Current DG Framework for Competitive Areas of ERCOT DREAM TF September 28, 2015.

21
Current DG Framework for Competitive Areas of ERCOT DREAM TF September 28, 2015

Transcript of Current DG Framework for Competitive Areas of ERCOT DREAM TF September 28, 2015.

Page 1: Current DG Framework for Competitive Areas of ERCOT DREAM TF September 28, 2015.

Current DG Framework for Competitive Areas of ERCOTDREAM TFSeptember 28, 2015

Page 2: Current DG Framework for Competitive Areas of ERCOT DREAM TF September 28, 2015.

PurposeProvide a basic understanding of the current DG market framework for the competitive areas of ERCOT and clarify terminology, governance structure, and market processes related to DG

DisclaimerAlthough every attempt has been made to ensure the accuracy of the information provided herein, due to summarization, illustration, and other factors, inexact or erroneous information may exist. This presentation is not a substitute for the applicable statutes, rules, protocols, and guides. If any conflict exists between this presentation and the governing statutory and regulatory documents, those documents shall control in all respects.

2

Page 3: Current DG Framework for Competitive Areas of ERCOT DREAM TF September 28, 2015.

Relevant Terms*

Electric Generating Facility12

Non-Modeled Generator3

Generation Resource3

ERS Generator3

Distributed Resource2

On-site Distributed Generation123

Distributed Natural Gas Generation Facility12

Distributed Renewable Generation123

Independent School District-Solar Generation2

1 – PURA2 – PUCT Subst. Rules3 – ERCOT Protocols 3*See Appendix for definitions

Page 4: Current DG Framework for Competitive Areas of ERCOT DREAM TF September 28, 2015.

Specific DG-Related Statutes*

• Develops provisions for: • Owners/operators to sell electric power• Use of T&D Facilities to transport electric power• Utilities to recover costs of facilities for used for interconnection

PURA 35.036 – Distributed Natural Gas Generation Facilities

• Develops provisions for:• Interconnection of DRG• PUCT creation of rules and requirements for DRG• Requirement for TDU to measure out-flow• Ownership of Renewable Energy Credits• Selling surplus electricity to REP

PURA 39.916 – Interconnection of Distributed Renewable Generation

• Customers entitled to have access to on-site distributed generation

PURA 39.101 – Customer Safeguards

• Develops provisions for:• Allowing Independent School Districts to sell surplus energy form solar generation• Requiring utilities to provide metering to allow sell of energy

PURA 39.914 – Credit for Surplus Solar Generation by Public Schools

*other statutes may be applicable to DG based on operation in the ERCOT wholesale market 4

Page 5: Current DG Framework for Competitive Areas of ERCOT DREAM TF September 28, 2015.

Registration

• May require registration as • Power Generation Company, if

generating electricity intended to be sold at wholesale or

• Self-Generator, if rating is greater than or equal to 1MW and not a PGC

• Generally, DRG facilities are not required to register

PUCT

• DG with installed capacity of greater than 1MW, must register

• If required to have an IDR Meter and want settlement, must register as Generation Resource

• Protocol language unclear on when registration required as Generation Resource. May be required for distributed generation if capable of providing energy or Ancillary Service

ERCOT

5

Page 6: Current DG Framework for Competitive Areas of ERCOT DREAM TF September 28, 2015.

Interconnection

PUCT

• Detailed in PUCT Subst. Rules 25.211 & 25.212• Only applicable to facilities 10MW and less connected to the distribution

system• Intended to develop standard interconnection process and timeline for

distributed generation• TDUs may require supplemental terms and conditions

ERCOT

• Protocols and Guides do not addresses interconnection of DG facilities

6

Page 7: Current DG Framework for Competitive Areas of ERCOT DREAM TF September 28, 2015.

DRG MeteringPURA 39.916 (f) A [TDU] … shall make available to a [DRGO] … metering required for services provided under this section, including separate meters that measure the load and generator output or a single meter capable of measuring in-flow and out-flow at the point of common coupling meter point.

PUCT Subst. Rule 25.213 (b) (1) …an electric utility shall provide metering at the point of common coupling using one or two meters that separately measure both the customer’s electricity consumption from the distribution network and the out-flow that is delivered from the customer’s side of the meter to the distribution network …

7

Page 8: Current DG Framework for Competitive Areas of ERCOT DREAM TF September 28, 2015.

Metering

• For registered DG, ERCOT requires IDR Meter (BUSIDRRQ Profile)▫ Interval data submitted monthly via 867_03 transaction▫ In-flow energy associated with ESIID▫ Out-flow energy associated with RID

• Can opt to have ERCOT Polled Settlement (EPS) metering▫ ERCOT polls daily▫ Customer must pay differential cost for metering if not required

8

Page 9: Current DG Framework for Competitive Areas of ERCOT DREAM TF September 28, 2015.

Wholesale Storage Load

• Energy that is separately metered from all other Facilities to charge a technology that is capable of storing energy and releasing that energy at a later time to generate electric energy

• Exempt from charges and credits based on Load Ratio Share or per MWH basis

• Will not be included in the ERCOT 4CP calculations

• Pricing shall be based on the LMP at the electrical bus

9

Page 10: Current DG Framework for Competitive Areas of ERCOT DREAM TF September 28, 2015.

Settlement

Unregistered DG

•Energy settled as “negative Load”•QSE benefits from reduced Load and is effectively compensated at Load Zone Settlement Point Price•Energy payments to customer covered in bilateral contract between customer and REP

Registered DGSame QSE for Load and Generation

•QSE paid directly for energy out-flow at Load Zone Settlement Point Price•QSE charged Load Zone Settlement Point Price for each interval of energy in-flow (Net Load)•Energy payments to customer covered in bilateral contract between customer and REP/QSE

Registered DGDifferent QSEs for Load and

Generation

•DG QSE paid directly for energy out-flow at Load Zone Settlement Point Price•REP QSE charged Load Zone Settlement Point Price for each interval of energy in-flow (Net Load) •Energy payments to customer covered in bilateral contract between customer and DG QSE

10

Page 11: Current DG Framework for Competitive Areas of ERCOT DREAM TF September 28, 2015.

PUC Reporting

• Per PUC Subst. Rule 25.211 (n), utilities must file annual report identifying each interconnected DG facility by March 30th

• Reports for 2014 are filed under PUC Project #44023

Report includes:

• New DG Facilities since previous report

• Change in ownership or cessation of operations that has been reported to the utility

• Capacity of each facility and whether it’s a renewable energy resource

• Feeder or other point of connection to distribution system

• All applications for interconnections received for previous 1-yr period and the disposition of those applications

11

Page 12: Current DG Framework for Competitive Areas of ERCOT DREAM TF September 28, 2015.

ERCOT Reporting

• TDSPs in competitive areas submit DG information to ERCOT for each unregistered DG facility (<=1MW)

• Currently, ERCOT produces report of unregistered DG greater than 50kW

DG Information submitted:

• ESI ID• Generation type• Interconnection Agreement effective

date• Total inverter capacity• The inverter's published peak

efficiency rating• Total PV generation capacity in kW• Total wind generation capacity in kW• For other generation types, total

generation capacity in kW

12

Page 13: Current DG Framework for Competitive Areas of ERCOT DREAM TF September 28, 2015.

NPRR719 & COPMGRR040

•Removes threshold for unregistered DG in single load zone

•NRG comments remove reporting threshold of 50kW and modifies reporting requirements

•NPRR currently tabled at PRS & COPMGRR currently at COPS awaiting approval

13

Page 14: Current DG Framework for Competitive Areas of ERCOT DREAM TF September 28, 2015.

Appendix

14

Page 15: Current DG Framework for Competitive Areas of ERCOT DREAM TF September 28, 2015.

References

Slide 3 • PURA 31.002 – Definitions• PURA 39.916 – Interconnection of Distributed Renewable Generation• PUC Subst. Rules 25.5 – Definitions• PUC Subst. Rules 25.211 – Interconnection of On-Site Distributed Generation• PUC Subst. Rules 25.217 – Distributed Renewable Generation• ERCOT Protocols Section 2.1 – Definitions

Slide 4 • PURA 35.036 - Distributed Natural Gas Generation Facilities• PURA 39.101 – Customer Safeguards• PURA 39.914 – Credit for Surplus Solar Generation by Public Schools• PURA 39.916 – Interconnection of Distributed Renewable Generation

15

Page 16: Current DG Framework for Competitive Areas of ERCOT DREAM TF September 28, 2015.

References (cont.)

16

Slide 5 • PUC Subst. Rule 25.109 – Registration of Power Generation Companies and Self Generators

• PUC Subst. Rule 25.217 – Distributed Renewable Generation• ERCOT Protocols Section 3.7 – Resource Parameters• ERCOT Planning Guide Section 6.8 – Resource Registration Procedures• ERCOT Protocols Section 16.5 – Registration of Resource Entities• ERCOT Retail Market Guide Section 7.14 – Out-flow Energy from Distributed

Generation Facilities Slide 6 • PUC Subst. Rule 25.211 – Interconnection of On-Site Distributed Generation (DG)

• PUC Subst. Rule 25.212 – Technical Requirements for Interconnection and Parallel Operation Of On-Site Distributed Generation

Slide 7 • PURA 39.916 – Interconnection of Distributed Renewable Generation• PUC Subst. Rule 25.213 – Metering for Distributed Renewable Generation and

Certain Qualifying Facilities

Page 17: Current DG Framework for Competitive Areas of ERCOT DREAM TF September 28, 2015.

References (cont.)

17

Slide 8 • ERCOT Protocols Section 10.2 – Scope of Metering Responsibilities• ERCOT Protocols Section 10.9 – Standards for Metering Facilities

Slide 9 • PUC Subst. Rule 25.192 – Transmission Service Rates• PUC Subst. Rule 25.501 – Wholesale Market Design• ERCOT Protocols Section 2.1 – Definitions

Slide 10 • ERCOT Protocols Section 6.6.3.2 – Real-Time Energy Imbalance Payment or Charge at a Load Zone

• ERCOT Protocols Section 11.4.4 – Data Aggregation Processing for Actual DataSlide 11 • PUC Subst. Rule 25.211 – Interconnection of On-Site Distributed Generation (DG)

Page 18: Current DG Framework for Competitive Areas of ERCOT DREAM TF September 28, 2015.

References (cont.)

18

Slide 12 • ERCOT Protocols Section 16.5 – Registration of a Resource Entity • ERCOT Commercial Operations Market Guide Section 10.3 – Unregistered

Distributed Generation Reports• ERCOT Retail Market Guide Section 7.14 – Out-flow Energy from Distributed

Generation Facilities • ERCOT Load Profiling Guide Appendix D – Load Profiling Decision Tree

Slide 13 • NPRR719 – Removal of Trigger and Requirement to Reduce the Distributed Generation (DG) Registration Threshold

• COPMGRR040 – Alignment with NPRR719, Removal of Trigger and Requirement to Reduce the Distributed Generation (DG) Registration Threshold

Page 19: Current DG Framework for Competitive Areas of ERCOT DREAM TF September 28, 2015.

PURA Definitions

• Distributed natural gas generation facility – a facility installed on the customer's side of the meter that uses natural gas to generate not more than 2,000 kilowatts of electricity

• Distributed renewable generation – electric generation with a capacity of not more than 2,000 kilowatts provided by a renewable energy technology, as defined by [PURA] Section 39.904, that is installed on a retail electric customer's side of the meter

• Electric generating facility – a facility that generates electric energy for compensation and is owned or operated by a person in this state, including a municipal corporation, electric cooperative, or river authority

19

Page 20: Current DG Framework for Competitive Areas of ERCOT DREAM TF September 28, 2015.

PUCT Definitions

• Distributed natural gas generation facility – a facility installed on the customer’s side of the meter that uses natural gas to generate not more than 2,000 kilowatts of electricity

• Distributed renewable generation (DRG) – electric generation equipment with a capacity of not more than 2,000 kilowatts provided by a renewable energy technology, as defined by Public Utility Regulatory Act §39.904(d), installed on a retail electric customer’s side of the meter

• Distributed resource – A generation, energy storage, or targeted demand-side resource, generally between one kilowatt and ten megawatts, located at a customer's site or near a load center, which may be connected at the distribution voltage level (below 60,000 volts), that provides advantages to the system, such as deferring the need for upgrading local distribution facilities.

• Electric generating facility – a facility that generates electric energy for compensation and that is owned or operated by a person in this state, including a municipal corporation, electric cooperative, or river authority.

• ERS resource – a resource contracted to provide ERS that meets one of the following descriptions: (A) A load or aggregation of loads; or (B) A dispatchable generator that is not registered with ERCOT as a Generation Resource, or an aggregation of such generators

• Independent school district solar generation (ISD-SG) – solar electric generation equipment installed on the customer’s side of the meter at a building or other facility owned or operated by an independent school district, irrespective of the level of generation capacity

• On-site distributed generation (or distributed generation) – an electrical generating facility located at a customer’s point of delivery (point of common coupling) of ten megawatts (MW) or less and connected at a voltage less than 60 kilovolts (kV) which may be connected in parallel operation to the utility system.

• Resource – a generation resource, or a load capable of complying with ERCOT instructions to reduce or increase the need for electrical energy or to provide an ancillary service (i.e., a “load acting as a resource”).

• Resource – Facilities capable of providing electrical energy or load capable of reducing or increasing the need for electrical energy or providing short-term reserves into the ERCOT system. This includes generation resources and loads acting as resources (LaaRs)

20

Page 21: Current DG Framework for Competitive Areas of ERCOT DREAM TF September 28, 2015.

ERCOT Definitions

• Distributed Generation (DG) – An electrical generating facility located at a Customer’s point of delivery (point of common coupling) ten megawatts (MW) or less and connected at a voltage less than or equal to 60 kilovolts (kV) which may be connected in parallel operation to the utility system.

• Distributed Renewable Generation (DRG) – Electric generation with a capacity of not more than 2,000 kW provided by a renewable energy technology that is installed on a retail electric Customer’s side of the meter.

• Emergency Response Service (ERS) Generator – Either (1) an individual generator contracted to provide ERS which is not a Generation Resource or a source of intermittent renewable generation and which provides ERS by injecting energy to the ERCOT System, or (2) an aggregation of such generators.

• Generation Resource – A generator capable of providing energy or Ancillary Service to the ERCOT System and is registered with ERCOT as a Generation Resource. The term “Generation Resource” used by itself in [the ERCOT] Protocols does not include a Non-Modeled Generator.

• Non-Modeled Generator – A generator that is: ▫ (a) Capable of providing net output of energy to the ERCOT System; ▫ (b) Ten MW or less in size; or greater than ten MW and registered with the PUCT according to P.U.C. SUBST. R. 25.109, Registration

of Power Generation Companies and Self-Generators, as a self-generator; and ▫ (c) Registered with ERCOT as a Non-Modeled Generator, which means that the generator may not participate in the Ancillary

Service or energy markets, RUC, or SCED.

21