CUNY/CUCF NYCCT New Academic Building
F.J. Sciame Construction PresentationAugust 12, 2013
![Page 2: CUNY/CUCF NYCCT New Academic Building F.J. Sciame Construction Presentation August 12, 2013.](https://reader036.fdocuments.in/reader036/viewer/2022062619/5518acf4550346881f8b4d5e/html5/thumbnails/2.jpg)
NYCCT New Academic Building Project Details
• 356,839 Square Foot New Academic Building– 8-Story Building with Training Lab, Classroom and Office Spaces– 1,000 Seat Auditorium– 800 Seat Gymnasium– Underground Parking Garage
• Start of Construction – January 2013• End of Construction – Spring 2017• MBE Requirement = 12% (NY State Certified)• WBE Requirement = 8% (NY State Certified)• Project Labor Agreement (Union Project)
![Page 3: CUNY/CUCF NYCCT New Academic Building F.J. Sciame Construction Presentation August 12, 2013.](https://reader036.fdocuments.in/reader036/viewer/2022062619/5518acf4550346881f8b4d5e/html5/thumbnails/3.jpg)
Project Site Plan Jay Street and Tillary Street, Brooklyn, NY
![Page 4: CUNY/CUCF NYCCT New Academic Building F.J. Sciame Construction Presentation August 12, 2013.](https://reader036.fdocuments.in/reader036/viewer/2022062619/5518acf4550346881f8b4d5e/html5/thumbnails/4.jpg)
Project Site Plan Jay Street and Tillary Street, Brooklyn, NY
![Page 5: CUNY/CUCF NYCCT New Academic Building F.J. Sciame Construction Presentation August 12, 2013.](https://reader036.fdocuments.in/reader036/viewer/2022062619/5518acf4550346881f8b4d5e/html5/thumbnails/5.jpg)
NYCCT New Academic Building Material Quantities
• Structural Steel: 4,600 Tons
• Steel Stairs: 18 Each
• Superstructure Concrete: 388,000 SF
• Masonry (CMU): 79,000 SF
• Exterior Wall System: 139,000 SF
• Tile Roofing: 43,000 SF
• Kemper/EPDM Roofing: 47,000 SF
• Laboratory Casework: 7,000 LF
• HM and Wood Doors: 651 Each
• Dental Chairs / Equipment: 24 Each
• GWB Walls and Ceilings: 877,000 SF
• Acoustical Tile Ceilings: 8,000 SF
• Ceramic Tile: 61,000 SF
• Wood Flooring: 44,000 SF
• Terrazzo Flooring: 35,000 SF
• Carpeting: 4,500 SY
• Resilient Tile Flooring: 35,000 SF
• Painting: 806,000 SF
• Elevators: 9 Each
• Escalators: 14 Each
![Page 6: CUNY/CUCF NYCCT New Academic Building F.J. Sciame Construction Presentation August 12, 2013.](https://reader036.fdocuments.in/reader036/viewer/2022062619/5518acf4550346881f8b4d5e/html5/thumbnails/6.jpg)
![Page 7: CUNY/CUCF NYCCT New Academic Building F.J. Sciame Construction Presentation August 12, 2013.](https://reader036.fdocuments.in/reader036/viewer/2022062619/5518acf4550346881f8b4d5e/html5/thumbnails/7.jpg)
![Page 8: CUNY/CUCF NYCCT New Academic Building F.J. Sciame Construction Presentation August 12, 2013.](https://reader036.fdocuments.in/reader036/viewer/2022062619/5518acf4550346881f8b4d5e/html5/thumbnails/8.jpg)
![Page 9: CUNY/CUCF NYCCT New Academic Building F.J. Sciame Construction Presentation August 12, 2013.](https://reader036.fdocuments.in/reader036/viewer/2022062619/5518acf4550346881f8b4d5e/html5/thumbnails/9.jpg)
![Page 10: CUNY/CUCF NYCCT New Academic Building F.J. Sciame Construction Presentation August 12, 2013.](https://reader036.fdocuments.in/reader036/viewer/2022062619/5518acf4550346881f8b4d5e/html5/thumbnails/10.jpg)
![Page 11: CUNY/CUCF NYCCT New Academic Building F.J. Sciame Construction Presentation August 12, 2013.](https://reader036.fdocuments.in/reader036/viewer/2022062619/5518acf4550346881f8b4d5e/html5/thumbnails/11.jpg)
![Page 12: CUNY/CUCF NYCCT New Academic Building F.J. Sciame Construction Presentation August 12, 2013.](https://reader036.fdocuments.in/reader036/viewer/2022062619/5518acf4550346881f8b4d5e/html5/thumbnails/12.jpg)
![Page 13: CUNY/CUCF NYCCT New Academic Building F.J. Sciame Construction Presentation August 12, 2013.](https://reader036.fdocuments.in/reader036/viewer/2022062619/5518acf4550346881f8b4d5e/html5/thumbnails/13.jpg)
![Page 14: CUNY/CUCF NYCCT New Academic Building F.J. Sciame Construction Presentation August 12, 2013.](https://reader036.fdocuments.in/reader036/viewer/2022062619/5518acf4550346881f8b4d5e/html5/thumbnails/14.jpg)
![Page 15: CUNY/CUCF NYCCT New Academic Building F.J. Sciame Construction Presentation August 12, 2013.](https://reader036.fdocuments.in/reader036/viewer/2022062619/5518acf4550346881f8b4d5e/html5/thumbnails/15.jpg)
![Page 16: CUNY/CUCF NYCCT New Academic Building F.J. Sciame Construction Presentation August 12, 2013.](https://reader036.fdocuments.in/reader036/viewer/2022062619/5518acf4550346881f8b4d5e/html5/thumbnails/16.jpg)
Procurement Process• Competitive Public Bidding Process
• Awarded to Lowest Responsive and Responsible Bidder
• Multiple Bid Packages
• Bidding and Partnering Opportunities for Prime Contractors, Subcontractors, Vendors & Suppliers
• CUCF/CUNY Advertises all Prime Contracts on:– New York State Contract Reporter – http://nyscr.org– New York City Record – http://a856-internet.nyc.gov/nycvendoronline/home.asp– Minority Commerce Weekly – http://mcwbids.com
• Register on Sciame Website to Download Bid Packages and Bidder Lists for NYCCT New Academic Building Project – http://cuny.sciame.com/
• Register for CUNY/CUCF’s Solicitation Outreach List at www.cuny.edu/cunybuilds
![Page 17: CUNY/CUCF NYCCT New Academic Building F.J. Sciame Construction Presentation August 12, 2013.](https://reader036.fdocuments.in/reader036/viewer/2022062619/5518acf4550346881f8b4d5e/html5/thumbnails/17.jpg)
Preliminary Bid / Award Schedule
Previously Awarded (or Award in Progress) Spring / Summer 2014- Demolition / Abatement - Misc. Specialties- Structural Steel / Misc Metals / Stairs - Parking Control Equipment- Superstructure Concrete - Theatrical / Gym Rigging- Curtainwall / Storefront - Dental Chairs / Med. Equipment- AV / IT / Tel-Data / Security - Food Service Equipment- Mechanical / HVAC / Controls - Shades / Window Treatments /
Draperies - Fire Protection - Auditorium Seating - Plumbing - Painting / Intumescent Paint- Elevators / Escalators
Fall / Winter 2013 Fall / Winter 2014- Ornamental Metals / Glass & Glazing - Landscaping / Sidewalks / Curbs / Paving- Sidewalk Bridge / Temp Hoist - Carpet / Resilient Tile & Wood Flooring- Spray Fireproofing - Ceramic Tile & Stone- Drywall / Acoustical Ceilings / HM Doors - Terrazzo Flooring / Epoxy Flooring - Façade Maintenance - Landscaping / Sidewalks / Curbs / Paving- Roofing / Tile Roofing / Waterproofing- Architectural Woodwork / Lab Casework