T E R R A S A N C T A R E T R E A T C E N T E R IMPACT REPORT
D I R E C T O R A T E O F R E V E N U E I N T E L … 3 of 97 2003 and the Maharashtra Electricity...
Transcript of D I R E C T O R A T E O F R E V E N U E I N T E L … 3 of 97 2003 and the Maharashtra Electricity...
Page 1 of 97
D I R E C T O R A T E O F R E V E N U E I N T E L L I G E N C E 13, SIR VITHALDAS THAKERSEY MARG, OPP PATKAR HALL, NEW MARINE LINES,
MUMBAI 400 020 PH: 022-22010115, 022-22010116
----------------------------------------------------------------------------------------------------------
F.No.DRI/MZU/CI-224 (PMC)/2013 Date: 15-05-2014
Subject: Gross over-valuation in the import of goods by M/s Maharashtra
Eastern Grid Power Transmission Company Limited (MEGPTCL), a
wholly owned subsidiary of M/s ADANI Enterprises Limited (AEL)
through the contractor M/s PMC Projects (India) Private Limited -
Show Cause Notice under Section 124 of the Customs Act, 1962 –
reg.
1.1 Intelligence developed by Mumbai Zonal Unit (MZU) of Directorate of
Revenue Intelligence (DRI) indicated that various entities of Adani group were
indulging in gross over-valuation of imported goods (zero or low duty rated) to siphon
off money abroad from public listed companies. The modus-operandi followed was
that for power sector imports (Power generation:- Zero % duty and Power
transmission:- 5% Basic Custom Duty), while the goods from various vendors (mostly
South Korean & Chinese) are sent directly to India, the documents are routed through
an intermediary entity created by them in the UAE, viz. M/s. Electrogen Infra FZE,
who raised inflated invoices (inflating the values in original invoices of OEMseveral
times) on the Indian company, against which money is remitted to UAE. The activities
of M/s Electrogen Infra FZE, UAE are apparently controlled and managed by the
Adani Group through one or more of its representative firms and/or personnel.
Intelligence further suggested that from UAE, while the actual invoice value is remitted
to respective OEMs, the extra amount is routed to the Mauritius account of the parent
company of M/s Electrogen Infra FZE i.e. M/s Electrogen Infra Holding Pvt. Ltd.
1.2 On the basis of the said intelligence, enquiries were initiated into the
import of goods invoiced by M/s Electrogen Infra FZE, UAE (here-in-after referred to
as ‘EIF’ also),which were found to have been imported and cleared in the name of M/s
PMC Projects (India) Private Limited, (IEC No. 0805004416)(here-in-after referred to as
‘PMC’ also), having its registeredoffice in Ahmedabad.
1.3 Information and documents were sought from PMCvideletter dated 05-
02-2013 bearing F.No.DRI/MZU/CI-224/2013/997(RUD-C/1). The company, vide its
letter Ref.No. PMC/DRI/Reply/1394/13 dated 26.02.2013, (RUD-D/1) sought extra-
time of 15 days upto 15.03.2013, on the plea of being unable to compile the
Page 2 of 97
requisitioned information within the given time frame. Subsequently, on or about
13/14-03-2013, the company through a representative from its Mumbai office, sought
to submit certain documents in two box files, which on preliminary scrutiny turned
out to be incomplete and did not contain all the requisitioneddocuments. The said
documents were returned back forthwith to the representative, since they were not
only found to be incomplete but submission of crucial documents also appeared to
have been withheld. This aspect was categorically pointed out to the concerned
person, Shri AjitBarodia, Associate VP of the Adani Group who had been been deputed
to this Unit with the documents to co-ordinate the company’s response, as well as
verbally to one Shri Vidyut Joshi, an employee of PMCbased at Ahmedabad. Despite
the documents having been returned back to the importer’s representative with
specific instructions, PMCproceeded to forward the same incomplete documents in two
box files by post. These facts were brought to the notice of the Vice-President of the
Adani Group, handling corporate affairs, who had liaised with this Unit on behalf of
PMC, through a letter dated 26-03-2013 (RUD-C/2) bearing F.No. DRI/MZU/CI-
224/2013/1869, drawing his attention to delay in furnishing of the requisitioned
information&documents
1.4 A specific request was made in the letter 26-03-2013, for immediate
submission of the all Contracts/Agreements entered into by EIF with one or more
overseas firms/entities in connection with sourcing of equipments/machinery for
eventual supply to PMC. Specific mention was made in the letter for submission of a
copy of the Contract No. bearing reference no. 700003, purported to be the contract
number for the Contract executed between EIF and M/s Hyundai Heavy Industries Co.
Ltd. , South Korea, involving supply of high voltage transformers, shunt reactors etc.,
mention of which was found in some of the documents forwarded by the importer in
the two box files.
2.1 The information and documents forwarded by PMC under cover of letter
bearing Ref : PMC/765/DRI/REPLY/1401/13 dated 12-03-2013 (RUD-D/2), were
examined. From the submissions made by the importer in the said letter, it appeared
that M/s Maharashtra Eastern Grid Power Transmission Company Limited, having its
registered office at Adani House, Mithakhali Six Roads, Navrangpura, Ahmebadad-
380009 (here-in-after referred to as ‘MEGPTCL’ also), a wholly owned subsidiary of
M/s Adani Enterprises Limited, (here-in-after referred to as ‘AEL’ also), the flagship
company of the Adani Group, under Licence from the Maharashtra Electricity
Regulatory Commission, Mumbai (here-in-after referred to as ‘MERC’ also), a
electricity regulatory body of government of Maharashtra, was setting up a 765 KV
intra-state transmission network in eastern part of the State of Maharashtra, to
evacuate power from the upcoming five power plants. The project apparently involved
setting up of two765 KV S/C transmission lines in the corridor of Tiroda– Koradi III –
Akola II – Aurangabad, alongwithassociated sub-stations and bays. It further appeared
that based on an application dated 18-02-2010, made by MEGPTCL to the MERC
requesting for grant of transmission licence under section 14 of the Electricity Act,
Page 3 of 97
2003 and the Maharashtra Electricity Regulatory Commission (Transmission Licence
Conditions) Regulations, 2004 for development of transmission system as above, for
evacuation of power from projects in north-eastern Maharashtra, the MERC vide its
order dated 14-09-2010 appears to have granted a Transmission Licence i.e
Transmission Licence No. 1 of 2010 (RUD-D/3)for a period of 25 years to MEGPTCL.
2.2 The Commission in its order dated 14-09-2010 observed that capital cost
of the transmission project should be optimized and grant of licence should not in any
manner be construed as approval of the cost and other details of the project by the
Commission. The Commission accordingly,inter-alia, imposed certain conditions,
which were to be construed as specific conditions for the Transmission Licence. The
first and foremost condition, as per the MERC’s order, was that the construction and
commissioning of the transmission system shall be executed through suitable
packages and contracts for these packages shall be awarded through Competitive
Bidding basis. The said order further contained directions that the aforesaid Specific
Conditions of the Transmission Licence of MEGPTCL are specified by regulations
under Section 16 of the Electricity Act, 2003 and that such conditions shall be deemed
to be conditions of Licence of MEGPTCL. These conditions appear to have been
expressly incorporated in the Transmission Licence No. 1 of 2010 dated 21-09-2010
granted to MEGPTCL.
2.3 Perusal of copy of the Purchase Order bearing Ref.
MEGPTCL/PMC/AD/03/10 dated 27-09-2010 (RUD-D/4)placed by MEGPTCL on
PMC revealed that it covered design, engineering, manufacture, procurement,
assembly and testing at works, packing & forwarding, supply, inland transportation
and transit insurance for items/materials for 765 KV & 400 KV sub-stations including
allequipments , auto transformers and shunt reactors associated with 765 KV Tiroda-
Koradi III-Akola III-Aurangabad Transmission System in Maharashtra. Relevant
extracts of the purchase order under the heading References is reproduced below :-
‘”References:
1. Tender Notice No. MEGPTCL/765 KV & 400 KV SS/EPC/02 issued vide letter ref.
no. MEGPTCL/Trans.Line/Tender-EPC/KP/36/10 dated 17-08-2010.
2. Pre-bid Meeting dated 21-08-2010
3. Your Techno-Commercial Bid Ref.PMC/MEGPTCL/Tender/696/10 dated 04-09-
2010
4. Letter of Intent Ref.AD/MEGPTCL/SS/01 dated 23-09-2010”
Contents of the Purchase Order, as reproduced above, appeared to indicate that
Purchase Order was placed pursuant to a tendering process in selection of PMC as the
contractor for execution of works. From the contents of the Purchase Order, it further
appeared that though the Purchase Order had been addressed to PMC, express
mention appears to have been made regarding the Purchase Order being placed on a
consortium which included M/s PMC Projects (India) Private Limited. However, the
Page 4 of 97
names of other members of the consortium were not forthcoming in the Purchase
Order. The Purchase Order value given at Clause 2.0 under Contract Price stood at Rs.
1440,65,10,525/- The price appeared to have been revised subsequently to Rs.
1693,94,04,176/- vide Purchase Order Amendment-1 bearing Ref. No.
MEGPTCL/PMC/AD/03/10/AMDT-1 dated 05-07-2011 (RUD-D/ 5 ).
2.4 On scrutiny of the documents, it further appearedthat PMC, for the
purpose of executing the order placed on by M/s MEGPTCL, on their part, in turn
appeared to have sub-contracted orders on two different entities viz. M/s ABB Limited,
Bangalore and EIF. A portion of the order placed on PMC by M/s MEGPTCL, was sub-
contracted to M/s ABB Limited, Bangalore by PMC by way of entering into a contract
dated 28-09-2010(RUD-D/6) with them,for sourcing of Surge Arresters & Isolators for
various sub-stations. The scope of supplies included both off-shore and onshore
supplies for an aggregate consideration of Rs. 189,40,37,306/- , price of the off-shore
and on-shore supply components being Rs. 20,76,16,131/- &Rs. 166,27,13,450/-
,respectively,and the balance of Rs. 2,37,07,726/-, being freight and transit insurance
for onshore and offshore supplies. The remaining portion of the work ordered on PMC
by MEGTPCL under Purchase Order dated 27-09-2010 appears to have beensub-
contracted by PMC to EIF, by way of entering into and executing an agreement bearing
no. 415703 on 01-10-2010 (RUD-D/7)with them for an aggregate consideration of
USD 376,195,652/- for sourcing Auto Transformers, Shunt Reactors, Disc
Insulatorsand OpticalFiber Ground Wire (OPGW) alongwith hardware and fittings.
It,therefore, appeared that PMC was to fulfilthe contractual obligations covered in the
Purchase Order dated 27-09-2010 placed on it by MEGTPCL in so far as it related to
sourcing of equipment and machinery, by way of arranging procurements from M/s
ABB Limited and EIFunder two separate contracts as narrated above.
2.5 PMC appears to be have been engaged by MEGPTCL, a wholly owned
subsidiary of M/s Adani Enterprises Limited, (AEL) and recipient of power
Transmission Licence issued by Maharashtra Electricity Regulatory Authority
Commission (MERC) for setting up two 765 KV Transmission corridor from Tiroda-
Koradi III-Akola II- Aurangabad in Maharashtra State, as a sub-contractor for and on
behalf of MEGPTCL, to execute works in pursuance of the power Transmission Licence
granted to it.
2.6 Vide a document titled Amendment-1 to Agreement No. 415703 dated
30-09-2011 (RUD-D/8)bearing reference no. Ref.415703/Amdt.-1, executed between
PMC and EIF, certain amendments appear to have been carried out. Marine Insurance
which was within the scope of EIF as per the original agreement appears to have been
removed from its scope vide the said Amendment. The total price under the scope of
work covered by the Agreement appears to have been amended and reduced to USD
376,077,628/- from USD 376,195,652/-.
Page 5 of 97
2.7 Further scrutiny of the documents appeared to reveal that MEGPTCL,
through an application bearing Ref.No. MEGPTCL/Energy/Certificate/01/11 dated
04-09-2011 (RUD/D-9)made to the Principal Secretary, Energy Department,
Government of Maharashtra, Mantralaya Main Building, Mumbai, requested for
issuance of essentiality certificate for import of transformers with accessories & shunt
reactors with accessories for the two transmission lines to be set up in the corridor of
Tiroda-Koradi-Akola- Aurangabad, while making a mention therein of the contract it
entered into with EIF. In its application, MEGPTCL,inter-alia, stated that PMC would
be importing transformers with accessories and shunt reactors, on behalf of MEGPTCL
as EPC contractor from EIF and would avail benefit of General Exemption No. 122. As
per the said application, the goods covered by the essentiality certificate to be issued,
were proposed to be registered with the Kandla Custom House for availing
concessional rate of duty as project imports. As a part of enclosures to the said letter,
MEGPTCL appear to have inter-alia, enclosed certain pages which apparently were
print-outs of product catalogues of M/s Hyundai Heavy Industries Co. Ltd. for shunt
reactors and transformers, thereby prima-facie indicative of the origin and make of the
transformers and shunt-reactors (i.eHyundai make, South Korea) to be supplied by
EIF to PMC. This appears to have been followed up by subsequent applications to the
Principal Secretary, Energy Department, Government of Maharashtra from time to
time through letters dated 24-09-2011, 17-11-2011 and 24-01-2012(RUD-D/10).
Similar correspondence made to Principal Secretary, Energy Department, Government
of Maharashtra seeking essentiality certificate so as to be able to avail concessional
rate of duty were also found in respect of Surge Arresters and Surge Counters to be
supplied by M/s ABB AB, Sweden through its Indian counterpart, M/s ABB Limited to
PMC, based on the application made by MEGPTCL. The Principal Secretary (Energy),
appears to have certified essentiality of goods for concessional rate of duty from time
to time.
2.8 From scrutiny of the documents submitted by the importer, it further
appeared that MEGPTCL made applications to the Commissioner of Customs, Kandla,
seeking to registerthe contract for supply of equipmentsfor availing concessional rate
of duty, to the extent of equipments for which they were in possession of certificate of
essentiality issued by the Government of Maharashra. Based on the applications
received, the office of Commissioner of Customs, Kandla Custom House appeared to
have registered the said project [(Registration No. 27/2011-12-Page No. 95) -F.No.
S/42-38/MEGPTCL/Gr.VI/2011] for assessment under heading 98.01.(RUD-D/11).
Entries in the register were updated for additional value registrationsdepending on
issuance of fresh essentiality certificates from time to time. Details of the registrations
done by the Kandla Custom House, as per information provided by PMC, with
reference to the supplies from EIF covered by Contract no. bearing 415703 dated 01-
10-2010 (RUD-D/12) is summarized in the table below :-
Page 6 of 97
Table - 1
Value of contracts registered with Kandla Custom House for assessment under
heading 98.01 against supplies covered by Contract no. 415703 dated 01-10-
2010 between PMC and EIF
S.No
.
Date & File No. of REIFstration CIF Value in USD Description of goods
1. S/42-38/MEGPTCL/Gr.VI/2011 dt. 01-11-2011
52313104.21 Auto Transformers, shunt reactors & mandatory spares.
2. S/42-38/MEGPTCL/Gr.VI/2011 dt. 17-11-2011
31872406.27 Auto Transformers & mandatory spares
3. S/42-38/MEGPTCL/Gr.VI/2011 dt.
23.12-2011
50179259.26 Shunt Reactors & mandatory spares
4. S/42-38/MEGPTCL/Gr.VI/2011 dt. 30-12-2011
20529460.48 Shunt Reactors & Mandatory spares
5. S/42-38/MEGPTCL/Gr.VI/2011 dt. 16-02-2012
55154343.68 50179259.12
Shunt Reactors & Mandatory spares Auto Transformers & mandatory spares
TOTAL CIF 260,227,832.90
2.9 From the figures shown in the table above, , it is evident that the
aggregate value of supply of auto transformers, shunt reactors and mandatory spares
to the tune of USD 260,227,832.90 appears to have been registered for assessment
under heading 98.01 by theOffice of Commissioner of Customs, Kandla. Going by the
price schedule summary sheet (RUD-D/13)given at Schedule 1 to Agreement No.
415703 dated 01-10-2010 between EIF and PMC, these items appear to be covered by
Sr.No. A & B. (A I & II and B-I &B-11) and the aggregate price works out to USD
260,269,978, value whereof being by and large in conformity with the aggregate value
registered for concessional assessment as project imports. The value of the other items
covered at Sr. No. C and D of Schedule 1 of the Agreement bearing No. 415703 dated
01-10-2010 between EIF and PMC involving supply of Disc Insulators and Optical
Fiber Ground Wire or Optical Ground Wire (OPGW)with hardware &accessories,
respectively, apparently were not sought to be registered for assessment under
heading 98.01, thereby implying that the these goods were to be cleared at merit rate
of duty.
2.10 Similar details of registration in respect of goods to be sourced by PMC
from M/s. ABB Limited, under Contract dated 28-09-2010 is summarized on the basis
of documents forwarded by the importer :-(RUD-D/14)
Table - 2
Value of contracts registered with Kandla Custom House for assessment under
heading 98.01 against supplies covered by Contract dated 28-09-2010 between
M/s PMC Projects (I) Pvt. Ltd. and M/s ABB Limited
S.No. Date & File No. of Registration CIF Value in USD Description of goods
1. S/42-38/MEGPTCL/Gr.VI/2011 dt. 16-02-2012
17866360 Surge Arrester and Surge Counter
2. S/42-38/MEGPTCL/Gr.VI/2011 dt. 16-02-2012
31991193 Surge Arrester and Surge Counter
3. S/42-38/MEGPTCL/Gr.VI/2011 dt. 07-05-2012
35024201.53 Isolator with one, two earth switch & spares
4. S/42-38/MEGPTCL/Gr.VI/2011
dt. 08-05-2012
51058246 Isolator with one, two earth switch & spares
5. S/42-38/MEGPTCL/Gr.VI/2011 dt. 16-02-2012
34167744 Isolator with one, two earth switch & spares
170,107,744.50
Page 7 of 97
It appears that pursuant to the above registration, goods were imported by M/s PMC
on high-sea-sale basis from M/s ABB Limited (IEC-0388038047) i.e M/s ABB Limited
(the original importer) imported the aforelisted goods and sold the same on high-sea-
sale basis to M/s PMC Projects (India) Pvt. Ltd., who filed bills of entry claiming
assessment at concessional rate of duty under heading 98.01. Since the present
investigation is in the context of supplies made by EIF, reference to imports by M/s
PMC Projects from ABB Limited, are being made and mentioned solely for the limited
purposes of understanding how the overall scope of work ordered by MEGPTCL on
PMC in the Purchase Order dated 27-09-2010 was further sub-contracted to the two
entities i.e. (i) EIF, and (ii) M/s ABB Limited.
2.11 With regard to the specific request made by this Unit for copies of the
invoices raised by the original supplier/original equipment manufacturer and copies of
the corresponding agreements entered into by EIF with such overseas entities, M/s
PMC Projects (India) Private Limited submitted, in their response dated 12-03-2013
that such documents were required to be obtained from EIF and M/s ABB Limited,
whom they had requested and that the said documents would be submitted
immediately upon receipt from EIF and M/s ABB Limited. Subsequently, vide another
letter bearing Ref.No. PMC/765/DRI/REPLY/1412/13 dated 25-04-2013, (RUD-
D/15)they conveyed that in response to their letter to EIF to provide copies of the
invoices/contracts between them and the original equipment manufacturer, M/s
Hyundai Heavy Industries Co. Ltd., South Korea, EIF had expressed their inability to
provide the requisite documents citing the reason of business confidentiality.
3.01 Imports made in the name of PMC as available on the Electronic-Data-
Interchange (EDI) system were retrieved and examined. It appeared from scrutiny of
the import data that PMC commenced its imports with invoice from EIF in the year
2011. As per the EDI data-base, the first consignment imported under Bill of Entry
No. 740818 dated 03-03-2011 with invoice from EIF involved import of goods declared
to be ‘120 KN and 210 KN Disc Insulators’ which were cleared through JNCH,
NhavaSheva at merit rate of duty applicable at the time of clearance. This
consignment was followed up,inter-alia,by several other imports which were noticed to
have been cleared through Mundra Port at merit rate duty involving clearance of goods
declared to be Glass Disc Insulators, OPGW cable, OPGW hardware and accessories.
The overseas firm, who had raised invoices in the name of PMC, for these
consignmentswas found to be EIF. The EDI data base also reflected certain imports
which were found to have been assessed and cleared at concessional rate of duty
under heading 98.01, details of which are narrated in the following paragraphs
separately.
3.2 Brief particulars of the consignments invoiced by EIF, imported,inter-
alia, by PMC involving import of goods required for setting up/installation of the two
transmission lines are tabulated below in Table-3A (those cleared at merit rate) and
Table-3B (those cleared claiming concessional rate under project import under 98.01)
Page 8 of 97
Table-3A
(Details of consignments imported by PMC and cleared at merit rate)
S. No.
BE No. & date
SUPPLIER (ELECTROGEN INFRA FZE’S INVOICE NO.
/DATE
INV. VALUE (USD)
BILL OF LADING (B.L.) NO./ DATE
SHIPPER AS PER B.L.
[A] [B] [C] [D] [E] [F]
1 740818/ 03-03-
2011
PMC/EG/11009/001 dt.: 09.02.11/09-02-
2011
4270200 MAEU601299135
/09-02-2011 DALIAN INSULATOR GROUP
CO. LTD
2 3036910/
24-03-2011
PMC/EG/FP09022011/002/15-02-2011
3269009.28 NDACVF300 /15-
02-2011 SEDIVER INSULATORS (SHANGHAI) CO. LTD.
3 3427185/
06-05-2011
PMC/EG/EG11053/DI/004 dt.: 26.04.11/26-
04-2011 8846304
YMLUZ245202791 /05-04-2011
DALIAN INSULATOR GROUP CO. LTD
4 3493704/
13-05-2011
PMC/EG/EG11067/DI/005/26-04-2011
3783025.2 APLU062194693
/31-03-2011 DALIAN INSULATOR GROUP
CO. LTD
5 3525050/
18-05-2011
PMC/EG/SE110325/SE/003 /26-04-2011
989736 YMLUZ230140405
/31-03-2011
SUZHOU FURUKAWA POWER OPTIC CABLE CO. LTD. ,
CHINA
6 3685422/
02-06-
2011
PMC/EG/FP23042011/SI/006 /20-05-2011
5608544.64 YMLUZ230145416
/28-04-2011 SEDIVER INSULATORS (SHANGHAI) CO. LTD.
7 3739813/
08-06-2011
PMC/EG/SE110509/SF/007 /26-05-2011
2499741.2 YMLUZ230148714
/12-05-2011
SUZHOU FURUKAWA POWER OPTIC CABLE CO. LTD. ,
CHINA
8
4472634/
26-08-2011
PMC/EG/FP15072011/SI/008 /06-08-2011
5608544.64 YMZUZ230162786
/22-07-2011 SEDIVER INSULATORS (SHANGHAI) CO. LTD.
9 4798484/
30-09-
2011
PMC/EG/SE110817/SF/012 /26-09-2011
4563413.62 KKLUSH4220867/
04-09-2011
SUZHOU FURUKAWA POWER OPTIC CABLE CO. LTD. ,
CHINA
10 4799346/
30-09-2011
PMC/EG/FP260822011/SI/011 /26-09-2011
5608544.64 MSCUY5709319/0
2-09-2011 SEDIVER INSULATORS (SHANGHAI) CO. LTD.
11 5327127/
29-11-2011
PMC/EG/EG11217/DI/015 /19-11-2011
5302000 MSCUDL744655
/11-11-2011 DALIAN INSULATOR GROUP
CO. LTD
12 5905812/
03-02-2012
PMC/EG/FP23122011/SI/021 /18-01-2011
5608544.64 YMLUZ230190641
/30-12-2011 SEDIVER INSULATORS (SHANGHAI) CO. LTD.
13
5906514/
30-02-2012
PMC/EG/FP16122011
/SI/020 /18-01-2012 5608544.64
NDAEHH600 /13-
12-2011
SEDIVER INSULATORS
(SHANGHAI) CO. LTD.
14
5971442/
10-02-2012
PMCEG111207SF019
/16-01-2011 5356134.48
NDAEHH600/13-
12-2011
SUZHOU FURUKAWA POWER
OPTIC CABLE CO. LTD. , CHINA
15 6225685/
12-03-
2012
PMC/EG/EG12001/DI
/027 /22-02-2012 5470280
MSCUDL786284/
28-01-2012
DALIAN INSULATOR GROUP
CO. LTD
16 6674228/
28-04-
2012
PMC/EG/EG12015/DI
/038/23-04-2012 7699000
MSCUDL815422/
30-03-2012
DALIAN INSULATOR GROUP
CO. LTD
17 6921529/
24-05-
2012
PMC/EG/EG12047/DI/039 dt.: 21.05.12/21-
05-2012
3792053.84 YMLUZ245204311
/04-05-2012 DALIAN INSULATOR GROUP
CO. LTD
18 7420406/
18-07-2012
PMC/EG/FP21062012/SI/043 /12-07-2012
5048000 YMLUZ230223990
/28-06-2012 SEDIVER INSULATORS (SHANGHAI) CO. LTD.
19 7421168/
18-07-2012
PMC/EG/EG12094/DI/042 /12-07-2012
2734564 YMLUZ245204378
/23-06-2012 DALIAN INSULATOR GROUP
CO. LTD
20 8104738/
03-10-
2012
PMC/EG/FP06092012/SI/045 /27-09-2012
5410356.4 YMLUZ230241803
/14-09-2012 SEDIVER INSULATORS
(SHANGHAI) CO. LTD. CHINA
21 8752773/
13-12-2012
PMC/EG/SE121116/SF/046 /10-12-2012
2438920 YMLUZ230256175
/22-11-2012
SUZHOU FURUKAWA POWER OPTIC CABLE CO. LTD. ,
CHINA
22
8823356/
20-12-2012
PMC/EG/FP03122012/SI/047 /19-12-2012
6429000 YMLUZ230259583
/06-12-2012 SEDIVER INSULATORS
(SHANGHAI) CO. LTD. CHINA
23 8924721/
02-01-2013
PMC/EG/SE121210/SF/052 /29-12-2012
4956776 YMLUZ230260792
/13-12-2012
SUZHOU FURUKAWA POWER OPTIC CABLE CO. LTD. ,
CHINA
Page 9 of 97
24 9215792/
04-02-2013
PMC/EG/SE130111/SF/054 /29-01-2012
4285010.4 YMLUZ230269660
/17-01-2013
SUZHOU FURUKAWA POWER OPTIC CABLE CO. LTD. ,
CHINA
25 9613690/
19-03-2013
PMCSE130224SF055 /13-02-2013
2830412.2 YMLUZ230277098
/28-02-2013
SUZHOU FURUKAWA POWER OPTIC CABLE CO. LTD. ,
CHINA
26 3071687/
22-08-2013
PMC/EG/SE130729/SF/060 /15-08-2013
1851454 YMLUZ231O0478
3/03-08-2013
SUZHOU FURUKAWA POWER OPTIC CABLE CO. LTD. ,
CHINA
TOTAL 119868113.82
Note 1 :All except Sr.No. 1 (cleared through NhavaSheva) have been cleared through
Mundra Port.
Table-3B
(Details of consignments imported by PMC and cleared at concessional rate of
duty under heading 98.01)
S. No.
BE No. & /date
SUPPLIER
(ELECTROGEN INFRA FZE’S INVOICE NO.
/DATE
INV. VALUE (USD)
BILL OF LADING (B.L.)/ NO./DATE
SHIPPER AS PER B.L.
[A] [B] [C] [D] [E] [F]
1 5094332/
03-11-2011
PMC/EG/20103354TNG001/HHI/009 /09-09-
2011 42836611.3
HDMUUSOMN1190100/ 13-08-2011
HHICL*
2 5094334/
03-11-2011
PMC/EG/20103354TNG001A01/HHI/013 /28-
09-2011 3859806.74
KECO12020337/ 03-09-2011
HHICL
3 5284599/
24-11-2011
PMC/EG/20103354TNG001A02/HHI/014 /21-
10-2011 1385993.65
11109521108011/ 02-10-2011
HHICL
4 5296316/
25-11-2011
PMC/EG/20103354TNG002A01/HHI/010/26-
09-2011 20870378.66
HDMUMAOMN1200100/ 27-08-2011
HHICL
5
5728265/
13-01-2012
PMC/EG/20103355TRG
0022A01/HHI/017 /05-01-2012
15095898.67 HDMD001A/ 27-10-
2011
HHICL
6
5907344/
03-02-2012
PMC/EG/20103355TRO
020A03/HHI/018A /10-01-2012
19395362.21 CPJQJI96MASMUN01
/ 22-11-2011
HHICL
7
5907347/
03-02-2012
PMC/EG/20103354TRO
020A02/HHI/016 /10-01-2012
19419250.35 HDMD001B/ 27-
10-2011
HHICL
8
6066894/
22-02-2012
PMC/EG/20103354TNG
004-003/HHI/022 /14-02-2012
6860212.97 POBUMASMUN120002
/ 22-01-2012
HHICL
9 6118467/
28-02-
2012
PMC/EG/20103355TNG003/HHI/025 /22-02-
2012
13838633.48 POBUMASMUN120001
/ 22-01-2012
HHICL
10 6186246/
06-03-
2012
PMC/EG/20103355TRO022A03/HHI/023 /18-
02-2012
2034920.44 11109521110012/ 01-
12-2011
HHICL
11 6186247/
06-03-
2012
PMC/EG/20103355TRO022A03/HHI/024 /18-
02-2012
2608159.99 11109521110011/ 01-
12-2011
HHICL
12 6186248/
06-03-
2012
PMC/EG/20103355TRO020A03/HHI/018 /10-
01-2012
3751551.3 CPJQJI96MASMUN02
/ 22-11-2011
HHICL
13 6257843/
14-03-2012
PMC/EG/20103355TR0021-01/HHI/028/27-02-
2012 19395362.21
HDEH002B/ 31-01-2012
HHICL
14 6257846/
14-03-2012
PMC/EG/20103355TR0021-01/HHI/029 /27-02-
2012 19419250.35
HDEH002A/ 31-01-2012
HHICL
15 6565565/
17-04-2012
PMC/EG/OIL/HHI/036 /12-04-2012
446057.79 11109521202011/
17-03-2012
HHICL
16 6624398/
23-04-2012
PMC/EG/20103355TNG004/HHI/031 /01-04-
2012 13838633.48
POBUMASMUN120010/ 29-02-2012
HHICL
17 6624583/
23-04-PMC/EG/20103355TNG003/003/HHI/032 /01-
6919316.74 POBUMASMUN120008
/ 29-02-2012
HHICL
Page 10 of 97
2012 04-2012
18 6624931/
23-04-2012
PMC/EG/20103355TNG003/004/HHI/033/01-
04-2012 6919316.74
POBUMASMUN120009/ 29-02-2012
HHICL
19 6634898/
24-04-2012
PMC/EG/20103355TSO153-01/HHI/035/01-04-
2012 3190913.12
POBUMASMUN120007/ 29-02-2012
HHICL
20 6636126/
24-04-2012
PMC/EG/20103355TNG004/004/HHI/030 /01-
04-2012 6954061.96
POBUMASMUN120011/ 29-02-2012
HHICL
21
6651942/
26-04-2012
PMC/EG/20103355TSO
153/HHI/034 /01-04-2012
6362219.47 POBUMASMUN120006
/ 29-02-2012
HHICL
22
6678179/
28-04-2012
PMC/EG/OIL/HHI/037
dt.: 12.04.12/12-04-2012
3428993.18 11109521109013/
25-03-2012
HHICL
23
7163485/
20-06-2012
PMC/EG/20103354TS01
50-02/HHI/041/20-05-2012
327416.49 GOSUSEL2062505/
08-05-2012
HHICL
24
7915569/
11-09-2012
PMC/EG/20103355TS01
53-02/HI/044/10-08-2012
852816.04 ESSAPUS12072026/2
8-07-2012
HHICL
25 8970044/
08-01-
2013
PMC/EG/OIL/HI/048 dt.: 24.12.12/24-12-
2012
2509261.93 11109521211012/
03-12-2012
HHICL
26 8993748/
10-01-
2013
PMC/EG/OIL/HI/051
/24-04-2012 2035000.42
11109521211015/
10-12-2012
HHICL
27 8994085/
10-01-
2013
PMC/EG/OIL/HI/049 /24-12-2012
5187830.19 11109521211013/
10-12-2012
HHICL
28 9001672/
11-01-
2013
PMC/EG/OIL/HI/050 /24-12-2012
3102860.2 11109521211014/
10-12-2012
HHICL
29 9260637 /08-02-
2013
PMC/EG/OIL/HI/053 /10-01-2012
108533.55 11109521212011/
17-12-2012
HHICL
30 9871984/
16-04-2013
PMC/EG/20123911TS0227/HI/057 /02-04-2013
56316 ESSAPUS13030769/1
9-03-2013
HHICL
31 9954571/
25-04-2013
PMC/EG/20103354TS0150-01/HI/056/02-04-
2013 361940.32
2512-0030-303.012 /16-03-2013
HHICL
Total 253372879.94
Note :1) * HHICL : Hyundai Heavy Industries Co. Ltd., South Korea
2)All except Sr.No. 30 (cleared through NhavaSheva) have been cleared through
Mundra Port.
3.03 Perusal of the EDI data base further revealed that in the case of
shipments by M/s Dalian Insulator Group Co. Ltd. (here-in-after referred to as ‘Dalian’
also) and M/s Sediver Insulators (Shanghai) Co. Ltd. (here-in-after referred to as
‘Sediver’ also),the shipments as listed in Table-3A, comprised various types of Disc
Insulators, whereas in the case of consignments shipped by M/s Suzhou Furukawa
Power Optic Cable Co.Ltd. , China (here-in-after referred to as ‘Suzhou’ also),the
shipments as listed in Table-3A, comprised OPGW cable, hardware and accessories
thereof, as is evident from the description of goods declared in the Bills of Entry as per
the EDI database. It, therefore,prima-facie appeared that the Disc Insulators under
import had been purchased/procured from the two China based original equipment
manufacturers (OEM) viz. M/s Dalian Insulator Group Co. Ltd. and M/s Sediver
Insulators (Shanghai) Co. Ltd.,whereas, the OPGW cable, OPGW hardware and
accessories appear to have been purchased/procured from Suzhou Furukawa Power
Optic Cable Co.Ltd. , China. In respect of consignments shown at Table-3B, the EDI
data base revealed that equipmentsimported i.e. single phase auto transformers,
Page 11 of 97
single phase shunt reactors, fittings and accessories had been shipped by Hyundai
Heavy Industries Co. Ltd., South Korea. It, therefore,prima-facie appeared that the
said goods had been purchased/procured from the South Korea based original
equipment manufacturer (OEM) viz. M/s Hyundai Heavy Industries Co. Ltd., South
Korea.
4.0 DOCUMENTS FROM BANKS
During enquiries, it was gathered that documents relating to
transactions of goods invoiced by M/s Electrogen Infra FZE, UAE and importation
thereof by M/s PMC Projects (India) Private Limited had,inter-alia, been negotiated
through certain Indian banks having their branches in the UAE. Accordingly,
pursuant to ascertaining the name of some of the banks, correspondence was initiated
with Axis Bank having their branch in Dubai International Financial Centre (DIFC)
Branch in Dubai, to begin with. Vide letter bearing F.No.DRI/MZU/CI-224/2013 dt.
05-04-2013 (RUD-C/3)addressed to the bank authorities, specific
information/documents were sought from them by providing them with details of 29
shipments involving M/s Hyundai Heavy Industries Co. Ltd., South Korea as the
shipper and M/s PMC Projects (India) Private Limited, as the notifying party.
Relevant portion of the specific request made to the Bank is reproduced below :-
“ “i) Copies of invoices, packing lists for the transactions covered by individual
Bills of lading shown in Annexure A to the said letter and/or any other
document submitted/lodged with the bank to facilitate the
negotiation/transaction.
ii) Copies of individual Letters of Credit.
iii) A copy of the Agreement bearing No. 700003 dated 05.10.2010 involving
M/s Electrogen Infra FZE, UAE”.
A general request was made to the bank authorities spelling out the requirement in
terms of documentation i.e. all documents negotiated through the bank in respect of
every shipment of goods by any firm/entity (shipper) to India having M/s PMC
Projects (India) Private Limited as the ‘Notifying party’, wherein the original consignee
is EIF and/or all such documents negotiated by the bank on the instructions of/at the
behest of EIF.
4.1 DOCUMENTS FROM AXIS BANK (First Lot) 4.1.1 Axis Bank, Mumbai responded by providing certain documents through
their letters bearing reference no. AXIS/CO/IBD/2013-14/35 dated 18-04-2013(RUD-
D/16) and AXIS/CO/IBD/2013-14/44 dated 25-04-2013 (RUD-D/17). The
documents forwarded by Axis Bank contained bank attested photo copies of some bills
of lading together with corresponding invoices and packing lists, pertaining to the
shipments covered by such bills of lading. A careful scrutiny of the contents of
individual bills of lading revealed that each of the bills of lading covered goods shipped
Page 12 of 97
by M/s Hyundai Heavy Industries Co. Ltd., South Korea in the name of PMC. The
name of M/s Hyundai Heavy Industries Co. Ltd., South Korea was indicated as the
‘Shipper’ in the respective bills of lading and the name of PMC was indicated as the
Notifying Party. The box provided for mentioning the name of the Consignee in the
Bills of Lading was found to contain a remark ‘To Order’ or ‘To Order of Axis Bank,
DIFC Branch’. The bills of lading were found to make a mention of Letter of Credit
(L/C) Number which apparently pertained to the Letter of Credit opened by M/s AXIS
Bank Limited, DIFC Bank as the issuing Bank on behalf of EIF, in favour of the
shipper M/s Hyundai Heavy Industries Co. Ltd., South Korea. Many of the bills of
lading contained a reference to an Agreement number ‘700003 dated 05-10-2010’,
apparently to denote that the goods being shipped under cover of that specific bill of
lading were covered by the said Agreement. Brief description of the goods and other
particulars thereof were also found on the body of the bill of lading.
4.1.2 Scrutiny of invoices & packing lists forwarded by the bank in support of
each of the bills of lading revealed that each of these invoices happened to be an
invoice raised by M/s Hyundai Heavy Industries Limited, South Korea (an original
equipment manufacturer-OEM) on or in favour of EIF, with the name of the notifying
party appearing thereon as ‘M/s PMC Projects India Private Limited’. It,
therefore,prima-facie appeared that these invoices (here-in-after referred to as OEM
invoices) had been raised by the OEM M/s Hyundai Heavy Industries Co. Ltd. , South
Korea towards sale of the goods supplied by them.
4.1.3 Each of the OEM invoices was invariably found to be containing a
remark-
‘The goods supplied are as per agreement no. 700003 dated 05-10-2010’.
The OEM-invoices were also found to specifically contain the name of ‘M/s PMC
Projects India Private Limited’ as the notifying party. It also bore reference to a Letter
of Credit No. and date. Each of the OEM invoices was found to be accompaniedby a
corresponding Packing List of Hyundai Heavy Industries Co. Ltd., giving details of the
cargo (here-in-after referred to as the OEM packing list). These OEM-packing lists were
found to invariably contain a mention of the invoice number and date, thereby linking
the packing list to its corresponding invoice. The OEM-packing lists were also found to
inter-alia, contain a mention of the same agreement number &date, and other
particulars, as found mentioned on the body of invoices and bills of lading
(i.eAgreement No. 700003 dated 05-10-2010), name of the notifying party-PMC and
Letter of Credit No. & date). Some of the OEM-packing lists, in addition to the above
details were also found to specifically mention the name of the L/C issuing bank as
‘AXIS Bank Limited, DIFC Branch (Regulated by DFSA) Dubai, UAE and the SWIFT
code of the Bank viz. AXISAEEDXXX. Some of the packing lists also contained details
of the bill of lading no. and date, apparently to denote the bill of lading under which
the cargo covered by such OEM was shipped. In many of the OEM-invoices and
corresponding OEM-packing lists raised by M/s Hyundai Heavy Industries Co. Ltd.,
South Korea, the OEM appears to have specifically mentioned the name and mobile
Page 13 of 97
number of one Shri Jatin Shah, which was apparently found to be mentioned below
the name and address of EIF, thereby implying that the said Shri Jatin Shah belonged
to and/or was employed and/or represented EIF.
4.1.4 From the analysis of OEM documents forwarded by the Axis Bank, as
discussed in the foregoing paragraphs, it prima-facie appears that the bank has
facilitated EIFin its transaction involving purchase/procurement of goods from the
OEM- M/s Hyundai Heavy Industries Co. Ltd. , South Korea. The services of the Bank
appear to have been,inter-alia, utilized by EIF for remitting the invoice value of goods
procured/purchased from M/s Hyundai Heavy Industries Co. Ltd., South Korea, to the
said OEM, as per the amounts indicated in the respective invoices raised by the OEM
on M/s Electrogen Infra FZE, UAE and in accordance with terms & conditions of the
Letters of Credit covering the said transaction.
4.1.5 Amongst the other documents forwarded by the Bank were copies of
Letters of Credit (L/C) opened by Axis Bank, DIFC, Dubai in the name of applicant
i.eEIF favouring M/s Hyundai Heavy Industries Co. Ltd., South Korea, whose name
has been indicated as the ‘Beneficiary’ in the SWIFT messages pertaining to the letters
of credit. Such L/Cs appeared to cover a fixed lumpsum amount, apparently
representing money payable by EIF to M/s Hyundai Heavy Industries Co. Ltd., South
Korea towards purchase/procurement of goods. The Letters of Credit, further,inter-
alia invariably indicate the name of PMC as the Notifying party and also specify an
Agreement no. (Agreement No. 700003 dated 05-10-2010), thereby implying that the
goods were for eventual supply to PMC.
4.1.6 A copy of the Agreement No. 700003 dated 05-10-2010, (RUD/D-
18)foundrepeatedlymentionedin the OEM-invoices/OEM-packing lists/bills of lading
pertaining to supplies by M/s Hyundai Heavy Industries Co. Ltd., was one of the
documents forwarded by Axis Bank, DIFC, Dubai. Scrutiny thereof revealed that the
Agreement appears to have been executed between EIF having its registered/head
office in Sharjah, UAE and M/s Hyundai Heavy Industries Co. Ltd., South Korea. The
scope of work as stipulated in the said Agreement was for the supply of single phase
auto transformers, single phase shunt reactors, fittings and accessories thereof for
installation of the transmission line in the corridor of Tiroda–Koradi-III - AkolaII -
Aurangabad. Since the scope of supply stipulated in the Agreement between the OEM
and EIF appeared to be identical to scope of supply of Auto transformer and Shunt
Reactors etc. covered by Agreement No. 415703 dated 01-10-2010 between EIF and
PMC, (covered at Sr. No. A and B of Schedule 1 to the said agreement) and because
equipments covered by both these Agreements were apparently meant for the same
transmission line project, it prima-facie appeared that goods covered by Agreement No.
700003 dated 05-10-2010 were supplied to PMC.
4.1.7 In order to ascertain this aspect, efforts made to compare the scope of
supply (Description & Quantity) and price thereof covered by Agreement no. 700003
dated 05-10-2010 between EIF and Hyundai Heavy Industries Co. Ltd. South, Korea
vis-à-vis scope of supply (Description & Quantity) and price thereof covered by
Page 14 of 97
Agreement no. No. 415703 dated 01-10-2010 between PMC and EIF. In so far as the
supply of Transformers and shunt reactors was concerned, Agreement no. 700003 dt.
05-10-2010 (between EIF and Hyundai) covered supply of 15 numbers of single phase
auto transformers and 50 numbers of shunt reactors, precisely identical to the scope
of supply covered by the Agreement bearing No. 415703 (between EIF and PMC) as is
evident from an equipment-wise aggregate of the figures at Sr.Nos. 1 to 4 of the table
appended at clause 3.02.1 in the said Agreement, which is re-produced below :-
Table-4
Table appended at clause 3.02.1 of Agreement No. 415703 dated 01-10-2010
between PMC and EIF
S No. Item Description Quantity (Nos) Commencement Period
Delivery/ Completion
Period
1 765/400 KV, 500 MVA Single Phase Auto Transformers
7 - Oct 2011
2 765/400 KV, 500 MVA Single Phase Auto Transformers
8 - Dec 2011
3 765 KV, 80 MVAR, Single Phase Shunt Reactors 7 - Oct 2011
4 765 KV, 80 MVAR, Single Phase Shunt Reactors 43 - Dec 2011
5 120 KN Disc Insulators for 2 Nos. 765 KV S/C
Transmission Lines.
496598 Jan 2011 Nov 2011
6 210 KN Disc Insulators for 2 Nos. 765KV S/C Transmission Lines
688244 Jan 2011 Nov 2011
7 OPGW along with Hardware’s and fittings for 765 KV S/C Transmission Line.
636 KM Jan 2011 Oct 2011
8 OPGW along with Hardware’s and fittings for 765 KV
S/C Transmission Line.
636 KM Jan 2011 Dec 2011
4.1.8 Perusal of Price Schedule Summary Sheet at Schedule-1(RUD-D/13) of
Agreement No. 415703 dated 01-10-2010 reveals that supplies to be made by EIFto
PMC, on the basis of procurements from M/s Hyundai Heavy Industries Co. Ltd.,
appear to be Sr.Nos. A & B of the summary sheet respectively, as is evident from the
description of goods covered at A & B respectively viz. auto transformers , shunt
reactors & spares thereof. Thus, the proportionate agreement value of goods supplied
by M/s Hyundai Heavy Industries Co. Ltd., to M/s PMC Projects (India) Private
Limited under Agreement No. 415703 works out to 260,269,798 USD. (AI+AII+BI+BII)
- (Scanned Copy of Price Schedule-Summary Sheet to this Agreement is at Para 13.1
below). The back-to-back contract prices are tabulated below :-
Table-5
Contract Price comparison:PMC<->EIF vis-à-vis EIF<->HHICL
Particulars Amt. in US $
a) Price : PMC EIF, UAE Value as per agreement no. 415703 dated 01-10-2010 between M/s Electrogen Infra FZE and M/s PMC Projects (India) Private Limited
260,269,798
b) Price : EIF, UAE HHICL Value as per agreement no. 700003 dated 05-10-2010 between M/s Hyundai Heavy Industries Co. Ltd. , South Korea and M/s Electrogen Infra FZE, UAE
65,328,309
DIFFERENCE 194,941,489
(a) as % of (b) 398%
Page 15 of 97
It appears that for the same goods, the contract value between PMC and EIF (the
intermediary invoicing agent)is nearly four times (398%) of the contract value between
EIF and OEM (HHICL) the actual overseas supplierwhich appears to be abnormal
andgross inflation, contrary to ordinary economic logic or prudence. The purpose and
cause of entering into agreement bearing No. 700003 dated 05.10.2010 by EIF with
HHICL appears to stem from the Agreement no. 415703 dated 01-10-2010 and
covered at Sr. No. A and B of Schedule 1. Contents of para (b) of the Agreement No.
700003 dated 05-10-2010, which containsa specific reference to Purchase Order dated
27-09-2010 (Order placed on PMC by MEGTPCL) as well as to Agreement dated 01-
10-2010 (Agreement bearing No. 415703 dated 01-10-2010) make it abundantly clear
that it is back-to-back procurement contract entered into by EIF with M/s Hyundai
Heavy Industries Co. Ltd.(HHICL), for actual of supply the goods to PMC in terms of
agreement no. 415703 dated 01-10-2010 entered between EIF with PMC.
4.1.9 It further appeared from a perusal of the signatories to the Agreement
No. 700003 dated 05-10-2010that one ShriDharmesh Parekh had signed the said
Agreement as an authorized signatory for and on behalf EIF, as is evident from the
handwritten text indicating his name appended below his signature. It,
therefore,prima-facie appeared that Shri Dharmesh Parekh represented the UAE
based firm EIF and held a responsible position with them, having signed on its behalf
as an authorized signatory involving consideration of nearly 65 Million USD.
4.1.10 It further prima-facie appeared that the goods shipped from time to time
under cover of bills of lading submitted by the bank involving M/s Hyundai Heavy
Industries Co. Ltd. as the shipper and imported by PMC, were part and parcel of the
goods covered by Agreement No. 700003 dated 05-10-2010. The price shown in
corresponding OEM-invoices raised by M/s Hyundai Heavy Industries Co. Ltd. on EIF
from time to time represented the proportionate contract value of the goods
commensurate with the value of the goods being shipped in piecemeal.
4.1.11 The price payable by EIF to M/s Hyundai Heavy Industries Co. Ltd. as
per the invoices raised by the OEM on EIF has been tabulated below in respect of 26
shipments, on the basis of documents forwarded by Axis Bank, DIFC, Dubai in
response to this Unit’s letter seeking documents for 29 consignments:-
Table-6
Price of goods as per invoices raised by HHICL on EIF
Sr. No.
Bill of Lading No. /date SHIPPER HYUNDAI HEAVY INDUSTRIES CO. LTD. INVOICE NO./DATE
SHIPPER'S INVOICE VALUE (CIF USD)
1 POBUMASMUN120007/29-02-12 20103355TSO153-01/28-02-2012 781704
2 HDMD001A/27-10-11 20103355TSO153-01/28-02-2012 3476403
3 11109521110012/01-12-11 20103355TSO153-01/28-02-2012 613683
4 11109521110011/01-12-11 20103355TSO153-01/28-02-2012 924172
5 POBUMASMUN120006/29-02-2012 20103355TSO153/28-02-2012 1612158
6 ESSAPUS12072026/28-07-2012 20103355TS0153-02/20-07-2012 221306
Page 16 of 97
7 11109521211015/10-12-2012 NIL/30-11-2012 643021
8 11109521109013/25-03-2012 NIL/26-03-2012 1105332
9 POBUMASMUN120002/22-01-12 20103355TSO153-01/28-02-2012 1740762
10 HDMUMAOMN1200100/27-08-11 20103355TSO153-01/28-02-2012 5165787
11 HDMD001B/27-10-11 20103355TSO153-01/28-02-2012 4469661
12 CPJQJI96MASMUN01/22-11-11 20103355TSO153-01/28-02-2012 4469661
13 POBUMASMUN120001/22-01-12 20103355TSO153-01/28-02-2012 3469843
14 HDEH002B/31-01-12 20103355TSO153-01/28-02-2012 4598482
15 HDEH002A/31-01-12 20103355TSO153-01/28-02-2012 4598482
16 POBUMASMUN120011/29-02-2012 20103355TNG004-004/20-02-2012 1734013
17 POBUMASMUN120010/29-02-2012 20103355TNG004/20-02-2012 3468027
18 POBUMASMUN120008/29-02-2012 20103355TNG003-003/20-02-2012 1385757
19 POBUMASMUN120009/29-02-2012 20103355TNG003-004/20-02-2012 1732196
20 11109521211013/10-12-2012 NIL/30-11-2012 1636376
21 11109521211014/10-12-2012 NIL/30-11-2012 574898.66
22 11109521211012/03-12-2012 NIL/30-11-2012 472101.45
23 HDMUUSOMN1190100/13-08-11 20103355TSO153-01/28-02-2012 10364119
24 KECO12020337/03-09-11 20103355TSO153-01/28-02-2012 1236935
25 11109521108011/02-10-11 20103355TSO153-01/28-02-2012 616927
26 CPJQJI96MASMUN02/22-11-11 20103355TSO153-01/28-02-2012 1170895
TOTAL 62282702.11
4.1.12 Since the name of PMC featured as a notifying party in many of the
above listed bills of lading and corresponding OEM-invoices/packing lists, raised by
Hyundai Heavy Industries Co. Ltd. on EIF, efforts were made to identify the import
particulars for each such consignment i.e. to ascertain the corresponding Bill of Entry
No. & date and the port of import in India. Examination of import particulars thereof
revealed that PMC had utilized these very Bills of Lading, whose numbers are listed
above, for clearance of 26 of the 31 consignments (Table-3B) imported and cleared by
them through Mundra Port at concessional rate of duty, as is evident from the
samebills of lading numbers featuring in the Table 3Bwhich providesparticulars of
consignments imported and cleared by PMC as per the EDI data base.
4.1.13 It, therefore, appears that while the importer utilized the above-listed
bills of lading for customs clearance purpose in India, the value for the purpose of
assessment appears to have been declared on the basis of back-to-back intermediary
invoices raised by EIF on M/s PMC Projects (India) Private Limited. The OEM invoices
and OEM packing lists of M/s Hyundai Heavy Industries Co. Ltd., South Korea do not
appear to be a part of the documents produced to the jurisdictional customs
authorities in India.
4.1.14 It, therefore,prima-facie appears to emerge that for each shipment
imported by M/s PMC Projects (India) Private Limited where EIF, is the
intermediaryinvoicing agent and M/s Hyundai Heavy Industries Co. Ltd. , South Korea
is the shipper, there are two sets of invoices:-
Page 17 of 97
i) OEM sale invoice of HHICL (Copy of the sale invoice raised by the M/s
Hyundai Heavy Industries Co. Ltd.-Original Equipment Manufacturer-
(OEM) on EIF alongwith corresponding packing list-Invoices raised for
supplies made in pursuance of Agreement No. 700003 dated 05-10-2010
between EIF and HHICL , South Korea)
ii) Intermediaryinvoice of EIF, UAE (Copy of the back-to-back
intermediaryinvoice/packing list raised by EIF on PMC - Invoices raised
for supplies made in pursuance of Agreement 415703 dated 01-10-2010
between PMC and EIF).
Scanned images of two sets of invoices for the same goods (the OEM invoice raised on
EIF and the back-to-back inflated intermediary invoice raised by EIFon PMC)and the
scanned image of the corresponding common Bill of Lading, in respect of one
consignment shipped by HHICL) is reproduced below as illustration:-
Page 19 of 97
Table-7
Comparison of invoice prices: HHICL(OEM) to EIF vis-a-vis EIF to PMC
SR. NO.
BILL OF LADING NO. /DATE PRICE SHOWN IN OEM (HHICL)
INVOICE USD
PRICE SHOWN IN ELECTROGEN
INVOICE (USD)
(d) as % of (c)
DIFFERENCE IN USD
(a) (b) [c] (d) [e] (f)
1 POBUMASMUN120007/29-02-12 781,704.00 3,190,913.12 408% 2,409,209.12
2 HDMD001A/27-10-11 3,476,403.00 15,095,898.67 434% 11,619,495.70
3 11109521110012/01-12-11 613,683.00 2,034,920.44 332% 1,421,237.44
4 11109521110011/01-12-11 924,172.00 2,608,159.99 282% 1,683,987.99
5 POBUMASMUN120006/29-02-2012 1,612,158.00 6,362,219.47 395% 4,750,061.47
6 ESSAPUS12072026/28-07-2012 221,306.00 852,816.04 385% 631,510.04
7 11109521211015/10-12-2012 643,021.00 2,035,000.42 316% 1,391,979.42
8 11109521109013/25-03-2012 1,105,332.00 3,428,993.18 310% 2,323,661.18
9 POBUMASMUN120002/22-01-12 1,740,762.00 6,860,212.97 394% 5,119,450.97
10 HDMUMAOMN1200100/27-08-11 5,165,787.00 20,870,378.66 404% 15,704,591.70
11 HDMD001B/27-10-11 4,469,661.00 19,419,250.35 434% 14,949,589.40
12 CPJQJI96MASMUN01/22-11-11 4,469,661.00 19,395,362.21 434% 14,925,701.20
13 POBUMASMUN120001/22-01-12 3,469,843.00 13,838,633.48 399% 10,368,790.50
14 HDEH002B/31-01-12 4,598,482.00 19,395,362.21 422% 14,796,880.20
15 HDEH002A/31-01-12 4,598,482.00 19,419,250.35 422% 14,820,768.40
16 POBUMASMUN120011/29-02-2012 1,734,013.00 6,954,061.96 401% 5,220,048.96
17 POBUMASMUN120010/29-02-2012 3,468,027.00 13,838,633.48 399% 10,370,606.50
18 POBUMASMUN120008/29-02-2012 1,385,757.00 6,919,316.74 499% 5,533,559.74
19 POBUMASMUN120009/29-02-2012 1,732,196.00 6,919,316.74 399% 5,187,120.74
20 11109521211013/10-12-2012 1,636,376.00 5,187,830.19 317% 3,551,454.19
21 11109521211014/10-12-2012 574,898.66 3,102,860.20 540% 2,527,961.54
22 11109521211012/03-12-2012 472,101.45 2,509,261.93 532% 2,037,160.48
23 HDMUUSOMN1190100/13-08-11 10,364,119.0
0
42,836,611.30 413% 32,472,492.30
24 KECO12020337/03-09-11 1,236,935.00 3,859,806.74 312% 2,622,871.74
25 11109521108011/02-10-11 616,927.00 1,385,993.65 225% 769,066.65
26 CPJQJI96MASMUN02/22-11-11 1,170,895.00 3,751,551.30 320% 2,580,656.30
TOTAL 62282702.11 252072615.79 404.73% 189,789,914.00
4.1.16 From the figures shown in the Table-7 above, it appears that the price
charged by EIF in the back-to-back invoices raised by it on PMC is substantially
higher than the price of invoice of the OEM- M/s Hyundai Heavy Industries Co. Ltd.
EIF appears to have inflated the invoice price of M/s Hyundai Heavy Industries Co.
Page 20 of 97
Ltd. to almost about 4 times on an average and raised invoices with such inflated
prices on PMC.On an average, values in the invoices raised by EIFon PMCappearto
be 400% of the values in the OEM invoice price.It, therefore, appears that the
consignments shipped by the OEM-M/s Hyundai Heavy Industries Co. Ltd., South
Korea, imported into India by M/s PMC Projects (India) Private Limited and cleared on
the strength of invoices raised by EIF had been grossly over-valued. It is apparent
that while the goods were shipped from HHICL (OEM) to PMC in India directly, the
invoices were routed through EIF, who merely acted as an intermediary invoicing
agent for facilitating inflation of invoice value. Given the scale and extent of invoice
inflation, it is apparent that it was with fraudulent intent of siphoning money from
India.
4.1.17 As brought out in para 4.1.3 above, the name of Shri Jatin Shah, as a
representative of EIF was found consistently appearing in majority of the
invoices/packing lists raised by M/s Hyundai Heavy Industries Co. Ltd. , South Korea
on EIF. Ondiscreet enquiries regarding Shri Jatin Shah, whose name was appearing
in many of the OEM invoices/packing lists, as a representative of UAE intermediary
EIF, it was gathered that he was an active member of Adani Group, visiting
Ahmedabad regularly to participate in meetings held by the Adani Group. It was also
gathered that he worked in the capacity of ‘Finance Controller’ for Adani Power
Limited. Accordingly, a summons under Section 108 of the Customs Act, 1962 bearing
F.No. DRI/MZU/CI-224/2013/3928 dated 30-04-2013 (RUD-C/4)was issued seeking
his appearance on 06-05-2013 withall agreements/contracts enteredinto/executed by
the Adani Group or its subsidiaries with the Hyundai Group, based on specific inputs
that the Hyundai Group had in the past signed a contract with the Adani Group for
100 units of high voltage transformers.
4.1.18 M/s Adani Power Limited, vide its reply bearing Ref:
APL/DRI/Mundra/088/RR/2013 dated 06-05-2013 (RUD-D/19),while acknowledging
receipt of the summons in the name of Shri Jatin Shah, informed in the letter that
Shri Jatin Shah was no longer working with them since 2009. They further informed
that Adani Power Limited or its subsidiaries had not entered into any
agreements/contracts with the Hyundai Group. In view of the information provided by
M/s Adani Power Limited, it was confirmed that Shri Jatin Shah, Manager of EIF, at
one point of time in the past was an employee of Adani Power Limited.
4.1.19 Shri Rajiv Rustogi, signatory to the aforesaid letter dated 06-05-2013,
was summoned under Section 108 of the Customs Act, 1962 through summons
issued under F.No. DRI/MZU/CI-224/2013/4112 dated 06-05-2013 (RUD-C/5)to
produce contracts relating to purchase/import of transformers with service records of
Shri Jatin Shah (designation & period when employed), date of relieving and copy of
relieving letter/resignation letter.
4.1.20 Shri Rajiv Rustogi, General Manager (Accounts), through his reply
bearing Ref.APL/DRI/Mundra/xxx/RR/2013 dated 09-05-2013 (RUD-
Page 21 of 97
D/20)responded stating that due to personal reasons, he was unable to remain
present in person. He provided certain information and documents under cover of the
said letter. On import of the transformers by M/s Adani Power Limited or its
subsidiary companies from the Hyundai Group, South Korea, he declared on behalf of
the company that Adani Power Limited or its subsidiaries had not entered into any
agreement/contract for transformers with Hyundai Group, South Korea.
4.1.21 From the employment details of Shri Jatin Shah as provided in the above
said letter, it appears that he worked for M/s Adani Enterprises Limited as Manager
(Finance) in 2002, as Senior Manager (Finance) and Deputy General Manager for
Adani Port Limited between 2003 and 2006, and finally as a General Manager with
Adani Power Limited in 2008 before resigning in August 2009. As per the documents
submitted, it appeared that Shri Jatin Shah submitted his resignation on 19-08-2009,
which was accepted by the company M/s Adani Power Limited on the same day while
communicating to him that he would stand relieved from the services of the company
with effect from 31-08-2009.
4.1.22 It, therefore, appears that M/s Jatin Shah, representative of the Dubai
based firm EIF in the past had been closely associated with the Adani Group by way of
being employed in different capacities in various Adanigroup companies for eight
consecutive years 2002 through 2009.
4.2 DOCUMENTS FROM ICICI BANK LTD (First Lot)
4.2.1 Besides, the Axis Bank Limited, it was gathered that documents relating
to transactions involving invoices raised byEIFonPMC had,inter-alia, been negotiated
through the ICICI Bank Limited, having its branch in the UAE viz. ICICI Bank, DIFC
Branch in Dubai. Accordingly, information was sought from ICICI Bank, DIFC Branch
Dubai, vide letter bearing F.No. DRI/MZU/C.I.-224/2013/3899 dated 30-04-
2013(RUD-C/6), while endorsing a copy thereof to Chief Manager of the ICICI Bank’s
corporate office in Mumbai to co-ordinate in the matter. Since there was no response,
a reminder was sent on 10-06-2013. (RUD-C/7)
4.2.2 The ICICI Bank’s Corporate office in Mumbai forwarded certain
documents under cover of their letter bearing reference no. NIL dated 19-06-2013
(RUD/D-21) as received by them from their DIFC Branch, in Dubai. The documents,
inter-alia, included details of the account held by EIF with their DIFC Branch in
Dubai; KYC (Know Your Customer) verification documents; account opening form;
details of inward and outward remittances into and from the account of EIF; and
certain import/export bills, as described in the letter dated 10-06-2013 of the ICICI
Bank’s DIFC,Dubai branch (RUD/D-22).Documents found relevant to the
investigation are discussed in the following paras.
4.2.3 As per letter dated 26th April 2012(RUD/D-23),written by EIF addressed
to the ICICI Bank Ltd., DIFC, Dubai Branch, the shareholding pattern of EIF was
Page 22 of 97
informed to the Bank. Relevant contents of the letter,apparently signed by Shri Jatin
Shah, are reproduced below :-
“Please find below the shareholding pattern of Electrogen Infra FZE :
i) Electrogen Infra FZE is 100% owned by Electrogen Infra Holding Pvt. Ltd.
ii) Electrogen Infra Holding Pvt. Ltd. is 100% owned by Asankhya Resources
Pvt. Ltd.
iii) Asankhya Resources Pvt. Ltd. is owned by Eagle Holding Ltd., which is a
nominee shareholder in Asankhya Resources Family Trust.
iv) In Asankhya Resources Family Trust, Mr. Vinod ShantilalAdani is the
settler.
From the above information given to the Bank by EIF, it appears that Shri
Vinod ShantilalAdani had a direct control over the activities of EIF through the
Asankhya Resources Family Trust.
4.2.4 Scrutiny of Audited Financial Statements (stated in US Dollars)
including Directors’ Report of ElectroGen Infra Holding Pvt. Ltd. (here-in-after referred
to as ‘EIH’ ) for the year ended 31-03-2011 (RUD/D-24), which contain parallel data
for the year ended 31st March 2010, revealed as under.
i) EIH was incorporated in Mauritius on 16 July 2009 as a private
company.
ii) In the Corporate Data, Shri Vinod Shantilal Shah has been listed as a
Director of EIH with the date of his appointment as Director shown as
12th January 2010. Other directors with their dates of appointment
and resignations are indicated as under :-
Name Appointed Resigned
GiandeoReemul 16 July 2009 08-March 2011
NavindBeeharry 16 July 2009 08 March 2011
Nasser Ali ShabanAhli 16 July 2009 01 October 2009
Chang Chung-Ling 01 October 2009 12 January 2010
Vinod Shantilal Shah 12 January 2010 N/A
Note :Name of Nasser Ali ShabanAhli, who was appointed Director from the
date of incorporation of the company and who resigned few months i.e
on 01-10-2009 before Vinod Shantilal Shah became a Directoron 12-
01-2010,is noteworthy.He was the initial subscriber on 16-07-2009 i.e
when the company was incorporated in Mauritius to the whole of
equity capital of USD 1000 divided into 1000 shares of USD one each
Page 23 of 97
of EIH and was thus the sole share-holder of the company. These
shares were thereafter transferred to Shri Vinod Shantilal Shah on 12-
01-2010, after Shri Vinod Shantilal Shah became the sole share-
holder and owner of EIH. Nasser Ali ShabanAhli was also the initial
subscriber to equity capital of AED 1,50,000 divided into one share of
AED 1,50,000 of M/s Sichuan Machinery &Equipments FZE
(name changed to EIF on 04-01-2010) on 07-07-2009, when the
company was registered in the UAE.The whole of this equity
was transferred and sold to EIH on 29-03-2010 after which EIF
became wholly owned subsidiary of EIH.
iii) The Directors’ Report of EIH appears to have been signed on 30-
05-2011 by Shri Vinod Shantilal Shah by order of the Board of
Director of EIH. Balance Sheet of EIH as on 31stMarch 2011 and
its profit and loss account for the year ended 31st March 2011 was
also approved on 30-05-2011 by Shri Vinod Shantilal Shah on
behalf of the Board of Directors of EIH. Incidentally, Shri Vinod
Shantilal Shah was the only Director of EIH as on 31-03-2011 as
is clear from sub-para (ii) above.
iv) As on 31st March 2010, EIH had paid-up share capital of USD
1000 divided into 1000 shares of one USD each which was
increased to USD 1,00,000 divided into one lakh shares of one
USD each by issue of 99,000 shares of one USD each during the
Financial Year 2010-11.
v) EIH had an investment of USD 40,872 as on 31-03-2010 in shares
of an unquoted company which went upto USD 14,81,390 as on
31-03-2011. This investment was in EIF, which was its wholly
owned subsidiary.
vi) EIH received dividend income of USD 53,850,954 during the
Financial Year 2010-11.Since EIH had investment only in EIF,
which was its wholly owned subsidiary, this dividend income was
also received from EIF only.
4.2.5 Scrutiny of Financial Statements of EIF for the year ended 31st March
2011, which included parallel data for the year ended 31st March 2010, revealed as
under :-
i) EIF was a Free Zone Establishment with limited liability registered in
Sharjah Airport International Free (SAIF) Zone, Sharjah. It was
incorporated on 08-July-2009.
ii) EIF had subscribed, issued and paid-up share capital of AED
1,50,000 divided into one share of AED 1,50,000. The subscribed
issued and paid-up share capital was raised during the financial
Page 24 of 97
year 2010-11 to AED 54,00,000 divided into 36 shares of AED
1,50,000 each.
iii) In the Notes to the Financial Statements, in Note No. 7, it is
mentioned that Share Certificate for share capital as on 31st March
2010 and 31st March 2011 was in the name of EIH. In the Manager’s
Report also, it is mentioned that as on 31st March 2011, the entire
share capital of AED 54,00,000 divided into 36 shares was held by
EIH, Mauritius.
iv) The Manager’s Report as on 31st March 2011 was signed by Shri
Jatin Shah. Financial Statements were also signed by him as
Manager of EIF.
4.2.6 Scrutiny of the application for opening of the account revealed that it was
made on 14-09-2011 signed by two individuals i.e Shri Jatin Shah, an ex-employee of
the Adani Group and Shri MehulJani, both apparently Indian nationals. As per the
business details provided to the Bank while opening of the account, the applicants
had declared nature of their business to be ‘General Trading’ and the country where
major business is carried out as ‘India’. Other information declared in the form was
annual turnover of AED 512 Million. The purpose of opening the relationship was
declared as ‘Loans’(RUD/D-25)
4.2.7 In the Signature Card, the above named two individuals had declared
themselves as Authorised Signatory 1 and Authorised Signatory 2, respectively
(RUD/D-26).Scrutiny of Annexure A to ICICI Bank’s application form (RUD/D-27),
which deals with information relating to Directors, Major Shareholders, Partner etc.,
the name of Shri Jatin Shah was found mentioned as a Director, while the name of
Shri MehulJani was found mentioned as an Authorised Signatory. From the
permanent residential addresses declared by the two individuals representing EIF, it
appears that they were residents of Ahmedabad and Vadodara (earlier Baroda),
respectively.
4.2.8 Scrutiny of a two-page document titled ‘Addendum to Memorandum and
Articles of Association of EIF. Scrutiny of the Addendum reveals that SAIF Zone
authorities have acknowledged the amendment made on 29-03-2010 to the
Memorandum and Articles of Association dated 07-07-2009 of EIF. As per the
amendment, Shri Nasser Ali ShabanAhli, a UAE national holding Passport no.
A1811119, who was the owner of EIF’s entire paid-up share capital of one share of
AED 1,50,000sold, transferred and assigned fully and wholly, the said one share of
EIF to EIH. The Addendum is signed by Shri Vinod Shantilal Shah as representative of
EIH. After execution of the Addendum, EIH has been described as the ‘owner’
substituting Mr. Nasser Ali ShabanAhli. With this sale, transfer and assignment, EIF
became wholly owned subsidiary of EIH with effect from 29-03-2010(RUD/D-28). This
was the second amendment to the Memorandum and Articles Association dated 07-
Page 25 of 97
07-2009 of EIF. The first amendment was made on 04-01-2010 to change name of the
company to EIF (para 4.3.4 below) and the third amendment was made on 17-06-2010
to increase share capital (para 4.4.12 below).
4.2.9 As percopy of‘Share Certificate No. 4107’ dated 21-06-2010 issued by
Government of Sharjah, SAIF Zone, it is certified that EIH,incorporated in the Republic
of Mauritius, is a registered holder of 36 shares of AED 54,00,0000 of EIF which is
stated to be a limited liability establishment incorporated and licensed at SAIF-Zone
with paid-up capital of Dhs 54,00,000 divided into 36 shares with a value of Dhs
1,50,000 each(RUD/D-29).
4.2.10 As per copy of Global Business Licence No. C211017320 dated 21-01-
2011 granted by the Government of the Republic of Mauritius to EIH, it is, inter-alia,
mentioned that the company shall not offer its shares or otherwise raise capital from
the public(RUD/D-30).
4.2.11 Copy of Certificate of Incorporation on Change of Name issued on 08-01-
2010 by the Registrar of Companies, Republic of Mauritius certifies that the name of
M/s Sichuan Machinery & Equipment Import & Export Co. Ltd have by special
resolution changed its name and is now incorporated under the name of M/s
ElectroGen Infra Holding Pvt. Ltd(RUD/D-31).
4.3 DOCUMENTS FROM BANK OF BARODA
4.3.1 Bank of Baroda, Dubai Main Branch,vide their letter Ref. No. CE:
Compliance:1612/2013 dated 05-11-2013 (RUD/D-32),referring to DRI’s letter
bearing F.No. DRI/MZU/CI-224/2013/3928 dated 30-04-2013 therein, forwarded
documents pertaining to EIF’s transactions to their corporate office located at Bandra-
Kurla Complex, Mumbai, which were retrieved by the officers of DRI on 18-11-2013.
4.3.2 These documents included, inter-alia, account opening form with related
documents and statement of account in respect of the USD account bearing no.
90010200008259held by EIF with BOB, Bur Dubai Branch. The above account was
initially opened on 06-07-2009 in the name of Sichuan Machinery and Equipments
FZE. As per copy of Memorandum and Articles of Association made on 07-07-2009 at
SAIF Zone, UAE, this company was incorporated with Shri Nasser Ali ShabanAhli, a
UAE national, as the ‘owner’ holding the entire authorised and paid-up capital of one
share valued at AED 1,50,000 (RUD/D-33). The Bank was authorised to honour
cheques/bills of exchange and promissory notes drawn, accepted or made on behalf of
the company singly byShri Nasser Ali ShabanAhli. As per the copy of the Licence
Certificate issued by SAIF Zone authorities on 07-07-2009(RUD/D-34)the company
was licensed for ‘general trading’.
4.3.3 Perusal of copy of document titled ‘Board Resolution of M/s Sichuan
Machinery &Equipments FZE dated 19th November 2009’ (RUD/D-35) reveals that the
purpose of the resolution was to open and operate accounts with any bank in the UAE
Page 26 of 97
in the name of M/s Sichuan Machinery &Equipments FZE, and to avail all types of
banking facilities in the company’s name. It was resolved, inter-alia, to add the name
of Shri Jatin Shah, holder of Indian Passport No. H3015351, as an the authorized
signatory in the bank accounts of M/s Sichuan Machinery &Equipments FZE;to
authorise Shri Jatin Shah to open, operate & close banking accounts with any bank of
the UAE and authorized to sign singly on Bank Mandate documents relating to use of
electronic distribution channels, undertakings, indemnity/security
documents/guarantees/agreements and any Finance Documents on behalf of the
Company excepting cheques and cheque book request forms which could only be
signed by Mr. Naseer Ali Shaban Ali singly. Accordingly, specimen signature card with
specimen signature of Shri Jatin Shah, stating that he could operate the account
singly, was submitted to the bank on 21-11-2009(RUD/D-36).
4.3.4 As per copy of Addendum to the Memorandum and Articles of
Association dated 07-07-2009 of EIF, an amendment made on 04-01-2010 to the
Memorandum and Articles of Association was acknowledged by SAIF Zone
authorities(RUD/D-37).As per the amendment, name of the company was changed
from Sichuan Machinery &Equipments FZE to EIF with same owner i.e. Shri Nasser
Ali ShabanAhli. This Addendum (amendment) to the Memorandum and Articles of
Association dated 07-07-2009 of EIF is immediately prior to the second Addendum as
discussed in para 4.2.8 above. Accordingly, SAIF Zone authorities also changed the
name of the Licence holder in the Licence Certificate no. 01-01-07314 on 14th January
2010 (RUD/D-38).EIF also intimated change of name to BOB, Bur Dubai vide its letter
dated 04-02-2010(RUD/D-39).
4.3.5 From the facts narrated above, it is evident that day to day work relating
to Sichuan Machinery &Equipments FZE was being handled by Shri Jatin Shah, (an
employee of Adani Group till 31-08-2009), since November 2009 even before the
company was taken over on 29-03-2010 by Shri Vinod ShantilalShah through EIH.
4.3.6 The documents processed by Bank of Baroda, Bur Dubai for and on
behalf of EIF were examined. Scrutiny revealed that these contained copies of certain
invoices and packing lists raised,inter-alia, by the some China based firms, who
appeared to be OEMs, on EIF towards the sale of certain goods. Each such
invoice/packing list was found to be accompanied by copy of a bill of lading,
apparently the corresponding bill of lading pertaining to shipment of the goods covered
by theOEM invoice/packing list, as could be reasonably inferred from the name of the
OEM raising the invoice whose name also appears as the ‘shipper’ in the
corresponding bill of lading found accompanying the invoice. On the basis of
commonalities appearing in the invoices, an OEM-wise summary is tabulated below:-
Table-8
Summary of invoices raised by three OEMs(Dalian, Sediver& Suzhou) on EIF
Page 27 of 97
Sr.No.
Name of the OEM-firm
raising the invoice/ packing list
Brief Description
of goods as per OEM invoice raised on
EIF
Description of the project for which
goods are meant as declared in the invoices
Contract/ Agreement No.
declared in the invoices
Notifying party as appearing in
the BL accompanying the invoice
Total Number of
distinct consignments for which
invoices available
1 Dalian
Insulator Group Co. Ltd, China
Disc
Insulators
2 nos. of 765KV S/C
(Quad Bersimis) Tiroda-Koradi-III-Akola II-Aurangabad Transmission Lines.
700002 dated 07-
10-2010
M/s PMC
Projects (India) Pvt. Ltd., Mundra Port, Navinal Islands, Mundra-
370 421
8
2 Sediver Insulators
(Shanghai) Co. Ltd., China
Toughened Glass Disc
Insulator
2 nos. of 765KV S/C (Quad Bersimis)
Tiroda-Koradi-III-Akola II-Aurangabad Transmission Lines.
700001 dated 07-10-2010
M/s PMC Projects (India)
Pvt. Ltd., Mundra Port, Navinal Islands, Mundra-370 421
9
3 Suzhou Furukawa Power Optic
Cable Co. Ltd. , China
OPGW with 8 Fibre with fittings &
accessories
2 nos. of 765KV S/C (Quad Bersimis) Tiroda-Koradi-III-
Akola II-Aurangabad Transmission Lines.
700004 dated22-10-2010
M/s PMC Projects (India) Pvt. Ltd., Mundra
Port, Navinal Islands, Mundra-370 421
8
TOTAL 25
4.3.7 From the data given in Table-8 above, it appears that in the case of 25
consignments, the transactions of sale/procurement by and between the respective
OEMs and EIF appear to have been negotiated through Bank of Baroda.
4.3.8 From analysis of the contents of the OEM documents, it prima-facie
appears that the Bank of Baroda, Bur Dubai Branch has facilitated its customer EIF
in the transactionsrelating to purchase/procurement of goods from the respective
OEMs viz. the transactions with M/s Dalian Insulator Group Co. Ltd. and M/s
SediverInsulators (Shanghai) Co. Ltd. for procurement/purchase of insulators, and the
transactions with Suzhou Furukawa Power Optic Cable Co.Ltd., China,for
procurement/purchase of OPGW cable, OPGW hardware and accessories. The services
of the Bank (Bank of Baroda, Bur Dubai) appear to have been,inter-alia, utilized by
EIF for remitting the value of the goods as per invoices raised on it by the respective
OEM firms.
4.3.9 Amongst other documents submitted by Bank of Baroda, Bur Dubai were
copies of Letters of Credit (L/Cs) opened by Bank of Baroda, Bur Dubai on behalf of
the applicant i.eEIF favouring the three OEM firms, whose names have been indicated
as the ‘Beneficiary’ in the SWIFT messages pertaining to such Letters of Credit. Such
L/Cs appeared to cover a fixed lump sum amount, apparently representing money
payable by EIF to the respective OEM towards goods supplied to PMC. The Letters of
Credit further,inter-alia, invariably indicate the name of M/s PMC Projects (India)
Private Limited as the ‘Notifying party’or ‘Notified Party’ thereby implying that the
goods were for supply to M/s PMC Projects (India) Private Limited. The Letters of
Credit were also found to make a mention of an Agreement no. (Agreement Numbers
reflected in Table 8 above against the name of respective OEMs were found mentioned
in the copy of the related letter of credit) purported to be Agreement executed by EIF
with the respective OEMs.
Page 28 of 97
4.3.10 The price payable by EIF to the OEMs towards goods supplied by the
three OEMs, respective OEM invoice-wise, has been tabulated below in respect of the
25 shipments, summarised at Table-8 above, on the basis of documents negotiated
through Bank of Baroda, Main Branch, as obtained by this Unit :-
Table-9
Invoice Price of goods as per invoices raised by three OEMs (Dalian Insulator
Group Co. Ltd., Sediver Insulators (Shanghai) Co. Ltd. and M/s Suzhou Furukawa
Power Optic Cable Co. Ltd. China) on Electrogen Infra FZE, UAE
S. No.
BILL OF LADING No. /DATE SHIPPER AS PER B.L.
SHIPPER INVOICE NO. /DATE VALUE (USD)
1
MAEU601299135
/09-02-2011 DALIAN INSULATOR GROUP CO. LTD EG11009/06-01-2011 605250
2 NDACVF300 / 15-02-2011
SEDIVER INSULATORS (SHANGHAI) CO. LTD.
FP09022011/ 09-02-2011 463342
3 YMLUZ245202791 /05-04-2011 DALIAN INSULATOR GROUP CO. LTD EG11053/ 06-01-2011 1253880
4
APLU062194693
/31-03-2011 DALIAN INSULATOR GROUP CO. LTD EG11067/ 18-03-2011 536176.8
5 YMLUZ230140405 /31-03-2011
SUZHOU FURUKAWA POWER OPTIC CABLE CO. LTD. , CHINA SE110325/ 25-03-2011 85177.3
6 YMLUZ230145416/28-04-2011
SEDIVER INSULATORS (SHANGHAI) CO. LTD.
FP23042011/ 23-04-2011 794944.8
7 YMLUZ230148714/12-05-2011
SUZHOU FURUKAWA POWER OPTIC CABLE CO. LTD. , CHINA SE110509/ 09-05-2011 185491.65
8
YMZUZ230162786
/22-07-2011
SEDIVER INSULATORS (SHANGHAI)
CO. LTD. FP15072011/15-07-2011 794944.8
9 KKLUSH4220867/04-09-2011
SUZHOU FURUKAWA POWER OPTIC CABLE CO. LTD. , CHINA SE110817/17-08-2011 438181.3
10 MSCUY5709319/ 02-09-2011
SEDIVER INSULATORS (SHANGHAI) CO. LTD.
FP260822011/26-08-2011 794944.8
11 MSCUDL744655 /11-11-2011 DALIAN INSULATOR GROUP CO. LTD EG11217/19-10-2011 751500
12 YMLUZ230190641/30-12-2011
SEDIVER INSULATORS (SHANGHAI) CO. LTD. FP23122011/23-12-2011 794944.8
13 NDAEHH600 / 13-12-2011
SEDIVER INSULATORS (SHANGHAI) CO. LTD. FP16122011/16-12-2011 794944.8
14 NDAEHH600/ 13-12-2011
SUZHOU FURUKAWA POWER OPTIC CABLE CO. LTD. , CHINA SE111207/07-12-2011 333245.16
15
MSCUDL786284/
28-01-2012 DALIAN INSULATOR GROUP CO. LTD EG12001/04-01-2012 775350
16 MSCUDL815422/ 30-03-2012 DALIAN INSULATOR GROUP CO. LTD EG12015/24-02-2012 1091250
17 YMLUZ245204311/04-05-2012 DALIAN INSULATOR GROUP CO. LTD EG12047/23-04-2012 537477.3
18
YMLUZ230223990
/28-06-2012
SEDIVER INSULATORS (SHANGHAI)
CO. LTD. FP21062012/21-06-2012 715500
19 YMLUZ245204378/23-06-2012 DALIAN INSULATOR GROUP CO. LTD EG12094/18-05-2012 387576
20 YMLUZ230241803/14-09-2012
SEDIVER INSULATORS (SHANGHAI) CO. LTD. CHINA FP06092012/06-09-2012 766857.6
21 YMLUZ230256175 /22-11-2012
SUZHOU FURUKAWA POWER OPTIC CABLE CO. LTD. , CHINA SE121116/16-11-2012 194125.39
22
YMLUZ230259583
/06-12-2012
SEDIVER INSULATORS (SHANGHAI)
CO. LTD. CHINA FP03122012/03-12-2012 911250
Page 29 of 97
23 YMLUZ230260792/13-12-2012
SUZHOU FURUKAWA POWER OPTIC CABLE CO. LTD. , CHINA SE121210/10-12-2012 391512.37
24 YMLUZ230269660/17-01-2013
SUZHOU FURUKAWA POWER OPTIC CABLE CO. LTD. , CHINA SE130111/11-01-2013 329586.44
25 YMLUZ230277098/28-02-2013
SUZHOU FURUKAWA POWER OPTIC CABLE CO. LTD. , CHINA SE130224/24-02-2013 211576.02
TOTAL 14939029.33
4.3.11 Since the name of M/s PMC Projects (India) Private Limited
appearedunder the column ‘Notify Party’ invariably in each of above listed bills of
lading pertaining to individual shipments by the respective OEMs, efforts were made
to identify the import particulars for each such consignment i.e to ascertain the bill of
entry no. & date and port of import, from the particulars available on individual bill of
lading. Examination revealed that the aforesaid bills of lading were the bills of lading
pertaining to 25 consignments (Sr.No. 1 to 25 of Table-3A) imported and cleared by
PMC Projects (India) Private Limited, as evident from the same bill of lading numbers
featuring in the table-3A, which provides details of consignments imported and cleared
by M/s PMC Projects (India) Private Limited as per the EDI data base.
4.3.12 It, therefore, appears that while the importer utilized the above-listed
bills of lading for customs clearance purpose in India, the value for the purpose of
assessment appears to have been declared on the basis of back-to-back invoices
raised separately by EIF on M/s PMC Projects (India) Private Limited. The respective
OEM invoices and packing lists do not appear to be part of the documents produced
by PMC to the jurisdictional customs authorities in India, on the strength of which
cargo appears to have been assessed and cleared, as was also the case with
procurements by EIF from M/s Hyundai Heavy Industries Co. Ltd.
4.3.13 It, therefore,prima-facie appears to emerge in the case of these
transactions also that for each shipment imported by M/s PMC Projects (India) Private
Limited where EIF is the intermediary invoicing agent and one of three OEMs is the
shipper, there are two sets of invoices:-
i) OEM sale invoices of the three OEM firms (Copies of the sale invoices
raised by each of the three OEMs viz. M/s Dalian Insulator Group Co.
Ltd., M/s Sediver Insulators (Shanghai) Co. Ltd. and Suzhou Furukawa
PowerOptic Cable Co.Ltd., China, onEIF along-with corresponding
packing lists-)
ii) Intermediary invoices of EIF, UAE (Copies of the back-to-back
intermediary invoices/packing lists raised by EIF on M/s PMC Projects
India Private Limited)-Invoices raised for supplies made in pursuance of
Agreement 415703 dated 05-10-2010 between PMC and EIF.)
Page 30 of 97
4.3.14 A comparison of prices between the two sets of invoices is tabulated
below for better appreciation of scale and extent of price difference:-
Table-10
Comparison of invoice prices: Three OEMs to EIF vis-a-vis EIF to PMC
SR. NO.
BILL OF LADING NO. /DATE PRICE SHOWN IN OEM
INVOICE USD
PRICE SHOWN IN ELECTROGE
N INVOICE (USD)
[D] AS % OF [C] DIFFERENCE IN USD
(A) (B) [C] [D] [E] [F]
1 MAEU601299135 /09-02-2011 605250 4270200 706 3664950
2 NDACVF300 / 15-02-2011 463342 3269009.3 706 2805667.28
3 YMLUZ245202791 /05-04-2011 1253880 8846304 706 7592424
4 APLU062194693 /31-03-2011 536176.8 3783025.2 706 3246848.4
5 YMLUZ230140405 /31-03-2011 85177.3 989736 1162 904558.7
6 YMLUZ230145416/28-04-2011 794944.8 5608544.6 706 4813599.84
7 YMLUZ230148714/12-05-2011 185491.65 2499741.2 1348 2314249.55
8 YMZUZ230162786/22-07-2011 794944.8 5608544.6 706 4813599.84
9 KKLUSH4220867/04-09-2011 438181.3 4563413.6 1041 4125232.32
10 MSCUY5709319/ 02-09-2011 794944.8 5608544.6 706 4813599.84
11 MSCUDL744655 /11-11-2011 751500 5302000 706 4550500
12 YMLUZ230190641/30-12-2011 794944.8 5608544.6 706 4813599.84
13 NDAEHH600 / 13-12-2011 794944.8 5608544.6 706 4813599.84
14 NDAEHH600/ 13-12-2011 333245.16 5356134.5 1607 5022889.32
15 MSCUDL786284/ 28-01-2012 775350 5470280 706 4694930
16 MSCUDL815422/ 30-03-2012 1091250 7699000 706 6607750
17 YMLUZ245204311/04-05-2012 537477.3 3792053.8 706 3254576.54
18 YMLUZ230223990/28-06-2012 715500 5048000 706 4332500
19 YMLUZ245204378/23-06-2012 387576 2734564 706 2346988
20 YMLUZ230241803/14-09-2012 766857.6 5410356.4 706 4643498.8
21 YMLUZ230256175 /22-11-2012 194125.39 2438920 1256 2244794.61
22 YMLUZ230259583/06-12-2012 911250 6429000 706 5517750
23 YMLUZ230260792/13-12-2012 391512.37 4956776 1266 4565263.63
24 YMLUZ230269660/17-01-2013 329586.44 4285010.4 1300 3955423.96
25 YMLUZ230277098/28-02-2013 211576.02 2830412.2 1338 2618836.18
14939029.33 118016659.6 858.46% 103077630.27
4.3.15 From the figures shown in Table-10 above, it appears that the price
charged by EIF in the invoices raised by it on M/s PMC Projects (India) Private Limited
is substantially higher than the price for corresponding shipments charged by these
OEMs. The invoice price of the respective OEMs appears to have been grossly inflated
in the back-to-back invoice raised by EIF on M/s PMC Projects (India) Private Limited.
It, therefore, appears that consignments shipped by the respective OEMs and imported
into India by M/s PMC Projects (India) Private Limited on the strength of grossly
inflated invoices raised by EIF had been cleared by resorting to gross over-valuation.
It is apparent that while the goods were shipped from the respective OEMs to PMC in
India directly, the invoices were routed through EIF, who merely acted as an
intermediary invoicing agentfor facilitating invoice inflation. The modus-operandi can
be diagrammatically described as under:-
Page 34 of 97
Given the scale and extent of invoice inflation and the relationship, it is apparent that
it was done with fraudulent intent of siphoning of public money from India.
4.3.16 Scrutiny of OEM invoices raised by the above named three OEMs on EIF,
it was observed that many of the OEM invoices contained references to certain
Agreement Numbers and dates, which were found to be distinct for each OEM raising
the invoice as shown below :-
Table-11
Details of Agreements between the three China based OEMs and EIF
Sr.No. Name of the OEM Agreement no. found mentioned in the OEM
invoices
1. Sediver Insulators (Shanghai) Co. Ltd., China
Agreement No. 700001 dated 07-10-2010
2. Dalian Insulator Group Co Ltd. Agreement No. 700002 dated 07-10-2010
3. Suzhou Furukawa Power Optic Cable Co. Ltd. , China
Agreement No. 700004 dated 22-10-2010
It appeared that the Agreement Numbers, referred in the OEM invoices as
above,were the Agreements executed by the respective OEMs with EIF. Supplies under
the respective OEM invoices apparently were being made in pursuance of these
Agreements.
4.3.17 On request, Axis Bank, DIFC Bank, Dubai, vide their letter bearing
Ref.No. AXIS/DIFC/55/2013-14 dated 10-04-2014 (RUD-D/40)forwarded,interalia,
bank attested photo-copies of each of the three Agreements referred to in the Table-11
above.
4.3.18 Key particulars of the respective Agreements in terms of description,
quantity and contract price as available in these Agreements are tabulated below :-
Table-12
Summary of Agreements between the three China based OEMs with EIF in terms
of description, quantity and value of goods
S.No Agreement No. /date
Executing parties to the contract
Item No.
Description of goods
Quantity (Nos.) Agreement value/consideration in USD
1 2 3 4 5 6 7
8 700001/ 07-10-2010
Sediver Insulators (Shanghai) Co. Ltd., China and
EIF
i)
120 KN Toughened
glass disc insulators
248299 Nos.
5938460.1
ii)
210 KN Toughened
glass disc insulators
341622 Nos.
Page 35 of 97
2 700002/
07-10-2010
Dalian Insulator
Group Co Ltd and EIF
i)
120 KN Toughened
glass disc insulators
248299 Nos.
5938460.1
ii)
210 KN Toughened
glass disc insulators
341622 Nos.
3 700004/ 22-10-2010
Suzhou Furukawa Power Optic Cable Co. Ltd. ,
China and EIF
i) OPGW with 8 Fibre
1272 KMS.
2637757
ii) Fitting and
accessories 341622
TOTAL 14514569.20
4.3.19 Each of these Agreements were found to make a mention of an
Agreement dated 01-10-2010 between the contractor and employer, designated as
PMC Projects (India) Private Limited and EIF thereby clearly enabling inference that it
referred to Agreement No. 415703 dated 01-10-2010 between the two parties.
Therefore, a scrutiny was done to examinethe scope of the goods described in the three
Agreements vis-à-vis those mentioned in the said Agreement 415703 dated 01-10-
2010 between PMC and EIF which revealed that the description and quantity of
different types of disc insulators and OPGW with hardware& fittings mentioned in the
three Agreements with OEMs were covered at Sr.No. 5 to 8 in the table appended at
clause 3.02.1 in the said Agreement between PMC and EIF as tabulatedbelow :-
Table-13
Table appended at clause 3.02.1 of Agreement No. 415703 dated 01-10-2010
between PMC and EIF
S No. Item Description Quantity (Nos) Commencement Period
Delivery/ Completion
Period
1 765/400 KV, 500 MVA Single Phase Auto Transformers
7 - Oct 2011
2 765/400 KV, 500 MVA Single Phase Auto Transformers
8 - Dec 2011
3 765 KV, 80 MVAR, Single Phase Shunt Reactors 7 - Oct 2011
4 765 KV, 80 MVAR, Single Phase Shunt Reactors 43 - Dec 2011
5 120 KN Disc Insulators for 2 Nos. 765 KV S/C
Transmission Lines.
496598 Jan 2011 Nov 2011
6 210 KN Disc Insulators for 2 Nos. 765KV S/C Transmission Lines
688244 Jan 2011 Nov 2011
7 OPGW along with Hardware’s and fittings for 765 KV S/C Transmission Line.
636 KM Jan 2011 Oct 2011
8 OPGW along with Hardware’s and fittings for 765 KV
S/C Transmission Line.
636 KM Jan 2011 Dec 2011
4.3.20 An aggregate of the same type of insulators covered by the two OEM
Contracts (Sr.No. 1 & 2) shown in Table-12above match with the figures of the same
type of insulators as shown at Sr.No. 5 and 6 of Table-13 inasmuch as in respect of
120 KN Toughened glass disc insulators at Sr.No.1(i) + 2(i) of Table-12, quantity works
out to 248299 + 248299 =496598- which is the same as the quantity shown at Sr.no 5
of Table-13 and in respect of 210 KN Toughened glass disc insulatorsat Sr.No. 1(ii) +
2(ii) of Table-12, quantity works out to 341622 + 341622 = 688244, which is same as
Page 36 of 97
the quantity shown at Sr.No. 6 of Table-13 above.The quantity of OPGW shown at
Sr.No. 3(i) of Table-12 matches with the aggregate of quantities shown at Sr.No. 7 & 8
(636+636=1272) of Table-13 above.
4.3.21 It, therefore, appears evident that the description and quantity of the
scope of supplies covered by the three OEM-Agreements with EIFshown at sr.no. 1, 2&
3 of Table-12above are identically covered in terms of description and quantity, for
supply under Agreement No. 415703 dated 01-10-2010 between PMC and EIF (Table-
13 above)
4.3.22 A comparison of the value of the same set of goods, with identical
description and quantity, indicated as consideration in two different sets of
agreements reveal gross disparity at the contract level as shown in the table below :-
Table-14
Contract Price as per Agreements between PMC & EIF vis-à-vis the Agreements
between EIF & the three OEMs (Sediver, Dalian & Suzhou)
S.No Description of goods Price as per Agreement No.
415703/ 01-10-2010 as per
break-up given at Schedule 1
Price Schedule Summary
Sheet (USD)
Price as per
OEM
Agreements
(USD)
Difference
(USD)
(C) as % of
(D)
(A) (B) (C) (D) (E) (F
1. Disc Insulators (120 KN
+ 210 KN)
Sub-total of C
(C.I + CII)
83,794,854 11,876,920.2 71,917,933.8 705.53%
2 Optical Fiber Ground
Wire with hardware and
accessories
Sub-total D 32,131,000 2,637,757 29,495,243 1218.12%
NOTE: - Scanned Copy of Price Schedule Summary Sheet of the Agreement no.
415703 Dt. 01-10-2010 between PMC and EIF is at para 13.1 below
4.3.23 It appears that Disc Insulators supplied at an aggregate cost of USD
11876920.2 by the two OEMsi.eM/s Sediver Insulators (Shanghai) Co. Ltd., China and
Dalian Insulator Group Co Ltd. China, and OPGW hardware and accessories for USD
2,637,757/- from M/s Suzhou Furukawa Power Optic Cable Co. Ltd. , Chinawere to
be invoiced to PMC under Agreement No. 415703 dated 01-10-2010 at contract value
consideration of USD 83,794,854 and USD 32,131,000 which works out to approx.
705.53% & 1218.12% of the corresponding OEM prices, respectively.
4.4 KYC DOCUMENTS FROM AXIS BANK (Second Lot)
4.4.1 Axis Bank, DIFC Branch, Dubai submitted certain documents vide their
letter bearing Ref.No. AXIS/DICF/1229/2013-14 dated 18th December 2013 (RUD-
D/41). It was, inter-alia, conveyed by the bank in its letter that EIF held a current
Page 37 of 97
account bearing no. 912020200000514 opened on 20-07-2010 and that EIH was the
parent company of EIF. The documents forwarded by the bank included copies of
account opening form alongwith supporting KYC documents submitted by EIF; copies
of the bank account statement since inception of the account till 12-12-2013 and copy
of the shareholding pattern of EIF. Documents relevant to the investigation are
discussed in the following paras.
4.4.2 As per Section I for stating Client Details, Analysis &Consent Form, EIF
have declared the name of Bank of Baroda, Bur Dubai, Main Branch as their principal
bankers. In the information provided regarding accounts held with other banks, they
have declared the names of Bank of Baroda and Standard Chartered Bank. With
regard to the declaration of their business activity, it was declared that it was a new
company and incorporated with the object of trading in power equipment.
Regarding the declaration on source of funds, EIF has declared that their promoter
was EIH, who would be bringing equity as and when required from their own
sources. On the reason for applying for opening of the account, they have declared
“asset handling”. The application appears to have been signed by Shri Jatin Shah on
10-07-2010(RUD/D-42).
4.4.3 As per Section II for details of Authorised Signatory/Director/Beneficial
Owner, the name and other personal details of Shri Vinod Shah and Shri Jatin Shah
were found declared. While employment details in terms of occupation and corporate
title were not filled in for Shri Vinod Shah, Shri Jatin Shah’s occupation was declared
as ‘service’ and his corporate title as ‘Manager’(RUD/D-43).
4.4.4 As per resolution dated 10-07-2010 of the Board of Directors of EIF,
available in the records of the bank, it was resolved that a bank account be opened in
the name of EIF and Shri Vinod S Shah &Shri Jatin C Shah be designated as
authorized signatories to operate the account and sign documents without any
limit(RUD/D-44).
4.4.5 From letter dated 10-07-2010 of EIF addressed to Axis Bank, it is
certified by Shri Jatin Shah as Chief Financial Officer of EIF that Shri Vinod Shantilal
Shah, Shri Moreshwar V. Rabade and Shri Jatin C Shah were Directors of
EIF(RUD/D-45).
4.4.6 The documents included a copy of the Licence Certificate No. 01-01-
07314 dated 14-01-2010 issued to EIF by SAIF Zone authorities, which was also
found in the records of the documents pertaining to Bank of Baroda, Bur Dubai (para
4.3.4 above)(RUD/D-46).
4.4.7 As per copy of Resolution dated 19-05-2011 passed by the Board of
Directors of EIF, it was resolved, inter-alia, that Shri Vinod Shah wasauthorized to
operate the account of EIF singly without any limit and that any two of the three
persons viz. Shri Jatin Shah, Shri MehulJani and Shri MiteshJani, could operate the
account jointly without any limit (RUD/D-47)
Page 38 of 97
4.4.8 As per letter dated 14-10-2012 submitted by EIF to Axis Bank, Shri Jatin
Shah and Shri Moreshwar V Rabadehad been certified as Directors of EIF (RUD/D-
48).
4.4.9 In letter dated 23-10-2012 addressed to the Bank, EIF informed the
Bank about the resignation of Vinod Shantilal Shah as a Director of their holding
company-EIH w.e.f. 31-05-2011(RUD/D-49).
4.4.10 In another letter dated 23-10-2012 addressed to the Bank, EIF has
confirmed the names of Shri Jatin Shah, Shri MehulJani and Shri MiteshJani as the
authorized signatories of EIF and the names of its directors as Shri Jatin Shah and
Shri MoreshwarRabade. This letter also reitereated that 100% of the equity capital of
EIF was held by EIH(RUD/D-50).
4.4.11 Copies of the amended License Certificates issued by SAIF Zone
authorities as of 07-08-2012 and 19-06-2013 show EIF as a firm engaged in “general
trading” activity & owned by EIH with Shri Jatin Shah as the manager(RUD/D-51).
EIF was also holding a Trading Licence issued by Jumeirah Lake Tower authorities
bearing Licence No. JLT-65859, as a Branch office, having address Unit N. 2707,
Jumeirah Business Center 5 Plot No.W1, Jumeirah Lakes Towers, Dubai, United Arab
Emirates(RUD/D-52). The copy of the said Trading Licence shows Shri Jatin Shah as
the Manager and activity undertaken by the company as Trading in Equipment related
to power lines, ports and transmission lines.
4.4.12 The documents include copy of the Addendum to the Memorandum &
Articles of Association dated 07-07-2009 of EIF. Vide this addendum, SAIF Zone
authorities acknowledged amendment made on 17-06-2010 to the Memorandum &
Articles of Association of EIF for increasing the share capital from AED 1,50,000 to
AED 54,00,000(RUD/D-53). The Addendum was signed by Shri Vinod Shantilal Shah
as a representative of EIH. This is the third Addendum to the Memorandum &
Articles of Association of EIF dated 07-07-2009, the other two being dated 04-01-2010
for change of name and 29-03-2010 for transfer of ownership as discussed at para
4.3.4 and 4.2.8 above respectively.
4.4.13 The documents include a copy of Register of Members of EIH certified on
25-01-2010 by Shri GiandeoReemul, for and on behalf of Trustlink International
Limited, Company Secretary(RUD/D-54). A scanned image of the Register of Members
is shown below for ease of appreciation
Page 40 of 97
4.4.14 Perusal of the Register of Members shows that on 16-07-2009 i.e the
date when EIH was incorporated in Mauritius, 1000 shares of USD 1 each (which was
the entire authorised and paid-up capital of EIH as on 16-07-2009) with distinctive
numbers from 0001 to 1000 were allotted to Nasser Ali Shaban Ahli. The same shares
were transferred on 01-10-2009 from Nasser Ali Shaban Ahli to Chang Chung Ling
and further transferred to Shri Vinod Shantilal Shah on 12-01-2010.
4.5 Documents from ICICI Bank Limited (2nd Lot)
4.5.1 In response to letter dated 27-03-2014, ICICI Bank, Singapore through
letter dated 02-04-2014 (RUD/D-55)conveyed that they had provided Advance
Payment Guarantee (APG) facility to EIF; that EIF did not accept and that the facility
was, therefore, not availed by EIF. The Bank also conveyed that no documents had
been lodged by EIF with the Singapore Branch. Therefore, the issue was taken up and
pursued with officials of ICICI Bank’s corporate office at Bandra Kurla Complex,
Mumbai. ICICI Bank, vide their letter dated 07-04-2014 (RUD-D/56),forwarded
certain documents, which appeared to be documents submitted by EIF to the Bank
authorities while applying for the APG facility. Documents relevant to this
investigation are discussed in the following paras.
4.5.2 From the documents forwarded by the Bank, it appeared that while
applying for APG facility, EIF had provided on 09-04-2010 a background of itself in a
document titled ‘Brief Background’(RUD-D/57),wherein they hadstated that the
company was established with SAIF Zone in July 2009 in the name and style of
Sichuan Machinery and Equipments FZE and with effect from 04-01-2010, the name
was changed to EIF.
4.5.3 In the said documents, EIF also disclosed to the bank on 09-04-2010
that it is a wholly owned subsidiary of EIH, registered in Mauritius,owned by Shri
Vinod Shantilal Shah. The names of Shri Vinod S Shah, Shri M.V.Rabade and Shri
Jatin Shah have been mentioned as Board Members of EIF.
4.5.4 ICICI Bank further submitted certain documents vide their letter
dated16-04-2014(RUD/D-58)which included a document titled ‘Details of Director’
provided by EIF to them at their specific insistence(RUD/D-59). Thisdocument
provides names and other particulars of Shri Jatin Champaklal Shah and Shri
Moreshwar Vasant Rabade, as Directors of EIF.MoreshwarVasantRabade appears to
be full name of ‘M.V.Rabade’ listed as one of members of the Board of Director of EIF
in the document titled ‘Brief Background’ referred to at the foregoing paragraph 4.5.2
above. The documents also include a certificate dated 01-06-2010 by Shri Jatin Shah
as Chief Financial Officer of EIF certifying that as on that date, Shri Vinod Shantilal
Shah, Shri Moreshwar V.Rabade and Shri Jatin C. Shah were members of the Board
of Directors of EIF(RUD/D-60).
Page 41 of 97
5.0 Visit to the offices of Adani Group companies in Ahmedabad and
summones issued to various persons of the group including those connected
with EIF.
5.1 The supplier on record for many of the Adani Group companies including
PMC was the UAE based firm EIF, which appear related to the Adani Group as
brought out elsewhere in this notice. Efforts were, therefore, made to obtain
documents covering transactions between EIF and overseas based OEMs/actual
suppliers, in the case of shipments where the goods were eventually supplied to one or
more of the Adani Group entities. The officers of MZU visited offices of the following
group entities of the Adani Group in Ahmedabad office on or about 25-09-2013, in an
attempt to procure OEM/actual supplier documentation with EIF under the
reasonable belief that such documents would be stored in the said offices. Shri Nayan
Rao, Vice President, Corporate Affairs, of the Adani Group voluntarily came forward
and agreed to co-operate with the officers during the course of their visit by supplying
the documents required by DRI. During the course of their visit, the officers visited
the following premises accompanied by Shri Nayan Rao, Vice President of the Adani
Group and directed him to produce specific documents required by them in exercise of
the power conferred by Section 107 of the Customs Act, 1962:-
i) M/s Adani Power Limited, Achalraj Building, Ahmedabad
ii) M/s Adani Enterprises, Adani House
iii) M/s Adani Enterprises, Shikhar Building
iv) Adani Group’s server room, Fortune House.
5.2 Certain documents/electronic data as specified in the visit report dated
25-09-2013, (RUD/C-8) were handed over by Shri Nayan Rao, Vice President, in co-
ordination and consultation with concerned officials at the above offices, to the officers
of DRI during the course of their visit, in response to the requisition under Section 107
of the Customs Act, 1962. However, documents pertaining to transactions between
EIF and one or more overseas based OEMs/actual suppliers and other entities, in the
form of OEM/actual supplier invoices and/or copies of agreements/contracts between
the OEM and EIF were not produced on the ground of non-availability.
5.3 Summons bearing F.No. DRI/MZU/C.I.-224/2013 (RUD/C-4) under
Section 108 of the Customs Act, 1962 was issued in the name of Shri Jatin Shah, who
is described variously as authorised signatory, Manager, Chief Financial Officer and
Director of EIF, to his known addresses, seeking his presence on 14-10-2013 to give
evidence and produce specific documents listed at Annexure A to the said summons,
relevant extracts of which are produced below :-
1. Self attested copies of all the agreements/contracts entered into with
various overseas based original equipment manufacturers/entities/firms
for sourcing of goods of foreign origin from them for eventual supply/sale
Page 42 of 97
to M/s PMC Projects (I) Pvt. Ltd, India and/or one or more firms of the
Adani Group based in India.
2. Self attested copies of the invoices raised on your firm (M/s Electrogen
Infra FZE), by overseas firms/entities in respect of goods supplied/to be
supplied to M/s PMC Projects (I) Pvt. Ltd, India and/or one or more firms
of the Adani group based in India.
3. Details of the payments made to various foreign firms/entities against
procurements from them invoice-wise in respect of goods eventually
supplied to M/s PMC Projects (I) Pvt. Ltd, India and/or one or more firms
of the Adani group based in India
4. Name and address of the bank and branch through which
remittances/payments referred to at sr. no. 3 were made.
5.4 M/s Electrogen Infra FZE, UAE, vide a letter bearing reference no. NIL
dated 11-10-2013 (RUD-D/61)forwarded by FAX, responded in acknowledgement of
the summons stating that Shri Jatin Shah was on his annual leave and they would
revert on his return.
5.5 Another summons was issued under F.No. DRI/MZU/C.I.-224/2013
dated 15-10-2010, (RUD-C/4) under Section 108 of the Customs Act, 1962 seeking
his presence on 28-10-2013 to give evidence and produce specific documents as per
Annexure A to the summons. Summonses under Section 108 of the Customs Act,
1962 were also issued in the names of the two Indian nationals Shri Mitesh Dani and
Shri Mehul Jani, who appeared to be working for EIF in the UAE, seeking their
appearance on 29-10-2013 and 30-10-2013 (RUD-C/9),respectively, with documents
in respect of the activities of EIF.
5.6 EIF in its response dated 28-10-2013 (RUD/D-62), sent via Fax,
acknowledged the summons issued in the names of three of its employees viz. Shri
Jatin Shah, Shri Mitesh Dani and Shri Mehul Jani. As per the letter, Shri Jatin Shah,
who was claimed to be aware of the matter, was stated to be on leave. The letter
further stated that he was expected to join duty by the end of November 2013 and that
they would revert accordingly.
5.7 Since none of the employees of EIF responded to the summons seeking
their appearances on various dates, summons bearing F.No. DRI/MZU/CI-224/2013
under Section 108 of the Customs Act, 1962 was issued in the name of Shri Vinod
Shantilal Shah, (sole shareholder and Director of the parent company of EIF viz. M/s
Electrogen Infra Holding Pvt. Ltd. and promoter shareholder in Adani Enterprises
Limited) to his known addresses seeking his presence on 11-11-2013 (RUD/C-10)with
specific information/documents listed at Annexure A to the said summons. Details of
the information/documents sought from him at Annexure A is identical to the
information sought from Shri Jatin Shah and other employees of EIF in Annexure A
Page 43 of 97
annexed to the summons issued to them, relevant contents of which are as
reproduced at para 5.3 above.
5.8 In response to the summons, Shri Vinod Shantilal Shah forwarded a
letter dated 11-11-2013 (RUD-D/63) by fax. In the said response, he stated that he
was neither a Director nor a Shareholder of the said company i.e.EIF at any point of
time. He further stated that he was the Director in Electrogen Infra Holdings Pvt. Ltd,
Mauritius, (holding company of EIF ) for the period from January, 2010 to May, 2011;
that as a director of the parent company, he was not involved in the business of EIF or
day to day operations thereof. In view of these submissions, he further stated that he
did not have access to the records of EIFand that he would not be in a position to
submit/furnish/provide the details/documents sought by DRI. He concluded the
letter by making a request to withdraw the summons issue in his name.
5.9 In view of his response, another summons bearing F.No. DRI/MZU/CI-
225/2013 dated 11-11-2013 (RUD-C/10) was issued to Shri Vinod Shantilal Shah
seeking his presence on 18-11-2013. He was informed that he had been empowered to
sign any documents for and on behalf of EIF as per Resolution passed the Board of
Directors of EIFon or about 19-05-2011. It was accordingly conveyed that by virtue of
the said resolved capacity as ‘Authorized Signatory’ for EIF, he was liable to honour
the summons by appearing on the designated date and time with the
information/documents requisitioned from him.
5.10 In response thereto, Shri Vinod Shantilal Shah while acknowledging
receipt of the said summons, inter-alia, conveyed vide his letter dated 18-11-2013
(RUD/D-64), that he had ceased to be the Director of M/s Electrogen Infra Holding
Pvt. Ltd., Mauritius (parent company of EIF) more than two years ago; that he,
therefore, was not in possession of the documents required by DRI, and that he had
noticed that the DRI had directly written to EIFalso for providing necessary
documents/information. With regard to the Board Resolution, he stated that since he
did not have access to the records of EIF, he was not aware about which Resolution
the DRI was referring to. He requested for being provided with a copy of the resolution
to enable him to revert.
5.11 From his response, it was observed that Shri Vinod Shantilal Shah did
not produce any evidence to refute the documented fact that he had been empowered
to sign any documents for and on behalf of EIFas per Resolution passed the Board of
Directors of EIFon or about 19-05-2011, Under the circumstances, and in view of his
resolved capacity as Authorized Signatory for and on behalf of EIF it appeared that he
was liable to honor the summons issued by the DRI. Accordingly, while conveying
these aspects to him, another summons bearing F.No. DRI/MZU/CI-224/2013 dated
20-11-2013 (RUD/C-10) was issued seeking his presence on 27-11-2013 with specific
information/documents which were specified at Annexure A to the summons. Since
Shri Vinod Shantilal Shah failed to appear on the designated date and time, yet
another summons bearing DRI/MZU/CI-224/2013 dated 29-11-2013, (RUD/C-10)
seeking his presence on 09-12-2013 was issued.In a letter bearing reference no. Nil
Page 44 of 97
dated 05-12-2013 (RUD/D-65), received via Fax, Shri Vinod Shantilal Shah, while
acknowledging the receipt of both the summonses dated 20-11-2013 and 29-11-2013,
stated that he had forwarded the said summonses to EIF and that the DRI should deal
with the said company directly. In the letter, he reiterated the stand taken by him in
his letter dated 11-11-2013, stating that he was not in possession of any of the
requisitioned documents. He requested that the matter may be taken up directly with
the company and that DRI should not send any further correspondence to him.
5.12 In response to the summons issued to Shri Jatin Shah, Shri MiteshDani
and Shri MehulJani of EIF on 20-11-2013 and 29-11-2013, Shri Jatin Shah forwarded
a letter dated 09-12-2013 (RUD/D-66), by fax. In context of the information sought
from each of them under the summons, he submitted, inter-alia, that EIF owned by
Electrogen Infra Holdings Pvt. Ltd., Mauritius, was a free zone establishment with
limited liability based in Sharjah Airport International Free Zone and that they had
been advised by local lawyers in the UAE that parting with any of the
information/details/documents to authorities outside UAE would constitute breach of
the UAE laws. He concluded by stating that since the information/documents sought
by the DRI contained highly confidential commercial/business information, EIFwould
not be able to part with any such information/details/documents.
5.13 Summons under section 108 of the Customs Act, 1962 were again issued
to Shri Vinod Shantilal Adani and Shri Jatin Shah on 10-12-2013 (RUD/C-10 & C-4)
seeking their presence on 17-12-2013. Summons were also issued on the same day i.e
10-12-2013 in the name of Shri Mitesh Dani and Shri Mehul Jani, seeking their
presence on 18-12-2013. (RUD-C/9) Since they failed to present themselves and join
the investigation, fresh summons were issued to Shri Vinod Shantilal Adani and Shri
Jatin Shah on 20-12-2013 (RUD/C-10 & C-4) seeking their presence on 27-12-2013
and to Shri Shri Mitesh Dani and Shri Mehul Jani on 20-12-2013, seeking their
presence on 30-12-2013 (RUD/C-9).
5.14 A summary of the summons issued from time to time to Shri Vinod
Shantilal Shah and employees of EIFis tabulated below :-
Table-14 A
List of summonses issued to officials of M/s Electrogen Infra FZE, UAE
S.No
Name of official of Electrogen Infra FZE, UAE summoned
F.No. under which summons issued
Date of issue of summonses and designated date for remaining present with information/documents requisitioned
1. Shri Vinod Shantilal Shah
F.No.DRI/MZU/C.I.-224/2013 30-10-2013 for appearance on 11-11-2013 11-11-2013 for appearance on 18-11-2013 20-11-2013 for appearance on 27-11-2013
29-11-2013 for appearance on 09-12-2013 10-12-2013 for appearance on 17-12-2013 20-12-2013 for appearance on 27-12-2013
2. Shri Jatin Shah F.No.DRI/MZU/C.I.-224/2013 30-04-2013 for appearance on 06-05-2013
26-09-2013 for appearance on 14-10-2013 15-10-2013 for appearance on 28-10-2013 11-11-2013 for appearance on 18-11-2013
20-11-2013 for appearance on 27-11-2013 29-11-2013 for appearance on 09-12-2013 10-12-2013 for appearance on 17-12-2013 20-12-2013 for appearance on 27-12-2013
3. Shri Mitesh Dani F.No.DRI/MZU/C.I.-224/2013 15-10-2013 for appearance on 28-10-2013
Page 45 of 97
11-11-2013 for appearance on 19-11-2013 20-11-2013 for appearance on 28-11-2013
29-11-2013 for appearance on 10-12-2013 10-12-2013 for appearance on 18-12-2013 20-12-2013 for appearance on 30-12-2013
4. Shri Mehul Jani F.No.DRI/MZU/C.I.-224/2013 15-10-2013 for appearance on 28-10-2013 11-11-2013 for appearance on 19-11-2013 20-11-2013 for appearance on 28-11-2013 29-11-2013 for appearance on 10-12-2013
10-12-2013 for appearance on 18-12-2013 20-12-2013 for appearance on 30-12-2013
5.15 Despite repeated summons, the aforesaid persons failed to present
themselves to join investigations and also failed to furnish information/documents
that were requisitioned from them, on one plea or the other.
5.16 Investigations revealed that Vinod Shantilal Shahis another name of
Vinod Shantilal Adani (one of the promoter and shareholders in flagship company of
the Adani group viz. M/s Adani Enterprises Ltd.) as is evident from contents of copy of
a letter dated September 13, 2012 (RUD/D-67) addressed to, inter-alia, the Bombay
Stock Exchange Limited and the National Stock Exchange of India Limited regarding
disclosure under Regulation 31 of the SEBI (Substantial Acquisition of Shares and
Takeovers) Regulations, 2011. The said letter and its annexure have been signed by
Shri Vinod Shantilal Adani clearly stating, inter-alia, that Vinod Shantilal Adani is
also known as Vinod Shantilal Shah. Scanned image of the said letter and
disclosure page is reproduced below :-
Page 47 of 97
5.17 It is further gathered that Shri Vinod Shantilal Adani, is one of the five
sons of Late Shri Shantilal Adani, his other brothers being Shri Mahasukhbhai S.
Adani, Shri Vasantbhai S. Adani, Shri Gautambhai S.Adani, and Shri Rajeshbhai S.
Adani. Each of the brothers of the Adani family holdssubstantial stake in the flagship
company of the Adani Group i.e M/s Adani Enterprises Limited.
6.1 Scrutiny of the signatories to Agreement no. 700003 between EIF and
HHICL dated 05-10-2010also revealed that the Agreement had been signed by,
inetralia,Shri Dharmesh Parekhfor and on behalf of EIF. An enquiry into his personal
details revealed that the said Shri Dharmesh Parekh was working in the capacity of a
Senior Manager with PMC at Ahmedabad.
6.2 Accordingly,Shri Dharmesh Arvindbhai Parekh, Senior Manager of M/s
PMC Projects (India) Private Limited, was summoned and his statement was recorded
under Section 108 of the Customs Act, 1962 on 10-12-2013(RUD-S/1).
6.2.1 In his statement he,inter-alia, stated that he joined a company named
M/s Adani Energy Limited in the year 2005 in the capacity of Assistant Manager
(Finance and Accounts) where he worked for about three years until 2008; that by the
timehe left, he had been elevated to the level of Deputy Manager (Finance and
Accounts).
6.2.2 He further stated that he joined M/s PMC Projects India Private Limited
in the year 2008 as Deputy Manager (Finance and Accounts); that at the material
time, he was still with M/s PMC Projects India Private Limited, working there in the
capacity of Senior Manager (Finance and Accounts); that as Senior Manager (Finance
and Accounts), he was responsible for maintenance of accounts for the Tiroda Project;
that their company (PMC Projects India Private Limited) was into two types of work viz.
Project Management &Consultancy services and execution of Engineering,
Procurement and Commissioning (EPC) contracts; that M/s PMC Projects India Private
Limited was engaged in handling the Tiroda thermal power project (5 x 660 MW) as a
part of Project management and consultancy services. He further divulged that they
(PMC) had been awarded a contract by M/s Powergen Infrastructure LLC, Dubai for
execution of Tiroda power project. In terms of Board Resolution passed by M/s
Powergen Infrastructure LLC, Dubai, he had been authorised to represent and sign on
behalf of the said Dubai based firm. During the course of the said statement, he
undertook to produce a copy of the said Board Resolution within a week’s time.
6.2.3 He further divulged that as a part of execution, the company provided
management and consultancy services for procurement of Balance of Plant (BOP)
supply, Balance of Plant (BOP) services and Boiler Turbine Generator (BTG) services.
He further stated that he reported to Shri Jaydev Mishra who was the Deputy General
Manager at M/s PMC Projects India Private Limited.
6.2.4 On being specifically questioned regarding details of his travel abroad, he
stated that he never travelled out of India at any point of time till date, though
Page 48 of 97
he held a passport issued to him by the Ahmedabad Passport office. He undertook to
produce a photo-copy of all the pages of his passport within a week’s time.
6.2.5 On being specifically questioned whether he had been a signatory to any
contracts/agreements/like documents on behalf of M/s PMC Projects, he stated that
he had never signed any Contract and/ or Agreement or any like documents on behalf
of M/s PMC Projects India Private Limited or any other firm/entity of the Adani group
or any overseas firm/entity, supplier or vendor barring the signatures made by him for
and on behalf of M/s Powergen Infrastructure LLC, Dubai.
6.2.6 During the course of his statement he was questioned if he had been
authorised to discharge responsibility on behalf of any other firm/entity other than
M/s PMC Projects India Private Limited at any point of time. He was also questioned if
he had been in possession of any such authority during his employment with M/s
PMC Project India Private Limited. In response thereof, Shri Dharmesh Arvind Parekh
stated that he had never been authorised to discharge responsibility on behalf of any
other firm/entity other than M/s PMC Projects India Private Limited at any point of
time and that he had never been in possession of any such authority during his
employment with M/s PMC Project India Private Limited.
6.2.7 During the course of his statement, he was asked to peruse a copy of the
Agreement bearing No. 700003 dated 05-10-2010 between EIF, a firm having its
registered office in the Sharjah, UAE and M/s Hyundai Heavy Industries Co. Ltd.,
having registered office at Seoul in South Korea. Upon perusal thereof, he was
requested to confirm whether the signature appended at page 4 of the Agreement
happened to be his signature. He was also specifically asked if he had signed the said
Agreement for and on behalf of EIF. Pursuant to perusal of contents of Agreement
no. 700003 between EIFand M/s Hyundai Heavy Industries Co. Ltd, South Korea,
shown to him, he confirmed that the signature appearing at page 4 belonged to
him and he had indeed signed the said Agreement. He also admitted to have put
his initials on every page at the place of the Agreement and its schedules, where-
ever the round seal of EIF was found affixed.
6.2.8 He put his dated signatures as well as his initials on every page of the
Agreement including its Schedule 1, Schedule 1A, Schedule 1B and Schedule 1C in
token of having carefully perused the signatures and initials appearing thereon. He
also put his dated signatures and initials on a copy of the bare Agreement no. 700003
running into five pages, which bears the original stamp/seal of Axis Bank, DIFC
Branch, Dubai and signature of the authorised official of the Bank.
6.2.9 On being questioned about the reason and the authority for having
signedAgreement no. 700003, for and on behalf of EIF, he stated that at the material
juncture, he was unable to recollect the circumstances under which he had signed to
the said Agreement bearing number 700003 between EIFand M/s Hyundai Heavy
Industries Co. Ltd, South Korea. He, however promised to revert within a week’s time
Page 49 of 97
and explain the reason as well as the circumstances for having signed the aforesaid
Agreement.
7.1 Vide letter bearing F.No.DRI/MZU/CI-224/2013 dated 20-12-2013
(RUD/C-11), a request was made to the Adani Group for submission of self-attested
copies of the Memorandum of Association and the Articles of Association together with
self-attested copies of the Balance Sheets with all theirSchedules and appendices for
the last three financial years in respect of select Adani Group entities including M/s
PMC Projects (India) Private Limited.
7.2 PMC,inter-alia, responded by providing the requisitioned details vide
their letter dated 08-01-2014(RUD-D/68).From scrutiny of the documents submitted,
it appeared that initially M/s Project Monitoring Construction Limited, situated at 44,
St. George Street, Port Louis, Republic of Mauritius held the shares of PMC Projects
(India) Private Limited as of 27th April 2005. Subsequently, as per information
declared in the financial statements for the year ending 31-03-2013, it appeared that
M/s PMC Projects (India) Private Limited was a wholly owned subsidiary of M/s PMC
Infra Limited (formerly known as M/s Gudami International (Mauritius) Limited. Since
no details were available with regard to the constitution and ownership of the holding
companyi.e M/s PMC Infra Limited, Mauritius, summons under Section 108 was
issued in the name Shri Mayur Shah, Finance Controller of M/s PMC Projects (India)
Private Limited seeking his presence for submission of Memorandum and Articles of
Association of the holding company of PMC i.e M/s Project Monitoring Construction
Limited, Republic of Mauritius subsequently known as PMC Infra Limited. Summons
under Section 108 was also issued in the name of Shri Dharmesh Parekh, Senior
Manager of M/s PMC Projects (India) Private Limited, who had failed to provide
information/documents as undertaken by him in his statement recorded on 10-12-
2013.(Para 6.2)
8.1 Shri Mayur Shah failed to appear on 03-02-2014 in response to the
summons and, therefore, another summons seeking his appearance on 13-02-2014
was issued in his name to produce documentation relating to the holding company of
M/s PMC Projects (India) Private Limited in response to which he appeared before this
office on the designated date.
8.1.1 In his statement recorded under Section 108 of the Customs Act, 1962,
on 13-02-2014(RUD-S/2), Shri MayurKiritkumar Shah,inter-alia, stated that he was a
qualified Chartered Accountant; that he joined M/s PMC Projects (India) Private
Limited, a foreign subsidiary owned by M/s PMC Infra Mauritius in February 2008,
that he joined the company as an Assistant Vice President; that he was responsible for
accounting and port related projects; that he worked with M/s PMC Projects (India)
Private Limited till August 2012 and that when he left, he held the position of
Associate Vice President.
Page 50 of 97
8.1.2 He,inter-alia, stated that he joined the Adani Group in September 2012
in their company Adani Ports and SEZ Limited as Associate Vice President and that he
was responsible for the company’s initiative for process transformation and IT
automation.On being asked about his inability to honor the earlier summons issued to
him requiring his presence on 3rd February 2014, he admitted to having failed to
honour the said summons. He also admitted to having failed to communicate or
convey any reasons for his inability to honour the summons.
8.1.3 On being asked to produce the information/documents called for under
the summons dated 07-02-2014, he responded by stating that he had requested Shri
Kumar Vikram, Director of M/s PMC Projects (I) Pvt. Ltd and since Shri Kumar Vikram
had expressed his inability to provide the requisitioned documents, he in turn has not
been in a position to provide the requisitioned documents.
8.1.4 On being asked about the parent company of M/s PMC Projects (I) Pvt.
Ltd., he deposed that PMC Projects (I) Pvt. Ltd was a 100% subsidiary of M/s PMC
Infra Limited, Mauritius. On being asked about the transmission project undertaken
by M/s PMC Projects (I) Pvt Ltd., he explained that PMC Projects (I) Pvt. Ltd. had
bagged a tender floated by Maharashtra Eastern Gujarat Power Transmission
Company Ltd. (MEGPTCL)., a wholly owned subsidiary of M/s Adani Enterprises,
under the International Competitive Bidding process for development of two
transmission lines in the corridor of Tiroda-Koradi-Akola-Aurangabad, as an
Engineering, Procurement, Construction (EPC) Contractor.
8.1.5 He further deposed that M/s PMC Projects (I) Pvt. Ltd., for execution of
the said contract, appointed contractors and placed orders for procurement of
materials and services including supply of offshore equipments (imported equipments);
that for the import of offshore equipments, orders were placed with EIF through
nomination basis on the directions of the then Director and CEO, Shri Arvind
Uplenchwar.
8.1.6 He further stated that PMC received transferable Letters of Credit (LC)
opened by State Bank of India, Ahmedabad Branch, covering supply of imported goods
for the transmission line project; that the applicant was MEGPTCL and the Letters of
Credit had been opened in favour of PMC in foreign currency i.e in US Dollars. On
being further asked to specify the contractual terms under which M/s MEGPTCL
opened the Letters of Credit in foreign currency (USD) in favour of PMC, in the light of
the fact that both these were local Indian companies, he assured to revert with
complete details on 17-02-2014.
8.1.7 On being questioned regarding the financing of the said project by M/s
PMC Projects (I) Pvt. Ltd., while stating that the setting up of the project involved both
imported as well as indigenous sourcing of goods and services, he disclosed that M/s
PMC Projects (I) Pvt. Ltd. had not raised any funds for the said project. He further
explained that as and when the supply was to take place from the supplier for
Page 51 of 97
imported equipments, PMC received transferable LCs in USD from MEGPTCL, which
were transferred in favour EIF.
8.1.8 On being specifically asked, regarding the possibility of any consortium
partner of M/s PMC Project (I) Pvt. Ltd. for supply of imported components for the said
transmission line project, he responded by stating that EIFwas the consortium partner
for supply of imported equipments. On being specifically asked to re-confirm whether
EIFhad jointly made a bid to MEGPTCL alongwith PMC as an EPC consortium partner
or as a consortium partner for supply of imported equipments, he stated that he
would revert with the correct position on 17-02-2014. On being further specifically
asked if EIFwas a consortium partner, and whether there was any consortium
agreement existing between PMC and EIFhe stated that a consortium agreement
between the PMC and other consortium partners had been executed and was in
existence. He undertook to produce a self-attested copy of the said consortium
agreement on 17-02-2014.
8.1.9 In view his deposition that a consortium agreement had been executed,
he was questioned about the need and reasons for having executed a separate
Agreement between PMC and EIFto supply imported equipments to MEGPTCL. In
response thereof, he expressed his inability to answer and stated that Shri Jaidev
Mishra would be able to provide an answer to the said query.
8.1.10 On being questionedwhether he had been privy to the supply
agreements and/or consortium agreements in the backdrop of the fact that he had
been authorised by M/s PMC Projects (I) Pvt. Ltd. to open Letters of Credit in favour of
EIFfor supply of imported equipments to the transmission line project, he deposed
that he had not been privy to the supply agreements and/or consortium agreements
and that applications for the LCs signed/made by him had been done on the
instructions of Shri Jaydev Mishra, who was stated to be aware of the modalities of the
purchase agreement.
8.1.11 On being asked tore-confirm that he had signed bank documents
associated with application/opening of the LCs in favour of EIFon behalf of PMC,as an
applicant, without looking into the basic documents such as contract / consortium
agreement / purchase order involving these parties, he stated that he did not recollect
having signed any bank documents associated with application/opening of the LC in
favour of EIFon behalf of PMC as an applicant.
8.1.12 Under the circumstances of Shri Mayur Shah not being
awareabout the value of supply of individual equipments nor being aware of the
contents of the purchase order/ contract/consortium agreement, he was to explain
the basis for indicating the value at the time of application /opening of LCs, to which
he reiterated stating that he had never signed any application or documents for
opening of the LCs.
8.1.13 In his capacity of beinghead of the finance department, he was
asked to confirm whether LC opening application was processed by the department
Page 52 of 97
under his charge and whether he had been privy to any LC applications in any
manner,heresponded by stating that the LC applications were processed by his
department but he was not privy to the LC applications. He requested for permission
to leave on the undertaking that he would appear on 17-02-2014 to continue with his
statement.
8.2 Shri Mayur Shah appeared on 17-02-2014 as undertaken and his
further statement was recorded under Section 108 of the Customs Act, 1962 (RUD-
S/3).
8.2.1 During his statement he produced a notarised copy of the Consortium
Agreement dated 16th August 2010 between PMC, EIFand M/s Hyundai Heavy
Industries Co. Ltd for tender specification no. MEGPTCL/765 KV ^ 400 KV
SS/EPC/02 which he tendered under his dated signature. He also produced a
notarised copy of the document titled ‘Power of Attorney for Lead Member’ executed
and signed on 16-08-2010 by PMC , EIFand M/s Hyundai Heavy Industries Co. Ltd.
He undertook to produce the original in their possession within a week’s time.
8.2.2 On being asked to identify the signatory for and on behalf of EIF who
had signed the ‘Consortium Agreement’ and ‘Power of Attorney for Lead
Member’, he confirmed that the signatures thereon belonged to Shri Dharmesh
Parekh, Senior Manager of PMC, who had signed as an authorized signatory for
EIF.
8.2.3 During the course of his statement, he was asked to go through a copy of
an agreement No. 700003 dated 5th October 2010 between EIFand M/s Hyundai
Heavy Industries Co. Ltd., South Korea for transformers, shunt reactors & other
equipments. After having done so, he was requested to identify and confirm the
person who has signed the said agreement as signatory on behalf of EIF. He was also
requested to specify the project for which the said agreement had been executed. In
response thereof Shri Mayur Shah perused copy of the Agreement between EIFand
M/s Hyundai Heavy Industries Co. Ltd. , South Korea, shown to him. He endorsed his
dated signature on each page of the Agreement in token of having read and having
perused its contents.
8.2.4 He, thereafter, proceeded to explain that the said Agreement was for the
transmission line project in the corridor of Tiroda-Koradi-Akola-Aurangabad for which
contract had been awarded to PMC by M/s MEGPTCL. After careful perusal of the
schedule to the above Agreement, he confirmed that the scope of supply of equipments
and technical specifications thereof for the transmission line project of Tiroda-
Koradi-Akola-Aurangabad as covered in the schedule to the said Agreement was the
same as covered in the Agreement between EIFand PMC in so far as it related to the
supply of transformers and shunt reactors (excluding the supply of OPGW cables and
Disc Insulators). After a careful perusal of the signatory to the said Agreement, he
confirmed that his subordinate Shri Dharmesh Parekh had signed the Agreement
Page 53 of 97
no. 700003 dated 05-10-2010 for and on behalf of EIFin the capacity of an
authorized signatory.
8.2.5 During the course of his statement, he was shown seven print-outs
containing tabulated charts. These charts,inter-alia, contained details of the
consignments imported by PMC from EIF, where back-to-back OEM invoices raised by
the four OEMs on EIFwere available. The prices appearing in the OEM invoices were
tabulated against individual bills of entry for 57 consignments imported and cleared
by PMC on the strength of inflated invoices raised by EIF. He was asked to go through
tabulated data in the seven pages which reflected details of 57 consignments shipped
by variousOEMs which had been imported by PMC on the strength of invoices raised
by EIF. He was also shown photo copies of the Bills of Lading and the invoices of the
respective OEMs as detailed at columns 6 and 9 of the tabulated sheets, alongwith
their respective packing lists, individually for each of the 57 consignments. After
goingthrough the tabulated data in the seven sheets giving details of 57 consignments
shipped by various OEMswhich were said to have been imported by M/s PMC Projects
(I) Pvt. Ltd. on the strength of invoices raised by EIF, he confirmed that the said
consignments had been imported by PMC and had been customs cleared on the
strength of invoices raised by EIF. He proceeded to put his dated signatures on copy of
each bill of lading and invoice of the respective shippers i.e. M/s Hyundai Heavy
Industries Co. Ltd., South Korea; Sediver Insulators (Shanghai) Co. Ltd., China;
Suzhou Furukawa Power Optic Cable Co. Ltd. , China; and Dalian Insulator Group Co
Ltd. China, details of which were appearing at column no. (6) and (9) of the tabulated
charts and also on the corresponding packing lists after comparing particulars as
appearing therein with the details mentioned in the tabulated sheet in token of having
carefully perused relevant contents thereof. He also put his dated signature on copy
of the Agreement bearing no. 700003.
9.0 Statement of Shri Jaydev Ramdatt Mishra, Associate General Manager, of
M/s PMC Projects (India) Private Limited, was recorded under Section 108 of the
Customs Act, 1962 on 17-02-2014(RUD-S/4).
9.1 In his statement, he,inter-alia, stated that he joined the Adani Group in
their company M/s Adani Power Limited as a Manager in the year 2007; that as a
Manager, he used to handle contracting work relating to various projects to be
executed by M/s Adani Power Limited and that he had handled work relating to
Mundra Project.
9.2 He further stated that sometime in the year 2008 end, he joined the
company M/s PMC Projects (I) Pvt. Ltd as a Senior Manager; that he was responsible
for contracting work i.e contracts and contract management which included
identifying overseas suppliers, formulation and signing of various contracts for
projects to be executed by M/s PMC Projects (I) Private Limited and monitoring the
execution of such projects to the extent of sourcing of equipments and machinery
required to execute such projects; that at the material time when he joined the
company, two persons by name Shri A.M.Uplenchwar and Shri Vinod George were the
Page 54 of 97
Directors; that he was promoted as Deputy General Manager and, thereafter, as
Associate General Manager; that he was presently working as an Associate General
Manager; that the company was engaged in setting up two transmission lines in the
corridor of Tiroda-Koradi-Akola-Aurangabad for which it has been awarded a turnkey
contract by M/s Maharashtra Eastern Grid Power Transmission Company Limited
(MEGPTCL); that orders for sourcing all the imported goods for the transmission line
project were placed on a company named EIFfor which M/s PMC Projects (I) Pvt. Ltd.
entered into agreement in respect of equipments for sub-stations; that some of the
imported equipments were also to be procured from M/s ABB Limited for which they
had entered into a separate contract with them; that he was associated with
formulation and execution of agreements with M/s Electrogen Infra FZE, UAE and
M/s ABB Limited; that he was also a signatory for these agreements on behalf of M/s
PMC Projects (I) Pvt. Ltd.
9.3 On being specifically questioned regarding Shri Dharmesh Parekh, he
stated that Shri Dharmesh Parekh was the Senior Manager of M/s PMC Projects (I)
Pvt. Ltd. and was presently working with them; that he knew Dharmesh Parekh as an
employee of M/s PMC Projects (I) Pvt. Ltd. since the year 2008 and that Shri
Dharmesh Parekh used to report to him.
9.4 On being asked to explain whether Shri Dharmesh Parekh had the
authority or power to sign documents/agreements/contracts on behalf of various
companies including foreign entities in the background of local Indian laws of
employment, he stated that he was not aware whether Shri Dharmesh Parekh had any
authority or power to sign on behalf of various companies including foreign entities.
9.5 On being asked about the parent holding company of M/s PMC Projects
(I) Pvt. Ltd., its structure and composition, he had to state that M/s PMC Infra
Limited, based in Mauritius, was at the material time their parent company. He
admitted that he was not aware of the structure or composition of M/s PMC Infra
Limited even though he held a responsible position.
9.6 On being asked whether he had signed any documents/agreements or
contracts for or on behalf of PMC, he stated that he had not signed any documents on
their behalf. On being asked whether he held any power of attorney or the status of
authorized signatory for any other company, he stated that he had never held power of
attorney nor was he the authorized signatory for any other company (other than PMC )
at any point of time during his tenure with PMC. On being specifically asked about
any power of attorney or authorization for or on behalf of MEGPCTL, including any
banking documents, he stated that he never held power of attorney nor was he the
authorized signatory for any other company (other than PMC) at any point of time
during his tenure with PMC.
9.7 During the course of his statement, he was shown a copy of Agreement
No. 700003 dated 5th October 2010 between EIFand M/s Hyundai Heavy Industries
Co. Ltd. , South Korea for supply of transformers, shunt reactors & other equipments.
Page 55 of 97
He was requested to identify and confirm the name of the person who has signed the
said Agreement as signatory on behalf of M/s Electrogen Infra FZE, UAE. He was also
requested to specify the project for which the said Agreement had been executed. After
perusing the copy of Agreement shown to him during the course of his statement, he
endorsed his dated signature on each page of the said agreement shown to him, in
token of having read and having perused its contents. He explained that the said
Agreement was for the transmission line project in the corridor of Tiroda-Koradi-Akola-
Aurangabad for which contract had been awarded to M/s PMC Projects (India) Private
Limited by M/s MEGPTCL for which he had been a signatory.
9.8 After careful perusal of the schedule to the above Agreement, he
confirmed that the scope of supply of equipments and technical specifications thereof
for the transmission line project of Tiroda-Koradi-Akola-Aurangabad as covered in the
schedule to the said Agreement was the same as covered in the Agreement between
EIFand M/s PMC Projects (I) Pvt. Ltd. in so far as it related to the supply of
transformers and shunt reactors (excluding the supply of OPGW cables and Disc
Insulators). After careful perusal of the signatory to the said Agreement, he
confirmed that his subordinate Shri Dharmesh Parekh had signed the Agreement
no. 700003 dated 05-10-2010 for and on behalf of EIFin capacity of an
authorized signatory.
9.9 During the course of his statement, he was shown seven print-outs
containing tabulated charts, which had been shown to Shri Mayur Shah, during the
course of his statement on the same day (para 8.2). He was asked to go
throughtabulated data in the seven pages which reflected details of 57 consignments
shipped by various OEMs which had been imported by M/s PMC Projects (I) Pvt. Ltd.
on the strength of invoices raised by EIF. He was also shown photo copies of the bills
of lading and the invoices of the respective OEMs as detailed at columns 6 and 9 of the
tabulated sheets alongwith their respective packing lists, individually for each of the
57 consignments. After goingthrough the tabulated data in the seven sheets giving
details of 57 consignments shipped by various OEMs which were imported by PMC on
the strength of invoices raised by EIF, he confirmed that the said consignments had
been imported by PMC and had been customs cleared on the strength of invoices
raised by EIF. He proceeded to put his dated signatures on copies of each bill of lading
and invoice of the respective shippers i.e. M/s Hyundai Heavy Industries Co. Ltd.,
South Korea; Sediver Insulators (Shanghai) Co. Ltd., China; Suzhou Furukawa Power
Optic Cable Co. Ltd. , China and ; Dalian Insulator Group Co Ltd. China, details of
which were appearing at column no. (6) and (9) of the tabulated charts and also on the
corresponding packing lists after comparing particulars as appearing therein with the
details mentioned in the tabulated sheets in token of havingcarefully perused relevant
contents thereof. He also put his dated signature on the copy of the Agreement
bearing no. 700003.
10.0 Another statement of Shri Dharmesh Arvindbhai Parekh was recorded
under Section 108 of the Customs Act, 1962 on 28-02-2014(RUD-S/5).
Page 56 of 97
10.1 He was specifically asked to state whether he had signed any documents
in the nature of Contracts/Deeds/Agreements/Power of Attorney/Purchase Orders or
like documents for and on behalf of EIFas an authorised signatory, at any point of
time in his employment with M/s PMC Projects (I) Private Limited. Shri Dharmesh
Parekh stated that besides, the Agreement No. 700003 dated 05-10-2010
between EIF and M/s Hyundai Heavy Industries Co. Ltd., to which he had been a
signatory for and on behalf of EIF, he had also been a signatory to additional
documents which he described as under :-
i) Consortium Agreement dated 16-10-2010 executed by and between
PMC,EIF and M/s Hyundai Heavy Industries Co. Ltd., in relation to the
transmission line project awarded to his company (PMC Projects) by M/s
Maharashtra Eastern Grid Power Transmission Company Limited
(MEGPTCL) involving sourcing of imported capital equipment/goods i.e
auto transformers, shunt reactors etc. from Hyundai Heavy Industries
Co. Ltd. for supply to their company (PMC) through EIF.
ii) Power of Attorney for Lead Member executed by and between EIF, M/s
Hyundai Heavy Industries Co. Ltd., South Korea and PMC as Lead
Member in relation to the aforesaid power transmission project.
He admitted that he had signed the aforesaid documents for and behalf of EIF as an
authorised signatory. He further divulged that in addition to the above documents, he
was also a signatory to Agreements/Contracts executed by and between EIF and
overseas based OEMs viz. Sediver Insulators (Shanghai) Co. Ltd., China; Dalian
Insulator Group Co Ltd. China and Suzhou Furukawa Power Optic Cable Co. Ltd.,
China; in capacity as an authorised signatory for EIF. While the
Agreement/Contracts executed by and between EIF and Sediver Insulators (Shanghai)
Co.. Ltd., China &Dalian Insulator Group Co Ltd. China were for the supply of disc
insulators for eventual supply to their company M/s PMC Projects (I) Private Limited
in relation to the above project, the agreement/contract executed by and between EIF
and M/s Suzhou Furukawa Power Optic Cable Co. Ltd. was for the supply of OPGW
cables and accessories.
10.2 On being asked about the signing/execution of the respective
agreements/contracts and value/consideration amount agreed for supply between the
parties, he stated that he had been a signatory to each of these agreements for
and on behalf of EIFand that he had signed these documents in India. He further
deposed that at the relevant juncture, he did not recollect the contract/agreement
value/consideration amount for respective agreements. He, however, assured to
confirm the consideration amount by producing photo-copies of each such agreement
which he had signed for and on behalf of EIF as an authorised signatory within ten
days.
10.3 During the course of his statement, he was shown photo-copies of the
documents that he had deposed to have signed as above, the contents of which he
Page 57 of 97
carefully perused including contents of the page which bore the signatures of the
authorised signatories of the respective executing parties. Pursuant to the perusal, he
confirmed that signatures appearing in the two documents for and behalf of M/s
Electrogen Infra FZE, UAE were his signatures. On being specifically asked, he
stated that his superior at PMC Projects (I) Pvt. Ltd. , Shri Jaydev Mishra, AGM
was also a signatory in these documents as an authorised signatory for and on
behalf of M/s PMC Projects (I) Pvt. Limited. He proceeded to put his dated
signatures of each of the aforesaid documents in token of his perusal and
identification.
10.4 On being specifically asked, he stated that apart from the above, he was
also a signatory to Agreement no. 415703 dated 01-10-2010 between PMC and
EIF, in the capacity of an independent witness, i.e as witness no. 1, in token of
having witnessed the signing of the Agreement by Shri Jatin Shah, Director, of EIFwho
has signed for and on behalf of EIF. He produced a copy of the above Agreement
under his dated signature.
10.5 On being asked to explain the authority or authorisation on the basis of
which Shri Dharmesh Parekh had signed documents for and on behalf of EIF, he
produced an authorisation under his dated signature, claimed to have been given to
him by Shri Jatin Shah, Director of EIFauthorizing him (Shri Dharmesh Parekh) to
sign on behalf of EIF. On being specifically asked about receipt of remuneration of any
kind from EIF, he stated that he had not been paid any consideration/remuneration at
any point of time by EIF in response to the signing authority conferred on him.
10.6 He was specifically asked, whether he had informed his employer firm
i.e.PMC before accepting such a signing authority for and on behalf of a foreign entity
i.e. EIF. He was also asked to state on whose directions/instructions he proceeded to
accept such an authorization and if he had informed his superiors, and if so, whom
had he informed. To this, he responded by stating that he did not recollect whom he
had informed within his company and on whose instructions/directions he had
accepted such an authority from a foreign entity. He also stated that he did not recall
if he had informed anybody in his company (PMC) before accepting such an authority
from a foreign company.
11.0 HOLDING COMPANY OF PMC IN MARITIUS
11.1 Perusal of the Notes forming part of the financial statements of PMC for
the years ending 31-03-2012 and 31-03-2013 (RUD-D/69)revealed that PMC Infra
Limited, Mauritius held 100% share capital of PMC as on 31.03.2011 and thereafter.
Since PMC appeared to be a wholly owned subsidiary of the Mauritius based company,
it was decided to obtain basic details such as constitution and share holding pattern
of the Mauritius based holding company from one or more of the officials declared to
be ‘Key Management Personnel’ for PMC.
11.2 Summons under Section 108 of the Customs Act, 1962 was issued to
Col. Vinod George for his appearance in this office on 10-03-2014,(RUD-C/12) since
Page 58 of 97
his name was found to appear consistently in the financial statements for each of the
three financial years 2010-11, 2011-12 and 2012-13 as ‘Key Management Personnel’
in the context of the Mauritius based holding company M/s PMC Infra Limited
[erstwhile name Gudami International (Mauritius) Limited]. Simultaneously, summons
was also issued in the name of Shri U.V.Phanikumar seeking his appearance on the
same date i.e 10-03-2014, (RUD-C/13)since his name was found to be mentioned as
fresh inclusion (w.e.f. 18-01-2013) in the list of ‘Key Management Personnel’ . Both
these officials were requested to produce Memorandum and the Articles of Association
of M/s PMC Infra Limited (holding company of M/s PMC Projects (India) Private
Limited) and all other relevant information in their respective capacities as “Key
Management Personnel” in the context of the Mauritius based holding company M/s
PMC Infra Limited.
11.3 Both the officials presented themselves on 07-03-2014. It was revealed
that while Col Vinod George (Retired) was the Chief Operating Officer, Dredging and
Reclamation for M/s PMC Projects (India) Private Limited , Shri U.V.Phani Kumar was
the Chief Executive Officer, for PMC Projects (India) Private Limited. Their joint
statement was recorded under Section 108 of the Customs Act, 1962 on 07-03-2014
(RUD-S/6).
11.3.1 During the course of their joint statement, Col. Vinod George
(Retd.) on his part stated,inter-alia, that he had worked as a consultant with M/s
Adani’s Mundra Port for dredging services from 2005 onwards till September 2011;
that thereafter in the same year of 2011, he joined the company named M/s PMC
Projects (India) Limited as a Senior Vice President in Ahmedabad and that he was
presently continuing to serve them (PMC) as on date.
11.3.2 Shri U.V.Phani Kumar on his part,inter-alia, stated that he joined
PMC Projects (India) Limited in January 2013 as Chief Operating Officer; that he was
inducted in the Board of Directors in June 2013 and that he was Chief Executive
Officer, of the company.
11.3.3 On being questioned jointly and severally, about the company
named PMC Infra Limited, they stated that it was a company incorporated in
Mauritius previously known as Gudami International (Mauritius) Limited; that the
current directors of PMC Infra Limited were Mr. Giandeo Reemul, Mr. Theyvarajen
Ponambalum and Mr. Chang Chung Ling and that PMC Infra Limited was the holding
company of M/s PMC Projects (India) Private Limited. They undertook to submit
authentic documents relating to the constitution and share holding pattern of M/s
PMC Infra Limited, Mauritius within five days.
11.3.4 On being further questioned about their role as ‘Key Management
Personnel’ for PMC Infra Limited, Mauritius, specifically declared in all statutory
documents such as Balance Sheets and Schedules thereof, they stated that their
names being Directors in the subsidiary company, had been stated as ‘Key
Page 59 of 97
Management Personnel’ for PMC Projects (India) Pvt. Ltd. in the statutory documents
i.e Balance Sheets etc.
11.3.5 On being asked to confirmjointly and severally whether they had
any role in PMC Infra Limited, Mauritius as far as its management in Mauritius was
concerned, they jointly and severally confirmed that they had no role in PMC Infra
Limited, Mauritius as far as its management in Mauritius was concerned. On being
further questioned to confirm whether M/s PMC Projects (I) Pvt. Ltd. was the only
subsidiary company of PMC Infra Limited, they responded by stating that they were
not aware whether M/s PMC Projects (I) Pvt. Ltd. was the only subsidiary company of
PMC Infra Limited. They, however, assured to confirm and revert within five days.
11.3.6 On being asked to statejointly and severally, whether M/s PMC
Projects (I) Pvt. Ltd. had given any dividend or royalty or any other payments to the
holding company PMC Infra Limited, Mauritius since its inception, they replied that
they were not aware at that juncture. They assured to confirm and revert within five
days.
11.3.7 On being asked tostate jointly and severally whether any of the
Directors/shareholders of the holding company M/s PMC Infra Limited, Mauritius,
was in the Board of Directors of M/s PMC Projects (I) Pvt. Ltd. or was controlling the
management of M/s PMC Projects (I) Pvt. Ltd., directly or indirectly, Col. Vinod George,
confirmed that there were no nominee Directors on the board of M/s PMC Projects (I)
Pvt. Ltd. since August 2010. Shri U.V.Phani Kumar also confirmed that there were no
nomineeDirectors on the board of M/s PMC Projects (I) Pvt. Ltd. since July 2013. They
stated that the Board of Directors of M/s PMC Projects (I) Private Limited reported to
the Directors of M/s PMC Infra Limited, Mauritius.
11.3.8 On being asked tostate jointly and severally whether the Board of
Directors of M/s PMC Projects (I) Pvt. Ltd. received any written instructions/directions
from the Directors/Board of Directors of M/s PMC Infra Limited, Mauritius, they
responded by stating that the Board of Directors of M/s PMC Projects (I) Pvt. Ltd. did
not receive any written instructions/directions from Directors/Board of Directors of
M/s PMC Infra Limited, Mauritius.
11.3.9 On being further asked to statejointly and severally whether concurrence
of Board of Directors of M/s PMC Infra Limited, Mauritius was sought or obtained
before taking up execution of the two transmission line project in the corridor of
Tiroda-Koradi-Akola-Aurangabad for Maharashtra Eastern Grid Power Transmission
Company Limited (MEGPTCL), they differed in their responses. While Col. Vinod
George, (Retd.) stated that such aspects were being dealt with by Shri
A.M.Uplenchwar, the then CEO, Shri U.V.Phani Kumar stated that he joined the
company only in January 2013. Regarding the concurrence of Board of Directors, they
together stated that the CEO is fully competent to execute such projects without the
concurrence of the Board of Directors of the holding company i.e M/s PMC Infra
Limited.
Page 60 of 97
12.0 TENDERING PROCESS:
12.1 Documents relating to the tendering process were called for from M/s
MEGPTCL vide letter bearing F.No. DRI/MZU/CI-224/2013/1485 dated 20-02-
2014.(RUD-C/14)
12.2 MEGPTCL, vide their letterbearing Ref :
MEGPTCL/765/DRI/AG/14/02/01 dated 28-02-2014 (RUD-D/70),stated, inter-alia,
that Notice InvitingTender (NIT) was published in three newspapers viz. the Financial
Express, the Business Standard and the Lokmaton 05-08-2010. They further
submitted that the consortium led by PMC Projects (India) Private Limited with EIF
and M/s Hyundai Heavy Industries Co. Ltd had participated in the -NIT No.
MEGPTCL/765 KV & 400 KV SS EPC/02 for substation package (the scope of work at
part B of the Notice Inviting Tender and were awarded the contract having emerged as
the lowest bidder for the sub-station package. However, M/s MEGPTCL failed to
furnish documents pertaining to the bids/offers received by themfrom other bidders
for the sub-station package.
12.3 The documents relating to the tendering process followed by MEGPTCL
for procurement to be made on international competitive bidding, submitted by them,
under their letter dated 28-02-2014 were examined.From perusal of the date of
publication of the NIT in the newspapers and other dates stipulated as timelines in the
NIT, it is noticed that that the date of NIT (05-08-2010) as well as opening dates of
Techno-Commercial bid (06-09-2010 and 07-09-2010) were prior to the date of grant
of Transmission License 1 of 2010dated 21-09-2010.It appears from perusal thereof
that MEGPTCL were aware of the above conditions much prior to issue of the
Transmission Licence i.e prior to 21-09-2010 as is evident from the fact that it
arranged to publish the NIT for International Competitive Bidding in English
newspaper as well as local language newspaper on 05-08-2010, more than a month
prior to grant of the licence. Scanned copy of one such published noticedated 05-08-
2010 inviting tenders is placed below:
Page 61 of 97
12.4 It further appears from perusal of the above advertisement that two
distinct tenders had been floated under a common NIT as under :-
(i) Tender No. MEGPTCL/765 KV_ 400 KV TL EPC/01 shown at Sr.No. A of
the Notice - (Scope of work involved under the said tender was for
setting up Transmission Lines)
(ii) Tender No. MEGPTCL/765 KV & 400 KV SS EPC/02 shown at Sr.No. B
of the Notice –(Scope of work involved under the said tender was for
setting up Sub-stations and Switchyard.
The scope of work covered by Tender No.- MEGPTCL/765 KV & 400 KV SS EPC/02 at
Part B specifically covers setting up of Sub-stations involving installation of Auto
Transformers and Shunt Reactors for three substations at Tiroda, Koradi III and Akola
II and equipment for Switch Yard (Tiroda) at designated site&Shunt Reactors at
Aurangabad.
Page 62 of 97
12.5 M/s MEGTPCL, through its letter dated 23-09-2010 bearing No.
AD/MEGPTCL/SS/01 (RUD-D/71),appears to have issued Letter of Intent to the
Consortium of PMC Projects (India) Private Limited, (Lead Member), M/s Hyundai
Heavy Industries Co. Ltd. and EIF (Members of the Consortium) for work relating to
the Sub-station package covered under Part B of the NIT involving setting up of sub-
stations) at a total price of Rs. 1895,88,15,657/-.Upon scrutiny of the documents
submitted by MEGPTCL under its letter dated 28-02-2014, it appears that
information/bid documents contained therein areonly in respect of the bid made by
the Consortium led by M/s PMC Projects (India) Pvt. Ltd. for Part B of the NIT
involving setting up of Sub-stations. MEGPTCL have failed in submitting documents
relating to other bids, if any, received for Part B. It prima-facie appears that possibly
no other bids were received for scope of work covered at Part B of NIT.
13.0 OUTWARD REMITTANCES BY MEGPTCL THROUGH PMC TO EIF
13.1 Letters of credit issued by the Banks and the remittances made against it
by MEGPTCL for the ultimate benefit of EIF through PMC Projects (India) Private
Limited, were examined in relation to scope of work for Part B of the NIT involving
supply of Auto Transformers, Shunt Reactors etc. M/s PMC Projects (India) Pvt. Ltd
appears to have placed back-to-back order for supply of Auto Transformers and Shunt
Reactors along with Disc Insulators and OPGW a/with hardware and fitting thereof for
the two transmission lines on EIF (one of consortium member) vide Agreement No.
415703 dated 1-10-2010 for an aggregate consideration of US$376,195,652/-. The
said Agreement provides break up of different items of supply in the Summary Sheet
to the Price Schedule at Schedule-I to the said Agreement, scanned image of which is
reproduced below :-
Page 63 of 97
13.2 Total cost of 765/400 KV, 500 MVA, single phase Auto Transformer
along with mandatory spares (Sr. No.-A) and 765 KV, 80 MVAR, 765 KV, single phase
Shunt Reactors along with mandatory spares (Sr. No.-B) for substations works out to
US$260269798 (US$118931930+US$141337868).
13.3 M/s MEGPTCL made applications to two banks for issue of Transferable
Letters of Credit in US Dollars from time to time for different amounts aggregating to
US$ 256156714.5 in favour of PMC to be transferred to EIF against order placed by it
on the consortium led by PMC, as detailed below:-
Table-16
Page 64 of 97
Details of the LCs issued by Banks in response to MEGPTCL’s application
Sr. No. Transferable L.C No. L. C.date Final L. C Value (US$) IssuingBank
1 0024ILC00025012 07-03-2012 17290291.16 ICICI Bank
2 0024ILC00018213 01-10-2012 19000000 ICICI Bank
3 0024ILC00024912 07-03-2012 17470825.99 ICICI Bank
4 0024ILC00004313 29-06-2012 18596464.44 ICICI Bank
5 0024ILC00004213 28-06-2012 17929082.01 ICICI Bank
6 0024ILC00004113 25-06-2012 15660178.71 ICICI Bank
7 0024ILC00004013 25-06-2012 17939106.13 ICICI Bank
8 0024ILC00004414 15-05-2013 12720000 ICICI Bank
9 0024ILC00004413 29-06-2012 16389630.82 ICICI Bank
10 0024ILC00004513 29-06-2012 15755135.27 ICICI Bank
11 00415211IM0050196 09-12-2011 18000000 SBI
12 00415211IM0050198 13-12-2011 18800000 SBI
13 00415211IM0050203 16-12-2011 19606000 SBI
14 00415211IM0050204 19-12-2011 18000000 SBI
15 00415211IM0050205 21-12-2011 13000000 SBI
Total 256156714.5
13.4 The aggregate amount of foreign exchange actually remitted by
MEGPTCL directly to EIF through the transferable LCs after deducting the “Usance
Interest and Marine Insurance” works out to US$ 253537619 as detailed below :-
Table-17
Details of amount actually remitted to EIF through the L/Cs shown at Table-16
Sr.no Transferable L.C No. L. C.date
Amount Transferred to
Electrogen Infra FZE UAE through transferable L.C by SBI, CAG, Ahmedabad, (US$)
Date Of transfer L.C To Electrogen Infra FZE UAE by SBI, CAG Ahmedabad
1 0024ILC00025012 07-03-2012 17275291.16 13-04-2012
2 0024ILC00018213 01-10-2012 19000000 11-10-2012
3 0024ILC00024912 07-03-2012 17455825.99 13-04-2012
4 0024ILC00004313 29-06-2012 18127574.27 04-07-2012
5 0024ILC00004213 28-06-2012 17477325.32 04-07-2012
6 0024ILC00004113 25-06-2012 15265200.43 04-07-2012
7 0024ILC00004013 25-06-2012 17487096.66 04-07-2012
8 0024ILC00004414 15-05-2013 12709066.55 27-05-2013
9 0024ILC00004413 29-06-2012 15976375.96 04-07-2012
10 0024ILC00004513 29-06-2012 15357862.64 04-07-2012
11 00415211IM0050196 09-12-2011 18000000 10-12-2011
12 00415211IM0050198 13-12-2011 18800000 13-12-2011
13 00415211IM0050203 16-12-2011 19606000 16-12-2011
14 00415211IM0050204 19-12-2011 18000000 19-12-2011
15 00415211IM0050205 21-12-2011 13000000 21-12-2011
Total 253537619
Note : L/Cs at Sr. No. 1 to 10 above were initially opened by ICICI bank as Local
Transferable L/Cs in Foreign Exchange which were later transferred to SBI which
Page 65 of 97
made the remittances. The actual remittances to EIF were facilitated by SBI,
Ahmedabad though OC were opened by ICICI Bank also.
14.0 RELATIONSHIP BETWEEN EIF, ELECTROGEN INFRA HOLDING PVT. LTD.
ON ONE HAND AND PMC & MEGPTCL ON THE OTHER THROUGH FAMILY
MEMBERS OF THE ADANIS:-
14.1 The parties involved in the present set of transactions involving import of
equipments and machinery for the two transmission lines and sub-stations thereof,
are :-
i) MEGPTCL-(wholly owned subsidiary of M/s Adani Enterprises Limited)-
the Licencee i.e , holder of the Transmission Licence issued by MERC
and the owner of the facility
ii) M/s PMC Projects (India) Private Limited, the contractor engaged by
MEGPTCL to execute its procurement by way of imports.
iii) M/s Electrogen Infra FZE, the UAE based intermediary invoicing agent
who raised invoices on M/s PMC Projects (India) Private Limited.
14.2 MEGPTCL is a wholly owned subsidiary of Adani Enterprises Limited
(AEL), the flagship company of the Adani Group. This fact stands well documented in
the Notes forming part of the Consolidated Financial Statements of AEL for the year
ended on 31st March, 2013, which in turn form part of its Annual Report 2012-13,
wherein M/s Adani Enterprises Limited is clearly shownto hold 100% of shares of
MEGPTCL. This position has continued since inception of MEGPTCL which is reflected
in the Financial Statements for the years ending 31st March 2012 and 31st March
2011. Therefore, MEGPTCL is directly related to the Adani Group as a result of this
parent-subsidiary relationship and shares common business interest.
14.3 As per documents available on record, MEGPTCL was incorporated on
15-02-2010 under the Companies Act, 1956 with the specific purpose to develop the
intra-state transmission system, as a joint venture company of Adani Enterprises
Limited (AEL) and Maharashtra State Electricity Transmission Company Ltd (MSETCL)
with equity participation of 74% and 26% respectively. However, AEL had an option
toarrange additional equity contribution of 26% (in place of MSETCL). This was
proposedand was and accepted, is evident from the contents of Order dated 14th
September 2010 passed by MERC(RUD-D/72). Therefore, even on inception of the
joint venture, as of February 2010, the Adani Group had a significant hold on
MEGPTCL by way of its 74% equity holding through AEL. It appears that the option to
infuse additional 26% equity (earmarked for MSETCL on formation) was exercised by
AELitself, in due course of time, as a result of which MEGPTCL became its wholly
owned subsidiary. Therefore, since the time of formation itself, AEL,by virtue of their
holding, appears to have absolute control over MEGPTCL.
Page 66 of 97
14.4 From the documents submitted by M/s PMC Projects (India) Private
Limited under its letter dated 12-03-2013,it appears evident that based on the
Transmission Licence granted to it by MERC, MEGPTCL from time to time applied to
the Principal Secretary, Energy Department, Government of Maharashtra, Mantralaya
Main Building, Mumbai, requesting for issuance of essentiality certificates for import
of Auto-Transformers with accessories &Shunt Reactors with accessories for sub-
stations at Tiroda, Koradi-III and Akola and Shunt Reactors at Aurangabad. It also
appears that the Principal Secretary (Energy),acceding to the request of MEGPTCL,
granted them the essentiality certificates, by way of endorsing the list of goods eligible
for essentiality certificate and conveying such certifications directly to the
jurisdictional Commissioner of Customs i.e Commissioner of Customs, Kandla Custom
House, recommending grant of concessional rate of duty under the Project Import
Regulations, 1986 for the certified goods.Through each such letter addressed to the
Commissioner of Customs, Kandla, as well as to the Principal Secretary (Energy),
MEGPTCL have themselves stated that they proposed to import goods fromM/s
Electrogen Infra FZE, UAE through M/s PMC Projects (India) Private
Limited.From this,it becomes clear that M/s MEGPTCL is the de-facto importer even
though they have engaged the contractor M/s PMC Projects (India) Private Limited for
filing bills of entry and clearing goods. It is also not in dispute that M/s MEGPTCL is
the sole and ultimate owner of the transmission line set up with the aid of imported
equipment & machinery and consequently of the imported equipments&machinery
installed as part of the facility.
14.5 As per various documents discussed in the foregoing paragraphs,
development and progress of EIF, since its registration on 07-07-2009 as a company
in the UAE, was as under :-
14.5.1 EIF was initially registered as a company in the name and style of M/s
Sichuan Machinery & Equipments FZE in SAIF Zone, Sharjah, UAE. Its Memorandum
& Articles of Association was dated 07-07-2009 and Shri Nasser Ali Shaban Ahli was
its sole promoter and shareholder having subscribed the entire share capital of AED
1,50,000 divided into one share of AED 1,50,000 (Memorandum and Articles of
Association dated 07-07-2009 refer in para 4.3.4).
14.5.2 M/s Sichuan Machinery & Equipments FZE passed a resolution
dated 19-11-2009 authorising Shri Jatin Shah singly as authorised signatory of its
bank accounts to open, operate and close banking accounts with any bank in the UAE
(para 4.3.3). Shri Jatin Shah is an ex-employee of Adani Group having resigned as
General Manager of Adani Power Limited ony on 31-08-2009 (para 4.1.21)
14.5.3 The Memorandum & Articles of Association of EIF dated 07-07-
2009 was amended thrice as under :-
i) On 04-01-2010-Changing name of company from M/s Sichuan
Machinery & Equipments FZE to M/s ElectroGen Infra FZE (para 4.3.4)
Page 67 of 97
ii) On 29-03-2010-Transfer of ownership of M/s ElectroGen Infra FZE from
Shri Nasser Ali Shaban Ahli to Electrogen Infra Holding Pvt. Ltd.,
Mauritius, thus making the EIF a fully owned subsidiary of EIH (para
4.2.8).
iii) On 17-06-2010-Increasing share capital of M/s ElectroGen Infra FZE
from AED 1,50,000 to AED 54,00,000/-. (para4.4.12). The increase in
the share capital was subscribed fully by M/s Electrogen Infra Holding
Pvt. Ltd., Mauritius, which was its holding company, during the
Financial Year 2010-11 (para 4.2.9).
14.5.4 From 29-03-2010, EIF became a 100% owned subsidiary of EIH
[para 4.2.8 &4.2.5 (iii)]. Further, share capital of AED 52,50,000 divided into 35
shares of AED 1,50,000 each was infused by EIH between 01-04-2010 to 21-06-2010
(para 4.2.9)
14.6 Similarly, development and progress of M/s Electrogen Infra Holding Pvt.
Ltd. , since its incorporation as a company in Mauritius, as observed from various
documents discussed in the foregoing paras, was as under :-
14.6.1 It was incorporated as a private company in Mauritius on 16-07-
2009 in the name and style of M/s Sichuan Machinery & Equipment Import & Export
Co. Ltd with paid-up equity share capital of USD 1000 divided into 1000 shares of
USD 1 each subscribed wholly by Shri Nasser Ali ShabanAhli.(para 4.2.4).
14.6.2 Name of the Company was changed to M/s Electrogen Infra
Holding Pvt. Ltd. with effect from 08-01-2010 by Special Resolution (para 4.2.11).
14.6.3 The entire share capital of the company i.e. USD 1000 divided into
1000 shares of USD 1 each was transferred to Shri Vinod Shantilal Shah on 12-01-
2010 from Shri Chang Chung Ling who in turn had purchased it from Shri Nasser Ali
Shaban Ahli, the initial subscriber, on 01-10-2009 (para 4.4.13 &4.4.14). Shri Nasser
Ali Shaban Ahli was also the initial subscriber of share capital of EIF on 07-07-2009
which he sold to EIH on 23-03-2010 (para 4.2.8).
14.6.4 Shri Vinod Shantilal Shah was also appointed Director of the
company on 12-01-2010 i.e. the date when the whole of share capital of EIH on that
date was transferred to him and continued as a Director till he resigned on 31-05-
2011 (para 4.4.9)
14.6.5 Paid-up share capital of the company was increase from USD
1000 to USD1,00,000 during the Financial Year 2010-11 (para 4.2.4 above).
14.6.6 EIH took over EIF’s entire paid-up capital of AED 1,50,000 on 29-
03-2010 and subscribed to further share capital of AED 52,50,000 between the period
from 01-04-2010 to 21-06-2010, because as shown in share certificate 4107 dated 21-
Page 68 of 97
06-2010 (para 4.2.9), EIH is mentioned as holder as on that date of 36 shares of AED
54,00,000.
14.6.7 Shri Vinod Shantilal Shah was the only owner of EIH as on 12-01-
2010. (para4.2.4). So, when full ownership of EIF was taken over by EIH as 29-03-
2010, Shri Vinod Shantilal Shah became owner of EIF also.
14.7 EIF was the intermediary invoicing agent between the OEMs/actual
suppliers and PMC. EIF was registered in the name and style of M/s Sichuan
Machinery and Equipments FZE on 07-07-2009 in the UAE with Shri Nasser Ali
Shaban Ahli as the sole share-holder holding the whole of share capital of the
company equal to AED 1,50,000 divided into one share of 1,50,000. Simultaneously,
Shri Nasser Ali Shaban Ahli incorporated another company by name M/s Sichuan
Machinery & Equipment Import & Export Co. Ltd in Mauritius, on 16-07-2009 by
subscribing to the whole of its paid-up capital of USD 1000 divided into 1000 shares
of USD one each. EIF, by way of Board Resolution dated 19-11-2009, authorised Shri
Jatin Shah, an ex-employee of Adani Group, to open, operate and close bank accounts
of the company with any bank in the UAE. Name of the existing company M/s
Sichuan Machinery and Equipments FZE in the UAE was changed to EIF on 04-01-
2010. Simultaneously, the name of M/s Sichuan Machinery & Equipment Import &
Export Co. Ltd in Mauritius was also changed to ElectroGen Infra Holding Pvt. Ltd. on
08-01-2010. Shri Nasser Ali Shaban Ahli transferred and sold the whole of equity
share capital of USD 1000 divided into 1000 shares of one USD each of M/s Sichuan
Machinery & Equipment Import & Export Co. Ltd, Mauritius (presently EIH) to Chang
Chung Ling on 01-10-2009, who further transferred the said share capital to Shri
Vinod Shantilal Shah on 12-01-2010, who thus became the sole owner of EIH.
Thereafter, Shri Nasser Ali Shaban Ahli also transferred and sold the whole of share
capital of EIF on 29-03-2010 to EIH and thus, EIH became holding company of EIF
with effect from 29-03-2010. Shri Vinod Shantilal Shah has been mentioned in
various documents as Authorised Signatory (para 4.4.3, 4.4.4 &4.4.7) and Director
(para 4.4.5) in connection with EIF.
14.7.1 EIF’s status as subsidiary of EIH is mentioned in various documents on
various dates such as;-
i) In letter dated 26-04-2012 from EIF addressed to ICICI Bank,
DIFC, Dubai Branch (para 4.2.3)
ii) In letter dated 23-10-2012 from EIF addressed to Axis Bank,
Dubai (para 4.4.10)
iii) Copies of amended Licence certificates issued by SAIF Zone
authorities as of 07-08-2012 and 19-06-2012 (para 4.4.11)
iv) In letter dated 09-12-2013 of Shri Jatin Shah addressed to DRI
(para 5.12)
Page 69 of 97
v) In letter dated 18-12-2013, addressed by Axis Bank, DIFC,Dubai
Branch to DRI (para 4.4.1)
14.7.2 EIF, in its letter dated 26-04-2012 addressed to ICICI Bank, DIFC,
Dubai Branch informed its share holding pattern as under (para 4.2.3 above):-
i) Electrogen Infra FZE is 100% owned by Electrogen Infra Holding Pvt. Ltd.
ii) Electrogen Infra Holding Pvt. Ltd. is 100% owned by Asankhya Resources
Pvt. Ltd.
iii) Asankhya Resources Pvt. Ltd. is owned by Eagle Holding Ltd., which is a
nominee shareholder in Asankhya Resources Family Trust.
iv) In Asankhya Resources Family Trust, Mr. Vinod Shantilal Adani is the
settler.
Thus, it appears that EIF is owned by Shri Vinod Shantilal Adani through the
above process of layering which is the common and known modus-operandi for
siphoning off of money by masking the actual owners.
14.7.3. Perusal of Financial Statements of EIH for the year 2010-11 (para 4.2.4)
reveals that as on 31.03.2010, it had an investment of USD 40,872/- in an unquoted
company, which went up to USD 14,81,390/- as on 31.03.2011. EIF, registered in
UAE, is the only company where EIH was holding equity of AED 1,50,000/- as on
31.03.2010, which was purchased by it from Shri Nasser Ali ShabanAhli on
29.03.2010. Share capital of EIF was increased from AED 1,50,000/- to AED
54,00,000/- on 17.06.2010, and the increase was fully subscribed by EIH only, by
investing USD 14,40,518/- (equal to AED 52,50,000/-) as is evident from share
certificate dated 21.06.2010 (para 4.2.9). Perusal of the Financial Statements of EIH
further reveals that on an amount of USD 14,81,390/- invested by EIH in EIF, it
received dividend income of USD 5,39,50,954/-, [EIF declared a dividend of AED 198
million for the year 2010-11 as revealed in its financial statement (para 4.2.5) and the
whole of these dividends went to EIH because EIF was a 100% subsidiary of EIH]
which works out to a return of 3641.91%, which is unheard of in any legitimate
business activity.
14.8 By virtue of his capacity as a Director of M/s Electrogen Infra Holding
Pvt. Ltd. , Mauritius, Shri Vinod Shantilal Adaniappears to have enjoyed a direct and
absolute control over its wholly owned subsidiary M/s Electrogen Infra FZE, UAE. In
addition to being directly related to Electrogen Infra FZE, UAE, in his capacity as a
Director of its parent holding company (Electrogen Infra Holdings Pvt. Ltd., Mauritius),
it is an undisputed fact that Shri Vinod Shantilal Adani also happens to be a member
of the Adani Family and one of siblings of the Adani brothers(refer para4.5.17above)
operating the group’s business in diverse areas through and under the banner of its
flagship company, M/s Adani Enterprises Limited (AEL).Shri Vinod Shantilal Adani is
Page 70 of 97
one of five brothers who, inter-alia, has a substantial share-holding in the flagship
company of the group i.e M/s Adani Enterprises Limited and his shareholding is a
part of promoter/promoter group shareholding. The shareholding pattern for the
quarter ending June 2013 reveals him to hold 90749100 shares in the group’s flagship
company (AEL),which work out to about 8.25% of the total share capital of AEL as per
information submitted to DRI on 25-09-2013,(RUD-D/73)during course of the visit of
the officers to Ahmedabad. Therefore, while being a promoter shareholder of the flag
ship group company all along, Shri Vinod Shantilal Shah, concurrently appears to
have held the position of a Director of the parent holding company of M/s Electrogen
Infra FZE, UAE. MEGPTCL, which is a wholly owned subsidiary of AEL is thus
directly related to Electrogen Infra FZE, UAE (wholly owned subsidiary of Electrogen
Infra Holdings Pvt. Ltd., Mauritius having Shri Vinod Shantilal Adani as its owner).
Thus, the importer MEGPTCL and the overseas intermediary invoicing agent EIFare
related. Shri Vinod Shantitlal Shah, is a member of the Adani family, which runs the
flagship company of the Group Adani Enterprises Limited and is also a promoter share
holder therein. This appears to reveal direct and clear nexus the Adani Group has with
the overseas intermediary invoicing agent EIF through Vinod ShantilalAdani. This in
turn appears to indicate that the so called supplier and the de-facto importer i.e
MEGPTCL are also related to each other since MEGPTCL is a wholly owned subsidiary
of the Adani Group.
14.9 Therefore, EIF, the intermediary invoicing agent, and MEPTCL, the owner
and de-facto importer appear to be related to each other through Shri Vinod Shantilal
Adani @ Vinod Shantilal Adani in terms of Rule 2 (2) of the CVR, 2007.
14.10 In so far as M/s PMC Projects (India) Pvt. Ltd. is concerned,
investigations have revealed that two of its employees, Shri Dharmesh Parekh, Senior
Manager and Shri Jaydev Mishra, Associate General Manager, both of whom joined
PMC Projects (India) Private Limited in the same year i.e in 2008 had their association
with the Adani Group in the past (prior to 2008), having served one of the group
companies as employees. While Shri Dharmesh Parekh, served as an employee of
Adani Energy Limited for three years between 2005-2008, Shri Jaydev Mishra served
Adani Power Limited for over a year since 2007, till they joined M/s PMC Projects
(India) Private Limited in varying capacities in the year 2008. In view of their
association with the group, these employees appear to have got closely acquainted
with the functioning of the Adani Group. During their employment with M/s PMC
Projects (India) Private Limited, they appear to have signed important documents in
the nature of contracts/agreements/power of attorney, particulars of which are
tabulated below :-
Table-18
Summary of agreements/contracts signed by Shri Jaydev Mishra and Shri
Dharmesh Parekh, both employees of PMC Projects (I) Pvt. Ltd.
Page 71 of 97
Sr.No. Documents description JAYDEV MISHRA DHARMESH PAREKH
1 Consortium Agreement dated 16-10-2010 between M/s PMC
Projects (India) Private Limited, (PMC) M/s Electrogen Infra FZE, UAE (EIF) and M/s Hyundai Heavy Industries Co. Ltd., South Korea
Signatory to the agreement as authorised signatory for and
on behalf of lead member of the consortium i.e. PMC
Signatory to the agreement as authorised signatory for and on
behalf of one of the members of the consortium i.e. EIF.
2 Power of Attorney (POA) for Lead Member executed by & between M/s PMC Projects (India) Private Limited, M/s Electrogen Infra FZE,
UAE and M/s Hyundai Heavy Industries Co. Ltd., South Korea
Signatory to the POA as an Executant for and on behalf of Lead Member of the consortium i.e PMC & signed
in token of acceptance of POA for & on behalf of PMC
Signatory to the agreement as authorised signatory for and on behalf EIF (one of the Consortium member)
3 Agreement No.700003 dated 05-
10-2010 between M/s Electrogen Infra FZE, UAE and M/s Hyundai Heavy Industries Co. Ltd., South
- Signatory to the agreement as
authorised signatory for and on behalf of EIF.
4 Agreement No.700001 dated 05-10-2010 between M/s Electrogen Infra FZE, UAE and M/s Sediver Indulators (Shanghai) Co. Ltd. ,
China
- Signatory to the agreement as authorised signatory for and on behalf of EIF.
5 Agreement No.700002 dated 05-10-2010 between Electrogen Infra
FZE, UAE and M/s Dalian Insulator Group Co. Ltd., China
- Signatory to the agreement as authorised signatory for and on
behalf of EIF.
6 Agreement No.700004 dated 05-10-2010 between M/s Electrogen
Infra FZE, UAE and M/s Suzhou Furukuwa Power Optic Cable Co. Ltd., China
- Signatory to the agreement as authorised signatory for and on
behalf of EIF.
7 Letters, correspondences, offers/bid between M/s PMC Projects (India) Pvt. Ld. and MEGPTCL
Signatory to most of the correspondence made with MEGPTCL and acknowledging receipt of key documents such
as Purchase Order, Letter of Intent etc issued by MEGPTCL to PMC
-
8 Agreement No. 415703 dated 01-10-2010 between M/s PMC Projects (India) Private Limited and M/s Electrogen Infra FZE , UAE
(EIF)
Signatory to the agreement as authorised signatory for and on behalf of PMC
Signatory to the Agreement as a witness i.e signed in token of having witnessed the signing of the agreement by Shri Jatin Shah, who
signed for and on behalf of EIF
9 Agreement dated 28-09-2010 by and between M/s PMC Projects
(India) Private Limited and M/s ABB Limited
Signatory to the agreement as authorised signatory for and
on behalf of PMC
Signatory to the Agreement as a witness i.e signed in token of having
witnessed the signing of the agreement by Shri Jaydev Mishra, who signed for and on behalf of PMC
10. Amendment no. 1 dated 30-09-
2011 to Agreement No. 415703 dated 01-10-2010 between M/s PMC Projects (India) Private
Limited and M/s Electrogen Infra FZE , UAE (EIF)
Signatory to the agreement as
authorised signatory for and on behalf of PMC
-
It may be seen from the description of the document given in Table-18 above that
these are vital documents which constitute the cause of action that led to the
execution of the entire workassociated for the projectinvolving setting up of two
numbers of 765 KV S/C transmission lines from Tiroda-Koradi III – Akola II –
Aurangabad, 400 KV D/C Line from Akola II –Akola I and associated 765/400 KV
substations at Tiroda, Koradi III, Akola II and Aurangabad, for execution of which
MEGPTCL had been given a Transmission Licence by MERC and which sub-contracted
the works to PMC Projects (India) Private Limited.
14.11 It appears that Shri Dharmesh Parekh, employee of PMC had signed
contracts/agreements as an authorised signatory for and on behalf of a UAE based
company, EIF, as admitted by him in his statement recorded under Section 108 of the
Customs Act, 1962 on 10-12-2013.(RUD-S/1)These contracts including the contract
between EIF and M/s Hyundai Heavy Industries Co. Ltd., South Korea,are key
documents which formed the basis of procurement of goods by EIF for ultimate supply
Page 72 of 97
to MEGPTCL through PMC Projects (India) Private Limited. Shri Dharmesh Parekh in
his statement recorded under Section 108 claimed to have signed the respective
agreements on the basis of authorisation given to him by Shri Jatin Shah, Director of
EIF.It is inconceivable that a non-related foreign registered company confers the
authority /authorises the employee of, ostensibly an unconnected private limited
company in India to sign important documents viz. letters of intent, letters of award,
contracts etc. on its behalf, as an authorisedperson,simply by issuing a one page
document to the said effect. The one page document, in the form of an authority letter,
is apparently signed by Shri Jatin Shah on behalf of EIF, on one part in token of
having conferred the authority to sign on Shri Dharmesh Parekh (apparently in his
individual capacity) and signed by Shri Dharmesh Parekh, on the other part,
apparently in token of accepting the said authorisation, in individual capacity. It is
also unusual for an ordinary employee of private limited company in India to accept
such an authorisation given by a foreign registered company to sign documents on its
behalf, as an authorised signatory, to exercise such power in an unhesitant manner
and proceed to sign several key documents with huge financial implications running
into millions of US Dollars. It is a recorded fact both Shri Dharmesh Parekh and Shri
Jatin Shah, have in the past served the Adani Group as employees in group
companies. This prima-facie appears illogical and the only logical conclusion is that
for these individuals there is no distinction between these two companies, though on
paper it may be so and that their interests are common.
14.12 It is relevant to mention here that Shri Dharmesh Parkeh in his
statement recorded on10-12-2013(RUD-S/1)on being questioned on these aspects
has,inter-alia,deposed that he had never travelled abroad at any point of time which
clearly indicates that all documents signed by him for and on behalf of the UAE based
company EIF were signed in India. In his subsequent statement recorded under
Section 108 of the Customs Act, 1962 on 28-02-2014, (RUD-S/5)on being specifically
questioned about receipt of remuneration of any kind from EIF towards the signing
authority conferred on him and exercised by him, he deposed that he had not been
paid any consideration/remuneration at any point of time by EIF. In response to
specific questions viz. whether he had informed his employer firm i.e M/s PMC
Projects (I) Private Limited before accepting such a signing authority for and on behalf
of a foreign entity i.e. M/s Electrogen Infra FZE, UAE; on whose
directions/instructions he proceeded to accept such an authorization; whether he had
informed his superiors regarding this aspect, and if so, to name the person whom he
had informed. To this, he responded by stating that he did not recollect whom he had
informed within his company and on whose instructions/directions he had accepted
such an authority from a foreign entity. He also stated that he did not recall if he had
informed anybody in his company (PMC) before accepting such an authority from a
foreign company.
14.13 The entire sequence of events starting with Shri Dharmesh Parekh, being
conferred the power to sign on behalf of a foreign registered company (EIF) during his
Page 73 of 97
employment with a private limited company in India (PMC), his proceeding to sign
agreements & important documents having financial implications of hundreds of
millions of US Dollars (Sr.No. 1 to 6 of Table-18) in exercise of the said authorisation
and offering his services free of charge without any extra consideration/remuneration
and his plea of being unable to recollect if he had informed any of his superiors within
his employer firm PMC,only goes to show that for him there is no distinction between
PMC and EIF. Looking at the issue from other side, the fact that the so called UAE
based company has allowed Shri Dharmesh Parekh, an employee of PMC to sign
agreements on its behalf with financial implications of over hundreds of millions of US
Dollars, clearly imply that even EIF has treated Shri Dharmesh Parekh as its own
authorised representative. All these only go to show that there is no distinction
between PMC and EIF, they are only working for common interest as a part of a large
modus-operandi for siphoning off of money from India by invoice inflation.
14.14 Shri Jaydev Mishra, Associate General Manager of M/s PMC Projects
(India) Private Limited, to whom Shri Dharmesh Parekh, reports to in the company as
his sub-ordinate/junior, on being specifically questioned regarding Shri Dharmesh
Parekh during the course of his statement recorded under Section 108 of the Customs
Act, 1962 on 17-02-2014, (RUD-S/4)categorically acknowledged in the affirmative that
that he knew Shri Dharmesh Parekh as an employee of M/s PMC Projects (I) Pvt. Ltd.
since the year 2008 and that Shri Dharmesh Parekh reported to him.On being further
questioned to explain if Shri Dharmesh Parekh had the authority or power to sign
documents/agreements/contracts on behalf of various companies including foreign
entities in the background of local Indian laws of employment, he responded by stating
that he was not aware whether Shri Dharmesh Parekh had any authority or power to
sign on behalf of various companies including foreign entities.In this context, perusal
of the signatories to agreements/documents listed at Sr.Nos. 1 and 2 of Table-
18,clearly shows that both the ex-employees of the Adani Group were signatories to
the said documentsin varying capacities. Shri Jaydev Mishra, having signed the
Consortium Agreement (Sr.no. 1 of Table-18) as well as the Power of Attorney (Sr.No. 2
of Table), as an authorised signatory of M/s PMC Projects (India) Private Limited)and
Shri Dharmesh Parekh, his sub-ordinate, having signed as authorised signatory for
and on behalf of M/s Electrogen Infra FZE, UAE, boththe documentshaving been
executed between M/s PMC Projects (India) Private Limited, M/s Electrogen Infra FZE,
UAE and M/s Hyundai Heavy Industries Co. Ltd., South Korea. The fact that two
employees of PMC: senior and sub-ordinate duo (Shri Jaydev Mishra and Shri
Dharmesh Parekh) signed the Consortium Agreement on 16.10.2010 for and on behalf
of two different companies, one for PMC and the other for the overseas company EIF,
clearly obliterates the distinction between these two companies, as if they are two
sides of the same coin.
14.15 It, therefore, appears that both the above personnel, being ex-employees
of the Adani Group, continued to serve the interest of the groupby their acts of
omissions and commission, while being employed with M/s PMC Projects (India)
Private Limited. Both the employees appear to have traversed beyond the scope of
Page 74 of 97
their normal role and responsibilities as employees of M/s PMC Projects (India) Private
Limited by their acts of omission and commission; Shri Dharmesh Parekh by
proceeding to sign on behalf of a foreign registeredentity and his superior, Shri Jaydev
Mishra, knowinglyallowing/permitting his sub-ordinate to sign for and on behalf of a
foreign company, without raising any objection as a superior. That they acted in the
manner they did, only shows that for them, PMC Projects (India) Pvt. Ltd., Ahmedabad
and Electrogen Infra FZE, UAE were not different; both these entities were merely
acting to further the Adani group’s interest. That Electrogen Infra FZE, UAE is not a
bonafide supplier but merely a front for creating inflated invoices as part of the overall
plan is obvious from the above.
14.16 It further appears that the M/s PMC Projects (India) Private Limited was
directly related to the Adani Group at one point in time through Shri Malay
Mahadevia, one of the Directors in M/s PMC Projects (India) Private Limited,who in
addition to that,also appeared to be a director in Adani Hazira Port Pvt. Ltd as per
information available in the Import-Export-Code (IEC) profile (RUD-D/74).The Articles
of Association of PMC Projects (India) Private Limited as of 27-04-2005 submitted by
M/s PMC Projects (India) Private Limited thorough their letter dated 08-01-2014reveal
that PMC Projects (India) Private Limited was a subsidiary of a Mauritius based
company, M/s Projects Monitoring Construction Limited, having its address at 44,
St.George Street, Port Louis, Republic of Mauritius, which subscribed to 10,000
shares (9999 shares through nominee Dr.Malay Mahadevia and one share through
him individually)of PMC. Presently, it appears that PMC Projects (India) Private
Limited is a wholly owned subsidiary of PMC Infra Limited, Mauritius. It appears that
name of the holding company of PMC was changed from M/s Projects Monitoring
Construction Limited initially to M/s Gudami International (Mauritius) Limited, and
finally to PMC Infra Limited.
14.17 With a view to ascertain who controlled the Mauritius based parent
company of M/s PMC Projects (India) Private Limited, two of the directors of M/s PMC
Projects (India) Private Limited, Col Vinod George (Retired) and Shri U.V.Phani Kumar
during the course of their joint statement recorded under Section 108 of the Customs
Act, 1962 on 07-03-2014 (RUD-S/6),inter-alia,had undertook to submit authentic
documents relating to the constitution and share holding pattern of M/s PMC Infra
Limited, Mauritius within five days. They also assured to confirm and revert if M/s
PMC Projects (I) Pvt Ltd. was the only subsidiary company of PMC Infra Limited within
five days. However, they failed to provide any information on these aspects. On or
about 10-03-2014, through a letter bearing Ref: PMC/DRI/JM/1451/14, (RUD-
D/75)Shri U.V. Phanikumar, Director of the company, stated that he had no idea of
either the shareholding pattern of M/s PMC Infra Limited, Mauritius or information
about its other subsidiaries.
14.18 From the response of Shri Vinod George and Shri U.V.Phanikumar, both
being key management personnel for M/s PMC Projects (India) Private Limited, Shri
Page 75 of 97
Vinod George, holding the position since 17-05-2010,it appears rather unusual that
key management personnel within the company have no knowledge or idea of the
constitution and share holding pattern of the parent holding company in Mauritius
and related information. From their acts, it appears that they are deliberately
refraining from divulging information in their domainso as to thwart investigation into
relationship between M/s PMC Projects (India) Private Limited and the Adani Group.
14.19 It appears that PMC Projects (India) Private Limited, as a contractor,
entrusted with the responsibility of executing work ordered on it by MEGPTCL, itself
sought financial assistance from MEPTCL and requested them to open transferable
Letters of Credit (LCs) in its favour. MEPTCL also acceded to this request and agreed
to open transferable letters of credit. By way of an arrangement with MEGPTCL, they
subsequently have straightway arranged for remittances to be made to EIF by
amending the LCs to incorporate the name of EIF as the beneficiary. Thus, the
remittances for the invoices received by M/s PMC Projects (India) Private Limited
fromEIF were actually made directly by M/s MEGPTCL to EIF through mechanism of
transferable letters of credits. These sorts of transactions are not normal business
practices. M/s PMC Projects (India) Private Limited appears to have rendered its
services as a contractor, free of charge, without any consideration, as they have failed
to retain any margin money for themselves, i.e difference between its cost of
procurement and price of supply which appears to be another abnormality.
14.20 Therefore, the activities of M/s PMC Projects (India) Private Limited
appear to be managed, controlled and influenced by the Adani Group through its
entity MEGPTCL, common directors and employees. M/s Electrogen Infra FZE, based
in the UAE,appears to be only a front for facilitating siphoning of funds through over-
valuation of imports by creating inflated intermediary invoicing.
15.0 REJECTION OF DECLARED VALUE AND RE-DETERMINATION OF
ASSESSABLE VALUE
15.1 Based on documents obtained from AXIS Bank, DIFC branch, UAE and
Bank of Baroda, Dubai Main Branch, Bur Dubai, (back-to-back procurement invoices
-invoices raised by OEMs on M/s Electrogen Infra FZE, UAE) for consignments
shipped to India by various OEMs and cleared through Customs on the strength of
invoices with inflated prices raised by M/s Electrogen Infra FZE on PMC Projects
(India) Private Limited, a tabulated chart has been prepared which gives details of all
such consignments imported by MEGTPCL through PMC Projects (India) Private
Limited. A total of 57 consignments imported by MEGPTCL through PMC Projects
(India) Private Limited have been detailed in Annexure A to this Show cause notice.
Particulars in Columns [A] to columns[G] of Annexure Ato this Notice have been
tabulated on the basis of information available in the documents submitted by PMC to
the Customs at the time of assessment, on the strength of which the goods were
Page 76 of 97
assessed and cleared for home consumption. These documents were submitted to DRI
by the importer in response to the requisitionbearing F.No. DRI/MZU/CI-224/2013
dated 17-10-2013.The inflated invoice prices as appearing in the invoices raised by
M/s Electrogen Infra FZE, UAE on the basis of which the assessable valueswere
worked out and declared in the respective bills of entry is available at Column [F].
Particulars in Columns [H] to [L] have been tabulated on the basis of information
available in the respective shipper (OEM) invoices raised on M/s Electrogen Infra FZE
by the respective OEM.In respect of Bills of Entry shown at Sr.No. 56 and 57of
Annexure A, pertaining to shipments by M/s Hyundai Heavy Industries Co. Ltd. and
M/s Suzhou Furukawa Power Power Optic Cable Co.Ltd,respectively, the differential
value has been worked out on the basis of proportionate contract value for
identical/similar goods available in Contract No. 700003 dated 05-10-2010 between
HHICL &EIF and contemporary price of similar goods available in other OEM-invoices
raised by M/s Suzhou Furukawa Power Optic Cable Co.Ltd on EIF, respectively.
15.2 A chart containing particulars of the said 57 consignments imported by
M/s PMC Projects (India) Private Limited (B.E.No. /date, bill of lading no. /date) with
details of corresponding OEM invoices, as featured in Annexure A to this notice, was
shown to Shri Mayur Shah, ex-Associate Vice President of M/s PMC Projects (India)
Private Limited and Shri Jaydev Mishra, Associate General Manager, M/s PMC
Projects (India) Private Limited during the course of their statements recorded under
Section 108 of the Customs Act, 1962, on 17-02-2014. After going through
information in the said chart and physical cross verification thereof on the basis of
copies of OEM invoices/packing lists and copies of corresponding bills of lading, they
confirmed that the OEM invoices/packing lists pertained to consignments imported
and cleared on the strength of invoices raised by EIF, thereby confirming authenticity
of back-to-back nature of the invoicing pattern.
Note : The chart shown to them during the course of their statement on 17-02-2014
contained 58 bills of entry, as one bill of entry 7420406 dated 18-07-2012 had been
inadvertently repeated at Sr.No. 34 and again at Sr.No. 54.The duplicate entry has
since been deleted while preparing Annexure-Amaking it a total of 57 import
consignments.
15.3 In the 57 Bills of Entry featured in Annexure-A, it has been held out that
the value declared therein represents the Transaction Value paid or payable for the
goods imported, which is not correct, legally or factually for the following reasons :-
(i) PMC and EIF, the so called buyer and seller were not different. EIF was
only a front and intermediary invoicingagent , for inflating the invoice
value as part of the modus-operandi. This is evident from the foregoing
discussions and more particularly from the manner in which Agreements
have been signed obliterating distinction between PMC and EIF.
Page 77 of 97
(ii) Goods were supplied directly to India by respective OEMs. Though it was
a direct supply and three entities viz. HHICL (OEM), PMC and EIF had
bid as a consortium based on which contract for supply of goods was
given to the consortium, on paper the transaction was split as between
OEM(HHICL)---> EIF---> PMC for invoicing with fraudulent intent of
siphoning off of money from India, by inflating the value on paper in the
2nd stage (EIF---> PMC ). Interestingly, two employees of PMC Shri
Jaydev Mishra and Shri Dharmesh Parekh – (Senior and sub-ordinate)
have signed both the Contracts- First stage i.e.OEM(HHICL)--->
EIFsigned by Dharmesh Parekh for & behalf of EIF and second stage i.e.
EIF--->PMC signed by Jaydev Mishra for PMC. It applies, mutatis
mutandis, to the other OEMs (Dalian, Sediver and Suzhou) and the
goods supplied by them.
(iii) The contract for supply of goods between OEMs (HHICL, Sediver
andDalian) and the intermediary invoicing agent i.e.EIF was signed by an
employee of PMC (Shri Dharmesh Parekh) that too in India- thus not only
obliterating distinction between PMC and EIF (the so called buyer –
seller), but also rendering the contracts so executed, invalid and non-est.
(iv) Without prejudice to the above, since EIF and PMC are related to each
other and the declared value is not acceptable as the Transaction Value
as per the Customs Valuation (Determination of value of Imported goods)
Rules,-2007 (in short the CVR’ 2007)read with Section 14 of the Customs
Act, 1962.
(v) Further, they (PMC & EIF) had together (alongwith HHICL) signed a
Consortium Agreementon 16-10-2010. The said Consortium Agreement
was signed on behalf of PMC and EIF by two employees of PMC (senior
and sub-ordinate duo of Shri Jaydev Mishra and Shri Dharmesh
Parekh). Further, supply agreement between EIF and OEMs were also
signed by Shri Dharmesh Parekh on behalf of EIF. All these, not only
obliterate the distinction between PMC and EIF, but also establish
commonality of interest.
(vi) OEM value has been traditionally recognised as the more authentic value
which is recognised in law. Rule 11 of the CVR-2007 lists manufacturer’s
invoice as a relevant document for determination of the value of the
imported goods, particularly when goods are imported from or through a
person other than the manufacturer or producer. The text of Rule
11,ibid, is extracted below for ease of reference -
“Rule 11 .Declaration by the importer.---(1) The importer or his agent shall
furnish –
(a) A declaration disclosing full and accurate details relating to the
value of imported goods; and
(b) Any other statement, information or documents including an
invoice of the manufacturer or producer of the imported goods
Page 78 of 97
where the goods are imported from or through a person other
than the manufacturer or producer, as considered necessary by
the proper officer for determination of the value of imported
goods under these rules”.
Thus, the transaction between EIF and PMC, being apparently a sham
transaction for reasons set out above, the same is,therefore,liable to be rejected under
the provisions of Rule 12 of the CVR, 2007.Rule 11 of the Rules, prescribes various
documents required for ascertaining correctness of the declared value. One of the
prescribed documents is manufacturer’s invoice. Rule 4 of theCVR-2007 provides that
subject to the provisions of Rule 3, the value of the imported goods shall be the
Transaction Value of identical goods sold for export to India and imported at or about
the same time as the goods being valued. In the present case, the goods in question
themselves have been shown as sold to the intermediary invoicing agent i.e EIF but
have been directly shipped to India by the OEMs. EIF has merely acted as an
intermediary invoicing agent for inflating the invoice. Thus, the invoice value of the
manufacturer (OEM) appears to be the actual value of goods. Rule 4 refers to value of
identical goods being sold for export to India and imported at or about the same time.
The ambit of identical goods covers same goods as well, being identical in all respects.
Therefore, the price available in such OEM invoices appears to be the actual
Transaction Value of the same goods (Identical goods-Rule 4)-being the same set of
goods, covered by two different sets of invoices.It is obvious that there is no material
difference of any kind in description, quantity, make, or the manufacturer.Therefore,
the value is required to be re-determined under the provisions of Rule 4 of the CVR,
2007 read with Section 14 of the Customs Act, 1962.
15.4 Thus, the declaredvalues in the impugned 57 bills of entry in total
amounting to Rs. 1887,06,49,088/-(CIF)declared on the basis of inflated invoice
prices of the intermediaryinvoicing agentEIF, do not represent actual value of the
goods as has been brought out by the investigation, as set out above, and the said
declared assessable value is required to be rejected under the provisions of Rule 12 of
the CVR, 2007 and re-determined under the provisions of Rule 4 of the CVR-2007
read with Section 14 of the Customs Act, 1962, on the basis of price available in the
back-to-back OEM invoices raised on the intermediary invoicing agent i.e. EIF.
Accordingly, the aggregate re-determined CIF value of the goods imported against the
57 bills of entry works out to Rs. 393,21,76,604/-(CIF)as worked out incolumns K of
Annexure A, on the basis of prices in OEM invoicesas against the declared CIF of Rs.
1887,06,49,088/-(CIF).The quantum of over-valuation arising out of the back-to-back
inflated invoicing by the intermediary-EIF on PMC, is shown incolumn N of Annexure
A, which works out to Rs.1493,84,72,484/-(Rupees One thousand four hundred
and ninety three crores, eight four lakhs, seventy two thousand fourhundred
eight fouronly)whichappears to have been siphonedoffout of
Page 79 of 97
India by MEGTPCL through PMC to their overseas intermediary invoicing agentand
related entity EIF, on account of invoice inflation, in the guise of outward remittances
as consideration for the imports.
16.0 RELEVANT LEGAL PROVISONS
16.1 The legal provisions relevant to the present proceedings are :-
i) Various provisions of the Customs Act, 1962 as mentioned
in the notice
ii) The Customs Valuation (Determination of Value of Imported
Goods) Rules 2007 (The CVR-2007)
iii) The Foreign Trade (Development & Regulation) Act, 1992
(The FTDR)
iv) The Foreign Trade (Regulation) Rules, 1993
Some of the specific provisions with particular relevance to the instant case are
discussed below:-
16.2 Section 46 of the Customs Act, 1962 provides for filing of Bill of
entry upon importation of goods, which casts a responsibility on the importer
to declare truthfully, all the contents in the bill of entry. Relevant portion of
Section 46 i.e. sub-section (4) thereof is reproduced below for ease of reference
:-
“(4) The importer while presenting a bill of entry shall
at the foot thereof make and subscribe to a declaration as
to the truth of the contents of such bill of entry and shall,
in support of such declaration, produce to the proper
officer the invoice, if any, relating to the imported goods
x xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx”
16.3 Section 111 of the Customs Act provides for confiscation of
improperly imported goods. The relevant sub-sections (d) and (m) are
reproduced below:-
“111. Confiscation of improperly imported goods, etc.-
The following goods brought from a place outside India shall be
liable to confiscation:-
Page 80 of 97
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
(d) any goods which are imported or attempted to be
imported or are brought within the Indian customs
waters for the purpose of being imported contrary to any
prohibition imposed by or under this Act or any other
law for the time being in force;
x xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
(m) any goods which do not correspond in respect of value
or in any other particular with the entry made under
this Act or in the case of baggage with the declaration
made under section 77 in respect thereof, or in the case
of goods under transhipment, with the declaration for
transhipment referred to in the proviso to sub-section (1)
of section 54;
x xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx”
Since the actual value of imported goods do not correspond with the
declared value of the goods in the Bills of Entry (which were grossly over-
valued) the said goods appear liable for confiscation under Section 111(m) of
the Customs Act, 1962.
Confiscation under Section 111(d) is discussed later.
16.4 Section 112 of the Customs Act, 1962 provides for improper
importation of goods etc.; while 112 (a) and (b) provide for situations, the sub-
sections (i) to (v) provide extent of penalty. Section 112 (iii) provides for penalty
in the case of import over-valuation, relevant text of which is reproduced
below:-
“112.Penalty for improper importation of goods, etc. –
Any person, -
(a) who, in relation to any goods, does or omits to do any
act which act or omission would render such goods lia-
ble to confiscation under section 111, or abets the doing
or omission of such an act, or
(b) who acquires possession of or is in any way con-
cerned in carrying, removing, depositing, harbouring,
keeping, concealing, selling or purchasing, or in any
other manner dealing with any goods which he knows
or has reason to believe are liable to confiscation under
section 111,
shall be liable, -
Page 81 of 97
x xxxxxxxxxxxxxxxxxxxxxxxxxxxx
(iii) in the case of goods in respect of which the value
stated in the entry made under this Act or in the
case of baggage, in the declaration made under sec-
tion 77 (in either case hereafter in this section re-
ferred to as the declared value) is higher than the
value thereof, to a penalty not exceeding the differ-
ence between the declared value and the value
thereof or five thousand rupees, whichever is the
greater
x xxxxxxxxxxxxxxxxxxxxxxxxxxxxx”
From the above specific provision of quantum for imposition of penalty in case
of import over-valuation of goods, it is clear that law specifically seeks to
penalise the over-valuation of the imported goods.
16.5 Section 114AA of the Customs Act, 1962 deals with penalty for use
of false and incorrect material. The relevant provision is reporoduced below:
“114AA. Penalty for use of false and incorrect material. –
If a person knowingly or intentionally makes, signs or uses, or
causes to be made, signed or used, any declaration, statement or
document which is false or incorrect in any material particular, in the
transaction of any business for the purposes of this Act, shall be
liable to a penalty not exceeding five times the value of goods.
In the instant case documents, particularly invoices have been manipulated
for the purpose of over-valuation of imported goods. Further false and incorrect
declarations/statements have been made in the import documentation.
16.6.1 As per Rule 11 of the Foreign Trade (Regulation) Rules, 1993,
inter-alia on the importation into any customs port of any goods, whether liable
to duty or not, the owner of such goods shall in the bill of entry prescribed
under the Customs Act, 1962 state the value, among others of such goods to
the best of his knowledge and belief and shall subscribe a declaration to the
truth of such statement at the foot of such bill of entry.
Page 82 of 97
16.6.2 Further, as per Rule 14(1) of the Foreign Trade (Regulation) Rules,
1993, no person shall make, sign, or use or cause to be made, signed or used
any declaration, statement or document for the purpose of, inter-alia,
importing any goods knowing or having reasons to believe that such
declaration, statement or document is false in any material particulars.
Further, as per Rule 14 (2), ibid, no person shall employ any corrupt or
fraudulent practice for the purpose of, inter-alia, importing any goods.
16.6.3 In this case, value of the imported goods has been over-stated by
the importer for the purpose of siphoning off money from India to their related
entities overseas. The importer and owner of the imported goods has thus
declared value which to the best of their knowledge and belief was incorrect
and was over-stated, as brought out here-in-above. They have also subscribed
a declaration of the truth regarding the statement of value which declaration
appears to be false due to over-valuation of the goods. Also, the importer has
made, signed and used and/or caused to be made, signed and used the
declaration, statement and invoices of EIF for the purpose of importing the
goods knwong or having reasons to believe that such declarations, statement
and invoice were false in respect of the value stated therein. Further, the
importer has employed corrupt or fraudulent practice of over-valuation for the
purpose of importing the impugned goods.
16.6.4 Therefore, the importer appears to have violated the restrictions
and prohibitions as per Rules 11 and 14 ibid. It is a settled point of law that
any restriction is also a prohibition.
16.6.5 In view of the overvaluation of the imported goods as a past
planned modus operandi for siphoning off money abroad as discussed above, it
appears that MEGPTCL - the owner, through its Contractor PMC, have
imported good by declaring the value, which they knew that was not true and
thus imports were effected contrary to the prohibition imposed under the
Foreign Trade (Regulation) Rules, 1993 made under Section 19 of the FTDR
1992. Therefore the imported goods are also liable for confiscation under
Section 111(d) of the Customs Act, 1962(in addition to Section 111(m) as
discussed elsewhere) and the importer is liable to penalty under Section 112(a)
of the Customs Act, 1962.
Page 83 of 97
17.0 SUMMARY OF INVESTIGATION
17.1 From the investigations, as brought out in the foregoing paragraphs,
MEGPTCL;EIF; PMC; Shri Vinod ShatilalAdani; Shri Jatin Shah, Shri MiteshDani,Shri
MehulJaniof EIF and Shri Dharmesh Parekh & Shri Jaydev Mishra of PMC, appear to
have hatched a conspiracy to siphon off money abroad by way of indulging in over-
valuation in imports for projects subject to low or nil rateof Customs duty, so that
the incidence/burden of duty on the over-valued amount i.e cost of fund transfer is
minimal.
17.2 On the overseas front, MEGPTCL appears to have engaged the services of
a closely related party EIF to arrange for procurement from various OEMs for eventual
supply to M/s PMC Projects (India) Private, another firm managed and controlled by
the Adani Group. M/s Electrogen Infra FZE, UAE acting as a front for PMC and
MEGPTCL, appears to have acted as an intermediary invoicing agent to inflate the
invoice value in procurement of equipments and machinery required for installation in
the transmission line system from respective South Korean and Chinese OEMs. As a
part of the modus-operandi, though the goods were shipped directly to
PMC/MEGPTCL in India by the overseas suppliers who were OEMs, but for enabling
inflation of invoices, it was made to appear on paper as if the goods are being supplied
by EIF. Accordingly, back-to-back contracts were signed between PMC (the contractor
for MEGPTCL) and EIF, UAE in one hand and EIF, UAE and the four OEMs in the
other. But the facts that the back-to-back contracts of EIF with OEMs were signed in
India, that too by Shri Dharmesh Parekh, an employee of PMC, clearly shows that the
said supply contracts were planned, conceived and executed in India by same set of
persons and that it was a sham transaction.
17.3 The value inflation over the contract price of one of the OEM M/s
Hyundai Heavy Industries Co. Ltd., South Korea with Electrogen Infra FZE, UAE in the
back-to-back supply agreement executed by Electrogen Infra FZE, UAE with PMC
Projects (India) Private Limited, clearly shows the contract level variation of about
400% as depicted in Table-5, supra, which is reproduced below :-
(Table-5)
Contract Price comparison: PMC-EIF vis-à-vis EIF-HHICL
Particulars Amt. in US $
a) Price : PMC EIF, UAE Value as per agreement no. 415703 dated 01-10-2010 between M/s Electrogen Infra FZE and M/s PMC Projects (India) Private Limited
260,269,798
b) Price : EIF, UAE HHICL
Value as per agreement no. 700003 dated 05-10-2010 between M/s Hyundai Heavy Industries Co. Ltd. , South Korea and M/s Electrogen Infra
65,328,309
Page 84 of 97
FZE, UAE
DIFFERENCE 194,941,489
(a) as % of (b) 398%
17.4 In so far as the scope of supplies of Auto Transformers, Shunt Reactors
and spares thereof is concerned (excluding Disc Insulators and OPGW), two of the
employees of the Adani Group viz. Shri Mayur Shah, ex-employee of PMC and Vice
President of M/s Adani Ports & SEZ Limited and Shri Jaydev Mishra, Associate
General Manager of PMC have admitted to the identical scope of supply in both the
above agreements, during course of their statements recorded under Section 108 of
the Customs Act, 1962 on 17-02-2014, thereby lending direct credence to the
corresponding values depicted in the Table above and the back-to-back nature of the
two contracts. EIF proceeded to raise inflated invoices from time to time on PMC under
the contract no. 415703 dated 01-10-2010 inflation being to the tune of about 400%
of OEM value.
17.5 In so far as supply of Disc Insulators and OPGW fiber, hardware and
accessories are concerned, investigations have clearly brought out the back-to-back
nature of the sale contracts as narrated in above. The overall contract level over-
valuation is depicted in the Table-14 supra, which is reproduced below:-
(Table-14)
Contract Price as per Agreements between PMC & EIF vis-à-vis the Agreements
between EIF & three OEMs (Sediver, Dalian & Suzhou)
S.No Description of goods Price as per Agreement No.
415703/ 01-10-2010 as per
break-up given at Schedule 1
Price Schedule Summary
Sheet (USD)
Price as per
OEM
Agreements
(USD)
Difference
(USD)
C as % of D
(A) (B) (C) (D) (E) (F)
1. Disc Insulators (120 KN
+ 210 KN)
Sub-total of C
(C.I + CII)
83,794,854 11,876,920.2 71,917,933.8 705.53%
2 Optical Fiber Ground
Wire with hardware and
accessories
Sub-total D 32,131,000 2,637,757 29,495,243 1218.12%
17.6 Investigations have clearly brought out that for every procurement
invoice raised on M/s Electrogen Infra FZE, UAE by the respective OEM, M/s
Electrogen Infra FZE in turn have arranged to raise and issue a back-to-back invoice
on M/s PMC Projects (India) Private Limited, wherein they have inflated the OEM price
commensurate with the average contract level value inflation and invoiced the goods at
inflated prices.M/s PMC Projects (India) Private Limited arranged for the importation
and clearance of the goods on the strength of the inflated invoices, showing prices
which did not represent the actual value of the goods. As per arrangement, the goods
were directly shipped from the load ports in South Korea and China, to ports in
Page 85 of 97
India,from they were eventually cleared by M/s PMC Projects (India) Private Limited
for use in the project. Since the goods have been directly shipped from the load ports
in South Korea &China and utilised directly for the purpose of installation in the
transmission system, there appears to have been no value-addition to the goods at any
point of time from the time of their shipment from the overseas load ports till their
installation in India.Therefore, value addition in the form of value inflation of about
400% (average)towards the supply of goods procured from Hyundai Heavy Industries
Co. Ltd. and about 800% (average) in the case of supply of goods procured from other
OEMsviz. M/s Dalian Insulator Group Co. Ltd., M/s Sediver Insulators (Shanghai) Co.
Ltd. and M/sSuzhou Furukawa Power Optic Cable Co.Ltdappearsarbitrary and
unrealistic. MEGTPCL appears to have arranged for remittances to M/s Electrogen
Infra FZE, UAE towards the inflated prices in invoices raised by it, thereby enabling
extra remittances to their related entity M/s Electrogen Infra FZE.
17.7 The manner in which Consortium Agreement and the Supply Agreements
for and on behalf of EIF, UAE were signed by employees of PMC obliterates the
distinction between PMC &EIF and establishes commonality of their interest. They
appear to have acted as per a planned modus-operandi to siphon off money from India
by inflating invoices.
17.08 MEGTPCL, being a wholly owned subsidiary of Adani Enterprises
Limited, the listed flagship company of the Adani Group, through PMC appears to
have made extra remittances to the extent of the inflated amountsto the tune of nearly
Rs. 1493,84,72,484/- which appears to have been siphoned off abroad to and for the
benefit of their related party M/s Electrogen Infra FZE, UAE, in the guise of import
remittances by resorting to gross over-valuation of the imported goods.M/s Electrogen
Infra FZE on its part, therefore,appears to have actively connived with MEGTPCL and
PMC by arranging to raise invoices with inflated prices, being fully aware that the price
charged in its invoices had been grossly over-valued and did not represent actual
value of the goods at any point of time.
17.9 At the time of clearance of goods imported under 57 Bills of entry
mentioned in Annexure A, MEGTPCL, through PMC, arranged for presentation of the
inflated invoices of EIFto the customs authorities, on the basis of which they declared
value of the goods. The importer held out that the value declared therein represented
the Transaction Value paid or payable for the goods imported, being fully aware that
the value declared by them on the strength of inflated invoices raised by EIF did not
represent the actual value of the goods. Investigations have clearly brought out that
EIF has all along only acted as front for inflating the invoice value as part of the
modus-operandi. The admitted fact that an employee of PMC (Shri Dharmesh Parkeh)
signed agreements between EIF and the OEM, for and behalf of the overseas entity
EIFfortifies the allegation that EIF is only a front created by the Adani Group for
intermediary invoicing.Scanned image of relevant portions of the three contracts
Page 86 of 97
executed between EIF and the three OEMs showing the signature of Dharmesh Parekh
on behalf of EIF is given below :-
Contract Signed between EIF and Hyundai Heavy Industries Co. Ltd.
Contract signed between EIF and Sediver Insulators (Shanghai) Co. Ltd.
Page 87 of 97
Contract signed between EIF and Dalian Insulator Group Co. Ltd.
In effect, therefore, it would only be reasonable to infer that PMC,on behalf of
MEGPTCL, itself has entered into and executed two distinct sets of contracts with
differing consideration amounts, for the same set of goods;one set of contracts entered
into and executed by them with EIFwith inflated consideration amounts and the other
entered into and executed with respective OEMs, through their employee Dharmesh
Parekh, for consideration amounts which represented the actual Transaction Value of
the goods. Therefore, being privy to the procurement price of the goods through their
employee Shri Dharmesh Parekh, PMC were aware at all material times that the price
shown in the invoices raised by the front created by the Adani Group i.e. EIF, was
value inflation on paper and did not represent the actual price of the goods, for
reasons set out above.
17.10 A chart summarising the relationship between various contracts
pertaining to the goods imported by MEGPTCL through PMC for the transmission line
project from various OEMs with invoices routed through Electrogen Infra FZE, UAE is
shown below: -
Page 88 of 97
The chart clearly brings out the sham nature of the transactions between the
intermediary and PMC.
Page 89 of 97
17.11 Section 111(m) of the Customs Act, 1962 provides, inter-alia, that any
goods which do not correspond in respect of value or in any other particular with the
entry made under this Act are liable to confiscation. In the present case, the actual
value of the goods is forthcoming in the back-to-back invoices raised by various OEMs
on M/s Electrogen Infra FZE, being the procurement price paid by it, whereas the
invoices raised by M/s Electrogen Infra FZE on back-to-back basis on M/s PMC
Projects (India) Private Limited contain the inflated prices, arbitrarily raised, which do
not represent the actual value of the goods. The provisions of Section 111(m) are
squarely applicable in the present case, as the MEGPTCL through M/s PMC Projects
(India) Pvt. Ltd. , have produced inflated invoices to the custom authorities on the
strength of which the goods appear to have been assessed and cleared. The fact
regarding the actual prices being available in the procurement invoices of M/s
Electrogen Infra FZE, UAE, has been suppressed from jurisdictional customs
authorities in India with a view to facilitate the over-invoiced clearances. Accordingly,
the goods imported and cleared under 57 bills of entry having aggregate value of Rs.
1887,06,49,088/- crores (CIF)as detailed in the Annexure to Order dated 14-05-
2014 (RUD/D-76) issued under proviso to Section 110 (1) of the Customs Act, 1962 to
the owner M/s MEGTPCL and the importer M/s PMC Projects (India) Private Limited,
were seized under proviso to Section 110(1)of the Customs Act, 1962 with specific
directions that they should not remove, part with, or otherwise deal with the goods
except with the previous permission of the proper officer.
18.0 MEGPTCL- the Actual Importer
It is an admitted fact that MEGPTCL have categorically held themselves out to
be the importer, as is evident from categorical submissions made by them to this effect
in the various letters addressed to different government departments viz. the Principal
Secretary, (Energy)Industries, Energy and Labour Department, Government of
Maharashtra and the Commissioner of Customs, Kandla Custom House, from time to
time. They have also stated that they would be importing goods through M/s PMC
Projects (India) Private Limited, thereby implying that PMC Projects (India) Private
Limited would be filing bills of entry for the goods imported on their behalf. It is also
an admitted fact that they are the holders of Transmission Licence and beneficiary for
the monthly tariff fixed for utilizing the transmission of power through their
transmission lines. The project cost incurred by MEPGTCL appears to have been
funded on a 70:30 debt-equity ratio, with 70% capital costlent by Bank of India &ICICI
Bank and final sanction letter issued by State Bank of India &ICICI Bank Limited.
MEGTPCL has also assigned the transmission licence in favour of the Security
Trustee acting on behalf of Project lenders i.e M/s SBI Cap Trustees Co Ltd.In the
Purchase Order placed by MEGPTCL on M/s PMC Projects (India) Private Limited,
they have referred to themselves as the ‘Owner’ while referring to PMC Projects
(India) Private Limited as the ‘contractor/supplier’.MEGPTCL, therefore, appears
to be owner of the transmission facility and so also of the goods imported by them
Page 90 of 97
through PMC Projects (India) Private Limited installed as part of the said facility. As
per Section 2 (26) of the Customs Act, 1962, an importer in relation to any goods at
any time between their importation and the time when they are cleared for home
consumption, includes any owner or any person holding himself out to be importer. In
view of MEGPCL being the owner of the facility and in view of its holding itself to be
the importer, before the jurisdictional Customs authorities for the purpose of availing
concessional rate of duty under Project Import, it appears that MEGPTCL is the de-
facto importer though Bills of Entry have been filed by PMC by arrangement. Further
as discussed earlier, remittances against import of goods from EIF have been directly
from the account of MEGPTCL against transferable Letters of Credit. Payments for
imports have not been made by PMC to EIF-the intermediary against their invoices
though theinvoices were raised on PMC. The fact that the remittances for the imports
were made directly from the accounts of MEGPTCL to EIF also corroborates the facts
that MEGPTCL is the owner and the actual importer of the goods.
19.0 ROLES FOR PENALTY
19.1 From the foregoing investigations, it appears that MEGPTCL, PMC
Projects (India) Private Limited and M/s Electrogen Infra FZE, UAE,various related
entities of Adani Group;Shri Vinod ShatilalAdani @ Vinod Shantilal Shah; Shri Jatin
Shah; Shri MiteshDani& Shri MehulJani of EIF;ShriDharmesh Parekh and Shri
Jaydev Mishra of PMC, conspired between themselves to execute the planned
conspiracy of siphoning off foreign exchange abroad to and for the benefit of their
related entity. M/s Electrogen Infra FZE, UAE, appears to have been created as a front
for siphoning off of money inthe guise of outward remittancesfor over-valued imports,
by indulging in invoice inflation. In their above act of conspiracy, they were aided and
abetted by Shri Vinod Shatilal Adani; Shri Jatin Shah; Shri Mitesh Dani&Shri Mehul
Jani of EIF and Shri Dharmesh Parekh &Shri Jaydev Mishra of PMC.
19.2. EIF - the created UAE based intermediary, on their part, knowingly and
intentionally arranged for supply of goods to MEGTPCL through PMC Projects (India)
Private Limited by raising invoices depicting grossly inflated prices, which did not
represent the actual price of the goods. EIF were aware at all material times that
actual price of the goods were available in the invoices raised on them by various
OEMs , and they had made remittances as per the prices shown in the OEM invoices
against procurements from the respective OEM. Interestingly, the contract for supply
of goods, between EIF and OEM (HHICL) was signed in India by an employee of PMC,
thus obliterating distinction between PMC and EIF. M/s Electrogen Infra FZE, UAE
and PMC,therefore, appear to be hand-in-glove for the arbitrary value inflation of
goods supplied to MEGTPCL through M/s PMC Projects (India) Private Limited.
MEGPTCL, by virtue of direct and close relationship with the intermediaryinvoicing
agentEIFand common business interest, also appear to have proceeded to import and
clear goods through PMC Projects (India) Private Limited, by producing inflated
invoices raised by EIF to the customs authorities at the time of clearance,being fully
Page 91 of 97
aware that the goods imported by them had been over-invoiced and value declared on
the basis of the EIF’s invoice pricesdid not represent actual value of the goods. PMC
Projects (India) Private Limited acted as a conduit and appears to have actively
connived with the owner, MEGPTCL and the invoicing intermediary EIFin their
objective of siphoning off foreign exchange by resorting to over-valuation by filing bills
of entry and arranging for clearance of goods. MEGTPCL, EIF and M/s PMC Projects
(India) Private Limited have in relation to the goods imported and cleared under bills of
entry detailed atAnnexure-A to this notice , have done acts, or omitted to act or have
abetted the commission or omission of the said acts, which appear to have rendered
the goods of declared value of Rs. 1887,06,49,088/- CIF (Assessable value of Rs.
1905,93,55,579/-)liable to confiscation under Section value 111(d) and Section
111(m) of the Customs Act, 1962.Consequently, MEGTPCL, Electrogen Infra FZE,UAE
and M/s PMC Projects (India) Private Limitedappear to have rendered themselves
liable to penalty under Section 112 (a) & (b) and 114 AA of the Customs Act, 1962.
19.3 Shri Jatin Shah (ex-employee of the Adani Group) and Director of
overseas supplier M/s Electrogen Infra FZE, UAE; Shri Mitesh Dani&Shri Mehul Jani,
both Indian nationals and employees of EIF, under the influence and guidance of Shri
Vinod Shantilal Adani, appear to have indulged in raising invoices on M/s PMC
Projects (India) Pvt. Ltd. for supply of goods to MEGPTCL, knowing fully well that price
charged in such invoices did not represent the actual value of the goods. Such
invoices have been raised and issued under the signature of one of the above named
three employees of M/s Electrogen Infra FZE, UAE from time to time. Despite,
repeated summons issued in their name seeking their presence with documents
(procurement invoices raised on Electrogen Infra FZE, UAE by various OEMs), they
appear to have deliberately avoided presenting themselves before the DRI to co-operate
with the on-going investigations, on one plea or the other. Shri Jatin Shah, Shri
Mitesh Dani, and Shri Mehul Jani, led by Shri Vinod Shantilal Adani, have done acts,
or omitted to act or have abetted the commission or omission of the said acts, which
appear to haverendered the goods of declared value of Rs. 1887,06,49,088/- CIF
(Assessable value of Rs. 1905,93,55,579/-)liable to confiscation under 111(d) and
Section 111(m) of the Customs Act, 1962. They have been signatories to contractual
documents/agreements with inflated consideration as well as to inflated invoices
raised from time to time on PMC, knowing full well that the contract consideration
and/or invoice price did not represent the actual value of the goods on account of
being privy to OEM contract price/OEM invoices showing actual Transaction Value.
Consequently, Shri Vinod Shantilal Adani,Shri Jatin Shah, Shri Mitesh Dani, and Shri
Mehul Jani appear to have rendered themselves liable to penalty under Section 112
(a)& (b) and under Section 114AA of the Customs Act, 1962.
19.4 Shri Jaydev Mishra, Associate General Manager, and Shri Dharmesh
Parekh, Senior Manager, both employees of M/s PMC Projects (India) Private Limited,
sharing a senior-subordinate relationship between them within the company, who
were also ex-employees of the Adani Group,appear to have aided and abetted in above
Page 92 of 97
modus-operandi of siphoning off money by invoice inflation of imported goods. Shri
Dharmesh Parekh, having admittedly signed the three Agreements by and between
M/s Electrogen Infra FZE, UAE and each of the three OEMs viz. M/s Hyundai Heavy
Industries Co. Ltd. , South Korea; M/s Dalian Insulator Group Co. Ltd. and M/s
Sediver Insulators (Shanghai) Co. Ltd. appears to have been fully aware of the
consideration mentionedtherein and thereby the actual prices of the goods. As
signatory to the Consortium Agreement and Power of Attorney for Lead Member, both
dated 16-08-2010, he appears to be aware of the purpose and objective thereof. As a
signatory (as a witness) to the back-to-back supply agreement bearing No. 415703
dated 01-10-2010, between M/s Electrogen Infra FZE and PMC Projects (India) Pvt.
Ltd., he appears to have been aware of the scope of supply covered therein as well as
the consideration amount, the agreement also having been signed by his superior Shri
Jaydev Mishra, on behalf of M/s PMC Projects (India) Private Limited. Thus, in his
capacity as signatory to the various agreements/contracts, it is evident that Shri
Dharmesh Parkeh was aware at all material times that the scope of supply &
description of goods covered in the four agreements between the OEMs and Electrogen
Infra FZE, UAE, were identical to the scope of supply and description of goods covered
in the single back-to-back agreement bearing No. 415703 dated 01-10-2010 executed
between M/s Electrogen Infra FZE, UAE and M/s PMC Projects (India) Private
Limited.Therefore, he was aware of the consideration covered by the two sets of
agreements :- (i) between EIF and OEMs(ii) the corresponding back-to-back agreement
between EIF and PMC-each such agreement having been signed by him and so also
about the substantial difference in the agreement values/consideration covered by the
two sets of agreements for identical scope of supply & description of goods. It follows
that Shri Jaydev Mishra, as his superior, and signatory to the Agreement 415703
dated 01-10-2010, as a controlling officer of his sub-ordinate Shri Dharmesh Parekh,
also appears to be fully aware about the substantial difference in the agreement
values/consideration covered by the two sets of agreements for identical scope of
supply & description of goods. On being shown a copy of theAgreement No. 700003
dated 5th October 2010 between M/s Electrogen Infra FZE, UAE and M/s Hyundai
Heavy Industries Co. Ltd. , South Korea, which his sub-ordinate had signed for and
behalf of M/s Electrogen Infra FZE, UAE, he,inter-alia,categorically admitted to his
sub-ordinate Shri Dharmesh Parekh having signed the said Agreement no. 700003
dated 05-10-2010 for and on behalf of M/s Electrogen Infra FZE, UAE in capacity of
authorized signatory. Therefore, Shri Jaydev Mishra in his capacity as a superior to
Dharmesh Parekh, also appears to have been fully aware of substantial difference in
the agreement values/consideration covered by the two sets of agreements for
identical scope of supply & description of goods. Yet, they proceeded to allow the
concerned officials in their company M/s PMC Projects (India) Private Limited to file
bills of entry on behalf of MEGPTCL and have the goods cleared on the strength of
inflated invoices raised in conformity with inflated consideration covered by agreement
no. 415703 dated 01-10-2010. Therefore,Shri Jaydev Mishra, Associate General
Manager, and Shri Dharmesh Parekh, Senior Manager of M/s PMC Projects (India)
Private Limited have done acts, or omitted to act or have abetted the commission or
Page 93 of 97
omission of the said acts, which appear to haverendered the goods of declared value of
Rs. 1887,06,49,088/- CIF (Assessable value of Rs. 1905,93,55,579/-)liable to
confiscation under 111(d) and Section 111(m) of the Customs Act, 1962. In view of
their superior-sub-ordinate relationship, they were aware at all material times that the
consideration amount agreed by and between EIF and PMC was an inflated one and
not based on actual Transaction Value of the goods. Yet they proceeded to sign
contractual documents as shown in Table-18.Consequently, Shri Jaydev Mishra,
Associate General Manager, and Shri Dharmesh Parekh, Senior Manager of PMC
appear to have rendered themselves liable to penalty under Section 112 (a) & (b) and
Section 114AAof the Customs Act, 1962.
20. Out of the 57 consignments, (26 at merit rate of duty and 31 on
concessional rate of duty under heading 98.01) covered at Annexure A to this show
cause notice, two consignments(740818/03-03-2011& 9871984/16-04-2013)have
been cleared through Nhava Sheva and the remaining 55 consignments have been
cleared through Mundra Sea port. The adjudicating authority for the imports effected
through NhavaSheva Port is the Commissioner of Customs, ( Import), Jawahar Lal
Nehru Custom House, NhavaSheva, TalukaUran, District Raigad, Maharashtra-
400707, and for the imports effected through Mundra Port is the Commissioner of
Customs, Custom House, Kandla, having his office having his office near Balaji
Temple, Kandla-370210.
21. Now, therefore, M/s MEGPTCL; M/s PMC Projects (India) Private
Limited; M/s Electrogen Infra FZE, UAE;, Shri Vinod ShantilalAdani @Vinod Shantilal
Shah; Shri Jatin Shah, Shri MiteshDani& Shri MehulJani - all
employees/representatives of EIF; and Shri Jaydev Mishra, Associate General Manager
& Shri Dharmesh Parekh, Senior Managerof M/s PMC Projects (India) Private Limited
are hereby called upon to show cause,within 30 days of receipt of this notice,to the
respective adjudicating authorities as under :-
(A) With respect to goods imported through Mundra Port (i.e 55
consignments - Sr.No. 1 to 44, Sr.No. 46 and Sr.Nos. 48 to 57) to the Commissioner
of Customs, Custom House, Kandla, having his office near Balaji Temple, Kandla-
370210
(I) M/s PMC Projects (India) Private Limited,the importer on record (as per
Bills of Entry); and MEGPTCL who are the owner of imported goods and who have held
themselves out as importer,are required to show cause as to why :-
i) the declared value (transaction value based on sham transaction between
EIF and PMC) in respect of equipments & machinery imported under 55
bills of entry having cumulative declared value of Rs. 1867,24,06,746/-
(CIF)(individual bill of entry-wise CIF valueshown under column E of
Annexure A) should not be rejected under Rule 12 of the Customs Valu-
Page 94 of 97
ation (Determination of Prices of Imported Goods) Rules, 2007 read with
Section 14 of the Customs Act, 1962.
ii) the declared value in respect of equipments & machinery imported under
55 bills of entry listed, at Annexure A,should not be re-determined cu-
mulative as Rs. 390,15,34,182/-(CIF)(individual bill of entry-wise CIF
valueshown under column K of Annexure A)on the basis of actual
Transaction Value available in the OEM invoice prices shown at column
J thereof, in terms of Rule 4 of the CVR,2007 read with Section 14 of the
Customs Act, 1962.
iii) Goods covered by 55 bills of entry, having aggregate declared value of Rs.
1867,24,06,746/-(CIF),as detailed at Annexure A to this notice, import-
ed & cleared in pursuance of Agreement No. 415703 dated 01-10-2010
by PMC, for and on behalf of the owner M/s MEGPTCL,seized under Or-
der dated 14-05-2014 issued under proviso to Section 110(1) of the Cus-
toms Act, 1962 should not be confiscated under 111(d) and Section
111(m) of Customs Act, 1962.
iv) Penalty under Section 112 (a) & (b)of the Customs Act, 1962 should not
be imposed on each one of them in relation to the above goods.
v) Penalty under Section 114AA of the Customs Act, 1962 should not be
imposed on them.
II) M/s Electrogen Infra FZE, UAE; Shri Vinod Shantilal Adani @Vinod
Shantilal Shah and Shri Jatin Shah, Shri Mitesh Dani and Shri Mehul Jani, all
employees of M/s Electrogen Infra FZE, UAE are required to show cause to the
adjudicating authority as to why penalty under Section 112 (a) & (b) and Section 114
AA of the Customs Act, 1962 should not be imposed on each one of them in relation to
the goods imported under the 55 Bills of entry.
III) Shri Jaydev Mishra, Associate General Manager, andShri Dharmesh
Parekh, Senior Manager, both employees of M/s PMC Projects (India) Private Limited,
are required to show cause to the adjudicating authority as to why penalty under
Section 112 (a) &(b) and Section 114AA of the Customs Act, 1962 should not be
imposed on each one of them in relation to above goods imported under 55 Bills of
entry.
(B) With respect to goods imported through Nhava Sheva Port, (i.e
twoconsignments - Sr.No. 45 and 47 of Annexure A) to the Commissioner of Customs,
Commissioner of Customs, (Port Import), Jawahar Lal Nehru Custom House,
having his office at Nhava Sheva, Taluka Uran, District Raigad, Maharashtra-400707
:-
(I) M/s PMC Projects (India) Private Limited,the importer on record (as per
Bills of Entry); and MEGPTCL who are the owner of imported goods and who have held
themselves out as importer are required to show cause as to why :-
Page 95 of 97
i) the declared value (Transaction Value based on sham transaction between
EIF and PMC) in respect of equipments & machinery imported under the two
bills of entry (Sr.No. 45 & 47 of Annexure A) having cumulative declared
value of Rs. 19,82,42,342/-(respective bill of entry-wise value shown at
sr.No. 45 & 47 of column E of Annexure A),should not be rejected under the
provisions of Rule 12 of the CVR, 2007 read with Section 14 of the Customs
Act, 1962.
ii) the declared value in respect of equipments & machinery imported under
two bills of entry (Sr.No. 45 and 47 of Annexure A) should not be re-
determined cumulatively as Rs.3,06,42,423/- CIF (respective bill of entry
wise value as shown at Sr.No.s. 45 and 47 of column K) on the basis of ac-
tual transaction value available in the OEM invoice price shown at column J
thereof, in terms of Rule 4 of the CVR-2007 read with Section 14 of the Cus-
toms Act, 1962.
iii) Goods covered by two bills of entry, having aggregate declared value of Rs.
19,82,42,342/-(CIF) as detailed at Sr.No. 45 & 47 of Annexure A to this no-
tice, imported & cleared in pursuance of Agreement No. 415703 dated 01-
10-2010 by M/s PMC Projects (India) Private Limited for and on behalf of the
owner MEGPTCL, seized under Order dated 14-05-2014 issued under provi-
so to Section 110(1) of the Customs Act, 1962 should not be confiscated un-
der 111(d) and Section 111(m) of Customs Act, 1962.
iv) Penalty under Section 112 (a) &(b) of the Customs Act, 1962 should not be
imposed on each one of them in relation to goods imported under the two
bills of entry.
v) Penalty under Section 114AA of the Customs Act, 1962 should not be im-
posed on them.
II) M/s Electrogen Infra FZE, UAE, Shri Vinod Shantilal Adani @Vinod
Shantilal Shah, Shri Jatin Shah, Shri Mitesh Dani, Shri Mehul Jani, all employees of
M/s Electrogen Infra FZE, UAE are required to show cause to the adjudicating
authority as to why penalty under Section 112 (a) & (b) and Section 114AA of the
Customs Act, 1962 should not be imposed on each one of them in relation to the
goods imported under the two bills of entry.
III) Shri Jaydev Mishra, Associate General Manager, and Shri Dharmesh
Parekh, Senior Manager - both employees of M/s PMC Projects (India) Private Limited,
are required to show cause to the adjudicating authority as to why penalty under
Section 112 (a) & (b) and Section 114AA of the Customs Act, 1962 should not be
imposed on each one of them in relation to above goods imported under the two bills
of entry.
22.0 Each of the above noticee, is required to submit a written reply to the
Adjudicating Authority within 30 days from the date of receipt of this notice. In their
written reply, the noticees may also indicate as to whether they would like to be heard
in person. In case no reply is received within the time limit stipulated above or any
Page 96 of 97
further time which may be granted and/or if nobody appears for personal hearing,
when the case is posted for the same, the case will be decided ex-parte on the basis of
evidence on record and without any further reference to the noticees.
23.0 The relied upon documents (RUD) are listed in Annexure ‘R’. Softcopies
of which are being supplied alongwith this notice in a CD. If, before filing replies to
this notice, the noticees desire to inspect any documents, which are relied upon, they
may do so with prior permission of the Deputy Director, Commercial Intelligence (C.I.)
Cell, 5th Floor, 13, Sir Vithaldas Thackersey Road, New Marine Lines, Mumbai 400
020 on any working day.
24.0 This show cause notice is being issued under section 124 of the Customs
Act-1962, without prejudice to any other action that may be taken in respect of the
above goods and / or the persons / firms mentioned in the notice under the provisions
of the Customs Act, 1962 and / or any other law for the time being in force in the
Republic of India.
(P.K. DASH)
ADDITIONAL DIRECTOR GENERAL
Encl :Annexure A&Annexure R
1. M/S MAHARASHTRA EASTERN GRID POWER TRANSMISSION COMPANY LIMITED (MEGPTCL), ‘ADANI HOUSE’, MITHAKHALI SIX ROADS, NAVRANGPURA, AHMEDABAD 380 009
2. M/S PMC PROJECTS (INDIA) PRIVATE LIMITED,
REGISTEREDOFFICE : AIIM, AT SHANTIGRAM, NEAR VAISHNODEVI CIRCLE, SG HIGHWAY,
AHMEDABAD-382421
3. M/S ELECTROGEN INFRA FZE, SAIF PLUS, R4, 38/A,SAIF ZONE, P.O.BOX 122528, SHARJAH UNITED ARAB EMIRATES
4. SHRI VINOD SHANTILA SHAH alias VINOD SHANTILAL ADANI, ADANI HOUSE NR MITHAKHALI CIRCLE NAVRANGPURA AHMEDABAD 380 009 GUJARAT
5. SHRI JATIN SHAH
Page 97 of 97
SAIF PLUS, R4, 38/A,SAIF ZONE, P.O.BOX 122528, SHARJAH UNITED ARAB EMIRATES
6. SHRI MITESH DANI
SAIF PLUS, R4, 38/A,SAIF ZONE, P.O.BOX 122528, SHARJAH UNITED ARAB EMIRATES
7. SHRI MEHUL JANI, SAIF PLUS, R4, 38/A,SAIF ZONE, P.O.BOX 122528, SHARJAH UNITED ARAB EMIRATES
8. SHRI JAYDEV MISHRA, ASSOCIATE GENERAL MANAGER, M/S PMC PROJECTS (INDIA) PRIVATE LIMITED,
REGISTEREDOFFICE : AIIM, AT SHANTIGRAM, NEAR VAISHNODEVI CIRCLE, SG HIGHWAY, AHMEDABAD-382421
9. SHRI DHARMESH PAREKH, SENIOR MANAGER, M/S PMC PROJECTS (INDIA) PRIVATE LIMITED,
REGISTEREDOFFICE : AIIM, AT SHANTIGRAM, NEAR VAISHNODEVI CIRCLE, SG HIGHWAY, AHMEDABAD-382421
Copy to :
i) The Commissioner of Customs, Kandla ii) The Commissioner of Customs, (Import), Nhava Sheva iii) The Deputy Director, B Cell, DRI, MZU, Mumbai