepts to commissioning not only in

    the field of energy but also in industry and

    transportation.

  • 8/8/2019 Deepika Final Report

    6/36

    In the world power scene, BHEL ranks among the top ten

    manufactures of power

    plant equipment and in terms of the spectrum of products and services

    offered, it is right

    on top. BHELs technological excellence and turnkey capabilities

    have won it worldwide

    recognition. Over 40 countries in the world over have placed orders

    with BHEL covering

    individual equipment to complete power stations on a turnkey basis.

    In 1978-79 export earnings reached Rs. 122 crores, the highest

    for any one-year.

    BHEL has its headquarters at New Delhi. Its operationsare spread over 11

    manufacturing plants and number of engineering and service divisions

    located across the

    country/ the service divisions includes a network of regional

    branch offices throughout

    India.

  • 8/8/2019 Deepika Final Report

    7/36

    BHEL-A Brief Profile

    BHEL is the largest engineering and manufacturing enterprise

    in India in the energy-related / infrastructure sector, today. BHEL isushering in the indigenous Heavy Electrical Equipment industry in

    India-a dream that has been more than realized with a well-

    recognized track record of Performa

    A widespread network comprising of 14 manufacturing

    companies, which have international recognition for its commitment

    towards quality. With an export presence in more than 60 countries,

    BHEL is truly Indias ambassador to the world. BHELs vision isto become world class engineering enterprise, committed to

    enhancing stakeholder value.

    BHEL has:-

  • 8/8/2019 Deepika Final Report

    8/36

    Installed equipment for over 90,000MW of power

    generation for Utilities, captive and Industrial users.

    Supplied over 25000 Motors with Drive Control System to

    power projects, Petrochemicals Refineries, Steel, Aluminum,

    Fertilizer, Cement plant, etc.

    Supplied Traction electrics and AC/DC locos over

    12000 kms Railway network.

    Supplied over one million Values to Power Plants and other

    Industries

    BHEL - AN OVERVIEW

  • 8/8/2019 Deepika Final Report

    9/36

    The first plant of what is today known as BHEL was established

    nearly 40 years ago at Bhopal & was the genesis of the Heavy

    Electrical Equipment industry in India.

    BHEL is today the largest Engineering Enterprise of its

    kind in India with excellent track record of performance, making

    profits continuously since 1971-72.

    BHEL business operations cater to core sectors of the Indian

    Economy like.

    Power

    Industry

    Transportation

    Transmission

    Defenses etc.

    Today BHEL has

    14 Manufacturing Divisions

    9 Service Centers

    4 Power Sector Regional Centers

    150 Project sites

    BHELs vision is to become world -class engineering

    enterprise, committed to enhancing stakeholder value. The

  • 8/8/2019 Deepika Final Report

    10/36

    greatest strength of BHEL is its highly skilled and committed

    44,000 employees.

    Spread all over India & abroad to provide prompt and effective

    service to customers.

    BUSINESS SECTOR

    BHEL operations are organized around business sectors to

    provide a strong market orientation. These business sectors are

    Power Indus and International operations.

    POWER SECTOR

    Power sector comprises of thermal, nuclear, gas and hydro

    business. Today BHEL supplied sets account for nearly 65% of

    the total installed capacity in the country as against nil till 1969-

    70.

    BHEL has proven turnkey capabilities for executing power projects from concept to commissioning and manufactures boilers, thermal turbine generator set and auxiliaries up to500MW.

    It possesses the technology and capability to procurethermal power generation equipment up to 1000MW.

    Co-generation and combined cycle plants have also beenintroduced.

    For efficient use of the high ash content coal-BHEL suppliescirculating fluidized boiler.

  • 8/8/2019 Deepika Final Report

    11/36

    BHEL manufactures 235MW nuclear sets and has alsocommenced production of 500MW nuclear set.

    Custom-made huge hydro sets of Francis, Elton and Kaplan types

    for different head- discharge combinations are also engineered andmanufactured by BHEL.

    INDUSTRY SECTOR

    BHEL is a major contributor of equipment and system toimportant industries like

    Cement

    Petrochemicals

    Fertilizers

    Steel paper

    Refineries

    Mining and Telecommunication

    The range of system and equipment supplied including captive powerstations

  • 8/8/2019 Deepika Final Report

    12/36

    High speed industrial drive turbines

    Industrial boilers and auxiliaries

    Waste heat recovery boilers

    Gas turbines pump, valves, seamless steel tubes

    Heat exchangers

    Process control etc.

    TRANSPORATION :-

    BHEL supplies a wide equipment and system to Indian

    Railways.

    Electric locomotive

    Traction electric and traction control equipment

    TELECOMMUNICATION:-

    BHEL also caters to Telecommunication sector by way of

    small, medium and large switching system.

    BHEL has divided into many blocks:-

  • 8/8/2019 Deepika Final Report

    13/36

    1). Block-1:-

    In block one turbo generator, generator, exciter motors

    (A.C&D.C) are manufactured & assembled

    2). Block-2:-

    In block two large size fabricated assemblies\component for

    power equipment are manufactured & assembled.

    3) Block-3:-

    In block -3 steam turbine, hydro turbines, and gas turbines,

    turbines blade are manufactured & assembled

    4) Block-4:-

    In block -4winding for turbo generator, hydro generator,

    insulation of A.C&D.C motors insulating component for turbo

    generator, hydro generator motors are manufactured &

    assembled

    5) Block-5:-

    In block -5 fabricated parts of steam turbine water box,

    hydro turbine turbines parts are manufactured & assembled

    6) Block-6:-

    In block -6 fabricated oil tanks hollow guide blades, rings,

    stator frames rotor spiders are manufactured & assembled

    7) Block-7:-

    In block -7all types of dies including stamping dies,

    stamping for generators &motors are manufactured & assembled

    8) Block-8:-

    In block -8 LP heaters, ejectors, steam coolers, oil coolers, ACG

    coolers, oil tanks are manufactured & assembled

    MANUFACTURING DIVISIONS

  • 8/8/2019 Deepika Final Report

    14/36

    Heavy Electrical Plant, Piplani, Bhopal

    Electrical Machines Repair Plant (EMRP), Mumbai

    Transformer Plant P.O. BHEL, Jhansi.

    Bharat Heavy Electrical Limited :

    Central Foundry Forge Plant., Ranipur, Hardwar

    Heavy Equipment Repair Plant, Varanasi.

    Insulator Plant, Jagdishpur, Distt. Sultanpur.

    Heavy Power Equipment Plant, Ramachandra Puram, Hyderabad

    High Pressure Boiler Plant & Seamless Steel Tube Plant,

    Tiruchirappalli.

    Boiler Auxiliaries Plant, Indira Gandhi Industrial Complex,

    Ranipet.

    Industrial Valves Plant, Goindwal.

    Electronics Division :

    Electronics Systems Division.

    Amorphous Silicon Solar Cell Plant (ASSCP).

    Electro porcelains Division.

    BANGALORE

  • 8/8/2019 Deepika Final Report

    15/36

    Component Fabrication Plant, Rudrapur.

    Piping Centre, Chennai.

    Heavy Electrical Equipment Plant,

    Regional Operations Division, New Delhi

    HEEP: AN OVERVIEW

    Over the years, Bharat Heavy Electrical Limited hasemerged as world class engineering and Industrial giant, the best of

    its kind in entire South East Asia. Its business profile cuts across

    various sectors of engineering/power utilities and industry. The

    company today enjoys national and international presence

    featuring in the " fortune international-500 and is ranked among

    the top 12 companies of the world, manufacturing power generation

    equipment. BHEL has now 14 manufacturing division, 8 service

    centers and 4power power sectors regional centers besides alarge number of project sites spread over India and abroad.

    The company is embarking upon an ambitious growth path

    through clear vision, mission and committed values to sustain and

    augment its image as a world-class enterprise.

    VISION

    A world-class innovating, competitive and profitable

    engineering enterprise providing total business solution.

  • 8/8/2019 Deepika Final Report

    16/36

    MISSION

    To be the leading Indian engineering enterprise providing

    quality products system and services in the field of energy,transportation, infrastructure and other potential areas.

    VALUES

    Meeting commitments made to external & internal

    customers

    Foster learning creative and speed of response

    Respect for dignity and potential of individual

    Loyalty and pride in the company

    Team playing

  • 8/8/2019 Deepika Final Report

    17/36

    MANUFACTURING PROCESS OF

    TURBO GENERATOR & STATOR BAR

    BRIEF SUMMARY: ABOUT THE BAR SHOP

    This shop is meant for manufacturing of stator winding coils of

    generator that may be turbo generator or hydro generator.

    HR BARS

    Manufacturing of bars of different capacity depends upon the

    water head available at site. The hydro generator is air called

    generator of lesser length.

    TURBO GENERATOR BAR

    For the turbo generator the manufacturing of bars of standard

    capacity such as 100 MW, 130MW, 150MW, 210/235MW,

    210/250MW. This plant has capacity and technology to

    manufacturing 800 MW generators.

  • 8/8/2019 Deepika Final Report

    18/36

    TYPE OF GENERATORS

    The generator may be classified based upon the cooling

    system used in the generators such as;

    THRI, TARI, THDI, THDD, THDF, THFF, THW

    T =i.e. Turbo Generator or Hydro Generator.

    H/A =i.e. Hydrogen Gas or Air.

    R/D/F/I =i.e. Radial, indirect, forced, direct etc.

    I/D/F =i.e. Indirect cooling, direct cooling, forced cooling.

    W =i.e. cooling media used for cooling of stator coil

    e.g. water.

    MATERIAL CHECKING

    First we check the material of the conductor. And the total

    insulation upon the conductor. The width of the copper

    conductor should be:

    a. For Lower bar = 8 x 2.8mm (Solid)

    b. For Upper bar = 8 x 1.3mm (Solid)

    c. For Hollow conductor= 8 x 4.6 x 1.5mm (Solid)

  • 8/8/2019 Deepika Final Report

    19/36

    CONDUCTOR CUTTING AND END CLEANING

    This process is done by the automatic CNC machine, in this

    process the length of lower bar & upper bar is decided as

    following as per drawing-

    Lower Bar

    a. Solid conductor length = 10,200mm (10

    Plates)

    b. Hollow conductor length = 10,200mm (10 Plates)

    Upper Bar

    a. Solid conductor length = 10,050mm (10

    Plates)

    b. Hollow conductor length = 10,050mm (10 Plates)

    This insulation is removed from both ends after the cutting of

    conductor i.e. 500mm for both lower & upper bar.

    TRANSPOSITION OF CONDUCTOR

    Transposition means changing or shifting of position of each

    conductor in active care (slot) part. After cutting the requirednumber of conductors are arranged on the comb in staggered

    manner and than bands are given to the conductor with the

    help of bending die at required distance.

  • 8/8/2019 Deepika Final Report

    20/36

    Setting of die

    a. Comb of setting for lower bars

    Die 1st Die 2nd Die 3rd

    2200.2mm 3735.3mm 6586.2mm

    b. Comb of setting for Upper bars

    Die 1st Die 2nd Die 3rd

    2109mm 3620.2mm 6496.2mm

    This process is repeated to making another half of the bar.

    CROSS OVER INSULATION

    Cross over insulation is give to the conductor for the protection

    in which the insulating spacer are provided at the cross over

    portion. In this insulation the No-max paper is used.

    Here the filter material (insulating putty of moulding

    micanite) spacer is provided along the high of bar to maintain

    the rectangular shape. The size of spacer should be

    1st Band = 146mm

    2nd Band = 219mm

    3rd Band = 292mm

  • 8/8/2019 Deepika Final Report

    21/36

    STACK CONSOLIDATION OR PRESSING

    The core part of the bar stack is pressed in press under the

    pressure between 70kg to 80kg (various from product to

    product) and the temperature between 90 Deg.C to 160 Deg.C

    for a given period. Here four bars is pressed in one time and six

    to eight plates are used for pressing. After that the consolidated

    stack is withdrawn from the press.

    INTER STAND SHORT TEST (I.S.S.Test)

    In this test first we make the distance to the non insulating

    portion of the bar. Here we check the short between any two

    conductor. After this test the bars are again go for the second

    pressing. In which attached full slot separator between two halfbar no-max paper and tapped with transparent film. In this test if

    any error is found then it has to be rectified.

    FORMING OF BAR

    In this operation the straight bar stack is formed as per overhang

    profile. In this process bars should be formed on universal

    former and marked for the thermal space. After it they are

    moved for cutting of extra conductor.

  • 8/8/2019 Deepika Final Report

    22/36

  • 8/8/2019 Deepika Final Report

    23/36

    COIL LUG MOUNTING

    In this process contact sleeve and the bottom part of the water

    box are adjust at the give dimensions. The operation of

    mounting of contact sleeve and bottom part of water box is

    complete in following steps-

    a. Check the dimension of contact sleeve and water box bottom

    part.

    b. Stand by bar for setting of lug.

    c. Setup to the solid conductor in each row as per drawing.

    d. Then insert the contact sleeve upon the solid and hollow

    conductor and temporally installed to it. And also installed thebottom part of water box.

    e. Maintain the gap between contact sleeve and bottom part of

    water box approx 20mm.

    After the lug mounting cutting of extra solid conductor.

  • 8/8/2019 Deepika Final Report

    24/36

    MAIN BRAZING

    There are the following steps to brazed the lug.

    a. Stand by bar of setting for brazing.

    b. Then heated the lug point through the two indictor at the

    temperature of 700 Deg.C .

    c. For brazing use brazing alloy L-Ag-15P by four person. This is

    the silver platinum alloy wire of melting point 700 Deg.C to 750Deg.C.

    d. This Temperature is give through the laser rays.

    CONDUCTOR CUTTING, FACE MILLING AND DEBBERING

    After the main brazing bars is moved for cutting of extra part ofconductors as per drawing. Here cut the end part of the bottom

    part of water box and taken for face milling.

    In this process the conductor is given the accurate shaped as per

    the measurement and it is taken in account that any part of the

    surface is not left uneven and dull.

    Then in Debbering, the bars edges are many a time left with

    twigs and sharp needle type mettle cutting known as bar and this

    process of removing is known as Debbering.

  • 8/8/2019 Deepika Final Report

    25/36

    FIRST PICKLING

    This is the same process of pickling which is done before the lug

    mounting or zero pickling. After this pickling process the bar is

    moved the brazing of top part of water box in both side.

    BRAZING OF TOP PART

    Thought the induction process the top part of water box is

    brazed in both side.

    As per the previous main brazing first we stand by bars of

    setting for brazing then we attached the top part from the bottom

    part of water box. Then healed the top part by top inductors at the

    temperature of 400Deg.c.

    For this type of brazing use L-Ag-40Cd. This is the alloy

    silver academy which have 40% cadmium and the melting point is

    400 Deg.C to 500 Deg.C. This brazing is done for both end.

    After the brazing the bars is go for second pickling which is the

    same process as previously explain.

  • 8/8/2019 Deepika Final Report

    26/36

    WATER FLOW TEST

    Thought this test check the flow water equivalently in the

    hollow conductor of the bar. There is the following steps of

    checking-

    a. Water should be exit all the total hollow conductor.

    b. If some burrs are jammed it should be removed to give very

    high pressure of water and clean with the help of solid wire.c. The main point of testing is that the water flow into the bar and

    exit from the water box fall down approximately to cover 1 Mtr.

    From each conductor.

    NITROGEN LEAK TEST

    In this test the bar is tested for leakage into the components of

    bar. In this test flow of nitrogen gas with pressure of 10kg/Cm2

    to check the leakage in to the hollow conductor. If leakage

    found the bar is rejected.

  • 8/8/2019 Deepika Final Report

    27/36

    THERMAL SHOCK TEST

    The cycles of hot (80 Deg.C) and cold (30 Deg.C) water are

    flew thought the bar to ensure the thermal expansion and

    contraction of the joints. The time of low of hot & cold water

    should be approx 32 to 40min and give the time between to flow

    of hot & cold water is 5 min. this process is applied atleast 8

    hours.

    HELIUM LEAKAGE TEST

    In this test the bars end is tested to flow of helium gas with the

    given pressure if the end part of the bar is leakage then the

    helium gas is covered the surface of water box and indicator

    indicate the point of leakage.

    INSULATION

    For the insulation sunmika therm tape or sunmika pleese tape is

    used which is the combination of mica + glass + varnish. It is

    used for corona protection. In this insulation to layer of pleese

    tape + to layer of therm tape and after them again to mica pleese

    tape is used.

  • 8/8/2019 Deepika Final Report

    28/36

    Process of Insulation

    a. Clean the bar.

    b. Clean with chemical or thinner.

    c. Taping

    d. Realizing film from the mica plastic section.

    In insulation the wall thickness of insulation is subjected to the

    generating voltage of the machine.

    IMPREGNATION AND BAKING

    1. Thermoreactive system: In case of rich resin insulation the bar

    is pressed in closed box in heated condition and baked under

    pressure and temperature as per requirement for a given period.

    2. Micalastic system: In case of poor resin system the insulated

    bars are heated under vaccum and impregnated (dipped) in

    heated resin so that all the air gaps are filled, layer by layer with

    resin then extra resin is drained out and bars are heated and

    baked under pressed condition in closed box fixture.

    VPI Micalastic System

    The bars already laid in closed fixture and full fixture is

    impregnated in resin and then fixture with box is baked under

    given temperature for the given duration.

  • 8/8/2019 Deepika Final Report

    29/36

    VIP Micalastic System

    The individual bar is heated in vaccum and impregnated in

    resin. Then bar is taken out and pressed in closed box fixture

    and then baked at given temperature for given duration.

    FINISHING

    The baked and dimensionally correct bars are sanded-off to

    smoothen the edges and surface calibrated if required for the

    dimension.

    CONDUCTING VARNISH COATING

    OCP (Outer Corona Protection) Coating: The black semi-

    conducting varnish coating is applied on the bar surface on the

    core length.

    ECP (End Corona Protection) Coating: The grey semi-

    conducting varnish is applied at the bend outside core end of

    bars in gradient to prevent from discharge and minimize the end

    corona.

  • 8/8/2019 Deepika Final Report

    30/36

    TESTING

    1. Tan Test: This test is carried out to ensure the healthiness of

    dielectric (insulation) i.e. dense or rare and measured the

    capacitance loss.

    2. H.V. Test: The each bar is tested momentarily at high voltage

    increased gradually to three times higher than rated voltage.

    DISPATCHED FOR WINDING

    If the bar is passed in all the operation and testing after

    completing then the bar is send for stator winding.

  • 8/8/2019 Deepika Final Report

    31/36

    TURBO GENERATORS

    (a) Air Cooled Generators Upto 200 Mw Range (Type:

    TARI ) Salient Design Features

    Stator core and rotor winding direct

    air-cooled

    Indirect cooling of stator winding

    Horizontally split casing design of

    stator

    Vertically side mounted coolers in a

    separate housing

    Micalastic bar type insulation system

    Separately assembled stator core and

    winding for reducing the manufacturing cycle

    Brushless/static excitation system

  • 8/8/2019 Deepika Final Report

    32/36

    (b) Hydrogen Cooled Turbogenerators Of 140-260 Mw Range(Type: THRI ) Salient Design Features

    Stator core and rotor winding directly

    hydrogen cooled

    Indirect cooling of stator winding

    Rigid core bar mounting

    Micalastic insulation system

    End shield mounted bearings

    Top ripple springs in stator slots

    Ring type shaft seals

    Symmetrical ventilation.

  • 8/8/2019 Deepika Final Report

    33/36

    MOTOR WINDING

    9.1 Technical Requirements

    (1) Count the coil groups in the anti clock wise direction locking

    from the connection end.

    (2) Leads of the coils groups lying on the outer periphery of the

    overhang position shall be the finish and those lying on the inner

    periphery shall be the start to coil groups.

    (3) Leads shall be taken form the coil side lying at inner periphery of

    slot No.1.

    (4) The coil group No.1 shall Lie at top with its axes coinciding with

    the vertical axis of the frame.

    (5) Take out terminal leads 02 U2, V2, W2 for left hand side terminal

    box and 02 U1, V1, W1 for right hand side terminal box. When

    looking form the connection end.

  • 8/8/2019 Deepika Final Report

    34/36

    Circuit diagram:-

    WINDING DIAGRAM OF MOTOR WINDING

  • 8/8/2019 Deepika Final Report

    35/36

    9.2 Winding data

    9.3 Connection of motor winding

    NO. OF PHASE 3

    NO. OF POLES 6

    PHASE CONNECTION Y

    NO. OF PARELLEL PATH 2

    NO. OF COIL GROUP 18

  • 8/8/2019 Deepika Final Report

    36/36

    CONCLUSION

    The second phase of training has proved to be quite

    faithful. It proved an opportunity for encounter with such huge

    machines like turbo-generator hydro generator etc.

    The architecture of B.H.E.L., the way various units are

    linked and the way working of whole plant is controlled make the

    students realize that Engineering is not just structural description but

    greater part is planning and management. It provides an

    opportunity to learn tech. Used at proper place and time can save a lotof labour.

    But there are few factors that require special mention.

    Training is not carried in true spirit. It is recommended that there

    should be projectors especially for trainees where presence of

    authorities is ensured.

    However, training has proved to be satisfactory. It has allowed

    us an opportunity to get an exposure of the practical implementation

    of theoretical fundamentals.