Day 2 Transmission Line Protection
Transcript of Day 2 Transmission Line Protection
-
8/3/2019 Day 2 Transmission Line Protection
1/38
TRANSMISSION LINEPROTECTION
TRANSMISSION LINEPROTECTION
20 December 2010 1Protection Courses
-
8/3/2019 Day 2 Transmission Line Protection
2/38
-
8/3/2019 Day 2 Transmission Line Protection
3/38
20 December 2010 3Protection Courses
TUTORIAL SCOPE8. LOAD ENCROACHMENT9. LOSS OF POTENTIAL10. UNIT PROTECTION11. PERMISSIVE UNDER REACH12. PERMISSIVE OVER REACH13. CARRIER BLOCKING14. CURRENT REVERSAL15. ZONE 1 EXTENSION
-
8/3/2019 Day 2 Transmission Line Protection
4/38
20 December 2010 4Protection Courses
TUTORIAL SCOPE16. WEAK IN-FEED17. SERIES COMPENSATION18. MUTUAL COMPENSATION19. AUTO RECLOSER20. STUB PROTECTION21. CCVT TRANSIENT22. DIRECTIONAL EARTH FAULT
-
8/3/2019 Day 2 Transmission Line Protection
5/38
20 December 2010 5Protection Courses
MHO CHARACTERISTICS
MHO
-
8/3/2019 Day 2 Transmission Line Protection
6/38
20 December 2010 6Protection Courses
MHO CHARACTERISTICS
-
8/3/2019 Day 2 Transmission Line Protection
7/38
20 December 2010 7Protection Courses
QUADRILATERAL CHARACTERISTICS
Quadrilateral
-
8/3/2019 Day 2 Transmission Line Protection
8/38
20 December 2010 8Protection Courses
OFFSET MHO CHARACTERISTICS
-
8/3/2019 Day 2 Transmission Line Protection
9/38
20 December 2010 9Protection Courses
-
8/3/2019 Day 2 Transmission Line Protection
10/38
20 December 2010 10Protection Courses
POLARIZATION METHODS SELF POLARIZATION
Terminal faults will not cover CROSS POLARIZATION
Use other healthy phase voltages Terminal three phase fault will not cover
MEMORY POLARIZATION Covers all type of faults
-
8/3/2019 Day 2 Transmission Line Protection
11/38
20 December 2010 11Protection Courses
VR
VB
VY
VRB
VBY
VYR
POLARIZATION METHODS
-
8/3/2019 Day 2 Transmission Line Protection
12/38
20 December 2010 12Protection Courses
S/Stn 1 S/Stn 2 S/Stn 3
Time
Zone 3R
Zone 3R
Zone 3R
Zone 2
Zone 2Zone 3R
Zone 2
RelayA
RelayB
RelayC
RelayD
Zone 3F
Zone 2Zone 3
Zone 1
Zone 1
Zone 1
Zone 1
ZONES SETTING CRITERIA
-
8/3/2019 Day 2 Transmission Line Protection
13/38
20 December 2010 13Protection Courses
A B C
X
R
Zone 1
Zone 3Zone 2
ZONES SETTING CRITERIA
Zone 4
-
8/3/2019 Day 2 Transmission Line Protection
14/38
20 December 2010 14Protection Courses
SWITCH ON TO FAULT SWITCH ON TO FAULT.
Failure to remove Earth Clamps after CB Maintenance
Practically Zero Impedance in fault path.
Fault Point is at the Origin - Boundary condition for Zones 1 & 2 For a 3-Phase fault, cross-polarising will have no effect
SOTF Fault Point
-
8/3/2019 Day 2 Transmission Line Protection
15/38
20 December 2010 15Protection Courses
AC SOTF - Used where VT is on LINE SIDE of the CBIF Current and Voltage have been Dead for 10 SecsAND the Current Rises ABOVE 30% of Nominal
AND Voltage remains BELOW 20% of NominalTHENRemove the Time Delay from Zone 3AND
Allow tripping on Overcurrent onlyFOR200ms
DC SOTF - Used where VT is on BUSBAR SIDE of the CB
When Circuit Breaker Manual Close Handle is OperatedRemove the Time Delay from Zone 3FOR 400ms
(Longer delay allows for CB Closing time)
SOTF ALGORITHMS
-
8/3/2019 Day 2 Transmission Line Protection
16/38
20 December 2010 16Protection Courses
Power Swing Outer
boundary
Power Swing Inner
boundary
Transittime
PowerswinglocusZone 1
Zone 2
Zone 3
If the System
ImpedanceRemains in thePower SwingDetection Zone forlonger than thePSD Transit Time
(Nominally 50 ms)POWER SWINGALARMwill Operate
POWER SWING DETECTION & BLOCKING
-
8/3/2019 Day 2 Transmission Line Protection
17/38
20 December 2010 17Protection Courses
POWER SWING DETECTION & BLOCKING
-
8/3/2019 Day 2 Transmission Line Protection
18/38
20 December 2010 18Protection Courses
LOAD ENCROACHMENT
-
8/3/2019 Day 2 Transmission Line Protection
19/38
20 December 2010 19Protection Courses
LOSS OF POTENTIAL
-
8/3/2019 Day 2 Transmission Line Protection
20/38
20 December 2010 20Protection Courses
Zone 2Carrier
AidedTrip
S/Stn 1 S/Stn 2
Time
Zone 1 (No Operation)
Distance
Distance
Zone 1
Relay
B
Relay
C
Relay
A Signalling Channel
Zone 2Time Delayed Trip
Operation of Zone 1 sends signal to remote end
Instantaneous trip if
Zone 1 Operation
Zone 2 + Signal from Remote end
ALLOWS INSTANTANEOUS TRIPPING OVER 100% OF THE LINE LENGTH
Zone 2
SIGNALLING CHANNELREQUIRED BETWEENENDS
PERMISSIVE UNDER REACH
-
8/3/2019 Day 2 Transmission Line Protection
21/38
20 December 2010 21Protection Courses
Zone 2Carrier
AidedTrip
S/Stn 1 S/Stn 2
Time
Zone 1 (No Operation)
Distance
Distance
Relay
B
Relay
C
Relay
A Signalling Channel
Zone 2Time Delayed Trip
Instantaneous Operation of Zone 2 sends signal to remote end
Instantaneous trip if
Zone 1 Operation
Zone 2 + Signal from Remote end
Zone 2Zone 2 Instantaneous
Zone 1
SIGNALLING CHANNELREQUIRED BETWEENENDS
ALLOWS INSTANTANEOUS TRIPPING OVER 100% OF THE LINE LENGTH
PERMISSIVE OVER REACH
-
8/3/2019 Day 2 Transmission Line Protection
22/38
20 December 2010 22Protection Courses
Zone 2Carrier
AidedTrip
S/Stn 1 S/Stn 2
Time
Zone 1 (No Operation)
Distance
Distance
Zone 1
Relay
B
Relay
C
Relay
A Signalling Channel
Zone 4 - Blocking
Operation of Zone 4 sends blocking signal to remote end
Instantaneous trip if
Zone 1 Operation
Zone 2 + No blocking Signal from Remote end WITHIN the Permissive Trip Time
Zone 2
SIGNALLING CHANNELREQUIRED BETWEENENDS
ALLOWS INSTANTANEOUS TRIPPING OVER 100% OF THE LINE LENGTH
BLOCKING SCHEME
-
8/3/2019 Day 2 Transmission Line Protection
23/38
20 December 2010 23Protection Courses
Zone 2CarrierAidedTrip
S/Stn 1 S/Stn 2
Time
Zone 1 (No Operation)
Distance
Distance
Zone 1
RelayB
RelayC
RelayA Signalling Channel
Zone 4 - Blocking(No Operation)
Operation of Zone 4 sends blocking signal to remote end
Instantaneous trip if
Zone 1 Operation
Zone 2 + NO BLOCKING SIGNAL from Remote End
WITHIN the Permissive Trip Time
Zone 2
SIGNALLING CHANNELREQUIRED BETWEENENDS
ALLOWS INSTANTANEOUS TRIPPING OVER 100% OF THE LINE LENGTH
BLOCKING SCHEME
-
8/3/2019 Day 2 Transmission Line Protection
24/38
24Protection Courses
CURRENT REVERSAL
20 December 2010
-
8/3/2019 Day 2 Transmission Line Protection
25/38
20 December 2010 25Protection Courses
CURRENT REVERSAL
-
8/3/2019 Day 2 Transmission Line Protection
26/38
20 December 2010 26Protection Courses
CURRENT REVERSAL
-
8/3/2019 Day 2 Transmission Line Protection
27/38
20 December 2010 27Protection Courses
Relay
A
Relay
B
Relay
C
S/Stn 1 S/Stn 2
Relay
C
S/Stn 3
Time
Gives improved fault clearancetime for fault @ this position
Will trip CB @ 'A' forfault @ this position
No Signalling used between ends
Used with Auto-Recloser only
Results in More Breaker Operations
Zone 2Zone 3F
Distance
Distance
Trip
Reclose
Zone 1 Ext
Zone 1
ZONE 1 EXTENSION SCHEME
-
8/3/2019 Day 2 Transmission Line Protection
28/38
20 December 2010 28Protection Courses
WEAK IN FEED LOGIC
-
8/3/2019 Day 2 Transmission Line Protection
29/38
20 December 2010 29Protection Courses
SERIES COMPENSATION Used to increase load capacity Improve power system stability Improve load division on parallel paths Reduce transmission losses
-
8/3/2019 Day 2 Transmission Line Protection
30/38
20 December 2010 30Protection Courses
SERIES COMPENSATION
Voltage reversal
-
8/3/2019 Day 2 Transmission Line Protection
31/38
20 December 2010 31Protection Courses
COUPLINGBETWEENLONGLINESCANHAVEASIGNIFICANTEFFECTONDISTANCEPROTECTIONMEASUREMENT
ONLYAFFECTSZEROSEQUENCECOMPONENT(PPSANDNPSCOMPONENTSAREBALANCEDANDTHEREFORESUMTOZERO)
IFRELAY
NOT
COMPENSATED
FOR
EARTH
RETURN
AND
MUTUAL
EFFECTS
Z1WILLBEOVER
ESTIMATEDANDTHERELAYWILLUNDERREACH
Ia
ZMO
Fault
Ib
Double Circuit Line
MUTUAL COMPENSATION 1
-
8/3/2019 Day 2 Transmission Line Protection
32/38
20 December 2010 32Protection Courses
When one of the lines is out of service and earthed at both ends
Energise a Status Input SWITCH TO ALTERNATE SETTINGS group
ALTERNATE SETTING GROUP uses
Increased Earth Fault Compensation Factor to take account of the Zero
Sequence Mutual Coupling due to the parallel line
MUTUAL COMPENSATION 2
-
8/3/2019 Day 2 Transmission Line Protection
33/38
20 December 2010 33Protection Courses
CCVT TRANSIENT
-
8/3/2019 Day 2 Transmission Line Protection
34/38
20 December 2010 34Protection Courses
CCVT TRANSIENT Distance element may over reach CCVT Trans. Reduce the fundamental component of the
fault voltage results in decrease in the calculated impedance High capacitance reduced transient effect Passive Ferro-resonance reduced transient effect
-
8/3/2019 Day 2 Transmission Line Protection
35/38
20 December 2010 35Protection Courses
CCVT TRANSIENT
-
8/3/2019 Day 2 Transmission Line Protection
36/38
20 December 2010 36Protection Courses
DIRECTIONAL EARTH FAULT 1
Unrestricted Characteristic
Operates for any fault current above setting in selected direction
Detects high impedance earth faults
Operate quantity - residual current
Polarising quantity - residual voltage
X
R
Line
Angle
-
8/3/2019 Day 2 Transmission Line Protection
37/38
20 December 2010 37Protection Courses
DUAL DIRECTIONAL EARTH FAULT TWO Unrestricted Characteristics
Common Line Angle Setting
Different Operating Current Settings
Forward DEF
Operates on Current above FWDsetting in FORWARD direction
Reverse DEF
Operates on Current above REVsetting in REVERSE direction
X
RLine
Angle
Forward
DEF
Reverse
DEF
-
8/3/2019 Day 2 Transmission Line Protection
38/38
20 December 2010 38Protection Courses
Discrimination using DTL or IDMTL Time Grading (DEF Direct Trip)
OR
High Speed operation using a Signalling Channel (DEF POR)
Operation of both DEF elementsallows instantaneous tripping
If no Signalling Channel is available
OR
Signalling Channel fails
RELAY CAN OPERATE AS BACK-UPTIME GRADED OVER CURRENT
DIRECTIONAL EARTH FAULT 2