PROJECT PROGRESS RDM PT. REKIND DAYA MAMUJU MAMUJU COAL FIRED STEAM POWER PLANT 2x25 MW

Transcript of Data Project PLTU 2x25 MW Mamuju -West Sulawesi - Indonesia

Page 1: Data Project PLTU 2x25 MW Mamuju -West Sulawesi - Indonesia

PROJECT PROGRESS

RDM

PT. REKIND DAYA MAMUJU

MAMUJU COAL FIRED STEAM POWER PLANT 2x25 MW

Page 2: Data Project PLTU 2x25 MW Mamuju -West Sulawesi - Indonesia

MILESTONE PROJECT (Status up to April 2015)RDM

MILESTONE Target Unit #1 Target Unit #2 Status Remark Site Development (Cut & Fill) May 2015 May 2015 Site Preparation

Commencement Of Date May 2015 May 2015 EPC Power Plant

First Piling July 2015 July 2015 EPC Power Plant

Boiler on Site Dec 2015 Januari 2016 EPC Power Plant

Boiler Steam Drum Lifting February 2016 April 2016 EPC Power Plant

Turbine Generator On site February 2016 April 2016 EPC Power Plant

Transmision Line & Substation ready operation

September 2016 September 2016 Substation 150 KV & Transmission (15km)

Back Feeding September 2016 September 2016 EPC Power Plant

Control Room Fully Operation October 2016 October 2016 EPC Power Plant

Demin Water Production October 2016 Nov 2016 EPC Power Plant

Hydrotest Boiler October 2016 Dec 2017 EPC Power Plant

Coal handling System Ready January 2016 February 2017 EPC Power Plant

First Firing Boiler Februari 2017 April 2017 EPC Power Plant

Steam Blow March 2017 May 2017 EPC Power Plant

First Synchrone April 2017 June 2017 EPC Power Plant

RRApril 2017 June 2017 EPC Power Plant

PTMay 2017 July 2017 EPC Power Plant

CODMay 2017 July 2017 EPC Power Plant

Page 3: Data Project PLTU 2x25 MW Mamuju -West Sulawesi - Indonesia

ENGINEERING ACTIVITIESRDM

Status 29 April 2015 (Before Consinyering Meting)

Status 11 Mei 2015 (after Consinyering Meeting)

Page 4: Data Project PLTU 2x25 MW Mamuju -West Sulawesi - Indonesia

2015 2016 2017

May

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Jun jUL

M0 M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M25 M26

Schedule Equipment On Site

Boiler Steel Structure On site (Oct’15)

Boiler Unit 1 On site (Dec’15)

Boiler Unit 2 On site (Jan’16)

Turbine & Generator foundation bolts, plates, Steel Structure unit 1 & 2 On site (Dec’15)

Turbine Generator unit 1 On Site (Feb’16)

Turbine Generator unit 2 On site (Apr’16)

Batch 1

Batch 2

Batch 3

Batch 4

Batch 6

Batch 5

On Site Batch 4 :1. Coal crusher2. Draft Fan(Induced draft fan,primary air fan,secondary air fan)3. Electrostatic precipitator 4. Coal feeder5. Feed pump6. High pressure heater7. Deaerator8. Transformers9. Circulation-water pump10. Condensate pump 11. Overhead crane Turbine house

On Site Batch 5 :1. Coal handling system 2. Mechanical cooling tower 3. Coal Unloader4. Seawater desalination Plant5. Chemical water treatment system6. Vacuum pump7. Ash handling system 8. Slag removal system 9. HP feed-water/steam pipe10. Hoisting Equipments 11. DC system12. Electrical protection system13. 6kV switch cabinet14. 6kV switch cabinet delivery15. PC&MCC cabinet16. HP&LP electrical panel cabinets17. Medium pressure and low pressure pipe (in batches)18. Valves (in batches)19. Cable & Cable tray

On Site Batch 6 :1. Air compressor2. Turbine bypass3. Rubber ball cleaning device 4. DCS system 5. HP fluidization fan6. Heating Ventilation Air Conditioning7. Continuous Emission Monitoring System 8. Fuel oil pump house equipments 3. Communication9. Emergency diesel generator10. Thermal control system 11. Plant & Demestic sewag treatment device12. Hydraulic fire system

Batch 7

On Site Batch 71. Fire alarm system2. Chemical laboratory equipment 3. Thermal instrusments 4. Motorized valve of CW system

Page 5: Data Project PLTU 2x25 MW Mamuju -West Sulawesi - Indonesia

CONSTRUCTION ACTIVITIES

I. Current Month Activities1. Pekerjaan EPC Project PLTU 2x25 MW

a. Soil Investigation (Soil test)•CHEC telah Memulai Pekerjaan Soil Test pada tanggal 26 Februari 2015.

b. Pekerjaan Temporary Facility dan Batching Plant•Persiapan Pengiriman dan Install

2. Pekerjaan EPC Project 150KV Substation and Transmission Line (15KM)a.Land Acquisition (Pembebasan Lahan) :

Proses pembebasan lahan Transmisi Line (15KM) bekerja sama dengan PT PLN UIP XIII dan Pemda Mamuju, target total penyelesaian pembebasan lahan pada bulan Juli 2015.

b. Target Ready to Supply : September 2016

RDM

Area Jumlah Rencana titik Soil Test Jumlah Aktual titik Soil Test Keterangan

BTG & Chimney 43 43 DoneBOP 24 11Oil Tank 5 1Coal Yard 28 23Building 12 12 DoneJetty 22 22 DoneAsh Yard 9 9 Done

Page 6: Data Project PLTU 2x25 MW Mamuju -West Sulawesi - Indonesia

PHOTOS PROJECTRDM

Page 7: Data Project PLTU 2x25 MW Mamuju -West Sulawesi - Indonesia

PHOTOS PROJECTRDM

Page 8: Data Project PLTU 2x25 MW Mamuju -West Sulawesi - Indonesia

PHOTOS PROJECTRDM

Page 9: Data Project PLTU 2x25 MW Mamuju -West Sulawesi - Indonesia

PHOTOS PROJECTRDM

Page 10: Data Project PLTU 2x25 MW Mamuju -West Sulawesi - Indonesia