CVS, PMI RMP, PMP, CCE/A - Value Analysis Value · PDF fileCSVA 2012 Conference Calgary,...
date post
05-Oct-2018Category
Documents
view
212download
0
Embed Size (px)
Transcript of CVS, PMI RMP, PMP, CCE/A - Value Analysis Value · PDF fileCSVA 2012 Conference Calgary,...
CSVA2012ConferenceCSVA2012ConferenceCalgary Alberta CanadaCalgary Alberta CanadaCalgary,Alberta,CanadaCalgary,Alberta,Canada
GregGregBrink,CVS,PMIBrink,CVS,PMIRMP,PMP,CCE/ARMP,PMP,CCE/A
BackgroundInformationFunctionDrivenRiskManagement(FDRM)g ( )ProcessRiskIdentificationRiskAnalysisRiskResponsePlanningRiskMonitoringandControl
ConclusionsQ iQuestions
Wi DOTM WisDOTMegaProjectEff ti l Effectivelyaprogramconsistingofmultipleprojectsp j17milesfrom20092014inWinnebagoCCounty14milesfrom20102017inBrownCounty2017inBrownCounty
ManychallengescreatinguncertaintyCoordinatingMultipleDesigns ConsultantdesignteamswithmultiplesubcontractorsROWAcquisitionandUtilityRelocationConstructionStagingManagementofTrafficContextSensitiveDesignEstimateUncertainty
Project B
Project A Project CProject A
Start End
Project C
Project D $$ }
Program
EstimateRisk
ProjectRiskRisk
ProfileEventRisk
ResultsInMoreRobustRiskManagement!
Response
Analysis
ProblemFocused
Identification
ResponseSolutionFocused
Analysis
Identification
?Response
? ?? ???Analysis
? Identification? ?
Id if Ri kIdentifyRiskCategories
(RBS)
BrainstormQualify/ RisksbyCategory
Qualify/PrioritizeRisk
PopulateRiskRegister
RiskCriticalFunctions
RiskCriticalFunctions
Function1
Ri k
Function2
Ri k
Function3
Ri k Risk1 Risk2 Risk3
Risk1 Risk2 Risk3
Risk1 Risk2 Risk3 Risk3 Risk3 Risk3
i iTeamBrainstorming
FunctionAnalysis:FocuseseffortintherightdirectionFacilitatestheprioritizationofrisksFacilitatesmanagementofprojectdelivery
DescribeRisks
IdentifyImpacts
EstablishPriorities
Identifyb b l
Runl ProbabilityAnalysis
IdentifyResponseStrategies
D l A ti S d Ri k DevelopActionPlans
SecondaryRiskAnalysis
IdentifyResponsibilitiesResponsibilities&Milestones
RiskObjectIdentification
BrainstormingofRiskResponseStrategiesbyFunction
SecondaryRiskAnalysis
Function
EvaluationofRiskResponse
DevelopmentofActionPlansforRi kR ResponseStrategiesRiskResponseStrategies
Avoid
ThreatResponseFunction
ResponseStrategy
Accept
Mitigate
T f
VerbTransfer
RiskDescription
ObjectofRisk Noun
ResponseStrategy Mitigatep gy g
P ibilit fPossibilityofencounteringconflictswithTransCanadian
Pipeline
PipelineConflicts
ResponseStrategy Avoidp gy
P ibilit fPossibilityofencounteringconflictswithTransCanadian
Pipeline
PipelineConflicts
E l it
OpportunityResponseFunction
ResponseStrategy
Exploit
Enhance
ShareVerb
RiskDescription
ObjectofRisk Noun
ResponseStrategy Exploitp gy p
ThereistheopportunityThereistheopportunitytorealizecostsavings
resultingfromreestimationof
quantities
Estimate
quantities
RiskResponseFunctions
Function1 Function2 Function3
Strategy1 Strategy2 Strategy3
Strategy1 Strategy2 Strategy3
Strategy1 Strategy2 Strategy3gy 3 gy 3 gy 3
i iTeamBrainstorming
Nextsteps:Nextsteps:PrioritizeriskresponsestrategiesD l d t il d ti lDevelopdetailedactionplansPerformsecondaryriskanalysisasneeded
RiskResponseStrategiesRiskResponseActionPlans
Ri k D i ti
L M H EV L M H EV1-48 Utility
Conflict Definition
Threat
80% $ 0.03 $ 0.05 $ 0.08 $ 0.04 0.00 1.00 2.00 0.80
RiskDescription
RiskID RiskName Type Description ProbabilityCost Schedule
There is confusion on the Domino Rd. project in terms of defining what a conflict is. Central office is saying that anything below the 18" subgrade is a conflict. This could result in a schedule delay as a result of disagreements between the contractors and the department.
L M H EV L M H EV
RiskResponseActionPlan
RiskResponseStrategies Probability
Cost Schedule
Primary Strategies:1. Settle on a definition now by getting key players involved2. Hold consensus building meeting to agree on definition
50% $ 0.03 $ 0.05 $ 0.08 $ 0.03 0.00 0.50 1.00 0.25
3. Add language to contracts to add clarity and specify4. On the design side, to avoid risk to DOT, follow the TRANS 220 processFallback Strategies:5. Pay for it6. Perform an early location through 3D layout of existing utilities (expensive)
RiskResponseActionPlan RiskOwner RiskReviewMilestone/FrequencyPrimary1. Setup meeting with key players to discuss and make final decision on the defention of a conflict. Prior to the meeting have Key playermeeting by end of Augustp g y p y gBobby Johnson talk to his chief counter parts to get input on this issue statewide. Identify who key player is. Who would be the DOT decision maker/voice in conflict scenario between Road Builders and DOT?2. Same as 1.3. Based on outcome for the conflict definition clarify in specs how to address. Make sure utilities are clear on what the requirments are for conflicts and ensure they convey that into future work plans. Clarify contractor vs. DOT vs utilty risk/responsability if issues are realized in the field. Cleary explain what the differences in risk/responsabilty are when trans 220 isn't followed to the tee.4. Continue tracking detailed shedules but determine what projects are at risk for not following trans 220. Then determine where to move those projects to ensure trans 220 is followed
SallyJonesKeyplayermeetingbyendofAugust2011.Speclanguagedevelpedprior
toDecember1stPS&E.
BaseCostImpactsNeed to budget contingency to address additional costs if DOT takes risk of incurring all costs.
No real design costs but could incure constrution delays if contractor is unclear on how to address "a conflict" and refuses to proceed.
where to move those projects to ensure trans 220 is followed.Fallback:5. Continue business as usual but take on the risk that DOT may incure delay costs and budget for those costs.6. Determine critical areas where multiple conficts are anticipated. Have detaild utiltiy identification/location done so it is clear where and how deep the facilities are to cleary identify possible conflicts in design.
BaseScheduleImpacts
FunctionAnalysis:AnchorsbrainstormingofresponsestrategiestofunctionsIncreasesquantityandqualityofresponse
istrategiesProvidesforamorerobustexplorationof
l tisolutions
CompileResultsofRiskAnalysis&
Workshop
CompileRiskEstablish&E Ri k CompileRiskManagementPlan
ExecuteRiskMonitoringandControlPlan
ProduceReportProduceReport
FunctionAnalysisEnhancesRiskManagement:FacilitatescommunicationImprovesunderstandingofprojectFocuseseffortoncriticalfunctionsandrisksImprovesquantityandqualityofresponsestrategiesResultsinrobustandmoredetailedactionplanswithmultiplecontingencies
TheBestValueresultswhenthenecessaryyfunctionstomeettherequiredperformanceatthelowestoverallcostandleastamountofdeliverytimeareperformedintheleastuncertainway.yPerformance,CostandScheduleareUncertainPerformanceincludesrequirementsandPerformanceincludesrequirementsandattributesRiskincostsanddurationsarecomprisedofpestimatingriskandeventrisk