DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam...

144
SUMMER INTERNSHIP REPORT ASSESMENT OF INDIAN POWER MARKET PRE AND POST GRID FAILURE Under the guidance of Ms Sugandha Agrawal, Sr Fellow (Strategic Management),CAMPS,NPTI & Mr.V.K Agrawal, General Manager, NLDC AT National Load Dispatch Centre, New Delhi Submitted by PRAVAR BALLAL ROLL NO:60 MBA( POWER MANAGEMENT ) (Under the Ministry of Power, Govt. of India) Affiliated to 1

Transcript of DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam...

Page 1: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

SUMMER INTERNSHIP REPORT

ASSESMENT OF INDIAN POWER MARKET PRE

AND

POST GRID FAILURE

Under the guidance of

Ms Sugandha Agrawal, Sr Fellow (Strategic Management),CAMPS,NPTI

&

Mr.V.K Agrawal, General Manager, NLDC

AT

National Load Dispatch Centre, New Delhi

Submitted by

PRAVAR BALLAL

ROLL NO:60

MBA( POWER MANAGEMENT )

(Under the Ministry of Power, Govt. of India)

Affiliated to

MAHARSHI DAYANAND UNIVERSITY, ROHTAK

1

Page 2: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

2

Page 3: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

DECLARATIONI,PRAVAR BALLAL, Roll No-60, student of MBA-Power Management(2012-14) at National Power Training Institute, Faridabad hereby declare that the Summer Training Report entitled “ASSESSMENT OF INDIAN POWER MARKET PRE AND POST GRID FAILURE” is an original work and the same has not been submitted to any other Institute for the award of any degree

A Seminar presentation of the Training Report was made on -----------------------------------

and the suggestions as approved by the faculty were duly incorporated.

Presentation In-Charge Signature of the Candidate

(Faculty)

Countersigned

Director/Principal of the Institute

3

Page 4: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

ACKNOWLEDGEMENT

I am thankful to Mr. V. K. Agrawal (GM,NLDC) for the support and help to carry out this project work successfully.

Words would be too small to describe the brilliance and versatility of my project guide Mr. Kaushik Dey (Sr. Engineer, NLDC) for their able and consistent guidance, supervision, help and encouragement at each step of the work which motivated me through the project. I really feel lucky to be under such an able guiding force in the field of power sector who never got irritated even with the most minor & silliest doubts of mine.

I would like to extend my gratitude to Ms. Sugandha Agrawal, Sr. Fellow, NPTI (My Mentor ) for her continuous help and motivation during summer internship.

I am very much thankful to Mr. S.K.Choudhary (Principal Director, CAMPS, NPTI),

Ms. Manju Mam (Director, NPTI), Ms. Indu Maheshwari (Deputy Director, NPTI) for providing me an opportunity to work with National Load Dispatch Centre & their precious help and support.

My sincere thanks to my Batch Mates & Seniors who are working with other reputed organization for the help they rendered at each stage of the project.

Pravar Ballal

4

Page 5: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

EXECUTIVE SUMMARY

An analysis of short-term transactions of electricity in India has been made in this Report on Short-term Power Market for the year 2012-13. Here, “short-term transactions of electricity” refers to contracts of less than one year period for electricity transacted under bilateral transactions through Inter-State Trading Licensees (only inter-state part) and directly by the

Distribution Licensees (also referred as Distribution Companies or DISCOMs), Power Exchanges (Indian Energy Exchange Ltd (IEX) and Power Exchange India Ltd (PXIL)), and Unscheduled Interchange (UI). The analysis includes (i) Yearly/monthly/daily trends in shortterm transactions of electricity; (ii) Time of the day variation in volume and price of electricity transacted through traders and power exchanges; (iii) Trading margin charged by trading licensees for bilateral transactions (iv) Analysis of open access consumers on power exchanges; (v) Major sellers and buyers of electricity through licensed traders and power exchanges; (vi) Effect of congestion on volume of electricity transacted through power exchanges; (vii) Tariffs of long-term sources of power for various distribution companies; and (viii) Analysis of Renewable Energy Certificates (RECs) transacted through power exchanges.

Salient features of the report are listed below and are discussed in details in subsequent sections.

1. Of the total electricity procured in India in 2012-13, the short-term power market comprised 11 per cent. The balance 89 percent of generation was procured mainly by distribution companies through long-term contracts and short-term intra-state transactions.

2. In volume terms, the size of the short-term market in India was 98.94 billion kWh (units) in the year 2012-13. As compared to the volume of electricity transacted through short-term market in the year 2011-12 (94.51 billion units), this was about 5 percent higher. Majority of this growth in volume of 4.43 billion units was accounted for by growth in transactions through power exchanges (181%), followed by bilateral transactions through the inter-state trading licensees (6%). The direct bilateral transactions between the DISCOMs and the transactions through UI declined by 19% and 68% respectively. A caveat, however, needs to be added; in case of traders only inter-state transactions have been considered.

5

Page 6: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

3. Excluding UI and direct bilateral sale between the DISCOMs, the volume of electricity transacted was 59.66 billion units in 2012-13. This was about 16 percent higher than in 2011-12. Volume of electricity transacted through power exchanges witnessed a sharp increase of about 51% over 2011-12 volume. On the other hand, the increase in the volumeof electricity transacted through inter-state trading licensees was very low at 0.8%. In monetary terms, the size of this segment of the short-term market was `24272 crore in the 2 year 2012-13 , which was 18% more than in the year 2011-12. Of this, 8646 crore was the value of electricity transacted through power exchanges (56% more than `5553 crore done in 2011-12), and the balance of `15624 crore was the value of inter-state transaction of electricitythroughtradinglicensees(about4%more than`14979croredone in2011-12).

4. In absolute terms, the volume of UI in the year 2012-13 decreased by 11% over 2011-12. The share of UI as a percentage of total volume of short-term transaction of electricity continued the downward trend of past years and was about 25% in 2012-13, down from 39%, 34% and 29% respectively in the years 2009-10, 2010-11 and 2011-12.

5. The share of direct bilateral transactions between DISCOMs as a percentage of total short term transaction volume declined to about 15% in the year 2012-13 (as compared to about 16% in the year 2011-12). In terms of volume, these direct bilateral transactions between

DISCOMs also witnessed a decline of about 6% in 2012-13 as compared to 2011-12.

6. The weighted average price of electricity transacted through power exchanges was Rs3.67 per kWh and through trading licensees was `4.33 per kWh in 2012-13. The corresponding values for the year 2011-12 were `3.57 per kWh and `4.18 per kWh, respectively. In the year 2012-13, the weighted average price of electricity transacted through Day Ahead Market sub-segment of the power exchanges was `3.67/kWh and that through Term Ahead Market sub-segment was Rs3.91/kWh.

6

Page 7: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

LIST OF FIGURESFigure 1:Total Volume of Electricity Transacted through Trading Licensees and Power

Exchange............................................................................................................................29

Figure 2:Electricity Transacted through traders and PXs as % to Total Volume of Short-

term....................................................................................................................................30

Figure 3:Price of Electricity transacted through Trading Licensees and Power Exchange

...........................................................................................................................................32

Figure 4:Volume of electricity transacted through UI.......................................................34

Figure 5:Price of electricity transacted through UI...........................................................35

Figure 6:Volume of Electricity Transacted Directly between DISCOMs.........................36

Figure 7:Share of Different Segments in Total Electricity................................................37

Figure 8:Share of Different Segments in Short Term Transactions..................................38

Figure 9:Total volume of short term transaction of Electricity.........................................40

Figure 10:PERCENTAGE SHARE OF ELECTRICITY TRANSACTED BY TRADING

LICENSEES IN 2012-13...................................................................................................46

Figure 11:Comparison of price of bilateral, Power Exchange and UI Transactions in

2012-13..............................................................................................................................48

Figure 12:Price of Electricity Transacted through Traders during....................................51

Figure 13:Details of congestion in Power Exchange.........................................................55

Figure 14:Frequency profile in India in 2012-13..............................................................61

7

Page 8: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

LIST OF TABLES

Table 1:Total Volume of Short-term Transactions of Electricity with respect to Total

Electricity Generation........................................................................................................27

Table 2:Total Volume of Short-term Transactions of Electricity with respect to Total

Electricity Generation........................................................................................................28

Table 3:Electricity Transacted through Trading Licensees and Power Exchanges...........29

Table 4:Electricity Transacted through traders and PXs as % to Total Volume of Short-

term....................................................................................................................................31

Table 5:Electricity Transacted through traders and PXs as % to Total Volume of Short-

term....................................................................................................................................33

Table 6:Volume and Price of Electricity Transacted through UI......................................34

Table 7: Volume of Electricity Transacted Directly between DISCOMs.........................36

Table 8:Total volume of short term transaction of Electricity...........................................41

Table 9:Volume of Short-term Transactions of Electricity as % of Total Electricity.......43

Table 10:PERCENTAGE SHARE OF ELECTRICITY TRANSACTED BY TRADING

LICENSEES IN 2012-13...................................................................................................44

Table 11:Price of Short-term Transactions of Electricity (Rs/kWh), 2012-13..................49

Table 12:Price of Electricity Transacted through Traders during.....................................52

Table 13:Frequency profile in india in 2012-13................................................................60

Table 14:Charges for Deviation.........................................................................................63

Table 15:OVER DRAWAL BY BENEFICIARY OR BUYER.......................................77

Table 16:UNDER DRAWAL BY BENEFICIARY / OVER INJECTION BY APM

GENERATING STATION/SELLER (EXCEPT INFIRM POWER)...............................78

Table 17:UNDER INJECTION BY GENERATOR OR SELLER..................................79

Table 18:INFIRM POWER BY GENERATOR UNDER APM OR SELLER.................80

8

Page 9: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

ABBREVIATIONS

Abbreviation Expanded Version

ADHPL Allain Duhangan Hydro Power Limited

ADHPL (GOHP) Allain Duhangan Hydro Power Limited (GOHP Share)

APCPDCL Central Power Distribution Company of Andhra Pradesh

APPCC Andhra Pradesh Power Coordination Committee

AVVNL Ajmer Vidyut Vitaran Nigam Limited

BALCO Bharat Aluminium Company Limited

BESCOM Bangalore Electricity Supply Company Limited

BRPL BSES Rajdhani Power Limited

BSEB Bihar State Electricity Board

BU Billion Units (Billion kWh)

BYPL BSES Yamuna Power Limited

CCGT Combined Cycle Gas Turbine

CERC Central Electricity Regulatory Commission

CGS Central Generating Stations

CPP Captive Power Producer/Plant

CSPTCL Chhattisgarh State Power Trading Company Limited

CSPDCL Chhattisgarh State Power Distribution Company Limited

DAM Day Ahead Market

DISCOMS Distribution Companies

FGUTPP Firoz Gandhi Unchahar Thermal Power Project

GoHP Government of Himachal Pradesh

GPS Gas Power Station

GUVNL Gujarat Urja Vikas Nigam Limited

HEP Hydro Electric Project

HHI Herfindahl-Hirschman Index

HPSEB Himachal Pradesh State Electricity Board

9

Page 10: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

HSD High Speed Diesel

IEX Indian Energy Exchange Limited

ISGS Inter State Generating Station

JKHCL Jaypee Karcham Hydro Corporation Limited

10

Page 11: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

TABLE OF CONTENTS

ContentsDECLARATION.........................................................................................................................................3

ACKNOWLEDGEMENT...........................................................................................................................4

EXECUTIVE SUMMARY.........................................................................................................................5

LIST OF FIGURES..........................................................................................................................................7

INTRODUCTION.....................................................................................................................................14

1.1 OVERVIEW.............................................................................................................................14

1.2 OBJECTIVE............................................................................................................................15

1.3 SCOPE OF WORK.................................................................................................................16

1.4ORGANIZATIONAL PROFILE..................................................................................................16

Mission..............................................................................................................................................17

Functions of National Load Dispatch Centre.....................................................................................17

CHAPTER-2.............................................................................................................................................19

LETERATURE SURVEY, LEGAL POLICIES AND RESEARCH METHODOLOGY.........................19

2.1 LITERATURE SURVEY................................................................................................................19

2.2 LEGAL POLICIES..........................................................................................................................20

2.2.1 Real Time Power System Operation and Control.....................................................................20

2.2.2 Cooperative Game Theory........................................................................................................20

2.2.3 Transmission costs allocation...................................................................................................21

2.2.4 Frequency Control Models.......................................................................................................22

2.3 METHODOLOGY..........................................................................................................................23

CHAPTER-3.............................................................................................................................................25

SHORT-TERM POWER MARKET IN INDIA, 2012-13.........................................................................25

3.1 Yearly Trends in Short-term Transactions of Electricity (2008-09 to 2011-12)...............................................................................................................................................................25

3.1.1 Total Short-term Transactions of Electricity with respect to Total Electricity Generation................................................................................................................26

3.1.2 Electricity Transacted through Trading Licensees and Power Exchanges.....27

3.1.3 Electricity Transacted through UI.............................................................................................33

3.1.4 Electricity Transacted Directly Between DISCOMs.................................................35

11

Page 12: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

3.2 Monthly Trends in Short-term Transactions of Electricity (April 2012-March 2013)...................................................................................................................................................37

3.2.1 Volume of Short-term Transactions of Electricity....................................................................38

3.2.2 Price of Short-term Transactions of Electricity........................................................47

3.3 Effect of Congestion on Volume of Electricity Transacted through Power Exchanges.........................................................................................................................................51

3.3.1Congestion management: Transmission congestion occurs when there is insufficient transmission capacity to simultaneously accommodate all requests for transmission service within a region. Where there is no congestion, there shall be no restriction of access to the interconnection and no specific procedure for access to transmission service.............................................................55

3.3.2PRINCIPLES OF CONGESTION MANAGEMENT: In principle, congestion can only be relieved physically by reducing generation or increasing consumption on the surplus side of the bottleneck and, conversely, by increasing generation or reducing consumption on the shortfall side. Depending on which time phase one is in, different methods can be used for managing congestion. These methods should be based on the following principles:............................................................56

3.3.3CONGESTION MANAGEMENT METHODS: Congestion is relatively prevalent on interconnections because they were not built to facilitate the current large electricity flows between countries............................................................................................................................................56

3.4 FREQUENCY PROFILE................................................................................................................59

CHAPTER-4.............................................................................................................................................62

INITIATIVES TAKEN TOWARDS FURTHER IMPROVEMENT OF GRID.......................................62

4.1 DEVIATION SETTELMENT MECHANISM................................................................................62

4.1.1. Objective..................................................................................................................................62

4.1.2. Scope.......................................................................................................................................62

4.1.3. Charges for the Deviations:.....................................................................................................62

4.1.4. Declaration, scheduling and elimination of gaming.................................................................66

4.1.5. Limits on Deviation volume and consequences of crossing limits...........................................67

4.1.6. Compliance with instructions of Load Despatch Centre..........................................................73

4.1.7. Accounting of Charges for Deviation......................................................................................73

4.1.8. Schedule of Payment of Charges for Deviation.......................................................................74

4.1.8. Application of fund collected through Deviations...................................................................76

4.1.9. Power to Relax.........................................................................................................................76

4.1.10. Power to issue directions:-.....................................................................................................77

4.2 Ancillary Service..............................................................................................................................81

4.2.1 Frequency Support Ancillary Services (FSAS).........................................................................84

12

Page 13: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

4.2.2 Voltage Control Ancillary Services (VCAS) & Black Start Ancillary Services (BSAS)..........85

CONCLUSION.........................................................................................................................................86

BIBLIOGRAPHY...........................................................................................................................................87

ANNEXURE – 1...........................................................................................................................................88

ANNEXURE – 2...........................................................................................................................................90

ANEXXURE-3..........................................................................................................................................99

13

Page 14: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

CHAPTER-1

INTRODUCTION

1.1OVERVIEWIn India, the total installed capacity of 211 GW is in excess of 35% of the total peak

demand in the country which was close to 135 GW for the year 2012-13. Whereas the

peak demand actually met was only to the extent of 123 GW, thereby leading to an

‘Unserved Demand’ of 12GW. Evidently, the issue is not with the availability of

adequate generation capacity but with the non-availability of generation capacity due

to the prevailing fuel shortage and then followed by non-utilization due to inadequacy

in evacuation system and inability of the cash strapped Discoms to purchase power to

serve the needs of the consumers.

Analysis of the Day-Ahead Market at IEX shows the same phenomenon where the

total monthly sell bids received were 3887 MUs, higher than the total buy bids of

3271 MUs in the market indicating an over-supply situation. As a result the prices of

electricity discovered at IEX came down substantially. The prices discovered on the

exchange in the recent months are lower than the prices that prevailed earlier this year

as well as the prices of last summer. The unconstrained price has come down from

Rs3.42 per unit in May’12 to Rs2.73 in May’13. Similarly the area price showed

downward trend as compared to the same month last year.

As compared to the last month the unconstrained price fell down by 15% from 3.16

per unit in April’13. The area prices were also lower than the values in the previous

14

Page 15: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

month. Even the constrained region of south experienced lower prices this month,

with average area price falling from Rs8.41 per unit in April’13 to Rs6.47 per unit in

May’13, a drop of 23%

While no Discoms are utilizing cheaper power from the exchange as an alternate to

load shedding, many industries are utilizing the exchange as an alternate to costly

power through diesel generator sets. In the month of May, the average participation at

IEX in the day-ahead electricity market was 1297, higher from 1244 in the month of

April’13, whereas the maximum participation of 1394 was observed on May 24

which was the hottest day of the year, with the average daily traded volume hovered

around 80.6 MUs in May’13

There was also a substantial decrease in the congested volume in May’13 as

compared to the previous month primarily due to more wind generations in Tamil

Nadu which relieved the shortage in the state. The volume lost due to congestion in

May’13 was close to 362.8 MUs whereas in April’13 the same touched 521.4 MUs, a

drop of 30%

1.2OBJECTIVE

A well-functioning electricity market requires an effective market monitoring

process. The main focus of this study is to be a part of market monitoring process and

to closely look after well-functioning of electricity market. Here, “short- term

transaction of electricity” refers to the contrast of less than one year period, for

electricity transacted (inter-state & intra-state) through Inter-state Trading Licensees 15

Page 16: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

and directly by the Distribution Licensees, power Exchanges (Indian Energy

Exchange Ltd (IEX) and Power Exchange India Ltd (PXIL), and Unscheduled

Interchange (UI).

The main objective behind commissioning this study were to:

i. To observe the trends in volume and price of the short-termtransactions of

electricity.

ii. To analyze competition among the market players

iii. To analyze effect of congestion on volume and price of Renewable Energy

Certificates (RECs) transacted through power exchanges.

iv. To disclose/sisseminate all relevant market information.

1.3SCOPE OF WORK

In the succeeding FY 2012-13 Power exchange has successfully overtaken the power

market business, initially the large portion of business was done through Unscheduled

Interchange (UI). But in recent trend it has overtaken by Power Exchange. The study

will help us to understand the entire process as to how the market players have

switched to Power Exchange from UI for short term transactions, and to see the

changing trend in volume and price in short-term transaction of electricity.

16

Page 17: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

1.4ORGANIZATIONAL PROFILE

National Load Dispatch Centre (NLDC) has been constituted as per Ministry of

Power(MOP) notification; New Delhi dated 2nd March 2005 and is the apex body to

ensure integrated operation of the national power system. On 25th February, 2009 the

National Load Dispatch Center (NLDC) was inaugurated. Now these Regional Load

Dispatch Centers (RLDCs) and National Load Dispatch Center (NLDC) is a separate

Organization named POSOCO (Power System Operation Corporation). POSOCO is

fully owned subsidiaries of POWERGRID. There are 5 RLDCs and 33 SLDCs under

NLDC

Mission

A ‘mission critical activity’ for uninterrupted, secure, reliable and

quality power supply in the country

A ‘relentless pursuit’ for optimization of precious power generating

resources under minimization of inherent system losses

A ‘facilitator’ for an efficient electricity market

A ‘vehicle’ far equitable and fair use of the transmission infrastructure

in the country

A ‘vital link’ between the administrators, planners & regulators on one

end and physical system on the other end.

Functions of National Load Dispatch Centre Supervision over Regional Load Dispatch Centers.

17

Page 18: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

Scheduling and dispatching of electricity over the inter regional links in

accordance with grid standards specified by the authority and grid code specified

by Central Commission in coordination with Regional Load Dispatch Centers.

Coordination with Regional Load Dispatch Centers for achieving maximum

economy and efficiency in the operation of National Grid.

Monitoring of operations and grid security of the National Grid.

Supervision and control over the inter-regional links as may be required for

ensuring stability of the power system under its control.

Coordination with Regional Power Committees for regional outage schedule in the

national perspective to ensure optimal utilization of power resources.

Coordination with Regional Load Dispatch Centers for the energy accounting of

inter-regional exchange of power.

Coordination for restoration of synchronous operation of national grid Regional

Load Dispatch Centers.

Coordination for trans-national exchange of power.

Providing Operational feedback for national grid planning to the Authority and

Central Transmission Utility.

Levy and collection of such fee and charges from the generating companies or

licensees involved in the power system, as may be specified by the Central

Commission.

Dissemination of information relating to operation of transmission system in

accordance with direct or regulations issued by Central Government from time to

time.

18

Page 19: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

CHAPTER-2

LETERATURE SURVEY, LEGAL POLICIES AND RESEARCH METHODOLOGY

2.1 LITERATURE SURVEYIn this Project certain concept related to “Real Time Power System Operation are

presented. These concepts are derived from extensive study of the practical power system

operation of Indian Electricity system and various regulations stipulated by Central

Electricity Authority of India.

In the late 1990’s, there was acute shortage in electricity before deregulation has taken

place in India. For most of the time the Indian Regional grid used to operate at

precariously low frequency at 48 Hz, voltage at 300KV (400KV) and around. This led to

severe insecurity in the grid operation. This instability in operation of power system

triggered grid contingencies very frequently, resulting in system separation and grid

disturbances. This insecure and unstable grid operation caused immense financial loss to

the industry and the inefficient operation of the electrical equipment led to increased

electrical losses also. In addition, with multiple blackouts in Indian Power systems,

electrical sector experienced energy crisis along with serious financial problems. During

this period, all electric power utilities throughout India were operated with an

organizational model i.e. vertically integrated model. The electrical utility as a controlling

19

Page 20: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

authority operated model. The Electrical utility as a controlling authority operated the

generation.

2.2 LEGAL POLICIES

2.2.1Real Time Power System Operation and Control

During this period there were wide fluctuations in the frequency and voltage in Indian

power systems due to shortage of power as indicated above. The new tariff mechanism

known as Availability Based Tariff (ABT) was implemented in regional grids so as to

impose the grid discipline. It came into existence for regional grids of India from the year

2003 onwards. The author identified complex issues and variety of critical situations

extending the new tariff mechanism to the inner layers of the state sector and implications

of the power system operations in a Real-time environment under ABT mechanism.

These electric utilities introduced privatization in their sectors to improve efficiency.

During 21st century many electrical utilities and power network companies have been

forced to change their ways of doing business from vertically integrated mechanism to

open market system. The Open Access was introduced in Indian electrical environment

with help of 2003 Electricity ACT.

2.2.2Cooperative Game Theory

The Game theory is divided in to two branches. One is non-cooperative and other is

cooperative Game theory. These two branches mainly differ in modeling interdependence

among the players. The non-cooperative game is generally termed as procedural game

theory whereas the cooperative game theory is termed as combinatorial game theory. The

first one specifies various actions that are available to the players while second one 20

Page 21: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

describes the outcomes that when the players come together in different combinations.

This would indicate an important analytical distinction between them.

The cooperative Game theory (CGT) is widely applied to allocate transmission costs,

wheeling charges and losses to the players of electricity markets. The CGT is also used

for analyzing the economic effect of interconnected power system

.

2.2.3Transmission costs allocation

Two solution concepts of nucleolus and the Shapley value of the cooperative game theory

are introduced in [28] for determining Wheeling charges allocation. In this case, everyone

has to share the incurred costs by the wheeler company in order to accommodate all the

transactions with adequate quality, reliability, and security levels. An approach for

congestion cost allocation in pool electricity markets, based on the Cooperative Game

Theory. The implementation of two well-known solution methods, nucleolus and the

Shapley value to a bilateral transaction electricity market as well as in a pool market is

discussed in this paper. A general game theoretic model for the RTN evaluation is

presented, and the solution procedure is discussed in this paper. The strategic behavior of

market agents in the spot market is modeled according to a Supply Function Equilibrium

approach. The impact of transmission capacity expansion on market participants’

strategic behavior is studied in this paper.

21

Page 22: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

A transmission trunk system is defined as a unique and common system constituted by

electrical lines and substations that are economically efficient and necessary to allow the

development of an electrical market and the supply of demand in the respective electrical

system at a minimum cost and in an efficient manner. The principles of cooperation and

interaction between agents that are the base for the cooperative games theory, the Shapley

value approach is used in [35].

A scheme for the allocation of the transmission network expansion costs among market

participants based on cooperative game theory is presented in [36]. The allocation takes

into account the physical and economic impacts of the new transmission assets in this

paper. The payments made by each participant are calculated using the Shapley value

formula .They are based on the increase in social welfare brought about by the new assets

and the pre-investment surpluses of the players. They influence the different market

participants on the expansion decision. All firms have incentives to support the expansion

through provision of reimbursements.

An open access transmission method is based on the Nash bargaining game for power

flow analysis in which each transaction and its optimal price are determined to optimize

the interests of individual parties of power system.

2.2.4Frequency Control Models

The power system modeling suitable to market structures must ensure controllable

generation for regulating both frequency (by controlling the output of the active power)

and voltage (by controlling the output of reactive power). Several control scenarios based

on robust and optimal approaches have been proposed for the AGC system in deregulated

power systems. A new load flow method considering governor characteristics of

generators andvoltage, frequency characteristics of loads are presented at [93]. The

method of power-flow analysis considering frequency as an additional variable depicts

the actual control phenomena in power systems The load frequency control in a

deregulated electricity market designed for Poolco-based transactions, 22

Page 23: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

bilateraltransactions, and a combination of these two utilizing an integral controller is

presented in [95] and [96]. A method to find the optimum parameter of this type of

controller for a two-area system of identical rating has been proposed and the concept of

“DISCO participation matrix” (DPM) that helps the visualization and implementation of

the contracts is proposed in [96].

2.3 METHODOLOGY

With the broad objective of analyzing the power market scenario pre and post grid failure, various data have been collected from different sources revealing the market operation in FY 2012-13. The main concern is been given to the short term transaction of electricity and hence data have been collected regarding Volume, Price, Percentage growth in revenue, Congestion and Voltage profile. Revealing from this data the conclusion has been drawn regarding the improvement of the grid post Grid Failure and further DEVIATION SETTELMENT MECHANISM has been discussed

23

Page 24: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

24

VOLUME OF SHORT TERM TRANSACTION OF ELECTRICITY

PRICE OF SHORT TERM TRANSACTION OF ELECTRICITY

PERCENTAGE VOLUME Vs PERCENTAGE REVENUE

EFFECT OF CONGESTION ON TRANSACTION OF ELECTRICITY

REQUENCY PEOFILE OVER THE YEAR

Page 25: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

CHAPTER-3

SHORT-TERM POWER MARKET IN INDIA, 2012-13

An analysis of the short-term transactions of electricity in India has been done in this

Report on Short-term Power Market3 for the year 2011-12. Here, “short-term

transactions of electricity” refers to contracts of less than one year period, for electricity

transacted under bilateral transactions through Inter-State Trading Licensees (only inter-

state part) and directly by the Distribution Licensees (also referred as Distribution

Companies or DISCOMs), Power Exchanges (Indian Energy Exchange Ltd (IEX) and

Power Exchange India Ltd (PXIL)), and Unscheduled Interchange (UI). The analysis

includes (i) Yearly/monthly/daily trends in short-term transactions of electricity; (ii) Time

of the day variation in volume and price of electricity transacted through traders and

power exchanges; (iii) Trading margin charged by trading licensees for bilateral

transactions (iv) Analysis of open access consumers on power exchanges; (v) Major

sellers and buyers of electricity through licensed traders and power exchanges; (vi) Effect

of congestion on volume of electricity transacted through power exchanges; and (vii)

Tariffs of long-term sources of power for various distribution companies.

3.1 Yearly Trends in Short-term Transactions of Electricity (2008-09 to 2011-12)

The analysis on yearly trends in short-term transactions includes the electricity transacted

through the following segments:25

Page 26: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

trading licensees (inter-state part only) under bilateral transactions or

“bilateraltrader” segment ,

power exchange segment with transactions in both, Day Ahead and Term

AheadMarkets,

UI segment and

direct transactions of electricity between DISCOMs.

Inter-state trading licensees have been undertaking trading in electricity since 2004and

the power exchanges started operating since 2008. The two power exchanges, IEX and

PXIL started their operations in June 2008 and October 2008 respectively. As of March

2012, there were 41 inter-state trading licensees and twopower exchanges.

3.1.1Total Short-term Transactions of Electricity with respect to Total Electricity Generation

Total volume of short-term transactions of electricity increased from 65.90 billion kWh

(BU) in 2009-10 to 98.94 BU in 2012-13. The annual growth in volume was 24% from

2009-10 to 2010-11 and 16% from 2010-11 to 2011-12 and 5% from 2011-12 to 2012-

13. Total volume of short-term transactions of electricity as percentage of total electricity

generation has increased from 9% in 2009-10 to 11% in 2012-13 (Table-1).

26

Page 27: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

Table 1:Total Volume of Short-term Transactions of Electricity with respect to Total Electricity Generation

Year

Total Volume of

Short-term

Transactions of

Electricity (BU)

Total Electricity

Generation (BU)

Total volume of Short-

term

Transactions of Electricity

as

% of Total Electricity

Generation

2009-10 65.9 764.03 9%

2010-11 81.56 809.45 10%

2011-12 94.51 874.17 11%

2012-13 98.94 907.49 11%

Source: NLDC

The analysis of yearly trends in different segments of short-term transactions of

electricity i.e. electricity transacted through traders and power exchanges, UI, directly

between DISCOMs is dealt in the following sections.

3.1.2 Electricity Transacted through Trading Licensees and Power Exchanges

Table-2, Table-3, Figure-1 & Figure-2 show details of volume of electricity transacted

through trading licensees under bilateral transactions and through power exchanges for

27

Page 28: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

the period from 2008-09 to 2011-12. The volume of electricity transacted through inter-

statetrading licensees and power exchanges increased from 24.69 BU in 2008-09to 59.66

BU in2012-13. The share of electricity transacted through trading licensees and power

exchanges(in volume terms) as a percentage of total short-term transactions of electricity

has shown a moderate rise (from 51.45% in 2009-10 to 60.29% in 2012-13). The growth

in volume forthis segment during the year 2012-13 as compared to 2011-12 was 8.28 BU

in absolute terms and about 16.11 in percentage terms. Majority of this growth has come

from the power exchange segment (7.48 BU). Looking at the individual sub-segment

growth between the years 2011-12 and 2012-13, it is observed that the growth was 2.27%

in bilateral trader segment and the growth was 48.86% in power exchange segment.

Whereas between the year 2010-11 and 2011-12 the growth in bilateral was 29% whereas

in power exchange it was only 15%.

Table 2:Total Volume of Short-term Transactions of Electricity with respect to Total Electricity Generation

Year

Electricity

Transacted

through

Trading

Licensees

(BU)

Electricity

Transacted

through

IEX and

PXIL

(BU)

Total

(BU)

2008-2009 21.92 2.77 24.69

2009-2010 26.72 7.19 33.91

2010-2011 27.7 15.52 43.22

2011-2012 35.84 15.54 51.38

2012-2013 36.64 23.02 59.66

28

Page 29: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

2008-2009 2009-2010 2010-2011 2011-2012 2012-20130

10

20

30

40

50

60

Figure 1 : Total Volume of Electricity Transacted through Trading Licensees and Power Exchange

Total Volume of Electricity Transacted through Trading Li-censees and Power Exchange

Figure 1:Total Volume of Electricity Transacted through Trading Licensees and Power Exchange

Table 3:Electricity Transacted through Trading Licensees and Power Exchanges

Year

Volume of Electricity

Transacted through

Traders and Power

Exchanges (BU)

Total Short-term

Transactions of

Electricity (BU)

Electricity Transacted

through traders and

PXs as % to Total

Volume of Short-term

2009-10 33.91 65.9 51.45%

2010-11 43.22 81.56 53.00%

2011-12 51.38 94.51 54.37%

2012-13 59.66 98.94 60.29%

29

Page 30: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

2009-10 2010-11 2011-12 2012-1346.00%

48.00%

50.00%

52.00%

54.00%

56.00%

58.00%

60.00%

62.00%

Figure-2:Electricity Transacted through traders and PXs as % to Total Volume of Short-term

Electricity Transactedthrough traders andPXs as % to TotalVolume of Short-term

Figure 2:Electricity Transacted through traders and PXs as % to Total Volume of Short-term

The price of electricity transacted through trading licensees and Power Exchanges is

shown in Table-4 and Figure-3. The weighted average price of electricity transacted

through trading licensees and power exchanges declined from `7.29/kWh and `7.49/kWh

respectively in 2008-09 to Rs4.33/kWh and Rs3.57/kWh respectively in 2012-13. It is

thus seen that the price of electricity in the short-term market in the year 2012-13 was on

the lower side as compared to price prevalent in the previous four years. The decreasing

trend in weighted average prices has had its effect on the market sizeof this segment in

monetary terms (Table-5). Thus, although in physical terms (BU terms) the size of this

30

Page 31: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

segment increased only by about 16 % in the year 2012-13 compared to 19% increase in

2011-12, But in monetary terms the growth has been about 17% (or about Rs3546crore),

which was only 10% (or about Rs1875crore) in 2011-12 . In fact, the bilateral trader sub-

segment, though registering a low growth of about 2.22 % in physical terms as compared

to 29% in 2011-12, also registered low growthin monetary terms of only about 2% (or

about Rs881crore) as compared to13 % (or about `1711 crore) in 2011-12.The power

exchange segment, though registered high growth of 48%in physical terms as compared

to growth of 0.15% in 2011-12, also registered high growth of about 48% in monetary

terms (or about Rs2665crore) as compared to growth of 3% (or about Rs164crore) in

2011-12.

Table 4:Electricity Transacted through traders and PXs as % to Total Volume of Short-term

Year

Price of Electricity transactedthrough Trading Licensees(`/kWh)

Price of Electricity transactedthrough Power Exchanges(DAM+TAM) (`/kWh)

2008-09 7.29 7.49

2009-10 5.26 4.96

2010-11 4.79 3.47

2011-12 4.18 3.57

2012-13 4.33 3.57

31

Page 32: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

2008-09 2009-10 2010-11 2011-12 2012-130

1

2

3

4

5

6

7

8

Price of Electricity transactedthrough Trading Licensees(`/kWh)

Price of Electricity transactedthrough Power Exchanges(DAM+TAM) (`/kWh)

Figure-3:

Figure 3:Price of Electricity transacted through Trading Licensees and Power Exchange

32

Page 33: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

Table 5:Electricity Transacted through traders and PXs as % to Total Volume of Short-term

Year

ElectricityTransacted throughTradingLicensees(BU)

Price ofElectricityTransactedthroughTradingLicensees(Rs/kWh)

Size ofbilateraltraderMarketin `Crore

ElectricityTransactedthroughPowerExchanges(BU)

Price ofElectricityTransactedthroughPowerExchanges(Rs/kWh)

Size ofPowerExchangeMarketin (Rs Crore)

Total Sizeof thebilateraltrader +PowerExchangeMarket (RsCrore)

2009-10 26.62 5.26 14055 7.19 4.96 3563 17617

2010-11 27.70 4.79 13268 15.52 3.47 5389 18657

2011-12 35.84 4.18 14979 15.54 3.57 5553 20532

2012-13 36.63 4.33 15860 23.02 3.57 8218 24078

3.1.3 Electricity Transacted through UI

The volume and price of electricity transacted through UI is shown in Table-6 andFigure-

4. The volume and price of electricity transacted through UI in 2008-09 represents the

period from August 2008 to March 2009. It can be observed from Table that the volume

of electricity transacted through UI has increased from 25.81 BU in 2009-10 to 27.76 BU

in 2011-12 but again decreased to 24.75 in 2012-13, and the volume of UI as percentage

of total short-term volume has declined to a level of 25% in the year 2012-13 as

compared to 39% in 2009-10. It can also be observed from the table that the average

price of UI (New Grid and SR Grid) declined from Rs4.62/kWh in 2009-10 to

Rs3.51/kWh in 2012-13.

33

Page 34: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

Table 6:Volume and Price of Electricity Transacted through UI

YearVolume of UI(BU)

Total Volume ofShort-term (BU)

Volume of UI as %of total volume ofShort-term

Price of UI(`/kWh)

2008-09 14.39 35.27 41% 6.7

2009-10 25.81 65.9 39% 4.62

2010-11 28.08 81.56 34% 3.91

2011-12 27.76 94.51 29% 4.09

2012-13 24.75 98.94 25% 3.51

2008-09 2009-10 2010-11 2011-12 2012-130

5

10

15

20

25

30

Figure-4:Volume of electricity transacted through UI

Volume of electricity transacted through UI

Figure 4:Volume of electricity transacted through UI

34

Page 35: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

2008-09 2009-10 2010-11 2011-12 2012-130

1

2

3

4

5

6

7

8

Figure-5:Price of electricity transacted through UI

Price of electricity transacted through UI

Figure 5:Price of electricity transacted through UI

3.1.4 Electricity Transacted Directly Between DISCOMs

The volume of electricity transacted directly between DISCOMs is shown in Table-7and

Figure-5. It can be observed from the table that the volume of electricity transacted

directly between DISCOMs increased significantly from 6.19 BU in 2009-10 to 15.37

BU in 2011-12 but again decreased to 14.51BU in 2012-13. It can also be observed that,

the share of electricity transacted directly between DISCOMs as percentage to total

volume of short-term transaction of electricity had also increased from 9% to 16%

between 2009-10 and 2011-12 but again decreased to 15% in 2012-13.

35

Page 36: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

Table 7: Volume of Electricity Transacted Directly between DISCOMs

Year

Volume of ElectricityTransacted Directlybetween DISCOMs(BU)

Total Volume ofShort-term (BU)

Volume of BilateralDirect as % of totalvolume of Short-term

2008-09 3.31 35.27 9%2009-10 6.19 65.9 9%2010-11 10.25 81.56 13%2011-12 15.37 94.51 16%2012-13 14.51 98.94 15%

2008-09 2009-10 2010-11 2011-12 2012-1302468

10121416

Figure-6:Volume of Electricity Transacted Directly between DISCOMs

(BU)

Volume of ElectricityTransacted Directlybetween DISCOMs(BU)

Figure 6:Volume of Electricity Transacted Directly between DISCOMs

36

Page 37: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

3.2Monthly Trends in Short-term Transactions of Electricity (April 2012-March 2013)

During 2011-12, the share of the total short-term transactions in volume terms,including

UI as a percentage of total electricity generation in the country was about 11 percent

(Figure-7 and Table-8)

4% 2% 2%3%

89%

Figure-7: Share of Different Segments in Total Electricity

Generation in 2012-13Bilateral through TradersBilateral between DIDCOMSPower Exchange transactionUI TRANSACTIONSLONG TERM TRANSACTION

Figure 7:Share of Different Segments in Total Electricity

The share of different segments within the total short-term transaction for the year2012-13 has been shown in the Figure-8 below.

37

Page 38: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

37%

15%

23%

25%

Figure-8: Share of Different Segments in Short Term Transactions

in 2012-13

Bilateral through TradersBilateral between DIDCOMSPower Exchange transactionUI TRANSACTIONS

Figure 8:Share of Different Segments in Short Term Transactions

3.2.1 Volume of Short-term Transactions of Electricity

During the FY2012-13, total electricity generation excluding generation from renewable

and captive power plants in India was 907490.43 MUs (Table-8). Of the total electricity

generation, 98940.45MUs (10.90%) were transacted through short-term, comprising of

51156.9MUs (5.63%) through Bilateral (through traders and term ahead contracts on

Power Exchanges and directly between distribution companies), followed by

23024.42MUs (2.53%) through day ahead collective transactions on Power Exchanges

(IEX and PXIL) and 24759.13MUs (2.72%) through UI (Table-8 & Figure-8). Of the

total short-term transactions, Bilateral constitute 51.70% (37.03% through traders and

term-ahead contracts on Power Exchanges and 14.67% directly between distribution

companies) followed by 23.27% through day ahead collective transactions on

38

Page 39: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

Power Exchanges and 25.02% through UI (Table-8& Figure-8). Daily volume of short-

term transactions is shown in Table-8 & Figure-8. The percentage share of electricity

traded by each trading licensee in the total volume of electricity traded by all trading

licensees is provided. The trading licensees undertake electricity transactions through

bilateral and through power exchanges. Here, the volume of electricity transacted by the

trading licensees includes bilateral transactions and the transactions undertaken through

power exchanges. There were 42 trading licensees as on 31.03.2013, of which only 20

have engaged in trading during March 2013. Top 5 trading licensees had a share of

79.79% in the total volume traded by all the licensees.

Herfindahl-Hirschman Index (HHI) has been used for measuring the competition

among the trading licensees. Increase in the HHI generally indicates a decrease in

competition and an increase of market power, whereas decrease indicates the opposite.

The HHI above 0.15 indicates a moderate concentration of market power. The HHI

computed for volume of electricity traded by trading licensees (inter-state & intra-state)

was 0.1583 for the month of March 2013, which indicates that there was moderate

concentration of market power. The volume of electricity transacted through IEX and

PXIL in the day ahead market was 2259.65MUs and 64.70MUs respectively. The volume

of total Buy bids and Sale bids was 3975.76MUs and 3721.00MUs respectively in IEX

and 246.26MUs and 206.68MUs respectively in PXIL. The gap between the volume of

buy bids and sale bids placed through power exchanges shows that there was more

demand in IEX (1.07 times) and PXIL (1.19 times) when compared with the supply

offered through these exchanges. The volume of electricity transacted through IEX and

PXIL in the term-ahead market was 6.80MUs and 0.30MUs respectively.

39

Page 40: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

APRIL'12

MAY'12

JUN'12

JULY'12

AUG'12

SEP'12

OCT'12

NOV'12

DEC'12

JAN'13

FEB'13

MAR'13

0

1000

2000

3000

4000

5000

6000

7000

Figure-9:Total volume of short term transaction of Electricity

Total Bilateral transactionPower Exchange transaction(DAM+TAMUItransactions

Month

Volu

me

in M

Us

Figure 9:Total volume of short term transaction of Electricity

40

Page 41: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

Table 8:Total volume of short term transaction of Electricity

PERIOD

Bilateral through Traders

Bilateral between DIDCOMS

Total Bilateral transaction

Power Exchange transactio

n (DAM+TA

M)

UI TRANSACTI

ONS

Total short term

transactions

Total electricitygener

ated

APRIL'12 2384.7 1011 3395.69 1337 2576 7309 74725

MAY'12 2416.6 1068.3 3484.82 1478 2737 7700 78786

JUN'12 2946.6 1148.4 4095.05 1629 3638 9362 76306

JULY'12 3766.4 1737.7 5504.12 1572 2900 9977 76091

AUG'12 3855 1910.7 5765.7 1861 2076 9703 74263

SEP'12 3072.2 1655.6 4727.76 1910 1662 8299 73075

OCT'12 2433.5 901.7 3335.15 2301 1542 7178 78311

NOV'12 3205.4 931.5 4136.86 2186 1475 7797 72602

DEC'12 3369.5 1086.3 4455.79 2315 1480 8251 76496

JAN'13 3547.3 1192.8 4740.11 2099 1503 8341 78404

FEB'13 2680.6 949.9 3630.45 2012 1534 7177 68459

MAR'13 2960.6 924.81 3885.4 2324 1637 7847 79974

Total 36638 14519 51156.9 23024 24759 98940 9E+05% share

4.0373 1.5999 5.637183 2.537 2.728 10.9 100in totalgeneration% share

37.031 14.674 51.70474 23.27 25.02 100 inShorttermVolume

As we can see from the above table as well as above graph the transaction through

bilateral has kept varying within a defined limit and always been on the higher side.

41

Page 42: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

Whereas the transaction through power exchanges has started at very low volume of 1337

MUs in the starting of this fiscal year which nearly kept on increasing with the preceding

months and crossed the UI consumption in month of August and ended in month of

march at 2324 MU.

On the other side the total volume of electricity transacted through UI started at higher

volume of 2576 MU which nearly kept on increasing upto month of july in which we

faced GRID FAILURE. Looking towards undue advantage of UI low rates the UI rates

were subsequently increased and thus the buyers started switching to power exchange

rather than UI to buy electricity in short term market.

Hence total volume of electricity transacted through UI decreased after month of july

which further kept on decreasing throughout the year and finally ended at the volume of

1637 MU at month of March’13

The volume of short-term transaction of electricity as percentage of total electricity

generated varied between 9.16% and 13.11% during the period

42

Page 43: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

Table 9:Volume of Short-term Transactions of Electricity as % of Total Electricity

Period

Short-term transactions as % of total electricitygeneration

APRIL'12 9.78%MAY'12 9.77%JUN'12 12.26%JULY'12 13.11%AUG'12 13.06%SEP'12 11.35%OCT'12 9.16%NOV'12 10.74%DEC'12 10.78%JAN'13 10.63%FEB'13 10.48%MAR'13 9.81%

There were 42 trading licensees as on 31.03.2013, of which only 20 have engaged in

trading during March 2013. Top 5 trading licensees had a share of 79.79% in the total

volume traded by all the licensees.

Herfindahl-Hirschman Index (HHI) has been used for measuring the competition

among the trading licensees. Increase in the HHI generally indicates a decrease in

competition and an increase of market power, whereas decrease indicates the opposite.

The HHI above 0.15 indicates a moderate concentration of market power. The HHI

computed for volume of electricity traded by trading licensees (inter-state & intra-state)

was 0.1583 for the month of March 2013, which indicates that there was moderate

43

Page 44: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

Table 10:PERCENTAGE SHARE OF ELECTRICITY TRANSACTED BY TRADING LICENSEES IN 2012-13

Sr.No

Name of the Trading Licensee

% Share in totalVolume transactedby TradingLicensees

Herfindahl-HirschmanIndex

1 PTC India Ltd 28.86% 0.0833

2Tata Power Trading Company(P) Ltd. 15.98% 0.0255

3JSW Power Trading Company Ltd. 15.69% 0.0246

4NTPC Vidyut Nigam Ltd. 10.60% 0.0112

5Reliance Energy Trading (P) Ltd. 8.66% 0.0075

6 Adani Enterprise Ltd. 5.97% 0.0036

7

Knowledge Infrastructure System (P) Ltd 3.27% 0.0011

8Mittal Processor (P) Ltd. 1.97% 0.0004

9 Shree ement td. 1.86% 0.0003

10GMR Energy Trading Ltd. 1.84% 0.0003

44

Page 45: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

11Instinct Infra & Power Ltd. 1.07% 0.0001

12National Energy Trading & Services Ltd. 0.96% 0.0001

13RPG Power Trading Company Ltd. 0.89% 0.0001

14Jaiprakash Associates Ltd. 0.75% 0.0001

15 Manikaran Power Ltd. 0.58% 0

16

Arunachal Pradesh Power Corporative Ltd. 0.33% 0

17Indrajit Power Technology (P) Ltd. 0.32% 0

18Pune Power Development Pvt Ltd. 0.29% 0

19Customized Energy Solution India Pvt Ltd. 0.08% 0

20

Essar Electric Power Development Corp. Ltd. 0.04% 0

TOTAL 100.00%

45

Page 46: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

29%

16%

16%

11%

9%

20%

Figure-10:PERCENTAGE SHARE OF ELECTRIC-ITY TRANSACTED BY TRADING LICENSEES IN

2012-13

PTC India LtdTata Power Trading Company(P) Ltd.JSW Power Trading Company Ltd.NTPC Vidyut Nigam Ltd.Reliance Energy Trading (P) Ltd.OTHERS

Figure 10:PERCENTAGE SHARE OF ELECTRICITY TRANSACTED BY TRADING LICENSEES IN 2012-13

Level of competition among the trading licensees (HHI based on volume of

tradeundertaken by the licensees) is shown in Figure-10 for the period 2004-05 to 2011-

12.

Number of inter-state trading licensees, who were undertaking trading bilaterally or

through power exchanges, increased from 4 in 2004-05 to 17 in 2011-12. It can be

observed from the figure that there is an inverse relationship between number of trading

licensees and the HHI.

The concentration of market power declined from high concentration (HHI of 0.5512) in

2004-05 to moderate concentration (HHI of 0.1732) in 2011-12. The competition among

the trading licensees resulted in increase in volume and decrease in prices in the short-

term bilateral market (Table-5).

46

Page 47: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

3.2.2 Price of Short-term Transactions of Electricity

The monthly trends in price of short-term transactions of electricity are shown in

Table-11 and Figure-10 & 11. The price analysis is mainly based on the average price of

UI and the weighted average price of other short-term transactions of electricity. The

price of bilateral trader transactions represents the price of electricity transacted through

trading licensees. The trends in price of electricity transacted through trading licensees

(bilateral trader transactions) were studied separately for total transactions as well as for

the transactions undertaken Round the Clock (RTC), during Peak, and during Off-peak

periods

Price of electricity transacted through Traders: Weighted average sale price has

been computed for the electricity transacted through traders and it was Rs4.335/kWh.

Weighted average sale price was also computed for the transactions during Round the

Clock (RTC), Peak, and Off-Peak periods separately, and the sale prices were

Rs4.305/kWh, Rs5.12/kWh and Rs4.655/kWh respectively. Minimum and Maximum

sale prices were Rs2.44/kWh and Rs7.07/kWh respectively.

Price of electricity transacted Through Power Exchanges:Minimum, Maximum

and Weighted Average Prices have been computed for the electricity transacted through

IEX and PXIL separately. The Minimum, Maximum and Weighted Average prices were

Rs0.35/kWh, Rs17.00/kWh and Rs3.67/kWh respectively in IEXand Rs1.31/kWh,

Rs7.50/kWh and Rs3.47/kWh respectively in PXIL.

The price of electricity transacted through IEX and PXIL in the term-ahead market

was Rs3.67/kWh and Rs3.47/kWh respectively.

47

Page 48: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

Price of electricity transacted Through UI:All-India UI price has beencomputed

for NEW Grid and SR Grid separately. The average UI price was Rs2.873/kWh in

the NEW Grid and Rs4.16/kWh in the SR Grid. Minimum and Maximum UI

prices were Rs0.00/kWh and Rs8.21/kWh respectively in the New Grid, and

Rs0.00/kWh and Rs10.80/kWhrespectively in the SR Grid.

The prices of electricity transacted through trading licensees, power exchanges

and UI and their comparison is shown in Table-11, Figure-10 & 11.

APRIL'12

MAY'12JUN'12

JULY'12

AUG'12SEP

'12

OCT'12

NOV'12

DEC'12

JAN'13FEB

'13

MAR'130

1

2

3

4

5

6

Figure-11:Comparison of price of bilateral, Power Exchange and UI Transactions in 2012-13

Price of Bilateral Transactions through tradersPrice of Power Exchange Trans-actions (TAM+DAM)Average Price of UI Transactions (NEW Grid+SR Grid)

Month

(Rs/

KWh)

Figure 11:Comparison of price of bilateral, Power Exchange and UI Transactions in 2012-13

48

Page 49: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

Table 11:Price of Short-term Transactions of Electricity (Rs/kWh), 2012-13

Period

Bilateral through TradersPower

Exchange UI

RTC Peak Offpeak Total IEX PXILNEWGrid

SRGrid

APRIL'12 4.35 5.78 4.95 4.4 3.19 4.71 2.81 5.16MAY'12 4.26 6.13 4.79 4.3 3.6 3.89 4.26 4.92JUN'12 4.11 4.91 4.17 4.11 4.11 4.1 5.55 5.29JULY'12 4.02 5.81 4.69 4.03 4.51 4.54 6.13 5.09AUG'12 4.22 4.89 4.3 4.22 3.89 3.53 2.16 4.12SEP'12 4.37 5.69 4.26 4.37 2.98 2.34 1.45 3.69OCT'12 4.43 5.73 4.85 4.41 4.03 3.76 2.29 3.91NOV'12 4.39 4.35 4.58 4.43 3.62 2.89 1.87 3.3DEC'12 4.25 4.77 4.67 4.39 3.9 3.08 2.33 3.33JAN'13 4.38 4.34 5.09 4.42 3.65 3.66 2.31 2.94FEB'13 4.42 4.48 4.89 4.46 2.9 2.42 1.53 3.83MAR'13 4.46 4.49 4.63 4.48 3.68 2.76 1.79 4.33

It can be observed from the above figure that the price of electricity transactedthrough

trading licensees was relatively low when compared with the price of electricity

transacted through power exchanges and UI during the period April to July in 2012,

which gradually increased from month of August to March’13 and was constantly on the

higher side as compared to UI and Power Exchange.

The price of UI transactions were constantly increasing and was relatively higher as

compared to Power Exchange and trading licensees until the month of July’12 after

which there was a sharp step fall in UI prices and remained lower than Power Exchanges

and Trading licensees.

49

Page 50: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

The price of electricity transacted through Power Exchange generally remained between

the prices of UI transactions and Trading licensees, though there were many up and

downs in the price of electricity transacted through Power Exchange throughout the year.

The trends in price of electricity transacted by trading licensees during RTC, Peak and

Off-peak periods are shown in Figure-11. It can be observed from the figure that the price

of electricity during peak period is high in all the months when compared with the price

during RTC and off peak periods until month of Oct’12 after which it decreased and was

approximately equal to RTC and off peak period throughout the year.

50

Page 51: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

APRIL'12

MAY'12

JUN'12

JULY'12

AUG'12SEP

'12

OCT'12

NOV'12

DEC'12

JAN'13FEB

'13

MAR'130

1

2

3

4

5

6

7

Figure-12: Price of Electricity Transacted through Traders during

Round the Clock, Peak and Off Peak Periods

RTCPeakOffpeak

Price

(Rs/

KWh)

Figure 12:Price of Electricity Transacted through Traders during

3.3 Effect of Congestion on Volume of Electricity Transacted through Power ExchangesThe volume of electricity transacted/sold through power exchange is sometimes

constrained due to transmission congestion. The details of congestion in both power

exchanges are shown in Table.

During 2012-13, in IEX, the unconstrained cleared volume and the actual volume

transacted were 26.14 billion KWh and 22.34 billion kWh respectively. This indicates

that the actual transacted volume could have been 17% higher if there was no congestion

in the system. During the same year, in PXIL, the unconstrained cleared volume and the

51

Page 52: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

actual volume transacted were 1.5 billion kWh and 0.678 billion kWh respectively. This

indicates that the actual transacted volume could have been about 125% higher, if there

was no congestion in the system.

Congestion, consequent market splitting, and the resultant difference in market

prices in different regions give rise to congestion charges. The congestion charges are

being deposited in the Power System Development Fund, which was created pursuant to

CEREC (Power System Development Fund) Regulations, 2010. Congestion in Power

exchanges, besides affecting the volume, also resulted in formation of the fund.

Table 12:Price of Electricity Transacted through Traders during

Details of Congestion APRIL MAY JUNE

IEX PXIL IEX PXIL IEX PXIL

A Unconstrained Cleared Volume (MUs)1586.9

6182.9

51445.2

1 124.291609.6

9 124.14

BActual Cleared Volume and hence scheduled (MUs)

1283.86 53.32

1388.39 89.69

1535.34 94.03

C

Volume of electricity that could not be cleared and hencenot scheduled because of congestion (MUs) (A-B) 303.1

129.63 56.82 34.6 74.35 30.11

D

Volume of electricity that could not be cleared as % toActual Cleared Volume 24% 243% 4.09% 38.58% 4.84% 32.02%

E

Percentage of the time congestion occurred during themonth (Number of hours congestion occurred/Totalnumber of hours in the month) 100% 100% 99.97%

100.00% 76.67% 80.42%

52

Page 53: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

Table-12:DETAILS OF CONGESTION IN POWER EXCHANGES, 2012-13 Details of Congestion JULY AUGUST SEPTEMBER

IEX PXIL IEX PXIL IEX PXIL

A Unconstrained Cleared Volume (MUs)1596.2

8 79.292001.3

4 87.332217.5

8 84.31

BActual Cleared Volume and hence scheduled (MUs)

1519.32 52.93

1821.02 39.93

1878.69 30.92

C

Volume of electricity that could not be cleared and hencenot scheduled because of congestion (MUs) (A-B) 76.96 26.36 180.32 47.4 338.89 53.4

D

Volume of electricity that could not be cleared as % toActual Cleared Volume 5.07% 49.80% 9.90%

118.72% 18.04% 172.71%

Table-12:DETAILS OF CONGESTION IN POWER EXCHANGES, 2012-13 Details of Congestion OCTOBER NOVEMEBER DECEMBER

IEX PXIL IEX PXIL IEX PXIL

A Unconstrained Cleared Volume (MUs)2452.0

7 53.19 2479.54 149.172633.3

6 185

BActual Cleared Volume and hence scheduled (MUs) 2277.6 23.32 2119.01 67.12

2242.51 72.1

C

Volume of electricity that could not be cleared and hencenot scheduled because of congestion (MUs) (A-B) 174.47 29.87 360.53 82.05 390.85 112.9

53

Page 54: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

D

Volume of electricity that could not be cleared as % toActual Cleared Volume 7.66%

128.08% 17.01%

122.25% 17.43% 156.59%

Table-12:DETAILS OF CONGESTION IN POWER EXCHANGES, 2012-13 Details of Congestion JANUARY FEB MARCH

IEX PXIL IEX PXIL IEX PXILA Unconstrained Cleared Volume (MUs) 2587.01 144.3 2513.75 147.5 3020.39 167.64

BActual Cleared Volume and hence scheduled (MUs) 2045.4 53.18 1975.42 36.97 2259.65 64.7

C

Volume of electricity that could not be cleared and hencenot scheduled because of congestion (MUs) (A-B) 541.61 91.12 538.33 110.53 760.74 102.94

D

Volume of electricity that could not be cleared as % toActual Cleared Volume 20.94% 63.14% 21.42% 74.93% 25.19% 61.41%

Table-12:DETAILS OF CONGESTION IN POWER EXCHANGE,2012-13

Details of Congestion AVERAGE

IEX PXIL

A Unconstrained Cleared Volume (MUs) 26143.18 1529.11

54

Page 55: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

B Actual Cleared Volume and hence scheduled (MUs) 22346.21 678.21

CVolume of electricity that could not be cleared and hencenot scheduled because of congestion (MUs) (A-B) 3796.97 850.9

DVolume of electricity that could not be cleared as % toActual Cleared Volume 17% 125%

APRILJUNE

AUGUST

OCTOBER

DECEM

BER

FEBRUARY

0100200300400500600700800

Figure-13:Details of congestion in Power Exchange

Volume of electricity that could not be cleared and hencenot scheduled because of congestion (MUs) IEXVolume of electricity that could not be cleared and hencenot scheduled because of congestion (MUs) PXIL

Volu

me

in M

U's

Figure 13:Details of congestion in Power Exchange

3.3.1Congestion management: Transmission congestion occurs when there is

insufficient transmission capacity to simultaneously accommodate all requests for

transmission service within a region. Where there is no congestion, there shall be no

restriction of access to the interconnection and no specific procedure for access to

transmission service.

55

Page 56: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

Congestion can have a temporary or structural cause. Temporary bottlenecks occur

relatively rarely and may be the result of outages for maintenance work, technical faults

or particular market conditions. Structural bottlenecks are a result of the level of

expansion of the grid and the localisation of generation and consumption within the grid.

Structural bottlenecks tend to occur over longer periods of time or at regular intervals. It

is often difficult to distinguish between the two types of congestion. It is, however,

important to determine whether one is faced with temporary or structural congestion as to

the best method of dealing with.

3.3.2PRINCIPLES OF CONGESTION MANAGEMENT: In principle, congestion

can only be relieved physicallyby reducing generation or increasing consumption on the

surplus side of the bottleneck and,conversely, by increasing generation or reducing

consumption on the shortfall side. Dependingon which time phase one is in, different

methods can be used for managing congestion. Thesemethods should be based on the

following principles:

1. Economic efficiency and promotion of competition,

2. Maximizing of the amount of capacity available and the use made of it,

3. Transparency to network users on a non‐discriminatory basis,

4. Efficient System Operation

3.3.3CONGESTION MANAGEMENT METHODS: Congestion is relatively prevalent

on interconnectionsbecause they were not built to facilitate the current large electricity

flows between countries.

Originally, their main purpose was to allow exchanges between regions for the purpose of

system stability. There are a variety of arrangements for congestion trade in use

worldwide:

Non Market based methods

56

Page 57: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

• Access limitation

• Priority List

• Pro rata rationing

• Counter trading and redispatching

Access Limitation: This congestion management tool which rations access

totransmission capacity applies to DC interconnections with ownership that differs

fromlinked networks. A few users may retain benefits from inter regional trade.

Priority List: Market players receive capacity in priority order until the ATC is

fullyallocated. The priority criteria could be the chronological order and historic use

ofcapacity

The method favors incumbents and long‐term trade because such contracts always have

priority over recent ones. Consequently, it leaves little opportunity for the short‐term

market. Allocation of a deliberately chosen fraction of the ATC for short‐term contracts

can be an Improvement.

Pro rata rationing: This mechanism allocates capacity in proportion to requests if

theyexceed the announced ATC. The method is non‐discriminatory, transparent and easy

toimplement compared to other mechanisms. However, it may very likely

induceunwanted behavior such as gaming. Market players anticipating congestion

mayoverestimate their capacity needs and purchase accordingly. Anti‐gaming measures

suchas the obligation to use the designated capacity appear to be a necessity if the method

isto be of any use.

Counter Trading and re-dispatching: In this method the TSO plays most important

rolein managing the congestion. This results in a planned electricity flow across

thecongested line that exceeds its capacity. They need to enter the market to buy

generationon one side and cancel generation on the other side.57

Page 58: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

Market based methods

• Explicit Auction

• Implicit Auction

Explicit Auctioning: In an explicit auction, the TSO determines ex ante the ATC

subjectto security analysis accepts bids from potential buyers and allocates the capacity to

themarket players that most value it. There is a distinction between the trading

oftransmission capacity and energy because they are traded separately. Each market

playerbids for the ATC it wants to reserve. The bids are sorted, with the highest bids first,

untilthe ATC is completely utilized.

The most common designs of explicit auctions are:

1. Uniform clearing price design, where all market players allocated transmission

capacity pays the clearing price or, alternatively, the pay‐as‐bid price design where all

players allocated capacity pay the price they have bid.

2. Different products with varying frequency (year, month or day).

3. Often a joint coordinated mechanism between the PX involved.

Implicit Auctioning: The implicit auction considers energy bids in each organized

market area.Based on submitted bids, demand and supply in market areas are matched.

Arbitrageopportunities arise because of area price differences. As long as there is

sufficient transmissioncapacity, demand and supply are matched and prices equalize (to

the system price). However,when congestion occurs, the area prices differ and markets

split. Each area has its own price:areas downstream of a congested interconnection will

have a higher area price, while areasupstream will have a lower area price. In the process,

energy and transmission capacity aretraded simultaneously. Interested parties bid across a

congested interconnect or into a powerpool. The market operator adds a surcharge to each

58

Page 59: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

bid that uses the interconnection. As a result,some of these bids are priced out of the

market. The market operator sets the level of thissurcharge precisely so that just as many

bids from across the interconnection are accepted as itscapacity allows.

1. Market Couplingwhere different power exchanges operate in each market area and a

(shared) coupling system manages the capacity between them; and

2. Market Splitting, where a single power exchange operates across the connected

3.4 FREQUENCY PROFILE

There were great deviation from frequency in last FY 2011-12, maximum number of

times the frequency remained below 49Hz and also above 50Hz due to this variation in

frequency the grid was greatly disturbed and was one of the cause for the Grid Failure

faced by most of the part of India for consecutive 2 days.

For further improvement of the grid Ministry Of Power has further narrowed the

frequency band width i.e between 49.95Hz to 50.05Hz and also increased the UI rates

looking towards this there was improvement in frequency profile in FY2012-13 as shown

in (Table-13)

59

Page 60: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

Table 13:Frequency profile in india in 2012-13

MONTHFRQUENCY PROFILE %Time

<49.5 49.5-50.2 >50.2

April'12 2.38% 93.68% 3.94%

May'12 10.82% 87.82% 1.36%

June'12 19.95% 78.66% 1.39%

July'12 24.38% 73.59% 2.03%

Aug'12 1.57% 89.72% 8.71%

Sept'12 3.22% 84.09% 12.69%Oct'12 3.33% 90.39% 6.28%

Nov'12 1.79% 85.83% 12.38%

Dec'12 4.39 84.1 11.51

Jan'13 4.63 80.95 14.42

Feb'13 1.31 78.76 19.93

March'13 1.03 87.43 11.54

60

Page 61: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

April'12

May'12

June'12July'

12

Aug'12

Sept'1

2Oct'1

2

Nov'12Dec'

12Jan

'13Feb

'13

March'13

0

10

20

30

40

50

60

70

80

90

100

Figure-14:Frequency profile in India in 2012-13

FRQUENCY PROFILE %Time <49.5FRQUENCY PROFILE %Time 49.5-50.2FRQUENCY PROFILE %Time >50.2

%ag

e of

tim

e

Figure 14:Frequency profile in India in 2012-13

As we can see from the graph for most of the time the frequency remained between 49.5

and 50.2, which remained fluctuating between 73% to 95% of time, hence this was a

good sign for the stability of the grid.

Initially in the starting of the year the frequency profile below 49.5 Hz gradually kept on

increasing and increased from 0% to 25% till month of July after which it gradually

decreased and remained low throughout the year.

The frequency profile above 50.2Hz was very less percentage of time. Hence looking

forward to frequency profile throughout the year it can be concluded that for maximum

number of times the frequency was between the prescribed limit hence this was a healthy

sign of stability of the grid.

61

Page 62: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

CHAPTER-4

INITIATIVES TAKEN TOWARDS FURTHER IMPROVEMENT OF GRID

4.1 DEVIATION SETTELMENT MECHANISM

4.1.1. ObjectiveThe objective of these regulations is to maintain grid security and grid discipline

as envisaged under the Grid Code through the commercial mechanism of Deviation

Settlement by controlling the users of the grid in scheduling, dispatch, drawal and

injection of electricity.

4.1.2. ScopeThese regulations shall be applicable to –

(i) The generating stations and the beneficiaries, and

(ii) Sellers and buyers involved in the transaction facilitated through short-term open

access or medium-term open access or long-term access in inter-State transmission of

electricity.

4.1.3. Charges for the Deviations:(1) The charges for the Deviations for all the time-blocks shall be payable for over drawal

by the buyer or the beneficiary and under-injection by the generating station or the seller

62

Page 63: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

and receivable for under-drawal by the buyer or the beneficiary and over-injection by the

generating station or the seller and shall be worked out on the average frequency of a

time-block at the rates specified below as per the methodology specified in clause

(2) Of this regulation:

Average Frequency of the time block(Hz) Charges for Deviation Table 14:Charges for Deviation

Average Frequency of the time block(Hz)

Charges for Deviation

Below Not Below Paise/KWh 50.05 050.05 50.04 35.6050.04 50.03 71.2050.03 50.02 106.8050.02 50.01 142.4050.01 50.00 178.0050.00 49.99 333.4049.99 49.98 488.80

(Each 0.01 Hz step is equivalent to 35.60Paise/kWh in the 50.05-50.00 Hz frequency

range, 155.40Paise/kWh in the below 50 Hz to 49.95 Hz frequency range) Provided that

the charges for the Deviation for the generating stations using coal or lignite or gas

supplied under Administered Price Mechanism (APM) as fuel, when actual generation is

higher or lower than the scheduled generation, shall not exceed the Cap Rate of

333.40Paise/kWh as per the methodology specified in clause (3) of this regulation:

Provided that the charges for the Deviation for the under drawls by the buyer and the

over-injection by the seller shall not exceed the Cap Rate of 333.40Paise/kWh as per the

methodology specified in clause (3) of this regulation:

63

Page 64: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

Provided also that the charges for the Deviation for the under drawls by the buyer or the

beneficiaries in a time block in excess of 12% of the schedule or 150 MW whichever is

less and in excess of 3% of the schedule over the day, shall be zero.

Provided also that the charges for the Deviation for the over-injection by the seller in a

time block in excess of 12% of the schedule or 150 MW whichever is less and in excess

of 3% of the schedule over a day shall be zero except in case of injection of infirm power

which shall be governed by the clause (6) of this Regulation.

Provided also that the Charges for the Deviation for the under injection by the generating

station “below 50.0 Hz” shall be the energy charge of the previous month if energy

charge is higher than the charges for the Deviation corresponding to the grid frequency of

the time block. In case of gas based generating stations the energy charge shall be

considered for this purpose starting from the highest to lower for the respective fuels

corresponding to the capacity scheduled on each fuel.

Note: Each generating station shall furnish the energy charges for the previous month to

the respective Regional Power Committee (RPC) each month.

(2) The Charge for Deviation shall be determined in accordance with the following

methodology:

(a) The Charge for Deviation shall be zero at grid frequency of 50.05 Hz and above.

(b) The Charge for Deviation corresponding to grid frequency interval of ‘below 50.01

Hz and not below 50.0 Hz’ shall be based on the median value of the average energy

charge of coal/lignite based generating stations for any six months period preferably from

July to December of previous year or from Jan to June for the year or any other six month

period if deemed necessary and suitably adjusted upward to decide on the Deviation price

vector.

64

Page 65: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

(c) The Deviation Price Vector shall accordingly, be in steps for a frequency interval of

0.01 Hz between 50.05 Hz and ‘below 50.01 Hz and not below 50.0 Hz’.

(d) The Deviation Price Vector shall accordingly, be in steps for a frequency interval of

0.01 Hz between grid frequency interval of ‘below 50.01 Hz and not below 50.0 Hz’ and

‘below 49.95 Hz.

(e) The Charge for Deviation at grid frequency "below 49.95 Hz" shall be based on the

highest of the average energy charges of generating stations for any six months period

preferably from July to December of previous year or from Jan to June for the year or any

other six month period if deemed necessary and suitably adjusted upward to decide on the

Deviation price vector.

(3) The Cap rate for the charges for the Deviation for the generating stations using coal or

lignite or gas supplied under Administered Price Mechanism (APM) as the fuel shall be 7

the value close to the energy charges on imported coal on Deviation Price vector.

(4) The Cap rate for the charges for the Deviation for the under drawls by the buyer and

the over-injection by the seller shall be the value close to the energy charges on imported

coal on Deviation Price vector.

(5) The Charges for Deviation may be reviewed from time to time by the Commission

and shall be re-notified accordingly.

(6) The infirm power injected into the grid by a generating unit of a generating station

during the testing, prior to COD of the unit shall be paid at Charges for Deviation for

infirm power injected into the grid, consequent to testing, for a period not exceeding 6

65

Page 66: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

months or the extended time allowed by the Commission in the Central Electricity

Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term

Open Access and related matters) Regulations, 2009, as amended from time to time,

subject to ceiling of Cap rates corresponding to the main fuel used for such generation as

specified below:

Domestic coal/ Lignite/Hydro `1.78 / kWh sent out

APM gas as fuel `2.82/ kWh sent out

Imported Coal/RLNG `3.05 / kWh sent out

Liquid Fuel `11.104 / kWh sent out

(7) Charges for Deviation of Inter-regional Exchange between the two asynchronously

inter-connected Regions shall be computed by the respective Regional Power

Committees, based on Charges for Deviation as per the frequency of the respective

Region. The amount to be settled for the inter-regional exchanges shall be average of the

Charges for Deviation computed for the two regions by way of such inter-change. 8

4.1.4. Declaration, scheduling and elimination of gaming(1) The provisions of the Grid Code and the Central Electricity Regulatory

Commission (Open Access in inter-State Transmission) Regulations, 2008, as amended

from time to time, shall be applicable for declaration of capacity, scheduling and

elimination of gaming.

(2) The generating station, as far as possible, shall generate electricity as per the day-

ahead generation schedule finalized by the Regional Load Dispatch Centre in accordance

with the Grid Code.

Provided that the revision in generation schedule on the day of operation shall be

permitted, in accordance with the procedure specified under the Grid Code and Central 66

Page 67: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

Electricity Regulatory Commission (Open Access in inter-State Transmission)

Regulations, 2008, as the case may be.

(3) The Commission, either suo motu or on a petition made by RLDC, or any affected

party, may initiate proceedings against any generating company or seller on charges of

gaming and if required, may order an inquiry in such manner as decided by the

Commission. When the charge of gaming is established in the above inquiry, the

Commission may, without prejudice to any other action under the Act or regulations there

under, disallow any Charges for Deviation received by such generating company or the

seller during the period of such gaming.”

4.1.5. Limits on Deviation volume and consequences of crossing limits

(1) The over-drawls / under drawls of electricity by any beneficiary or a buyer during a

time block shall not exceed 12% of its scheduled drawal or 150 MW, whichever is lower,

when frequency is ‘49.95’ Hz and above" and 3% on a daily aggregate basis for all the

time blocks when the frequency is ‘‘49.95 Hz and above’.

Provided that any drawal of power by a generating station prior to COD of a unit for 9 the

startup activities shall be exempted from the volume limit specified above.

Explanation: The limits specified in this clause shall apply to the sum total of over-

drawal by all the intra-State entities in the State including the distribution companies and

other intra-State buyers, and shall be applicable at the inter-State boundary of the

respective State.

(2) The under-injection / over-injection of electricity by a generating station or a seller

during a time-block shall not exceed 12% of the scheduled injection of such generating

67

Page 68: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

station or seller or 150 MW, whichever is lower, when frequency is ‘‘49.95 Hz and

above’ and 3% on daily aggregate basis for all the time blocks when the frequency is

‘‘49.95 Hz and above’.

Provided that any infirm injection of power by a generating station prior to COD of a unit

during testing and commissioning activities shall be exempted from the volume limit

specified above for a period not exceeding 6 months or the extended time allowed by the

Commission in accordance with the Connectivity Regulations.

(3) In addition to Charges for Deviation as stipulated under Regulation 5 of these

regulations, Additional Charge for Deviation shall be applicable for over-drawal/ under

drawls as well as under-injection/ over-injection of electricity for each time block in

excess of the volume limit specified in Clauses (1) and (2) of this regulation when grid

frequency is ‘‘49.95 Hz and above” at the rates specified below in accordance with the

methodology specified in clause 6 of this regulation:

(i) For over drawls/under drawls of electricity by any beneficiary or a buyer in excess of

12% and up to 15% of the schedule or above 150 MW and up to 200 MW in a time block

or in excess of 3% and up to 4% of the schedule over a day: equivalent to 20% of the

Charge for Deviation corresponding to grid frequency of "below 49.95 Hz".

(ii) For over drawls/under drawls of electricity by any beneficiary or a buyer in excess 10

of 15 % and up to 20% of the schedule or above 200 MW and up to 250 MW in a time

block or in excess of 4% and up to 5% of the schedule over a day: equivalent to 40% of

the Charge for Deviation corresponding to grid frequency of "below 49.95 Hz".

(iii) For over drawls/under drawls of electricity by any beneficiary or a buyer in excess of

20 % of the schedule or above 250 MW in a time block or in excess of 5% of the

schedule over a day: equivalent to 100% of the Charge for Deviation corresponding to

grid frequency of "below 49.95 Hz".

(iv) For under injection/ over-injection in excess of 12% and up to 15% of the schedule or

above 150 MW and up to 200 MW in a time block or in excess of 3% and up to 4% of the

68

Page 69: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

schedule over a day: equivalent to 20% of the Charge for Deviation corresponding to grid

frequency of "below 49.95 Hz".

(v) For under injection/over-injection in excess of 15 % and up to 20% of the schedule or

above 200 MW and up to 250 MW in a time block or in excess of 4% and up to 5% of the

schedule over a day: equivalent to 40% of the Charge for Deviation corresponding to grid

frequency of "below 49.95 Hz".

(vi)For under injection/over-injection in excess of 20 % of the schedule or above 250

MW in a time block or in excess of 5% of the schedule over a day: equivalent to 100% of

the Charge for Deviation corresponding to grid frequency of "below 49.95 Hz".

Provided further that Additional Charge for Deviation for under-injection/ over-injection

of electricity, during the time-block in excess of the volume limit specified in (1) and (2)

of this regulation when grid frequency is ‘‘49.95 Hz and above’, by the generating

stations using coal or lignite or gas supplied under Administered Price

Mechanism (APM) as the fuel shall be at the rates specified below in accordance with the

methodology specified in clause 8 of this regulation:

(i) For under injection in excess of 12% and up to 15% of the schedule or above 150

MW and up to 200 MW in a time block or in excess of 3% and up to 4% of the schedule

over a day: equivalent to 20% of the Cap Rate for Deviations of Rs 333.40/kWh. 11

(ii) For under injection in excess of 15 % and up to 20% of the schedule or above 200

MW and up to 250 MW in a time block or in excess of 4% and up to 5% of the schedule

over a day: equivalent to 40% of the Cap Rate for Deviations of Rs 333.40/kWh.

(iii) For under injection in excess of 20 % of the schedule or above 250 MW in a time

block or in excess of 5% of the schedule over a day: equivalent to 100% of the Cap Rate

for Deviations of Rs 333.40/kWh.

Provided that any drawal of power by a generating station prior to COD of a unit for the

startup activities shall be exempted from the levy of additional Charges of Deviation.

Provided also that any infirm injection of power by a generating station prior to

COD of a unit during testing and commissioning activities shall be exempted from levy

of additional charges for Deviation for a period not exceeding 6 months or the extended

69

Page 70: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

time as may be allowed by the Commission in accordance with the Connectivity

Regulations.

(4) Methodologies for the computation of Charges for Deviation and Additional Charges

for deviation for each regional entity for crossing the volume limits specified for the

under drawal /over-injection and for overdrawal and under-injection in clause (3) of this

regulation shall be as per Annexure-I and II respectively of these Regulations.

(5) In addition to Charges for Deviation as stipulated under Regulation 5 of these

Regulations, Additional Charge for Deviation shall be applicable for over-drawal/ under

drawls or under-injection/ over-injection of electricity for each time block when grid

frequency is ‘‘below 49.95 Hz’ in accordance with the methodology specified in clause 7

of this regulation shall be equivalent to 100% of the Charge for Deviation of

1110.40Paise/kWh corresponding to the grid frequency of "below 49.95 Hz".

Provided further that Additional Charge for Deviation for under-injection of electricity,

during the time-block when grid frequency is ‘‘below 49.95 Hz’, by the generating

stations using coal or lignite or gas supplied under Administered Price Mechanism

(APM) as the fuel in accordance with the methodology specified in clause 9 of 12 this

regulation shall be equivalent to 100% of the Cap Rate for Deviations of

333.40Paise/kWh.

Explanation: Additional Charges for Deviation shall not be applicable for net over

drawls by a region as a whole from other regions.

(6) The Additional Charge for Deviation for over-drawals / under-drawal and under-

injection / over-injection of electricity for each time block when grid frequency is"

49.95 Hz and above" shall be as specified by the Commission as a percentage of the

charges for the Deviation in grid frequency ‘below 49.95 Hz’ with due consideration to

70

Page 71: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

the behavior of the buyer and beneficiaries and sellers and the generating stations towards

grid discipline:

Provided that the Commission may specify different rates for additional Charges for

Deviation for over drawls/ under-drawal and under injections/ over-injection depending

upon different % deviation from the schedule in excess of the volume limit specified in

clause (1) and (2) of this Regulation.

(7) The additional Charge for Deviation for over-drawals and under-injection of

electricity for each time block when grid frequency is “below 49.95 Hz” shall be as

specified by the Commission as a percentage of the charges for the Deviation in grid

frequency ‘below 49.95 Hz’ with due consideration to the behavior of the buyer and

beneficiaries and sellers and the generating stations towards grid discipline: Provided that

the Commission may specify different rates for additional Charges for Deviation for over

drawls and under injections and for different ranges of frequencies ‘below 49.95 Hz’.

(8) The additional Charge for Deviation for under-injection of electricity during the time-

block in excess of the volume limit specified in Clause (2) of this regulation when grid

frequency is ‘49.95 Hz and above’, by the generating stations using coal or lignite or gas

supplied under Administered Price Mechanism (APM) as the fuel shall be as specified by

13 the Commission as a percentage of the Cap Rate, with due consideration to the

behavior of the generating stations towards grid discipline:

(9) The additional Charge for Deviation for under-injection of electricity during the time-

block when grid frequency is ‘below 49.95 Hz’, by the generating stations using coal or

lignite or gas supplied under Administered Price Mechanism (APM) as the fuel shall be

as specified by the Commission as a percentage of the Cap Rate, with due consideration

to the behavior of the generating stations towards grid discipline: Provided that the

71

Page 72: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

Commission may specify different rates for additional Charges for Deviation for under

injections at different ranges of frequencies ‘below 49.95 Hz’.

(10) Payment of Charges for Deviation under Regulation 5 and the Additional Charges

for Deviation under Clauses (3) and (4) of this regulation, shall be levied without

prejudice to any action that may be considered appropriate by the Commission under

Section 142 of the Act for contravention of the limits of over-drawal/ under drawal or

under-generation/over-injection as specified in these regulations, for each time block.

(11) Each of the regional entity such as generating station, beneficiary, buyer or the seller

shall have to make sign of their deviation from schedule changed, at least once, in every 6

time blocks. To illustrate, if a regional entity has positive deviation from schedule from

07.30hrs to 0.845hrs, then it must have negative deviation from schedule in the time

block 08.45hrs to 09.00hrs.

(12) The charges for over-drawal/ under-injection and under-drawal/ over-injection of

electricity shall be computed by the respective Regional Power Committee in accordance

with the methodology used for preparation of ‘Regional Energy Accounts’.

(13) The Regional Load Despatch Centre shall prepare and publish on its website the

records, on monthly basis, of the Deviation Accounts, specifying the quantum of over-

drawal/ under-generation and corresponding amount of charges for Deviation payable for

each beneficiary or buyer and receivable for each generating station or seller 14 for all the

time-blocks when grid frequency was "49.95 Hz and above" and "below 49.95" Hz

separately.”

72

Page 73: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

4.1.6. Compliance with instructions of Load Despatch Centre

Notwithstanding anything specified in these Regulations, the generating station, the

seller, the beneficiary and the buyer shall strictly follow the instructions of the Regional

Load Despatch Centre on generation and drawal in the interest of grid security and grid

discipline.

4.1.7. Accounting of Charges for Deviation

(1) A statement of charges for Deviations including Additional Charges for Deviation

levied under these regulations shall be prepared by the Secretariat of the respective

Regional Power Committee on weekly basis based on the data provided by the concerned

RLDC(s) and shall be issued to all constituents by Tuesday, for seven day period ending

on the penultimate Sunday mid-night.

(2) All payments on account of Charges for Deviation including Additional Charges for

Deviation levied under these regulations and interest, if any, received for late payment

shall be credited to the funds called the “Regional Deviation Pool Account Fund”, which

shall be maintained and operated by the concerned Regional Load Dispatch Centers in

each region in accordance with provisions of these regulations.

Provided that the Commission may by order direct any other entity to operate and

maintain the respective “Regional Deviation Pool Account Funds”:

Provided further that separate books of accounts shall be maintained for the principal

component and interest component of Charges for Deviation and Additional Charges for

Deviation by the Secretariat of the respective Regional Power Committee. 15

73

Page 74: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

(3) All payments received in the “Regional Deviation Pool Account Fund” of each region

shall be appropriated in the following sequence:

(a) First towards any cost or expense or other charges incurred on recovery of Charges

for deviation.

(b) Next towards over dues or penal interest, if applicable.

(c) Next towards normal interest.

(d) Lastly, towards charges for deviation and additional charges for deviation.

Explanation: Any Additional Charge for Deviation collected from a regional entity shall

be retained in the “Regional Deviation Pool Account Fund” of the concerned region

where the regional entity is located.

4.1.8. Schedule of Payment of Charges for Deviation

(1) The payment of charges for Deviation shall have a high priority and the concerned

constituent shall pay the indicated amounts within 10 (ten) days of the issue of statement

of Charges for Deviation including Additional Charges for Deviation by the Secretariat of

the respective Regional Power Committee into the “Regional Deviation Pool Account

Fund” of the concerned region.

(2) If payments against the Charges for Deviation including Additional Charges for

Deviation are delayed by more than two days, i.e., beyond twelve (12) days from the date

of issue of the statement by the Secretariat of the respective Regional Power Committee,

the defaulting constituent shall have to pay simple interest @ 0.04% for each day of

delay.

(3) All payments to the entities entitled to receive any amount on account of charges for

74

Page 75: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

Deviation shall be made within 2 working days of receipt of the payments in the

“Regional Deviation Pool Account Fund” of the concerned region. 16

Provided that in case of delay in the Payment of charges for Deviations into the

respective Regional Deviation Pool Account Fund and interest there on if any, beyond 12

days from the date of issue of the Statement of charges for Deviations then the regional

entities who have to receive payment for Deviation or interest thereon shall be paid from

the balance available if any, in the Regional Deviation Pool Account Fund of the region.

In case the balance available is not sufficient to meet the payment to the Regional

Entities, then the payment from the Regional Deviation Pool Accounts Fund shall be

made on pro rata basis from the balance available in the Fund.

Provided further that the liability to pay interest for the delay in payments to the

“Regional Deviation Pool Account Fund” shall remain till interest is not paid;

irrespective of the fact that constituents who have to receive payments have been paid

from the “Regional Deviation Pool Account Fund” in part or full.

(4) All regional entities which had at any time during the previous financial year failed to

make payment of Charges for Deviation including Additional Charges for Deviation

within the time specified in these regulations shall be required to open a Letter of Credit

(LC) equal to 110% of its average payable weekly liability for Deviations in the previous

financial year, in favour of the concerned RLDC within a fortnight from the date these

Regulations come into force.

Provided that if any regional entity fails to make payment of Charges for Deviation

including Additional Charges for Deviation by the time specified in these regulations

during the current financial year, it shall be required to open a Letter of Credit equal to

110% of weekly outstanding liability in favour of respective Regional Load Despatch

Centre within a fortnight from the due date of payment.

75

Page 76: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

Provided further that LC amount shall be increased to 110% of the payable weekly

liability for Deviation in any week during the year, if it exceeds the previous LC amount

by more than 50%.

Illustration: If the average payable weekly liability for Deviation of a regional entity

during 17 2009-10 is Rs.20crore, the regional entity shall open LC for 22crore in 2010-

11. If the weekly payable liability during any week in 2010-11 is Rs35crore which is

more than 50% of the previous financial year’s average payable weekly liability of

Rs30Crore, the concerned regional entity shall increase the LC amount to Rs38.5Crore

(1.1*Rs35.0) by adding Rs16.5Crore.

(5) In case of failure to pay into the “Regional Deviation Pool Account Fund” within the

specified time of 12 days from the date of issue of statement of charges for Deviations,

the RLDC shall be entitled to encash the LC of the concerned constituent to the extent of

the default and the concerned constituent shall recoup the LC amount within 3 days.

4.1.8. Application of fund collected through Deviations

The amount left in the Deviation Pool Account Fund after final settlement of claims of

Charges for Deviation of the generating stations and the beneficiaries shall be transferred

to a separate fund as "Power Systems Development Fund" specified by the Commission

and shall be utilized, for the purpose specified by the Commission.

4.1.9. Power to Relax.The Commission may by general or special order, for reasons to be recorded in writing,

and after giving an opportunity of hearing to the parties likely to be affected by grant of

76

Page 77: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

relaxation, may relax any of the provisions of these regulations on its own motion or on

an application made before it by an interested person.

4.1.10. Power to issue directions:-If any difficulty arises in giving effect to these regulations, the Commission may on its

own motion or on an application filed by any affected party, issue such directions as

may be considered necessary in furtherance of the objective and purpose of these

Table 15:OVER DRAWAL BY BENEFICIARY OR BUYER

Frequency

In a Time Block DayDeviation Charges

Payable(+)

Additional Deviation Charge

Payable(+)Total Deviation Charge

A B C D E F = D +E

49.95 AND

ABOVE

upto 12% of schedule or 150 MW whichever

is low

0 to 3%

Normal Deviation

rate correspond

ing to frequency

0

SUM OF COLUMN D & E

>12% to 15% of

schedule

>150MW to 200 MW

>3% to

4%

20% of charge for deviation

corresponding to below 49.95 =

222.08

>15% to 20% of

schedule

>200MW to 250 MW

>4% to

5%

40% of charge for deviation

corresponding to below 49.95 =

444.16

> 20% of schedule > 250MW > 5%

100% of charge for deviation

corresponding to below 49.95 =

1110.40

<49.95 >0 >0 >0 1110100% of charge

for deviation corresponding to

#

77

Page 78: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

below 49.95 = 1110.40

Table 16:UNDER DRAWAL BY BENEFICIARY / OVER INJECTION BY APM GENERATING STATION/SELLER (EXCEPT INFIRM POWER)

Frequency

In a Time Block DayDeviation Charges

Recivable(-)

Additional Deviation Charge

Payable(+)Total Deviation Charge

A B C D E F = D + E

49.95 AND

ABOVE

upto 12% of schedule or 150 MW whichever is

low

0 to 3%

Normal Deviation rate corresponding to frequency Ceiled to Rs

333.4

0

SUM OF COLUMN D & E

>12% to 15% of

schedule

>150MW to 200 MW

>3% to

4%0

20% of charge for deviation

corresponding to below

49.95 = 66.8

>15% to 20% of

schedule

>200MW to 250 MW

>4% to

5%0

40% of charge for deviation

corresponding to below 49.95 = 133.36

> 20% of schedule

> 250MW

> 5% 0 100% of

charge for

78

Page 79: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

deviation corresponding

to below 49.95 = 333.4

<49.95

upto 12% of schedule or 150 MW whichever is

low

0 to 3%

Normal Deviation rate corresponding to frequency Ceiled to Rs

333.4

0 D + E

> 12% of schedule or 150 MW

whichever is low>3% 0

100% of charge for deviation

corresponding to below

49.95 = 333.4

#

Table 17:UNDER INJECTION BY GENERATOR OR SELLER

Frequency

In a Time Block DayDeviation Charges

Payable(+)

Additional Deviation Charge

Payable(+)Total Deviation Charge

A B C D E F = D +E

49.95 AND

ABOVE

upto 12% of schedule or 150 MW whichever is

low

0 to 3%

Normal Deviation rate corresponding to frequency Ceiled to Rs 333.4. The Deviation for under-injection by a generating station “below 50.0 Hz” shall be its energy charge of the previous month, if energy charge is higher than the charges for Deviation

0

SUM OF COLUMN D & E>12% to 15% of

schedule

>150MW to 200 MW

>3% to

4%

20% of charge for deviation

corresponding to below

49.95 = 66.8

>15% to 20% of

schedule

>200MW to 250 MW

>4% to

5%

40% of charge for deviation

corresponding to below 49.95 = 133.36

79

Page 80: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

corresponding to the grid frequency of the time

> 20% of schedule

> 250MW

> 5%

100% of charge for deviation

corresponding to below

49.95 = 333.4

<49.95 >0 >0 >0

333.4 or its energy charge of the previous month, if energy charge is higher than the charges for Deviation corresponding to the grid frequency of the time block.

100% of charge for deviation

corresponding to below

49.95 = 333.4

666.8 Or Greater if energy charge rate is higher than

333.4

Table 18:INFIRM POWER BY GENERATOR UNDER APM OR SELLER

Frequency

In a Time Block Day

Deviation Charges

Payable(+) / Recievable

(-)

Additional Deviation Charge

Payable(+)Total Deviation Charge

A B C D E F = D +E

49.95 AND

ABOVE

No deviation limit specified, Allowed till 6 months or

extended time allowed by CERC

Normal Deviation Charge

subject to cap rate as below

0 SUM OF COLUMN D & E

80

Page 81: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

a) Domestic coal/

Lignite/Hydro `1.78 / kWh

sent outb) APM gas as fuel `2.82/ kWh sent outc) Imported Coal/RLNG `3.05 / kWh

sent outd) Liquid Fuel `11.104 / kWh

sent out<49.95 0

IR Deviation Charge: Charges for Deviation of Inter-regional Exchange between the two asynchronously inter-connected Regions shall be computed by the respective Regional Power Committees, based on Charges for Deviation as per the frequency of the respective Region. The amount to be settled for the inter-regional exchanges shall be average of the Charges for Deviation computed for the two regions by way of such inter-change.

4.2 Ancillary Service

The grid disturbance episodes on 30 and 31 July, 2012 have drawn the attention of the

policy makers to a very relevant issue of ensuring grid stability and reliability in the

country. With the restructuring of the power sector, the responsibility of ensuring grid

stability has been entrusted upon the system operators i.e. the Load Dispatch Centers at

the state, regional and national levels.

For any power system to operate efficiently, two unique requirements which must be

continuously and exactly satisfied in order to maintain overall system stability and

reliability is to maintain a constant balance between generation and load and to adjust

generation to manage power flows within the constraints of individual transmission

81

Page 82: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

facilities. Therefore, system operators need some resources to balance grid during

contingencies at short notice. These resources are commonly known as ancillary services.

In cost-plus regulated regime, these resources can be built and operated under the

instructions of system operators. However, in competitive, de-regulated regime,

developing markets for such resources is a need.

A general classification of ancillary services is given below:

Presently, in the Indian context, it is envisioned that a Frequency Support Ancillary

Service (FSAS) would help in improving the reliability of the operating system by

harnessing the unutilized generation units with capabilities of ramping up in about 30

82

Page 83: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

minutes. Currently, over 20,000 MW of bottled up generation is estimated to be present

in the country and close to 1000 MW of capacity is left unutilized in the Day-Ahead

Markets at exchanges. Such idle generationcapacity due to un-dispatched surpluses and

the un-cleared bids in the day-ahead market at the two power exchanges operating in the

country can be aggregated to create the Ancillary Market.

As such we need to create a market place to equip the system operator to aid in ensuring

grid reliability by providing support services. The broad principles to govern the

operations of such a market would entail:

1. Maintain grid frequency / voltage and other quality parameters within band as

specified in Indian Electricity Grid Code (IEGC).

2. Encourage qualified resources to support system by participating in the market

3. Resource pricing should be market-based

The recent staff paper by Central Electricity Regulatory Commission (CERC) on April

’13 on Introduction of Ancillary Services in Indian Electricity Market’ touches upon the

nuances and issues associated with the ancillary market design. Although the finer

peculiarity of the operations ofsuch a market needs to be worked out, the overall market

is perceived to operate through the exchanges approved by CERC. Once implemented,

the ancillary services will serve as an ‘insurance’ product which would help in

maintaining system reliability & security available directly to system operators at

regional and national level.

83

Page 84: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

4.2.1Frequency Support Ancillary Services (FSAS)

FSAS would be the service offered through bids by a generating station or any other

authorized entity on behalf of the generating station to make itself available for despatch

and get dispatched/ scheduled by the nodal agency to support the system frequency.

Hence, the focus of introducing Frequency Support Ancillary Service (FSAS) would be

to maintain the frequency within the band specified in the IEGC. FSAS, at present in the

Indian context, aims to stabilize the grid frequency by maximizing unutilized generation

and minimizing load shedding, under certain conditions, for ensuring grid safety and

security. Gradually as this market grows and imbalances are better handled with

improved system security and reliability, this market could phase out the UI Mechanism.

It is however pertinent to mention that introduction of ancillary services may not

automatically mean a good frequency profile.

Integration of renewable energy in the grid is one of the biggest thrust areas. The

installed generation capacity of renewable generators is expected to grow manifold in the

coming years. Considering the high variability and unpredictability of generation from

renewable, the FSAS would serve to stabilize the frequency for increased integration of

renewable sources into the grid. Frequency Support Ancillary Service (FSAS) can be

used to complement the diurnal changes in renewable generation. FSAS can thus also be

used as a mechanism to facilitate renewable integration by reducing the impact of their

variation.

4.2.2 Voltage Control Ancillary Services (VCAS) & Black Start Ancillary Services (BSAS)

The Electricity Act 2003 entrusts the responsibility of transmission system planning on

the CEA and the CTU. While the CEA forms perspective plans, the CTU fine tunes them

84

Page 85: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

over a shorter period in coordination with the CEA amongst others. While planning for

the grid, the CEA and CTU, use system studies for ensuring a proper voltage profile at

various points in the grid. However, the planning is done in anticipation of generators and

loads coming up at various points in the grid. Due to variations between the anticipated

and the actual for generation and load, the reactive power requirements change. The

reactive power requirements also change as more and more elements get added to the

grid. Since voltage is a local phenomenon and not a global phenomenon like frequency,

the requirement of capacitor and/or reactor at a various nodes (sub-station or switchyard

of generating station) may need to be changed. Therefore, we feel that the provision of

reactive power, which may require a change in location, could be allowed under reactive

power support ancillary services. There is already a commercial mechanism in the IEGC

under Regulation 6.6 of the IEGC Regulations, w.r.t. voltage reference at the interchange

point, which incentivizes maintaining a proper voltage profile at all interchange points

between control areas in the grid. However, in case it is observed by the system operator

that there is a critically low voltage in the grid at one or more such interconnection points

persisting during a season, the system operator may requisition voltage support ancillary

services from any service provider, who may bid the same through the power exchange.

Given that mobile substations, installed in trailers, which allow flexibility for quick

installation to restore supply, are gaining popularity, we feel that mobile reactors or

capacitors would be a big advantage and also result in reduction in cost, since they could

easily be moved from one sub-station to another, as per requirement. But to start with, the

mobile reactive compensation would be provided by the government owned transmission

companies only.

CONCLUSION

From the above report it can be concluded that the grid as well as short-term market

transactions were relatively more reliable as well as stable in FY 2012-13 as compared to 85

Page 86: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

FY 2011-12. The volume of short term electricity transacted through UI has been

successfully been reduced from 2576.06MUs in April’12 to 1637.26 MUs in March’13.

The volume of electricity transacted through short-term transactions in Power Exchange

has gradually been in increasing mode and has increased from 1337.18MUs in April’12

to 2324.35MUs in March’13. The volume transacted through Bilateral Transactions were

continuously on higher side and kept fluctuating within a prescribed limit.

The total short–term transaction of electricity which were 9% of total electricity

generated in 2009-10, has gradually increased to 11% of total generation in 2012-13.

The total percentage increase in volume transacted through Power Exchange from

FY2011-12 to FY2012-13 was 49% which was only 0.13% from FY2010-11 to FY2011-

12 and the percentage increase in total revenue generated through Power Exchange was

also 49% from FY2011-12 to FY2012-13, which was only 3.04% from FY2010-11 to

FY2011-12.

At the end of the report brief discussion on the DEVIATION SETTLEMENT

MECHANISM has been done, which is currently recommended by CEREC as a tool to

replace UI mechanism of charging for the deviation in actual transactions from the

scheduled one. Also the Ancillary Services has been discussed as a tool to further support

the Grid.

BIBLIOGRAPHY

[1] Central Electricity Regulatory Commission (CERC)(2012). Monthly report on Short-

Term Power Market April’12-March’13

86

Page 87: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

[2] Central Electricity Authority. Report on Congestion Management.

[3] Power Exchange India Limited (PXIL). Congestion Management Methods.

[4] India Energy Exchange (IEX). Congestion Management Operations.

[5] Power System Operation Corporation Limited (POSOCO). Monthly Report On

Operational Performance

[6] India Energy Exchange (IEX). Bulletin News and Information issue of June ‘13

[7] Integrated Council on Large Electric System (CIGRE). The challenge of ensuring

adequate generation capacity in the competitive market.

[8] Central Electricity Regulatory Commission (CERC). Introduction to Ancillary

Services

[9] shodhganga.inflibnet.ac.in/jspui/bitstream/10603/.../11_chapter%202.pdf.Report on power

market operations.

ANNEXURE – 1

Volume of Short Term Transactions (in MUs) for 2012-13 (till Dec'12)

87

Page 88: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

S.NoName of the State

Through Bilateral Through Power ExchangeThrough UI with Regional

Grid

Sale Purchase Net Sale Purchase Net

Export(UnderDrawl)

Import(OverDrawl) Net

TotalNet

1 Punjab 1031 5330 4299 42.96 2382 2339 378 1251 872.9 75112 Haryana 836 2251 1415 24.87 1100 1075 679 1661 981.6 34723 Rajasthan 1766 756.6 -1009 242.7 2954 2712 444 1724 1279 2982

4 Delhi 1585 2205 620.5 1981 63.78-

1917 1707 77-

1630-

2927

5Uttar Pradesh 477.2 1906 1429 69.88 1422 1352 586 3523 2937 5719

6Uttarakhand 223.4 725.5 502.1 48.78 208.9

160.1 123 671.6 548.4 1211

7Himachal Pradesh 1587 599.2 -988 1750 41.07

-1709 315 274.5 -40.7

-2738

8 J&K 2070 1070 -1000 72.58 11.52 -61.1 465 420.8 -44.2-

11059 Chandigarh 14.64 152.5 137.9 50.29 11.88 -38.4 86.9 51.77 -35.1 64.3

10 MP 1627 1861 233.8 1131 335.2 -796 969 512.4 -457-

1018

11Maharashtra 796.8 4166 3369 321.9 1208

886.3 893 944.2 50.81 4306

12 Gujarat 4199 1587 -2613 1708 3212 1504 1811 449.6-

1361-

2470

13 Chattisgarh 1277 458.2 -818.5 716.4 27.49 -689 439 437.5 -1.41-

1509

14Daman and Diu 0 105.7 105.7 0 0 0 73.7 32.08 -41.7 64

15

Dadra & Nagar Havelli 0 568.4 568.4 0 0 0 141 55.13 -86.3 482

16Andhra Pradesh 128.5 3915 3786 469.8 1045

575.7 270 503.9 233.8 4596

17 Karnataka 1802 146.5 -1655 1842 35.07-

1807 357 251.2 -105-

356818 Kerala 0 1031 1031 0.97 1105 1104 8.59 786.6 778 291319 Tamilnadu 0 1421 1421 0.26 1008 1008 429 424.7 -3.97 242520 Pondicherry 0 0 0 0 0 0 239 9.29 -230 -230

21West Bengal 1591 2677 1087 500.6 252.1 -249 614 530.8 -83 755

22 Orissa 938 456.4 -481.6 172.8 89.97 -82.8 253 498.4 245.2 -31923 Bihar 76.94 1816 1740 23.36 0 -23.4 558 156.4 -402 1314

24 Jharkhand 80.24 837 756.7 0 46.8246.8

2 497 98.37 -399 405

88

Page 89: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

25 Sikkim 217.1 131.5 -85.52 145.6 0 -146 65.6 41.65 -23.9 -255

26 DVC 1812 163.3 -1648 180 11.73 -168 339 437.2 98.32-

1718

27Arunachal Pradesh 358.2 54.51 -303.7 19.97 23.39 3.42 186 237.9 52 -248

28 Assam 0 426 426 52.34 163.6111.

3 296 331.5 35.95 573

29 Manipur 0 37.54 37.54 0.02 36.9136.8

9 264 211.9 -52.2 22.230 Meghalaya 51.42 49.85 -1.57 32.64 22.03 -10.6 197 196.8 0.03 -12.231 Mizoram 0 15.13 15.13 23.19 3.51 -19.7 158 161.7 4.11 -0.4432 Nagaland 28.77 0 -28.77 1.31 6.73 5.42 176 194.8 18.94 -4.4133 Tripura 13.42 40.46 27.04 11.8 1.98 -9.82 205 178.3 -26.3 -9.0634 Goa 0.82 54.61 53.79 37.99 3.64 -34.4 115 141.4 26.47 45.9

ANNEXURE – 2

89

Page 90: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

Time Block Time

Frequency Code

FREQUENC

YDelhi

  Schedule Actual

Deviation

12% deviation

UI RATE

Deviation Charges Recivable(-)

Deviation Charges Payable(+)

Additional Deviation Charge Payable(+)

Total Deviation Charge

1 00:00-00:15 45 49.9

977.20 934.28-42.91

117.26 1110 333.4 0 0 -333.4

2 00:15-00:30 51 50

967.32 934.22-33.10

116.08 142.4 142.4 0 0 -142.4

3 00:30-00:45 52 50

959.23 915.21-44.02

115.11 35.6 35.6 0 0 -35.6

4 00:45-01:00 46 49.9

950.88 895.47-55.41

114.11 1110 333.4 0 0 -333.4

5 01:00-01:15 53 50.1

947.34 878.45-68.88

113.68 0 0 0 0 0

6 01:15-01:30 56 50.1

934.72 882.01-52.71

112.17 0 0 0 0 0

7 01:30-01:45 59 50.2

906.83 875.75-31.08

108.82 0 0 0 0 0

8 01:45-02:00 53 50.1 877.52 862.59 -14.93 105.3 0 0 0 0 0

9 02:00-02:15 50 50

854.75 858.313.56

102.57 333.4 0 333.4 0 333.4

10 02:15-02:30 49 50

847.99 841.20-6.79

101.76 644.2 333.4 0 0 -333.4

11 02:30-02:45 46 49.9

842.35 822.49-19.86

101.08 1110 333.4 0 0 -333.4

12 02:45-03:00 49 50

771.10 821.2050.10

92.532 644.2 0 644.2 0 644.2

13 03:00-03:15 51 50

747.38 813.4766.09

89.686 142.4 0 142.4 0 142.4

14 03:15-03:30 53 50.1

740.08 802.1262.05

88.809 0 0 0 0 0

15 03:30-03:45 56 50.1

730.34 796.3265.98

87.641 0 0 0 0 0

16 03:45-04:00 52 50

723.03 784.3461.31

86.764 35.6 0 35.6 0 35.6

17 04:00-04:15 50 50

705.72 775.0169.29

84.687 333.4 0 333.4 0 333.4

18 04:15-04:30 54 50.1

700.95 770.8269.87

84.114 0 0 0 0 0

19 04:30-04:45 50 50

686.59 758.4971.90

82.391 333.4 0 333.4 0 333.4

90

Page 91: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

20 04:45-05:00 48 50

686.59 743.9657.37

82.391 995 0 995 0 995

21 05:00-05:15 46 49.9

661.03 730.4769.44

79.324 1110 0 1110 1110 2220.8

22 05:15-05:30 50 50

662.91 721.9859.08

79.549 333.4 0 333.4 0 333.4

23 05:30-05:45 41 49.8

662.91 698.1335.23

79.549 1110 0 1110 1110 2220.8

24 05:45-06:00 46 49.9

669.67 681.7412.07

80.361 1110 0 1110 1110 2220.8

25 06:00-06:15 56 50.1

666.21 684.9018.70

79.945 0 0 0 0 0

26 06:15-06:30 51 50

691.40 673.41-17.99

82.968 142.4 142.4 0 0 -142.4

27 06:30-06:45 50 50

726.20 669.50-56.69

87.143 333.4 333.4 0 0 -333.4

28 06:45-07:00 51 50 724.59 662.81 -61.77 86.95 142.4 142 0 0 -142

29 07:00-07:15 49 50

727.27 662.61-64.66

87.272 644.2 333.4 0 0 -333.4

30 07:15-07:30 45 49.9

725.06 657.95-67.10

87.007 1110 333.4 0 1110 777

31 07:30-07:45 48 50

717.05 653.17-63.88

86.046 995 333.4 0 0 -333.4

32 07:45-08:00 53 50.1

700.18 655.86-44.32

84.022 0 0 0 0 0

33 08:00-08:15 48 50

718.66 649.15-69.51

86.239 995 333.4 0 0 -333.4

34 08:15-08:30 39 49.8

733.48 636.90-96.57

88.017 1110 0 0 222.1 222.08

35 08:30-08:45 34 49.7

722.96 635.42-87.54

86.755 1110 0 0 222.1 222.08

36 08:45-09:00 44 49.9

719.92 651.92-68.00

86.391 1110 333.4 0 0 -333.4

37 09:00-09:15 41 49.8

710.60 676.82-33.78

85.272 1110 333.4 0 0 -333.4

38 09:15-09:30 40 49.8

743.36 709.76-33.60

89.203 1110 333.4 0 0 -333.4

39 09:30-09:45 44 49.9

751.76 737.53-14.23

90.212 1110 333.4 0 0 -333.4

40 09:45-10:00 54 50.1 747.92 766.27 18.35 89.75 0 0 0 0 0

41 10:00-10:15 54 50.1

791.73 779.37-12.35

95.007 0 0 0 0 0

42 10:15-10:30 52 50

795.06 791.92-3.14

95.407 35.6 35.6 0 0 -35.6

43 10:30-10:45

55 50.1 793.28 803.59 10.31 95.19 0 0 0 0 0

91

Page 92: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

4

44 10:45-11:00 49 50 803.75 819.60 15.85 96.45 644.2 0 644.2 0 644.2

45 11:00-11:15 48 50

806.15 830.5324.38

96.738 995 0 995 0 995

46 11:15-11:30 43 49.9

817.50 833.1415.65

98.099 1110 0 1110 1110 2220.8

47 11:30-11:45 51 50

823.18 820.72-2.46

98.782 142.4 142.4 0 0 -142.4

48 11:45-12:00 51 50

819.78 829.759.97

98.373 142.4 0 142.4 0 142.4

49 12:00-12:15 48 50 848.35 839.11 -9.24 101.8 995 333.4 0 0 -333.4

50 12:15-12:30 50 50

862.84 849.88-12.96

103.54 333.4 333.4 0 0 -333.4

51 12:30-12:45 44 49.9

859.65 872.1512.50

103.16 1110 0 1110 1110 2220.8

52 12:45-13:00 51 50

859.91 870.6510.74

103.19 142.4 0 142.4 0 142.4

53 13:00-13:15 60 50.2

842.42 856.4714.05

101.09 0 0 0 0 0

54 13:15-13:30 47 49.9

837.78 847.119.33

100.53 1110 0 1110 1110 2220.8

55 13:30-13:45 45 49.9 839.14 872.75 33.61 100.7 1110 0 1110 1110 2220.8

56 13:45-14:00 52 50

858.13 903.3445.22

102.98 35.6 0 35.6 0 35.6

57 14:00-14:15 57 50.1

926.50 928.712.21

111.18 0 0 0 0 0

58 14:15-14:30 46 49.9

938.95 959.3320.38

112.67 1110 0 1110 1110 2220.8

59 14:30-14:45 50 50

948.93 969.7220.79

113.87 333.4 0 333.4 0 333.4

60 14:45-15:00 51 50

952.96 996.2043.24

114.35 142.4 0 142.4 0 142.4

61 15:00-15:15 54 50.1

966.20 1024.25 58.05

115.94 0 0 0 0 0

62 15:15-15:30 57 50.1

1019.93

1028.56 8.63

122.39 0 0 0 0 0

63 15:30-15:45 55 50.1

1021.55

1018.49 -3.06

122.59 0 0 0 0 0

64 15:45-16:00 60 50.2

1022.00

1021.68 -0.32

122.64 0 0 0 0 0

65 16:00-16:15 64 50.3

961.77 1010.58 48.80

115.41 0 0 0 0 0

66 16:15-16:30 51 50

951.45 1016.41 64.96

114.17 142.4 0 142.4 0 142.4

67 16:30- 52 50 945.84 1020.3 74.52 113.5 35.6 0 35.6 0 35.6

92

Page 93: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

16:45 6

68 16:45-17:00 54 50.1

942.44 1002.18 59.74

113.09 0 0 0 0 0

69 17:00-17:15 61 50.2

915.42 977.1261.70

109.85 0 0 0 0 0

70 17:15-17:30 54 50.1

911.23 940.4129.18

109.35 0 0 0 0 0

71 17:30-17:45 53 50.1

894.53 905.2710.74

107.34 0 0 0 0 0

72 17:45-18:00 53 50.1

877.63 863.76-13.87

105.32 0 0 0 0 0

73 18:00-18:15 60 50.2

856.81 843.49-13.32

102.82 0 0 0 0 0

74 18:15-18:30 56 50.1

862.12 823.53-38.59

103.45 0 0 0 0 0

75 18:30-18:45 52 50

858.18 795.95-62.23

102.98 35.6 35.6 0 0 -35.6

76 18:45-19:00 53 50.1

856.99 793.66-63.33

102.84 0 0 0 0 0

77 19:00-19:15 55 50.1

857.93 775.34-82.58

102.95 0 0 0 0 0

78 19:15-19:30 45 49.9

855.33 772.82-82.52

102.64 1110 0 1110 1110 2220.8

79 19:30-19:45 48 50

867.30 778.93-88.37

104.08 995 0 995 0 995

80 19:45-20:00 49 50

886.17 795.00-91.16

106.34 644.2 333.4 0 0 -333.4

81 20:00-20:15 48 50

898.96 810.30-88.66

107.87 995 333.4 0 0 -333.4

82 20:15-20:30 50 50

913.78 810.90-

102.87

109.65 333.4 333.4 0 0 -333.4

83 20:30-20:45 47 49.9

891.81 806.44-85.37

107.02 1110 0 1110 1110 2220.8

84 20:45-21:00 53 50.1

898.48 805.29-93.19

107.82 0 0 0 0 0

85 21:00-21:15 58 50.2

906.97 810.82-96.15

108.84 0 0 0 0 0

86 21:15-21:30 51 50

895.35 816.87-78.48

107.44 142.4 142.4 0 0 -142.4

87 21:30-21:45 49 50

901.81 832.44-69.37

108.22 644.2 333.4 0 0 -333.4

88 21:45-22:00 55 50.1

900.55 855.62-44.93

108.07 0 0 0 0 0

89 22:00-22:15 48 50 905.02 862.85 -42.17 108.6 995 333.4 0 0 -333.4

90 22:15- 52 50 923.58 878.19 -45.39 110.8 35.6 35.6 0 0 -35.6

93

Page 94: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

22:30 3

91 22:30-22:45 52 50

957.35 889.19-68.16

114.88 35.6 35.6 0 0 -35.6

92 22:45-23:00 60 50.2

962.88 894.78-68.09

115.55 0 0 0 0 0

93 23:00-23:15 51 50

966.07 896.86-69.21

115.93 142.4 142.4 0 0 -142.4

94 23:15-23:30 48 50

953.69 892.20-61.49

114.44 995 333.4 0 0 -333.4

95 23s:30-23:45 53 50.1

953.96 887.88-66.08

114.48 0 0 0 0 0

96 23:45-24:00 55 50.1

951.41 883.30-68.11

114.17 0 0 0 0 0

      5080879 79498

-1381.

009705.

5 333.4 0 0 -333.4 234.25

Time Time Frequen   Singrauli

94

Page 95: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

Block cy Code

frequency

Schedule Actual

Deviation

12% of schedule

UI RATE

Deviation Charges Recivable(-)

Deviation Charges Payable(+)

Additional Deviation Charge Payable(+)

Total Deviation Charge

1 00:00-00:15 45 49.9 483.75 485.09 1.34 58.05 1110 333 0 0 -333.4

2 00:15-00:30 51 50 483.75 486.29 2.54 58.05 142 142 0 0 -142.4

3 00:30-00:45 52 50 483.75 483.78 0.03 58.05 35.6 35.6 0 0 -35.6

4 00:45-01:00 46 49.9 483.75 485.53 1.78 58.05 1110 333 0 0 -333.4

5 01:00-01:15 53 50.1 483.75 483.02 -0.73 58.05 0 0 132 0 132

6 01:15-01:30 56 50.1 483.75 487.53 3.78 58.05 0 0 0 0 0

7 01:30-01:45 59 50.2 483.75 482.58 -1.17 58.05 0 0 0 0 0

8 01:45-02:00 53 50.1 483.75 481.02 -2.73 58.05 0 0 0 0 0

9 02:00-02:15 50 50 483.75 486.18 2.43 58.05 333 333 0 0 -333.4

10 02:15-02:30 49 50 483.75 485.64 1.89 58.05 644 333 0 0 -333.4

11 02:30-02:45 46 49.9 483.75 484.11 0.36 58.05 1110 333 0 0 -333.4

12 02:45-03:00 49 50 483.75 483.64 -0.11 58.05 644 0 333.4 0 333.4

13 03:00-03:15 51 50 483.75 484.98 1.23 58.05 142 142 0 0 -142.4

14 03:15-03:30 53 50.1 483.75 485.56 1.81 58.05 0 0 0 0 0

15 03:30-03:45 56 50.1 483.75 486.36 2.61 58.05 0 0 0 0 0

16 03:45-04:00 52 50 483.75 483.96 0.21 58.05 35.6 35.6 0 0 -35.6

17 04:00-04:15 50 50 483.75 484.07 0.32 58.05 333 333 0 0 -333.4

18 04:15-04:30 54 50.1 483.75 482.65 -1.10 58.05 0 0 0 0 0

19 04:30-04:45 50 50 483.75 483.38 -0.37 58.05 333 0 333.4 0 333.4

20 04:45-05:00 48 50 483.75 481.42 -2.33 58.05 995 0 333.4 0 333.4

21 05:00-05:15 46 49.9 483.75 484.91 1.16 58.05 1110 333 0 0 -333.4

22 05:15-05:30 50 50 483.75 484.29 0.54 58.05 333 333 0 0 -333.4

23 05:30-05:45 41 49.8 483.75 485.71 1.96 58.05 1110 333 0 0 -333.4

24 05:45-06:00 46 49.9 483.75 486.98 3.23 58.05 1110 333 0 0 -333.4

95

Page 96: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

25 06:00-06:15 56 50.1 483.75 486.84 3.09 58.05 0 0 0 0 0

26 06:15-06:30 51 50 483.75 487.38 3.63 58.05 142 142 0 0 -142.4

27 06:30-06:45 50 50 483.75 488.55 4.80 58.05 333 333 0 0 -333.4

28 06:45-07:00 51 50 483.75 487.75 4.00 58.05 142 142 0 0 -142.4

29 07:00-07:15 49 50 483.75 489.31 5.56 58.05 644 333 0 0 -333.4

30 07:15-07:30 45 49.9 483.75 486.36 2.61 58.05 1110 333 0 0 -333.4

31 07:30-07:45 48 50 483.75 484.11 0.36 58.05 995 333 0 0 -333.4

32 07:45-08:00 53 50.1 483.75 485.24 1.49 58.05 0 0 0 0 0

33 08:00-08:15 48 50 483.75 484.18 0.43 58.05 995 333 0 0 -333.4

34 08:15-08:30 39 49.8 483.75 485.31 1.56 58.05 1110 333 0 0 -333.4

35 08:30-08:45 34 49.7 483.75 484.44 0.69 58.05 1110 333 0 0 -333.4

36 08:45-09:00 44 49.9 483.75 484.36 0.61 58.05 1110 333 0 0 -333.4

37 09:00-09:15 41 49.8 483.75 486.11 2.36 58.05 1110 333 0 0 -333.4

38 09:15-09:30 40 49.8 483.75 483.20 -0.55 58.05 1110 0 333.4 333 666.8

39 09:30-09:45 44 49.9 483.75 482.47 -1.28 58.05 1110 0 333.4 333 666.8

40 09:45-10:00 54 50.1 483.75 479.05 -4.70 58.05 0 0 0 0 0

41 10:00-10:15 54 50.1 483.75 480.47 -3.28 58.05 0 0 0 0 0

42 10:15-10:30 52 50 483.75 479.49 -4.26 58.05 35.6 0 35.6 0 35.6

43 10:30-10:45 55 50.1 483.75 475.71 -8.04 58.05 0 0 0 0 0

44 10:45-11:00 49 50 483.75 474.95 -8.80 58.05 644 0 333.4 0 333.4

45 11:00-11:15 48 50 483.75 467.09 -16.66 58.05 995 0 333.4 0 333.4

46 11:15-11:30

4349.9

483.75 351.82-

131.93 58.05 1110 0 333.4 333 666.8

47 11:30-11:45

5150

483.75 352.98-

130.77 58.05 142 0 142.4 142 284.8

48 11:45-12:00 51 50 355.00 353.96 -1.04 42.6 142 0 142.4 0 142.4

49 12:00-12:15 48 50 355.00 355.09 0.09 42.6 995 333 0 0 -333.4

50 12:15-12:30 50 50 355.00 354.62 -0.38 42.6 333 0 333.4 0 333.4

96

Page 97: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

51 12:30-12:45 44 49.9 355.00 355.60 0.60 42.6 1110 333 0 0 -333.4

52 12:45-13:00 51 50 355.00 354.55 -0.45 42.6 142 0 142.4 0 142.4

53 13:00-13:15 60 50.2 355.00 353.20 -1.80 42.6 0 0 0 0 0

54 13:15-13:30 47 49.9 355.00 353.64 -1.36 42.6 1110 0 333.4 0 333.4

55 13:30-13:45 45 49.9 355.00 360.36 5.36 42.6 1110 333 0 0 -333.4

56 13:45-14:00 52 50 367.50 381.35 13.85 44.1 35.6 35.6 0 0 -35.6

57 14:00-14:15 57 50.1 380.00 380.51 0.51 45.6 0 0 0 0 0

58 14:15-14:30 46 49.9 392.50 404.25 11.75 47.1 1110 333 0 0 -333.4

59 14:30-14:45 50 50 392.50 417.45 24.95 47.1 333 333 0 0 -333.4

60 14:45-15:00 51 50 405.00 427.78 22.78 48.6 142 142 0 0 -142.4

61 15:00-15:15 54 50.1 415.00 431.20 16.20 49.8 0 0 0 0 0

62 15:15-15:30 57 50.1 430.00 432.07 2.07 51.6 0 0 0 0 0

63 15:30-15:45 55 50.1 442.50 350.65 -91.85 53.1 0 0 0 333 333.4

64 15:45-16:00 60 50.2 442.50 342.65 -99.85 53.1 0 0 0 333 333.4

65 16:00-16:15

6450.3

455.00 348.44-

106.56 54.6 0 0 0 333 333.4

66 16:15-16:30 51 50 355.00 355.67 0.67 42.6 142 142 0 0 -142.4

67 16:30-16:45 52 50 355.00 355.93 0.93 42.6 35.6 35.6 0 0 -35.6

68 16:45-17:00 54 50.1 355.00 356.91 1.91 42.6 0 0 0 0 0

69 17:00-17:15 61 50.2 355.00 357.24 2.24 42.6 0 0 0 0 0

70 17:15-17:30 54 50.1 355.00 355.85 0.85 42.6 0 0 0 0 0

71 17:30-17:45 53 50.1 355.00 356.55 1.55 42.6 0 0 0 0 0

72 17:45-18:00 53 50.1 355.00 355.05 0.05 42.6 0 0 0 0 0

73 18:00-18:15 60 50.2 355.00 354.80 -0.20 42.6 0 0 0 0 0

74 18:15-18:30 56 50.1 355.00 354.44 -0.56 42.6 0 0 0 0 0

75 18:30-18:45 52 50 355.00 354.04 -0.96 42.6 35.6 0 35.6 0 35.6

76 18:45-19:00 53 50.1 355.00 352.33 -2.67 42.6 0 0 0 0 0

77 19:00- 55 50.1 355.00 352.04 -2.96 42.6 0 0 0 0 0

97

Page 98: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

19:15

78 19:15-19:30 45 49.9 355.00 355.24 0.24 42.6 1110 333 0 0 -333.4

79 19:30-19:45 48 50 355.00 351.56 -3.44 42.6 995 0 333.4 0 333.4

80 19:45-20:00 49 50 355.00 351.13 -3.87 42.6 644 0 333.4 0 333.4

81 20:00-20:15 48 50 355.00 354.40 -0.60 42.6 995 0 333.4 0 333.4

82 20:15-20:30 50 50 355.00 354.87 -0.13 42.6 333 0 333.4 0 333.4

83 20:30-20:45 47 49.9 355.00 355.71 0.71 42.6 1110 333 0 0 -333.4

84 20:45-21:00 53 50.1 355.00 355.20 0.20 42.6 0 0 0 0 0

85 21:00-21:15 58 50.2 355.00 353.56 -1.44 42.6 0 0 0 0 0

86 21:15-21:30 51 50 355.00 354.29 -0.71 42.6 142 0 142.4 0 142.4

87 21:30-21:45 49 50 355.00 355.09 0.09 42.6 644 333 0 0 -333.4

88 21:45-22:00 55 50.1 355.00 355.93 0.93 42.6 0 0 0 0 0

89 22:00-22:15 48 50 355.00 358.15 3.15 42.6 995 333 0 0 -333.4

90 22:15-22:30 52 50 367.50 378.73 11.23 44.1 35.6 35.6 0 0 -35.6

91 22:30-22:45 52 50 380.00 367.89 -12.11 45.6 35.6 0 35.6 0 35.6

92 22:45-23:00 60 50.2 392.50 349.35 -43.15 47.1 0 0 0 0 0

93 23:00-23:15 51 50 405.00 353.42 -51.58 48.6 142 0 142.4 142 284.8

94 23:15-23:30 48 50 355.00 357.78 2.78 42.6 995 333 0 0 -333.4

95 23:30-23:45 53 50.1 355.00 357.31 2.31 42.6 0 42.6 0 0 -42.6

96 23:45-24:00 55 50.1 355.00 359.49 4.49 42.6 0 0 0 0 0

98

Page 99: DECLARATION - .: National Power Training Institute · Web viewGUVNL Gujarat Urja Vikas Nigam Limited HEP Hydro Electric Project HHI Herfindahl-Hirschman Index HPSEB Himachal Pradesh

ANEXXURE-3

Herfindahl-Hirschman Index (HHI) CalculationFormula for computing the HHI is as under:

NHHI = Σ si2i =1where si is the market share of firm i in the market, and N is the number of firms.

The Herfindahl-Hirschman Index (HHI) ranges from 1 / N to one, where N is the

number of firms in the market. Equivalently, if percents are used as whole numbers, as in

75

instead of 0.75, the index can range up to 1002 or 10,000.

· A HHI index below 0.01 (or 100) indicates a highly competitive index.

· A HHI index below 0.15 (or 1,500) indicates an unconcentrated index.

· A HHI index between 0.15 to 0.25 (or 1,500 to 2,500) indicates moderate

concentration.

· A HHI index above 0.25 (above 2,500) indicates high concentration.

There is also a normalised Herfindahl index. Whereas the Herfindahl index ranges from

1/N to one, the normalized Herfindahl index ranges from 0 to 1.

99