Dah time mgmt matching exercise answers

2
PMBOK 4th Edition PMI-CCVC Time managment CAPM Prep 6/21/2011 1 Define Activities v a Progressive elaboration where near term work is planned in detail and future work is planned at a higher level of the WBS. 2 Sequence Activities e b The process of estimating the type and quantities of material, people, equipment, or supplies required to perform each activity. 3 Estimate Activity Resources b c The process of monitoring the status of the project to update project progress and managing changes to the schedule baseline. 4 Estimate Activity Durations s d Specify when and how long identified project resources are available. This includes resource skill level and geographical locations of orgin. 5 Develop Schedule t e The process of identifying and documenting relationships among the project activities. 6 Control Schedule c f Preferred logic, preferential logic, or soft logic. When fast tracking techniques are used, these should be reviewed and considered for modification or removal. 7 Finalized and Approved Schedule l g A project schedule developed from the schedule network analysis. It is accepted and approved by the project management team as the schedule with start and finish dates. It is a component of the project management plan. 8 Decomposition m h Uses Most likely, Optimistic and Pessimistic values for Three-Point Estimates. 9 Rolling Wave Planning a i Resource need is estimated and the quantities are totaled for each activitiy's resources. 10 Activity Attributes k j Uses parameters such as duration, budget, size, weight and complexity from a previous project as the basis for estimating the same parameter for a future project. 11 Precedence Diagramming Method (PDM) n k Used for schedule development and for selecting, ordering, and sorting the planned activities in reports. 12 Discretionary dependencies f l The baseline that is used in the Control Schedule process. 13 Resource Calendars d m Subdividing the project work packages into smaller, more manageable compoents called activities. 14 Bottom-Up Estimating i n Uses boxes, referred to as nodes, to represent activities, and connects them with arrows that show the logical relationships that exist between them. This technique is also called Activity-On-Node (AON). 15 Resource Breakdown Structure o o A structure of identified resources by resource category and resource type. 16 Analogous Estimating j p A schedule network analysis technique applied to a schedule that has been analysised by critical path method. Can be used when shared resources are only available at certain times or limited quantities. 17 Program Evaluation and Review Technique (PERT) h q Schedule performance measurements (SV, SPI) are used to assess the changes from the original schedule baseline. Page 1 of 2

description

CAPM Matching Test and Answers

Transcript of Dah time mgmt matching exercise answers

Page 1: Dah time mgmt matching exercise answers

PMBOK 4th Edition PMI-CCVC Time managment CAPM Prep 6/21/2011

1 Define Activitiesv

aProgressive elaboration where near term work is planned in detail and

future work is planned at a higher level of the WBS.

2 Sequence Activitiese

bThe process of estimating the type and quantities of material, people,

equipment, or supplies required to perform each activity.

3Estimate Activity

Resourcesb

cThe process of monitoring the status of the project to update project

progress and managing changes to the schedule baseline.

4Estimate Activity

Durationss

dSpecify when and how long identified project resources are available.

This includes resource skill level and geographical locations of orgin.

5 Develop Schedulet

eThe process of identifying and documenting relationships among the

project activities.

6 Control Schedulec

fPreferred logic, preferential logic, or soft logic. When fast tracking

techniques are used, these should be reviewed and considered for

modification or removal.

7Finalized and Approved

Schedulel

g

A project schedule developed from the schedule network analysis. It is

accepted and approved by the project management team as the

schedule with start and finish dates. It is a component of the project

management plan.

8 Decompositionm

hUses Most likely, Optimistic and Pessimistic values for Three-Point

Estimates.

9 Rolling Wave Planninga

iResource need is estimated and the quantities are totaled for each

activitiy's resources.

10 Activity Attributesk

jUses parameters such as duration, budget, size, weight and complexity

from a previous project as the basis for estimating the same parameter

for a future project.

11

Precedence

Diagramming Method

(PDM) n

kUsed for schedule development and for selecting, ordering, and sorting

the planned activities in reports.

12Discretionary

dependencies fl The baseline that is used in the Control Schedule process.

13 Resource Calendarsd

mSubdividing the project work packages into smaller, more manageable

compoents called activities.

14 Bottom-Up Estimating

i

nUses boxes, referred to as nodes, to represent activities, and connects

them with arrows that show the logical relationships that exist

between them. This technique is also called Activity-On-Node (AON).

15Resource Breakdown

Structure oo

A structure of identified resources by resource category and resource

type.

16 Analogous Estimating

j

pA schedule network analysis technique applied to a schedule that has

been analysised by critical path method. Can be used when shared

resources are only available at certain times or limited quantities.

17

Program Evaluation and

Review Technique

(PERT) h

qSchedule performance measurements (SV, SPI) are used to assess the

changes from the original schedule baseline.

Page 1 of 2

Page 2: Dah time mgmt matching exercise answers

PMBOK 4th Edition PMI-CCVC Time managment CAPM Prep 6/21/2011

18Schedule Network

Analysisr

rUses analytical techniques such as critical path method, critical chain

method and resource leveling for generating a project schedule.

19 Resource Levelingp

sThe process of approximating the number of work periods needed to

complete individual activities with estimated resources.

20 Schedule Baselineg

tThe process of analyzing activity sequences, durations, resource

requirements, and schedule constraints to create the project schedule.

21 Variance Analysisq

vThe process of identifying the specific actions to be performed to

produce the project deliverables.

Page 2 of 2