Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

60
A Fairfax County, VA, publication Department of Public Works and Environmental Services Working for You! Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan Community Meeting Dolley Madison Library May 4, 2016

Transcript of Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

Page 1: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

A Fairfax County, VA, publication

Department of Public Works and Environmental Services

Working for You!

Dead Run Stream Restoration ProjectSegments 2/3 – Final Concept PlanCommunity MeetingDolley Madison Library

May 4, 2016

Page 2: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

2

Dead Run Segment 2/3 Stream Restoration Project

Stormwater Planning Division

Meeting Outline

• Project Scope• Project Timeline• Background• Existing Conditions• Task Force and Community Involvement • Revised Final Concept Changes – Summary• Proposed Condition Renderings• Revised Final Concept Design Approach• Buffer and Riparian Corridor Restoration Plan• Next Steps• Q&A

Page 3: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

3

Dead Run Stream Restoration

Project Limits – Two Projects

Segment 2:McLean Central Park• 750 linear feet of main

channel and 560 feet of tributary channels

Segment 3:Dead Run Stream Valley Park• 1,460 linear feet of main

channel and 350 feet of tributary channels

Segment 1:Dominican Retreat• 1,500 linear feet of main

channel and 380 feet of tributary channels

Page 4: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

4

Dead Run Stream RestorationSegment 2 – McLean Central Park• 750 linear feet main

channel and 560 feet of tributary channels

• Completely in Park

• Starts below previously restored section near library

Page 5: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

5

Dead Run Stream RestorationSegment 3 – Dead Run Stream Valley Park• 1,460 linear feet of main channel

and 350 feet of tributary channels

• Extends to Churchill Road

• Residential lots along Elizabeth Drive and Carol Raye Street

Page 6: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

6Stormwater Planning Divison

Dead Run Segment 2/3 Stream Restoration Project

Project timeline• Fall, 2013: Project initiated

• Winter, 2013: Surveys and assessment completed

• April, 2014: Pre-concepts submitted

• April 23, 2014: First public meeting

• August 15, 2014: Field walk with FCPA, MTF, Urban Forestry

• February, 2015: Pre-concept revisions to minimize tree loss completed

• February 18, 2015: Second public meeting

• May 12, 2015: Revised concept plan with alternative access options for Segment 3 completed

• May 19, 2015: Third public meeting and first field walk with community

• June 9, 2015: Fourth public meeting and second field walk with community

Page 7: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

7Stormwater Planning Divison

Dead Run Segment 2/3 Stream Restoration Project

Project timeline• Community Stream Team – Task Force

• Held 4 meetings between August and December 2015

• Visited completed stream restoration sites

• Met with residents adjacent to project in March, 2016

• Revised final concept design completed in April, 2016.

Next Steps:

• Site visit with Community (May 19, 2016)

• Final design phase

• Coordination with task force and community

• Final construction documents and bidding

• Pardon our dust community meeting and construction

• Post-construction monitoring and maintenance

Page 8: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

Stormwater Planning Division

Watershed Planning and Project Implementation

• Watershed Characterization– Water Quality Monitoring– Physical Stream Assessment– Land Use Change– Pollutant Loading

• Structural Project– 25 year plan

• Non-Structural Practices– Policy and Regulations

8

http://www.fairfaxcounty.gov/dpwes/watersheds/

Page 9: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

9Stormwater Planning Division

Watershed Planning and Project Implementation

• Dead Run has a drainage area just over 3 mi2

• 24 priority projects identified in the watershed management plan• Pond retrofits• LID Stormwater Enhancements• Stream Restoration• Neighborhood Stormwater

Improvements

http://www.fairfaxcounty.gov/dpwes/stormwater/projects/project_list.htm

Page 10: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

10Stormwater Planning Division

Stormwater Program Regulatory Drivers

• National Pollutant Discharge Elimination System (NPDES)

• Virginia Stormwater Management Program (VSMP)– Municipal Separate Storm Sewer Permit (MS4)– Discharge from approximately 7,000 storm drain outfalls– Includes watershed planning and project implementation

• Total Maximum Daily Loads (TMDLs)– Chesapeake Bay– Local Streams– Establishes pollutant loading budget for a given impaired water

body to meet water quality standards

Page 11: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

11Stormwater Planning Division

Dead Run– Stream Conditions

http://www.deq.virginia.gov/Programs/Water.aspx

Page 12: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Existing Conditions - Biological Monitoring Data

12

Page 13: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

13Stormwater Planning Division

Dead Run– Stream Conditions

Fairfax County Annual Water Quality Report• http://www.fairfaxcounty.gov/hd/streams/strannualrpt.htm

Virginia Department of Environmental Quality • Water Quality Report (305b report)• http://www.deq.virginia.gov/Programs/Water.aspx

U.S. Geological Survey• Dead Run stream gage at Whann Avenue• Fairfax County Water Resources Monitoring• http://va.water.usgs.gov/fairfax/

Page 14: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

14

Page 15: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

15Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Dead Run Stream Valley – A historical perspective

1937

Page 16: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

16Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Dead Run Stream Valley – A historical perspective

1954

Page 17: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

17Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Dead Run Stream Valley – Today

2015

Page 18: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

18Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Segment 2 Existing Conditions

Page 19: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

19Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Segment 2 Existing Conditions

Stream Bank Erosion and at Risk Trees

Page 20: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

20Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Segment 3 Existing Conditions

February 2012

July 2015

Trees along stream bank continue to fall and/or die

Page 21: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

21Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Segment 3 Existing Conditions

Page 22: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

22Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Segment 3 Existing Conditions

Page 23: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

23Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Segment 3 Existing Conditions

Page 24: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

24Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Segment 3 Existing Conditions

February 2012

July 2015

Page 25: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

25Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Segment 3 Existing Conditions

Page 26: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

26Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Segment 3 Existing Conditions

Page 27: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

27Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Segment 3 Existing Conditions

Bridge at Churchill Road

Page 28: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

28Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

On-line: Story Map of Existing ConditionsExisting conditions: http://arcg.is/1Y55MNj

Page 29: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

29

Dead Run Segment 2/3 Stream Restoration Project

Stormwater Planning Division

Summary of Task Force Comments and Concerns• Project Benefits • Design Approach • Tree Loss• Frequent Yard Flooding• Flooding at Churchill Road• Construction Equipment and Footprint • Trail Closures• Invasive Plant Management• Others

– Site restoration and maintenance– Stream conditions and erosion below Churchill Road

Page 30: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

30

Dead Run Segment 2/3 Stream Restoration Project

Stormwater Planning Division

Project Benefits

• Estimated annual erosion rates for Segment 2/3 based on field data is between 783 to 1,500 tons/year

Stream Bank Erosion Field Data• Chesapeake Bay Expert Panel protocols used for estimating stream restoration nutrient and sediment credits.

• Estimated reduction in Total Phosphorus loading is between 190 and 788 lbs/year

Page 31: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

31

Dead Run Segment 2/3 Stream Restoration Project

Stormwater Planning Division

Churchill Road Flooding

• VDOT staff attended last Stream Team meeting (December, 2015)

• VDOT inspection reports indicate no deficiencies with the bridge

• No current or future project planned for the bridge at this time

• Proposed stream restoration project includes removing sediment and debris upstream of the bridge and aligning channel with bridge abutments.

Page 32: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

32Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Churchill Road Bridge Backwater area

Page 33: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

33Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Summary of Plan Revisions – Tree LossTree Loss Summary

Date 6” to 12” 12” and Larger Total Trees at Risk

February 2014Not Surveyed

137 137

February 2015 110 110

May 2015

Alt 1 133 88 221

Alt 2 153 98 251

December 2015

Alt 1 76 72 148 48

Alt 2 81 72 153 45

Alt 1 and Alt 2 refer to access alternatives 1 and 2:Alt 1: Access road is closer to the stream for Segment 3Alt 2: Access road follows trail and utilizes cut-throughs for access to stream for Segment 3.

Page 34: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

34Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Summary of Plan Revisions – Tree Loss

• Total number of trees to be removed for project (148-153)

• Total number of trees within the LOD that were either dead or at risk (45-48) – approximately 1/3rd

• Reduction in tree loss impact as a result of design modification between May 2015 and December 2015:

• Alt 1 – 73 trees saved (33% reduction)

• Alt 2 – 98 trees saved (39% reduction)

• Existing trees have very little diversity with only 2 species making up the majority of trees: red maples and tulip poplars.

Page 35: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

35Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Proposed Planting

• Proposed Planting Based on Alternative 1

• Approx. 250 trees 1 inch to 1.5 inch caliper size

• Approx. 500 trees that are 6 to 8 feet tall

• Approx. 2,600 shrubs

• All vegetation is native species and specifically selected for the stream corridor

Page 36: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

36

Dead Run Segment 2/3 Stream Restoration Project

Stormwater Planning Division

Dead Run Stream Restoration Project

Existing Park Conditions• Park Area = 33.25 acres• Tree Canopy = 27.45 acres

Page 37: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

37Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Summary of Plan Revisions – Area disturbed Total Acres* Woodland /

Open**May 2015

Alt 1 ~5.05 Acres 3.65Alt 2 ~5.15 Acres 3.75

December 2015 Alt 1 ~4.58 Acres 3.18Alt 2 ~4.72 Acres 3.32

*Excludes trail area, ** Excludes stream channel area and trail area

Conclusion Alt 2 access has slightly more disturbance and would close the trails for a longer period of time compared to Alt 1, and would likely necessitate the use of woodchip trails which would have additional impacts.

The overall area of disturbance has been reduced by 10% from May 2015. If the stream channel area (1.4 ac) is excluded (i.e only impacts to woodland/open areas considered), the actual AOD has been reduced by 11-13%

Page 38: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

38Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Summary of Plan Revisions – Channel Size

Segment 2 Upper Segment 3 Lower Segment 3

Existing channel size(SF) 59-82 57-113 62-70Proposed channel size (SF) 55-80 60-129 62-72

Proposed channel size is now comparable in size to the existing channel.

This channel was sized using natural channel design principles and represents a balance to minimize impacts but still provide long-term channel stability and water quality benefits.

Page 39: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

39

Dead Run Segment 2/3 Stream Restoration Project

Stormwater Planning Division

Summary of Plan Revisions – Floodplain and Drainage

• No change in 100-year or FEMA floodplain

• No rise certification• Improve drainage from

existing storm drains

Fairfax County 100-Year Floodplain

FEMA Special Flood Hazard Area

Page 40: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

40Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Proposed Conditions Renderings – Segment 2

Existing Conditions

Page 41: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

41Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Proposed Conditions Renderings – Segment 2

Rendering of Proposed Conditions

Page 42: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

42Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Proposed Conditions Renderings – Segment 3

Existing Conditions

Page 43: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

43Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Proposed Conditions Renderings – Segment 3

Rendering of Proposed Conditions

Page 44: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

44Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Proposed Conditions Renderings – Segment 3

Existing Conditions

Page 45: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

45Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Proposed Conditions Renderings – Segment 3

Rendering of Proposed Conditions

Page 46: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

46Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Proposed Conditions On-line Map Tour

http://arcg.is/1N4KSgq

Page 47: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

Dead Run Segment 2/3 Stream Restoration Project

Stormwater Planning Division

Riparian Corridor Restoration Plan

47

Page 48: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

Dead Run Segment 2/3 Stream Restoration Project

Stormwater Planning Division

Existing vegetation baseline characterization

48

Existing Vegetation classified into 5 major areas:

MCPP1: Gazebo area, Area near Martha Jane Street

MCPP2: Areas adjacent to Segment 2 and upstream of Segment 2.

MCPP3: Adjacent to Segment 3

MCPP4: Area to the right of trail along middle and lower Segment 3 (looking towards Churchill Road

MCPP5: Area to the right when entering park from Oak Ridge Avenue (near tennis courts)

Story Map: http://arcg.is/1TKK67P

Page 49: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

Dead Run Segment 2/3 Stream Restoration Project

Stormwater Planning Division

Existing vegetation baseline characterization

49

Page 50: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

Dead Run Segment 2/3 Stream Restoration Project

Stormwater Planning Division

Dolley Madison Library Outfall before Restoration

50

Page 51: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

Dead Run Segment 2/3 Stream Restoration Project

Stormwater Planning Division

Existing vegetation baseline characterization

51

Page 52: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

Dead Run Segment 2/3 Stream Restoration Project

Stormwater Planning Division

Existing vegetation baseline characterization

52

Page 53: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

Dead Run Segment 2/3 Stream Restoration Project

Stormwater Planning Divison

Existing vegetation baseline characterization

53

Page 54: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

Dead Run Segment 2/3 Stream Restoration Project

Stormwater Planning Division

Existing vegetation baseline characterization

54

Page 55: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

55

Dead Run Segment 2/3 Stream Restoration Project

Stormwater Planning Division

Elements of Riparian Corridor Restoration Plan

• Invasive Plant Management• Planting plan

– Inside and outside project limits within park

• Residential lots adjacent to stream

• Warranty requirements (2-years)• Long-term monitoring and

maintenance

Page 56: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

Dead Run Segment 2/3 Stream Restoration Project

Stormwater Planning Division

Chesapeake Bay Preservation Ordinance Resource Protection Area (RPA)

56

http://www.fairfaxcounty.gov/dpwes/environmental/cbay/

Page 57: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

57Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Proposed Planting

• Proposed Planting Based on Alternative 1

• Approx. 250 trees 1 inch to 1.5 inch caliper size

• Approx. 500 trees that are 6 to 8 feet tall

• Approx. 2,600 shrubs

• All vegetation is native species and specifically selected for the stream corridor

Page 58: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

58Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Next Steps

• Continue to work with residents to develop buffer enhancements on private lots adjoining Segment 3.

• Site visit (May 19, 2016) – trees to be flagged

• Final design phase and prepare construction documents

• Coordination with Task Force and community

• Bidding and contract award

• Pardon Our Dust Meeting

• Construction

• Post-construction monitoring and maintenance

Page 59: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

59

Dead Run Segment 2/3 Stream Restoration Project

Stormwater Planning Division

Next Steps: Site VisitSite Visit

• Date: Thursday, May 19, 2016

• Time: 6:30 – 8:00 pm

• Meeting Location: McLean Central Park - Pedestrian bridge crossing Dead Run near tennis courts

Meeting Location

Page 60: Dead Run Stream Restoration Project Segments 2/3 – Final Concept Plan

Additional Information

For additional information, please contact

www.fairfaxcounty.gov/dpwes

60

Dead Run Segment 2/3 Stream Restoration Project

Stormwater Planning Division

Dipmani KumarProject Manager

[email protected]