Cut and Cover Tunnels - Waterproof Magazine Winter 2012.pdf

download Cut and Cover Tunnels - Waterproof Magazine Winter 2012.pdf

of 5

Transcript of Cut and Cover Tunnels - Waterproof Magazine Winter 2012.pdf

  • 8/11/2019 Cut and Cover Tunnels - Waterproof Magazine Winter 2012.pdf

    1/5

    Cut and Cover

    Tunnels

    he vast majority o below-grade

    tunneling projects today

    are actually created using cut-

    and-cover construction methods. Tis

    methodin which a trench is excavated

    rom the surace, then re-coveredisusually more economical and more

    practical than mined or bored tunneling.

    Its especially practical at shallow depths

    (30 or 40 eet) but depths to 60 eet are

    not uncommon.

    Cut-and-cover tunneling is

    extremely versatile. Most o the worlds

    subways have been built using cut-and-

    cover techniques. Its the overwhelming

    method o choice or traffic, rail and

    pedestrian underpasses, utility tunnels,and a host o other applications.

    Construction MethodsDepending on the situation, a variety

    o different construction methods can

    be used. Stacy Byrd, National Products

    Manager at CECO, says, Tere are so

    many different methods o constructing

    a tunnel and the waterproofing solution

    should be designed to fit that particular

    project and the expected jobsite

    conditions.

    Byrd continues, o determine

    the best waterproofing solution, one

    must consider how the tunnel will be

    constructed. Will it be constructed withcast-in-place concrete, precast, shotcrete,

    or a combination such as a precast

    tunnel roo placed onto cast-in-place

    walls? Access is also a defining actor in

    product selection. Will the waterprooer

    have the space to install the membrane

    rom the exterior or will it be blindside

    construction?

    Major actors determining the

    construction method include the

    excavation depth, soil type, elevation

    o the water table, site access, and the

    amount o time which the final at grade

    surace can be disturbed.

    In general, the many different

    construction method used to build cut-

    and-cover tunnels can be divided intothree major categories. Each o them

    requires an entirely different approach to

    waterproofing.

    Bottom-Up Construction: Te most

    common technique is the bottom-up

    construction. Here, a trench is excavated

    rom the surace downward. Once the

    final depth is reached, the tunnel floor

    is built, then the walls and roo are put

    into place. Finally, the entire structure is

    buried and the surace restored.I the construction site has plenty

    o room, the trench is usually cut back.

    Walls are typically cast in place, and

    the waterproofing can be applied to the

    P h o t o C o u r t e s y C E T C OMost tunnels are actually built as trenches using cut-and-cover

    techniques. This St. Louis subway tunnel was built using thebottom-up method, using cast-in-place concrete walls and

    precast roof segments.

    Photo Courtesy City of Calgary

    The Calgary light rail tunnels

    reached 60 feet below grade, and

    used a combination of soil nails,

    shotcrete, and cutback slopes that

    waterproofers had to work around.

    20 WATERPROOF!

  • 8/11/2019 Cut and Cover Tunnels - Waterproof Magazine Winter 2012.pdf

    2/5

    outside ace o the concrete with minimal

    problems.

    Usually, though, theres not enough

    room or positive side waterproofing.

    Especially in urban settings, where most

    cut-and-and cover tunnels are built, land

    is at a premium, so the excavation is cut

    vertically and reinorced with soldier

    piles or soil nails. In these cases, the

    waterproofing is done blindside. With

    this construction method, the walls

    (usually shotcrete or using removeable

    orms on the exposed ace) are poured

    afer the waterproofing is finished.

    Roos can be poured in place or

    ormed with precast planks. Te roo

    waterproofing is then tied into the wall

    waterproofing and drainage, and then

    the whole system is buried.

    Bottom-up construction offers

    several advantages: First, its well

    understood by contractors, so finding

    skilled labor isnt a problem. Additionally,

    waterproofing and drainage systems can

    be applied to the outside surace o the

    structure. Te floor o the excavation is

    easily accessible or equipment and or

    the delivery, storage and placement o

    materials.

    For these reasons, bottom-up

    construction is perhaps the most

    economical method o building large,

    shallow tunnels, but has the disadvantage

    o making the site unusable longer than

    either o the other methods detailed

    below.

    Dave Polk, owner o Epro Services,

    has been involved with a number o

    complex tunnel projects, including the

    Calgary light rail extension.

    Calgary was cut-and cover, says

    Polk, at Epro, but it was a little different

    because portions o it were open-cut.

    Polk adds that the deepest areas reach

    60 eet below grade, and that parts o the

    line are a dual tunnel layout.

    We did underslab on everything,

    says Polk. Its a 60-mil HDPE film, and

    that underslab system is bath-tubbed up

    the wall to water table height. Once the

    walls were in place, the roo was poured

    in place in 15-oot sections using slip

    orms.

    Te roo experienced a tremendous

    amount o construction traffic during

    the backfill process, so the membrane

    All of the joints in the precast roof

    segments of the St. Louis subway

    tunnel at left were detailed and

    sealed before the waterproofing and

    drainage layers were installed.

    PhotoCourtesyCETCO

    Winter 2012 21

    http://www.ravenefd.com/cwhttp://www.rhinocarbonfiber.com/
  • 8/11/2019 Cut and Cover Tunnels - Waterproof Magazine Winter 2012.pdf

    3/5

    chosen had to be extremely durable.We started with a spray-applied

    liquid membrane, and then laid down a

    abric reinorcement, says Polk. Ten

    we spray another membrane over that,

    which creates a reinorced monolithic

    membrane that will stand up to site

    conditions. Tat was covered with a

    15-mil polyolefin film, and then a heavy

    duty drainage composite, which we tied

    into the composite on the walls.

    CECO was involved withwaterproofing the recent extension o

    the below-ground St. Louis light rail,

    which used bottom-up cut-and-cover

    construction or the walls and a pre-cast

    roo.

    Byrd explains. Because it was

    going through residential sections o the

    community, they couldnt overexcavate

    and had to pour the tunnel walls

    directly onto the soil retention system.

    We provided a bentonite-geotextile

    membrane that was installed to the

    soil retention wall prior to the concrete

    placement. Te bentonite geotextile

    membrane was also used as an underslab

    barrier over the gravel substrate.

    Te precast arched concrete

    segments or the roo were waterprooed

    using a peel-and-stick butyl rubber

    membrane that tied into the system used

    on the walls.

    Modular Tunnels: For small

    tunnels, such as utility or sewer access

    tunnels and pedestrian underpasses, a

    variation on bottom-up construction can

    be used. Called modular tunnels, this

    construction method uses corrugated

    steel or pre-cast concrete segments to

    create the structure. Tese segments are

    usually waterprooed offsite and craned

    into place.

    One o the primary challenges with

    waterproofing precast tunnels, then,

    is ensuring that the membrane is not

    damaged between when it is applied and

    when the tunnel segments are set into

    place. o ensure the waterproofing and

    drainage components stay in constant

    contact with the bottom o the precast

    section, designers ofen call or a concretemud slab instead o loose gravel at the

    bottom o the excavation.

    Waterprooers must also pay careul

    attention to the many joints between the

    pre-cast sections to ensure the tunnel

    remains dry.

    A utility corridor built on the

    campus o the University o Connecticut

    in 2006 used this method. Each segment

    measured ten eet square and eight

    eet long, and was craned into placeonto a our-inch thick mudslab, then

    waterprooed. First, the joints between

    each segment were sealed using Ultraseal

    B, a product that combines bentonite

    clay with a hydrophilic polymer. Ten,

    workers covered the roo and walls o

    the tunnel with Volclay, a similar sheet

    product that also contains a bentonite-

    polymer alloy.

    Top-down Construction: Te top-

    down construction method calls or the

    walls and roo o the tunnel to be put into

    place beore the actual excavation takes

    place. Te advantage o this method

    is that the surace is disturbed or a

    minimal amount o timean important

    consideration i the tunnel is being built

    under a heavily used traffic artery.

    In the top-down method, the first

    step is getting the temporary walls in

    place. Tese could be steel sheet piles

    or a concrete slurry wall. Once the walls

    are completed, the roo o the tunnel is

    constructed and the surace (usually a

    roadway) is restored.

    Te surace is then available or

    normal use while the tunnel excavation

    is carried out.

    op-down cut-and-cover tunnels

    use blind-side waterproofing techniques.

    Te waterproofing membrane is typically

    applied between the temporary shoring

    wall and the permanent tunnel lining.

    Te tunnel floor slab and the underslab

    barrier are typically the last part o

    construction to be completed.

    Te underpass tunnel leading to

    the San Jose Airport was built using this

    method. Site conditions were difficult,

    to say the least; the water table was onlysix eet below grade, which meant even

    the top o the tunnel would be below the

    water table.

    Polk, at Epro Services, explains

    how the job went. Te first thing that

    needed to be done was the installation

    o construction wells and pumpsa site

    dewatering system, says Polk. Tey

    built the top o the tunnel first. Tey

    drove pilings in, then poured corbels and

    reinorced concrete beams on that. Oncethat was is place, we could waterproo

    the top. By finishing the top first,

    surace roads could be opened sooner

    and minimize the traffic disturbance.

    We used our spray membrane with

    a HDPE [high-density polyethylene]

    film over the top, says Polk. We knew

    it would be covered by paving, so we just

    used strip drains or drainage.

    Ten they began excavating under

    PhotoCourtesyCETCO

    This college utility tunnel used

    modular precast sections. It was

    waterproofed using a bentonite-

    polymer alloy after the segments

    were placed in their final location.

    22 WATERPROOF!

  • 8/11/2019 Cut and Cover Tunnels - Waterproof Magazine Winter 2012.pdf

    4/5

    the roo, installing post-tensioned

    tiebacks as the work progressed to keep

    the pilings stable. Te tunnel bottom had

    to withstand 20 eet or more o hydrostatic

    pressure, so the waterproofing system

    here was absolutely critical. Tey used

    a seamless, spray-applied membrane

    sandwiched between two layers o

    HDPE.

    Te wall waterproofing was done

    blindside. Polks crew first applied

    a dimple drain sheet, then careully

    sealed around the tiebacks and other

    penetrations. Tey tied this into the top

    and bottom waterproofing systems, then

    sprayed a final layer o waterproofing

    on the walls. Ten it was enclosed in

    shotcrete. Completed about ten years

    ago, its still as watertight as the day it

    was completed.

    WaterproofingConsiderations

    Te type o waterproofing used

    on cut-and-cover tunnel installations

    usually hinges on the type o soil

    retention system used on the sides o

    the excavation. As noted above, open

    cut excavations are the easiest. Soldier

    piles and sheet piles are more difficult.Soil nails retention systems, which

    can involve detailing around literally

    hundreds o different points, are the

    most involved.

    Regardless o the system used,

    waterproofing is essential. Not only does

    it reduce corrosion and maintenance and

    extend the lie o the structure, but it can

    also improve saety. In colder climates,

    leaking tunnels can create hazardous

    ceiling icicles or ice patches on roadways.Additionally, once a tunnel is

    placed in service, theyre extremely

    inconvenient to close, which imposes

    severe constraints on remedial

    waterproofing options. Particularly with

    rail tunnels, options or getting toand

    repairingleaking sections become

    extremely limited.

    A ew years ago, the U.S. Department

    o ransportation published a white

    paper explaining good design o cut-

    and cover tunnels. It places special

    emphasis on waterproofing. Te

    conception o the waterproofing system

    in cut-and-cover tunnels demands an

    exact planning o the system, a good

    collaboration and discussion between

    producer, designer o the project, main

    contractor and installer, it reads. oo

    ofen the importance o waterproofing

    is underestimated by the designer with

    the consequence that the execution o

    the waterproofing works are immensely

    difficult to achieve.

    Teir study indicates that the best

    results can be achieved by paying special

    attention to joint sealing, waterproofing

    o penetrations, reinorcement opti-

    mization, and drainage in area o the

    ceiling/crown. n

    Your Waterproofing Solution forRemoving Airborne Moisture

    BalancedVENTILATION for

    HEALTHIER Living.

    Breathe easier with the cleanest ventilation ever EZ Breathe.To find out more about how EZ Breathe offers balanced home ventilation

    for all home types, visit www.ezbreathe.comor call 866.822.7328.

    www.ezBreathe.com 866.822.7328

    Even though the job was done right and

    the waterproofing system was performing,

    the lingering smell left a negative

    impression. EZ Breathe has completely

    eliminated that problem. We just don't

    receive those calls anymore. Ever. This

    system really works and the results that

    it produces are truly remarkable.

    J. Gielty, EverDry Waterproofing

    EZ Breathe Advantages

    Dries out damp/musty basements

    and crawlspaces

    Helps in reducing mold growth

    Reduces window condensation

    Removes allergens and

    indoor pollutants More efficient energy consumption

    Reduces number of service calls

    *Patent

    pending

    Watch Your Profits Soar by

    Becoming an EZ Breathe Distributor

    LowMoisture,

    CleanA ir,

    Healthy Home.

    LowMoisture,

    CleanA ir,

    Healthy Home.

    LISTED24MUE245128

    CU L US

    VentilationFan

    Model:400Electric Rating:120V, 60H

    z, 31W

    Winter 2012 23

    http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/http://www.ezbreathe.com/
  • 8/11/2019 Cut and Cover Tunnels - Waterproof Magazine Winter 2012.pdf

    5/5

    *All Rhino urethanes are 100% solids. Some epoxy and polyaspartic products may contain less than 100% solids. The photos depicted in this advertisement are shown for

    illustration purposes only and are not intended to represent particular applications or methods. All businesses are independently owned and operated. 2012 Rhino Linings

    Corporation. All rights reserved. Waterproof Winter12 6272

    For information on becoming a Rhino Industrial Applicator call: in the USA 877-509-4603, in Europe, Africa andMiddle East: +49 6103 936474, in Latin America: 1-858-450-0441 ext. 6021, in Australasia: +61 7 5585 7000

    Rhino Linings is a leading

    manufacturer of 100% solids (no

    solvents or VOCs) spray-applied

    linings. These linings can beapplied to above and below grade

    concrete and masonry substrates in new

    and existing structures. They cure to the touch in

    just seconds to allow for rapid backfilling and fast

    site turnaround.

    When you need long term waterproofing solutions,

    use the #1 brand name chosen by hundreds of

    people every day.

    Solvent free (LEED compliant)

    Cures in just seconds

    Very low permeability

    Seamless, Monolithic

    Impact & tear resistant

    Call Rhino Industrial today!

    1-877-509-4603RhinoLiningsIndustrial.com

    The more complex yourwaterproofing andcontainment problems,

    the more you need theRhino

    solution.

    JANUARY 2427, 2012

    Booth# S-12039

    http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/http://www.rhinoliningsindustrial.com/