APPLYING MANAGEMENT SCIENCE MODELING TECHNIQUES
Managing Project with CPM Model
MANAGEMENT SCIENCEADB-MBA PROGRAM, BATCH 10
GROUP 3Erin Lumanta
Marjorie Anne O. JavillonarMinerva B. Abrera
Submitted to:Prof. Rene J. Aguila
Date Submitted:14 March 2011
I. Introduction
Management Science is very important in making the right business decision for different
situations in any organization. This paper will show how CPM is utilized in the planned reorga-
nization of the Controller’s Department (CTL) of the Asian Development Bank (ADB) that will
minimize disruption of its operations. Actual data was taken from the department which are pre-
sented and analyzed in this paper. The teachings from Prof. Rene Aguila and the techniques
gathered from the “Introduction to Management Science” book by Bernard Taylor III greatly
helped the ADB MBA-Batch 10 students in appreciating the importance of Management Science
not only in business operations but also in an individual’s decision making.
II. Controller’s Department
A. Background
CTL is supporting ADB’s operations in: (i) preparing financial reports; (ii) processing and
overseeing administrative and capital expense payments; (iii) processing and overseeing
loan/technical assistance/grant disbursements; (iv) working with the Regional Departments
(RDs) and Resident Mission (RM) offices to ensure optimal fiduciary control over project funds;
and (v) maintaining loan accounting and servicing. As of 31 December 2010, CTL has 166 staff
composing of 21 international staff, 31 national staff and 114 administrative staff organized in
different units and sections.
In February 2011, CTL planned to realign its organizational structure based on functional
responsibilities to achieve and promote (i) greater efficiencies and effectiveness, (ii) more
efficient use of staff resources, (iii) greater outsourcing opportunities, and (iv) greater delegation
of authority to empower staff.
B. Impact of Reorganization and Realignment in CTL
CTL will now be divided into two divisions, Accounting Division (CTAC) and Loan
Administration Division (CTLA), and one unit, Institutional Services Unit (CTIS) from the original
two divisions. Staff reassignment to different divisions or unit will require manpower, logistics,
systems restructuring, turnover of documents, and the physical transfer of staff to their
designated areas. The anticipated activities for the reorganization are projected to take 41 days
to complete. However, it is hoped that CTL be able to complete the activities in less than a
month in order to minimize disruption of operations.
C. CPM Model – Single Time Estimate
To plan CTL’s reorganization activities and timing, the critical path method (CPM) was
applied. A single estimate for activity time, precedence relationships, and activity-on-node
(AON) are incorporated in this model. It is also important to determine the critical path or the
longest path throughout the network to find out the minimum time in which the network can be
completed. The QM application was used to determine the results.
CTL’s reorganization consists of the following activities and the coresponding
precedence activities:
No. Activities Normal Time (in day/s) Precedence
1 Inventory of CTL staff 1
2 Identification of staff new assignments 5 1
3 Notification of other departments on CTL’s
reorganization
1 2
4 Turn-over of files 18 2
5 Office lay-out planning 5 2
6 System access request of affected staff 3 2
7 Physical movement 2 4
8 System access of affected staff in place 14 6, 7
9 Transfer completed 1 7
On the above activities, CPM with single time estimate was applied resulting to:
No. Activities Activity Time (in day/s)
Early Start
Early Finish
Late Start
Late Finish
Slack
Project 411* Inventory of CTL staff 1 0 1 0 1 0
2* Identification of staff new assignments
5 1 6 1 6 0
3 Notification of other departments on CTL’s reorganization
1 6 7 40 41 34
4* Turn-over of files 18 6 24 6 24 05 Office lay-out planning 5 6 11 19 24 136 System access request of affected
staff3 6 9 38 41 32
7* Physical movement 2 24 26 24 26 08* System access of affected staff in
place14 26 40 26 40 0
9* Transfer completed 1 40 41 40 41 0
*Critical path activities
Based from the above data, a precedence chart is also created to clearly illustrate how
each activities are related to other activities.
From the table and chart of CPM with single time, it can be concluded that activities 3, 5,
and 6 can be delayed by 34, 13 and 32 days, respectively. The reorganization will still be
completed after 41 days. However, if activities 1, 2, 4, 7, 8 and 9 are delayed, the
reorganization completion date will be extended which can affect the operations of CTL and
other departments supported by CTL.
D. CPM Model - Crashing
However, CTL management would like to shorten the activities of the reorganization to
minimize disruptions as much as possible both internally and externally.
Looking at the planned activities in the previous table, there are activities that can be
shortened, especially activities that are in the critical path, but would generally entail costs.
Costs to be incurred are mainly overtime charges for staff and contractors rendering staff time
during weekends. The previous table included weekends that are not utilized as the projections
are based on working days.
One activity that can be shortened is the turning over of files (activity 4). It can be
shortened to 14 days from 18 days if about 100 staff will render overtime on a weekend (either
Saturday or Sunday). The average cost for this is Php2,000 per staff. IT works on system
access (activity 8) can also be shortened to 10 days from 14 days if 5 contractual staff will
render overtime for two weekend days at a cost of Php1,000 per day per staff.
Using the CPM model of crashing and the above additional data, the activities are again
inputted in the QM application.
No. Events Normal Time
(in day/s)
Crash time
(in day/s)
Crash Cost Precedence
1Inventory of CTL staff
1
2 Identification of staff new assignments
5 1
3 Notification of other departments on CTL’s reorganization
1 2
4Turn-over of files
18 14 200,000 2
5Office lay-out planning
5 2
6 System access request of affected staff
3 2
7Physical movement
2 4, 5
8 System access of affected staff in place
14 10 10,000 6, 7
9Transfer completed
1 7, 8
The following are the results with crash cost and the crash schedule:
Events Normal
Time (in
day/s)
Crash
time (in
day/s)
Crash
Cost
Crash Cost
Paid
Crash by Crashing
Cost
Project 41 24
1Inventory of CTL staff
1 1
2 Identification of staff new assignments
5 5
3 Notification of other departments on CTL’s reorganization
1 0
4Turn-over of files
18 14 200,000 50,000 4 200,000
5Office lay-out planning
5 0
6 System access request of affected staff
3 0
7Physical movement
2 2
8 System access of affected staff in place
14 10 10,000 2,500 4 10,000
9Transfer completed
1 1
Total210,000
Based on the above, the reorganization activities can be shortened substantially from 41
days to 24 days if staff and contractors are allowed to work on overtime during weekends.
However, a cost of Php210,000 will be incurred if staff overtime pushes through. Considering
the volume of daily operations and the importance of the supporting function of CTL to the
operations of ADB, it is recommended that staff be allowed to render overtime to complete the
reorganization significantly earlier than initially projected so that efficient and effective service
will be maintained and disruption to operations will be minimized.