Daily Cost Control Using P6 and PCM

Prepared by:

Nicole Jardin, P.Eng. - CEO

Emerald Associates Inc.

Preventing Margin Erosion in an Engineered Manufacturing Organization

Session ID#: 200070

@nicolejardineai

Page 2: Daily Cost Control Using P6 and PCM

Agenda Daily Margin Control through Automation

■ Background

1. Project Creation

▪ Sell Price vs Cost Estimate

2. Managing Changes

▪ BCO/VCE/CO

3. Daily Actuals Integration – Time & Expenses

4. PM Forecasting

5. Month End

▪ Closing

▪ Snapshotting

▪ Reporting

Page 3: Daily Cost Control Using P6 and PCM

Background

This is a subtitle or bulleted list

Page 4: Daily Cost Control Using P6 and PCM

Presenter Emerald Associates Inc.

Nicole Jardin, P.Eng.

Founder & CEO

Delivering Primavera for 20 years

■ Platinum Partner

■ Canada, US, Australia

■ P6, PCM, Unifier, Risk Analysis, UPK,

OPPM, Instantis

■ ODA, managed services, hosting

■ Contact Info

[email protected]

Page 5: Daily Cost Control Using P6 and PCM

Client Background

■ Custom Module Manufacturer

▪ Worldwide Projects

▪ 100-125 projects on the go at once

▪ 3-24 months durations

▪ 8-10 PMs in the team

■ Projects

▪ Types - Pre-fab Buildings/Skids/Camps

▪ Phases - Engineer/Procure/Manufacture/Ship/Install

Page 6: Daily Cost Control Using P6 and PCM

Automations the only way to go!

This is a subtitle or bulleted list

Page 7: Daily Cost Control Using P6 and PCM

Automations Margin Erosion Controls

Page 8: Daily Cost Control Using P6 and PCM

1. Project Award Sell Price vs Cost Estimate

Page 9: Daily Cost Control Using P6 and PCM

Project Creation PCM->P6 Project Loader

■ Create project in PCM only manual step!

■ PCM-> P6 – auto create

▪ Grab matching template

▪ Put into EPS

▪ Put into OBS

▪ Load in project codes

▪ Load in start and must finish (if applicable)

▪ Load in budgeted costs

Page 10: Daily Cost Control Using P6 and PCM

Sell Price - Revenue Prorate Payment Milestones P6->PCM

■ Client Contract - Payment Milestones

▪ P6-Rollups & Calculators – Original Sell Price

■ Budget Costs P6 -> Budget Contract PCM

▪ Backpump PCM ->P6 for integrity

Page 11: Daily Cost Control Using P6 and PCM

Cost Estimate P6-Cost Loader Sheet

■ Populate P6 with Excel estimates

▪ Expenses – buyouts (sub-contracts, materials), inventory

▪ Resources – hours & costs

▪ Markups, overheads reporting

■ P6-Rollups & Calculators – Bid Margins, Markups

Page 12: Daily Cost Control Using P6 and PCM

Procurement Spending Plan P6->PCM Commitment Loader

■ Load into PCM Modules

▪ Cost Estimate – Original Procurement (Bid Price)

▪ Bid Package Items – for buyouts

▪ Internal Work – Contracts

▪ External Work – PO

■ Backpump PCM -> P6 activities for integrity

Page 13: Daily Cost Control Using P6 and PCM

Procurement Spending Plan P6->PCM Commitment Loader

■ Load into PCM Modules

▪ Cost Estimate – Original Procurement (Bid Price)

Page 14: Daily Cost Control Using P6 and PCM

Procurement Spending Plan P6->PCM Commitment Loader

■ Load into PCM Modules

▪ Internal Work – Contracts

▪ External Work – PO

Page 15: Daily Cost Control Using P6 and PCM

2. Managing Changes Estimates & Change Orders

Page 16: Daily Cost Control Using P6 and PCM

PCM Vendor Change Estimates-Order VCE Loader

■ VCE-Load – from same Excel estimate sheet

▪ Load multiple Proposals

▪ Create a new PO if new scope!

Page 17: Daily Cost Control Using P6 and PCM

PCM Change Orders Loaded into P6 CO Loader

■ CO-Loader

▪ Approved change order

▪ Verify match -> to P6 activities

▪ Load CO to date

▪ Revise current budget

■ P6-Rollup & Calculators

▪ Margin for changes, overall, variances

Page 18: Daily Cost Control Using P6 and PCM

3. Daily Actuals Integrating Accounting ->P6

Page 19: Daily Cost Control Using P6 and PCM

Nightly Integration Accounting ->P6 -> PCM

1. Accounting -> P6

▪ Load actuals to financial & holding buckets

▪ Error handling

2. Autorun EAI Auto-scheduler

3. Summarize

4. PM Integration & Status Dashboard

▪ Run in verifiers

▪ Run in electors – forecasts vs accounting

▪ Run rollups – margins

5. Autorun Snapshot Current – EP-datawarehouse

6. Autorun P6->PCM payment certificate loader

Page 20: Daily Cost Control Using P6 and PCM

Financial Period Actuals Loads Timesheets & Invoices ->P6

■ Timesheets

▪ Actual hours & costs

▪ Match role or add new roles

■ Invoices

▪ Expenses – services, materials

▪ Bundles – non-planned

▪ Inventory – long lead

■ P6 Rollup & Calculator

Current margins, indicators

Page 21: Daily Cost Control Using P6 and PCM

PM Integration & Status Dashboard see problems and drill in

■ Error handling layouts

■ Month Close Special Holding Buckets

Page 22: Daily Cost Control Using P6 and PCM

PCM Payment Certificates Auto Create & Actual Loader

■ Auto create new payment requisitions

▪ Nightly load actuals this period

▪ Runs after integration

■ Always ready to invoice client

■ Always ready to capture accruals

Page 23: Daily Cost Control Using P6 and PCM

4. PM Forecasting diaries to tasks

Page 24: Daily Cost Control Using P6 and PCM

Forecasting Controls PCM diaries->P6 Loader

■ PM Forecast

▪ Efficiencies

▪ Overruns

▪ Start

▪ Finish

Page 25: Daily Cost Control Using P6 and PCM

Forecasting Controls PCM diaries->P6 Loader

■ Elaborate Electors accounting <> forecast

▪ Not started

▪ In progress

▪ Complete

Page 26: Daily Cost Control Using P6 and PCM

5. Month End closing, snapshotting & reporting

Page 27: Daily Cost Control Using P6 and PCM

Closing P6 & PCM

■ PCM – Accruals

▪ Review Accruals – PCM->Accounting

■ P6 - Progress & Notes

▪ Finalize Progress

▪ Clear any coding errors

— Costs coded by mistake

— New POs not pre-authorized

— Review inventory transfers

▪ Finalize Straggler transactions from accounting

▪ Make progress notes

— Efficiencies/overruns

— Delays

■ Re-baseline if needed

Page 28: Daily Cost Control Using P6 and PCM

Snapshotting P6->EP-datawarehouse

■ Snapshot - Project & Baseline

▪ Financial period spreads

▪ Special Holding buckets

— True Month End Reporting

■ EP-datawarehouse

▪ All snapshots available for reporting against

— Month over month, year over year

— Current period to last period

Page 29: Daily Cost Control Using P6 and PCM

BI Reporting Project Manager & Management

■ Project Progress Report

▪ P6 & PCM info combined

■ Management

▪ Portfolio progress

▪ Revenue recognition

■ Adhoc

Page 30: Daily Cost Control Using P6 and PCM

Project Progress status & margins

Page 31: Daily Cost Control Using P6 and PCM

Portfolio Progress

■ Portfolio Rollups by WBS elements

Page 32: Daily Cost Control Using P6 and PCM

P6 & PCM Info Combined

Page 33: Daily Cost Control Using P6 and PCM

Questions?

Page 34: Daily Cost Control Using P6 and PCM

Please complete the session evaluation We appreciate your feedback and insight

You may complete the session evaluation either

on paper or online via the mobile app

Page 35: Daily Cost Control Using P6 and PCM

■ Our purpose is to inform and educate our members on current and future

functionality of Oracle Primavera products, while offering a forum for peers to

share their experience and knowledge in the use of Primavera.

■ Educational opportunities across the Primavera product suite

■ Online Learning Series August 17th – September 4th

■ Call for presentation opening April 27th

■ Monthly Community Calls

■ 3rd Thursday of the month at 1:00 pm ET

■ Networking with other users within the Primavera community

■ Partnering with Oracle Primavera to meet the needs of our diverse

membership.

■ Membership is open to anyone with an interest in the Oracle Primavera products,

with no dues for membership. All members can vote on matters brought before

the OPSIG. Membership requests may be reviewed by the OPSIG board.

OPSIG is the home for

Primavera Users