DART progress report – July 2011

download DART progress report – July 2011

of 4

Transcript of DART progress report – July 2011

  • 8/6/2019 DART progress report July 2011

    1/4

    DART progress report July 2011

    Sensor Arrays and Surveys

    The past 6 months have represented a major milestone for the project. We have installed both

    sensor arrays at RAC and one sensor array at Diddington the final array will be installed in late July.The regular monitoring surveys have started. At present the geophysical surveys geotechnical

    sampling and spectro-radiometry have a monthly baseline interval. Further, two weekly, spectro-

    radiometry surveys are taken at Diddington and will continue until the crop is harvested. In addition

    we have been in communication with the farmers and will attempt to take specific geophysical

    measurements to evaluate the impact of ploughing and harrowing on signal attenuation. The

    experience of doing this work has led to the consolidation of methodology.

    Aerial Surveys

    Two local aerial archaeologists, Robert Bewley (Cirencester) and Rog Palmer (Diddington) are

    undertaking regular flights over both sites. These photographs can be found on the DART website:

    http://dartproject.info/WPBlog/?page_id=63. On the 27th

    June 2011 the Environment Agency haveundertook a CASI hyperspectral, LiDAR and vertical photograph survey. These are collected at a

    ground resolution of 1m, 1m and 0.25m respectively. The LiDAR and vertical photography cover

    approximately 20km2

    around each site and the CASI covers approximately 3km2. In addition we put

    in a bespoke application to NERCs Airborne Remote Sensing Facility for hyperspectral flights after

    observing the impact that the 1 in 100 years drought event was having on cropmarks at Diddington.

    This was submitted on Friday 10th

    June, approved on Monday 13th

    June and flown on Tuesday 14th

    June. Many thanks to NERC for this flight. Concurrent spectro-radiometry readings were taken for

    both the CASE and NERC ARSF flights to compensate for atmospheric effects. NERC, Cambridgeshire

    County Council and DART will produce a press release on these flights.

    WorkshopOn the 27th April the first DART community workshop was held at Leeds University. Given the time

    of year it was well attended with 30 community participants and the DART team bringing this up to a

    total of 40 people. We managed to get a good cross-section of academics, curators, practitioners

    and community groups as can be seen from the delegate breakdown below. The day is summarised

    in a blog post http://dartproject.info/WPBlog/?p=1253.

    Partnerships

    Van Walt Ltd., Allied Associates Geophysical Ltd., Leica Geosystems have all continued to offer

    support. Van Walt will be installing one of their TDR probes for comparative analysis at the next

    Diddington installation. Allied Associates have provided geophysical equipment. Leica Geosystems

    have provided access to both RTK-GPS and their SmartNET service. Many thanks to all these

    organisations for their support.

    Future work

    From here on in DART will become very data intensive. We need to put in place effective back-end

    infrastructure to host and share large data and to find appropriate mechanisms to place this data in

    the public domain and present (or visualize) the data. The ARSF grant for 2012 will need submitting

    in October.

  • 8/6/2019 DART progress report July 2011

    2/4

    Robert Fry: Geophysics

    Preliminary Geophysics at Sites

    Fluxgate Gradiometer surveys were undertaken at Harnhill and Diddington. These were used at the

    main location maps for the TDR placement on site. The survey was conducted by RF and DS during

    January and February, with associated reports written up for the landowners and DART principal

    investigators. From the successful results of the surveys, coring locations were selected in order to

    characterise the ditch locations (coring completed by KW).

    FlashRes64Resistivity Imaging Equipment

    The new FlashRes resistivity Imaging Equipment has currently been on loan from Allied Associates,

    and tested on a number of different sites. I am now confident the instrument works sufficiently and

    the University of Bradford (UoB) are purchasing the equipment to be used and to constitute the

    main focus of the monthly surveys and indeed, the PhD. The importance of the high-definition

    results from the instrument should really help with characterising the seasonal moisture contrasts in

    the soil. To help disseminate and understand the data further, I am currently attempting to write a

    Python program which extracts specific arrays from the FlashRes data.

    EM CMD MiniExplorer equipment

    After the DART workshop, it was noted that testing Electro Magnetic (EM) survey would be of

    interest to commercial interested parties. Thanks to Allied Associates again, UoB have been lent a

    new EM instrument which could revolutionise the use of this method for archaeological prospecting.

    After successful surveys at Quarry Field (Harnhill) it is hoped that a future lending program might be

    arranged to collect more EM data over the fields.

    Excavation and Installation

    After successfully locating the sites through geophysical survey and coring, 3 TDR boxes at

    Cirencester and 1 at Diddington have been installed. Soil samples taken from all fields.

    Publications / Dissemination

    y AARG News: DART students AARG conference summaryy ISAP News: The DART project a roadmap for the 21st centuryy RSPSoc News: DART project updatey ISAP Conference: FlashRes64 - extended abstractandDART project extended abstract

    Future work

    I am about to start undertaking the monthly survey of the fields. This will generally be in the last

    week of the selected month (where logistically viable) and will involve, survey with a multiplexed

    resistance meter (at Twin probe spacings of 0.25m / 0.5m / 0.75m and 1m), the FlashRes ERI system,

    as well as EM survey when available. (Dan will also be providing GPR data from each site eachmonth).

    Foreseeable issues

    Not so much an issue yet, but I am currently attempting to work out how to correctly and effectively

    compare and analyse the data I collect.

  • 8/6/2019 DART progress report July 2011

    3/4

    Dan Boddice and Laura Pring: Geotechnics

    TDR installation

    The three TDR monitoring stations at the RAC (two in quarryfields, one in cherry copse) have been

    activated, and have been collecting data since May. Large scale analysis of this data in its entirety is

    currently impossible, as each waveform takes a considerable amount of time to locate the start and

    end reflection points. However, a small sample of the data has been analysed, to check viability, the

    results of which were positive. After the final installations have been completed, a script to

    automatically locate the reflection points will be developed. This will dramatically improve analysis

    time.

    TDR logging issues

    Some outstanding issues exist with the data collection, with the principle problem being that the CF

    cards used to store the data are filling up at a much quicker rate than expected (around 2 weeks).

    Contact has been made with Campbell scientific on this issue, and they are currently investigating.

    The latest thinking is that the table fill times being reported by loggernet are not accurate and

    running a program in the lab may help us to determine accurate table fill times. Investigations into

    uploading the data to an ftp server using the GSM modems are also being conducted, as this would

    produce a pseudo-live data feed, from which any problems or data skips could quickly be identified,

    and reduce the CF cards role to backup.

    Weather station installation

    Three weather stations have currently been installed, two at the RAC and another at the pasture

    field at Diddington. A final station will be installed at Diddington in July. All three of these have been

    observed to be collecting and recording data at regular intervals appropriately.

    Weather logging issues

    Some of the measurements are not fully explained by the software or manual, and we are currently

    in contact with Prodata (who sold us the weather stations) and Davis (the manufacturer) to obtain

    information on how some of the derived measurements such as rain rate are calculated, in order to

    better understand the data and use it more effectively.

    Future work

    In the forthcoming months of the project, we will be undertaking a number of different activities

    y Solve the data issues mentioned above on the TDR sensorsy Finish and install the remaining two sensors at the clay site at Diddingtony Develop a script to computer analyse the waveforms from the TDR to process the data

    quickly

    y Source a vibracorer and develop a methodology on frequency and locations for coringy Begin geotechnical laboratory tests on the soil samples from the two sites

  • 8/6/2019 DART progress report July 2011

    4/4

    David Stott: Spectral analyses

    Spectro-radiometry survey

    Since the last meeting we have recorded three spectro-radiometry transects at Diddington on a two

    week interval. Diddington has become the focus for this work as it has had both EAGLE, HAWK and

    CASI hyperspectral (pre and post a rain event), it is also logistically easier to get to Diddington from

    Leeds. This is essential as we are weather dependant. The methodology for this work has been

    refined to enable the lab work to be conducted at or near site using a portable enclosure and sun

    emulating lamps. This reduces the risk that the vegetation samples will degrade after being taken,

    and reduces dependency on the weather for field measurements. Vegetation height and relative

    chlorophyll content are also recorded for each spectro-radiometry transect.

    In addition to the site work additional spectro-radiometry reading are being recorded of the wheat

    plants being subjected to lab based stress testing in Leeds (Plant Biology).

    Excavation and Probe installation

    The excavations provided a detailed understanding of the nature of the three features identified so

    far. These are:

    y A relict field boundary and drain in clay (Quarry Field at Harnhill)y A substantial relict field boundary cut into limestone bedrock (Cherry Copse at Harnhill)y A prehistoric ditch in gravel, sealed by an alluvial deposit (the pasture field at Diddington)

    That these features are all so different is encouraging, as they will surely provide a wide range of

    responses to changing conditions.

    The monthly surveys

    The monthly surveys began in the last week of June 2011. During these the spectro-radiometry and

    geophysical data will be co-collected. The first survey provided valuable insights as to how we can

    work together most efficiently.

    Aerial data

    Ground-based spectro-radiometry readings were co-collected during the NERC and Environment

    Agency hyperspectral flights. This will allow us to correct for atmospheric attenuation. The oblique

    aerial photography provided by Bob Bewley and Rog Palmer have provided valuable information

    regarding the location of archaeological features that can be targeted for further spectro-radiometry

    transects next year.

    Further work

    y Continuing the spectro-radiometry surveys until the harvest this year (mid-August)y Locating further transects for the growing season in 2012. This will involve working closely

    with the land-owners to locate transects in areas of different crop and cultivation regimes

    y Designing a data structure for interrogating the datay Correction and exploration of the aerial datay Writing the NERC Airborne Remote Sensing Facility grant for the 2012 season