Dec 12-14, 2005 TBM Planning and Costing Meeting
DCLL R&D Evaluations Summary
Compiled by Neil Morley for the TBM Planning and Costing Meeting
Dec 12-14, 2005
Dec 12-14, 2005 TBM Planning and Costing Meeting
Main DCLL R&D areas
R&D Morley 47 Subtasks
Tritium Control Merrill/Willms 3 subtasks
Thermofluid MHD Smolentsev 7 subtasks
SiC/SiC Fab Process & Properties Katoh 6 subtasks
SiC/PbLi/FS Compatibility Pint 4 subtasks
FS Box Fabrication & Material Issues Rowcliffe/Kurtz/Dagher 10 subtasks
Helium Systems Subcomponent Tests Wong 2 subtasks
PbLi Hydrogen Production Merrill 1 subtask
Be Joining to FS Zinkle,Ulrickson 4 subtasks
Virtual TBM Abdou 3 subtasks
Advanced Diagnostics Morley 4 subtasks
Integrated mockup tests Tanaka/Fogarty 3 subtasks
Dec 12-14, 2005 TBM Planning and Costing Meeting
Evaluating R&D Tasks Summarize the main purpose of this subtask. What critical need does this R&D
address? Is it more oriented towards (1) Establishing basic TBM feasibility for fusion (2) Understanding/predicting TBM performance required for design, or (3) Adding to safety and qualification database.
Summarize the risks to the machine or mission if this R&D is not performed. Do you have suggestions for modification of this R&D Subtask to make it more useful
or cost effective? For instance, you know of specific facilities, past work, capabilities that already exist that could be tapped for this work? Etc.
Categorize this subtask based on the following system: – E = Essential for the qualification and successful execution of the TBM experiment, and no
other party is doing it– I = Important for the qualification and successful execution of the TBM experiment, or
Essential but is definitely being done by another party– D = Desirable but the risk is acceptable if not performed
Categorize this subtask schedule over the next 10 year period based on the following system
– B = Beginning 3-4 years. Needed immediately for preliminary design choices– M = Middle 3-4 years. Needed in the middle of the next 10 years after initial R&D is
performed (for instance for qualification or integrated effects tests).– E = Ending 3-4 years. Needed before performance of first experiments or is specific for
subsequent modules
Dec 12-14, 2005 TBM Planning and Costing Meeting
10 year R&D Cost Estimate Summary (burdened, 2005 dollars, no contingency)
R&D ~$47.3M
Tritium Permeation ($2.8M)+$1m
Thermofluid MHD $10M
SiC/SiC Fab Process & Properties $2.25M
SiC/PbLi/FS Compatibility $.75M
FS Box Fabrication & Material Issues $15M
Helium Systems Subcomponent Tests $.84M
PbLi Hydrogen Production $2.4M
Be Joining to FS (TBM PFC) $4.7M
Virtual TBM $4.3M
Advanced Diagnostics $2.7M
Integrated mockup tests $4.34M
Dec 12-14, 2005 TBM Planning and Costing Meeting
DCLL 1st Test Module Fabrication Schedule Summary
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015
Administration
R&D
Thermofluid & Performance R&D
Fabrication and Properties R&D
Partially Integrated Tests
Engineering
Preliminary Design
Detailed Design
Title III Activities (Fab Support)
TBM Fabrication
Bid Package Contract Award
Material Procurement
Tooling & Processing
Prototype Fabrication
TBM Fabrication
Assembly, Testing, and Installation
Prototype Packaging & Shipping
Prototype Testing
TBM QA Tests
TBM Packing and Shipping
TBM Assembly & Port Integration
DCLL Test Module Schedule
First plasmaQualification Criteria Safety Dossier
TBMExperiment Execution
Permission to Install
TBMExperiment Execution
*Prototype may or may not be full scale
Dec 12-14, 2005 TBM Planning and Costing Meeting
Main DCLL TBM R&D areas
R&D Morley 47 Subtasks
Tritium Control Merrill/Willms 3 subtasks
Thermofluid MHD Smolentsev 7 subtasks
SiC/SiC Fab Process & Properties Katoh 6 subtasks
SiC/PbLi/FS Compatibility Pint 4 subtasks
FS Box Fabrication & Material Issues Rowcliffe/Kurtz/Dagher 10 subtasks
Helium Systems Subcomponent Tests Wong 2 subtasks
PbLi Hydrogen Production Merrill 1 subtask
Be Joining to FS Zinkle,Ulrickson 4 subtasks
Virtual TBM Abdou 3 subtasks
Advanced Diagnostics Morley 4 subtasks
Integrated mockup tests Tanaka/Fogarty 3 subtasks
Yellow indicates some disagreement
Dec 12-14, 2005 TBM Planning and Costing Meeting
Resolving remaining conflicts
Let me speak to coordinator and people offering dissenting opinions and make a judgment for the first draft of the report
People can make a case offering a different opinion and we will note it in the report as well
Other suggestions? Committee, etc…
Dec 12-14, 2005 TBM Planning and Costing Meeting
What needs to be provided/written by task coordinators by Dec 23
Review the WBS structure (Attachment 1) and provide any suggested changes before proceeding with the following actions. Create lower level WBS elements to the point where costs will be collected (subtask level either 6 or 7).
Prepare a brief description of the work scope content for each WBS element for which you are responsible utilizing the format provided in Attachment 2. These descriptions should clearly reflect what is included or excluded from the associated estimate and the basis for the scope and requirements.
Dec 12-14, 2005 TBM Planning and Costing Meeting
What needs to be written (cont.)
Fill in the detailed cost sheet (Attachment 3), one for each WBS subtask level 6 and 7. For the current pre CD-0 cost activity, it is not necessary to have every element on the form completed, but where the detail is available, please provide it. Contingency is not included in the base cost.
Complete Attachment 4 by summarizing the detailed cost sheets completed in action 3.
Using Tables 2 and 3, fill in the assessment of the technical, cost, and schedule risks and the weighting factors on the bottom section of the detailed cost sheets generated in step 4 (Attachment 3) (one for each WBS level 6 and 7).
Dec 12-14, 2005 TBM Planning and Costing Meeting
What needs to be written (cont.)
Using the format in Attachment 4, provide a schedule network (list of activities and durations) for all of your Level 6 and 7 WBS elements, with at least 3 activities listed for each WBS element. When designating predecessors or successor activities, please be sure to consider activities that must be done by other participants and the Planning Milestones (see attachment 5). List key assumptions.
Review the milestones provided in Attachment 5; suggest others to show start or finish of significant project tasks. Provide the expected completion dates.
For each WBS level 5 (or below) list and describe the major risks utilizing Attachment 6 and the guidelines in Tables 4 – 6.