Customer Facing Performance Measures Feedback Summary Response

download Customer Facing Performance Measures Feedback Summary Response

of 22

Transcript of Customer Facing Performance Measures Feedback Summary Response

  • 7/28/2019 Customer Facing Performance Measures Feedback Summary Response

    1/22

    Customer-facing performance measures Transpower New Zealand Limited 2007. All rights reserved. i

    CUSTOMER-FACINGPERFORMANCE MEASURES

    CUSTOMER FEEDBACK AND RESPONSE

    Transpower New Zealand Limited

    March 2013

  • 7/28/2019 Customer Facing Performance Measures Feedback Summary Response

    2/22

  • 7/28/2019 Customer Facing Performance Measures Feedback Summary Response

    3/22

    Customer-facing performance measures Transpower New Zealand Limited 2007. All rights reserved. iii

    Table of Contents

    Executive Summary ............................................................................................................ iv

    1 Introduction and purpose .......................................................................................... 5

    1.1 Note on terminology .............................................................................................. 5

    1.2 Overview of original proposal ................................................................................ 6

    1.3 Overview of feedback ............................................................................................ 7

    2 Our general approach ............................................................................................... 8

    3 Our proposed measures ........................................................................................... 9

    3.1 Proposed categories ............................................................................................. 9

    3.2 Number and duration of unplanned interruptions ................................................. 11

    3.3 Information provision ........................................................................................... 14

    3.4 Comparisons with distribution .............................................................................. 15

    4 Other issues and possible measures ...................................................................... 17

    4.1 Voltage sags ....................................................................................................... 17

    4.2 Economic impact ................................................................................................. 18

    4.3 Planned outages and the impact on the market ................................................... 19

    4.4 Risks of non-supply ............................................................................................. 20

    4.5 Qualitative customer service ............................................................................... 21

    4.6 Feedback: other issues ....................................................................................... 21

  • 7/28/2019 Customer Facing Performance Measures Feedback Summary Response

    4/22

    Customer-facing performance measures: Customer feedback and response

    Customer-facing performance measures Transpower New Zealand Limited. All rights reserved.iv

    Executive Summary

    We are developing new measures and targets for grid performance based on what matters

    to our customers and to end consumers. We published proposed new measures at the end

    of October 2012 and invited customers and their representatives to provide feedback either

    at meetings or in writing.

    This document provides a summary of customer views on the proposed measures and

    targets. It outlines the way we intend to develop grid performance measures in light of the

    feedback.

    We experienced widespread support for our approach and the measures we proposed. The

    key measures focus on the number and duration of interruptions and the information we

    provide during interruptions.

    Customers provided suggestions for improving the measures and highlighted other areas

    that are important to them.

    Key issues raised by customers were:

    Whether interruptions caused by extreme events and those that are less than one

    minute long should be included.

    The importance of power quality, in particular voltage sags.

    The impact on the market of both planned and unplanned outages this was of

    particular importance to generator-retailers.

    The financial impact of interruptions.

    Information on the risks of non-supply and improved communication after interruptions.

    A separate paper describes our revised proposal, how the performance measures fit with

    our next regulatory control period proposal and the next steps. It is available on our

    website1.

    1https://www.transpower.co.nz/about-us/industry-information/customer-facing-grid-performance-measures-consultation

    https://www.transpower.co.nz/about-us/industry-information/customer-facing-grid-performance-measures-consultationhttps://www.transpower.co.nz/about-us/industry-information/customer-facing-grid-performance-measures-consultationhttps://www.transpower.co.nz/about-us/industry-information/customer-facing-grid-performance-measures-consultationhttps://www.transpower.co.nz/about-us/industry-information/customer-facing-grid-performance-measures-consultationhttps://www.transpower.co.nz/about-us/industry-information/customer-facing-grid-performance-measures-consultationhttps://www.transpower.co.nz/about-us/industry-information/customer-facing-grid-performance-measures-consultation
  • 7/28/2019 Customer Facing Performance Measures Feedback Summary Response

    5/22

    Customer-facing performance measures: Customer feedback and response

    Customer-facing performance measures Transpower New Zealand Limited. All rights reserved. 5

    1 Introduction and purpose

    We are introducing new measures and targets for grid performance based on what

    performance matters to our customers and end consumers. These targets will be

    used to report our performance, to prioritise our expenditure and to inform therevenue incentive regime applying to Transpower in our next regulatory control

    period (2015-2020).

    We prepared a draft proposal2 for review by our customers and end-consumer

    representatives in October 2012.

    We met with representatives of 30 customers over a series of meetings, and received

    written feedback from 13 parties. We also met with Commerce Commission

    representatives to discuss the proposal and consultation process. Written feedback is

    available on our website3.

    Our customers generally supported the overall approach we are taking in introducing

    measures focusing more directly on the service that customers receive and the shift

    away from system average-based measures. Customers welcomed the opportunity

    to comment and we would like to thank all those customers and their representatives

    for their time and expertise. These performance measures involve a change in

    emphasis for us and the consultation has been a critical part of making sure that we

    target efforts and spending on performance that our customers value.

    This paper summarises the feedback, discusses issues raised by customers or

    consumer representatives and outlines the way we intend to progress these

    measures and targets in light of the feedback.

    A separate paper describes our revised proposal, how the performance measures fit

    with our next regulatory control period proposal and the next steps. It is available on

    our website4.

    1.1 Note on terminology

    In our proposal we used the term outage to mean an event that causes a loss of

    supply or loss of generation connection. We used this term because we thought it

    was more relevant to consumers and is often used by distributors in communicationwith their customers.

    This confused some customers because the term outage is often used to mean when

    assets are out of service, but there is no loss of supply, and it can be used to

    describe both planned and unplanned outages. The term interruption is used

    internationally and by the Commerce Commission to refer to a loss of supply.

    2 Transpower: Customer-facing grid performance measures consultation paper, October2012, available at:https://www.transpower.co.nz/sites/default/files/plain-page/attachments/long-term-performance-measures-consultation-paper_1.pdf3

    https://www.transpower.co.nz/about-us/industry-information/customer-facing-grid-performance-measures-consultation4ibid

    https://www.transpower.co.nz/sites/default/files/plain-page/attachments/long-term-performance-measures-consultation-paper_1.pdfhttps://www.transpower.co.nz/sites/default/files/plain-page/attachments/long-term-performance-measures-consultation-paper_1.pdfhttps://www.transpower.co.nz/sites/default/files/plain-page/attachments/long-term-performance-measures-consultation-paper_1.pdfhttps://www.transpower.co.nz/sites/default/files/plain-page/attachments/long-term-performance-measures-consultation-paper_1.pdfhttps://www.transpower.co.nz/about-us/industry-information/customer-facing-grid-performance-measures-consultationhttps://www.transpower.co.nz/about-us/industry-information/customer-facing-grid-performance-measures-consultationhttps://www.transpower.co.nz/about-us/industry-information/customer-facing-grid-performance-measures-consultationhttps://www.transpower.co.nz/about-us/industry-information/customer-facing-grid-performance-measures-consultationhttps://www.transpower.co.nz/about-us/industry-information/customer-facing-grid-performance-measures-consultationhttps://www.transpower.co.nz/about-us/industry-information/customer-facing-grid-performance-measures-consultationhttps://www.transpower.co.nz/about-us/industry-information/customer-facing-grid-performance-measures-consultationhttps://www.transpower.co.nz/about-us/industry-information/customer-facing-grid-performance-measures-consultationhttps://www.transpower.co.nz/about-us/industry-information/customer-facing-grid-performance-measures-consultationhttps://www.transpower.co.nz/about-us/industry-information/customer-facing-grid-performance-measures-consultationhttps://www.transpower.co.nz/sites/default/files/plain-page/attachments/long-term-performance-measures-consultation-paper_1.pdfhttps://www.transpower.co.nz/sites/default/files/plain-page/attachments/long-term-performance-measures-consultation-paper_1.pdf
  • 7/28/2019 Customer Facing Performance Measures Feedback Summary Response

    6/22

    Customer-facing performance measures: Customer feedback and response

    Customer-facing performance measures Transpower New Zealand Limited. All rights reserved.6

    In this paper we have reverted to the standard terminology to avoid confusion. An

    interruption is a loss of supply; an outage is an equipment outage. Both interruptions

    and outages can be planned or unplanned.

    1.2 Overview of original proposal

    The proposal that we set out in our consultation paper described performance

    measures and targets that are significantly different from our existing measures. The

    main differences were:

    A change in emphasis from measures that are focused on the performance of our

    assets to measures of the service received by customers.

    Different targets reflecting different categories of customers at grid connections.

    Forward-looking targets that reflect what customers expect rather than targets

    based on historical performance.

    The measures focused on the ability of the grid to transmit power without interruption

    and not on power quality aspects of grid performance or power losses or constraints.

    Table 1 provides an overview of the original proposal. For a more detailed description

    of the proposal refer to the consultation paper5.

    Table 1 Overview of original proposal

    Proposed customer-facing measures(Measured at the customer point of service)

    Proposed long-term targets

    Number of unplanned interruptions Different for different categories: high-priority, important, standard, generatorand N security connections.

    Average and 90th percentile duration ofunplanned interruptions

    Information provision during unplannedinterruptions:

    - Time to provide first notice- Time to provide updates- Accuracy of restoration estimates

    Common targets for all customers.

    Comparisons with distribution companies A national target for number and

    duration of unplanned interruptionsrelative to distribution networks.

    5https://www.transpower.co.nz/sites/default/files/plain-page/attachments/long-term-

    performance-measures-consultation-paper_1.pdf

    https://www.transpower.co.nz/sites/default/files/plain-page/attachments/long-term-performance-measures-consultation-paper_1.pdfhttps://www.transpower.co.nz/sites/default/files/plain-page/attachments/long-term-performance-measures-consultation-paper_1.pdfhttps://www.transpower.co.nz/sites/default/files/plain-page/attachments/long-term-performance-measures-consultation-paper_1.pdfhttps://www.transpower.co.nz/sites/default/files/plain-page/attachments/long-term-performance-measures-consultation-paper_1.pdfhttps://www.transpower.co.nz/sites/default/files/plain-page/attachments/long-term-performance-measures-consultation-paper_1.pdfhttps://www.transpower.co.nz/sites/default/files/plain-page/attachments/long-term-performance-measures-consultation-paper_1.pdf
  • 7/28/2019 Customer Facing Performance Measures Feedback Summary Response

    7/22

    Customer-facing performance measures: Customer feedback and response

    Customer-facing performance measures Transpower New Zealand Limited. All rights reserved. 7

    1.3 Overview of feedback

    Both the customer meetings and the written feedback support the direction and

    emphasis that we proposed in the consultation paper. Distributors and large users

    support concentrating on the number and duration of interruptions but some havesuggested improvements or further measures. Generator-retailers also consider

    these measures are appropriate for off-take, but want to see development of market

    impact measures and consideration of planned outages. All customers value the

    information provision measures.

    For these reasons, we will continue with the core parts of our published proposal

    measures focused on the number of interruptions, the duration of interruptions and

    information provision. We will refine these measures to reflect suggestions. In

    addition, we will look at ways to develop our performance measures and targets in

    the future to respond to customer feedback through consultations and trials.

    The three following sections summarise customers views and our response.

  • 7/28/2019 Customer Facing Performance Measures Feedback Summary Response

    8/22

    Customer-facing performance measures: Customer feedback and response

    Customer-facing performance measures Transpower New Zealand Limited. All rights reserved.8

    2 Our general approach

    2.1.1 Customer views

    There was significant support from distributors and large users for our overall

    approach which involves:

    a change in emphasis to measures of the service received by customers rather

    than system averages

    using different targets for different categories of customers

    using forward-looking targets that reflect what customers expect rather than

    targets based solely on historical performance, and

    concentrating on the number and durations of unplanned interruptions.

    The generator-retailers supported the approach for off-take, but would like to see

    measures that reflect the impact of both planned and unplanned outages on themarket.

    Individual customers made the following comments about our general approach.

    Measures should be meaningful to Transpower and our contractors as well as to

    customers.

    Measures should encourage learning from all events, not just high profile events.

    We should be mindful of the end-plan and trial reporting and measures that

    customers would like to see in the future.

    2.1.2 Our response

    Reflecting on the feedback, we consider that our measures and targets should first

    be meaningful to our customers and ensure we are managing our assets to deliver

    the service valued by our customers. They should focus on measurable outcomes,

    not on inputs.

    Efforts to achieve these outcomes will be embedded into our asset management

    approach and will be important in driving improvements. We have structured the

    measures so that they are meaningful to both us and our contractors.

  • 7/28/2019 Customer Facing Performance Measures Feedback Summary Response

    9/22

    Customer-facing performance measures: Customer feedback and response

    Customer-facing performance measures Transpower New Zealand Limited. All rights reserved. 9

    3 Our proposed measures

    3.1 Proposed categories

    3.1.1 Customer views: categories

    Customers were generally supportive of introducing categories for different customer

    loads. We proposed a relatively simple method of categorisation that most customers

    or their representatives thought was broadly sensible. Customers widely supported

    treating N security sites separately. However, customers made the following

    comments or suggestions:

    Finer differentiation or use of an economic metric. Some customers said we

    should introduce further categories and one suggested we should have individual

    customer targets. Some recommended a closer alignment of the categories with

    an economic metric such as the Value of Lost Load (VOLL).

    Price-quality trade-off. A small number of customers commented that with

    different performance categories customers should be able to make a price-

    quality trade-off.

    Feedback on categories and targets. Some customers asked for more

    transparency on how we will determine categories and the opportunity to discuss

    their categories and targets with us before they are finalised.

    Use of the term essential. At one of the customer meetings, customers pointed

    out that ranking a point of service as essential implies that it should never lose

    supply. One customer suggested high priority may be better.

    Generation targets. Two generators objected to the generator targets being set

    at the same level as the standard off-take categories. One generator suggested

    that the generator performance targets should reflect the different securities at

    generator points of connection and the other considered that the targets should

    be the same as the important or essential load categories, as least for those

    Grid Injection Points (GIPs) where the loss of generation would have a significant

    impact on the market (eg 100 MW or greater).

    3.1.2 Our response: categories

    Finer differentiation or an economic metric

    We think the proposed three off-take and one generator categories, with particular

    consideration of N security sites, is a pragmatic way to introduce different targets for

    different customers. It is easily understood and relevant to customers as well as

    being relatively easily translated into objectives for our asset management strategy,

    staff and contractors.

    Some customers suggested using size of load (eg peak demand in MW) or value of

    the load (ie based on some value of VOLL) as the basis for defining criticality. Using

    size of load alone does not take into account the different values of the supply to

    different customers. Explicitly using VOLL values that reflect the different values to

  • 7/28/2019 Customer Facing Performance Measures Feedback Summary Response

    10/22

    Customer-facing performance measures: Customer feedback and response

    Customer-facing performance measures Transpower New Zealand Limited. All rights reserved.10

    different customers may be theoretically correct but is limited by the approximations

    inherent in VOLL calculations and does not capture effects not currently considered

    in VOLL calculations. VOLL will vary hugely by season, time, length of outage and

    type of customer and we doubt that the classification which results would be either

    significantly different or any more correct.

    The Electricity Authority is undertaking a study to determine a value, or range of

    values, for VOLL that is relevant to New Zealand electricity consumers. When this is

    completed, we will consider integrating VOLL into the off-take criticality framework -

    providingthe overall VOLL framework is sufficiently robust.

    In the meantime, our proposed categories provide a proxy for economic impact. They

    take into account the number of customers connected at a point, whether there are

    large industrial customers or CBDs connected for whom an interruption is more

    costly, and whether there are loads of national significance connected.

    Price-quality trade-off

    The nature of transmission networks means that the same assets are often used to

    supply many customers, and the grid is designed as an interconnected network. This

    makes it difficult to provide different levels of service at different points of within the

    grid, beyond negotiated connection assets.

    The different categories may invite useful discussions on price and quality and

    potentially open up further development of price-quality trade-offs.

    Feedback on categories and targets

    During the consultation period, we published a spreadsheet showing the full list of

    points of service and the method of allocating categories to points of service. We

    received very little feedback on the detail in the spreadsheet. We have made this

    spreadsheet available again and invite more detailed feedback by Tuesday 16 April

    2013. A copy of the spreadsheet including details of how to provide feedback are

    provided on our website6.

    Use of the word essential

    We agree that high priority is a better term to describe the essential category.

    Generator targets

    We have ignored the nature of the network when categorising off-take points of

    service and considered solely the nature of the customer and therefore the impact of

    an interruption. We will do the same for generation. However, there is already some

    reflection of the different security levels at different generators as N and N-1 points of

    service are treated differently as they are for off-take.

    We will set the generator targets at the level of the standard off-take category rather

    than important or high priority as generally the impact of an interruption on a

    6https://www.transpower.co.nz/about-us/industry-information/customer-facing-grid-

    performance-measures-consultation

    https://www.transpower.co.nz/about-us/industry-information/customer-facing-grid-performance-measures-consultationhttps://www.transpower.co.nz/about-us/industry-information/customer-facing-grid-performance-measures-consultationhttps://www.transpower.co.nz/about-us/industry-information/customer-facing-grid-performance-measures-consultationhttps://www.transpower.co.nz/about-us/industry-information/customer-facing-grid-performance-measures-consultationhttps://www.transpower.co.nz/about-us/industry-information/customer-facing-grid-performance-measures-consultationhttps://www.transpower.co.nz/about-us/industry-information/customer-facing-grid-performance-measures-consultation
  • 7/28/2019 Customer Facing Performance Measures Feedback Summary Response

    11/22

    Customer-facing performance measures: Customer feedback and response

    Customer-facing performance measures Transpower New Zealand Limited. All rights reserved. 11

    generator is lower than on off-take as foregone revenue is partly offset by avoided

    costs.

    The instantaneous reserves regime already provides financial incentives on

    Transpower to maintain the performance of grid assets connecting large generatingunits. The causer of under-frequency events is liable for the event charge.

    Transpower is the causer when the unplanned outage of transmission assets causes

    the under-frequency event through the disconnection of generation.

    3.2 Number and duration of unplanned interruptions

    All customers supported the use of the number and duration of unplanned

    interruptions as performance measures. Customers made the following comments or

    suggestions on three key aspects of the definitions of the two measures.

    Whether interruptions less than one minute should be included.Whether interruptions caused by extreme events should be included.

    How back-feeding and load management should be considered when measuring

    the duration of an interruption.

    3.2.1 Customer views: less than one minute interruptions

    Our consultation paper proposed that only those unplanned interruptions longer than

    1 minute should be reported and included in the targets. This would be consistent

    with the definition of an interruption for information disclosure and other Commerce

    Commission and Electricity Authority purposes.

    It is clear from the feedback that shorter interruptions are a problem, particularly for

    both directly connected large users and for industrial and other customers embedded

    in the distribution networks.

    For example, Powerco noted that: for some major process-intensive industrial

    connections, momentary outages of as little as thirty seconds can have a substantial

    negative impact on their business operations. NZSteel commented: after only 0.5s,

    NZSteel loses load and the damage is done. The large users and a number of

    distributors all requested that interruptions less than one minute be included. Other

    distributors considered that definitions of interruptions should be consistent with

    those used by distribution companies the SAIDI and SAIFI measures which

    exclude interruptions less than one minute.

    3.2.2 Our response: less than one minute interruptions

    Over the last five years, we have recorded 289 interruptions of less than one minute

    these are known as momentary interruptions. This compares with 712 longer

    interruptions over the same period.

    We do not measure the length of interruptions less than one minute and they are

    recorded with a duration of zero (All durations are rounded down to the nearest

    minute). However, most 281 out of 289 of the momentary interruptions were theresult of protection systems acting to remove faulted circuits from service followed by

  • 7/28/2019 Customer Facing Performance Measures Feedback Summary Response

    12/22

    Customer-facing performance measures: Customer feedback and response

    Customer-facing performance measures Transpower New Zealand Limited. All rights reserved.12

    a successful autoreclose operation. The vast majority of these momentary

    interruptions will have durations of 1 to 2 seconds7. These momentary interruptions

    generally have little impact on all but sensitive consumer loads.

    We report these momentary interruptions to our customers under the Benchmark

    Agreement requirements, and we will continue to do so. At this stage, we will notinclude these interruptions in our targets, but will investigate how we could do so in

    the future.

    Customer concern about momentary interruptions was related to concerns about

    voltage sags (which are covered in section 4.1.) Momentary interruptions and voltage

    sags can have similar impacts on our customers. We will set up an industry working

    group to look at how we might introduce voltage sag, momentary interruptions and

    other power quality reporting.

    3.2.3 Customer views: extreme events

    Our proposal raised the issue of whether we should include unplanned interruptions

    caused by extreme events in our measures and targets. Customers held different

    views but generally agreed that whether the events were included or excluded, we

    should provide information on them.

    For example Meridian commented: We consider it is reasonable to exclude outages

    caused by extreme conditions with respect to targets for outage frequency and

    duration, however we consider targets relating to information provision should still

    apply. Further, we consider that it is important to measure the frequency and

    duration of outages caused by extreme conditions in order to track long-term system

    resilience, even if such measures are not used as targets.

    Customers supporting the inclusion of the events said that since, in at least some

    cases, an economic solution to mitigating the impact of extreme conditions can be

    found, these interruptions should be included in the performance measures. While it

    is accepted that extreme conditions can and do have an impact on interruptions, it is

    possible to at least mitigate the impact of some extreme conditions.

    Customers supporting the exclusion of the events recognised that in some cases

    such as earthquakes our assets are not designed to withstand severe events.

    To exclude extreme events, we would need to develop a definition of what comprisesan extreme event. Customers had suggestions about how to define an extreme

    event, however some noted the difficulties in agreeing a definition and that the

    present extreme events regime used by the Commerce Commission is causing

    problems for distributors.

    3.2.4 Our response: extreme events

    We agree that we should report all events, and on balance consider that it is

    appropriate to include all events in our targets partly due to the problems in defining

    7The majority of the reclose time delays on our protection relays are set for 1s.

  • 7/28/2019 Customer Facing Performance Measures Feedback Summary Response

    13/22

    Customer-facing performance measures: Customer feedback and response

    Customer-facing performance measures Transpower New Zealand Limited. All rights reserved. 13

    extreme events and because it is possible to take account, at least partly, for extreme

    events in our asset management.

    3.2.5 Customer views: measuring duration (back-feeding and load

    management)

    We sometimes restore supply gradually through load management or a staged

    restoration. In other cases, distributors have arrangements in place to back-feed from

    other grid connections or from generators within their own network until we can

    restore supply.

    Our proposal raised the issue of how to measure the duration of an interruption.

    Customers responded with a range of suggestions:

    Interruption duration should end when the issues with Transpower assets are

    resolved.Duration should not be measured to the time when restoration is achieved

    through customer back-feeds and load management as this distorts

    Transpowers interruption duration statistics.

    The duration should be measured from when the customer loses supply to when

    the customer has full supply restored (ie no load management is required, but

    supply may be by back-feed or alternate configuration).

    Transpower could report to the customer when the supply is restored, but have

    an internal KPI to restore assets to service.

    It would be more appropriate to weight the restoration based on time to restore

    and customers affected rather than when first restoration occurs.

    In addition, customers made related comments:

    Back-feeding through the network places strain on distributor equipment which

    has a cost. If customers incur an additional cost of back-feeding or load

    management as a result of a transmission service fault, then that cost should be

    measured. The measurement should be in economic terms; though a time lapsed

    measure could be designed initially.

    Do unplanned interruptions include planned interruptions that are extended?

    Where a distribution solution is used to provide supply an avoided customer

    minutes could be recorded to provide an indication of how severe the interruptioncould have been if a distribution solution was not available/present.

    3.2.6 Our response: measuring duration (back-feeding and load management)

    We record two different durations; initial duration (which we generally report) and

    final duration.

    Initial duration is the elapsed time until the first significant tranche of customers have

    their supply restored, whether through bring assets back into service or through

    backfeeding. This is typically at least 50 percent of the load lost and possibly 80 to

    100 percent.

  • 7/28/2019 Customer Facing Performance Measures Feedback Summary Response

    14/22

    Customer-facing performance measures: Customer feedback and response

    Customer-facing performance measures Transpower New Zealand Limited. All rights reserved.14

    Final duration is the elapsed time until, for example, the last feeder is closed or, if

    restoration is by backfeed, all of our assets are back in service.

    Back-feeding or load management is often a cost-effective alternative to investing in

    N-1 reliability. We discuss these options with customers, and take account of them in

    our planning. There may be a cost associated with providing the backfeed, but thereis also the avoided cost of paying for higher security. For this reason, it makes sense

    to measure the duration of an interruption to the initial restoration even though our

    assets may not be restored to full operation. That reflects the outcome to the

    customer: to use an intermediary measure, such as our restoration time, could

    encourage us to invest when there is no change in outcome to the customer.

    In addition, the nature and speed of our response to an interruption is sometimes

    governed by the availability of a backfeed, so the duration to final restoration might

    be longer than would be the case without a backfeed being in place.

    We will continue to measure final duration but propose to continue reporting initialrestoration.

    Unplanned interruptions include all interruptions with less than 24 hours notice.

    Planned interruptions that overrun are not included in the unplanned interruptions. It

    is appropriate to report planned overruns separately from unplanned interruptions.

    Planned outage overruns are covered in more detail in section 4.3.

    3.3 Information provision

    3.3.1 Customer views: information provision

    Customers strongly valued clear and timely information provision and generally

    supported the proposed information provision measures and targets. Some noted

    that the quality of the information is more important than the timing and that

    information should be given as soon as it is available regardless of targets.

    Customers made the following suggestions:

    Information should include information on what is the worst that can happen.

    There should be a target for providing post-event information including what

    happened and what we are doing to prevent it happening again.

    There is a need to coordinate and avoid parallel paths of communication(distributors/retailers/system operator/grid operator).

    Information should be available even if it is not in the customers area as out-of-

    area customers may experience voltage sags.

    Information provision targets should also track communications when planned

    outages are delayed unexpectedly.

    Although customers widely supported the proposed measures, they differed in their

    views on the proposed targets. Here is a sample of views:

    The proposed targets for accuracy of restoration time might be too challenging

    with one customer suggesting that a window of two hours is more realistic.

  • 7/28/2019 Customer Facing Performance Measures Feedback Summary Response

    15/22

    Customer-facing performance measures: Customer feedback and response

    Customer-facing performance measures Transpower New Zealand Limited. All rights reserved. 15

    The target should be to provide some information within 15 minutes, with updates

    every 30 minutes.

    30 minutes to get information on estimated restoration time is too long as most

    interruptions are restored in less than 30 minutes.

    Provision of information about the interruption as soon as possible after the eventis critical preferably in a timeframe much less than the 15 minutes proposed.

    3.3.2 Our response: information provision

    We propose to report the information provision measures for unplanned interruptions

    as described in the consultation paper which were:

    Time to provide an initial notice.

    Time to provide follow-ups.

    Accuracy of restoration estimate.

    We will set targets for the first of these two measures, but at this point we are

    proposing to report the accuracy of the restoration estimates without targets. We

    expect that reporting these measures will provide both us and our customers with

    useful information and will encourage discussions around the types of information

    customers value during unplanned interruptions.

    Reporting accuracy of restoration estimates is new for us and we want to build

    experience in reporting this measure. Setting targets now may drive compliance with

    targets at the expense of quality and timely information.

    Customers provided useful feedback on other aspects of our communication and wepropose to include these concerns in a wider review of what we communicate and

    how we communicate to customers. The review should involve: discussions with

    customers on coordination of communication and on post-event information, and

    discussions with the Electricity Authority on the requirements set out in the

    Benchmark Agreement and Part 12 of the Electricity Industry Participation Code.

    3.4 Comparisons with distribution

    3.4.1 Customer views

    We received mixed views on this proposed measure. Some customers saw thesemeasures as interesting but we received the following feedback:

    Cross-New Zealand averages hold little relevance; different regions may have

    very different performance. We could consider comparisons by distribution

    company region, but these may not be statistically significant.

    It is not clear how these measures would influence behaviour.

    If these measures are to be used we need to ensure we are comparing like with

    like. Horizon summed up the pitfalls in interpretation of this measure: With the

    addition of relative cost comparisons the measure may help inform future

    investment decision making, however without access to a lot of backgroundmaterial it will be interpreted incorrectly. For example it does not provide a valid

  • 7/28/2019 Customer Facing Performance Measures Feedback Summary Response

    16/22

    Customer-facing performance measures: Customer feedback and response

    Customer-facing performance measures Transpower New Zealand Limited. All rights reserved.16

    comparison of relative asset performance due to the differing nature of

    transmission and distribution grids.

    3.4.2 Our response

    There are some practical problems in calculating these measures. As they are

    comparisons with distribution company numbers and durations of interruptions we

    need to ensure that we are comparing like with like.

    For example, SAIDI and SAIFI calculations require knowledge of the number of ICPs

    (Installation Control Points) connected to the point of service. For small remote points

    of service this is sometimes straightforward, but if the customer has a meshed

    system and routinely transfers customers to one point of service or the other, we

    would not know how many ICPs are affected.

    Our discussions with customers suggested that it is unlikely that these measures will

    provide information we or our customers can usefully act on.

    We are not proceeding with these measures.

  • 7/28/2019 Customer Facing Performance Measures Feedback Summary Response

    17/22

    Customer-facing performance measures: Customer feedback and response

    Customer-facing performance measures Transpower New Zealand Limited. All rights reserved. 17

    4 Other issues and possible measures

    4.1 Voltage sags

    4.1.1 Customer views: voltage sags

    A number of customers cited power quality and voltage sags in particular as just as

    important an issue as losses of supply.

    Voltage sags are caused mainly by faults or large, sudden changes in load. A fault

    can depress voltages a long distance away for up to several seconds until the fault is

    removed. Large changes in load can cause voltage drops which will remain until

    voltage regulating equipment can act to improve voltages. Some equipment and

    appliances cannot ride out these voltage sags and either operation is affected for a

    short time, protection systems trip, or the equipment itself fails. These types of

    voltage sags can occur more frequently than full losses of supply.

    This comment from Carter Holt Harvey was typical of comments from large users:

    For many customers, a momentary loss or even a momentary voltage dip has an

    impact on them that is similar to a total loss of supply of a minute or more so these

    types of outage should be included in any assessment or measure of outages.

    Whilst voltage quality is not a problem for all distributors, a number gave examples of

    problems: a voltage fluctuation can turn lights off in freezing works causing injuries,

    cause flaws in weave at a woollen mill, or cause wastage for a preserving works.

    Distributed generation can also be affected.

    One customer said that it is essential to include measures on voltage sags and

    suggested reporting against statistical limits. Other customers commented that it is

    important to at least start reporting and providing information on voltage quality.

    4.1.2 Our response: voltage sags

    We will not include voltage sag as part of our RCP2 performance measures and

    targets. We do not yet have enough understanding about voltage sag to be able to

    set meaningful targets.

    While we currently have a fully developed, formal system for recording and reportingprimary equipment outages and interruptions, there is nothing similar in place for

    voltage sags or other aspects of power quality such as harmonics or transients.

    However, we are installing new revenue meters at grid exit points that come

    complete with the built-in capability to automatically record (and analyse) power

    quality. The nationwide meter replacement programme will be completed by around

    May 2013.

    We already have access to the power quality information from some of the

    meters. There is also a back-office software system we have deployed to manage

    access to the power quality information.

  • 7/28/2019 Customer Facing Performance Measures Feedback Summary Response

    18/22

    Customer-facing performance measures: Customer feedback and response

    Customer-facing performance measures Transpower New Zealand Limited. All rights reserved.18

    Given the infrastructure that is in place, or will shortly be in place, it would be

    possible to design and develop a power quality monitoring and reporting

    service. This might take a range of forms, and we need to identify what would be of

    most use to customers.

    At this point, we will not include voltage quality in our performance measures andtargets for the next regulatory control period (RCP2) because there are too many

    uncertainties around what would be the most useful, our ability to record and report

    any measures and our only partial of control over power quality.

    We will set up an industry working group to analyse the voltage disturbance

    information becoming available with the end goal of determining voltage sag

    measurements and targets that are meaningful and valuable to customers and end

    consumers. This working group will also look at reporting and targets for momentary

    interruptions. We may trial some measures and targets and incorporate them in a

    later regulatory control period proposal.

    4.2 Economic impact

    4.2.1 Customer views: economic impact

    A number of customers (including generator-retailers, distributors and large

    industrials) would like to see a measure that more closely reflects the financial impact

    of interruptions.

    Customers suggested that we include a financial loss measure based on VOLL. One

    suggested that every event should be followed up and a financial impact recorded.

    Another suggested a MWh or unserved energy measure would be useful8.

    Customers acknowledge the limitations of VOLL. For example, MEUG made the

    following comment in its feedback: We accept that . VOLL is prone to wide error

    bounds. Nevertheless publication of a dollar impact range with wide probability

    distributions provides another measure to prioritise effort to reduce USE [Unserved

    Energy] in the future.

    4.2.2 Our response: economic impact

    Ideally, our performance measures should reflect the economic impacts on our

    customers and the wider impacts on New Zealand.

    At present, the Electricity Authority and Commerce Commission use a $20,000/MWh

    value for VOLL, but as mentioned in section 3.1.2, the Electricity Authority is

    undertaking a study to establish appropriate VOLL ranges for New Zealand electricity

    consumers.

    When this study is complete, assuming it provides a more robust and wider

    assessment of VOLL, we can report the value of lost load for interruptions in order to

    provide an indication of the potential economic impact of interruptions.

    8

    We report annual unserved energy for planned and unplanned interruptions under theBenchmark Agreement, although this report does not show the unserved energy for individualevents. We also report to customers breaches of the service levels for unserved energy.

  • 7/28/2019 Customer Facing Performance Measures Feedback Summary Response

    19/22

    Customer-facing performance measures: Customer feedback and response

    Customer-facing performance measures Transpower New Zealand Limited. All rights reserved. 19

    4.3 Planned outages and the impact on the market

    4.3.1 Customer views: planned outages and impact on the market

    The three generator-retailers who provided feedback were concerned that ourproposed measures did not cover planned equipment outages and the impacts that

    our performance can have on the electricity market.

    In summary, their concerns were:

    That asset availability can have impacts on the electricity market and therefore

    our customers. When assets are not available through planned or unplanned

    outages, this can restrict generators ability to provide electricity to the market

    and can increase prices. Over time, any market impacts faced by generators are

    likely to be passed on to end consumers. Outage frequency and duration will

    contribute to the size of market impacts, but outage timing (eg peak or offpeak) isalso critical. Meridian particularly mentioned the impact on the market from the

    unavailability of the HVDC.

    Minimising and avoiding planned outages is important; these outages comprise a

    majority of total outages.

    Unplanned extensions to planned outages should be included as unplanned

    outages.

    The existing net-benefit test9 applying to grid outage decisions does not provide

    sufficient incentive for Transpower to take account of market impacts.

    Generators suggested possible measures that could be introduced:

    Targets for planned outages completed on time.

    Targets for information provision for planned as well as unplanned outages,

    including the quality and notice period of information provided. Such targets

    might include churn (i.e. how many times an outage schedule is revised), and

    variations between actual and estimated return times.

    4.3.2 Our response: planned outages and the impact on the market

    In our proposal we did not include measures that related to market impact. This is not

    because we do not recognise the importance of optimising grid availability with

    respect to the market: rather, it is because of the difficulty in doing it so it positively

    influences our performance.

    Losses and constraints are heavily affected by the behaviour of generators and

    retailers - not just Transpower performance - and the wholesale market includes

    pricing mechanisms to take account of losses and constraints. In addition, the

    Electricity Authority is implementing Financial Transmission Rights which will enable

    the market to better manage some costs and risks associated with constraints.

    9

    The net benefit test is specified in part 2 of Appendix A of the Outage Protocol. If aninterested participant does not think a planned outage meets the net benefit principle,Transpower must carry out a net benefit test on the planned outage.

  • 7/28/2019 Customer Facing Performance Measures Feedback Summary Response

    20/22

    Customer-facing performance measures: Customer feedback and response

    Customer-facing performance measures Transpower New Zealand Limited. All rights reserved.20

    We also did not include measures related to planned outages as the outage

    protocol10 prescribes the process and considerations involved in planning outages11.

    However, general availability measures provide reporting that covers both planned

    and unplanned outages. We are required to have at least one asset performance

    measure in our RCP2 performance targets. We intend to include HVDC branchavailability targets as the availability of the HVDC link has a major effect on market

    outcomes. We will also include some availability measures for some other core grid

    branches with a significant market impact as part of our RCP2 proposal. Possible

    branches are the 220kV circuits from Haywards to Bunnythorpe through to

    Whakamaru (including those that are part of the Wairakei Ring.)

    We recognise that extensions to planned interruptions can be disruptive to

    customers, but it is appropriate to report them separately from unplanned

    interruptions. They have different impacts on customers than unplanned interruptions

    and they are driven by different aspects of our performance.

    Currently, we notify customers directly when a planned interruption overruns through

    the interruption to connection notices. We also report planned interruption restoration

    performance, under information disclosure requirements.

    We do not at present compile reports on planned outage overruns but we will

    introduce reporting planned outage restoration and set targets. We have some work

    to do to develop the measure and to set targets.

    4.4 Risks of non-supply

    4.4.1 Customer views: risk of non-supply

    Both through discussions at meetings and written feedback it is clear that

    understanding the risks of non-supply is an important matter to customers.

    Customers commented that they want to know when planned or unplanned

    equipment outages place them at higher risk of interruption. A number of customers

    suggested we report when the security of their supply moves from N-1 to N.

    4.4.2 Our response: risk of non-supply

    We consider the ability to signal future risks of non-supply to be more valuable to

    customers and end customers than analysis of historic risks (although these areinformative).

    We communicate our upcoming outage plans to customers as part of our outage

    planning processes. However, the risks of non-supply that these outages pose are

    not necessarily presented clearly.

    Upon request we can arrange notice of upcoming outages that cause individual

    customers to be placed on N security to be provided. As part of a wider review of

    10The Outage Protocol is incorporated into the Code bv reference and is available at:

    http://www.ea.govt.nz/dmsdocument/905911Planned outages and interruptions are those for which at least 24 hours notice has been

    given, all remaining outages and interrupions are unplanned.

    http://www.ea.govt.nz/dmsdocument/9059http://www.ea.govt.nz/dmsdocument/9059http://www.ea.govt.nz/dmsdocument/9059
  • 7/28/2019 Customer Facing Performance Measures Feedback Summary Response

    21/22

    Customer-facing performance measures: Customer feedback and response

    Customer-facing performance measures Transpower New Zealand Limited. All rights reserved. 21

    what and how we communicate to customers, we intend to look at options for

    communicating risks of future non-supply to customers.

    We will also report on a national time on N security measure and are investigating

    ways to measure and report this.

    4.5 Qualitative customer service

    4.5.1 Customer views: customer service

    Powerco suggested that we should include a measure that reflects our customer

    service and interactions with customers. Powerco commented that meaningful

    interaction with customers, the on-going provision of information even when no

    particular problem exists and the perception that a constructive approach is being

    taken to customer relationships are all important.

    Powerco proposed that an overall target rating from Transpowers annual customer

    satisfaction survey should form part of the set of customer-facing grid performance

    measures but should not be linked to revenue.

    4.5.2 Our response: customer service

    We already include this as an important internal performance indicator and plan to

    continue to do so rather than include it in our grid performance measures.

    4.6 Feedback: other issues

    There were a number of issues that customers provided views on that we will

    consider as we progress our work. These are summarised here.

    4.6.1 Customer views: targets

    We did not ask customers specifically about the proposed targets, however,

    customers made the following comments and we will take these into account as we

    finalise the targets:

    The objective should be to target a downwards trend in interruptions or an

    improvement in service.

    One approach may be to have both average and maximum targets.

    Targets should be what we tell you, not what you tell us.

    Targets should be driven by business targets, not historical performance.

    Indicative targets shown for generation connection locations are broadly in line

    with those for standard (rural) loads. Many generation connection locations,

    particularly those on the 220 kV grid and interconnected grid, enjoy a high level of

    transmission security via multiple circuits. In comparison, many rural connection

    locations would fall into the category of relatively low security connection grid

    spurs. Performance targets should therefore be relatively ambitious for high

    security generation connection locations, scaling downwards as the level of

    redundancy decreases.

  • 7/28/2019 Customer Facing Performance Measures Feedback Summary Response

    22/22

    Customer-facing performance measures: Customer feedback and response

    4.6.2 Customer views: Benchmark agreements

    Transmission customers Transmission Agreements (based on the Benchmark

    Agreement) currently include a schedule on service measures. A number of

    customers noted that they would support Transpower and the Electricity Authority

    amending these service measures to align with the final performance measures thatwe develop.

    Some customers were dissatisfied with the current Benchmark Agreement measures

    noting that:

    They were imposed on both customers and Transpower rather than negotiated.

    They are based on historic performance rather than forward-looking objectives.

    The performance reporting required under the Benchmark Agreement is not of

    value.

    4.6.3 Customer views: price-quality and getting the incentives right

    Customers have concerns that:

    Incentives should be aligned with the costs of interruptions and not encourage

    inefficient spending.

    That the performance targets will be different for different points of service, so

    customers should be given the ability to make price quality trade-offs.

    That there is no direct compensation to individual customers for poor

    performance.