Dante Alighieri and Mundi · 2020-03-10 · Relocate Dante, Fall 2021 for 2 years (Deferral of...
Embed Size (px)
Transcript of Dante Alighieri and Mundi · 2020-03-10 · Relocate Dante, Fall 2021 for 2 years (Deferral of...

Dante
Alighieri
and
Regina
Mundi
Community
Consultation

AGENDA
1. Welcome and Prayer
2. Introductions
3. Review of Options from Feb. 10 Consultation
4. Summary of Feedback from Feb. 10 Consultation
5. Further Development of Options
6. Consultation Break Out Groups

Relocate Dante, Fall 2020 for 3 yearsYEAR 1
Dante students move off-site
YEAR 2 & 3Dante students move off-site
YEAR 4Dante students return
on-site to new building
RECAP OF OPTIONS
Cost – Approx. $750K/yr
for Transportation

Relocate Dante, Fall 2021 for 2 years (Deferral of Child Care)YEAR 1
Dante students remain on-site
during FDK renovations
YEAR 2 & 3Dante students move off-site
YEAR 4Dante students return
to new building
RECAP OF OPTIONS
DANTE ALIGHIERI
REGINA MUNDI
Cost – Approx. $750K/yr
for Transportation

No Relocation – Dante & Regina share building plus portables (Deferral of Child Care)
YEAR 1Dante students remain on-site
during FDK renovations
YEAR 2 & 3Dante students remain on-site,
share building & portables with
Regina Mundi
YEAR 4Dante students move into new
building
RECAP OF OPTIONS

TCDSB locations
• Msgr. Fraser – Norfinch (former Regina Pacis) –
can accommodate entire Dante population
without need for portables, currently
operating, no modifications required
• Don Bosco – decision on use of this building is
required as soon as possible to allow TCDSB to
make use of site for other opportunities.
• TCDSB is actively looking for opportunities at
TDSB sites should they become available.
RELOCATION OPTIONS

Feedback Summary – Feb. 10
• Questions included priorities in accommodating students,
transportation and relocation options
• Majority preferred to explore ways to stay on site (while also
recognizing redevelopment would take longer)
• Majority felt relocation options were not viable
• From presented options, Bosco was preferred
• If relocating, hybrid of central pick-ups and ttc tickets

Additional Option – Phased Child CareOption A: Relocate Dante, Fall 2021 for 2 years
Year 1
Fall 2020-Fall 2021
Years 2 & 3
Fall 2021 – Fall 2023
Year 4
Fall 2023
• Dante students remain
on site
• FDK and Child Care
retrofits and elevator
installation begin at 60
Playfair
• Use of Good Shepherd +
portables
• Dante students relocated
• Regina Mundi students
move into 60 Playfair
• Demo of 70 Playfair and
Good Shepherd
• Construction of new Dante
• New Dante and all site
work complete

Year 1
Fall 2020-Fall 2021
Years 2 & 3
Fall 2021 – Fall 2023
Year 4
Fall 2023 – Fall 2024
• Dante students remain
on site
• FDK and Child Care
retrofits and elevator
installation begin at 60
Playfair
• Use of Good Shepherd
• Regina Mundi students
move into 60 Playfair
• Dante students use 3rd
floor, portables + leased
space
• Demo of 70 Playfair
• Construction of new Dante
• New Dante Complete
• Portables removed
• Site work completed by
Fall 2024
Additional Option – Phased Child CareOption B: No Relocation

Ground Floor
Phased Child Care – Year 1, Phase 1 (First 6 months)

Ground Floor
Phased Child Care – Year 1, Phase 2 (Second 6 months)

Second Floor
Phased Child Care – Year 1

Third Floor
Phased Child Care – Year 1

Remain On Site Considerations: Year 1
• Portables remain - potential need of 4 additional portables.
• Cafeteria and Staff room available at Good Shepherd.
• Elevator installation will affect classes on 2nd and 3rd floor as well.
• Building access
• For Phased Child Care Option:
• No access to Change rooms/Showers for 6 months
• Art Rooms/Library out of use for 6 months
• More classrooms out of use

Remain On Site Considerations: Year 2 to Completion
• No additional student transportation
• Maintains existing campus style approach to elementary/secondary
• Minimal parking available on site (potentially 30 spots).
• Drop off for Regina Mundi; located in front of school on Playfair.
• Bell times adjustment to offset traffic flow on site.
REGINA WOULD OCCUPY: DANTE WOULD OCCUPY:
• 1st and 2nd
• Part of 3rd floor
• Part of 3rd floor
• Existing & additional portables (potential cost of $1.2 M)
• Good Shepherd & Leased space (Cost TBD)

• Gym space required by both schools
• Music program would be shared space
• Play space and field reduced
• Interaction between Elementary/Secondary students will increase
over existing setup, but will be minimized through careful planning
• Moving required in all phases of construction.
• Yr. 1 – Dante vacate ground floor, some 2nd and 3rd floor rooms under
construction
• Yr. 2 and 3 – Dante relocate to portables, GS etc., Regina moves in
• Yr. 4 – Dante to new building
Remain On Site Considerations: Year 2 to Completion

MODERATED DISCUSSIONS
Each group discussion will be directed by the moderator (TCDSB staff).
Feedback received will be presented in an upcoming Board report.
• Which of the options presented do you prefer and why?
• Any additional comments?
• Any additional questions?