Dam Maintenance Fact Sheet Maintenance Fact Sheet ... 82 dams are jurisdictional (creates a...
Transcript of Dam Maintenance Fact Sheet Maintenance Fact Sheet ... 82 dams are jurisdictional (creates a...
C O L O R A D O P A R K S & W I L D L I F E
Dam Maintenance Fact Sheet
5-YR PARKS AND WILDLIFE FUNDING PROPOSAL FOR DAMS
COLORADO PARKS & WILDLIFE • 6060 Broadway, Denver CO 80216 • (303) 297-1192 • cpw.state.co.us
Colorado Parks and Wildlife (CPW) owns and operates over 110 dams (100 Wildlife, 10 Parks) , the largest inventory of dams for any owner in the State. An inventory of the dams shows that, as classified by the State of Colorado, the CPW dams are classified as follows:
82 dams are jurisdictional (creates a reservoir which impounds more than 100 acre-feet, or a surface area in excess of 20 acres, or dam exceeds 10 feet in height)
17 are high hazard (loss of human life is expected to result from failure of the dam) 17 are significant hazard (significant damage is expected to occur, but no loss of human life is expected)
48 low hazard (no human loss and no significant damage is expected from a dam failure)
In mid-2013, CPW developed a Screening Level Risk Analysis (SLRA) tool to provide an overview of our dams’ risk profile and to assist in prioritizing future actions to manage and reduce risks for the portfolio. The SLRA results clearly indicated that based on the consequences vs. the probability of occurrence that 11 dams were higher risk and very evenly matched. In order to determine the priority of fixing these dams, we developed an analysis “tool” that considered multiple factors including; Loss of Life, Economic/ Recreation and Environmental Impacts.
Based on the results of this analysis, 11 CPW dams are in need of critical repairs to reduce their risk to an acceptable level. Of these 11 dams, two (2) are “parks-owned” dams and nine (9) are “wildlife-owned” dams. The total capital necessary to improve these 11 dams, in 2015 dollars is $38,890,000.00. Accomplishing this important work will take years.
1. Alberta Park (w) 7. Sylvan Lake (p)
2. Willow Creek (p) 8. Spring Creek (w)
3. Chief Creek #4 (w) 9. Haviland Lake (w)
4. Rito Hondo (w) 10. Black Lake #2 (w)
5. Trujillo Meadows (w) 11. Two Buttes (w)
6. Big Meadows (w)
5 year Funding Proposal
Year Parks Capital Wildlife Capital Parks Maintenance Wildlife Maintenance 2016/17 $8,000,000.00 $2,000,000.00 $800,000.00 $600,000.00
2017/18 $2,500,000.00 $2,100,000.00 $800,000.00 $630,000.00 2018/19 $2,500,000.00 $2,200,000.00 $800,000.00 $660,000.00 2019/2020 $0.0 $2,300,000.00 $800,000.00 $690,000.00
2020/2021 $0.0 $2,400,000.00 $800,000.00 $720,000.00 Total $13,000,000.00 $11,000,000.00 $4,000,000.00 $3,300,000.00
The Dam Capital Request will be updated annually for a 5-yr period until we have accomplished our goal of reducing risk at the facilities to a level that meets industry standards. An ongoing maintenance budget will still be required to keep all 110 dams in reasonable condition and to fix minor problems before they require major repairs. For the last 4 years we have experience at least one dam repair emergency per year, which requires a quick response and available funds.
Proposed Capital Dam Funding Fact Sheet
COLORADO PARKS & WILDLIFE • 6060 Broadway, Denver CO 80216 • (303) 297-1192 • cpw.state.co.us
Alphabetical List of CPW’s Portfolio of Jurisdictional Dams
High Hazard
Dams
Significant Hazard
Dams
Low Hazard Dams 1 Alberta Park1 Banner Lake #1 North Michigan Creek
2 Beaver Park2 Banner Lake #10 Poose Creek
3 Big Beaver Banner Lake #11 R.R. Rutherford
4 Big Meadows Banner Lake #2 Road Canyon #2
5 Black Lake #2 Banner Lake #3 Sand Creek
6 Chief Creek #4 Banner Lake #4 Supply Basin
7 Dowdy Lake Banner Lake #5 Twin Lakes
8 Echo Canyon Banner Lake #8 Upper Dome
9 Flagler Beaver Lake Upper Elk Falls Ranch
10 Garfield Wildlife Pond Bellaire Upper Stillwater
11 Garnet Mesa Cabin Creek Watson Lake2
12 Haviland Lake Clark White Owl
13 Heart Lake Davis #1 Woods Lake
14 Horseshoe Lake Davis #2 Zimmerman Lake 2
15 La Jara Dam Davis #3
16 Lake Christine Deer Creek #1
17 Lake John Deer Creek #3
18 Lester Creek Deer Creek #4
19 Meadow Creek1 Duck Slough
20 Miramonte Freeman
21 Parvin Frenchman Creek
22 Rito Hondo Hahns Peak
23 Road Canyon #1 Heart Lake North Dike
24 Skaguay Home Lake
25 Spring Creek Johnnie Johnson
26 Sylvan Lake Jumbo
27 Tarryall Karval 2
28 Troutvale #1 (upper) L.G. Kinney
29 Troutvale #2 (lower) Lake Brennand
30 Trujillo Meadows Lake John Annex
31 Two Buttes2 Las Animas Fish Hat. 70B
32 Upper Highline Lost Lake
33 Williams Creek Mesa Creek #2
34 Willow Creek Muddy Creek
(1) Alberta Park and Meadow Creek Dams are being reclass i fied to High Hazard dams (2) Currently under a State Engineer’s Office Storage Restriction
STATE OF COLORADO DEPARTMENT OF NATURAL RESOURCES COLORADO PARKS AND WILDLIFE 6060 BROADWAY | DENVER, CO 80216
Executive Summary Screening Level Risk Analysis Colorado Parks & Wildlife Project No. 114-311351 Date: February 2, 2015
350 Indiana Street, Suite 500, Golden, CO 80401 Phone: 303-217-5700 Fax: 303-217-5705
Screening Level Risk Analysis Colorado Parks & Wildlife
February 2015 1
1 .0 EXECUTIVE SUMMARY
1 . 1 P R O J E C T O V E R V I E W
Colorado Parks and Wildlife (CPW) owns and operates over 110 dams, the largest inventory of dams for any owner in the State (Figure 1-1). An inventory of the dams shows that, as classified by the State of Colorado, the CPW dams are classified as follows (Table 1-1):
82 dams are jurisdictional (creates a reservoir which impounds more than 100 acre-feet, or a surface area in excess of 20 acres, or dam exceeds 10 feet in height)
17 are high hazard (loss of human life is expected to result from failure of the dam)
17 are significant hazard (significant damage is expected to occur, but no loss of human life is expected)
48 are low hazard (no human loss and no significant damage is expected from a dam failure)
The average age of this portfolio of dams is approximately 67 years, with construction of most of the dams taking place between 1950 and mid 1970’s. The majority of dams are earthen structures, generally with an impervious core and an up and downstream shell. Two older dams, Skaguay and Beaver Park, are rockfill dams. Tarryall Dam, a thin concrete arch dam, was constructed in the mid-1920’s. The dams are exposed to highly-variable climatic conditions, and many structures have limited seasonal access due to their elevation, and normal snow pack.
Figure 1-1 - Location of CPW’s High and Significant Hazard Dams
Screening Level Risk Analysis Colorado Parks & Wildlife
February 2015 2
Table 1-1 - CPW’s Portfolio of Jurisdictional Dams (Alphabetically Sorted)
High Hazard Dams Significant Hazard Dams Low Hazard Dams
1 Alberta Park1 Banner Lake #1 Muddy Creek
2 Beaver Park2 Banner Lake #10 North Michigan Creek
3 Big Beaver Banner Lake #11 Poose Creek
4 Big Meadows Banner Lake #2 R.R. Rutherford
5 Black Lake #2 Banner Lake #3 Road Canyon #2
6 Chief Creek #4 Banner Lake #4 Sand Creek
7 Dowdy Lake Banner Lake #5 Supply Basin
8 Echo Canyon Banner Lake #8 Twin Lakes
9 Flagler Beaver Lake Upper Dome
10 Garfield Wildlife Pond Bellaire Upper Elk Falls Ranch
11 Garnet Mesa Cabin Creek Upper Stillwater
12 Haviland Lake Clark Watson Lake2
13 Heart Lake Davis #1 White Owl
14 Horseshoe Lake Davis #2 Woods Lake
15 La Jara Dam Davis #3 Zimmerman Lake 2
16 Lake Christine Deer Creek #1
17 Lake John Deer Creek #3
18 Lester Creek Deer Creek #4
19 Meadow Creek1 Duck Slough
20 Miramonte Freeman
21 Parvin Frenchman Creek
22 Rito Hondo Hahns Peak
23 Road Canyon #1 Heart Lake North Dike
24 Skaguay Home Lake
25 Spring Creek Johnnie Johnson
26 Sylvan Lake Jumbo
27 Tarryall Karval 2
28 Troutvale #1 (upper) L.G. Kinney
29 Troutvale #2 (lower) Lake Brennand
30 Trujillo Meadows Lake John Annex
31 Two Buttes2 Las Animas Fish Hat. 70B
32 Upper Highline Lost Lake
33 Williams Creek Mesa Creek #2
34 Willow Creek
(1) Alberta Park and Meadow Creek Dams are being reclassified to High Hazard dams (2) Currently under a State Engineer’s Office Storage Restriction
With this number and varied condition of dams, coupled with limited funds for capital and maintenance of the aging portfolio, CPW required methodology to:
1. Identify dams which may pose the largest risk 2. Develop a capital improvement plan for funding improvements, and 3. Prioritize actions with the acknowledgement that capital and personnel resources are
limited.
Screening Level Risk Analysis Colorado Parks & Wildlife
February 2015 3
In order to meet these goals and objectives, the CPW embarked upon a Screening Level Risk Analysis (SLRA) for the high and significant hazard dams.
1 . 2 S C R E E N I N G L E V E L R I S K A N A L Y S I S
CPW determined that a semi-quantitative method was the most appropriate way to efficiently evaluate risks associated with 34 high and significant hazard dams that it owns and operates. The CPW Dam Operations Engineer engaged with the agency responsible for regulating these dams, the Division of Water Resources State Engineer’s Office (SEO), to capitalize on the knowledge base within these two Department of Natural Resources agencies. In mid-2013, CPW retained Tetra Tech to design and facilitate the process, and codify the results for the Screening Level Risk Analysis (SLRA).
The SLRA generally follows the Best Practices in Dam and Levee Safety Risk Analysis prepared by Reclamation and the U. S. Army Corp of Engineers (USACE). Dams were screened in a workshop setting, attended by SEO Dam Safety Engineers, CPW and Tetra Tech personnel. To facilitate rapid assessment of the risk of each dam, Tetra Tech developed an SLRA tool that enabled capture of information about the dam as well as to facilitate discussion of potential failure modes (PFM). The output of each workshop included a semi-quantitative risk assessment and ranking for each dam.
1 . 3 P O T E N T I A L F A I L U R E M O D E S & L O S S O F L I F E
Dams were generally classified based upon the likelihood of failure (qualitatively ranked from low to very high likelihood - Figure 1-2) and the potential for loss of life (Figure 1-3 —Level 1 indicates that the loss of life is unlikely; Level 4 indicates that loss of life could be greater than 100 persons).
Screening Level Risk Analysis Colorado Parks & Wildlife
February 2015 4
Figure 1-2 - Failure likelihood categories and descriptors for semi-quantitative dam safety studies.
Screening Level Risk Analysis Colorado Parks & Wildlife
February 2015 5
Figure 1-3 - Loss of life consequences descriptors mirror for a semi-quantitative assessment.
Once the individual failure likelihood/consequence value was determined for each PFM, all PFMs were factored and summed to represent the overall potential for risk by dam. Table 1-2 provides this data.
Table 1-2 - PFM Scoring for Loss of Life (N) x Failure Likelihood (f)
Dam Name Sum of PFMs from f-N Chart Dam Name Sum of PFMs Considering f-N Chart
Alberta Park 142 Flagler 17
Rito Hondo 52 Lester Creek 17
Willow Creek 45 Heart Lake 14
Sylvan Lake 43 Dowdy Lake 13
Big Meadows 42 Tarryall 13
Haviland Lake 41 Lake John 12
Trujillo Meadows 41 Horseshoe Lake 11
Chief Creek #4 40 Miramonte 11
Spring Creek 39 Parvin 11
Black Lake #2 31 Williams Creek 11
Two Buttes 31 Lake Christine 10
Troutvale #2 24 Troutvale #1 10
Road Canyon 23 La Jara #1 8
Garnet Mesa 21 Beaver Park 3
Meadow Creek 21 Skaguay 3
Upper Highline 20 Echo Canyon 2
Screening Level Risk Analysis Colorado Parks & Wildlife
February 2015 6
1 . 4 R E C R E A T I O N / E C O N O M I C & E N V I R O N M E N T A L R I S K F A C T O R S
Due to limited resources, CPW required additional factors to assist in prioritizing capital and maintenance projects. In keeping with the CPW Dam Safety Mission to “Prevent loss of life and property damage, manage reservoirs to enhance the wildlife resources of the state and provide enjoyable and sustainable outdoor recreational opportunities” CPW decided to include the evaluation of environmental and economic/recreational factors that would be affected downstream of each dam should it fail. Table 1-3 explains the qualitative, semi-quantitative and quantative units that were used for input into the decision model.
Table 1-3 - Qualitative and Quantative Environmental & Economic Attributes
Attributes Placed in Model for Assessment Associated Units (Quantitative, Qualitative or Semi-Qualitative)
ENVIRONMENTAL
BIOLOGICAL DIVERSITY
Aquatic: Downstream River Fishery 1 to 5 ranking (5 is important) Terrestrial 1 to 5 ranking (5 is important)
CULTURAL RESOURCES 1 to 5 ranking (5 is important)
RECREATION/ECONOMIC
COSTS
Essential Facilities (from FEMA’s HAZUS) # of Facilities with Loss of Use Damage to Structures (from HAZUS) $ / 10,000 Dam Reconstruction Costs $ / 10,000 Road Level of Service
Federal Average Annual Daily Traffic (AADT) State AADT
County AADT Diversity Fish Replacement Cost $/1,000
REVENUE
Fishing Recreation Day Annual Economic Value $/1,000 Water Rights 0 to 5 ranking (5 is important) Park Revenue Annual Park Revenue in $ / 1000
POTENTIAL FAILURE/LOSS OF LIFE
Number of people who might potentially suffer loss of life (Consequence) X Likelihood
0 to 150 Summed for Each Dam’s PFM
1 . 5 L I F E L O S S , R E C R E A T I O N / E C O N O M I C I M P A C T A N D E N V I R O N M E N T A L
R I S K S C R E E N I N G
Using these quantitative and qualitative data, each criteria category was given a weight by CPW staff based on its importance. Rankings add to 100%, and in the outcomes presented below loss of life was given a weight of 80, Environment was given a weight of 15, and Recreation/Economic Impact was given a weight of 5, summing to a total of 100. Because of the importance of loss of life, it was given a commensurate high weighting. When the model was run with this weighting, the dams are prioritized around the estimated loss of life due to failure (Figure 1-4).
Screening Level Risk Analysis Colorado Parks & Wildlife
February 2015 7
Figure 1-4 - Prioritization of Dam capital improvements based on loss of life weighting at 80%; environment weighted at 15% and recreation/economic impact weighted at 5% in overall importance
1 . 6 R E C O M M E N D A T I O N S A N D C O N C L U S I O N S
Findings from the potential failure mode analyses include that the average condition of the high hazard dams is fair, with a number of dams having inadequately-sized spillways and, as such, are unable pass the 100-year or greater flood. Generally the significant hazard dams are in similar condition, while the low and non-jurisdictional dams tend to be in relatively worse condition. Additional effort from the CPW’s outlet investigation program conducted in 2014 determined that a number of the outlet works were in need of immediate repair. In addition, maintenance work is needed on some of the structures’ embankments, outlet works, spillways, and other appurtenances. There are some rehabilitation, refurbishment and replacement items that require immediate attention in order to manage the potential for loss of life or significant damage to downstream facilities and the environment.
Table 1-4 provides an overview of the condition and risk analysis information of the highest priority dams, as well as a rough order magnitude (ROM) cost for repairing, replacing or refurbishing dam structures and appurtenances.
Screening Level Risk Analysis Colorado Parks & Wildlife
February 2015 8
Table 1-4 - ROM Estimate to Replace, Repair and Refurbish the Highest Priority Structures
Dam Potential Failure Mode Analysis (PFMA)
Required Capital Improvements (Rough Order of Magnitude -ROM)
Estimated Maintenance Work
Estimated Repair Costs (ROM) Estimated Capital Costs
Alberta Park*
Significant Hazard
Overtopping of Embankment by Flood - (Undersized Spillway) Concentrated leakage out of conduit
Enlarge spillway Rehabilitate Outlet Pipe
Perform survey for dam and set monumentation Rehabilitate gate to reduce leakage at gate
Spillway Work - $2.75M Rehabilitate outlet conduit -$400K Rehabilitate outlet gate - $400k Set survey monumentation -$20k $3,570,000
Willow Creek
High Hazard
(Parks Dam)
Concentrated leakage into/ out of conduit Tower
Tower is structurally deficient - working with a consultant to identify solution
Tower work is currently being evaluated - repair costs presented are approximate $8,000,000
Rito Hondo
Significant Hazard
Overtopping of Embankment by Flood - (Undersized Spillway) Concentrated leakage out of conduit Left Abutment Seepage issues (filter and collections system required)
Enlarge spillway Rehabilitate Outlet Pipe Design filter and drainage system for left abutment
Perform survey for dam and set monumentation Rehabilitate gate to reduce leakage at gate
Spillway Work - $2.75M Rehabilitate outlet conduit -$400K Rehabilitate outlet gate -$400K Set survey monumentation -$20K Resolve left abutment seepage -$200K $3,770,000
Trujillo Meadows
Significant Hazard
Overtopping of embankment by flood (undersized spillway) Concentrated leakage into conduit
Enlarge spillway Rehabilitate outlet pipe Add seepage collection for left abutment
Perform survey for dam and set monumentation Rehabilitate gate to reduce leakage at gate Correct spillway channel to remove water from outlet pipe
Spillway Work - $2.75M Rehabilitate outlet conduit -$500K Rehabilitate outlet gate - $400K Set survey monumentation -$20K Spillway channel- $30K $3,870,000
Big Meadows
High Hazard
Overtopping of embankment by flood Saddle dam is 3-ft lower than the main dam
Enlarge spillway Evaluate saddle dam with inflow design flood Determine if capacity must be increased
Perform survey for dam and set monumentation
Spillway Work - $2.75M Improve Saddle Dam - $300K Raise 4-ft and set survey monumentation - $20k $3,070,000
Spring Creek
High Hazard Concentrated leakage into conduit Rehabilitate Conduit
Perform survey for dam and set monumentation
Rehabilitate outlet pipe and gate - $500K Set survey monumentation - $20K $520,000
Sylvan Lake
High Hazard
(Parks Dam)
Overtopping of Embankment by flood - (undersized spillway) Concentrated leakage into conduit
Enlarge spillway (Alternative report currently in progress) Rehabilitate conduit
Perform survey for dam and set monumentation (with the current design)
Spillway Work - $3.0M Rehabilitate outlet conduit - $400K Rehabilitate Gate - $400K Set survey monumentation -$20K $4,000,000
Screening Level Risk Analysis Colorado Parks & Wildlife
February 2015 9
Dam Potential Failure Mode Analysis (PFMA)
Required Capital Improvements (Rough Order of Magnitude -ROM)
Estimated Maintenance Work
Estimated Repair Costs (ROM) Estimated Capital Costs
Black Lake #2
Significant Hazard Overtopping of embankment by flood
Enlarge spillway Complete hydrology study
Perform survey for dam and set monumentation
Spillway Work - $1.5M Set survey monumentation -$20K $1,700,000
Haviland Lake
High Hazard
Overtopping of embankment by Flood Concentrated leakage into conduit
Rehabilitate Conduit Perform hydrological analysis
Perform survey for dam and set monumentation
Rehabilitate outlet conduit - $400K Set survey monumentation - $20K Upgrade spillway - $1.0M $1,420,000
Chief Creek #4
Significant Hazard
Overtopping of embankment by Flood Concentrated leakage into conduit
Enlarge spillway Rehabilitate outlet works
Perform survey for dam and set monumentation Improve concrete slope paving on upstream side of dam embankment Rehabilitate gate to reduce leakage
Spillway Work -$2.0M Rehabilitate outlet gate -$200K Repair upstream slope paving - $30K Set survey monumentation -$20k $2,450,000
Two Buttes **
High Hazard
Overtopping of embankment by flood Dam currently restricted based on Spillway Maintenance work also include rehabilitation of outlet gates
Work with the State Dam Safety engineer to reduce the risk for the dam
Post Request For Qualifications for gate rehabilitation Determine if work to be performed in the wet or when reservoir is dry again Repair downstream channel from effects of 2013 flood
Repair Gates - $500K Spillway work - $6.0M Set survey monumentation - $20K $6,520,000
Subtotal Parks Dams $12,000,000
Subtotal Wildlife Dams $26,890,000
Subtotal Parks and Wildlife Dams (Table 1-4) $38,890,000
* Dam currently being re-classified to high hazard by SEO Repair & Maintenance - other High and Significant Hazard (Table 1-5) $3,403,500
** Currently under a State Engineers Office Storage Restriction Repair & Maintenance - Low and NJ Dams
(Table 1-6) $2,383,500
G R A N D T O T A L ESTIMATED REHABILITATION, REFURBISHMENT, REPAIR AND MAINTENANCE FOR ALL CPW DAMS $44,677,000
Screening Level Risk Analysis Colorado Parks & Wildlife
February 2015 10
Table 1-5 provides a rough order of magnitude estimate of refurbishment, rehabilitation and repair costs for the remaining high and significant hazard dams, as well as a rough order magnitude cost for annual maintenance of dam structures and appurtenances.
Table 1-5 - ROM Estimate to Replace, Repair and Refurbish Remaining High and Significant Hazard Structures
Dam Estimated Maintenance Work Estimated Cost
for Maintenance Work
Comments
Tarryall High Hazard
Clean Spillway $10,000 Complete Structural Analysis $275,000 Repair spalling concrete at joints $75,000 Repair upstream to resolve waterstop leakage $750,000 Perform Hydrology Study to determine overtopping of dam $40,000 Create inundation mapping for downstream $10,000
Dowdy Significant Hazard
Repair Vent Pipe (may cause dam to drain) $2,500 Repair damage from rodent burrow activity on south dam $10,000 Perform survey for dam and set monumentation $20,000 Rehabilitation of outlet pipe (specifically structural hole located at upper end) $300,000 Update Hydrology Study $40,000
Parvin Significant Hazard
Repair and/or remove old valve stem in outlet conduit $2,500 Complete video investigation following the above $6,500 Perform survey for dam and set monumentation $20,000
Big Beaver High Hazard
Grade Dam Crest and add roadbase $15,000 Perform survey for dam and set monumentation $20,000 Grade left abutment for drainage $7,500 Rehabilitate gates to reduce localized leakage $50,000
Meadow Creek* Significant Hazard
Perform outlet video inspection $6,500 Already Funded Construct headwall at outlet pipe $15,000 Update dam Hydrology Study and evaluate spillway $40,000 Perform survey for dam and set monumentation $20,000
Upper Highline High Hazard/Parks Continue monitoring program $100,000
Heart Lake High Hazard
Complete outlet video inspection $6,500 Grade Crest of dam and add roadbase $18,500 Replace seepage weir $20,000 Implement piezometer monitoring program $85,000 Already Funded Identify consultant to investigate seepage and install piezometers along seepage path $75,000 Perform survey for dam and set monumentation $20,000
Lake Christine Significant Hazard
Clear brush and trees from right side of spillway $2,000 DOC Crew Repair grouted riprap along spillway channel $15,500 Perform survey for dam and set monumentation $20,000
Garfield Wildlife Pond *** Significant Hazard
Clear brush and trees from dam $3,500 DOC Crew
Alternative for Dam Embankment $25,000
Lake John Significant Hazard
Perform Video Outlet Inspection $6,500 Already funded Maintain repaired condition for upstream and downstream slopes (specifically regarding animal activity) $15,000 Perform survey for dam and set monumentation $20,000
Lester Creek (Pearl Lake) High Hazard/Parks
Perform survey for dam and set monumentation Check spillway elevation in relation to dam crest $20,000
Horseshoe Dam (Lathrop State Park) High Hazard/Parks
Seal leakage in horizontal opening in principal spillway riser $15,000
Continue with rodent abetment $5,000
Screening Level Risk Analysis Colorado Parks & Wildlife
February 2015 11
Dam Estimated Maintenance Work Estimated Cost
for Maintenance Work
Comments
Skaguay Significant Hazard
Structural analysis for existing retaining wall $75,000 Resolve willow growth in spillway channel $4,000 DOC Crew Perform survey for dam and set monumentation $20,000 Direct divers to assess condition of upstream steel plate $15,000
Williams Creek High Hazard
Perform survey for dam and set monumentation $20,000 Grade Spillway Crest and add roadbase material $15,000 Minor clearing of vegetation (upstream and downstream) $3,000 DOC Crew
Perform lower gate seepage investigation $7,000 Diver Only - Check Gate
Update Hydrology Report and assess spillway capacity $40,000 Rehabilitate gates to reduce gate leakage $250,000
Echo Canyon Significant Hazard
Grade Crest and add roadbase material $12,500 Clear vegetation in spillway and dam groins $3,000 DOC Crews Perform survey for dam and set monumentation $20,000
Beaver Park ** Currently under repair
Currently under repair
Upper Troutvale #1 Significant Hazard
Clear brush on right toe of dam $3,000 DOC Crew Repair joints in spillway $12,500
Perform outlet video inspection $6,500
Previous inspection yielded sub-optimal results
Perform survey for dam and set monumentation $20,000
Lower Troutvale #2 Significant Hazard
Rehabilitate outlet conduit and wet well $250,000 Perform survey for dam and set monumentation $20,000
La Jara Significant Hazard
Keep animal borrows off of dam $5,000 Perform survey for dam/ set Monumentation $20,000 Clear vegetation from downstream dam face $3,000 DOC crew
Garnet Mesa (Sweitzer Lake) High Hazard/Parks
Tree and weed control Update hydraulic motor for gate Perform survey for dam and set monumentation
$5,000 $5,000
$20,000
DOC crew
Miramonte High Hazard
Clean spillway (rock falls) Seal cracks in spillway Perform survey for dam and set monumentation Update Hydrology Report (undersized spillway)
$12,000 $5,000
$20,000 $40,000
TOTAL REHAB/REPAIR FOR 4 REMAINING PARKS DAMS $ 170,000
TOTAL REHAB/REPAIR FOR REMAINING 17 WILDLIFE DAMS $2,969,500
TOTAL REHAB/REPAIR & REFURBISHMENT FOR REMAINING 21 HIGH & SIGNIFICANT HAZARD DAMS (ENSURES DAMS ARE FUNCTIONING AS INTENDED)
$3,139,500
Complete inundation mapping for all dams (Assume $8K per dam)
$264,000
GRAND TOTAL $3,403,500
* Dam currently being re-classified to high hazard by SEO
** Currently under a State Engineers Office Storage Restriction *** Currently a Significant Hazard Dam - should be rated as Low Hazard
Table 1-6 provides a rough order of magnitude estimate of refurbishment, rehabilitation and repair costs for the low hazard and non-jurisdictional dams, as well as a rough order magnitude cost for annual maintenance of dam structures and appurtenances.
Screening Level Risk Analysis Colorado Parks & Wildlife
February 2015 12
Table 1-6 - ROM Estimate to Replace, Repair and Refurbish and Maintain Low Hazard and Non-Jurisdictional Dams
Dam Name Description of Work
Rehabilitation, Replacement,
Refurbishment, Maintenance
Cost
LOW HAZARD DAMS Rehabilitation, Replacement, and Refurbishment Items
ZIMMERMAN LAKE** Needs to be re-built $1,500,000
WATSON LAKE** Flood Damage and Inlet needs to be re-built $208,000
NORTH MICHIGAN CREEK (Parks Dam)
Needs some concrete work in the spillway - and other maintenance work - Dam is in State Forrest State Park
$75,000
KARVAL** Buttress was not constructed correctly - needs to be removed and re-built
$500,000
Sub-Total Rehabilitation, Replacement and Refurbishment Items (Low Hazard) $2,283,000
** Currently under a State Engineers Office Storage Restriction
Annual Maintenance Items – Low Hazard Dams Annual Maintenance Cost
DAVIS #3 (Parks Dam) Estimated Annual Maintenance Low Hazard Dam $ 1,000
DAVIS #2 (Parks Dam) Estimated Annual Maintenance Low Hazard Dam $ 1,000
DAVIS #1 (Parks Dam) Estimated Annual Maintenance Low Hazard Dam $ 1,000
UPPER ELK FALLS RANCH (Parks Dam)
Estimated Annual Maintenance Low Hazard Dam $ 1,000
BANNER LAKE #1 Estimated Annual Maintenance Low Hazard Dam $ 1,000
BANNER LAKE #2 Estimated Annual Maintenance Low Hazard Dam $ 1,000
BANNER LAKE #3 Estimated Annual Maintenance Low Hazard Dam $ 1,000
BANNER LAKE #4 Estimated Annual Maintenance Low Hazard Dam $ 1,000
BANNER LAKE #5 Estimated Annual Maintenance Low Hazard Dam $ 1,000
BANNER LAKE #8 Estimated Annual Maintenance Low Hazard Dam $ 1,000
BANNER LAKE #10 Estimated Annual Maintenance Low Hazard Dam $ 1,000
BANNER LAKE #11 Estimated Annual Maintenance Low Hazard Dam $ 1,000
FRENCHMAN CREEK Estimated Annual Maintenance Low Hazard Dam $ 1,000
SAND CREEK Estimated Annual Maintenance Low Hazard Dam $ 1,000
LOST LAKE Estimated Annual Maintenance Low Hazard Dam $ 1,000
BELLAIRE Estimated Annual Maintenance Low Hazard Dam $ 1,000
TWIN LAKES Estimated Annual Maintenance Low Hazard Dam $ 1,000
JOHNNIE JOHNSON Estimated Annual Maintenance Low Hazard Dam $ 1,000
POOSE CREEK Estimated Annual Maintenance Low Hazard Dam $ 1,000
FREEMAN Estimated Annual Maintenance Low Hazard Dam $ 1,000
MESA CREEK #2 Estimated Annual Maintenance Low Hazard Dam $ 1,000
BEAVER LAKE Estimated Annual Maintenance Low Hazard Dam $ 1,000
WHITE OWL Estimated Annual Maintenance Low Hazard Dam $ 1,000
SUPPLY BASIN Estimated Annual Maintenance Low Hazard Dam $ 1,000
HEART LAKE NORTH DIKE Estimated Annual Maintenance Low Hazard Dam $ 1,000
MUDDY CREEK Estimated Annual Maintenance Low Hazard Dam $ 1,000
UPPER STILLWATER Estimated Annual Maintenance Low Hazard Dam $ 1,000
Screening Level Risk Analysis Colorado Parks & Wildlife
February 2015 13
Dam Name Description of Work
Rehabilitation, Replacement,
Refurbishment, Maintenance
Cost
LAKE JOHN ANNEX Estimated Annual Maintenance Low Hazard Dam $ 1,000
HAHNS PEAK Estimated Annual Maintenance Low Hazard Dam $ 1,000
R.R. RUTHERFORD Estimated Annual Maintenance Low Hazard Dam $ 1,000
CABIN CREEK Estimated Annual Maintenance Low Hazard Dam $ 1,000
L.G. KINNEY Estimated Annual Maintenance Low Hazard Dam $ 1,000
DUCK SLOUGH Estimated Annual Maintenance Low Hazard Dam $ 1,000
DEER CREEK #3 Estimated Annual Maintenance Low Hazard Dam $ 1,000
DEER CREEK #4 Estimated Annual Maintenance Low Hazard Dam $ 1,000
DEER CREEK #1 Estimated Annual Maintenance Low Hazard Dam $ 1,000
UPPER DOME Estimated Annual Maintenance Low Hazard Dam $ 1,000
LAKE BRENNAND Estimated Annual Maintenance Low Hazard Dam $ 1,000
HOME LAKE Estimated Annual Maintenance Low Hazard Dam $ 1,000
ROAD CANYON #2 Estimated Annual Maintenance Low Hazard Dam $ 1,000
WOODS LAKE Estimated Annual Maintenance Low Hazard Dam $ 1,000
Sub-Total Estimated Annual Maintenance (Low Hazard Dams) $41,000
NON - JURISDICTIONAL DAMS
Rehabilitation, Replacement, and Refurbishment Items
BANNER LAKE #7 $50,000
Sub-Total Rehabilitation, Replacement and Refurbishment Items (Non-Jurisdictional) $50,000
Annual Maintenance Items – Non Jurisdictional Dams
BANNER LAKE #12A Est. Annual Maintenance Non-Jurisdictional Dam $ 500
BANNER LAKE #6 Est. Annual Maintenance Non-Jurisdictional Dam $ 500
BANNER LAKE #9 Est. Annual Maintenance Non-Jurisdictional Dam $ 500
TAMARAC WILDLIFE AREA POND B
Est. Annual Maintenance Non-Jurisdictional Dam $ 500
JUMBO Est. Annual Maintenance Non-Jurisdictional Dam $ 500
MACK MESA Est. Annual Maintenance Non-Jurisdictional Dam $ 500
BISON LAKE Est. Annual Maintenance Non-Jurisdictional Dam $ 500
KONANTZ Est. Annual Maintenance Non-Jurisdictional Dam $ 500
LAS ANIMAS FISH HAT. 70A
Est. Annual Maintenance Non-Jurisdictional Dam $ 500
FRANZ #2 Est. Annual Maintenance Non-Jurisdictional Dam $ 500
FRANZ #1 Est. Annual Maintenance Non-Jurisdictional Dam $ 500
CLINGINGSMITH #2 Est. Annual Maintenance Non-Jurisdictional Dam $ 500
HOMESTAKE CREEK Est. Annual Maintenance Non-Jurisdictional Dam $ 500
SMITH Est. Annual Maintenance Non-Jurisdictional Dam $ 500
ROCK CREEK Est. Annual Maintenance Non-Jurisdictional Dam $ 500
MUDDY CREEK Est. Annual Maintenance Non-Jurisdictional Dam $ 500
CLAY CREEK Est. Annual Maintenance Non-Jurisdictional Dam $ 500
FOUNTAIN CREEK #2 Est. Annual Maintenance Non-Jurisdictional Dam $ 500
FOUNTAIN CREEK #3 Est. Annual Maintenance Non-Jurisdictional Dam $ 500
Sub-Total Estimated Annual Maintenance (Non-Jurisdictional Dams) $ 9,500
Screening Level Risk Analysis Colorado Parks & Wildlife
February 2015 14
Dam Name Description of Work
Rehabilitation, Replacement,
Refurbishment, Maintenance
Cost
Total Rehab i l i tat ion, Refurb ishment and Repair I tems (Parks Dams) $ 75,000
Total Rehab i l i tat ion, Refurb ishment and Repair I tems (Wild l i fe Dams) $2,258,000
TOTAL REHABILITATION, REFURBISHMENT AND REPAIR ITEMS $ 2,333,000
Total Annual Maintenance (Parks Dams) $ 4,000
Total Annual Maintenance (Wi ld l i fe Dams) $ 46,500
TOTAL ANNUAL MAINTENANCE $ 50,500
GRAND TOTAL FOR LOW HAZARD AND NON-JURISDICTIONAL DAMS $ 2,383,000