D0109 CDM M24 - URBANTRACK.EU - URBAN TRACK · PARTNERS Société des Transports Intercommunaux de...
Transcript of D0109 CDM M24 - URBANTRACK.EU - URBAN TRACK · PARTNERS Société des Transports Intercommunaux de...
TIP5-CT-2006-031312 Page 1 of 22URBAN TRACK Issued: 26/8/2008
Quality checked and approved by project co-ordinator André Van Leuven
D0109_CDM_M24.doc
DELIVERABLE D1.9
Related Milestone M1.7
CONTRACT N° TIP5-CT-2006-031312
PROJECT N° FP6-31312
ACRONYM URBAN TRACK
TITLE Urban Rail Transport
PROJECT START DATE September 1, 2006
DURATION 48 months
Subproject SP 1 Design of modular low cost new Integrated track system
Work Package WP 1.3.1 Installation of modular track systems
Rapid installation methods for modular track systems
Written by Anneleen Bergiers CDM
Date of issue of this report 26/08/2008
PROJECT CO-ORDINATOR Dynamics, Structures & Systems International D2S BE
PARTNERS Société des Transports Intercommunaux de Bruxelles STIB BE
Alstom Transport Systems ALSTOM FR
Bremen Strassenbahn AG BSAG DE
Composite Damping Materials CDM BE
Die Ingenieurswerkstatt DI DE
Institut für Agrar- und Stadtökologische Projekte ander Humboldt
ASP DE
Tecnologia e Investigacion Ferriaria INECO-TIFSA ES
Institut National de Recherche sur les Transports &leur Sécurité
INRETS FR
Institut National des Sciences Appliquées de Lyon INSA-CNRS FR
Ferrocarriles Andaluces FA-DGT ES
Alfa Products & Technologies APT BE
Autre Porte Technique Global GLOBAL PH
Politecnico di Milano POLIMI IT
Régie Autonome des Transports Parisiens RATP FR
Studiengesellschaft für Unterirdische Verkehrsanlagen STUVA DE
Stellenbosch University SU ZA
Transport for London LONDONTRAMS
UK
Ferrocarril Metropolita de Barcelona TMB ES
Transport Technology Consult Karlsruhe TTK DE
Université Catholique de Louvain UCL BE
Universiteit Hasselt UHASSELT BE
Project funded by theEuropean Community undertheSIXTH FRAMEWORKPROGRAMMEPRIORITY 6Sustainable development,global change & ecosystems International Association of Public Transport UITP BE
Union of European Railway Industries UNIFE BE
Verkehrsbetriebe Karlsruhe VBK DE
Fritsch Chiari & Partner FCP AT
Metro de Madrid MDM ES
TIP5-CT-2006-031312 Page 2 of 22URBAN TRACK Issued: 26/8/2008
Quality checked and approved by project co-ordinator André Van Leuven
D0109_CDM_M24.doc
T A B L E O F C O N T E N T S
0. Executive summary...................................................................................................................... 3
0.1. Objective of the deliverable.................................................................................................. 3
0.2. Strategy used and/or a description of the methods (techniques) used with the
justification thereof ............................................................................................................... 3
0.3. Background info available and the innovative elements which were developed ........... 3
0.4. Problems encountered.......................................................................................................... 3
0.5. Partners involved and their contribution ........................................................................... 4
0.6. Conclusions ........................................................................................................................... 4
0.7. Relation with the other deliverables (input/output/timing)............................................ 4
1. Introduction.................................................................................................................................. 5
1.1. General context ..................................................................................................................... 5
1.2. The Re-Modulix concept ...................................................................................................... 6
1.3. Design of Re-Modulix .......................................................................................................... 7
1.4. Re-Modulix installation sequences...................................................................................... 7
1.5. Removal and/or replacement of the modules ................................................................. 11
2. Testing......................................................................................................................................... 13
2.1. Integration into the STUVA test circuit............................................................................. 13
2.2. Small Removability Test..................................................................................................... 16
2.3. Big Removability Test......................................................................................................... 19
2.4. Surface finishing ................................................................................................................. 20
3. Life cycle cost.............................................................................................................................. 21
TIP5-CT-2006-031312 Page 3 of 22URBAN TRACK Issued: 26/8/2008
Quality checked and approved by project co-ordinator André Van Leuven
D0109_CDM_M24.doc
0. EXECUTIVE SUMMARY
0.1. OBJECTIVE OF THE DELIVERABLE
This document describes the development of a prefabricated, modular and reusable track
system to be installed in Karlsruhe.
The system is designed to follow demands to reduce the nuisance to the users and services of
the urban environment and to lower Life Cycle Cost. It also has to resist actual rolling stock axle
loads and traffic loads. This prefabricated slab track technique allows the track to be installed in
critical areas within a short intervention period and thus limit the nuisance for users,
neighbours etc. Furthermore stiff road surface finishing directly integrated in the slab offers the
optimal solution with respect to Life Cycle Cost control (reduced maintenance). The new
feature of this development is the possibility to remove the prefabricated track after some years
of operation and to reuse it again somewhere else.
0.2. STRATEGY USED AND/OR A DESCRIPTION OF THE METHODS (TECHNIQUES) USED
WITH THE JUSTIFICATION THEREOF
The system called Re-Modulix will be based on the Modulix-system of CDM, which consists of
prefabricated reinforced concrete modules with integrated road finishing. Modification of the
foundation layers and composition are adopted to make it removable. The installation
procedure is also adapted.
0.3. BACKGROUND INFO AVAILABLE AND THE INNOVATIVE ELEMENTS WHICH WERE
DEVELOPED
Background info available:
Specifications provided by VBK.
Specifications of the Modulix system of CDM.
Innovative element: removability and reuse.
0.4. PROBLEMS ENCOUNTERED
The test site is located within the Kaiserstrasse of Karlsruhe. Most of the street is characterised
by a typical pedestrian precinct with a double track in the middle an numerous installations like
street lamps, benches, showcases and trees at both sides of the street. Cause of the numerous
shops and the necessity to keep them open during the installation and the already mentioned
installations, space for the preparation of site facilities and the work site itself is very short in
spite of an average cross-section of about 23 m. Therefore, a special installation sequence and
module design was conceived by CDM. However due to a decision of the executive board of
VBK, based on an internal risk analysis, the location of the test track has changed to the
Kaiserstrasse in front of the University which postpones the installation into summer 2009
TIP5-CT-2006-031312 Page 4 of 22URBAN TRACK Issued: 26/8/2008
Quality checked and approved by project co-ordinator André Van Leuven
D0109_CDM_M24.doc
instead of summer 2008. This new track section is outside the pedestrian precinct with a typical
urban cross section. Segregated tracks are lying in the middle flanked by a car lane, parallel
parking and pavements. This street section of Kaiserstraße allows to use larger modules and
limits former difficulties. Because of this decision, further changes are possible to the design
described in this document. The prolongation of a year caused also a postponement of tests to
perform. The design will without doubt still be refined during the following year.
0.5. PARTNERS INVOLVED AND THEIR CONTRIBUTION
CDM, VBK, TTK, STUVA, UCL
0.6. CONCLUSIONS
A prefabricated modular and removable embedded track system is developed for the needs of
Karlsruhe city. Installation and removal procedures are specified.
0.7. RELATION WITH THE OTHER DELIVERABLES (INPUT/OUTPUT/TIMING)
This deliverable is linked to SP3 dealing with the Re-Modulix installation and validation in
Karlsruhe and also has relations with SP4 and SP5.
The installation in Karlsruhe has to be done according to a narrow time schedule and is
postponed to summer 2009.
TIP5-CT-2006-031312 Page 5 of 22URBAN TRACK Issued: 26/8/2008
Quality checked and approved by project co-ordinator André Van Leuven
D0109_CDM_M24.doc
1. INTRODUCTION
1.1. GENERAL CONTEXT
Karlsruhe has a 70km tram and light-rail network carrying
108 million passengers per year. The section located in
Kaiserstrasse is the most critical section:
Located within the pedestrian area of Karlsruhe
Five tramlines and three light rail lines are running on
this track in a ten minute frequency from 06:00 o’clock
in the morning until 08:00 o’clock in the evening.
During the off peak time there is still a 20 minutes
frequency.
As there are no alternative tracks, the maintenance is a
very sensitive operation (problems in the past).
Furthermore, City of Karlsruhe is planning a light rail
tunnel under this pedestrian district (best-case scenario is
assuming an inauguration not before 2015).
On one hand, there is an urgent need to renew the tracks
in the pedestrian area; on the other hand, the same tracks
will disappear when the light rail tunnel will start
operating in 2015.
VBK would like to solve this problem by using removable prefabricated tracks. In general, the Re-
Modulix system aims to give an answer to the following major practical concerns:
fast temporary track installation with possibility to reuse system components in other
locations within the network.
easy renovation of entire multimodal track elements (track and road surface).
TIP5-CT-2006-031312 Page 6 of 22URBAN TRACK Issued: 26/8/2008
Quality checked and approved by project co-ordinator André Van Leuven
D0109_CDM_M24.doc
1.2. THE RE-MODULIX CONCEPT
Based on a modular prefabricated track-system and a catalogue of requirements from VBK the
design for a Re-Modulix system was developed.
The Re-Modulix system will be an embedded track system (ERS) delivered as a prefabricated
concrete slab with final road covering (pavement) included. It allows the tracks to be installed
in strategic critical points of a network in very short time period (e.g. crossings, access to
strategic sites, by hospitals, …). The slab includes all possible elements such as drainage
elements, electrical boxes, etc.
Figure 1
Examples of classical prefabricated track module installation with final road covering included
TIP5-CT-2006-031312 Page 7 of 22URBAN TRACK Issued: 26/8/2008
Quality checked and approved by project co-ordinator André Van Leuven
D0109_CDM_M24.doc
1.3. DESIGN OF RE-MODULIX
The Re-Modulix concept is based on a prefabricated modular track system (Modulix) with
adapted foundation layers. The removability is ensured by adding two PE-films:
one between the prefabricated module itself and the lean concrete to prevent any cohesion
between the slab and the foundation;
one under the lean concrete layer to allow the removal of the supporting beams and fixation
concrete layer when the module has been removed.
Figure 2
Cross-section of the Re-Modulix concept
1.4. RE-MODULIX INSTALLATION SEQUENCES
The system consists of modules with a length of 16,5m and intermediary pieces to place
between 2 modules. In the Modulix system those modules have the same width and both tracks
are installed at the same time. However in Karlsruhe a change was needed.
KaiserStrasse has a width of 5,870m. The sidewalk can not be used for the installation because
of many obstructions like benches, lampposts, garbage-cans, … Transport trucks must be able
to drive to the unloading-point and a truck needs 2,5m width to drive on.
Therefore the installation will be done in 2 phases. In the first phase the track of side 1 is
demolished (Figure 3). The old track at the other side is used to drive on. After the installation of
the modules of side 1, side 2 is demolished during the second phase. The new track at side 1 is
used to drive on. The modules of the first phase will be wider then the modules of the second
phase (Figure 4). This allows trucks to drive on the wider modules during installation.
TIP5-CT-2006-031312 Page 8 of 22URBAN TRACK Issued: 26/8/2008
Quality checked and approved by project co-ordinator André Van Leuven
D0109_CDM_M24.doc
Figure 3
Cross-section of the KaiserStrasse phase 1: one side of the old track is used to drive on; the other side is
demolished and installed
Figure 4
Cross-section of the KaiserStrasse with installed modules of 2 widths
The installation of phase 1 (Figure 5) begins by demolishing the old track and preparing the
platform surface, i.e. a clean lean concrete layer with a PE-film covering it. The supporting
beams (provided with the modules) are then placed on the lean concrete layer to support the
different modules. The position of those beams is determined by the surveyor (based on
drawings).
The pieces of the welding zone are placed between the beams. After this the modules are
installed on the beams. The rails are welded and the welding zones are completed.
Subsequently the pieces of the welding zone are lifted and positioned using steel supporting
beams. The concrete of the first phase is poured. The steel supporting beams are removed once
the concrete curing is completed.
In phase 2 (Figure 6) all these steps are repeated at the other side of the street. Finally the concrete
of phase 2 is poured and the intermediary pieces between the modules are placed in the fresh
concrete using steel support beams.
TIP5-CT-2006-031312 Page 9 of 22URBAN TRACK Issued: 26/8/2008
Quality checked and approved by project co-ordinator André Van Leuven
D0109_CDM_M24.doc
Figure 5
Re-Modulix concept – Installation sequence
TIP5-CT-2006-031312 Page 10 of 22URBAN TRACK Issued: 26/8/2008
Quality checked and approved by project co-ordinator André Van Leuven
D0109_CDM_M24.doc
Figure 6:
Re-Modulix concept – Installation sequence
TIP5-CT-2006-031312 Page 11 of 22URBAN TRACK Issued: 26/8/2008
Quality checked and approved by project co-ordinator André Van Leuven
D0109_CDM_M24.doc
1.5. REMOVAL AND/OR REPLACEMENT OF THE MODULES
To remove the modules, the jackets (elastic encapsulation) and rail are cut in the intermediary
zone i.e. original welding area (Figure 7, phase 2). The intermediary modules between the two
tracks as well as the main modules are then removed using the available anchors in the slabs.
These anchors have to withstand the weight of the modules and the force needed to pull the
modules out. To estimate this force tests are performed (see 3.2.)
Figure 7
Re-Modulix concept: removal and replacement of modules
This phase is followed by the removal of the intermediary slabs of the welding zone (Figure 8,
phase 4) and the cleaning of the fixation concrete surface poured around the supporting beams
(Figure 8, phase 5).
Again, this removal should be done in 2 phases because of limited space (first one side, then
other side).
TIP5-CT-2006-031312 Page 12 of 22URBAN TRACK Issued: 26/8/2008
Quality checked and approved by project co-ordinator André Van Leuven
D0109_CDM_M24.doc
Figure 8
Re-Modulix concept: removal and re-use of modules
TIP5-CT-2006-031312 Page 13 of 22URBAN TRACK Issued: 26/8/2008
Quality checked and approved by project co-ordinator André Van Leuven
D0109_CDM_M24.doc
2. TESTING
2.1. INTEGRATION INTO THE STUVA TEST CIRCUIT
The Re-Modulix system is based on an embedded rail system where the rail is completely put in
an elastic encapsulation (rubber-jacket) and embedded in a concrete slab, ensuring fastening in
all directions and completely decoupling the rail from the environment (electrical and vibration
protection).
The slab and the jacket are designed to take over specified rolling stock axle loads. They also
need to resist to road traffic (e.g. heavy truck loads, traffic at grade crossing). The behaviour of
the Re-Modulix system and its elastic encapsulation is tested on the STUVA test circuit (using
test samples of slab with rail and elastic encapsulation).
This test circuit allows testing tyres, shock absorbers, road
surfaces, expansion joints and roadway markings under
extreme conditions (temperature range + 60 °C to – 30 °C,
axle load 10 t, maximum speed 100 km/h) in order to be
able to simulate high traffic loads in a short time.
Two test slabs are fabricated (Figure 9). The same road
finishing is applied as will be installed in Karlsruhe: basalt
stones. The rail orientation is different for both of them
(Figure 10, Figure 11). The dimensions were fixed during
meetings at Stuva in Cologne.
The test was carried out the beginning of 2008. After this test, it can be stated that the test slabs
with basalt stones show excellent results.
Figure 9
Fabricated test slabs
TIP5-CT-2006-031312 Page 14 of 22URBAN TRACK Issued: 26/8/2008
Quality checked and approved by project co-ordinator André Van Leuven
D0109_CDM_M24.doc
Figure 10
STUVA test circuit composition. List of partners and position of their test slab on the circuit
Figure 11
Two different STUVA test slabs proposed: rail in the direction of the rolling surface and two rails
perpendicular to the rolling surface
TIP5-CT-2006-031312 Page 15 of 22URBAN TRACK Issued: 26/8/2008
Quality checked and approved by project co-ordinator André Van Leuven
D0109_CDM_M24.doc
Figure 12
Test bodies with Karlsruhe basalt stones on test circuit STUVA during test
TIP5-CT-2006-031312 Page 16 of 22URBAN TRACK Issued: 26/8/2008
Quality checked and approved by project co-ordinator André Van Leuven
D0109_CDM_M24.doc
2.2. SMALL REMOVABILITY TEST
Because the modules are surrounded by concrete during installation, the modules have to be
separated from the concrete to prevent that the concrete attaches to the modules. 2 possible
solutions are contemplated: rubber and PE-film (plastic foil). To make sure that the PE-film
doesn’t melt by the hardening warmth of the concrete and to determine the force necessary to
pull out the modules, a test is carried out.
The test involves the production of a small concrete block (representing the prefabricated
module). This small block is surrounded with a separating material. Concrete is poured around
it, simulating the concrete poured in reality (Figure 13). After the hardening, the small block is
pulled out the surrounding block and the force needed to do so, is measured.
It can be assumed that decompression complicates the pulling out. Therefore, in some blocks a
tube is inserted to make contact with the air and eliminate decompression.
Figure 13
Plan test block small removability test
TIP5-CT-2006-031312 Page 17 of 22URBAN TRACK Issued: 26/8/2008
Quality checked and approved by project co-ordinator André Van Leuven
D0109_CDM_M24.doc
Three test blocks are produced (Figure 14):
1. test block with plastic foil;
2. test block with plastic foil and tube against decompression;
3. test block with rubber, vaseline and tube against decompression.
Figure 14
Production 3 test blocks
The force needed to push out the small cube of test blocks 2 and 3 is measured in the CDM
laboratory.
Figure 15
Test setup CDM laboratory
TIP5-CT-2006-031312 Page 18 of 22URBAN TRACK Issued: 26/8/2008
Quality checked and approved by project co-ordinator André Van Leuven
D0109_CDM_M24.doc
Figure 16
Test block with plastic foil and tube against decompression
5kN was needed to pull out the small block of the test block with plastic foil and tube against
decompression.
Figure 17
Test block with rubber, vaseline and tube against decompression
The first movement of the test block with rubber, vaseline and tube against decompression took
place at 8kN. The force needed to push out the rest of the block was 5kN.
The blocks came out undamaged. The test block with plastic foil gave the best results. These
tests show that the force needed to remove the modules can‘t be neglected and the anchors of
the modules should be calculated accordingly. However small scale parameters may have
influenced these test results. Therefore, a big scale test with plastic foil is planned to compare
and to simulate real scale.
The force needed to pull out the small cube of test block 1. (without tube, no possibility to push)
will be measured at UCL “Université Catholique de Louvain”, one of the Urban Track partners.
If this gives good results, an execution without decompression tube is preferable, because of the
difficulty to implement this on site.
TIP5-CT-2006-031312 Page 19 of 22URBAN TRACK Issued: 26/8/2008
Quality checked and approved by project co-ordinator André Van Leuven
D0109_CDM_M24.doc
2.3. BIG REMOVABILITY TEST
Dimensions of the big removability test block (width, height) will be adapted to the project
dimensions (Figure 18). A length of 3 m is proposed. The version with plastic foil will be tested
with or without decompression tube, depending on the results of the small removability test at
UCL.
Figure 18
First proposal big removability test, dimensions have to be changed according to project in reality
TIP5-CT-2006-031312 Page 20 of 22URBAN TRACK Issued: 26/8/2008
Quality checked and approved by project co-ordinator André Van Leuven
D0109_CDM_M24.doc
2.4. SURFACE FINISHING
The surface finishing is very important in a street like Kaiserstrasse. Therefore VBK requested to
make a test piece (1m²) with basalt stones provided from them. This way the prefabrication
could be tested and a first impression of the joints-stones and total finishing was possible.
Figure 19
Prefabricated test piece with basalt stones
TIP5-CT-2006-031312 Page 21 of 22URBAN TRACK Issued: 26/8/2008
Quality checked and approved by project co-ordinator André Van Leuven
D0109_CDM_M24.doc
3. LIFE CYCLE COST
Participation at the SP4 LCC-workshop, organised by TTK and DI :
The handling of the LCC tool, developed in SP4, was taught. LCC calculation for the developed
re-modulix design and a reference track (Modulix) were carried out. Data were collected for life
cycle cost calculations. As reference track the same prefabricated system was taken into account
without special slabs to allow re-use.
The most important parameters adopted in the LCC calculation are:
200 m of straight single track;
Cost of engineer = 70 €/h, technician = 50 €/h, skilled labour = 30 €/h;
After 10 years the track has to be demolished because of the construction of a tunnel which
will make all urban tracks underground. Re-modulix can be “recycled” and re-installed on
another track. Modulix has to be demolished and a new modulix has to be installed on
another track.
Re-modulix:
Demolition old track and installation new track: 1900 €/m (every life cycle);
Demolition old track and re-installation: 1900 €/m (after first 10 years);
Rail renewal: 140 €/m material cost; 80 €/m external cost; 0,25 h/m engineer; 0,75 h/m
skilled labour (after 15 years);
Rail grinding: 10 €/m external cost; 1 h/m skilled labour (every 3 years).
Modulix:
Demolition old track and installation new track: 1900 €/m (every life cycle);
Demolition, re-installation and re-use: 1100 €/m (after first 10 years); 250 €/m socio-
economic cost (modulix can not be re-used, no recycling of materials);
Rail renewal: 140 €/m material cost; 80 €/m external cost; 0,25 h/m engineer; 0,75 h/m
skilled labour (after 15 years);
Rail grinding: 10 €/m external cost; 1 h/m skilled labour (every 3 years).
TIP5-CT-2006-031312 Page 22 of 22URBAN TRACK Issued: 26/8/2008
Quality checked and approved by project co-ordinator André Van Leuven
D0109_CDM_M24.doc
Figure 20
Graphic of total LCC over period under consideration candidates vs. Life Cycle phases
Construction &Investment
Operation &Maintenance
Total
Reference: Modulix 521.577 € 64.151 € 585.728 €
Ca
nd
idat
es
Re-Modulix 472.435 € 73.636 € 546.071 €
Reduction 9,4% -14,8% 6,8%
Figure 21 Table for total LCC over period under consideration candidates vs. Life Cycle phases
Further to the last calculations, the comparison of re-modulix and reference track shows a LCC
reduction of 6,8% without incorporating socio-economic costs.
The main difference with this reference system is the fact that the system is reusable after
demolition of the track. This way the materials are recycled which follows the current tendency
towards recycling and care for the environment (reduction 9,4% construction and investment
costs).
Operation and maintenance costs do not show a reduction because of the rail renewal that is
necessary for the Re-Modulix but not for the Modulix system (re-used rail versus new rail).
When incorporating socio-economic costs in a further phase of the LCC calculations, the LCC
reduction will improve.