Cycle Time Definitions and Line Balancing (Yamazumi) Charting · Cycle Time Definitions and Line...
Transcript of Cycle Time Definitions and Line Balancing (Yamazumi) Charting · Cycle Time Definitions and Line...
EDMM 4870
Cycle Time Definitions and
Line Balancing (Yamazumi)
Charting
1
EDMM 4870
2
EDMM 4870
Ideal Cycle Time:
The maximum time (generally in seconds) to perform a process; in terms of
Standardized Work, it is the Total Time to perform the entire cycle.
Cycle time definitions:
1. Where there are a series of processes that are linked, there will be a
“Maximum Cycle” and a “Minimum Cycle” time.
2. The Ideal Process is where the Maximum and Minimum are equal.
3. Cycle time should not include delays and outside interference. It should
include everything on the Standardized Work / Job Break down Sheet.
Actual Cycle Time:
The maximum time (generally in seconds) to perform a process; in terms of
Standardized Work, it is the Total Time to perform the entire cycle, plus the Periodic
Work is added in.
3
EDMM 4870
Each of these operations is required to make one finished good. There
are 8 operations and the critical cycle or “bottle neck” is 20 seconds.
Operation01
Operation02
Operation03
Operation04
Operation05
Operation06
Operation07
Operation08
Series1 16 19 14.5 17.5 20 11.25 12.5 17
0
5
10
15
20
25
Sec
on
ds
4
EDMM 4870
Identifying Waste in Cycle Imbalance:
1. Find the “Critical Cycle” or “Bottleneck”
2. The time not being utilized by the other processes is waste.
Operation01
Operation02
Operation03
Operation04
Operation05
Operation06
Operation07
Operation08
Series1 16 19 14.5 17.5 20 11.25 12.5 17
0
5
10
15
20
25
Sec
on
ds
5
EDMM 4870
Operation01
Operation02
Operation03
Operation04
Operation05
Operation06
Operation07
Operation08
Waste 4 1 5.5 2.5 0 8.75 7.5 3
Seconds 16 19 14.5 17.5 20 11.25 12.5 17
4 1 5.5 2.5 0 8.75 7.5 3
0
5
10
15
20
25
Sec
on
ds
4 + 1 + 5.5 + 2.5 + 8.75 + 7.5 + 3 = 32.25 seconds waste
6
EDMM 4870
How much labor is being wasted in this process?
“Critical Cycle is 17.8
seconds
All the processes are limited by the “bottleneck”, which is 17.8 seconds.
17.8 x 6 operations = 106.8 seconds will be worked to produce one Unit.
The “Actual” Labor is 12.35s + 14.22s +17.8s + 13.5s + 11.91s + 8.44s = 78.22 seconds.
EXERCISE 01 – Processes 1 through 6 are in series and will result in one (1) Unit
7
EDMM 4870
106.8s - 78.22s = 28.58 seconds are being wasted per unit.
In this example, let’s say this is a supplier to you and you believe their price is too high. They
disclose to you that their fully loaded cost is $68.00/hour, and you think they are about $0.25
too high for the part that you are buying from them, is there hope to reduce the price?
EXERCISE 01 – Processes 1 through 6 are in series and will result in one (1) Unit
8
EDMM 4870
At 28.58 seconds of wasted labor per part (which is 0.0079 hours/part) and a loaded cost of
$68.00/hour, the supplier has approximately ($68.00 x 0.0079 = ) $0.54 of added costs to the
part.
You thought we were paying about $0.25 too much, does there seem to be some data to
support that?
Remember:
to convert
seconds to hours;
divide by 3,600.
So, 25.58 / 3,600
= 0.0079 hours.
9
EDMM 4870
Working with the supplier and showing them some basic Lean principles and tools, the process has been
better balanced (see chart on right). “Critical” or “Bottleneck” cycle is Process 2, and it is 15.34.
The new waste is now 13.74 seconds; or 0.0038 hours; at $68.00/hr. = $0.2595.
This new line balance has reduced the wasted labor by (previous was) $0.54 - $0.26 = $0.28.
Now you can negotiate the $0.25 price reduction, they keep the $0.03, and all the learning from the
improvement event.
12.35
15.34 15.11 15.15
11.91
8.44
0
2
4
6
8
10
12
14
16
18
Process 1 Process 2 Process 3 Process 4 Process 5 Process 6
Tasks move to Operations 2 and 4.
10
EDMM 4870
Line balancing (Yamazumi)
• Line Balancing is leveling the workload across all processes in a cell or value stream to remove bottlenecks and excess capacity.
• A constraint slows the process down and results if waiting for downstream operations and excess capacity results in waiting and no absorption of fixed costs.
11
EDMM 4870
Yamazumi Chart (Stack or Pillar charting):
12
Line Balance ChartTakt Time (27sec)
13
Line Balance
• Show visually what each Team Member is doing
• How close each operation is loaded to Takt time
• Identify waste:
– Waste is incurred whenever there is unnecessary movement or
excessive wait time or rework (Correction)
– Error of most companies is to “balance the load among Team
Members “. This does not make the waste obvious
– Minimize walking time
14
Cycle Time
• Amount of time to process 1 unit
• Includes human & machine work, walking & waiting time
• Determine by taking the average time to process one part
15
Theoretical # of Associates = = = 3.6 = 4 AssociatesTotal Work Time
Takt Time
13+28+16+19+22
27
Takt Time (27sec)
16
Methods for Loading Team Member
Waste Waste Waste Waste
Takt
Takt
Waste is not obvious! i.e. not
likely to be addressed
When allocating work, try NOT to
balance work between Team
Members. Load individual Team
Members as close to Takt time
as possible!
Make waste more obvious & more
likely to be addressed!
Waste
Waste
Waste
17
Value Added, generally are defined as any processing that is converting raw
materials / components to what the Customer wants.
Here are some examples:
1. It must transform the product or service.
2. The customer must be willing to “pay” for it.
3. It must be done correctly the first time.
Therefore, anything that does not fit these definitions, will fall in the category of
“waste”.
• Corrections – Reworking
• Over Producing
• Motion that adds no value
• Material Movement / Transportation and Handling
• Waiting (machine and/or Team Member)
• Inventory
• Process Inefficiencies18
EDMM 4870
The Team Member is
working in a process
where the equipment
cycles every 25 seconds.
How much Idle (Waste)
did the Engineer who
launched this process
design for this Team
Member?
Cycle Time = 25s;
25.0 – (All Value Added
Time;
1.89s + 2.45s + 2.10s +
0.89s.) =
17.67 seconds.19
EDMM 4870
If this Team Member is being paid $16.50 / hour and Fringes and Benefits increase this
cost to $23.60 / hour and the team member will work at this job all year, how much are they
being paid to add no value to the product? (Reminder; the process makes a part every 25
seconds and for this exercise, the process runs 7.2 hours a shift and there are 245 working days
in a year.
Because most hourly Team Members are paid by the ‘hour’, we need to convert the
wasted time of 17.67 seconds into hour’s:
0.0049 hour per part of wasted time x ((7.2 hours x 3600)/ 25 seconds per part) x 245
working days a year) x $23.50/hour (including fringes) =
$29,249.94 of the $48,880 (2,080 hours x $23.50) is paid to this team member to do nothing
that adds value to the product; almost 60%.
20
Process 01Process 02
Process 03Process 04
Raw
Material
Finished
Material
Example 01:
In this process, there is only one team member performing all the processes. Please note that the time to
get the raw material from the tote is included in the total cycle time of Process 01. Also, Process 04 includes
the time to perform Process 04 and place the item in the Finished goods container and step back to the
Raw Material container.
Question 01; How much total Labor is there for making one complete unit?
Question 02: How much Line Imbalance it their in this layout?
Question 03; If this process runs 3 shifts a day, 245 days a year and there is 320 minutes per shift (with
OEE and PFD removed), how many parts will this process manufacture in a year?
25
28
25
17
0
5
10
15
20
25
30
Process 01 Process 02 Process 03 Process 0421
Process 01Process 02
Process 03Process 04
Raw
Material
Finished
Material
Example 01: In this process, there is only one team member performing all the processes. Please note that the time to get the raw
material from the tote is included in the total cycle time of Process 01. Also, Process 04 includes the time to perform
Process 04 and place the item in the Finished goods container and step back to the Raw Material container.
Question 01; How much total Labor is there for making one complete unit?
25s + 28s+ 25s + 17s = 95 seconds
Question 02: How much Line Imbalance it their in this layout?
None. With only one team member operating each station, there is no
imbalance.
Question 03; If this process runs 3 shifts a day, 245 days a year and there is 320 minutes per shift (with OEE and
PFD removed), how many parts will this process manufacture in a year?
(245 days x 3 shifts x 320 minutes/shift x 60 seconds/minute ) / 95 seconds =
148,547 per year.
25
28
25
17
0
5
10
15
20
25
30
Process 01 Process 02 Process 03 Process 0422
Process 01Process 02
Process 03Process 04
Raw
Material
Finished
Material
Example 02
The process is not different for cycle time and activity per process, however, your customer has called and
their annual demand is increasing from 140,000 units a year, to 250,000 units a year.
Question 01; What do you propose be done to meet the new demand?
Question 02: How much Line Imbalance it their in this layout?
25
28
25
17
0
5
10
15
20
25
30
Process 01 Process 02 Process 03 Process 0423
Process 01Process 02
Process 03Process 04
Raw
Material
Finished
Material
Example 02
The process is not different for cycle time and activity per process, however, your customer has called and
their annual demand is increasing from 140,000 units a year, to 250,000 units a year.
Question 01; What do you propose be done to meet the new demand?
Add a team member and combine processes. Because Process 01 and 03 are the
same value, there is no advantage if process 01 and 02 are combined, versus 02 and
03; they will always add up to 53 seconds, while the other process is (25 + 17) 42
seconds. Using the total of 14,112,000 seconds in a year and divide this by 53
seconds (the critical cycle time) = the annual yield is 266,264; which exceeds the
Customer requirement of 250, 000 units per year.
Question 02: How much Line Imbalance it their in this layout?
Refer to the answer in Question 01; where we see 42 seconds and 53 seconds; so
the line balance is (42 / 53 ) = 79%.
25
28
25
17
0
5
10
15
20
25
30
Process 01 Process 02 Process 03 Process 0424
Example 03
The process is not different for cycle time and activity per process, however, the process is now staffed with
four (4) Team members; one at each station. Still 320 minutes per shift x 3 shifts x 245 working days/year.
Question 01; What is the potential yield per year?
Question 02: How much Line in the same layout, but staffed with four team members?
Question 03; How much waste is there in this line balance ( in seconds )?
25
28
25
17
0
5
10
15
20
25
30
Process 01 Process 02 Process 03 Process 04
Process 01Process 02
Process 03Process 04
Raw
Material
Finished
Material25
Example 03
The process is not different for cycle time and activity per process, however, the process is now staffed with
four (4) Team members; one at each station. Still 320 minutes per shift x 3 shifts x 245 working days/year.
Question 01; What is the potential yield per year?
14,112,000 seconds/year divide by maximum cycle time (28 seconds) = 504,000/yr.
Question 02: What is the new line balance?
Minimum Cycle / Maximum Cycle 17 / 28 = 60.7%
Question 03; How much waste is there in this line balance ( in seconds )?
Maximum Cycle time x number of Team Members – Aggregated Time;
28 seconds x 4 = 112 seconds – 95 seconds (25s + 28s+ 25s + 17s) =
17 seconds
25
28
25
17
0
5
10
15
20
25
30
Process 01 Process 02 Process 03 Process 04
Process 01Process 02
Process 03Process 04
Raw
Material
Finished
Material26
Example 04
The process is not different for cycle time and activity per process, however, the process is now staffed with
four (4) Team members; one at each station. Still 320 minutes per shift x 3 shifts x 245 working days/year.
Question 03; How much waste is there in this line balance ( in seconds )?
Maximum Cycle time x number of Team Members – Aggregated Time;
28 seconds x 4 = 112 seconds – 95 seconds (25s + 28s+ 25s + 17s) =
17 seconds
Question 01: Referring to the answer from Example 03, if our fully burdened cost is $75.00 per hour, how
much is this imbalance costing us?
25
28
25
17
0
5
10
15
20
25
30
Process 01 Process 02 Process 03 Process 04
Process 01Process 02
Process 03Process 04
Raw
Material
Finished
Material27
Example 04
The process is not different for cycle time and activity per process, however, the process is now staffed with
four (4) Team members; one at each station. Still 320 minutes per shift x 3 shifts x 245 working days/year.
Question 03; How much waste is there in this line balance ( in seconds )?
Maximum Cycle time x number of Team Members – Aggregated Time;
28 seconds x 4 = 112 seconds – 95 seconds (25s + 28s+ 25s + 17s) =
17 seconds
Question 01: Referring to the answer from Example 03, if our fully burdened cost is $75.00 per hour, how
much is this imbalance costing us?
Convert the 17 seconds of wasted labor into hours (17 / 3,600 ) and multiply by the
Fully Burdened Cost (17 / 3,600 ) = 0.0047 hours x $75.00/hour = $0.3542/part.
25
28
25
17
0
5
10
15
20
25
30
Process 01 Process 02 Process 03 Process 04
Process 01Process 02
Process 03Process 04
Raw
Material
Finished
Material28
Example 05
The customer has communicated that they will be needing 450,000 units per year. The challenge is that the
overall costs are still too high by $0.40 per part. All material costs are reduced as low as possible and there
is no other place to look, except in labor. The good news is that some “C.I.” type team members have
evaluated the processes and have determine the following about process 04.
Question: Seeing this new data, what do you propose the team try out?
Process 01Process 02
Process 03Process 04
Raw
Material
Finished
Material
25
28
25
17
0
5
10
15
20
25
30
Process 01 Process 02 Process 03 Process 0429
Example 05
The customer has communicated that they will be needing 450,000 units per year. The challenge is that the
overall costs are still too high by $0.40 per part. All material costs are reduced as low as possible and there
is no other place to look, except in labor. The good news is that some “C.I.” type team members have
evaluated the processes and have determine the following about process 04.
Question: Seeing this new data, what do you propose the team try out?
A first step is in determining what the Customer Takt time is. All along we have assumed
that they only thing made on this process is for this one customer, and for this example,
that is correct. So, we know our ‘allocated time’ from earlier examples and it is 14,112,000
seconds per year, so with the new demand of 450,000 units, the equation is as follows:
Allocated Time 14,112,000
Customer Demand 450,000
Process 01Process 02
Process 03Process 04
Raw
Material
Finished
Material
25
28
25
17
0
5
10
15
20
25
30
Process 01 Process 02 Process 03 Process 04
= 31.36 seconds Takt Time
30
Example 05 - Continued
The customer has communicated that they will be needing 450,000 units per year. The challenge is that the
overall costs are still too high by $0.40 per part. All material costs are reduced as low as possible and there
is no other place to look, except in labor. The good news is that some “C.I.” type team members have
evaluated the processes and have determine the following about process 04.
Question: Seeing this new data, what do you propose the team try out?
Answer: See if a three (3) TM process will work by combining the
loading process (3.38 to Process 03) and adding the pack-
ing of the part to Process 01; which will increase it to
(25.0 + 1.41 + 3.76 = ) 30.17.
Using the 14,112,000 seconds/year divide by 30.17, the
annual capacity is 467,749; in excess of the Customer
Demand and 31.36 Takt Time.
Process 01Process 02
Process 03Process 04
Raw
Material
Finished
Material
Get part and place in tester and activate tester, 3.38
Tester Cycle time and auto ejects from tester, 8.45
Get part and step to Finished Goods container and pack, 3.76
Return to testing machine., 1.41
0
2
4
6
8
10
12
14
16
18
Process 04
30.1728 28.38
0
5
10
15
20
25
30
Process 01 Process 02 Process 03
31
Example 05 - Continued
The customer has communicated that they will be needing 450,000 units per year. The challenge is that the
overall costs are still too high by $0.40 per part. All material costs are reduced as low as possible and there
is no other place to look, except in labor. The good news is that some “C.I.” type team members have
evaluated the processes and have determine the following about process 04.
Question: Did the proposal reduce the labor cost by $0.40/part?
Answer: Original Cost is 28s x 4 TM’s = 112s; 112/3600 x $75 =
$2.3333 per unit.
New layout is 31.17 seconds x 3 team members = 91.51s;
91.51 / 3600 x $75.00 = $1.8856 per unit
$2.3333 - $1.8856 = $0.4477 cost reduction; Target Achieved!
Also; line balance improved to 92.8%.
Process 01Process 02
Process 03Process 04
Raw
Material
Finished
Material
30.1728 28.38
0
5
10
15
20
25
30
35
Process 01 Process 02 Process 03
32