DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through...

103
i DECLARATION I, Satyanarayan Mahapatra, Roll No 1120812269, student of MBA-Power Management (2011- 13) at National Power Training Institute, Faridabad hereby declare that the Summer Training Report entitled ―STUDY ON REDUCTION OF BARRIERS TO R&M INTERVENTIONS IN THERMAL POWER STATIONS IN INDIA‖ is an original work and the same has not been submitted to any other Institute for the award of any other degree. A Seminar presentation of the Training Report was made on ________________________ and the suggestions as approved by the faculty were duly incorporated. Presentation In-Charge Signature of the Candidate (Faculty) Countersigned Director/Principal of the Institute

Transcript of DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through...

Page 1: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

i

DECLARATION

I, Satyanarayan Mahapatra, Roll No 1120812269, student of MBA-Power Management (2011-

13) at National Power Training Institute, Faridabad hereby declare that the Summer Training

Report entitled ―STUDY ON REDUCTION OF BARRIERS TO R&M INTERVENTIONS IN

THERMAL POWER STATIONS IN INDIA‖ is an original work and the same has not been

submitted to any other Institute for the award of any other degree.

A Seminar presentation of the Training Report was made on ________________________

and the suggestions as approved by the faculty were duly incorporated.

Presentation In-Charge Signature of the Candidate

(Faculty)

Countersigned

Director/Principal of the Institute

Page 2: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

ii

ACKNOWLEDGEMENT

Apart from efforts of the person doing the project, the success of any project depends

largely on the encouragements and guidelines of many others. I take this opportunity to

express my gratitude to the people who have been instrumental in the successful completion of

the project.

I thank to Shri Anish De, CEO AF-Mercados EMI for giving me the opportunity to work on such

an insightful project for CEA and World Bank. I would like to extend my thanks to my guide Mr.

Vikas Gaba, Senior Manager, AF-Mercados for showing me the right path and approach towards

the project.

I also record my sincere thanks to Mr. Sarim Siddiquie and Mr. Bharath V. for their support

during my project. I also give my immense pleasure to thank the entire staff for their

immeasurable cooperation necessary for carrying out project related work.

I feel deep sense of gratitude towards Mr. J.S.S. RAO, Principal Director, CAMPS (NPTI),

Mr.S.K.Chaudhary, Principal Director, CAMPS, Mrs. Indu Maheshwari, Dy. Director, NPTI

and Mrs. Manju Mam, Dy. Director, NPTI for arranging my internship and being a constant

source of motivation and guidance throughout the course of my internship.

I also extend my thanks to our course co-coordinator Mr. K.P.S.Parmar, Asst. Director, NPTI,

Mr. Amit Mishra, Asst. Director, NPTI and all the faculties and my batch mates in CAMPS

(NPTI), for their support and guidance throughout the course of internship.

Thank you all for being there for me always.

Satyanarayan Mahapatra

Page 3: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

iii

EXECUTIVE SUMMARY

The Indian power sector suffers from considerable supply shortages. The Government of India

(GoI) is addressing this problem both through a major new build programme (including certain

fiscal incentives for construction of larger and more efficient plant) and through Renovation and

Modernization (R&M) of existing coal fired plant. Around two-thirds of India‘s existing coal

fired plant capacity is owned by State Government utilities, but much of this is reported to be in

a poor condition, with low load factors and station heat rates of up to 4,000 kcal/kwh. R&M is

required to counteract the effects of deterioration of equipment due to aging, design deficiencies,

safety and pollution related factors. Poor maintenance and inefficient operation of plant also

raises the need for R&M. Technological obsolescence too lead to non-availability of spares,

leaving no other option but to upgrade. The GoI has taken several policy initiatives to support

R&M activity which is reflected in the Electricity Act 2003 and the National Tariff Policy.

However, despite several policy and programme initiatives by the GoI pace of R&M projects in

India remains extremely slow. Clearly, there are a number of barriers affecting the rate of

investment. The GoI has requested the World Bank and Global Environment Facility (GEF) to

demonstrate the viability of energy efficient R&M practices through pilot projects in three coal-

fired generation units across the states of Maharashtra (Koradi TPP), West Bengal (Bandel TPP)

and Haryana (Panipat TPP). During plant visits and discussions with stakeholders the barriers

and constraints to promotion of energy efficient R&M projects have been identified. These

discussions and analysis are summarized in section 3 and 4 of Chapter 2 of this report. A review

of international best practices that could apply to considerations in India is documented in

section 5 of Chapter 3. Based on these, a range of potential options was developed for successful

R&M implementation. These options were analyzed and refined using cost-benefit analysis

approach and subsequently discussed with the regulators, utilities, generators and policy makers.

This report provides guidance to plan and implement renovation & modernization (R&M)

projects of thermal power plants (TPPs) in India. More specifically, it is intended to provide

input into the development of more comprehensive set of guidelines, which may be developed by

the Central Electricity Authority (CEA), in collaboration with the World Bank for the successful

implementation of R&M projects during 12th five year plan.

Page 4: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

iv

LIST OF FIGURES

Figure 1.1 Business Sectors and Services of AF-Mercados

Figure 2.1 Chronological order of Policies Introduced for R&M

Figure 2.2 Research Approach towards the Project

Figure 3.1 R&M Process Cycle

Figure 3.2 Stages of Risk Identification and Mitigation Strategies

Figure 3.3 Risk Breakdown Structure (RBS)

Figure 3.4 Probabilities and Impact Matrix

Figure 3.5 Early Technical Surprises Identification Approach

Figure 3.6 Impact Assessment Matrixes

Figure 3.7 Mitigation Mechanism Table

Figure 4.1 Cost break up of plant equipment in total equipment cost

Figure 4.2 Cost break up of Services in total service cost

Figure4.3 Effect of Plant availability on Cash Inflows and Effect of efficiency on Cash Outflows

Figure 4.4 Generation addition due to reduced Heat rate and Effect of PLF and Capacity on Fuel

Requirement

Page 5: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

v

LIST OF TABLES

Table 1.1 Benefits associated with R&M of Torrent AEC Sabarmati ―D‖ Station, 110 MW

Table 3.1 Current Power Sector Market Scenario for R&M Implementation

Table 3.2: Tabulation of Technical Surprises

Table 4.1 Comparison of three level of project Assessment

Table 4.2 Risk-Responsibility matrix for R&M projects

Table 4.3 Energy Audit studies of thermal Power Plant at PTPS, Panipat

Table 4.4 Performance of Unit-1 PTPS Panipat Before and After R&M

Table 4.5 Overall Plant Performance of PTPS Panipat

Page 6: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

vi

ABBREVIATIONS

AHP Ash Handling Plant

BoP Balance of Plant

BTG Boiler-Turbine-Generator

CEA Central Electricity Authority

CER Carbon Emission Reduction

CDM Clean Development Mechanism

EA Energy Audit

EE R&M Energy Efficient Renovation and Modernization

GEF Global Environment Facility

GoI Government of India

GHG Greenhouse Gas

LROT Lease, Rehabilitate, Operate and Transfer

LE Life Extension

MW Mega Watt

MYT Multi Year Tariff

MHR Maximum Heat Rate

O&M Operation and Maintenance

OEM Original Equipment Manufacturer

PAT Performance, Achieve and Trade

PLF Plant Load Factor

R&M Renovation and Modernization

RLA Residual Life Assessment

UNFCCC United Nations Framework Convention on Climate Change

Page 7: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

vii

TABLE OF CONTENTS

DECLARATION…………………………………………………………………………………..i

ACKNOWLEDGEMENT .............................................................................................................. ii

EXECUTIVE SUMMARY ........................................................................................................... iii

LIST OF FIGURES ....................................................................................................................... iv

LIST OF TABLES .......................................................................................................................... v

ABBREVIATIONS ....................................................................................................................... vi

TABLE OF CONTENTS .............................................................................................................. vii

CHAPTER-1

INTRODUCTION

1.1. THERMAL POWER GENERATION IN INDIA ............................................................... 1

1.2. RENOVATION AND MODERNIZATION ....................................................................... 2

1.3. PROBLEM STATEMENT .................................................................................................. 3

1.4. OBJECTIVE ........................................................................................................................ 4

1.5. SCOPE OF WORK .............................................................................................................. 4

1.5.1. Study on Strategies to handle risks during R&M interventions: .................................. 4

1.5.2. Study on Strategies to handle technical surprises in R&M Interventions: ................... 5

1.5.3. Review of International best practices in R&M: .......................................................... 6

1.6. ORGANIZATION PROFILE .............................................................................................. 7

CHAPTER-2

LITERATURE SURVEY, POLICY AND RESEARCH METHODOLOGY

2.1. LITERATURE REVIEW .................................................................................................... 9

2.2. ANALYSIS ........................................................................................................................ 14

2.3. R&M POLICY, REGULATIONS AND PROGRAMME IN INDIA ............................... 14

2.3.1. MoP policy for R&M of existing stations-1995 ......................................................... 15

2.3.2. Electricity Act, 2003 ................................................................................................... 16

2.3.3. Energy Conservation Act, 2001 .................................................................................. 17

2.3.4. National Electricity Policy, 2005 ................................................................................ 17

2.3.5. National Tariff Policy, 2006 ....................................................................................... 18

Page 8: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

viii

2.3.6. Integrated Energy Policy, 2006 .................................................................................. 18

2.3.7. CERC (Terms and Conditions of Tariff) Regulations, 2009-14 ................................ 21

2.3.8. National Renovation & Modernization Programme: .................................................. 22

2.3.9. Accelerated Generation and Supply Programme (AG&SP) ....................................... 23

2.4. BARRIERS AND CONSTRAINTS TO R&M ................................................................. 24

2.5. RESEARCH METHODOLOGY....................................................................................... 25

2.5.1. REVIEW OF PAST EXPERIENCES ........................................................................ 25

2.5.2. REVIEW OF PROJECT DOCUMENTS ................................................................... 25

2.5.3. PLANT VISITS .......................................................................................................... 26

2.5.4. REVIEW OF INTERNATIONAL EXPERIENCE .................................................... 27

2.5.5. STAKEHOLDER CONSULTATION ....................................................................... 28

CHAPTER-3

RENOVATION & MODERNIZATION AND PROPOSED GUIDELINES

3.1. INTRODUCTION ............................................................................................................. 30

3.2. R&M PROJECT IMPLEMENTATION STRATEGIES ................................................... 30

3.3. R&M PROCESS CYCLE .................................................................................................. 35

3.3.1. ASSESSMENT STAGE ......................................................................................... 35

3.3.2. PLANNING STAGE .............................................................................................. 37

3.3.3. EXECUTION STAGE ............................................................................................ 38

3.3.4. CLOSURE STAGE ................................................................................................. 38

3.3.5. POST R&M STAGE ............................................................................................... 38

3.4. GUIDELINES FOR RISK IDENTIFICATION AND MITIGATION MEASURES ........ 39

3.4.1 RISK IDENTIFICATION AND CLASSIFICATION ................................................ 40

3.4.2 RISK ASSESSMENT ................................................................................................. 41

3.4.3 RISK MITIGATION .................................................................................................. 43

3.5 GUIDELINES FOR EARLY IDENTIFICATION OF POTENTIAL TECHNICAL

SURPRISES AND WAYS OF ADDRESSING THEM ............................................................... 45

3.6 REVIEW OF INTERNATIONAL BEST PRACTICES IN R&M .................................... 49

3.6.1 UKRAINE .................................................................................................................. 51

3.6.1.1 BACKGROUND OF UKRAINE POWER SECTOR ........................................ 51

3.6.1.2 SELECTION OF UNITS AND OBJECTIVES OF CARRYING OUT R&M .. 54

3.6.1.3 FINALISATION OF SCOPE OF WORK .......................................................... 57

Page 9: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

ix

3.6.1.4 PROCUREMENT PROCESS FOR SELECTION OF CONTRACTOR ........... 58

3.6.1.5 FUNDING MECHANISM OF R&M PROJECTS ............................................. 59

3.6.2 CHINA........................................................................................................................ 62

3.6.2.1 BACKGROUND OF CHINA POWER SECTOR.............................................. 62

3.6.2.2 LESSONS FROM R&M PROJECTS OF CHINA ............................................. 64

3.6.3 AUSTRALIA.............................................................................................................. 67

3.6.3.1 BACKGROUND OF AUSTRALIA POWER SECTOR ................................... 67

3.6.3.2 CONTROLS AND INCENTIVES FOR GENERATION THROUGH R&M ... 69

3.6.3.3 THE NATIONAL GREENHOUSE AND ENERGY REPORTING ACT ........ 69

3.6.3.4 GENERATOR EFFICIENCY STANDARDS.................................................... 70

3.6.3.5 FUNDING FOR LOW EMISSIONS TECHNOLOGY AND ABATEMENT .. 70

3.6.3.6 COAL21 Programme .......................................................................................... 71

3.6.3.7 GREENHOUSE GAS ABATEMENT PROGRAM (GGAP) ............................ 72

CHAPTER-4

RESULTS AND DISCUSSION

4.1. RESULTS .......................................................................................................................... 74

4.2. DISCUSSION .................................................................................................................... 79

4.3. RECOMMENDATIONS ................................................................................................... 80

CHAPTER-5

CONCLUSION AND FUTURE SCOPE OF WORK

5.1. CONCLUSION .................................................................................................................. 81

5.2. FUTURE SCOPE OF WORK ........................................................................................... 82

BIBLIOGRAPHY ......................................................................................................................... 83

ANNEXURES .............................................................................................................................. 87

Page 10: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

1

CHAPTER-1

INTRODUCTION

1.1. THERMAL POWER GENERATION IN INDIA

The Power Sector is imperative for sustained and inclusive economic growth. At the time of

independence, the total installed capacity in the power sector was 1362 MW of which steam

power plants contributed 756 MW. The installed generation capacity has since grown manifold.

The total installed capacity as on 30.06.2012 is 205340 MW of which Thermal power plants

contributed 116333 MW (Coal based) and 18903 MW (Gas based). Though the power sector in

India has witnessed a few success stories in the last 4-5 years, the road that lies ahead of us is

dotted with innumerable challenges that result from the gaps that exist between what is

planned versus what the power sector has been able to deliver. Coal fired generation in India

accounts for 56% of the total installed generation capacity and all future estimates of capacity

addition show that coal will continue to be the dominant fuel source despite the recent short

supply in the domestic coal. The envisaged coal based capacity for the 12th plan period is

62,695 MW i.e. 82.7% of the total proposed capacity addition (75,785 MW).In addition to the

above; there is considerable gap between demand and availability of power in the country in

spite of substantial increases in capacity addition in successive Five Year Plans. India faces

severe peak shortages (Peak Deficit of 11.1% and Energy deficit of 10.2% in 2011-12). With the

high cost of new installations, it is essential to maximize generation from the existing power

stations by restoring their rated capacity as, also, the efficiency of the power stations.

This will involve, necessarily, the replacement of the existing obsolete items of equipment with

those having higher efficiencies. While much of the 1970s (and older) vintage units have been or

need to be retired, many of the coal-fired power plants (NTPC as well as state utility owned

plants) that were commissioned on and before early 1980s are now due for rehabilitation and life

extension. Most of the smaller size units ranging from 30 MW to 100 MW are operating for

more than 30 years and are of non-reheat type with low design efficiency and are operating at

poor efficiency and very low plant load factors. Such units are being considered for retirement in

a phased manner. During the 11th Plan, 47 units amounting to 2,098 MW have already been

retired. The 210-500 MW sized Units have a better track record in terms of their plant load factor

Page 11: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

2

and availability. However, many of 200/210 MW units have completed or are near the end of

their normal operating life and require inputs for life extension and modernization to upgrade and

improve their performance level.

1.2. RENOVATION AND MODERNIZATION

It is essential to view the broad meaning of the term renovation & modernization (R&M) with

specific reference to thermal power plants (TPPs) before proposing specific guidelines to R&M

planning. R&M is defined broadly as set of activities which lead to improved performance and

reliability of an existing power generation facility. It is natural for the performance and reliability

(sometimes the output, too) of a power plant to decline over its operating life. Typically R&M

requires that the plant comes off line for longer than typically scheduled outages for maintenance

and repairs.

Many of the thermal power plants in India are not operating to their full potential. Also large

numbers of thermal units are old and outlived their normal life. Renovation and Modernization

(R&M) and Life Extension (LE) of existing old power stations have been recognized as an

effective option to achieve additional generation from existing units at low cost and short

gestation period. Besides generation improvement and life extension, other benefits achieved

from R&M / LE include improvement in availability, safety, reliability and environmental

emissions. Presently, a large number of 200/210 MW units have completed or are near

completion of their normal design life. The perspective R&M programme aims at extending their

operating life further and also upgrade their performance through Energy Efficient R&M.

In addition to lowering generation costs and having positive local and global environmental

effects, R&M has the added advantage of: (i) not involving land acquisition and resettlement of

people; (ii) being able to avail of existing coal, water supply, power transmission and other

facilities and linkages; and (iii) enhancing the effective utilization of scarce fuel resources. Table

below indicates a case study of benefits associated with the R&M of a thermal power plant.

Page 12: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

3

Table 1.1 Benefits associated with R&M of Torrent AEC Sabarmati “D” Station, 110 MW

Parameter Before R&M After R&M

Turbine Heat Rate 2200 kCal/kWh 2030 kCal/kWh

Output 105 MW 120 MW Plus

Availability after R&M 90.5% (3 years) 98% plus

Average PLF after R&M >83.5% (3 years) 87.5%

Uninterrupted Continuous

Run

- 186 days

Highest PLF - 101.2% (quarter average

post R&M)

Source: NTPC-Alstom Power Services Pvt. Ltd.

1.3. PROBLEM STATEMENT

India was able to keep pace with much needed Renovation and Modernization (R&M)

investments through the better part of the 7th, 8th and 9th Five-Year Plans, covering the fifteen

years until 2002. Since then though the R&M requirements have increased rapidly the

implementation of R&M schemes has slowed down. The 10th Plan (2002-2007) R&M target was

not fully met especially by the state generation utilities and nearly 8000 MW spilled over

into the 11th Plan, which now has an R&M requirement of nearly 27,000 MW (about a third

of the total installed coal-fired generation capacity in the country) for the 12th

Plan. But there are

many constraints and barriers within and beyond regulatory framework such as longer shut

downs of plants, procurement process, financial risk as well as various technical risks due to

which there is lack of interest among generating companies and equipment suppliers towards

R&M projects as compared to green field projects.

Page 13: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

4

1.4. OBJECTIVE

The main objective of the assignment is to review and access the risks associated with

implementation of R&M projects in thermal power stations in India and technical surprises

encountered while carrying out R&M works in thermal power stations in India. In this study a

detailed review of international best practices adopted by different entities in countries like

Ukraine, Romania, Australia, and China where R&M have been very successful in capacity

addition. Based on these reviews guidelines are to be prepared which after review of CEA will

be handy for the generating companies to carry out R&M works for effective mitigation of risks

and surprises in the R&M projects in thermal power stations.

1.5. SCOPE OF WORK

1.5.1. Study on Strategies to handle risks during R&M interventions:

a) Reviewing the past experiences of developing and implementing R&M with Life

Extension Projects. The detailed review of past R&M and Life Extension experiences

in Indian thermal power stations (list enclosed at Annexure-1) to identify the various

risks encountered while carrying out such R&M works.

b) Studying and analyzing the risks identified in detail and the consequences of such

risks on R&M projects. study and analyze the various risks associated with

development and implementation of R&M projects in technical, commercial,

contractual and market aspects including but not limited to following risks:

Policy and Regulatory Risks including recovery of Capital Cost and its impact on

post R&M Tariff;

Project Schedule and Time Over-run Risks along with its impact on Estimated

R&M Cost due to time over-run and provisions in contractual arrangements;

Cost Over-run Risks including change in scope and provisions in contractual

arrangements;

Page 14: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

5

Risks during execution phase including resources risks;

Post R&M Performance Risks and associated mitigation measures i.e. Liquidated

Damages, etc.

c) Conducting meetings and interaction with the concerned stakeholders such as State

Generating Stations, Central and State Electricity Regulatory Commissions,

Equipment Suppliers, Design Consultants, Funding Agencies and CEA to analyze the

identified risks.

d) Based on the above study and interactions with stakeholders, the Consultant shall

strategies are developed to mitigate the risks and prepare ―Guidelines for Risk

Identification and Mitigation in R&M Projects in Thermal Power Stations in India‖.

1.5.2. Study on Strategies to handle technical surprises in R&M Interventions:

a) Reviewing the past experiences of developing and implementing R&M with Life

Extension Projects the technical surprises encountered by the utilities while carrying

out the R&M works to be identified.

b) Interacting with State Generating Companies, various Suppliers and Design

Consultants to collect information on surprises experienced in R&M works of thermal

power stations and suggestions for addressing them. Based on the identified technical

surprises and experiences at thermal power stations in India strategies to be developed

to address and mitigate such technical surprises.

c) On the basis of this study and interaction with Suppliers and Design Consultants,

guidelines to be prepared for ―Early Identification of Potential Surprises in R&M

Projects and Ways of addressing them‖.

Page 15: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

6

1.5.3. Review of International best practices in R&M:

a) Detailed review of international best practices in developing and implementing the

R&M projects considering the energy efficiency and rehabilitation of thermal power

stations. The various best practices to be reviewed are as per details below:

i) Selection of Unit/Plant for R&M along with objectives of carrying out

R&M,

ii) Advanced technological options for EE R&M such as turbine up

gradation, efficient and environment friendly furnace-boilers, coal

utilization etc.

iii) Finalization of Scope of Work for R&M,

iv) Procurement Process for Selection of Consultant/Contractor,

v) Funding of R&M Projects,

vi) Cost Benefit Analysis,

vii) Implementation of R&M Projects including shut down time,

viii) Environmental safeguards,

ix) Measures for Guaranteed Performance post R&M.

b) Based on the above review, recommendation and suggestion for alternate cost-

effective options of R&M under Indian conditions with respect to the following

parameters:

i) Augmentation of project capacity,

ii) Technical feasibility,

iii) Cost effectiveness,

iv) Efficiency Improvement

Page 16: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

7

1.6. ORGANIZATION PROFILE

AF-Mercados EMI is a specialist consulting and transaction advisory firm based in Madrid, with

regional offices in Edinburgh, Rome, Ankara, Moscow, New Delhi and Beijing. In its nearly

20-year history, the company has evolved from a focus largely on energy sector

restructuring, policy and regulation to an integrated practice that supports sustainable

energy development through public and private initiatives, market-based mechanisms and

efficient management on national, regional and corporate levels. AF-Mercados EMI integrates

its in-depth experience and long history in the detailed development of electricity and gas

policy, utilities regulation and markets, with the needs of the global economy for reliable and

sustainable energy infrastructure.

We support governments to integrate low carbon energy policy objectives – the use of renewable

energies, energy efficiency and carbon-reductions strategies – and up to date incentive

mechanisms into a realistic regulation and sector operation. With the understanding of how

markets & policies affect investors, we also actively assist private firms to meet the ever-

growing demands for affordable electricity and natural gas supply, advising on financially solid

investment opportunities in infrastructure and supply.

Our approach combines innovation and experience, state-of-the- art techniques with practical,

tailor-made solutions to today s energy sector challenges. Our key people offer both, academic

qualification and the experience of having held top positions in government, regulatory

authorities and corporations. In addition our multinational, multicultural footprint and our

background of having worked in more than 60 countries around the world allow us to bring a

global perspective to local and regional issues.

In December 2010 AF-Mercados EMI became a member company of the ÅF Group, one of the

largest and fastest-growing consultancy businesses in Europe.

Page 17: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

8

VISION:

ÅF Mercados EMI, through its hands-on energy market experience, its highly qualified experts

and international footprint aims to:

Become the leading energy consultancy in South Europe

Expand its position in key emerging energy markets such as Russia, India, Turkey and

beyond

Further establishing its key advisory role among international institutions

Offer expert advice covering the full spectrum of energy consulting services to energy

businesses

MISSION:

Respond to our clients‟ needs in a changing world

Create value for our clients and for our future

Respect our values

SECTORS AND PRACTICES:

Figure 1.1 Business Sectors and Services of AF-Mercados

Page 18: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

9

CHAPTER-2

LITERATURE SURVEY, POLICY AND RESEARCH METHODOLOGY

2.1. LITERATURE REVIEW

Gill et al (1984) mentioned in his studies that with higher rated machines in service and capacity

of boiler and ancillary plant been installed to meet the peak demand. But the expansion coupled

with escalating fuel costs has imposed an increasingly urgent need to ensure that the plant is

operated and maintained as near to optimum conditions as possible. As per his findings at the

fuel prices that time in UK if a large unit is operated at an efficiency one percentage point lower

than design it will incur an additional fuel cost of over two million pounds per year. In his

studies he has suggested many technological aspects of boiler efficiency improvement, pollution

control methods, turbine performance and monitoring through heat consumption tests, economies

of various outages etc.

Sethi et al (1986) suggested improvement in energy efficiency during conversion from heat to

electricity is one of the potential areas for energy saving keeping in view of the high capital cost

in newer capacity addition. According to his opinion Energy audit will thus go a long way in

improving energy efficiency of existing plants. This requires check on fuel consumption,

auxiliary power consumption, heat rate and heat balance of thermal systems. There is need of

introducing of practice of periodic in house performance testing of existing plants for

determining fuel consumption, boiler efficiency and turbine heat rate.

Fuzikura et al (2000) in the study investigated methodological shortcomings in the impact

assessment practices employed by environmentally concerned groups for Calaca TPP in

Philippines and proposes improvements in project assessment methodology. The second thermal

power plant project constructed in the Philippine city of Calaca was examined. This post project

review found the assessment made by environmentally concerned groups to be inaccurate. The

following factors were identified as the probable causes of their erroneous estimates: the lack of

a holistic approach in the particular sector or regional assessment; misunderstandings about the

Page 19: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

10

environmental regulation of the Philippines; the imposition of the environmental standards of the

lending nation upon the borrower nation; excessively simplified assumptions about the second

project's cause-and-effect relationships; preoccupation with problems of the first power plant

project, particularly in confusing its soluble and insoluble aspects; which not only led to

erroneous estimates but also prevented them from examining the full range of alternative options.

Another lesson from the case was that pre-existing political bias in the minds of practitioners

tended to prevent them from examining the full range of alternative options in the event that

some adverse impact was predicted. Such political bias also had a tendency to lead to technically

erroneous methodologies in assessing project impact.

Bansal et al (2007) stated that the objective of R&M of power plants is generally to regain the

capacity lost due to plant aging, availability and include environmental performance and to

improve the reliability of plant. R&M of old power plants can deliver additional clean power,

cheaper and faster. But very less progress has been made in this area. The reason sited most often

is the shortage of funds. The State Electricity Boards (SEBs) are not in position to invest in

R&M even when institution like Power Finance Corporation (PFC) is willing to finance the

R&M projects at concessional rates. Most of the SEBs are yet to qualify even for minimum loan

requirements. The CEA has estimated that during ninth, tenth and eleventh five-year plans, an

investment of approximately Rs.225 million is required for R&M activities and live extension

services. The total expected capacity increase would be 25,000 MW [6]. New plant installation

would require over Rs.1000 million. Thus it is especially remarkably that these benefits can be

just derived by investing just 20 to 25% of the investment required for installing new power

plants. Additionally it will reduce the problems of finding new locations for power plants,

reduction of pollution of old power plants, etc. The scope of any R&M activities varies from

plant to plant. Its range may vary from a simple replacement of components to complete the

redesign of process. The specific scope of any R&M effort is generally determined after a

comprehensive study of all the critical components and auxiliaries. Such study is often termed as

residual life assessment (RLA). RLA exercise pinpoints the key weak points in the power

stations [7].Any major R&M drive involve some changes in the critical components of the power

station. These may include turbo generator, steam generator, boilers and its auxiliaries,

instrumentation and control (I&C) system, coal-handling plants, etc.

Page 20: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

11

Chikkatur et al (2007) stated that the performance of India‘s power sector can be improved by

improving the efficiency of coal-based power plant. It allows for increased consumer benefits

through cost reduction, while enhancing energy security and helping reduce local and global

pollution through more efficient coal use. A focus on supply-side efficiency also complements

other on-going efforts on end-use efficiency. The restructuring of the Indian electricity sector

have offered an important route to improving power plant efficiency, through regulatory

mechanisms that allow for an independent tariff setting process for bulk purchases of electricity

from generators. Current tariffs based on normative benchmarks for performance norms are

hobbled by information asymmetry (where regulators do not have access to detailed performance

data). A new incentive scheme had been proposed that gets around the asymmetry problem by

setting performance benchmarks based on actual efficiency data, rather than on a normative

basis. The scheme provides direct tariff-based incentives for efficiency improvements, while

benefiting consumers by reducing electricity costs in the long run. These proposals were also

useful for regulators in other countries to incorporate similar incentives for efficiency

improvement in power generation. Three types of proposals for incentive-based efficiency

improvement have been mentioned such as; revised performance benchmark, Relative

performance incentive and Self-improvement incentive (SII) that work concomitantly with the

MHR-based benchmark to improve heat rates, similar to the existing interlinking of PLF and UI

incentives for increasing generation. Thus, the combined effect of all three elements of the

proposal would result in improved efficiency of the system. The low generation efficiency is

usually blamed on a variety of technical and institutional factors such as poor quality of coal, bad

grid conditions, low PLF, degradation due to age, lack of proper operation and maintenance at

power plants, ownership patterns, regulatory framework, and tariff structure and incentives

(CEA, 2005; Khanna and Zilberman, 1999; Shukla et al., 2004). However, regardless of reason,

it is increasingly apparent that there will not be significant improvements in power-plant

efficiency unless there are either mandates or appropriate incentives for improving efficiency.

While the Ministry of Environment and Forests in India mandates the control of air, water and

solid waste pollution from power plants, it does not provide any guidelines for overall plant

efficiency. Efficiency of power plants is generally considered to be a technical operational issue

outside the purview of the environmental guidelines, despite the fact the improving efficiency of

power plants reduces coal use (per MWh generated) and thereby directly contributes to reduction

Page 21: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

12

of pollution. Rather, the management of operational parameters is left to electricity regulators.

To ensure high generation (i.e., high PLF), a PLF norm was set between 62.8% and 68.5% for

different power plants in 1992, wherein the full recovery of fixed charges was subject to plants

meeting the PLF norm. Furthermore, power plants were offered an incentive of Rs. 0.01/kWh for

every 1% increase in deemed PLF above the norm (Rao, 1999). The incentive was mainly

targeted at improving economy and efficiency of the generators, while encouraging private

investment into the electricity sector.

Avdiu et al (2008) stated that as per United Nation Interim Administration Mission in Kosovo-

UNMIK main activities in the KOSOVO energy sector consisted of repairing damaged facilities,

rehabilitating equipment that had been inadequately maintained during the years of conflict,

restoring production at thermal power stations and in coal mines. The most urgent tasks in power

sector for the Kosovo is rehabilitation of its thermal power plants and building new generating

capacity. In the paper he has presented energy situation in Kosovo and the dilemmas of

rehabilitation of old thermal power plant Kosovo A. Investigation regarding the feasibility of

rehabilitation of coal thermal power plant Kosovo A with five units have been done. Further in

the paper he also presented structural changes of power sector; main pieces of Kosovo legislation

regarding the interaction between energy conversion technologies and environment; evolution

trends of the pollution generated by thermal power units; difficulties encountered in the process

of alignment to the EU provisions. To ensure an acceptable extension of life for the operation of

the existing units of Kosovo A, within the frame of the EU standards for environment protection

related to the electrical generation (i.e. noxious flue gas contents such as carbon oxide, nitrogen

oxide, sulphur etc. and dust emission) it will be mandatory to analyse the incidence of coal

combustion as polluting factor and to replace or eventually repair existing electrostatic

precipitators to reduce dust emission. The paper also presents some rehabilitation aspects of

existing TPP A taking into account the technical assessment, economic cost-benefit evaluation,

with sensitivity analyses on variable parameters, and calculated the internal rate of return and

other representative economic criteria for each scenario.

Shrivastava et al (2011) in the study concluded that over use of coal input is one of the reasons

behind poor performance of inefficient power plants. It could increase emission of carbon

Page 22: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

13

dioxide too. Over use of auxiliary power and secondary fuel oil are other reasons behind

inefficiency. Study suggested that efficient utilization of resources will lead to higher efficiency

and lesser emissions of carbon dioxide. Better operational practices and regular maintenance are

recommended to reduce input resources. Results reveal that efficiency of small category power

plants is lower than medium and large category. It would be better to plan long term strategy to

replace old aged small power plants by large power plants of latest and efficient technology

(super critical technology).According to National Perspective Plan for R&M,(Central Electricity

Authority,2009c), some power plants have completed or about to complete their economic life.

Replacement of over aged power plants with latest technology power plants is also

recommended in order to improve overall efficiency. Renovation and modernization will be the

effective method to improve technical efficiency and to extend life of a power plant in moderate

investment. Periodic renovation and modernization is recommended to minimize coal

consumption, secondary fuel oil consumption and auxiliary power consumption. Results reveal

that performance of state government owned power plant is comparatively low than central and

private owned. There would also be scope to modify managerial measures to improve

performance of state owned power plants. Study recommends that like central owned power

plants, state owned should also introduce maintenance planning department (if not introduced till

now), headed by a senior officer. This department will be responsible to organize daily, monthly

and annual review meetings of departmental heads to improve coordination. Results indicate that

performance of private owned power plant is slightly better than its counterpart of central

government owned. Mild managerial adjustment could improve performance of central owned

power plants.

Rai et al (2012) suggested that theoretically maximum achievable thermal efficiency by a power

plant by using the Rankine cycle regardless of the technologies used is approximately 63 % but

due to thermodynamic limitations and energy losses that cannot be recovered. Existing coal fired

Power plant using the Rankine cycle operates well below this limit. If the energy input to the

cycle is kept constant, increasing the pressures and temperatures for the water-steam cycle will

increase the output and the overall efficiency. However, a practical limitation to the higher

pressure and temperatures that can be achieved in a boiler is the availability of boiler materials

Page 23: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

14

that can withstand these increased conditions over an acceptable service life. To improve the

operating efficiency of the coal-fired power plants and thereby significantly reduce CO2

emissions various recommendations on advanced technological options like Combustion

Management and Flue Gas Exhaust temperature Optimization, Cooling System Heat Loss

Recovery, Flue Gas Heat Recovery, Low-Grade Coal Drying, Intelligent Soot Blowers

Optimization etc. The development and demonstration of these technologies that target higher

efficiency at coal-fired power plants should be accelerated. For example, advanced materials,

coal cleaning and drying, co-generation of heat and power, and more efficient CO2 capture

technologies all need to be deployed. In addition to these efficiency improvements, the

deployment of CO2capture and storage (CCS) technology is vital.

2.2. ANALYSIS

Although a lot of research has been done and many techniques are proposed by eminent people

for R&M implementation but still there is no standard set of guidelines available in India for

reduction of barriers to R&M projects in thermal power plants. Hence in order to achieve the 12th

plan target of capacity addition through R&M, I have proposed a set of guidelines through my

research work based on best practises followed by other countries. During my plant visits with

the consultation of utilities and various stakeholders the existing barriers and constraints has

been identified and the measures to mitigate them have been suggested.

2.3. R&M POLICY, REGULATIONS AND PROGRAMME IN INDIA

R&M of generation utilities were given prime importance by the government to improve the

operational performance and overall efficiency. Consequently, GoI initiated a centrally

sponsored R&M programme in a structured manner in 1984. However, with some initial success,

the programme did not progress as per schedule mainly due to non-availability of funds and poor

financial condition of State Electricity Board (SEBs). As a result, importance of private

investment was felt in order to address the financial constraints in R&M implementation. With

this consideration, GoI announced Independent Power Producer (IPP) policy in 1991. The policy

Page 24: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

15

brought much needed private investment in the sector and a new avenue of financing of R&M of

power plants got opened up. In order to mobilize the private investment, Ministry of Power

(MoP) came out with a policy framework for private sector participation in R&M of existing

power stations. MoP policy was followed by various other provisions represented in a

chronological order as follows:

Figure 2.1 Chronological order of Policies Introduced for R&M

2.3.1. MoP policy for R&M of existing stations-1995

The policy introduced on October, 1995, laid out the framework for private sector participation

in R&M of existing power stations. The policy advocates private sector participation in R&M for

the following reasons:

Relative economics: Private sector involvement would result participation by larger number of

players, thereby increasing competition in choice of supply and making it cost effective.

Risks: In privatized R&M, risks associated with time and cost overruns, plans and design,

operational risks and shortfall in realizing target improvement would be transferred to the private

sector.

Financing other priority areas: Private sector involvement will result in generation of

resources and will reduce calls on limited public sector finances. The public sector finances

Page 25: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

16

could then be used to finance other priority areas such as system up gradation, improvement in

metering etc.

Resulting price of energy: The higher cost of private financing will find reflection in the

resulting energy prices. By providing a closer reflection of real current costs, competitively

derived prices of privatized R&M, would help eliminate hidden subsidies that are detrimental to

effective functioning. The policy recognized that ―for most SEBs, the alternative of traditional

financing no longer exists; the choice for them is to postpone R&M for some- perhaps for all-

times (foregoing the benefits correspondingly) or to draft private investment from among the

different forms available‖. However, the options identified are only illustrative and the choice

and initiative would lie with the states. The remaining aspects of the policy document set out

issues related to payment security, contracts &agreements and the procedure for implementation

of R&M through competitive bidding.

2.3.2. Electricity Act, 2003

The EA, 2003 is the primary legislative instrument which governs the electricity supply industry

in India. The salient provisions of the act on R&M are:

As per section 73(m), it is the duty of CEA to give advice to generating companies on

matters that enable them to operate in ―an improved manner‖.

As per section 79(2) and 86(2) (i), it is the duty of regulatory commission to be guided by

the encouragement of competition, efficiency, the economical use of resources, improved

performance and the need to reward efficiency in performance.

From the above provisions, it is clear that the Act provides a framework under which the

central and state level bodies are expected to take account of measures that promote

efficiency through improved performance. This includes R&M measures which reward

generators to improve efficiency by providing them suitable incentives.

Page 26: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

17

2.3.3. Energy Conservation Act, 2001

Similar to EA 2003, the Energy Conservation Act, 2001 contain provisions related to the

promotion, efficient use and consumption of energy. It empowers the Central Government to

force inefficient generation utilities to take ―appropriate measures‖ to increase energy conversion

efficiency in their operations.

2.3.4. National Electricity Policy, 2005

National Electricity Policy is determined by the GoI, in accordance with the provisions of the

Electricity Act and in consultation with the various stakeholders of the electricity industry.

The salient provisions of NEP related to R&M are:

R&M for achieving higher efficiency levels needs to be pursued vigorously and all

existing generation capacity should be brought to minimum acceptable standards.

For projects performing below acceptable standards, R&M should be undertaken as per

well-defined plans featuring necessary cost benefit analysis. If economic operation does

not appear feasible through R&M, then there may be no alternative to closure of such

plants as the last resort.

In case of plants with poor O&M record and persisting operational problems, alternative

strategies including change in management may need to be considered so as to improve

efficiency to acceptable levels of these power stations.

The NEP imposes somewhat stronger demands in relation to R&M than the Electricity

Act or Energy Conservation Act, since it clearly specifies that R&M for achieving higher

efficiency levels needs to be pursued vigorously.

Page 27: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

18

2.3.5. National Tariff Policy, 2006

The National Tariff Policy came out in 2006 in accordance with the provisions of EA 2003. The

salient provisions of the policy regarding R&M are:

R&M for higher efficiency levels needs to be encouraged, but it must not include

periodic overhauls.

Consistent with the overall objectives, a Multi-Year Tariff (MYT) framework may be

prescribed which should cover capital investments necessary for R&M and an incentive

framework to share the benefits of efficiency improvement between the utilities and the

beneficiaries with reference to revised and specific performance norms to be fixed by the

appropriate commission.

Appropriate regulatory costs required for pre-determined efficiency gains and/or for

sustenance of high level performance would need to be assessed by the appropriate

regulatory commission.

Just like NEP, NTP also recognized the role of R&M in the generation sector. However,

NTP suggested a overall regulatory framework for functioning and promotion of R&M

activities.

2.3.6. Integrated Energy Policy, 2006

Integrated Energy Policy came out in 2006 with an overall objective for sustainable growth with

energy security and improved efficiency. The salient provisions of IEP, 2006 related to R&M

are:

Rehabilitation of existing thermal stations could raise capacity at least cost in the short-

term and must be taken urgently.

Incentives for increasing the energy efficiency of thermal power stations need to be

provided through appropriate pricing and policy interventions.

Page 28: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

19

IEP also specified the importance of R&M and recognized the fact of energy efficiency

as the most important virtual energy supply source over the next

Guidelines for R&M/LE works for power generating stations-2009

With a view to expedite the R&M/ LE works during the Xth plan period, GoI, MoP issued

guidelines in Feb, 2004. The guidelines provided a framework to be followed if generators are to

get benefit from debt financing from the PFC (Power Finance Corporation) at an interest rate

subsidy of 3-4 percent.

The guidelines outlined three main categories of plant that can be considered for R&M and Life

Extension:

i) Plants that has been under long shut down or that has a very low level of performance i.e.

PLF below 40 percent - Decision to revive/scrap has to be taken by the consultant.

ii) Plants that do not operate to a desired level of performance i.e. having PLF between 40-

60 percent - Performance of these units is to be improved by taking R&M and LE

measures.

iii) Plants operating at satisfactory levels of performance but where performance can be

further improved/ sustained (PLF above 60 percent) - Efforts need to be made to further

improve the performance and sustain high levels of performance. Latest O&M practices

and RLA studies should be taken up to reduce cost of generation as well as to extend the

life of the units.

However, a need was felt to revise the guidelines due to:

Delays in achieving desired completion targets.

Constraints in supply of materials resulting in time/ cost overrun.

Large number of units of 200 MW capacities is becoming due for R&M and LE Works

Shift in objective from ‗generation maximization‘ to performance optimization

Page 29: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

20

Consequently, the guidelines were revised in 2009 by MoP for R&M/LE works for power

generating stations.

Salient features of new guidelines:

The new guidelines laid down the framework for the scope and the implementation of

R&M and LE&U schemes. Moreover, it specified the cost estimates along with cost-

benefit analysis.

Lastly, similar to the MoP policy on R&M, it specified same three options for

participation of private sector in LE&U programme.

Methodology of implementation of R&M and LE&U schemes

R&M works

The guidelines recognized that power utilities are adopting two main variants in implementation

of R&M programme which are:

A rolling plan in which the activities/ schemes identified for R&M are implemented in

phases depending on the availability of particular system/ unit shutdown.

A comprehensive scheme is implemented in a single stretch and taking unit‘s planned

shutdown after ensuring all inputs and supply of materials.

The methodology for implementation is to be decided by the utility. However the option of

comprehensive scheme is preferable due to well definable and quantifiable benefits.

LE&U works

In order to facilitate the implementation of LE&U works, utilities may appoint a reputed

consultant for rapid life assessment, condition assessment, energy auditing, performance

tests, environmental studies, preparation of DPR etc.

Page 30: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

21

Based on DPR, a detailed technical specification & contract document may be prepared

which includes detailed scope of work, responsibilities to be shared with regard to

implementation of LE&U works and time frame for implementation of activities.

Monitoring the progress of implementation of R&M/LE schemes -R&M/LE&U schemes

of INR 100 crore and above shall be monitored by MoP/ CEA.

Physical and financial progress report in prescribed format shall be submitted to CEA on

regularly basis.

Cost estimates

The cost of LE&U shall not exceed 50 percent of the EPC cost of a new generating unit

of indigenous origin (such as BHEL-Bharat Heavy Electricals Limited). However, a

detailed study should be carried out to ensure its techno-economic viability.

In cases, where the cost is estimated to exceed the above limits, a detailed cost

comparison & cost benefit analysis shall be carried out between the R& M/ LE work and

that of setting up a new green field plant.

2.3.7. CERC (Terms and Conditions of Tariff) Regulations, 2009-14

As per the CERC tariff regulations, provisions related to R&M are:

The generating company or the transmission licensee, for meeting the expenditure on R&M for

the purpose of extension of life beyond the useful life of the associated facility, shall make an

application before the Commission for approval of the proposal. The application for the approval

should be accompanied with a Detailed Project Report (DPR).

The approval shall be granted after due consideration of reasonableness of the cost estimates,

financing plan, schedule of completion, interest during construction, use of efficient technology,

cost-benefit analysis, and such other factors as may be considered relevant by the Commission.

Page 31: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

22

Any expenditure incurred or projected to be incurred and admitted by the Commission after

prudence check based on the estimates of R&M expenditure and life extension, and after

deducting the accumulated depreciation already recovered from the original project cost, shall

form the basis for determination of tariff.

For a coal-based/ lignite fired thermal generating station, the generating company, may, in its

discretion, avail of a ‗special allowance‘ in accordance with the norms as compensation for

meeting the requirement of expenses including R&M beyond the useful life of the generating

station or a unit thereof. In such an event revision of the capital cost shall not be considered and

the applicable operational norms shall not be relaxed but the special allowance shall be included

in the annual fixed cost.

The allowed special allowance would be @ INR 5 lakh per MW per annum in 2009-10 and

thereafter escalated @ 5.72 percent every year during the tariff period 2009-14, unit-wise from

the next financial year from the respective date of the completion of useful life with reference to

the date of commercial operation of the respective unit of the generating station. Moreover, no

such allowance shall be applicable for a generating station or unit for which R&M has been

undertaken and the expenditure has been admitted by the Commission before commencement of

these regulations, or for a generating station or unit which is in a depleted condition or operating

under relaxed operational and performance norms.

2.3.8. National Renovation & Modernization Programme:

In order to improve performance of underperforming thermal power stations in the country, GoI

initiated National Renovation and Modernization Programme in 1984. Financial assistance for

implementing R&M works was provided by GoI. In the first phase, the programme covered 34

thermal power stations involving 163 thermal units. The first phase was successfully completed

in the year 1992 and an additional generation of 10,000 MU annum was achieved.

The second phase R&M programme was taken up in the year 1990-91. Loan assistance was

provided to the SEBs through PFC for R&M works. However, this programme could not

Page 32: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

23

progress as per schedule mainly due to non-availability of funds and poor financial condition of

SEBs. However, the programme continued albeit in a different form subsequently during IXth

and Xth plan periods with resultant improved performance from thermal generating units. The

programme is being further continued in the XIth plan and future FYPs.

2.3.9. Accelerated Generation and Supply Programme (AG&SP)

The Accelerated Generation and Supply Programme (AG&SP) were launched in the IXth plan

and were extended to the Xth FYP. The programme was launched with an objective of

accelerating power supply to consumers through implementation of R&M and LE extension

schemes and new generation projects. PFC was identified as an agency to provide subsidized

financing at an interest subsidy under the scheme is up to 3 percent and the subsidy for north-

eastern projects in up to 4 percent. This interest subsidy is passed on to the utilities over the life

of the loans.

Under AG&SP, during IXth plan, MoP has released INR 1,476 crore to PFC for passing it on to

eligible borrowers as per the programme. During Xth plan, funds of INR 1500 crore was

provided for the programme. Parallel to this programme, Accelerated Power Development

Programme for thermal and hydro power stations was launched in 2000-01. Under this

programme, R&M/ LE/ Uprating of old power plants were taken up. The programme provided

funds in the form of 50 percent grant and 50 percent loan. However, from Xth plan onwards, the

programme was discontinued and all funding was brought under AG&SP.

Page 33: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

24

2.4. BARRIERS AND CONSTRAINTS TO R&M

In spite of all research work and policies undertaken R&M is still not successful in India as far as

10th

and 11th

plan is concerned. Hence CEA decided to appoint independent consultant for

identification of major barriers and prepare guidelines for implementation of R&M projects in

12th

plan for which 27,000 MW of capacity addition has been planned. The World Bank is

providing technical assistance of US $ 1.1 million as a part of GEF grant to CEA under ―Coal

Fired Generation Rehabilitation Project-India‖ for addressing the barriers to Energy Efficient

R&M of coal fired generating units in India. The project is being implemented by CEA through

appointment of consultant (AF-Mercados) for carrying out the studies. As a part of this project

team I have done detailed research for identification of barriers and constraints to R&M and also

prepared guidelines to mitigate the problems faced by various utilities. Through literature survey

and studies based on past experiences the following barriers have been identified:

R&M require long shutdowns: 4-5 months at the best that can go even up to 8-12 months

Unpredictability of shutdown duration due to technical surprises, non-availability of

spares, changes in scopes after opening the equipment etc.

Shutdowns for residual life assessments are also sometimes difficult to secure

R&M requires greater institutional involvement compared to green-field projects, while

adding less capacity.

Institutional capacities of utilities to prepare and implement projects is limited

Design, Procurement and Implementation challenges

Limited Supplier Capacity and interest

Risks and Rewards are not balanced

Poor O&M practices of Utilities in many states

Financial Constraints

Challenges in meeting National Safeguard Norms

Compliance with Environmental norms

Page 34: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

25

2.5. RESEARCH METHODOLOGY

The graphic below highlights the overall approach proposed for undertaking various tasks.

The following sections detail out the specific approach proposed to be adopted for various

tasks of the assignment.

Figure 2.2 Research Approach towards the Project

2.5.1. REVIEW OF PAST EXPERIENCES

In order to understand the issues related to R&M project, the detailed research on past

experiences of the stakeholders in undertaking R&M for their plants has been undertaken.

This will involve consultation with the stakeholders to understand their concerns, issues, as

well as factors that influenced their decision to go ahead with R&M. Review of past

experiences will provide rich information base about the root underlying causes that motivate

utilities to go ahead with R&M of their thermal power plants.

2.5.2. REVIEW OF PROJECT DOCUMENTS

Review of project documents, plans, assumptions, contacts and other information will help in

reviewing the inherent risks and barriers inhibiting successful R&M Project. The quality of

plans as well as consistency between these plans and project requirements can be a good

indicator to the possible inherent R&M risks. This will include R&M Project DPRs of the

utilities, Design Consultant‘s reports on RLA, Energy Audits and Complete Plant

Assessment, Performance Test Reports, Presentations by different stakeholders that were

Page 35: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

26

conducted Post R&M as Experience/Knowledge sharing to its employees, Reports by World

Bank/GEF/USAID on R&M Project, Bids and Tender Documents of R&M Projects. It is

expected that the counter-part team at the CEA will facilitate AF-Mercados EMI team‟s

access to such documents.

2.5.3. PLANT VISITS

Thermal power plants visits (list provided in annexure-2 ) have been done as part of research

methodology that have undergone R&M in order to understand the ground realities and the

experiences of the utility in evaluating, planning, tendering and executing R&M. Also,

specific plants would be chosen for which reasonable time has elapsed since R&M was

undertaken to understand whether the performance outputs were in conformance to the plant

outputs or deviations were observed. Further, issues like whether the plants are able to

maintain their performance or are there issues associated with the same. In case of deviations,

reasons for deviations will also be discussed and analyzed. The plant visit is proposed to be

undertaken in two phases:

PHASE-1: During the first phase (to be performed at early stages of the assignment) visits

will be undertaken for diagnostic study to understand the issues, concerns and the risks faced

PHASE-2: During the second phase (to be performed at later stages of the assignment) visits

will be undertaken to validate the findings derived from the study.Selection of plants for the

visits shall be done to ensure that a representative sample has been considered. The criteria

proposed for selection is as follows:

History of R&M – Whether the plants has undertaken R&M previously or not. Efforts will

be made to select plant in both categories.

Plant Capacity – Plants with different unit size (MW range) will be selected to ensure that

specific issues with plants of certain MW range are captured.

Page 36: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

27

Equipment Supplier and Executing Agencies - Majority of the old plants run on equipment

supplied by the BHEL; however there could be other plants as well. Efforts will be made to

select plants in both the categories.

Geographical Coverage – To ensure that sample is geographically representative.

Objective of R&M for the selected plants: Specific purposes for which R&M decisions was

considered.

In undertaking the above three tasks specific facilitation and support would be required from

the CEA. This includes:

Providing authorization letters for visiting the plants and utilities of the state for

consultation purposes

Obtaining relevant documents including project plans, contracts, tender documents

(RfQ, RFP etc.) of various plants that have executed R&M.

2.5.4. REVIEW OF INTERNATIONAL EXPERIENCE

Having understood the issues and concerns faced in planning and executing R&M projects at

the national level, state utility level and the plant level (in the previous steps), AF-Mercados

EMI will undertake a detailed review of international experience in R&M. The review in

particular will aim to undertake process benchmarking covering issues such as:

a) Mechanism of selection of Unit/Plant for R&M along with objectives of carrying out

R&M

b) Advanced technological options considered for EE R&M such as turbine up-

gradation, efficient and environment friendly furnace-boilers, coal utilization etc

c) Process of Finalization of Scope of Work for R&M

d) Procurement Process for Selection of Consultant/Contractor

e) Mechanism of funding of R&M Projects

f) Methodology adopted for Cost Benefit Analysis

g) Process of implementation of R&M Projects including shut down time

Page 37: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

28

h) Environmental safeguards

i) Measures for Guaranteed Performance post R&M

Chapter-3 provides more a detailed description of the approach proposed to be undertaken

for review of international experience.

2.5.5. STAKEHOLDER CONSULTATION

Effective Consultation Methodology that is proposed to be deployed for the assignment

which will be invaluable towards development of practical solutions that stand the test of

robust scrutiny. This research includes variety of techniques such as personal interview and

focus group discussions for similar assignments. The core focus of such consultation is to

elicit a set of qualitative and quantitative outputs from such consultation to obtain a set of

actionable outputs. For this, issues are categorized and thereafter specific views are obtained

on those parameters in a manner that aids statistical analysis which in turn aids decision.

Such statistical analysis backed by qualitative results becomes the basis of refinement of the

base propositions made to stakeholders. This sub-task will involve stakeholder consultation

with key experts and relevant entities in the sector. The purpose of the stakeholder

consultation would be to:

Obtain perspectives

Validate findings

Sharing of experiences and case studies

The methodology to the stakeholder consultation will include:

Identification of critical stakeholder groups: This step will involve the key stakeholder

group at various levels. The graphic below indicates the critical stakeholder groups for

consultation. Conducting meetings and interaction with the concerned stakeholders such as

State Generating Stations, Central and State Electricity Regulatory Commissions, Equipment

Suppliers, Design Consultants, Funding Agencies and CEA to analyze the identified risks.

Page 38: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

29

List of identified stakeholders with whom we will hold meetings and discuss about R&M are

in Annexure 3 and indicative questions to them are also in Annexure 4.

Method of Consultation: The approach and technique adopted for consultation with various

stakeholder groups may differ from entity to entity. Broadly, the three methods extensively

used as part of various assignments include:

Surveys through structured questionnaires

One-on-one meetings

Multi-stakeholder consultations

At various stages of the assignment, the above three methods will be adopted to capture the

views of stakeholders. Box below indicates a snapshot of questionnaire developed as part of

study undertaken to review the policy aspects of hydro power development for the Finance

Commission, Government of India.

Collation of Responses and its analysis (Cross-Tabulation): Once the responses from

various stakeholder groups are in place, the responses are collated and analyzed. Responses

and outcomes of all consultations will be documented and recorded for the purpose of

reference.

Expert validation: Validation of responses received from various stakeholders is extremely

crucial to ensure meaningful outcomes. This is done through discussion with a select

stakeholder group and the Client. Box below indicates approach to the consultation process.

Identification of Issues: This step will involve documentation and listing of key issues that

are required to be address during the stakeholder discussion. Issues for stakeholders may

differ and hence its identification at early stages is very important. Based on the above study

and interactions with stakeholders, strategies to mitigate the barriers and prepare detailed set

of ―Study on Reduction of Barriers to R&M Interventions in Thermal Power Stations in

India‖.

Page 39: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

30

CHAPTER-3

RENOVATION & MODERNIZATION AND PROPOSED GUIDELINES

3.1. INTRODUCTION

Renovation and modernization gained prominence in India since mid-1970. The government

came out with the national perspective plan for R&M/LE of thermal power plant in order to

emphasize the importance of and to encourage further investments in this segment. An

organization which plans to undertake R&M of its existing plant shall go through the R&M

process. The process starts off with corporate planning which is followed by R&M planning,

implementation and monitoring. The preceding chapter explains in depth the planning and

development stages of the R&M process. This chapter delineates further the implementation and

monitoring phase of the R&M process. First the current R& M practices has been explained post

reform era then a new set of schemes have been proposed in order to reduce the barriers and

constraints to R&M. Subsequently guidelines for risk identification and mitigation measures have

been explained in detail. The approach for identification of potential technical surprises has been

given so that the appropriate measures can be taken to avoid further delays in commissioning. A

detailed review of countries like Ukraine, China and Australia has been done to derive the best

practices followed by them for successful R&M implementation.

3.2. R&M PROJECT IMPLEMENTATION STRATEGIES

Ever since the enactment of Electricity Act 2003, there are several changes that have occurred in

the electricity market and electricity supply industry. The table below maps out the changes and

its implications for R&M project in India. The implementation strategies can be developed based

on the current power market scenario and stakeholder consultation.

Page 40: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

31

Table 3.1 Current Power Sector Market Scenario for R&M Implementation

Characteristics /

Market Changes

Before

enactment of

the EA 2003

Current

Scenario

Implementation for R&M

Presence of Power

Markets and

Competition

Absent Present

As a result of emergence of power

markets, alternate procurement

avenues are now available to the

state utilities to prevent outages

when plants undergo R&M

Increased focus on efficiency

improvement owing to competitive

procurement of power and

possibility of extension of the

framework to state generating

companies in the near future

Degree of Private

Sector Participation Low High

Increased private sector

participation across the value

chain in the electricity supply

industry has resulted in better

response, lower lead-time and risk

sharing.

Equipment Vendors

Base Small Large

Open market policy of GoI and

increasing capacity expansion has

attracted many international

players, rubbing shoulder against

market dominant players like

BHEL by providing comparable

technological competencies and

services.

Alongside, the equipment market

has also seen emergence of several

domestic players as well, leading

to a much more diversified

equipment vendor base.

Page 41: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

32

Focus on

Optimization Lower Higher

One of the strategies of Perform

Achieve & Trade (PAT) Scheme

of the Bureau of Energy Efficiency

(BEE) is aimed at enhancing

energy efficiency in existing

power plants and has set power

sector as one of the Designated

Consumers (DC). DCs have to

achieve notified reduction in fuel

consumption (kcal/kWh) by 2014-

15.

Along with the above there are

several generation optimization

products/modules that many new

generating plants or plants

undergoing refurbishment are

opting for to increase the overall

plant output and increase process

efficiency.

Market framework

for GHG emission

reduction and

Environmental

Compliance

Absent Present

With power sector contributing

40% to carbon emissions of India,

R&M with short gestation time

can be short and medium term

strategy to achieve National

Action Plan on Climate Change.

Although at present the

contribution of R&M towards

GHG mitigation is small, the

capabilities promise the flexibility

for responding to emerging

economic, environmental and

sustainable development needs.

Page 42: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

33

Each of the points mentioned in the table is explained below through a strategic approach:

Presence of Power Markets has enabled the state utilities to go for alternative procurement

strategies like procuring power competitively from Trader and Power Exchanges in the

country i.e., Indian Energy Exchange (IEX) and Power Exchange of India (PXIL) in order

to negate long outages during R&M Project.

In addition to the above, Power Market overtime has now become much more

Competitive. As per the National Tariff Policy, the procurement of power by distribution

licensees has to be made through competitive bidding and thus arrangement of power

supply both in the short and medium term is no longer a constraint. Soon Central / State

public sector companies are also expected to compete with private sector to supply power

to the distribution companies through competitive bidding. The above clearly requires the

state utilities/generating plants to gear up to meet the improved efficiency requirement that

comes along with competitive conditions.

Coal Constraint No Yes

At present, acute coal shortage

looms large on the sector.

Domestic coal shortage was never

envisaged in any of the previous

plan period; however the sector

today has suddenly awakened up

to this reality.

In such extreme coal supply

constrained scenario, focus on

available coal being used in most

efficient form by the market

participants is high.

The above trend supports R&M as

energy efficient R&M results in

lowering specific coal

consumption of the plant and

hence promotes optimal

utilization.

Page 43: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

34

Energy Efficient R&M also allows suitable performance optimization of the plant and

helps in reducing the Station Heat Rate. This traditionally has not been the focus (most of

the old plants that have undergone R&M have focused on life extension or improvement

in plant availability).

Improvement in efficiency and quality of supply allows reduction of Variable Cost of the

plant and thus helps the plant be in higher position in State Merit Order Dispatch. Further

going deeper, EE R&M allows exploration of newer technologies in Coal Blending for

reducing the cost of generation.

Higher Degree of Private Sector Participation across the entire energy sector value chain

has enabled streamlined processes for quicker response, lower lead time and efficient

delivery. R&M projects traditionally beleaguered with delays due to poor project

management, active participation of private parties from the beginning of R&M process as

design consultants, in bidding and procurement of materials, etc. can reduce the

unnecessary delays.

Increase of Equipment Vendors Base since GoI opened up the power sector to competition

has allowed bringing in market innovations and advanced technological options to Indian

Power Sector. The shift in focus from ―Generation Maximization‖ to ―Generation

Optimization‖ with efficiency enhancement, recent global forays of companies and

strategic alliances with Indian vendors can provide quicker and more reliable supply of

diverse systems and equipments to counteract the shortages and delays in R&M Project.

In addition, emergence of several domestic manufacturers has also led to diversification of

equipment supplier vendor database. GoI‘s various initiatives to focus on Optimization in

Energy sector by creating nodal agency Bureau of Energy Efficiency has resulted in

handsome savings by implementing Perform, Achieve & Trade (PAT) Scheme. Under this

scheme, power utilities can purchase Energy Saving Certificates (ESCerts) by reducing

their specific energy consumption and trade in Power Exchanges or pay penalties.

Due to the predominance of fossil fuels in the generation mix, there are large negative

environmental externalities caused by electricity generation. Market framework for GHG

emission reduction and Environmental Compliance promotes energy efficient drivers like

R&M intervention that lead to sustainability of the energy –environment system. R&M

Page 44: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

35

Program contributes to global sustainability through GHG mitigation and it conforms to

national priorities of development of local capacities and infrastructure.

Coal Constraint faced by power project developers in India is adding significantly to the

woes of the power sector, given it is already grappling with challenges of land acquisition

and environmental clearances.

Energy Efficient R&M Intervention mitigates the problem to an extent as it allows the

utility to operate the plant at its designed parameters with lower specific coal consumption

and doesn‘t require land acquisition and environmental clearances. State utilities and

private players may also think of options like LROT (Lease, Rehabilitate, Operate and

Transfer), Sale of Plant and Joint venture.

3.3. R&M PROCESS CYCLE

Having understood the market context of the R&M, it is essential now to understand various sub-

steps of the R&M, the activities that are undertaken at each step and the stakeholders involved

during various stages of the R&M process cycle.

3.3.1. ASSESSMENT STAGE

Step 1: Most of the equipment of a power plant is subjected to high temperature and pressure and

are designed for fatigue life of about 25-30 years of operation. However, differences in the

operational practices from design operation environment may lead to premature equipment failure

or lower than expected output. This calls for systematic evaluation of the plant to understand the

available options and decide on the most optimal option. In the context of R&M these are:

Plant retirement

Maintain and operate for extended time and retire subsequently

Capital Overhaul and refurbishment

R&M and Life Extension (LE)

R&M, LE and Up-rating

Page 45: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

36

Fig

ure

3.1

R&

M P

RO

CE

SS

CY

CL

E

Page 46: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

37

The above decision is supported by undertaking various technical studies (often performed

through the Design Consultants employed by the State Utility). These tests include:

Residual Life Assessment

Complete Condition Assessment

Energy Audit

Past History of Plant, O&M Practices

The outputs of the above tests are then utilized for decision making and selection of optimal

option among those listed above.

3.3.2. PLANNING STAGE

Assuming that the decision of the utility is to go for R&M of the plant, the next exercise is to plan

for executing the R&M of the plant. This involves the following steps:

Step 2: The scope of the R&M Project is prepared after detailed assessment of the condition of

the plant components and evaluation of technical alternatives and constraints. The aim here is

generally to define scope in as precise terms as possible however often changes and surprises

occur when the plant is actually opened up for implementing the R&M. The utility often is faced

with the issue of level of detailing that is required at the planning stage itself vs. the time and

resources that are available to be committed for achieving marginal improvement in the scope

assessment exercise.

Step 3: Next step after the finalization of the scope of work involves evaluation of Cost-Benefit

Analysis to fulfill the objectives of the scope. Cost benefit analysis is done after preparation of

budget and evaluating various sources of fund.

Step 4: After the scope of the project is finalized, the utility decides on following tasks prior to

initiating bidding process:

Development of design specification and proposal package

Determination of procurement/bidding strategy

Approval of the R&M Plan by the Regulatory Authority

Page 47: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

38

3.3.3. EXECUTION STAGE

Step 5: Involves the entire bid process management covering evaluation of commercial bids,

selection of most suitable bids, and negotiation of contracts and award of R&M contracts to

vendors/suppliers/OEMs takes place. Several options can be worked out for involvement of

private players in the R&M process. Some options often discussed include: (i) Lease, rehabilitate,

operate and transfer; (ii) Sale of plant; (iii) Joint venture between the private player and

public/private utilities.

The utility also needs to make Procurement Strategies and Planning for quality assurance,

inspection and expedite dispatch with sequential importance of procurement and arrival.

Step 6: The actual R&M project implementation begins after arrival of equipments to the site and

planning of shutdown of unit. One of the areas of concern towards successfully implementing

R&M often pointed out is the delay between decision to undertake R&M and actual

commencement of R&M. Lack of maintenance during this period could further deteriorate the

plant condition.

3.3.4. CLOSURE STAGE

Step 7: After the R&M work is completed, it is very essential to evaluate whether the goals and

objectives of the R&M project was achieved or not. For this post-R&M Performance Guarantee

Test is conducted.

3.3.5. POST R&M STAGE

Step 8: Operation and Maintenance Training is imparted to engineers for efficient operation of

the unit that has undergone R&M. This is very important as there are issues involved in effective

interfacing of the new installations with the existing ones, commercial issues linked to change in

tariff; actual vs. planned performance outputs etc.

Page 48: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

39

3.4. GUIDELINES FOR RISK IDENTIFICATION AND MITIGATION MEASURES

Planning and implementing R&M projects is often witnessed by occurrence of adverse events that

can derail the objectives of the project. Thus, a well-structured and documented Risk

Management at each nodal point is of utmost importance. The main objective of Risk

Management is to increase the probability and impact of positive events and decrease the

probability and impact of negative events.

Identifying and mitigating project risks are crucial steps in managing successful R&M projects.

Today, effectively managing risk is an essential element of successful project management.

Proper risk management can assist the project manager to mitigate both known and unanticipated

risks on projects of all kinds. Failure to perform effective risk management can cause R&M

projects to exceed budget, fall behind schedule, miss critical performance targets, or exhibit any

combination of these troubles.

The figure below indicates steps for risk identification and mitigation during planning and

execution stage of the R&M.

Figure 3.2 Stages of Risk Identification and Mitigation Strategies

Though a number of factors influence R&M decisions and determine successful outcomes; a

robust risk management framework can contribute significantly towards ensuring that the project

undergoes R&M successfully. The following sections provide a description of approach proposed

to be adopted for developing guidelines for risk identification and its management.

Page 49: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

40

3.4.1 RISK IDENTIFICATION AND CLASSIFICATION

Risk Identification consists of determining which risks are likely to affect the R&M project and

documenting the characteristics of each. Risk Identification should address both internal and

external risks. Internal risks are those that project team can control or influence whereas external

risks are those that are beyond project team‘s influence and control.

In order to undertake this task, a Risk Breakdown Structure proposed (Fig No. 10) that ensures

comprehensive and systematic identification of risks in the R&M Process. The Risk Breakdown

Structure will also identify various areas and causes of potential risks.

Figure 3.3 Risk Breakdown Structure (RBS)

Tabulation of Risk experience in each of the above stages will help in identifying the key issues

and reasons why, what and how the risks come into existence in an R&M project. The tabulation

Page 50: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

41

can be exhaustive but ultimately this will help future R&M projects in risk identification during

conceptualization phase only.

The above risks will be classified further into the following for proper mitigation strategies:

Internal and External Risk – Classification of risks whether they are controllable or

uncontrollable. The classification may be grouped based on the themes such as regulatory risks

during the course of the R&M process, technical risks in R&M, market risks in R&M, Project

Planning and Control Risk, Regulatory and Policy Risk, Natural Calamity Risk etc.

Risk Bearer – Classification of risk borne by entities involved. The risk borne by various entities

also stems from the concerns experience by various entities in planning and implementing R&M.

Annexure 13.2 provides a list of key concerns faced by various entities involved in the R&M

process.

Impact of Occurrence – Likely impact of the risk to occur

Frequency of Occurrence – the possibility of occurrence of a particular risk

Magnitude of Risk – this implies degree of severity of the risk being faced (discussed in more

detail in the following sub-section)

The aim of the above is to focus on developing strategies for risk identification and mitigation for

risks that under the current system and mechanism are unmanageable and have a high impact.

3.4.2 RISK ASSESSMENT

Estimation of risks can involve both Qualitative Assessment and Quantitative Assessment. The

main objective is to quantify the risks wherever possible so that the impact of a particular risk is

well understood. However, at places where quantification is not feasible, qualitative risk

assessment shall be undertaken.

Page 51: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

42

Some of the key activities that will be performed here are as follows:

Risk Probability Assessment – This investigates the likelihood that each specific risk will

occur. During the meetings with the stakeholders the level of probability for each source of risks

and its impact on each objective has been accessed and rating has been done accordingly. Risks

with low probability and impact can be included in the watch list for future monitoring.

Risk Impact Assessment – This investigates the potential effect on project objectives such as

schedule, cost, quality or performance. The Probability and Impact Matrix will be prepared based

on risk rating as illustrated in the table below.

Figure 3.4 Probabilities and Impact Matrix (ILLUSTRATIVE)

Page 52: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

43

3.4.3 RISK MITIGATION

Risk Mitigation response involves defining steps to respond to risks. Respond to threats in R&M

Project can be mitigated by the following methods:

Avoidance

o Risk avoidance involves changing the R&M project management plan to eliminate the

threat entirely either by isolating the objectives of the project from the risk‘s impact or

change the objective that will be affected.

o For example: Extending the schedule, change the strategy or reducing the scope. Some

risks that arise early can be avoided by clarifying requirements, obtaining information,

improving communication or acquiring expertise.

Transfer

o Risk transfer requires shifting some or all of the negative impact of the R&M Project

threat, along with ownership of the responses to a third party. Transferring the risk

simply gives another party responsibility for its management- it doesn‘t eliminate it.

o Transference tools can be quite diverse and include, but not limited to, the use of

insurance, performance bonds, warrantees, guarantees etc. Risk Transference nearly

always involves payment of risk premium to the party taking the risk.

o However, there are strategies where transfer is carried out in a manner that it transfers

the risk to entity that is able to manage that risk well, hence resulting in minimizing

the impact of the identified risk. Thus, transfer could also lead to mitigation in certain

cases.

Mitigation

o Risk mitigation in R&M Project implies a reduction in the probability and impact of

an adverse risk event to be within acceptable threshold limits.

Page 53: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

44

o Adopting less complex processes, conducting more tests or choosing more stable

suppliers, having contract flexibilities to handle surprises are some examples of

mitigation actions.

o Another way can be development of redundancy into a system may reduce the impact

from failure of original component.

Acceptance

o This strategy is adopted because it is seldom possible to eliminate all threats from a

project. Acceptance can be active (by developing a contingency reserve to execute

should the risk event occur) or passive (by accepting a lower profit if some activities

overrun)

NOTE: The strategies or mix of strategies most likely to be effective will be selected for each

risk identified in the previous stage. Specific action plan will be developed to implement the

strategies that will include primary and back-up strategies as necessary.

Page 54: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

45

3.5 GUIDELINES FOR EARLY IDENTIFICATION OF POTENTIAL TECHNICAL

SURPRISES AND WAYS OF ADDRESSING THEM

Potential Technical Surprise is itself a type of risk which may arise due to improper assessment

of the plant and inadequate scope definition. Given that it is difficult to design and assess

technical specifications initially without actually opening the unit, upfront studies like Residual

Life Assessment, Energy Audits etc. need to be carried out. However past experiences shows

that the sometimes there is a huge time lapse between RLA Studies and actual implementation of

R&M and the units that are planned to undergo R&M do not get any maintenance priority. Both

these factors lead to further deterioration and also lead to some level of surprises experienced

when the units are actually opened for R&M. RLA and other tests are conducted by OEMs and

reputed agencies whereas in case of rest of areas like Balance of Plant (BoP) the scope is derived

from the Plant O&M. When the actual work is executed by respective suppliers, along with

changes in scope, many technical surprises are encountered.

During plant visits many such cases were identified, for example initial plan for R&M of Korba

TPP in Chhattisgarh required overhauling of Ash Handling Plant (AHP), however after

dismantling unforeseen damages required replacement of AHP. Similarly, in case of Panipat TPS

in Haryana, the Executing Agency had to change the scope of project when they found that the

boiler foundation had sunk and required additional civil work to repair the foundation. Similarly

in Obra TPP in Uttar Pradesh non-availability of spare parts led to complete replacement of

condensers by BHEL. These changes in scope are generally not compensated and Executing

Agency has to bear the losses. The anonymity of actual scope is deterrent for Bidders besides

hosts of concerns like delay between RLA studies and actual bidding, delay in payment,

fluctuations in commodity prices etc.

Hence, a three stage approach is proposed for early identification of technical surprises.

Page 55: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

46

Figure 3.5 Early Technical Surprises Identification Approach

Stage 1: Identification of Technical Surprises

The Identification of Technical Risks shall be sub-divided in two stages. Initially, based on

review of stakeholder experiences, documents on surprises and technical barriers encountered are

framed. Then discussion with the industry experts are held about the possibilities and range of

technical surprises that R&M Project can face. Subsequently the surprises encountered by

reviewing technical reports like DPRs, RLA Studies etc. are validated to check whether the

surprises faced have been flagged or indicated initially before beginning of R&M or not.

For example in Korba as mentioned above, it is important to check whether the Design

Consultant has done analysis of the performance of AHP or not and whether a root-cause

analysis was done or not on why the performance is below the designed parameters. Such prior

detailed analysis though it takes time goes a long way in keeping the R&M Project economically

viable. In order the exhaustive list can be examined in a more meaningful and useful manner, the

technical surprises are tabulated as mentioned below.

Page 56: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

47

Table 3.2: Tabulation of Technical Surprises (ILLUSTRATION)

PLANT SYSTEM TYPICAL EE R&M MEASURES POSSIBLE TECHNICAL SURPRISES

MAIN PLANT

Boiler and Auxiliaries Improve Combustion

Arrest air leakages

Reduce dry flue gas heat

Reduce leaks in air heater

Reduce auxiliary consumption

Replace high pressure valves, parts

Turbine and Auxiliaries Replacement/modification of HP,IP and LP turbine blades

Proper Regenerative System

Modification of cooling water pumps

Improve heat transfers and heat exchangers

Generator Increase generator rating by better insulation, cooling and sealing system

OTHERS

Control and Instrumentation System

Replacement of entire C&I system with DDC system

Advanced control system for turbine furnace etc.

New UPS system for reliability

New Stem and water Analyzer

Balance of Plant Enhance coal handling plant capacity

Strengthen Ash Handling System

Fire detection and Protection system

Enhance DM plant

Environmental and social consideration

Suppression of dust in CHP, AHP

Stage 2: Impact Assessment

Identification of Technical Risk alone will not serve the purpose unless the impacts of these

surprises can have on Scope, Cost, Schedule and Quality is assessed. This will help the

stakeholders in making proper Cost-Benefit Analysis and in the preparation of budgets.

Currently the Executing Agencies or OEMs keep a cap of certain amount to tackle technical

Page 57: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

48

surprises but it is not based on proper scientific evaluation. An Impact Assessment Matrix is

designed that will give exhaustive possible technical surprises. Based on these surprises the

Scope, Cost, Schedule and Quality of R&M projects are determined.

Figure 3.6 Impact Assessment matrix (ILLUSTRATION)

The Impact Assessment Matrix will contain how these technical surprises can affect the overall

project on different objectives of the project.

Stage 3: Mechanism for Mitigation

After the assessment of impact technical surprises can have on R&M project, we will

recommend mechanisms to mitigate the surprises as per the table below:

Figure 3.7 Mitigation Mechanism Table (ILLUSTRATION)

Page 58: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

49

3.6 REVIEW OF INTERNATIONAL BEST PRACTICES IN R&M

Assessment and Review of other countries reveal many similar barriers faced by India. Few of

the constraints faced by other countries are regulatory constraints (tariff and recovery

mechanism), funding constraints, inability to keep scope, schedule, cost and time of R&M

projects in check, lack of supplier‘s interest etc. However many noteworthy R&M Projects have

taken place in countries like Ukraine, Romania, Albania, China, Australia. In these countries

similar to Indian scenario it is seen that R&M is still competitive despite increasing fuel prices

(in case of India it is quality and availability of coal), increasing price of new plants, emphasis on

efficiency and emissions provided impetus to go for R&M Projects.

Though the similarity in constraints in other countries may seem despairing, it actually provides

a window to examine strategies, policies and regulation interventions of these countries on

―how‖ they overcame the barriers and risks to make R&M program successful. This is

particularly for the reason that most of the countries emphasis on efficiency and reduction of

GHG emission like in India. Many countries like in Australia, Great Britain, USA and South

Africa have paved the ways in amending regulatory incentives and market framework to

incentivize and support R&M Projects.

The usual process at first is identifying the best practices across the world and then

contextualized to the local context. This approach can sometime backfire as this approach

doesn‘t take into consideration the key issues faced internally and hence mapping sometimes has

to be abandoned in the middle. Henceforth, first step would be to understand and assess the key

issues and risks faced in India. Tabulation of issues in each stage of R&M allows clearer picture

in identifying best International Practices and also to look specifically for solutions across hosts

of countries.

Thus, the international review proposed to be carried out shall be theme/issues based. The table

below illustrates the approach proposed for capturing the International Experience.

Page 59: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

50

Table 3.2 Mapping of International Best Practices to Indian Context

Some of the key themes where the process benchmarking3 shall be undertaken are as follows:

Mechanism of selection of Unit/Plant for R&M along with objectives of carrying out

R&M

Advanced technological options considered for EE R&M such as turbine up-gradation,

efficient and environment friendly furnace-boilers, coal utilization etc.

Process of Finalization of Scope of Work for R&M

Procurement Process for Selection of Consultant/Contractor

Mechanism of funding of R&M Projects

Methodology adopted for Cost Benefit Analysis

Process of implementation of R&M Projects including shut down time

Environmental safeguards

Measures for Guaranteed Performance post R&M

R &M Stage Key Issues Faced in Indian R &M Ukraine Romania Australia China

Assessment Stage

Improper plant assessment

Poor past O&M practice

Improper cost benefit

Limited agencies undertake assessment

Planning Stage

Improper planning of scopes and budget

Improper Risk management plan

Regulatory approvals

Procurement Stage

Improper negotiations and contracts

Suppliers reliance on design consultant's report

Different solution by suppliers

Execution and Closure Stage

Delay in delivery of components to plant site

Inability to mitigate technical surprises

Inadequate skills

Post R&M Performance stage

Efficiency gains/ perf. not realized

Unmet emissions standard

Page 60: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

51

3.6.1 UKRAINE

3.6.1.1 BACKGROUND OF UKRAINE POWER SECTOR

Ukraine‘s power sector is structured along the major business activities: generation,

transmission, distribution and supply of electricity. Electricity generation is mainly presented by

thermal power plants and nuclear power plants. In early 2012 the total installed capacity in

Ukraine was 53,341 MW out of which 27.2 GW (51% of installed capacity of Ukrainian plants)

generated by five thermal power generation companies- Centrenergo, Donbasenergo,

Dniproenergo, Skhidenergo and Zahidenergo comprising 14 powerful thermal power plants; 4

nuclear power plants with total installed capacity of 13.8 GW united in the State Enterprise

Energoatom; 2 hydro power generation companies - Ukrhydroenergo and Dniester HPSP

comprising cascades of hydro power plants at Dnieper and Dniester rivers with total installed

capacity of 4.6 GW. Besides there is a number of combined heat & power plants (CHPs). Some

of them are being operated by local power distribution companies and other institutions while

others became separate enterprises.

The Ukrainian electricity market is currently organized under a single-buyer model. A

competitive wholesale electricity market (WEM) was established in 1996, with the state

enterprise Energorynok functioning as market administrator. Transmission is organized within

NEC (National Electricity Company) Ukrenergo, which owns and operates the high voltage

network. Distribution is carried out via 27 regional distributions and supply companies (so-called

Oblenergos).Supply is conducted by Oblenergos (suppliers at regulated tariff) and independent

(non-regulated tariff) suppliers. In the mid-1990s, the government unbundled transmission and

distribution from supply. However, in 2004, the government created a new company, Energy

Company of Ukraine, which took over the state power assets (both supply and distribution). The

grid company and nuclear operator are also state owned, although in separate companies. Several

of the regional distribution companies are in private hands and are not part of Energy Company

of Ukraine. The power sector is significantly more stable than it was several years ago, with

fewer outages, more stable grid frequency and higher levels of payment. At the same time, the

sector needs significant new investment and would benefit from a more vibrant market with

greater incentives for efficiency.

Page 61: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

52

In the coal sector, the privatized mines attracted most investments and showed positive

production results, but privatization and restructuring slowed down by 2003. In electricity, only

six distribution companies were privatized by 2001. The remaining 21 power distributors are

partially privatized with a mix of free-floating shares and shares owned by the government or

other shareholders. Ukraine has several private companies and organizations working on energy

efficiency, as well as a state-owned energy service company, UkrESCO. In addition, several

state research institutes focus on energy- efficiency issues. In 2002 an Act was implemented for

Thermal Power Reconstruction, as per Article 18, Design and construction (new construction,

expansion, reconstruction and technical re-equipment) of electricity is based on the laws of

construction. Rigging of electricity carried out on tender basis. {Part one of Article 18 as

amended by the Law N 741-IV (741-15) of 15.05.2003}.

In 2004, the government somewhat changed the policy direction and took new steps to increase

state control in the energy sector. It reconsolidated the electricity and coal industries into large,

vertically-integrated companies, similar to Naftogaz of Ukraine, which dominates the

hydrocarbon sector. In the electricity sector, the government created the state holding Energy

Company of Ukraine (ECU) in June 2004. The holding company Coal of Ukraine was created in

the autumn of 2004 by consolidating state-owned assets, although it has since been abolished and

its assets have been transferred to the Ministry of Coal Industry. By 2003-04 it became clear that

the comprehensive energy programme were not being implemented as expected. The government

tasked the Ministry of Fuel and Energy with preparing an improved energy strategy. The

Ministry adjusted the previous draft version, using the most recent statistical data and the state

policy trends. Ukraine has been in an energy crisis at least since the gas supply disruption from

Russia in January 2006. The actual energy crisis has been triggered mostly by low energy prices

which have implications both on energy supply and energy demand. Most Ukrainian energy

providers have been unable to finance even their replacement investments as their revenues from

sales did not cover all their costs. The importance of cost-reflective energy prices has been well

recognized in Ukraine.

The Energy Strategy of Ukraine to 2030, approved by the Cabinet of Ministers of Ukraine in

March 2006 (Cabinet of Ministers, 2006a), indicates that privatisation of energy sector facilities

Page 62: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

53

should be based on an individual approach towards each company. It also highlights the need to

apply privatization methods that would re-invest revenue from privatisation (in full or in part) in

the company privatized. It is important to ensure that privatisation takes place in a transparent

and competitive manner. The sector‘s regulation is performed by the Ministry of Fuel and

Energy and the National Electricity Regulatory Commission (NERC).

FUEL & ENERGY MINISTRY

The main function of the Fuel and Energy Ministry is implementation of the Government policy

in energy sector, regulation and reformation of the power industry and energy market. It is also

responsible for keeping integrity and reliability of the Ukrainian energy system. The Ministry

takes part in the forecasts and scheduling of energy generation, development of technical, social,

financial and other areas in the industry, as well as development and implementation of

investment policy in the industry. Fuel and Energy Ministry manages NEC Ukrenergo,

Energoatom and holding Energy Company of Ukraine which in its turn manages state‘s stakes in

the state owned power companies.

NATIONAL ELECTRICITY REGULATORY COMMISSION (NERC)

In December 1994, the National Energy Regulatory Commission (―NERC‖) was formed. It was

founded as the Commission Dealing with Issues on Electricity in 1994 and became NERC under

a new Charter approved by the Decree of the President in 1998.Laws providing for NERC‘s

regulatory authority include the Law on Electricity(1997), the Law on Natural Monopolies

(2000), and the Law on the Principles of State Regulation in the Economy (2003). NERC‘s

authority to make rules and decisions is subject to the Law of Ukraine ―On Electricity‖, Law of

Ukraine ―On Natural Monopolies‖, Regulation on NERC. The procedure set by the Law of

Ukraine ―On the basics of the State Regulatory Policy‖ imposes a variety of requirements, such

as public opportunities to comment and submission to various government agencies for

agreement, which can sometimes lead to very lengthy rule and decision‐making processes.

NERC has set about 60 technical rules since 1995; ten of these were issued in the first half of

2005 alone.

Page 63: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

54

The major roles and responsibilities of NERC are as follows:

Regulation of natural monopolies activities in the power sector, in the oil and gas

complex and in the sphere of heat generation;

Electricity, heat, gas, oil and oil products consumers rights protection;

Issuance of licenses to entrepreneurial entities operating in the energy sector;

Ensures implementation of pricing policies in the power sector, in the oil and gas

complex and in the sphere of heat generation;

Regulation of relations in the retail electricity market

3.6.1.2 SELECTION OF UNITS AND OBJECTIVES OF CARRYING OUT R&M

Production capacities in electricity sector of Ukraine were badly out-dated by 1994. As per the

survey by clean coal technology task force in 1994, 95% of power units had already worked out

their normal service life (100,000 hours), more than a half were been working for 200,000 hours.

80% of power plants have been operating for 30 years. According to official estimates, the

residual life of thermal power plants is 5-7 years. Given high depreciation level of power plants

the future of Ukrainian electricity sector was ambiguous. Such deterioration was stipulated by

low quality fuel (with high sulphur and ash content), fickle regime of TPPs capacities due to

poor maneuverability and lack of funds for reconstruction. Nuclear power plants will approach

the end of their designed service life in 2011-2030. Proposals to implement a restructuring

programme along the lines of the British model were then discussed with Minenergo, Ukraine.

This rather complicated and, at the time, relatively untested arrangement of unbundling and

privatization was accepted by the international donors for implementation in Ukraine.

Beginning in 1994, a Clean Coal Technology Task Force was formed to demonstrate in a

concrete way how modern technologies for coal utilization could be used to benefit the thermal

power sector of Ukraine. The Task Force was formed under sponsorship of the U.S. Agency for

International Development, and membership consisted of the U.S. Department of Energy (Office

of Fossil Energy), the Ukrainian Ministry of Energy (Minenergo), and the Ukrainian Academy of

Sciences. The Task Force performed a project definition study for upgrading the anthracite

burning generating stations of Ukraine that were not performing well in the Donbass region,

named Lugansk GRES. The study was completed in 1997 with the preparation of engineering

Page 64: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

55

and financial analyses for the upgrade project. It was observed in the study that Power plants

built in the period 1959-1975 do not comply with modem standards of economic efficiency and

environment protection. As about 80% of fossil power units have exceeded their lifetime

(100,000 operation hours), thermal power plants need extensive reconstruction.

Ministry of Energy of Ukraine (Minenergo), Federal Energy Technology Centre, US Department

of Energy, Pittsburgh, Babcock & Wilcox and Burns and Roe Enterprises, USA and Coal Energy

Technology Centre (CETC), Kyiv, a division of the Ukrainian National Academy of Sciences

cooperatively devised the power plant upgrade project. Collecting data, inspection and

evaluation of the plant equipment, engineering and financial analysis to determine optimal

upgrading plans for different levels of capital investment that was performed during more than

two years period have confirmed technical possibility and economic feasibility of reconstruction

of different power plants in Ukraine.

Burns and Roe Enterprises, Inc. within the framework of the U S. Agency for International

Development (USAID) Emergency Energy Program for the Newly Independent States (NIS),

Energy Efficiency and Reliability - Ukraine, Task 1- Technology Based Project, Energy

Efficiency and Market Reform Project (EEMRP), Task 2 - Power Plants Combustion Efficiency.

As per the survey the following observations were made as per Ukrainian average figures:

The net efficiency of power plants based on condition assessment of boilers, turbines,

generators, and process steam parameters etc. which was found to be 31% for

GRES(condenser type TPP) and 55% for TEZ(Co-generation type TPP).

The CHP plants were operating in extraction-condensing mode which is less energy

efficient than back the back pressure operation due to low availability of units annual

load factor was very low.

Average gross electric efficiency (34% for GRES and 29% for TEZ) that are almost 5%

below the modern plants.

Auxiliary power consumption was 10% which is 4-5% more than global average. It‘s due

to inefficient motors, pumps, fans, drives, regulation and control systems.

Page 65: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

56

The average sulphur oxide emissions from coal-fired plants are about 20 times higher

than the LCP values for new plants, and 10 times higher than the LCP values for existing

plants.

The average operation hours of steam turbines exceeds 200 000 hours which can be

generally considered as upper limit for major reconstruction.

The average annual operation time of turbines, boilers and other main equipment is about

5500 hours which describes the availability of the units, but possibly also the electricity

market situation. Based on this figure, the average availability is about 65%, which are

25%-units less than in Western plants.

The average time that the turbines are operating between each start and shutdown is about

400 hours (17 days), which is very low figure and indicates problems in the reliability of

the plant.

U S AID/Kiev has submitted an energy savings program by providing instrumentation equipment

to combined heat and power plants (CHP) and power plant stations to improve combustion

efficiency of the boilers as a first step towards life extension of these plants. The purpose of

Task-2 is to implement this energy saving program at seven power and/or CHP plants. The

project team visited Ukraine September 14-0ctober 13, 1994, to select representative plants and

to gather preliminary information at the selected plants. The project teams performed combustion

audits during February and March 1995. During these audits, the project teams trained plant

personnel on the use of portable combustion efficiency instrumentation. A set of portable

combustion efficiency instrumentation was given to Zmiev plant in 1995. In 1997 the Zmiev

plant received and accepted oxygen analyzer, high range infrared thermometer, liquid flow

meter, combustion analyzer consumables, and sulphur analyzer. Installation of oxygen analyzers

was initiated at Zmiev in May 1997.The Zmiev Power Plant is presently 51% government owned

and is in the process of privatization.

The plant consists of six subcritical 200 MW units and four supercritical 300 MW units with a

total of 2400 MW installed capacity. The plant was commissioned between 1960 and 1969. The

coal supplied to the power station has poor quality, with calorific values of 3200 to 5000 kcal/kg

and 40% ash content.

Page 66: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

57

The purpose of Task -2 is to improve boiler efficiency at seven power plants and/or combined

power and district heating plants which were selected by USAID/Kiev in consultation With the

Ministry of Energy and Electrification. These plants are fired with natural gas, fuel oil or coal.

The objectives are:

To foster Improved management of boiler/plant operations by Identifying and

implementing immediately cost-effective "low cost - no cost" efficiency Improvements.

Provide equipment support to Implement low-cost operations, improve monitoring and

energy management.

Provide operation training.

Source: Audit report of Burns and Roe Enterprises, Inc. submitted to USAID

3.6.1.3 FINALISATION OF SCOPE OF WORK

The various scope of work of the repair and service manufacture enterprise as part of

rehabilitation work was as follows:

To provide reliable operation of the existing boilers and improve boiler techno economic

performance which allows competing efficiently at the Wholesale Energy Market and

getting maximum profit.

To provide reliable operation of the existing 200 MW boiler units is planned to realize by

staged reconstruction together with overhaul repair.

The scope of the reconstruction will include boiler modernization with implementation of

new solid fuel combustion technology, reconstruction of regenerative air-heater seals,

reconstruction of turbines by low-pressure rotor replacement, reconstruction or

replacement of electrostatic precipitators (ESP), implementation of SOx and NOx

removal systems.

Replacement of non-effective and worn 100 MW turbo generators by new power

equipment using new coal combustion technologies.

Improvement of ecological performance of the plant by reconstruction or replacement of

the ESPs with further implementation of advanced electronic-beam flue-gas cleaning

system at the 200-300 MW boilers.

Page 67: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

58

3.6.1.4 PROCUREMENT PROCESS FOR SELECTION OF CONTRACTOR

In Ukraine the procurement process for selection of consultant/contractor are done through a

tender committee that consist of group of specialists designated by the procuring entity who is

responsible for conducting the procurement procedure in accordance with the law of Ukraine on

Procurement of Goods, Works, and Services with State Funds. The detailed procurement

processes for Rehabilitation work of power plants are as follows:

The Tender Committee is established by the client for organization of procurement

procedures. The Tender Committee functions on a collegiate basis. Its members must be

unbiased and there must be no conflicts of interests between them.

The composition of the Tender Committee and the Regulation on the Tender Committee

are approved by the decision of the client (Genco) and the Tender Committee must

include at least 5 persons.

Experts and consultants involved in the work of tender committees on a contractual basis

in accordance with the legislation may not be members of the tender committee and are

not responsible for decisions, actions or inactivity of the tender committee and officials of

the client, participant or other persons, for the fulfillment (non-fulfillment) of

procurement contracts, as well as for consequences of such decisions, actions or

inactivity.

The work of the tender committee is managed by its Chairperson. The Chairperson of the

tender committee organizes the work of the committee and is personally responsible for

the fulfillment of the committee‘s functions. The Chairperson, Deputy Chairperson and

Secretary of the tender committee must receive a document certifying that they have

received training (qualification upgrade) in the procurement sphere following the

procedure established by the Authorized Body.

Decisions of the tender committee are presented in the form of a protocol, which must be

signed by all members of the committee who participated in the voting. Members of the

tender committee are personally responsible for their decisions in accordance with laws

of Ukraine.

The Authorized Body drafts and approved a Model Regulation for the tender committee.

Page 68: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

59

3.6.1.5 FUNDING MECHANISM OF R&M PROJECTS

A large share of assets in the Ukrainian energy sector have worked beyond their design life and

need urgent replacement or modernization. The Energy Strategy to 2030 estimates the total

investment requirements in the supply side of the energy sector at more than UAH 1 trillion

(USD 200 billion) from 2005-30 (Table 1.2), which implies a substantial higher rate of

investment than occurred in the last 15 years. In looking at the demand side, it estimates

investments in energy-efficiency improvements at UAH 102.3 billion (USD 21 billion) over the

same time period. Currently, investment in the sector is insufficient to meet the needs of the

ageing infrastructure. One reason for underinvestment is the sector‘s ownership structure: most

assets belong to the state, which cannot make all the necessary investments because it faces other

priorities for the state budget. Moreover, financing from the state budget is not always very

efficient because social or political concerns often prevail over economics. Private investment

has made inroads in the energy sector, but private companies could play an even greater role.

In general, the project implementation provides funding in the amount of 3 to 10 million USD

(approximately for Ukraine may be the sum of $ 5 million). It will consist of five stages.

Stage 1: Development of technical specifications and proposals for market readiness (description

of available resources, characteristics of the Ukrainian system of greenhouse gas emissions and

their accounting, proposals to improve existing capabilities).

Stage 2: Collection of data on greenhouse gas emissions and development of methods to manage

these data.

Stage 3: Determination of volumes of permits for greenhouse gases which will be distributed

among market makers.

Stage 4: Development of legal framework for the further implementation of the chosen model of

the market.

Stage 5: Forming of management system by the market.

Page 69: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

60

CASE STUDY: Krivoy Rog Power Plant Rehabilitation

Krivoy Rog GRES is a coal-fired power station with 3,000 MW installed capacity (10x300MW),

located in Zelenodolsk (Dnipropetrovsk region) and operated by Dniproenergo Joint Stock

Power Company, based in Zaporozhye. Because of derating, the current operating capacity is

only 2,600 MW. A number of Krivoy Rog units are nearing their design lives and vital

components are at the end of their safe metallurgical life. The Station's environmental

performance is inadequate. Serious deterioration in reliability of equipment has adversely

affecting unit generating capacity, availability and efficiency. Rebuilding or replacement of some

of these components is necessary for the continued economical, reliable and environmentally

sustainable operation of this plant.

The main development objectives of the proposed project include support for:

The full implementation of the on-going power market reforms;

Transforming Dniproenergo into a commercially oriented and financially viable modern

utility;

Implementing the sector investment plan leading to the closure of the Chernobyl nuclear

power station as agreed between the Ukraine and the G-7 by financing a priority project,

which is part of the plan;

Rehabilitating a total of 900 MW generating capacity at Krivoy Rog GRES.

Specific technical objectives include:

Extending the life of three 300 MW power units by at least 15 years;

Increasing power output through improved unit availability and thermal efficiency;

Reducing operating and maintenance costs;

Improving load-following capability;

Improving environmental performance of the plant.

Six thermal power plants have been identified by the Ministry of Power and Electrification

(Minenergo) as possible investment targets. Of these six plants, detailed rehabilitation feasibility

studies were carried out for Krivoy Rog GRES. Based on these studies, the major components of

the proposed project are:

Page 70: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

61

General Station Rehabilitation: This includes upgrading of fuel receiving and handling

facilities, including installation of a new crane; rehabilitation or replacement of parts of the

electrical system, including transformers, switchgear, cables, circuit breakers; installation of

automatic dispatch controls; upgrading of water treatment and waste water disposal; installation

of ash, S02 and NOx measuring devices; and upgrading of service facilities;

Boiler Rehabilitation (Units 6, 7, 8): This includes reconstruction of pulverizers and the air and

flue gas system; improvement of casing and insulation; replacement of high pressure parts;

upgrading/replacement of main and reheat steam piping; reconstruction of feed water system;

replacement/reconstruction of electrostatic precipitators; upgrading of instrumentation and

control; and installation of emission measuring instruments;

Turbine-Generator Rehabilitation (Units 6, 7, 8): This includes replacement of governors,

controls, medium and high pressure cylinders, condenser tubes and screens; and reconstruction

of condensate pumps, heaters and motors; Replacement of Generator for Unit 2; and

Environmental Aspects: With respect to its environmental impact, the proposed project has

been classified in the World Bank as category B, under which an environmental analysis is

required. The project is designed to bring about a substantial improvement of air quality in the

Krivoy Rog region, which is regarded as one of the most polluted regions in Ukraine. The

estimated reductions are 12,000 tons of S02, 5,000 tons of NOx, and 28,000 tons of fly ash

emissions per year. In accordance with the environmental regulation of the Government of

Ukraine, the Ecological Assessment of the project by the appropriate regional environmental

office is in progress. In October 1996, a preliminary official approval was granted by the

Dnipropetrovsk Environmental Inspectorate.

The proposed rehabilitation extends the life of three 300 MW units by at least 15 years. It is

expected to increase:

Generating capacity for the total plant from 2,600 MW to 2,993 MW.

Annual availability by 24%; (84% against 60%)

Overall plant thermal efficiency by 5.2%.

Page 71: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

62

3.6.2 CHINA

3.6.2.1 BACKGROUND OF CHINA POWER SECTOR

In China, the power industry has gone through a series of changes since 1985, including: the

termination of the monopoly of ‗‗exclusive investment in power generation,‘‘ which existed for

over 30 years during China‘s planned economy period; the gradual opening of the power

generation market; and the introduction of new investment and operation entities to relieve the

power shortage that had been hindering the development of the Chinese economy. Such changes

led to the remarkably rapid development of China‘s power industry. For example, the demands

for electricity have been largely met.

In 1997, the Chinese government took more radical steps to reform the power industry,

particularly with respect to separating business operations and management from government

oversight and guidance. The governmental functions of the former Ministry of Electric Power

were divided between the State Power Corporation of China (which was newly established) and

the State Economic and Trade Commission. In the evolution of the People‘s Republic of China,

we can identify the following three main phases of the power regulatory system:

1st Phase (1986-1995): 7th and 8th Five year Plans

Multi-channel financing capital expansion project

Allow foreign investment since 1995

Aroused the enthusiasm of the society to generate power and rapidly changed the serious

power shortage all around the country

Multiple investment bodies gradually formed in the power market

2nd Phase (1996-2000): 9th Five year Plan

State Power Corporation was founded in January 1997

Four-step reform strategy in August 1998

Separation of Administration from Enterprise Operation

Separation of Generation from Grid and bidding for on-grid

Page 72: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

63

3rd Phase (2001-2010): 10th and 11th Five year Plan

Plans of Power Regime Reform was formally approved by the State Council in March

2002

State Electricity Regulatory Commission (SERC) was set up in October 2002

The former SPC was restructured into two grid corporations, five large GenCo‘s and four

subsidy groups in Dec 2002

Separation of Generation from Grid

4th Phase (2011-Present): 12th Five year Plan

Approved by the Central Committee of the Communist Party of China (CPC) on 14

March 2011

Focused on optimizing the structure of power generation in a micro-level for better

economic and sustainable development

Set out systematic reform strategies for developing clean energies, optimizing production

of coal-fired electricity, rationally allocate peaking power, developing distributed energy

and constructing a strong and smart grid.

Reference: China Energy Policy, 2006

Major Objectives of Reform

Introduce competitive incentives

Improve efficiency

Reduce generation cost

Ensure the sector contribute to meeting boarder economic and environmental goal

Optimizing coal-fired power generation capacity by accelerating construction of coal-

based generation

Achieve greater overall economic and social benefits

Page 73: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

64

3.6.2.2 LESSONS FROM R&M PROJECTS OF CHINA

CASE STUDY: HuBei Hanxin Power Station

Location: Hanchuan, Hubei Province, People‘s Republic of China

Unit: No. 2

Capacity Rating (MCR): 326 MW

Owner: China GuoDian Group

Components Renovated/Upgraded:

• Air Heater

• Boiler Burner

• Soot blower

• Turbine

• Condenser

Year commissioning after R&M: 2004

Plant Background:

Hanxin Group is located in Hanchuan, Hubei province. The company has total installed capacity

of 4 × 300-MWe. All four units are pulverized coal-fired subcritical type. Original commercial

operation of Unit No. 2 started in June 1996 (Unit No. 1 started earlier), and Units 3 & 4 were

started in 1998.

Scope of work and technological up gradation:

• Air Heater – Air heater had high air leakage and poor heat transfer

• Oil Burners – Poor combustion efficiency and stability

• Soot blowers – Soot blower performance deteriorated to a very low level

• Steam Turbine – Seal needed retrofit. Governing stage nozzles required replacement.

• Condenser – Steam turbine back pressure consistently high due to insufficient heat

transfer surface area.

Page 74: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

65

Installation Cost:

• Air Heater - $542,857 (RMB 3,800,000)

• Boil Burner - $285,714 (RMB 2,000,000)

• Soot blowers - $571,429 (RMB 4,000,000)

• Steam Turbine - $757,143 (RMB 5,300,000)

• Condenser - S1, 542,857 (RMB 10,800,000)

Total = $3,700,000 (RMB 25,900,000)

Source of Funding – Self-funded

Age of Plant when Upgraded/Refurbished: 4.5 years (start of plant commercial operation was on

June 28, 1996)

Savings/Benefits from R&M:

$795,171 base year 2000 (from 2004 – 2007) inflated at 2% per year

$1,665,882 base year 2008, inflated at 2% per year thereafter

Savings/Benefits derived from: Turbine Heat Rate Improvement of 179 BTU/kWh

Assumptions:

A yearly escalation factor (inflation rate) of 2% is assumed on all cost related items.

A Plant Capacity Factor of 70% is assumed. Capacity factor in this case, is equal to the

average annual operating time that the Unit is running @ 100% Load.

Basis: Reference point of Economic Analysis is year 2004.

Dollar values is based at year 2004

Coal Price basis: $2.00 /mm BTU (year 2000 inflated @ 2% per annum till price surge in

2008 due to Chinese coal industry deregulation $4.19/mmBTU (year 2008 price upward

Page 75: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

66

shift which is higher than the 2% annual increase projection as reckoned from year 2004;

partly due to coal industry deregulation.

15 years of economic life for the new upgrades/refurbishment.

Economic Evaluation Tool(s) Used in Project Performance Assessment:

The economic tools used in evaluating this case are DCFROR or IRR, the Net Present Value at

guideline rate of 20% and calculation for the Payback Period. The generally accepted definition

of a project‘s discounted cash flow rate of return is that it is the discount rate which makes the

present value of future cash flows equal to the initial capital outlay. It may be defined as that

discount rate which makes NPV equal to zero. As reinforcing indicator of the economic

feasibility of the project, payback period is also calculated. In this case, payback period is

obtained by simply dividing the total initial investment cost (outflow) by the annual income in

terms of fuel savings (Inflow).

Calculating for the Levelized life cycle cost of the plant, another approach to see the impact of

investments on plant upgrades is not used in this case, since the initial cost of the power plant is

not known.

Economic Feasibility Calculations:

Project Feasibility Indicator for this case is as follows:

• Discounted Cash Flow Rate of Return (DCFROR) = 29.54%

• NPV @ 20% Guideline Rate (Base Year 2004) = $1,700,000

• Payback Period = 3.74 years

The Net Present Value Profile for the project is shown below.

Page 76: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

67

3.6.3 AUSTRALIA

3.6.3.1 BACKGROUND OF AUSTRALIA POWER SECTOR

Australia is one of the largest coal exporters of the world. Power generation is Australia is

dominated by thermal power plants with a share of 69%. The electricity industry, consisting of

generators, transmission and distribution networks, and retailers, is one of Australia‘s largest

industries, contributing 1.4 per cent to Australian industry value added in 2009–10. Between

1999–2000 and 2009–10, Australia‘s electricity generation increased at an average rate of 1.4 per

cent a year. However, in 2009–10, electricity generation declined by 1.2 per cent.

Industry structure

The current structure of Australia‘s south-east electricity market was shaped by industry reforms

in the early 1990s. A key element of these reforms was the establishment of the National

Electricity Market (NEM), which began operation in 1998. The NEM allows market determined

Page 77: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

68

power flows across the Australian Capital Territory, New South Wales, Queensland, South

Australia, Victoria, and, from May 2005, Tasmania. Western Australia and the Northern

Territory are not connected to the NEM, primarily because of their geographical distance from

the east coast. The NEM operates as a wholesale spot market in which generators and retailers

trade electricity through a gross pool managed by the Australian Energy Market Operator

(AEMO). AEMO is responsible for aggregating and dispatching supply to meet demand in the

lowest cost manner available. In addition to the physical wholesale market, retailers may also

contract with generators through financial markets to better manage any price risk associated

with trade on the spot market.

The Australian Energy Market Commission (AEMC) is responsible for reviewing, amending and

expanding the National Electricity Rules (NER) which govern the operations of the NEM. The

enforcement of these rules, in addition to the economic regulation of electricity transmission and

distribution networks and covered gas pipelines, is the responsibility of the Australian Energy

Regulator (AER). The AER is also responsible for reporting on generator bidding behavior in the

NEM and compliance. The interaction between these three bodies (AEMO, the AEMC and the

AER) allows a consistent near national approach to regulate Australia‘s energy markets.

There is no formal, integrated electricity market in Western Australia. Electricity infrastructure is

organized in several distinct systems including the South West Interconnected System (SWIS);

the North West Interconnected System (NWIS); and a number of regional, non-interconnected

power systems. The SWIS became a wholesale market (where generators sell directly to

retailers) in 2006. The Independent Market Operator (IMO) is responsible for the administration

and operation of this market. Because of the small scale of the other systems in Western

Australia it is impractical to introduce a wholesale market. Instead, they operate as retail markets

where consumers purchase from competing retailers. Western Australia retains state-based

regulation of its electricity sector. The regulation of electricity transmission and distribution

networks is the responsibility of the local Economic Regulation Authority (ERA). The ERA

interprets, applies, and enforces the Electricity Networks Access Code which governs the

operations of these networks.

Page 78: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

69

3.6.3.2 CONTROLS AND INCENTIVES FOR GENERATION THROUGH R&M

The Australian Federal Government has created a Low Emissions Technology Demonstration

Fund, with around A$500m available to help finance projects that would reduce greenhouse gas

emissions and one of the key projects supported by this fund is the so-called ―Oxygen‖ project,

which plans to alter the way in which coal is burned to enable CO2 to be more easily separated

and then stored, so reducing the negative impacts on efficiency of other CO‖ capture

technologies. In addition, BP and Rio Tinto (Anglo-Australian mining company) have

announced plans to build a A$2bn coal fired plant in Western Australia that would bury most of

its CO2 in an offshore underground reservoir, whilst Stanwell Corporation (owned by the State

Government of Queensland) has announced similar plans in relation to the ZeroGen project to be

located within the state. Zero Gen has applied for support from the Federal Governments Low

Emissions Technology Demonstration Fund.

A summary of each of the incentives and controls applicable at the present time is set out below.

3.6.3.3 THE NATIONAL GREENHOUSE AND ENERGY REPORTING ACT

The National Greenhouse and Energy Reporting Act 2007 established a single, national system

for reporting greenhouse gas emissions, abatement actions, and energy consumption and

production by companies, commencing on 1 July 2008. Data reported through the system will

underpin the Australian Emissions Trading Scheme. The ability to monitor report and verify

businesses' emissions data will be essential for maintaining the environmental and financial

integrity of the trading system.

Key features of the system are:

a single online entry point for reporting based on the Online System for Comprehensive

Activity Reporting (OSCAR);

a standard data set and nationally consistent methodologies for reporting;

public disclosure of company level greenhouse gas emissions and energy data;

consistent and comparable data provided to government for policy making;

Page 79: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

70

3.6.3.4 GENERATOR EFFICIENCY STANDARDS

On 1 July 2000, Australia introduced a voluntary measure for fossil fuel electricity generators to

reduce the greenhouse intensity of energy supply. The Generator Efficiency Standards apply to

new projects and existing electricity generators above a minimum threshold, whether grid

connected, off-grid or self-generators. The minimum threshold is 30 MW capacity, 50 GWh

electrical output, and capacity factor of 5% or more in each of the last three years. The current

(2004) best-practice efficiency guidelines for new plants are:

Natural gas plant, 52% net thermal efficiency (Higher Heating Value HHV);

Black coal plant, 42% net thermal efficiency (HHV) and,

Brown coal plan, 31% net thermal efficiency (HHV).

The measure is implemented through legally-binding, 5-year Deeds of Agreement between the

Australian Government and participating businesses. Following implementation of action plans,

generators are required to monitor their performance and report to the AGO (Australian

Greenhouse Office) on an annual basis. The efficiency targets set under the scheme are expected

to be reviewed every 5 years. The scheme is focused on greenhouse gas emissions, rather than

analyzing any economic benefits from enhanced generation efficiency. Nevertheless, the

methodology and process used may provide useful models for India.

3.6.3.5 FUNDING FOR LOW EMISSIONS TECHNOLOGY AND ABATEMENT

In 2005, the Australian Government announced that it would provide funding of $26.9 million

over four years (2005-2009) to encourage ongoing investment in the development, demonstration

and deployment of smaller scale low emissions technologies, and other cost-effective abatement

activities through the Australian Greenhouse Office and the Department of Environment and

Water Resources. Projects eligible for funding should fall into one or more of the following

categories:

Page 80: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

71

Low Emissions Fossil Fuel Technology

Strategic Abatement

Geosequestration

Renewable Energy

The Low Emissions Technology Demonstration Fund supports industry-led projects to

demonstrate low-emission technologies. These technologies must have the potential to lower

Australia‘s emissions by at least 2% in the long term at realistic uptake rates and be

commercially available by 2020 to 2030.

The fund is designed to facilitate private sector investment of at least $1 billion and provides a

path by which industry can invest in a low-emissions future. It is aimed at supporting

technologies at the commercial and demonstration stage, when required investments are large

and risks remain high.

In 2006, the Australian Government committed $AUS 60 million to develop the world's then

largest carbon capture and storage (CCS) project in Western Australia.

3.6.3.6 COAL21 Programme

The COAL21 programme is a collaborative partnership between Federal and State Governments,

the coal and electricity generation industries and the research community. The key objectives of

COAL21 are to:

Create a national plan to scope, develop, demonstrate and implement near zero

emissions coal-based electricity generation;

Use the plan to inform Governments and industry as an input to policy

development;

Facilitate the demonstration, commercialization and early uptake of technologies

identified in the plan;

Page 81: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

72

Promote relevant Australian R&D;

Foster greater public awareness of the role of coal and the potential for near zero

emissions coal based electricity generation to reduce or eliminate greenhouse gas

emissions and other environmental impacts associated with its use;

Provide a mechanism for effective interaction and integration with other

international zero-emission coal initiatives.

3.6.3.7 GREENHOUSE GAS ABATEMENT PROGRAM (GGAP)

The Australian Government's Greenhouse Gas Abatement Programme (GGAP) has played an

important part in helping Australia meet its international emissions reduction target. GGAP aims

to reduce Australia's net greenhouse gas emissions by supporting activities that are likely to

result in substantial emissions reductions or activities to offset greenhouse emissions, particularly

in the period 2008-2012. The most recent emission projections show that GGAP will deliver an

abatement of 5 million tonnes (Mt) of carbon dioxide equivalent (CO2-e) in 2010. The

programme leverages private sector investment in activities or technologies through projects.

Examples of GGAP projects are based on co-generation (the use of waste heat or steam from

power production or greenhouse gas emissions reductions and industrial processes for power

generation), energy efficiency, travel demand management, alternative fuels, coal mine gas

technologies and fuel conversion.

CASE STUDY: Macquarie Generation – Liddell Power Station, NSW

Plant Background:

The Macquarie Generation project was designed to increase the generating efficiency at the

Liddell Power Station located near Muswellbrook in New South Wales. Prior to the project, the

efficiency of the Liddell Power Station turbines was around 85 per cent. Through the

replacement of the old low pressure turbines with modern turbines, the GGAP project increased

the generation efficiency of the four 500MW units by an average of 3.32% across the four units.

Page 82: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

73

Hitachi Australia Ltd was contracted by Macquarie Generation to design, manufacture, install

and commission the new Low Pressure turbines at Liddell Power Station and the upgrade was

successfully completed in July 2005.

GGAP funding: $5 million

Total project cost: Over $53 million.

Expected greenhouse gas abatement:

Total abatement up to 1.66 million tonnes of carbon dioxide equivalent is expected in the Kyoto

commitment period 2008-2012.

Efficiency improvements:

More energy can now be extracted from the steam flowing through the turbine, allowing an

increase of more than 60MW in the output capacity of Liddell, with no increase in CO2

emissions and reduced sulphur dioxide and nitrous oxide emissions from burning less coal. There

are also lower water demands from the power station and reduced sulphur dioxide and nitrous

oxide emissions from burning less coal. As a result the project is a potential catalyst for

investment in similar large scale abatement projects by other coal fired generators.

Technical summary:

The efficiency increase is achieved through improved control of the flow of steam through the

turbine. Advances in computer modeling techniques allow for more detailed assessment of the

impact of various steam path design options. This results in closer to optimum conditions than

was achievable when the Liddell turbines were originally designed.

Page 83: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

74

CHAPTER-4

RESULTS, DISCUSSIONS AND RECOMMENDATIONS

4.1.RESULTS

4.1.1. Augmentation of project capacity

A three stage project assessment is undertaken to ensure effective implementation of R&M/LE

work. Initially (Level 1), the assessment is based on available plant records and design data; no

inspections and testing of materials is required. Level 2 assessments involve measured data

(including performance testing), inspections and preliminary estimation of component remaining

life. Finally, Level 3 assessment is based on detailed inspection, actual material properties and

testing of material samples.

Table 4.1 Comparison of three level of project Assessment

Comparison Parameters Level 1 Level 2 Level 3

Level of Detail Minimum Details Substantial details Maximum Details

Information Source Plant Records Plant Records Plant Records

Nature of study Preliminary Extensive Comprehensive

Plant Dimensions Designed or Nominal Measured or Nominal Measured

Parameter Measurement Designed or Operational Operational or Measured Measured

Condition Assessment Records Inspection Detailed Inspection

Material Properties Minimum Minimum Actual material

Need of Material Samples No No Yes

In context to successful implementation of an R&M project, planning and development of R&M

project assumes a critical role. In this regard, detailed project assessment needs to be carried out

by undertaking various studies before appointment of an R&M contractor. These studies

mandate the need of appointment of an R&M consultant with suitable experience, which requires

a well-defined procedure to mitigate any future risks. Moreover, it is of critical importance that a

Page 84: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

75

project owner should balance risks and responsibilities through appropriate contracts. Table 4.5

represents the risk-responsibility matrix for R&M projects.

Table 4.2 Risk-Responsibility matrix for R&M projects

PARTY INVOLVED RISK RESPONSIBILITY

PLANT OWNER

Regulatory risk-Uncertainty of capital cost approval and reasonableness of tariff for recovery of capital cost

Coordination with different project agencies

Time overrun risk-Extended shutdown period

CONSULTANT Performance Risk

Detailed Project Assessment

Supervision of implementation works

Strengthening of O&M practices

CONTRACTOR

Cost Overrun risk-Unforeseen items/surprises during execution and impact on cost escalation

Execution of R&M works within the scheduled timeline

Scope surprises

Performing quality R&M works and providing performance guarantees

FINANCIAL INSTITUTION

Credit Risk- Utility dismal financial situation or project not viable

Providing sufficient and timely loans to project owner

4.1.2. Technical feasibility

Energy Audit studies, Residual Life Assessment (RLA) and Condition Assessment studies of

various equipments of plants were undertaken during plant visits. Based on these data the various

levels of assessments have been done and cost of losses due to deterioration in various system

and sub-system condition has been calculated. Deterioration has been calculated by comparison

with performance guarantee test figures wherever available or with designs figure in its absence.

Table 4.3 Energy Audit studies of thermal Power Plant at PTPS, Panipat

Component/System Studies Conducted

Boiler and Auxiliaries

Boiler Combustion efficiency

Boiler Outlet temperature

Air preheated efficiency and leakage, flue gas temperature

Power consumption by Boiler feed pump

Turbine Turbine cylinder efficiency and cycle efficiency

Page 85: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

76

Condenser Condensate pumps power consumption and performance evaluation

Coal handling Plant Estimation of average capacity utilization of CHP

Coal measuring system and quality check

Ash Handling system and ESP

Electricity consumption of ESP

Collection efficiency, coal quality and ash property

Ash utilization and disposal methods

Power consumption and pump performance of ash handling system

Cooling water system

Cooling tower capacity and efficiency

Circulating water pump performance and power consumption

Water circulation, condenser efficiency and turbine heat rate

Assessment of vacuum system

Raw water system and waste water treatment system

Capacity utilization and power consumption by the system

Electrical system

Transformer load management

Power factor management

Distribution losses

Harmonic analysis

Performance guarantee test were done after R&M and the various parameters like Specific oil

consumption, Coal consumption, PLF, Auxiliary power, Heat rate and availability of plant have

been tabulated as mentioned below.

Table 4.4 Performance of Unit-1 PTPS Panipat Before and After R&M

Financial

Year

Generation (MU) Sp. Oil Consp.

(ml/kwh)

Sp. Coal Cons.

(Kg/kwh) Gross Net

2002-03 559.7812 494.5107 6.26 0.864

2003-04 609.6400 542.2748 4.50 0.813

2004-05 506.7770 444.9502 5.13 0.858

2005-06 572.3970 503.4232 4.97 0.843

2006-07 603.5300 533.0981 3.11 0.842

R&M of Unit-1 carried out from 25.09.2007 to 04.11.2008

2009-10 815.1560 730.2782 1.95 0.795

2010-11 504.6018 450.3209 4.08 0.842

2011-12 820.2800 727.3118 2.89 0.831

Page 86: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

77

Table 4.5 Overall Plant Performance of PTPS Panipat

Year Plant Load Factor (%)

Aux. Power Cons. (%)

Heat Rate (Kcal/kWh) Availability factor (%)

No. of Trippings HERC Norm Actual

2002-03 58.09 11.66 3718 72.88 100

2003-04 63.09 11.04 3479 82.54 142

2004-05 52.59 12.2 3500 3554 71 112

2005-06 59.4 12.05 3450 3508 80.5 75

2006-07 62.63 11.67 3450 3342 89.16 55

2009-10 79.08 10.37 2930 3047** 83.67 70

2010-11 48.90* 10.09 2750 3112** 54.68 28

2011-12 79.27 11.24 3050 2916** 93.91 32

NOTE: In 2010-11 the PLF was low as unit-3 and 4 were under shutdown for R&M

4.1.3. Cost effectiveness

Figure 4.1 Cost break up of plant equipment in total equipment cost

82%

7% 5% 6%

BTG

CHP

BOP

ESP

Page 87: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

78

Figure 4.2 Cost break up of Services in total service cost

4.1.4. Efficiency Improvement (Sensitivity Analysis)

Fig 4.3 Effect of Plant availability on Cash Inflows Effect of efficiency on Cash Outflows

Note: The analysis was done for a 210 MW plant at 0.4 PLF and Heat Rate 3300 Kcal/kwh

22%

4%

41%

18%

7% 8% Design consultancy

EA and RSA

Better O&M practices

Implementation support

Quality Assurance

Front End Fee

Page 88: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

79

Fig4.4 Generation addition due to reduced Effect of PLF and Capacity Improvement

Heat Rate on Fuel Requirement

4.2.DISCUSSION

During plant visits and discussion with various stakeholders, equipment suppliers and meeting

with state regulatory commission the following aspects were discussed to minimize barriers and

effective implementation of R&M work.

15-20 % additional fund should be approved as contingency fund to avoid time overrun

due to technical surprises.

A single consultant should be appointed starting from RLA study till re-commissioning

of units.

R&M work should be started only after receiving 100% material at site

The contract and bid documents should be transparent and must contain all relevant work

and spare supplies during R&M.

A performance monitoring cell should be established and calibration of major equipments

should be done regularly (for example PTPS is planning to install the I-GEN software for

performance monitoring).

Page 89: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

80

4.3.RECOMMENDATIONS

4.3.1. Improve regulations affecting R&M projects and streamline approval process

It is recommended that a working group be established in collaboration with the Ministry of

Power and the Forum of Regulators to propose specific changes in the regulatory process.

4.3.2. Standardized documents

Guidelines on how to plan and implement R&M projects

Scope of Consultancy Services

Bid Documents

Commercial Contracts

4.3.3. Assistance to minimize power supply issues

It is recommended that the Central and the State Governments collaborate to allocate more

power supply to companies planning R&M projects

4.3.4. Bulk tendering

Tendering multiple units together should be explored urgently especially for the steam turbines

which are of identical design (210 MW LMZ or Siemens turbines). Also, a central organization

could be established to provide spare parts to power companies.

4.3.5. Private sector financing

Private-Public-Partnership (PPP) Guidelines should be developed and opportunities should be

sought to apply such concept. The Lease-Rehabilitate-Operate-Transfer (LROT) option may be

the most suitable option short-term.

4.3.6. Dissemination of best practice experience

International best practices are important for Indian power companies planning R&M projects. A

tour of plants which have implemented 210 MW LMZ design plants in Eastern Europe has been

proposed by USAID. Also, it would be beneficial to have a ―road show‖ to encourage equipment

suppliers and engineering companies to participate in R&M projects in India

Page 90: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

81

CHAPTER-5

CONCLUSION AND FUTURE SCOPE OF WORK

5.1.CONCLUSION

The Indian power sector has been embroiled in issues like energy deficits and load shedding.

Though the government has emphasized and advocated the need for R&M and has come out

with national perspective plan, but lacks serious implementation on its part with most of the

R&M projects not yet started or are getting delayed due to inadequate and inefficient project

management. This is primarily due to lack of participation by the private sector for government

projects, as most of the plants undertaken or eligible for R&M lies with the central or state

utilities which are already financially handicapped with huge annual losses. Thus the opportunity

cost favors private players to go ahead with Greenfield projects where returns are assured rather

than getting trapped in issues with payments and lack of authentic data regarding actual

operational parameters of plant in R&M projects. Now, with government‘s emphasis on

improving power availability in the XII plan and a proper risk mitigation strategy in place, the

R&M segment is going to be highly lucrative. For successful implementation of an R&M

project, planning and development of R&M project assumes a critical role. In this regard,

detailed project assessment needs to be carried out by undertaking various studies before

appointment of an R&M contractor. These studies mandate the need of appointment of an R&M

.consultant with suitable experience, which requires a well-defined procedure to mitigate any

future risks. Moreover, it is of critical importance that a project owner should balance risks and

responsibilities through appropriate contracts. This would require standardization of tendering

procedure for appointment of R&M consultant and contractor. Standardization will assist in

smooth and quick execution of R&M projects.

Page 91: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

82

5.2.FUTURE SCOPE OF WORK

Reducing carbon footprint in energy production activities has emerged as the one of the topmost

priorities as in India power sector is a major contributor to India‘s overall GHG emissions.

Moreover with growing economic growth the demand is going to grow more and the large

capacity installation in the pipeline might not be able to meet the demand. Further coal supply

constraint adds another dimension of distress about the economic growth. While the long term

opportunity to reshape this infrastructure to have a low carbon profile is promising, near term

opportunities to reduce carbon emissions are very limited. Because power plants account for over

40% of carbon emissions of overall India‘s GHG emission and growing at the rate of nearly

10%, improving the efficiency of the existing coal fired power plant fleet presents one of the

most promising, low cost options for reducing near term carbon emissions.

Currently there are two frameworks adopted in developed countries that can be applied to

monetize the emission reduction benefits associated with R&M of thermal power plants:

Clean Development Mechanism (CDM): The Clean Development Mechanism (CDM) allows a

country with an emission-reduction or emission-limitation commitment under the Kyoto Protocol

to implement an emission-reduction project in developing countries. Such projects can earn

saleable certified emission reduction (CER) credits, each equivalent to one tonne of CO2, which

can be counted towards meeting Kyoto targets. The mechanism stimulates sustainable

development and emission reductions, while giving industrialized countries some flexibility in

how they meet their emission reduction or limitation targets.

Verified Carbon Standard (VCS): The Verified Carbon Standard is a greenhouse gas accounting

program used by projects around the world to verify and issue carbon credits in voluntary

markets. VCS was founded in 2005 by business and environmental leaders who identified a need

for greater quality assurance in voluntary markets.

Page 92: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

83

BIBLIOGRAPHY

[1] Electric Power Research Institute (EPRI) ―Generic Guidelines for the Life Extension of

Fossil Fuel Power Plants‖, EPRI CS-4778, November, 1986

[2] EPRI ―Heat Rate Improvement Guidelines for Existing Fossil Plants‖, CS-4554, May

1986

[3] EPRI, ―Condition Assessment Guidelines for Fossil Fuel Power Plant Components‖, GS-

6724, March 1990

[4] EPRI ―Heat Rate Improvement Reference Manual‖, TR-109546, July 1998

[5] Ananth P. Chikkatur, Ambuj D. Sagar,Nikit Abhyankar and N. Sreekumar, "Tariff-based

incentives for improving coal-power-plant efficiencies in India" Energy policy 2007

[6] N. Z. Avdiu "Rehabilitation of Coal Power Plant in Kosova", IEEE 2008

[7] R.C. Bansal and J Hammons,, ―A Discussion on the Restructuring of Indian Power

Sector‖, IEEE 2007

[8] Ashish Rai, Mukesh Pandey and Prashant Baredar, ―Emerging Technologies for

Optimizing Efficiency and Minimizing GHG Emission in Existing and Upcoming Coal

Fired Plants in India‖ International Journal of Electrical, Electronics and Computer

Engineering .

[9] Ryo Fujikuraa and Mikiyasu Nakayama "Factors leading to an erroneous impact

assessment A postproject review of the Calaca power plant, unit two" ELSIVER

Environmental Impact Assessment Review 21 (2001) pp. 181-200.

[10] Naveen Shrivastava, Seema Sharma and Kavita Chauhan "Efficiency assessment and

benchmarking of thermal power plants in India" pp. 159-176, ELSEVIER Journal on

Energy Policy 2012.

[11] "Pre-feasibility studies for the new lignite fired power plant and for pollution mitigation

measure at Kosovo B power plant", EAR, contract nr. 04KOS01/03/009, January 10,

2005.

[12] S. Tavoulareas, M. Jovanic, D. Kennedy, "World Bank Assessment of Environmental

Protection and its Impacts on Power Development in South Eastern Europe", Report June

23, 2005 World Bank.

Page 93: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

84

[13] K.N. Joshi, N. Kumar, D.N. Pant, and S. Kakkar, ―Power Sectors Reforms –

Restructuring and Management of Electricity Boards‖, Proc. Sustainable Energy Options

for the New Millennium, Organized by Institution of Engineers (India), Nov. 2000, pp.

234-238.

[14] Jamasb, T.,Mota,R.,Newbery,D.,Pollitt,M.Electricity sector reform in developing

countries: a survey of empirical evidence on determinants and performance. World Bank

Policy Research Working Papers, 2005 vol.3549.

[15] Jamasb, T.,Nillesen,P.,Pollitt,M.,.Strategic behavior under regulatory benchmarking.

Energy Economics, 2004 26,825–843.

[16] Conservation, accounting and management of coal in thermal power plants, M.

Siddhartha Bhatt, Rajashekar P. Mandi and N.Rajkumar , Energy Manager, Vol. 4, No. 2,

Apr.-May 2011, pp. 51-56.

[17] N.Rajkumar, Best practices for energy conservation in cooling towers, Workshop on Best

Practices in Energy Conservation,18-20 August 2005.

[18] Siddhartha Bhatt M. and Vinita Chellapan, ―Control of specific energy consumption and

energy efficiency in selected industries for CO2 mitigation‖, Energy Research at the

Cutting Edge (ed. John R. Blackwood), Nova. Science Publishers Inc., New York, pp.

95-122.

[19] Carstairs, J., Ehrhardt, D., 1995. Financial structure in the Indian power sector. Energy

Policy 23 (11), 981–990.

[20] Hawdon, D., 1996. Performance of power sectors in developing countries—a study of

efficiency and world bank policy using data envelopment analysis. Energy Economics

Centre Discussion Paper, No. 88. Surrey.

[21] B.H. Narayana & M. Siddhartha Bhatt Modernisation of 110-120 MW units through

State of the art retrofits ,International Conference on Optimization of Existing capacity

(R&M) February 2002.

[22] R. P. Mandi, R.K. Hegde & S.N. Sinha, ―Enhancement of performance of cooling tower

in thermal power plants through energy conservation‖ ,International conference on Power

& Energy Power Tech 2005, IEEE Power Engg.

Page 94: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

85

[23] Jothi Basu Energy efficiency improvement in cooling tower of Thermal power plant – A

case study, S., Proceedings of International Conference on ―Indian Power Stations-2008‖,

13 – 15th Feb. 2008, Organized by NTPC, New Delhi, pp 293-299.

[24] Varone, F; Aebischer, B. ―Energy Efficiency: the challenges of policy design‖, Energy

Policy, 2001, Vol. 29, p615-629.

[25] R K Kaporia, S Kumar and K S Kasana, ―Technological investigations and efficiency

analysis of a steam heat exchange condenser: conceptual design of a hybrid steam

condenser,‖ Journal of Energy in Southern Africa, August 2008. vol. 19, no. 3, pp. 33-45

[26] V. S. Reddy, S. C. Kaushik, S. K. Tyagi, N. L. Panwar, ―An Approach to Analyse Energy

and Exergy Analysis of Thermal Power Plants, pp.143-152, 2006

[27] Shanmugam, K.R. and Kulshreshtha, P. ‗Efficiency of thermal power plants in India‘,

2002, Vikalpa, Vol. 27, No. 4, pp.57–-68.

[28] Bhattacharyya, S C. "Environmental-Thermal Power Generation Nexus: The Indian

Scenario," 1994, Energy and Environment, Vol 5, pp 105-20.

[29] Singh, J. "Plant Size and Technical Efficiency in the Indian Thermal Power Industry,"

1991, Indian Economic Review, Vol 26, No 2, pp 239-52

[30] C. Palanisamy, N. Sundar Babu, R. K. Chelvan, and C. Nadarajan, ―Restructuring of

Indian Power Sector with Energy Conservation as the Motive for the Economic and

Environmental Benefit‖, IEEE Trans. Energy Conversion,vol.14, no. 4, Dec. 1999, pp.

1589 - 1595.

[31] ] Edward S. Rubin, Chao Chen, Anand B. Rao "Cost and performance of fossil fuel

power plants with CO2 capture and storage" Energy Policy , 2007

[32] Quarterly Review Reports of CEA on Renovation, Modernization and Life Extension of

Thermal Power Plants in India. (January- March 2012).

[33] Policy for Private Sector Participation in R&M dated 28th October 1995.

[34] CERC- Terms and Conditions of Tariff along with all its amendments

[35] UPERC Order dated 7th Nov 2006 regarding refurbishment of 5*200 MW units at Obra

―B‖ TPS

[36] CEA performance review of thermal power stations 2010-11

[37] www.energy-community.org on 15th

June and 12th

July 2012

[38] www.esmap.org on 18th

June 2012.

Page 95: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

86

[39] www.transition.usaid.gov/in on 22nd June 2012

[40] www.cercind.gov.in on 14th

July and 28th

July 2012

[41] India Energy Book 2012 by World Energy Council

[42] Global Power Business by Dr. Rohit Verma

[43] Annual Reports and monthly magazines of Power Line 2010, 2011.

[44] ESMAP study reports on Energy Assessment and Strategy Program 2011

[45] Power plant performance by Allan.B.Gill

[46] Power Plant engineering by P.K.Nag

[47] CRISIL and ICRA, ―Rating of the State Power Sector‖, Ministry of Power, Government

of India, New Delhi, 8 January 2003.

[48] Report on tendering procedures and documents followed by public utilities for

Renovation & Modernization projects by Evonik Energy Services Ltd.

[49] Report of Energy working group of Asia Pacific Economic Co-operation

[50] Financial Management by I M Pandey

[51] Coal Fired Electric Power Life Extension: An Overview by M J Taylor and F C Fuller

Page 96: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

87

ANNEXURES

ANNEX- I: INDICATIVE QUESTIONNAIRES

a) State Electricity Utilities (SEBs)

What were Objective Criteria to go for R&M on the basis of various Assessment Tests?

S.No Criteria Yes/No Comment

1 Increase of PLF

2 Increase Availability of the Plant

3 Decrease Specific Coal Consumption of the

Plant

4 Decrease Specific Oil Consumption of the Plant

5 Improve Turbine Heat Rate or increase the

capacity increases

6 Improve Boiler Heat Rate

8 Improvement in the performance of Mill

Functions

9 Improvement in water consumption

10 Improve C&I system to reduce manual

interventions

11 Online Condition Monitoring

12 Environment (Emission level reduction)

Page 97: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

88

S.No Criteria Yes/No Comment

13 Upgrade Electrical System Reliability

14 Improvement in Water Chemistry

15 Improvement in CHP availability

16 Up-gradation of ID Fan

17 Overall Energy Efficient Plant

18 Increase Plant Safety

19 Decrease Auxiliary Power Consumption

20 Proper Metering for better Energy Measurement

21 Any Other

1. What were the factors that were looked into while preparing the scope of work?

2. How were the R&M Team selected?

3. Were the Scope of Work developed after careful consideration of the following criteria:

Page 98: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

89

S.No Criteria Yes/No Comment

1 RLA Studies and Life Extension

2 Complete Condition Studies

3 Post Overhaul Evaluation Test

4 Post Overhaul Energy Audit

5 Utility Experience

6 Discussions with OEMs and

Consultants

4. Was the finalization of scope done keeping the balance of both Technical and

Commercial aspects of the project?

5. Were Cost and Time factors taken into consideration?

6. Were Risk Analysis/Evaluations done?

7. Did the utility interact with OEMs and Consultations?

8. Was Cost-Benefit (CB) analysis done? What costs and benefits were taken into account?

9. Whether tariff calculated after R&M were within the permissible Regulatory Band? If

not, what steps were taken?

10. Were there any interactions with the Regulator during the preparation of proposed tariff

after R&M?

Page 99: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

90

11. Were the tariff before R&M and after R&M were taken into consideration or not? If not,

why?

12. After finalization of scope, how were the costs, what types of costs were considered? Did

they look into OEMs budgetary offers? Were there any comparisons of OEMs?

13. What were the qualifying requirements put in preparation of bid to get response from

bidders?

14. How was the response? How many bid documents were purchased and how many

actually submitted

15. What was the consultant‘s overall experience in Preparation of Bids?

16. What was the form of contract in terms of base price or unit price?

17. How were the scopes surprises dealt?

18. How was the bidding done? How was the negotiations done?

19. What were the selection criteria?

20. What was the technical financial ratio taken? Why and How?

21. While planning for shutting down the plant, did the utility tie up capacity from the central

sector unallocated quota of 15%?

22. Did the utility tie up with the Power trading companies?

23. What other planning was taken into consideration?

24. Were Road Permits taken during transportation of Materials?

Page 100: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

91

25. How was the movement of materials planned? Were delays like Road accidents etc taken

into consideration?

26. Were any priorities on basis of importance given to any material‘s arrival at the site?

How was it prioritized?

27. Were inspectors present during R&M? Did the utility tie up with any inspectors?

28. Were Equipments/Instruments ready to measure Performance Guarantee Tests?

29. Did the plant stabilize after R&M? What problems did it face?

30. Were there any discussions with the R&M Agencies initially regarding clarifications of

the Performance Guarantee Tests?

31. Were penalties inbuilt if Performance Guarantee Tests failed?

32. Did the utility provide samples like coal etc. to the OEMs to be analyzed in their lab so

that proper specifications could be provided?

33. After the R&M, did the utility initiate Operation Efficiency Cell?

34. How were the maintenance planning done?

35. Were any training provided to the engineers for safe and correct operations of the new

equipments? Who were given?

b) REGULATORS

c) EXECUTING AGENCY

Page 101: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

92

ANNEX-II: KEY CONCERN OF STAKE HOLDERS

Page 102: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

93

ANNEX-III: LIST OF POWER PLANT VISITS AND THEIR CURRENT STATUS

S.

No

Unit

No. Capacity

(MW)

Name of

Thermal

Power

Station (TPS)

Name of

Utility/State

Executing

Agency

Completion of LE

Works

1 1, 2

& 3

3 x 110 Bhatinda TPS PSPCL/

Punjab

Unit 1 -

NASL,

Unit 2&3-

BHEL

Unit 1- Unit was

synchronized on 8 Feb

2007 after LE works

Unit 2- Unit was

synchronized on 5

Oct 2005 after LE

works

Unit 3 –

Synchronization

expected by

November 2011 after

LE works

2 1& 4,

5 & 6

2x50,

2 x 120

Korba (East)

TPS

CSPGCL/

Chhattisgarh

Unit 1&4,

ABB

Alstom,

Unit 5 & 6-

BHEL,

Unit 1- Unit was

synchronized on 31

Mar 2004 after LE

works.

Unit 4- Unit was

synchronized on 3 Oct

2003 after LE works.

Unit 5- Unit was

synchronized on 3

Mar 2005 after LE

works

Unit 6- Unit was

synchronized on 8

October 2003 after

LE works

3 1,3

&4

3x110, Panipat TPS HPGCL/

Haryana

Unit 1-

BHEL,

Unit 3 & 4-

Yet to be

awarded

Unit 1- Unit was

synchronized on 4

Nov 2008 after LE

works

Unit 3 &4 – DPRs for

LE works is under

finalization.

4 1& 2 2x120 Ukai TPS GSECL/

Gujarat

BHEL Unit 1- Unit was

synchronized on 24

Page 103: DECLARATION - National Power Training · PDF fileDECLARATION I, Satyanarayan ... and through Renovation and Modernization (R&M) ... 110 MW Table 3.1 Current Power Sector Market Scenario

94

May 2008 after LE

works

Unit 2 – Unit was

synchronized on 24

February 2010 after

LE works

5 1 & 2 2x120 Amarkantak

Extension

TPS

MPPGCL/

Madhya

Pradesh

BHEL Unit 1- Expected date

of Completion by

October 2011

Unit 2 – Unit was

synchronized on 26

October 2010

6 9 &

10

2x200 Obra TPS UPRUNVL/

Uttar Pradesh

BHEL Unit 9- Synchronized

in September 2010.

Unit is under

stabilization after

R&M

Unit 10 –Shut down is

expected in October

2011. LE works to be

completed in 2012-13

7

7

1x110

Barauni TPS

BESB/Bihar

BHEL

Completion of LE

works is expected in

2012-13

8

1

1x110

Muzzaffurpur

KBUNL/Bihar

BHEL

Expected date of

Completion November

2011 after LE works

9

5

1x110

Bandel TPS

WBPDCL/

West Bengal

Yet to be

awarded

Procurement of

executing Agencies

are under process

10

6

1X210 Koradi TPS MSPGCL/

Maharashtra

Yet to be

awarded

Procurement of

executing Agencies

are under process

Total No of TPS- 10