David McGiven FAC: Construction [email protected] 20-21 April 2006 Facility...
-
Upload
susan-caldwell -
Category
Documents
-
view
219 -
download
2
Transcript of David McGiven FAC: Construction [email protected] 20-21 April 2006 Facility...
David McGiven
FAC: Construction Procurement [email protected]
20-21 April 2006
Facility Advisory Committee (FAC)
Construction Procurement
David McGiven
LCLS Procurement Manager
David McGiven
FAC: Construction Procurement [email protected]
20-21 April 2006
Construction Procurement Overview
Contract Features
Unique Aspects of the Contract
Contract Administration Challenges
Initiatives
David McGiven
FAC: Construction Procurement [email protected]
20-21 April 2006
Contract FeaturesConstruction Management / General Contractor (CM/GC) services performed by Turner Construction
SLAC assumes most construction cost risk
CM/GC assumes schedule risk via liquidated damages
Two PhasesPhase 1- Preconstruction services, cost ~ $600k, constructability reviews, cost estimates, solicitation packages, etc.
Phase 2 - Turner Construction “holds paper” and provides: Construction management services for ~ 28 months, cost ~ $12 million (Fixed Price)
Awards/administers construction subcontracts (~ $65-70 million)
Manages and co-ordinates construction activities
David McGiven
FAC: Construction Procurement [email protected]
20-21 April 2006
Unique Aspects
Phase 2 is a unilateral option of SLAC
Providing direction to and surveillance over a CM/GC
Sub-subcontract costs pass through to SLAC
CM/GC is responsible for co-ordination efforts
Contractor controlled insurance program
Incentive Provisions—Safety, Schedule, Cost Control
Tunneling operations (25-30% of all construction)
David McGiven
FAC: Construction Procurement [email protected]
20-21 April 2006
Contract Administration Challenges
Developing “partnering” mentality with the CM/GCSafetyCoordinating with SLAC (security, ES&H, etc.) Schedule developmentRisk Management
Establishing responsive business controls Limited contingency management delegated to CM/GC
Blanket fundingMonthly reviews
Change order managementTechnical field order authority up to $25,000Flow chartsWeb based configuration control
Sub-subcontracts / Bidder selectionReview and approve bid packagesReview and approve award recommendation
David McGiven
FAC: Construction Procurement [email protected]
20-21 April 2006
Initiatives
Consultant support and reviewer feedbackDOE experienced construction project procurement professionals Estimator specialists and/or temporary personnel to augment staff Take review group/committee comments seriously
Work more closely with Project staff to understand milestones, develop strategies, advance planning, and avoid problemsPartnering SessionsTraining
Managing contractsControlling change order costs
David McGiven
FAC: Construction Procurement [email protected]
20-21 April 2006
Summary
Establishing dedicated procurement office, setting up effective business controls, and supporting project goals are challenging on a $75+ million construction management services contract
Initiatives and external advice should help achieve our goal to: effectively support the LCLS project with timely, cost effective acquisition support using best business practices