Dairy Effluent Pond Construction[1]

download Dairy Effluent Pond Construction[1]

of 5

Transcript of Dairy Effluent Pond Construction[1]

  • 7/27/2019 Dairy Effluent Pond Construction[1]

    1/5

    Dairy effluent: Pond constructionBarrie Bradshaw, Ellinbank

    October, 2002

    AG0425ISSN 1329-8062

    State of Victoria, Department of Primary Industries Page 1

    Good site investigation and construction are essential for

    the long-term success of dairy shed effluent pond

    systems. Refer to the Agriculture NoteAG0424; Dairy

    effluent: Pond site selection before constructing ponds.

    Local government requirements

    Check whether your local government requires a permit for

    the construction of a pond. Whether a permit is required

    will vary between areas and can depend on whether the

    natural drainage or active flow path in the area is affected.

    Pond sizing

    Ponds should be designed to hold the maximum quantity

    of effluent produced over the wetter months to avoid

    waterlogging and pugging of pastures. Effluent may need

    to be stored between 46 months depending on the farms

    location. Refer to the Agriculture Note,AG0441:Dairy

    effluent: Storage pond sizing for more information.

    It is important to ensure that the contractor follows the

    plans, which have been designed, and that the minimum

    size specifications are adhered to.

    Types of ponds

    The type of pond or ponds that you select will depend on

    the topography of the farm and the type of effluent system

    implemented to return nutrients back to pasture.

    Excavation costs will depend on the storage/excavation

    ratio of the pond. The storage ratio is the number of cubic

    metres of water stored in the pond for each cubic metre of

    earth moved to build the pond.

    Hillside ponds generally have a 3-sided or curved bank.

    These ponds have relatively poor storage ratios but often

    have the advantage of allowing gravity flow to and from

    the system. A hillside slope of 8% gives the best storageratio.

    Excavated ponds or below ground ponds will supply

    excavated material which can be stockpiled for other use.

    Whilst effluent can usually be gravitated to an excavated

    pond, usually only the overflow from the pond can be

    gravity fed out. Excavated ponds are not suitable in areas

    where the watertable is close to the land surface.

    Turkey nest ponds or above ground storages can be

    built by using the soil which is obtained from digging the

    hole to build the embankments. Effluent generally has to

    be pumped into a turkey nest dam, but it can be released by

    gravity through an outlet pipe. Turkey nest ponds are ideal

    if the watertable is close to the land surface and shandying

    effluent into irrigation channels.

    Pond dimensions

    Ponds do not have to be regular shapes and can be blended

    into the topography or surroundings.

    Rectangular ponds are easier to de-sludge, when necessary,than square ponds since they give better access to the

    centre.

    Rectangular ponds compared to square ponds are also

    cheaper to construct on hill country with the long side on

    the contour.

    Long narrow ponds should be avoided, as they tend to

    crust and silt at the end where effluent is entering. This

    affects anaerobic functioning.

    Earthmoving machines

    There are many types of machines that can be used to

    construct ponds. However equipment which can spreadand compact excavated material is best. The more

    compacted the embankments and pond surface are, the less

    likely it is that the pond will leak or crack.

    Bucket type earthmoving equipment cannot spread or

    compact excavated material or embankments as well as

    bulldozers, whilst scrapers are even better compacters but

    are only suited to large jobs. Sheepsfoot and tamping foot

    rollers in association with water carts provide even better

    compaction.

    Site preparation

    Payment of contractors is generally determined by theamount of earthworks required to construct the system.

    However, where fences, vegetation and other obstacles

    require removal the contractor may charge for further time.

    The farmer can reduce costs by carrying out as much of

    this work as possible prior to the contractor commencing.

    All topsoil should be cleared and stockpiled, and replaced

    on the completed walls to enable regrowth preventing bank

    erosion and providing wall stability. Dams in which

    topsoil is incorporated in, or left under the clay material

    that forms the bank, are more likely to leak.

  • 7/27/2019 Dairy Effluent Pond Construction[1]

    2/5

    State of Victoria, Department of Primary Industries Page 2

    Dairy effluent: Pond construction AG0425

    Sealing

    Ponds should be impermeable to water and a soil

    investigation should be undertaken. Refer to Agriculture

    Note;AG0424: Dairy effluent:Pond site selection. The

    organic matter from the cow manure entering the system

    will eventually form a biological seal.

    Ponds constructed using cracking clay soils, or soils

    containing less than 20 per cent clay require sealing. Clay

    from another area can be placed 150 mm thick and

    compacted with 150 mm of existing soil on the pond floor

    and walls. Alternatively there are additives, which can be

    mixed with soil such as bentonite and Kaolin clay, to

    reduce soil permeability.

    To prevent the clay seal from drying out and cracking, the

    pond should be filled with water as soon as possible after

    completion and at least 0.5 metre of effluent should be

    maintained in the pond.

    Polyethylene liners are also available to seal ponds in light

    soils, however good management is essential to preventliner damage. Placing tyres in the base of the pond on top

    of the liner will assist contractors in locating the liner and

    possibly avoid puncturing.

    Side slopes and embankments

    The crest of embankments should be a minimum width of

    3.5 metres. This will allow for vehicular movement during

    construction and desludging. Both internal and external

    batters should have at least a

    2:1 slope (2 metre in the horizontal direction for every

    1 metres in the vertical direction) to prevent batters

    slumping, and to allow free machinery movement. Bankbatters of 3:1 are preferable especially for the external

    batter and where ponds are to be located in sites with

    unstable soils, or when optimal compaction is not possible.

    When desludging, ponds with steeper banks may clean

    more easily, but an adequate slope is needed to prevent the

    banks from slumping or breaching.

    Pipe sizing and type

    UPVC and HDPE (polyethylene) pipes are suitable for

    gravity or pressure pipelines. Rubber-ring-jointed PVC

    pipe should be installed in preference to solvent-welded

    pipe to avoid corrosion from the effluent.If concrete pipes are used, sulphate-resistant cement is

    recommended with all exposed starter bars being

    galvanised to avoid decay. Steel cast iron and ductile iron

    pipes should be given a protective coating to avoid

    corrosion from the effluent.

    For gravity pipelines, sewer-class pipes should be used

    rather than stormwater-class pipes. The main

    consideration for gravity conveyance is the presence of

    solids in the liquid. Table 1 gives recommended grade

    requirements of pipelines.

    Table 1: Minimum grades for gravity pipe drainsconveying effluent.

    Inside

    diameter(mm)

    Minimum grade

    Without solids

    Minimum grade

    With Solids

    75 0.2% (1:500) 3.3 % (1:30)

    100 0.1% (1:1000) 2.5 % (1:40)

    125 0.07% (1:1450) 2.0% (1:50)

    150 0.05% (1:2000) 1.7% (1:60)

    At least 150mm pipe is recommended for transferring

    effluent between ponds and for the outlet from ponds to

    the land application area or irrigation channel. Larger

    diameter pipes will have the advantage of higher discharge

    rates and less likelihood of blocking.

    At least 50mm piping is needed for pumping effluent. For

    pipeline lengths exceeding 100 metres or where higherheads (the distance between the effluent level and the

    pump outlet) are involved, at least 75mm pipe is

    preferable. When choosing pressure classes for pipes

    some extra strength needs to be allowed for water hammer.

    HDPE pipe has greater flexibility to withstand water

    hammer than UPVC pipe.

    Table 2: Common p ipe classes recommended forpumping effluent.

    Imperial K119 Metric AS1159

    Class A - 150 ft head

    65psi

    Class 4.5 - 45 m head

    65 psi

    Class B - 200 ft head

    87 psi

    Class 6 - 60 m head

    88 psi

    Class C - 300 ft head

    135 psi

    Class 9 - 90 m head

    131 psi

    Class D - 400 ft head

    175 psi

    Class 12 - 120 m head

    176 psi

    Pipe positioning

    The effective storage capacity of a pond is the difference

    in the effluent level at the start of the winter or storage

    period and the effluent level when the pond is full.

    It is therefore important to be able to empty the pond so

    that there is sufficient storage capacity for the wetter

    months of the year.

  • 7/27/2019 Dairy Effluent Pond Construction[1]

    3/5

    State of Victoria, Department of Primary Industries Page 3

    Dairy effluent: Pond construction AG0425

    Storage

    capacity

    Figure 1. Storage capacity of a pond

    However it is recommended that the outlet pipe or pump suction line are not within 0.5m of the bottom of pond. This will

    prevent sludge and solid material from blocking the pipes and pumps.

    Overflow pipes, such as pipes used between dams should be as far as possible from inlet pipes so that the effluent is held in the

    pond long enough to be broken down and for solid settlement to occur. Pipes should be fitted with baffles or T-junctions tostop any surface scum passing through them.

    Figure 2. Simple baffle to prevent pipe blockages

    Concrete or UPVC cut-off collars should be installed with pipes passing through embankments to minimise seepage around the

    pipe. The longer the pipe the greater number of collars are needed.

  • 7/27/2019 Dairy Effluent Pond Construction[1]

    4/5

    State of Victoria, Department of Primary Industries Page 4

    Dairy effluent: Pond construction AG0425

    Figure 3. Configuration of pipes and earthen banks

    If the pond is to be emptied using gravity, flows can be controlled by a gate valve, slide or a similar structure, which can be

    placed on the downstream or upstream end of the pipe.

    Figure 4. Position of valves/controls on outlet pipes.

    A downstream control is convenient to operate but the pipe is exposed to constant water pressure, which may cause leakage.

    The main disadvantage of the upstream control is the inconvenience of operating and maintaining it. If it is laid in a sloping

    position it requires a very long spindle supported on concrete cradles, and if set in a vertical position it needs a catwalk with a

    safety fence to reach it.

    Pipe covering

    Pipelines should be buried at least 500 mm below the earth surface and at least 600 mm below where there is vehicle

    movement. The larger the pipe, the greater the cover required.

  • 7/27/2019 Dairy Effluent Pond Construction[1]

    5/5

    State of Victoria, Department of Primary Industries Page 5

    Dairy effluent: Pond construction AG0425

    Rainfall run-off diversion

    There should be a diversion or cut-away ditch around

    excavated or hillside ponds so that rainfall run-off is

    diverted away.

    Starting and fill ing new ponds

    The organisms in the dairy effluent are generally sufficient

    to start the pond functioning, and therefore the ponds will

    usually not require 'seeding'.

    However if seeding is required then effluent from an

    active pond (approx. 200 litres) is recommended

    Ponds should be filled with clean water before effluent is

    discharged into them. This helps seal the bed and banks,

    decreases odour and reduces the concentration of effluent

    components.

    Grassing and treesOnce the earthen banks are formed, the stockpiled topsoil

    can be placed on the crest and batters. Grass cover on the

    embankments will help stabilise the banks, prevent

    cracking walls and potential leaks, and help to protect the

    banks from wave damage and rainfall erosion.

    Trees should not be allowed to establish on embankments

    since they can disturb the stability of the batters.

    Fencing and safety

    Ponds must be fenced to keep out children and stock.

    Stock can cause extensive damage to batters and

    structures.

    A sign should be erected on ponds warning of deep water

    which may be hidden by a surface crust or scum.

    References

    Managing Dairy Shed Wastes Technical Bulletin; Vol. 2,

    Dairy Research and Development Corporation 1994.

    Published by Department of Agriculture, Victoria.

    This publication may be of assistance to you but the State of Victoria and its officers do not guarantee that the publication is without flaw of any

    kind or is wholly appropriate for your particular purposes and therefore disclaims all liability for any error, loss or other consequence which may

    arise from you relying on any information in this publication.