Day 3 Analogous, estimates and semantics for process

15
Estimation course Introducing ANALOGOUS ESTIMATE

Transcript of Day 3 Analogous, estimates and semantics for process

Page 1: Day 3   Analogous, estimates and semantics for process

Estimation course

Introducing

ANALOGOUS ESTIMATE

Page 2: Day 3   Analogous, estimates and semantics for process

This is how Mgt views your estimates

Page 3: Day 3   Analogous, estimates and semantics for process

This is how they will treat the estimates

Take your time and do them well

Page 4: Day 3   Analogous, estimates and semantics for process

Analogous estimates

What is an analogy?

Page 5: Day 3   Analogous, estimates and semantics for process

Analogy explained

Page 6: Day 3   Analogous, estimates and semantics for process

Steps to analogy

1. Find out the parameters of project2.Find the project from past which

maps best3.Find out the changes as they are

today4.Account for the changes5.Compute the estimates

Page 7: Day 3   Analogous, estimates and semantics for process

Examples

Building a standard home

6 months

Road trip to Ladakh on a Pulsar

15 Calendar days

Page 8: Day 3   Analogous, estimates and semantics for process

Analogous Estimates are applicable when

The following are available1.Historical records2.High Congruence3.Trustable data4.Same units5.Variance in operatingConditions known

Page 9: Day 3   Analogous, estimates and semantics for process

Analogous :

Project Parameters, Performance details of previous projects . Minor variance in operating conditions

Precise Inputs

Precise Output

Project Likely timeLikely cost

Page 10: Day 3   Analogous, estimates and semantics for process

Typical timelines

http://www.amazon.com/Eliciting-Analyzing-Expert-Judgment-Probability/dp/0898714745

Page 11: Day 3   Analogous, estimates and semantics for process

Process Semantics

Action Block

I

STARTING INPUT

TECHNIQUES AND TOOLS

MAIN OUTPUT

BYPRODUCTS& WASTE

FEEDBACK LOOP

Page 12: Day 3   Analogous, estimates and semantics for process

Estimation in Windows copy file dialog

Page 13: Day 3   Analogous, estimates and semantics for process

Top down and bottoms up

Page 14: Day 3   Analogous, estimates and semantics for process

Assignment on Expert judgment

1. Context : You are the President of US and have got confirmed intelligence on the hideout of Osama Bin Laden and have decided to authorize his capture/killing . The operation involves Transporting elite Navy seals, Air Operations to transport ammunitions and equipment , Land operations to neutralize the guards and defenses and recover evidences . Finally transport the seals and body of Osama to a Naval vessel and do the final rites .

2. Divide the team into 3 groups : Air , Navy , Land3. Each team solves the problem of finding the time and aggregate cost of the

operation .4. Allow each team to complete the plans and summarize the figures to team5. Compare the estimates and plannings with actual operation : http://

en.wikipedia.org/wiki/Death_of_Osama_bin_Laden#Operation_Neptune_Spear

Page 15: Day 3   Analogous, estimates and semantics for process

What’s Your Message? DRIVE WELL