D. Beavis (BNL) HFT Workshop March 10-11, 2009 BNL HFT Beam Pipe and Safety.
-
Upload
rebecca-allen -
Category
Documents
-
view
215 -
download
0
Transcript of D. Beavis (BNL) HFT Workshop March 10-11, 2009 BNL HFT Beam Pipe and Safety.
D. Beavis (BNL)D. Beavis (BNL)
HFT WorkshopHFT Workshop
March 10-11, 2009March 10-11, 2009
BNLBNL
HFTHFTBeam PipeBeam Pipe
andand
SafetySafety
ScheduleSchedule
item schedule Completion Dates
STAR (E&D) (start) 7/24/09
Bid (complete) 12/24/09 1/27/10
Manufacturer Engineering (complete)
2/24/10 (3/24/10)
Fabrication 1/24/11
Acceptance BNL 3/24/11
NEG coating 5/24/11
BNL prepare for Install 7/24/11 (8/24/11)
Total 24 months (25 months)
CostCost
Estimate $292,000 with 20% cont. for a Estimate $292,000 with 20% cont. for a total of $350,000total of $350,000
Actual $327,116 Actual $327,116
CommentsComments
PHENIX pipe came in one week agoPHENIX pipe came in one week ago They are confident it will be installedThey are confident it will be installed There was trouble with fabrication of PHENIX pipe There was trouble with fabrication of PHENIX pipe
and this is causing a few weeks delay in our customer and this is causing a few weeks delay in our customer prints to address issuesprints to address issues
PHENIX pipe length out of tolerance and roundness PHENIX pipe length out of tolerance and roundness was just acceptable.was just acceptable.
The pipe was “dirty” insideThe pipe was “dirty” inside
Although nearly on schedule there is still lots of Although nearly on schedule there is still lots of opportunities to be late for our pipeopportunities to be late for our pipe
Remaining itemsRemaining items
Outside sections--design and orderOutside sections--design and orderBellows and mountsBellows and mountsHeating blanketsHeating blanketsBlanket insertion deviceBlanket insertion device
HFT SafetyHFT Safety
Have a pHAD (preliminary Hazard Have a pHAD (preliminary Hazard Analysis Document)Analysis Document)
pHAD and Design Questionnaire sent to pHAD and Design Questionnaire sent to safety in C-AD on Sept. 30, 2009safety in C-AD on Sept. 30, 2009
Update to a HAD for CD-2Update to a HAD for CD-2Send an updated version of pHAD (HAD) Send an updated version of pHAD (HAD)
to safety people in about 2 monthsto safety people in about 2 months
SafetySafety
Individual items can be addressed as Individual items can be addressed as neededneeded
Fire test of carbon fiber is pending (FGT)Fire test of carbon fiber is pending (FGT)Paperwork found for lifting fixture (550 #)Paperwork found for lifting fixture (550 #)Others as they come upOthers as they come up