Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol (Panglao)AIRPORTS DEVELOPMENT,

OPERATIONS AND MAINTENANCE PROJECTS

___________________________

Pre-Qualification Conference

13 March 2017

Page 2: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

2

Outline of Presentation

Way Forward

Instructions to Prospective Bidders

Bidding Process

Project Description & Scope

Background of Airports

Development Objective

Page 3: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

3

Airport Projects Development Objective

To improve services at the respective key regional airportsincluding required enhancement of airside and landside facilities atthe respective airports by granting concessions to private sectorproponents.

Page 4: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

Location- Airports

4

Iloilo AirportEstimated Cost:

PHP 30.4 BnPassenger Traffic (2016):

~1.94 Mn

New Bohol Airport

Estimated Cost: PHP 4.57 Bn

Passenger Traffic (Tagbilaran) : 0.9 Mn

Davao AirportEstimated Cost:

PHP 40.57 BnPassenger Traffic (2016):

~3.55 Mn

Bacolod-SilayAirport

Estimated Cost: PHP 20.26 Bn

Passenger Traffic (2016): ~1.53 Mn

LaguindinganAirport

Estimated Cost: PHP 14.62 Bn

Passenger Traffic (2016): ~1.80 Mn

Page 5: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

Davao International Airport

5

Davao airport is located inCatitipan, Barangay Buhangin,Davao City.

The Davao airport has beenoperational for more than 15 years

In terms of passenger trafficthroughput, it is the third largestairport in the Philippines

It provides both domestic andinternational connectivity

Passenger Traffic (2016) in Mn ~3.55

CAGR for the period 2007-16 ~9.78%

Cargo Traffic (2016) in MTs 53,659

CAGR for the period 2007-16 ~1.84%

Page 6: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

Iloilo International Airport

6

Iloilo International airport is located inCabatuan, Province of Iloilo (WesternVisayas region)

It commenced operations in 2007 andis one of the recently completedairports in Philippines with modernfacilities

In terms of passenger trafficthroughput, it is the fifth largest airportin the Philippines

It provides both domestic andinternational connectivity)

Passenger Traffic (2016) in Mn ~1.94

CAGR for the period 2007-16 ~7.62%

Cargo Traffic (2016) in MTs 13,339

CAGR for the period 2007-16 ~3.13%

Page 7: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

Laguindingan International Airport

7

Laguindingan International airport islocated on the northern tip of MisamisOriental and is approximately 45kilometers from Cagayan de Oro cityand approximately 65 kilometers fromIligan city

It commenced operations in June 2013replacing the old Lumbia Airport

It is the sixth largest airport in thePhilippines in terms of passenger traffichandled

Passenger Traffic (2016) in Mn ~1.80

CAGR for the period 2007-16 ~9.72%

Cargo Traffic (2016) in MTs 20,486

CAGR for the period 2007-16 ~5.73%

Page 8: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

Bacolod-Silay Airport

8

Bacolod Airport is located in Silay City,Negros Occidental (Western Visayasregion)

It commenced operations in 2008 andis one of the recently completedairports in Philippines with modernfacilities

In terms of passenger trafficthroughput, it is the eighth largestairport in the Philippines

Passenger Traffic (2016) in Mn ~1.53

CAGR for the period 2007-16 ~7.75%

Cargo Traffic (2016) in MTs 16,534

CAGR for the period 2007-16 ~8.24%

Page 9: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

New Bohol International Airport

9

New Bohol airport is to be located inPanglao Island and shall replace theexisting Tagbilaran Airport

Tagbilaran airport is an importantairport in the Philippines with largelytourist–driven traffic

The airport is expected to have adesign capacity of ~1.958 millionpassengers

Passenger Traffic (2016) in Mn(for existing Tagbilaran Airport)

~0.9

CAGR for 2007-16 ~10.88%

Terminal Design Capacity inMn 1.958

Cargo Traffic (2016) in MTs 4,138

Page 10: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

Existing Facilities at the Airports

10

Davao Iloilo Laguindingan

Bacolod-Silay New Bohol

Total Area (hectares) 217 188 354 187 220

Terminal Floor Area (sq.m.)

22,683 13,700 7,184 6,187 13,337

Runway 3000 m x 45m

2500 m x 45m 2100 m x 45m 2002 m

x 45m2500 m x 45m

Apron Area(sqm) 74,250 48,210 46,150 25,300 49,335

Page 11: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

1. Taking-over the operations and maintenance of the existing facilities (newlybuilt facilities in the case of the New Bohol Airport Project) from CAAP,excluding, in the case of the Davao Airport Project, the old passenger terminal,and except as otherwise provided in the Bidding Documents.

2. Enhancement/development of landside facilities, including passenger andcargo terminal(s), along with all associated infrastructures and facilities

3. Enhancement/development of airside facilities to meet the enhanced scale ofoperations of the airports

4. Installation of all required equipment and associated facilities

Project Description: Scope of Work (1/3)

11

Page 12: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

5. Provision of required works with respect to the existing terminals (eitherfacilities already in operation, as in the case of the Davao, Iloilo, LaguindinganAirport and Bacolod-Silay, Projects, or newly-constructed facilities, as in thecase of the New Bohol (Panglao) Airport Project), along with all associatedinfrastructure and facilities, necessary to handle operations until the expansionof the existing terminals and/or the development of new passenger terminal(s).

6. Operations and maintenance of landside facilities (including, among others,the passenger terminals) and associated airside facilities (including, amongothers, the apron, runway and taxiway), during the entire concession period

Project Description: Scope of Work (2/3)

12

Page 13: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

Project Description: Activities not included in

Scope of Work* (3/3)

13

Activities / Responsibilities of CAAP / DOTC:1. Air Traffic Control (“ATC”) Services

2. Air Navigation Services (“ANS”)3. Provision and operations of ATC and ANS facilities

4. Necessary upgrade and maintenance of ATC and ANS facilities5. Existing CAAP administration building

6. Existing CAAP staff houses

Further, the following services are not included in the scope of the Projects and wouldcontinue to be provided by the relevant agencies at the airports:1. Customs2. Immigration3. Security4. Quarantine5. Services provided by the Philippine Overseas Employment Administration (POEA) andthe Overseas Workers Welfare Administration (OWWA)6. Other services currently being provided by other Philippine government agencies

Page 14: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

Project Description: Contractual Framework

Legal FrameworkRepublic Act No. 6957, as amended by Republic Act No.7718 ("BOT Law”), and its 2012 Revised ImplementingRules and Regulations (“Revised IRR”)

PPP Structure Operate-Add-Transfer (“OAT”)Implementing Agencies

Department of Transportation andCivil Aviation Authority of the Philippines

Concession Period

30 years in the case of the Davao, Iloilo, Laguindinganand Bacolod-Silay Airport Projects35 years in the case of the New Bohol (Panglao) AirportProject

Right of Way and Possession of Airport Land

Government will grant appropriate rights to project siteand relevant existing assets

14

Page 15: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

Bidding Process(1/2)

Competitive bidding: two-stage bidding process Instructions to Prospective Bidders (ITPB) for Pre-Qualification of

Prospective Bidders for each Airport Project issued through the currentprocess

Evaluation of Pre-Qualification applications and announcement of Pre-Qualified Bidders for the 2nd stage for each Airport Project

Instructions to Bidders (ITB) including Draft Concession Agreements andMinimum Performance Standards and Specifications to be shared withPre-Qualified Bidders for each Airport Project

Post issuance of final documents, Bid Proposals, including technical andfinancial proposals, to be invited from Pre-Qualified Bidders for eachAirport Project.

15

Page 16: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

Bidding Process(2/2)

Evaluation of Technical Proposals for each Airport Project Financial evaluation of Technically Qualified bidders for each Airport Project Announcement of Winning Bidder for each Airport Project Notice of Award to be issued to the Winning Bidder for each Airport Project

16

Page 17: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

Eligible Sectors are airports, highways, expressways, power, ports, railways, metro rail,industrial parks/ estates, logistic parks, and real estate development

Projects in the Eligible Sector with minimum development costs of One Billion Pesos.Developments costs must be adjusted to current prices using the Philippine StatisticsAuthority’s Consumer Price Index as provided in the ITPBs.

A person, corporation or any entity Controlled by or Controlling the Prospective Bidder orConsortium Member (as the case may be) or associated with the Prospective Bidder orConsortium Member (as the case may be) under common ownership and Control

ITPB: Key Definitions

AFFILIATE

ELIGIBLE PROJECTS

ELIGIBLE PERIOD

ELIGIBLE SECTORS

17

A period of last 12 years ending on 31st December 2016

Page 18: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

The power to direct or cause the direction of the management policies and actions of a bodycorporate, whether through:

i. ownership of at least fifty percent (50%) plus one (1) of either or a combination of thefollowing:

(i.a) the total outstanding voting shares, or(i.b) the voting rights, in another entity, or

ii. the ability to elect a majority of the members of the other entity’s board of directors, or

iii. any legal agreement or legal agreements, including a voting trust or other votingagreements

In determining ownership of shares in a corporation, shares held both directly and indirectlywill be counted.

ITPB: Key Definitions

CONTROL

18

Page 19: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

An individual, partnership, corporation, or any other juridical entity that is a holder of any ofthe following permits issued by the Civil Aeronautics Board ("CAB") of the Philippines: A valid and effective Permit to Operate Scheduled International Air Transportation

Services; or A valid and effective Permit to Operate Scheduled Domestic Air Transportation

Services; or A valid and effective Foreign Air Carrier's Permit and providing scheduled passenger

services.For avoidance of doubt, an individual, partnership, corporation, or any other juridical entityproviding dedicated cargo transport services shall not be deemed an Airline for the purposesof this ITPB

ITPB: Key Definitions

AIRLINE

19

An individual, partnership, corporation, or any other juridical entity that:(1) is an Airline; or(2) is an Affiliate of an Airline

AIRLINE- RELATED ENTITY

Page 20: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

ITPB: Qualification Requirements

20

Legal Qualification Requirement

Technical Qualification Requirement

Development Experience

Design and Engineering Experience

Operations and Maintenance Experience, and

Qualified Key Personnel

Financial Qualification Requirement

Page 21: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

Legal Qualification Requirement (1/2)

21

Legal Qualification Requirement: A Prospective Bidder must be

An individual, partnership, corporation or any other juridical entity; or A Consortium whose members are individual(s), partnership(s),

corporation(s) or any other juridical entity(ies) Subject to the other provisions detailed in the ITPB

Participation of Airline Related Entities In the Consortium Airline Related Entity/Entities cannot own or be proposed to own an

aggregate of more than 33% total equity in the Consortium

Page 22: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

Legal Qualification Requirement (2/2)

22

Participation of Airline Related Entities Project SPC Airline-Related Entity/Entities in the Project SPC cannot own or be

proposed to own an aggregate of more than 33% total equity in anyProject SPC for the duration of the Concession Period

In the Facility Operator Airline-Related Entity/Entities in the Facility Operator cannot own or be

proposed to own an aggregate of more than 33% of the total equity in aFacility Operator if such Airline-Related Entity was the entity that fulfilledthe Winning Bidder’s Operations and Maintenance Experience asprovided in Section II-09 (2)(c);

Page 23: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

Technical Qualifications: Development Experience

23

Development Experience: must have satisfactorily undertaken thedevelopment of Eligible Projects in terms of overall responsibility fordesigning, engineering, and construction of Eligible Projects during theEligible Period, such that Sum total of the capital costs incurred for Eligible Projects is at least PhP

5.0 Billion; and there is At least one Eligible Project for which the capital costs incurred is at least

PhP 2.0 Billion

Entities which fulfill this requirement An individual, partnership, corporation, or any other juridical entity, the

Prospective Bidder itself or its Affiliate; or In case of a Consortium, a Consortium Member having at least thirty-

three and one third percent (33 1/3%) interest in the Consortium or suchConsortium Member’s Affiliate.

Must propose at least one, and at most five, Construction Contractors

Page 24: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

Technical Qualifications: Design and Engineering

Experience (1/3)

24

Design and Engineering Experience: must have satisfactorily undertakenduring the Eligible Period, detailed architectural design and engineering,including airport planning, construction planning and phasing inimplementing projects, for airport terminal facilities and associatedinfrastructure for at least one (1) International Airport possessing with thefollowing criteria for respective airports:

Davao Iloilo Laguindingan

Bacolod New Bohol

Passenger capacity of at least

4 Million 3 Million 3 Million 2 Million 2 Million

Terminal area of at least 20,000 sqm 14,000 sqm 14,000 sqm 7,000 sqm 7,000 sqm

Handling capability

has the capability to handle Code 4E aircrafts, demonstrating works undertaken for landside facilities such as passenger terminals and associated facilities, and airside facilities such as runway, taxiways, aprons, etc.

Page 25: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

Technical Qualifications: Design and Engineering

Experience (2/3)

25

For expansion projects, the design and engineering experience mustinvolve upgrading the International Airport to meet all the criteria specifiedearlier (for respective airports), and additionally involve at least any of thefollowing criteria (for respective airports:

Davao Iloilo Laguindingan

Bacolod New Bohol

Increase in passenger capacity of at least

1 Million 750,000 750,000 500,000 500,000

Increase in terminal area of at least

5,000 sqm 3,500 sqm 3,500 sqm 1,700 sqm 1,700 sqm

Upgrade in handling capability

upgrade that allows the airport to handle Code 4E aircrafts

Page 26: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

Technical Qualifications: Design and Engineering

Experience (3/3)

26

Entities which fulfill this requirement

An individual, partnership, corporation, or any other juridical entity, theProspective Bidder itself or its Affiliate or a nominee Design andEngineering Contractor; or

In case of a Consortium, a Consortium Member or its Affiliate or anominee Design and Engineering Contractor

• If fulfilled by a Design and Engineering Contractor, at least one and atmost five, Design and Engineering Contractors to be proposed each ofwhich must have the relevant experience and possess the necessarylicenses

Page 27: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

Technical Qualifications: Operation and Maintenance

Experience(1/2)

27

Operation and Maintenance Experience: must have experience in either O&M of an International Airport for a period of at least three (3)

consecutive calendar years anytime within the Eligible Period , with suchInternational Airport having handled an Annual Passenger Throughput ofat least (for respective airports):

Davao Iloilo Laguindingan Bacolod New Bohol

4 Million 3 Million 3 Million 2 Million 2 Million

Page 28: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

Technical Qualifications: Operation and Maintenance

Experience(2/2)

28

Entities which fulfill this requirement

An individual, partnership, corporation, or any other juridical entity, theProspective Bidder itself or its Affiliate; or

In case of a Consortium, a Consortium Member having at least ten percent(10%) interest in the Consortium or such Consortium Member’s Affiliate

Page 29: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

The Prospective Bidder, the Consortium Members, and/or theproposed Subcontractors must have, among them and their Affiliates’personnel, with qualifications and experience as follows: At least 1 person with a minimum of 10 years of experience and having had the

overall responsibility for the development of at least 3 Eligible Projects, each witha project cost of at least Php 500 Million, with at least 1 of such Project having aproject cost of at least Php 1 Billion, and with at least one of such Project beingan airport

At least 1 person with a minimum of 10 years of experience and having beenresponsible for the coordination of the operations and maintenance of at least 1airport with an Annual Passenger Throughput of at least 2 million passengers perannum for a period of at least 3 consecutive calendar years anytime within theEligible Period

At least 1 person with a minimum of 10 years experience and having beenresponsible for the commercial development and marketing of an airport with anAnnual Passenger Throughput of at least 2 million passengers per annum for aperiod of at least 3 consecutive calendar years anytime within the Eligible Period

29

Technical Qualifications: Qualified Key Personnel

Page 30: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

Financial Qualification Requirement(1/2)

30

Financial Qualification Requirements: A Prospective Bidder must fulfill the

following requirements:

For a Prospective Bidder Net Worth of at least:

..or its foreign currency equivalent as of its latest audited financial statements, or A Set-Aside Deposit equivalent to the same amount.

For a Consortium the Net Worth of Consortium Members who have an equity share of at

least twenty-five percent (25%) each in the Consortium may be added

Davao Iloilo Laguindingan Bacolod New Bohol

Php 1.5 Billion Php 1 Billion Php 1 Billion Php 1 Billion Php 1 Billion

Page 31: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

Financial Qualification Requirement(2/2)

31

Entities which fulfill this requirement

An individual, partnership, corporation, or any other juridical entity, theProspective Bidder or its Affiliate; or

In case of a Consortium, Consortium Member with at least twenty-five per cent (25%) equity interest in the Consortium, or such Consortium Member’s Affiliate

Page 32: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

32

Prospective Bidder as a Corporation, Partnership or Other Juridical Entity No restrictions imposed on the ownership structure; provided that, the Prospective

Bidder ensures its continued eligibility with respect to the individual Technical andFinancial Qualification Requirements as provided in the Invitation Documents

Prospective Bidder as a Consortium Lead Member and the Consortium Member proposed to meet the Development

Experience may not withdraw or reduce their percentage interests in the Consortiumas declared in the Consortium`s Qualification Documents

Other members of the Consortium may withdraw/ be substituted prior to the BidProposals Submission Date

*These rules shall apply from the Qualification Documents Submission Date to the Bid Proposals Submission Date

Lock-Up Rules During the Bidding Process* (1/2)

Page 33: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

33

Prospective Bidder as a Consortium In case of substitution, the Prospective Bidder has to ensure its continued eligibility

with respect to the individual Technical and Financial Qualification Requirements asprovided in the Invitation Documents

Any change in the composition of the Consortium and/or in the list of Subcontractorsmust be approved by the PBAC

Lock-Up Rules During the Bidding Process* (2/2)

*These rules shall apply from the Qualification Documents Submission Date to the Bid Proposals Submission Date

Page 34: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

Government commitment for the projectFocus on development of the country’s transport infrastructure through private sector participation

Strong project fundamentals Attractive location of the airport with significant business and tourist potential

NEDA* Board-approved projects All projects have been approved by NEDA

Optimal PPP structuringbalanced risk sharing and competitive returns to private sector proponents

PPP Agreement for 30/35 yearsscope for long term investment & returns

Award through competitive biddingtransparency and equality for all prospective private sector bidders/investors

*NEDA - National Economic & Development Authority

Why Invest?

34

Strong Legal Framework – BOT LawEnunciates the policy of the state recognizing the role of the private sector as main engine for national growth and development

READY FOR BUSINESS.

Page 35: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

Activity Expected TimelinesQualification Documents Submission Date 11 May 2017

Notification of results of evaluation of Qualification Documents

within 5 calendar days fromapproval of Pre-Qualificationresults

Issuance of Instructions to Bidders, Draft Concession Agreement & Draft MPSS

1 June 2017

Bid Proposals Submission Date 8 December 2017Issuance of Notice of Award by January 2018

Signing Date of Concession Agreement

within 5 calendar days from receipt of the Notice of Complete Compliance with all Post-Award Requirements

Note that these timelines are tentative and may be subject to change. The final timelines shall be communicated at the appropriate time, as necessary.

Way Forward: Expected Timelines

35

Page 36: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

Way Forward: Pre-Qualification Submission

36

11 May 2017, Before 2:00 PMat

Pre-Qualification, Bids and Awards Committee for

Department of Transportation

Civil Aviation Authority of the Philippines,

[___________] Airport Project

Unit 164, 16/F, The Columbia Tower, Ortigas Avenue, Mandaluyong City

Manila, Philippines

Page 37: Davao, Iloilo, Laguindingan, Bacolod-Silay and New Bohol ... · Negros Occidental (Western Visayas region) Itcommencedoperationsin2008and is one of the recently completed airports

37

THANK YOU!