USSD The Challenges of Dams in
Cold Climates – September 2017
Dams in Cold Climates:
Design Considerations and
Challenges of Construction
Doug Johnson, P.E., FERC Division of Dam Safety and Inspections
Regional Engineer, Portland OR
![Page 2: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/2.jpg)
FERC-regulated Dams in Alaska
Susitna-Watana
![Page 3: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/3.jpg)
Hebgen Dam in MT
Hebgen Dam
![Page 4: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/4.jpg)
Portland Region Dams
> 5000 feet Elevation.
Dam NameCrest
ElevationState Hazard Class
Mystic Dike 7675 MT H
Mystic Lake 7674 MT H
Viva Naughton 7249 WY H
Hebgen Dam 6546 MT H
Georgetown Dam 6443 MT H
Soda 5725 ID H
Grace Dike 5559 ID S
Grace Main 5559 ID S
Ashton 5147 ID H
![Page 5: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/5.jpg)
Portland Region Dams
at Highest Elevations In Alaska
Dam Name Crest Elevation State Hazard Class
Collection Pond (Goat Lake) 2885 AK L
Middle Fork Diversion (Bradley Lk.) 2204 AK L
Shotgun Creek Div 1931 AK L
Falls Creek Div 1650 AK L
Rolling Rock Creek Div 1485 AK L
Stetson Creek Diversion 1430 AK L
Terror Lake 1428 AK L
Allison Creek 1300 AK L
Crystal Lake 1299 AK H
Nuka River Div 1286 AK L
Cooper Lake 1220 AK H
![Page 6: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/6.jpg)
Allison Creek Dam
If we keep digging we may find where we stopped working last summer!
![Page 7: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/7.jpg)
Challenges of Constructing
FERC Projects In Cold Regions
![Page 8: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/8.jpg)
Salmon Creek Dam
![Page 9: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/9.jpg)
View looking up Valley at Dam
Height = 170 ft.Crest Length = 650 ft.Storage ≈ 12,000 ac-ft
![Page 10: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/10.jpg)
Downstream Face of Dam
First Constant Angle Arch
Dam in US.
Completed 1914
![Page 11: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/11.jpg)
Upstream Face showing severe
freeze-thaw damage
![Page 12: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/12.jpg)
Close-up view of eroded area of
upstream face
![Page 13: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/13.jpg)
Rubble at base of dam is remnant of
shotcrete facing applied in 1960’s
![Page 14: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/14.jpg)
Cold Climate Design Considerations
Dam built in 1914 – no air entrainment, poor consolidation, segregation of concrete
Severe Freeze-thaw environment
Tried to shotcrete faces of dam in 60s – most of that has fallen off.
Dam has lost over 2 feet in thickness.
As result dam is under reservoir restriction due to seismic instability – 32 foot drawdown
However, even without the drawdown the dam still retains sufficient thickness to resist static loads
Cost to rehab is prohibitive due to remote access – AEL&P has decided to live with restriction
![Page 15: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/15.jpg)
Lake Dorothy Hydroelectric
Project
Alaska Electric Light and Power
Juneau, Alaska
2006 - 2010
![Page 16: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/16.jpg)
Juneau
![Page 17: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/17.jpg)
![Page 18: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/18.jpg)
![Page 19: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/19.jpg)
Lake Dorothy looking north toward outlet
![Page 20: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/20.jpg)
Lake Dorothy
Tunnel Entrance
![Page 21: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/21.jpg)
Final Round - 12’ dia. By 12’ Thick 8/19/2008
Water then fills tunnel up to plug
Valve on pipe side of plug is opened or closed to control water out of Lake
![Page 22: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/22.jpg)
Actual Tunneling Begins July 2007
![Page 23: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/23.jpg)
Downstream face of tunnel plug
![Page 24: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/24.jpg)
Lake Tap
Lake tap was initiated from Lake Dorothy shoreline to allow observation of air pocket and energy from the blast emerge from below the water line
The final lake tap blast took place on August 19, 2008.
![Page 25: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/25.jpg)
LAKE DOROTHY IS TAPPED!
![Page 26: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/26.jpg)
Bifurcation of 60-inch penstock
![Page 27: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/27.jpg)
![Page 28: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/28.jpg)
![Page 29: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/29.jpg)
Barge Landing Facility
Substation & Camp
Shop & Crew Quarters
Powerhouse
Access Road
![Page 30: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/30.jpg)
Losing Downhill Slope
![Page 31: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/31.jpg)
Completed Road
![Page 32: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/32.jpg)
Construction of concrete face panels
![Page 33: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/33.jpg)
Reservoir Elevation 985 feet
![Page 34: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/34.jpg)
6.4 cfs
![Page 35: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/35.jpg)
Lake Dorothy Powerhouse
The Lake Dorothy Project went into operation on Aug. 31, 2009
![Page 36: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/36.jpg)
Challenges Constructing the
Lake Dorothy Project
![Page 37: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/37.jpg)
Only Access to Site by Air
![Page 38: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/38.jpg)
Seasonal Working
Conditions
![Page 39: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/39.jpg)
Initial landing areas were limited
![Page 40: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/40.jpg)
All Tunneling Equipment Airlifted in Pieces
![Page 41: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/41.jpg)
Fog and rain can move in very quickly
![Page 42: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/42.jpg)
Weather Impacts
Good weather where crew could easily access tunnel - Rates of 40 feet per day
Typical advance rates averaged 25 feet per day
Changing weather conditions prevented mining crews from achieving steady advancement rates.
Fog and wind could quickly show up and force an early exit form the portal
2007 – 35 weather related delay days
2008 – 33 weather related delay days
![Page 43: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/43.jpg)
Allison Creek DamConstruction 2014-16
Main Project Features
• 16-foot-high, 95-foot-wide concrete gravity diversion dam with 50-foot-wide spillway
• 42-inch-diameter, 7,200-foot-long steel penstock
• 700-foot-long, 16-foot-diameter access tunnel through which a segment of the penstock would be routed
• 65 foot by 65 foot powerhouse with two turbine/generating units with a combined capacity of 6.5-MW
![Page 44: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/44.jpg)
Alyeska Oil Terminal
![Page 45: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/45.jpg)
Powerhouse foundation construction with lower tunnel
portal in background
![Page 46: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/46.jpg)
Upper Portal August 2014 – Tunnel near completion
![Page 47: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/47.jpg)
Pioneering Road from Upper Portal to Dam Site
August 2014
![Page 48: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/48.jpg)
Diversion Dam Site July 2015
Twin 48-inch-diameter CMP diversion conduits carry
Allison Creek through right abutment
![Page 49: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/49.jpg)
View of Penstock Below Lower Tunnel Portal and
Powerhouse Below July 2015
![Page 50: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/50.jpg)
Concrete being placed for diversion dam intake structure.
August 2015
![Page 51: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/51.jpg)
Allison Creek diversion dam at spring break-up 2016
getting ready for final construction season to start.
![Page 52: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/52.jpg)
Allison Creek Powerhouse at spring break-up 2016
![Page 53: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/53.jpg)
Allison Creek Diversion Dam nearing completion
June 2016
![Page 54: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/54.jpg)
Mass excavation of steep slope in reach 4 continues before
penstock installation (dashed line) can resume.
![Page 55: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/55.jpg)
Upstream face of completed diversion dam with reservoir
full to the top of the spillway. August 2016
![Page 56: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/56.jpg)
Downstream View of Completed Diversion Dam
![Page 57: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/57.jpg)
Completed Powerhouse
![Page 58: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/58.jpg)
Cold Climate Design Considerations
Rugged terrain, no existing roads – the use of tunnels is common in Alaska. Construction can continue through winter.
The Allison tunnel was designed to serve as both the penstock route and construction access road to site.
Very Limited window for construction – June to September. Took 3 years to complete project.
Frigid temps and deep snow necessitated burying penstock
Project can only generate 6 months out of the year due to deep snow and frozen conditions at diversion dam.
![Page 59: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/59.jpg)
Hebgen Lake Dam
![Page 60: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/60.jpg)
Hebgen Lake Dam
Dam Height = 88ftCrest Length = 721 ftNormal Storage 386,000 af
![Page 61: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/61.jpg)
Hebgen Lake Dam
Underwent 2 major rehab projects in the 2008-2016 period.
Failure of Outlet Tower Stoplogs in Aug 2008 + seismic inadequacy –necessitated rehab of tower 2008-14
Spillway removal and replacement 2015-16
![Page 62: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/62.jpg)
Outlet Tower Rehab
Had to build cellular cofferdam first to dewater front of tower.
Work could not proceed in winter, due to ice, snow, and reservoir lowering which required use of outlet instead of spillway.
Cofferdam provided with a spillway gate to discharge wintertime flows.
Scope of Project was to first stabilize tower, then improve seismic stability, replace the intake gates, and install a guard gate
![Page 63: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/63.jpg)
Cellular cofferdam
Outlet tower
![Page 64: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/64.jpg)
Winter comes early here
December 8, 2010
![Page 65: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/65.jpg)
Work was able to continue despite cold and snow
![Page 66: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/66.jpg)
View inside Outlet Tower
Extreme danger posed by ice overhead from
leaking stoplogs.
![Page 67: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/67.jpg)
Rebar and concrete damaged from winter flows.
June 3013
![Page 68: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/68.jpg)
Eventually, the structure was competed, in 2015!
Which leads us to the next phase…..
![Page 69: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/69.jpg)
Spillway Removal and
Replacement Once Intake was completed and functional,
spillway removal could start
Contractor reused sheetpiling from outlet cellular cofferdam to construct new cofferdam in front of spillway.
Cofferdam installed in December 2015 so that it would be in place come spring, when reservoir was filled.
New Outlet Tower acted as only spillway during
construction.
![Page 70: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/70.jpg)
Being December, it wasn’t the most hospitable
condition for construction!
![Page 71: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/71.jpg)
Sheet Piling being installed
![Page 72: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/72.jpg)
View of ongoing removal of cofferdam from intake
structure.
![Page 73: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/73.jpg)
Not surprisingly, come the following spring, there
was a lot of seepage through the cofferdam!
550 gpm.
![Page 74: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/74.jpg)
Subsequently, a second cofferdam and sheetpile
wall was constructed along with a sump to improve
seepage control at the site
![Page 75: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/75.jpg)
View of cofferdam with spillway fully removed
![Page 76: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/76.jpg)
Once again, construction extended into December
Placing embankment fill around core wall
![Page 77: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/77.jpg)
Blankets were placed on fill surface at night to
keep snow off and prevent freezing.
![Page 78: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/78.jpg)
Snow was cleared off and blankets removed in
morning prior to fill placement.
![Page 79: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/79.jpg)
Finished Spillway and closure embankment in
2017
![Page 80: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/80.jpg)
Finished Spillway Chute
![Page 81: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/81.jpg)
Takeaway Points
Short construction seasons mean that work must be done in multi-year stages. Detailed scheduling and planning ahead are critical.
Severe weather conditions can damage recently completed work. Protecting partially completed work from damage can prevent delays in construction schedule.
Tunneling work can be done year round. This makes building a combined power tunnel (or penstock) and construction access road attractive.
![Page 82: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/82.jpg)
Takeaway Points
Portable structures such as tents and canopies can help extend the construction seasons but may require dis/re-assembly for winter snow loading.
In Alaska, lack of access is as much a problem as the cold climate. Equipment and supplies must be barged or helicoptered in, making construction costs much higher and advanced planning for deliveries critical.
![Page 83: Dams in Cold Climates: Design Considerations and ...€¦ · Spillway Removal and Replacement Once Intake was completed and functional, spillway removal could start Contractor reused](https://reader034.fdocuments.in/reader034/viewer/2022042115/5e92aa965ae76e09d32abccc/html5/thumbnails/83.jpg)
QUESTIONS?