CSSC.Nanjing Luzhou Machine Co., Ltd.maytau.ut.edu.vn/userfiles/files/STC2_STP_S1192... ·...

18
CSSC.Nanjing Luzhou Machine Co., Ltd. STC2 Marine Sewage Treatment Unit Contract: 2009/W3103-2210 Hulls: S1192 Approving Authority: Shanghai Shipyard Co.,Ltd. Date of delivery: 2012-11-27 FINAL DRAWINGS TEL: +86-025-84769603-8012 EMAIL: [email protected]

Transcript of CSSC.Nanjing Luzhou Machine Co., Ltd.maytau.ut.edu.vn/userfiles/files/STC2_STP_S1192... ·...

Page 1: CSSC.Nanjing Luzhou Machine Co., Ltd.maytau.ut.edu.vn/userfiles/files/STC2_STP_S1192... · CSSC.Nanjing Luzhou Machine Co., Ltd. STC2 Marine Sewage Treatment Unit Contract: 2009/W3103-2210

CSSC.Nanjing Luzhou Machine Co., Ltd.

STC2 Marine Sewage Treatment Unit

Contract: 2009/W3103-2210

Hulls: S1192

Approving Authority: Shanghai Shipyard Co.,Ltd.

Date of delivery: 2012-11-27

FINAL DRAWINGS

TEL: +86-025-84769603-8012

EMAIL: [email protected]

Page 2: CSSC.Nanjing Luzhou Machine Co., Ltd.maytau.ut.edu.vn/userfiles/files/STC2_STP_S1192... · CSSC.Nanjing Luzhou Machine Co., Ltd. STC2 Marine Sewage Treatment Unit Contract: 2009/W3103-2210

FINAL DRAWINGS Shanghai Shipyard Co., Ltd.

TITLE CONTENT PAGE 1/1 STC SEWAGE TREATMENT UNIT

Main Technical Data ………………………………………………………………1

Schematic Diagram …………………………………………………………….…2

System Installation ………………………………………………………………..3

Typical Installation and Description ……………………………………………..4

Main Dimension ……………………………………………………………………7

Membrane System&Outline Drawing of Membrane……………………………8

Outline Drawing of Discharge Pump………………………………..……………9

ELECTRICAL DRAWINGS

Electrical Drawing. Circuit(1)……………………………………………..….……10

Electrical Drawing. Circuit(2) ………………………………………….……….…11

Electrical Drawing. Circuit(3) ………………………………………….……….…12

Electrical Drawing. Circuit(4) ……………………………………………….….…13

Outline Drawing of El.Control Panel…………………………………….….……14

DELIVERY SCOPE AND SPARES LIST

Delivery Scope ………………………………………………………………….…15

Spares List ………………………………………………………………………....16

TYPE STC2 Marine Sewage Treatment Unit DATE

Page 3: CSSC.Nanjing Luzhou Machine Co., Ltd.maytau.ut.edu.vn/userfiles/files/STC2_STP_S1192... · CSSC.Nanjing Luzhou Machine Co., Ltd. STC2 Marine Sewage Treatment Unit Contract: 2009/W3103-2210

FINAL DRAWINGS Shanghai Shipyard Co., Ltd.

TITLE INDEX PAGE 1/16

Product: STC2 Marine Sewage Treatment Unit

Quantity: 1set / ship

MAIN TECHNICAL DATA

1 Type: STC2

2 Capacity: 2.1 m3/d

3 Effluent:

BOD5 ≤ 25 mg/l

SS ≤ 35 mg/l

Coliform ≤ 100 mpn/100ml

COD ≤125 mg/l

PH [6~8.5]

CL- ≤0.5mg/l

4 Power source: 440V 60HZ 3P

5 Control power: 220V 60HZ

6 Protection for motor: IP44

Insulation: F

7 Air compressor: DLT- 10 13m3/h 0.06mpa 0.44KW

8 Discharge pump: 50CPW-10-15,10m3/h,0.15Mpa,1.5Kw

9 Circulation Pump: CR32-2-2, 29m3/h, 0.29Mpa, 5.0kW

10 Protection for El-control panel: IP44 with Cable Glands

11 External painting color of the Plant and El-control Panel: Munsell 2.5 G 7/2

12 Power consumption: 5.9Kw

13 Main Dimension: 2460×1552×1600 mm(L×W×H)

14 Certification: EC + EC Type Approval Certificate

TYPE STC2 Marine Sewage Treatment Unit DATE

Page 4: CSSC.Nanjing Luzhou Machine Co., Ltd.maytau.ut.edu.vn/userfiles/files/STC2_STP_S1192... · CSSC.Nanjing Luzhou Machine Co., Ltd. STC2 Marine Sewage Treatment Unit Contract: 2009/W3103-2210
Page 5: CSSC.Nanjing Luzhou Machine Co., Ltd.maytau.ut.edu.vn/userfiles/files/STC2_STP_S1192... · CSSC.Nanjing Luzhou Machine Co., Ltd. STC2 Marine Sewage Treatment Unit Contract: 2009/W3103-2210
Page 6: CSSC.Nanjing Luzhou Machine Co., Ltd.maytau.ut.edu.vn/userfiles/files/STC2_STP_S1192... · CSSC.Nanjing Luzhou Machine Co., Ltd. STC2 Marine Sewage Treatment Unit Contract: 2009/W3103-2210

FINAL DRAWINGS Shanghai Shipyard Co., Ltd.

TITLE TYPICAL INSTALLATION AND DESCRIPTION PAGE 4/16

SOIL MAIN

These are for handling the waste from Water Closets, Urinals and all Hospital waste

water as required by health codes. Inputs from this source not exceed 70

liters/person/day. Overboard by-pass line must be fitted. A Luzhou Transfer Unit can

be fitted if the final soil pipe position is below the sewage treatment plant. Ensure

that peak pumping flows or periods don’t exceed the peak handling capability of the

Sewage Treatment Plant. On Gravity sewage collection system, a Macerator is

recommended with units sized above 150 crews and on passenger vessels and

ferries.

SOIL WATER GRAVITY PIPELINE FALLS

This should be a minimum of 10mm per 300mm run in the direction of flow, after

allowing for the worst trim conditions Non-Return Valves or Valves which could

cause a flow restriction should not be fitted.

AIR VENT

It is important that no liquid pockets can from to impede the free run of the gasses.

Luzhou can supply a centrifugal fan for difficult pipe arrangements. A flame trap is

not required.

TYPE STC2 Marine Sewage Treatment Unit DATE

Page 7: CSSC.Nanjing Luzhou Machine Co., Ltd.maytau.ut.edu.vn/userfiles/files/STC2_STP_S1192... · CSSC.Nanjing Luzhou Machine Co., Ltd. STC2 Marine Sewage Treatment Unit Contract: 2009/W3103-2210

FINAL DRAWINGS Shanghai Shipyard Co., Ltd.

TITLE TYPICAL INSTALLATION AND DESCRIPTION PAGE 5/16

EMERGENCY OVERFLOW FROM TREATMENT TANK

This can only be effective when the tank overflows. Connection must be 1.5m above

maximum sea water levels to ensure that the Non-Return Valves can be lifted and

flow take place. If the available is less than this a back-up will occur in the system

until the required head is available. If emergency overflow connection is below

maximum water level then connect to bilge including a ”U” trap of 200mm to prevent

venting into the compartment.

GALLEY WASTE

This should be treated comply with the IMO resolution; normally drain it overboard

directly via a 25mm screen. If it is intended to connect into soil inlet of the sewage

treatment plant, LUZHOU must be consulted, as size of plant will be affected and a

grease trap must be fitted.

NOTE: THE GREY WASTE PIPELINES SHOULD NOT CONNECT TO THE

TREATMENT PLANT.

SIPHON PREVENTION

If the top of the sewage treatment tank is above minimum sea water level, then the

pump discharge pipeline must be looped above the top of the tank and a connection

taken from the top of the loop to a point in the air vent line above the discharge head of

the pump.

TYPE STC2 Marine Sewage Treatment Unit DATE

Page 8: CSSC.Nanjing Luzhou Machine Co., Ltd.maytau.ut.edu.vn/userfiles/files/STC2_STP_S1192... · CSSC.Nanjing Luzhou Machine Co., Ltd. STC2 Marine Sewage Treatment Unit Contract: 2009/W3103-2210

FINAL DRAWINGS Shanghai Shipyard Co., Ltd.

TITLE TYPICAL INSTALLATION AND DESCRIPTION PAGE 6/16

MEMBRANE SYSTEM

Pretreatment water (in primary treatment tank) is circulated under the function of

MEMBRANE SYSTEM, and the concentrated water will return to the bioreactor but

the filtrate, accordance with the IMO 159(55) latest regulations, will be collected into

the treatment tank and pumped overboard automatically. The function, BACKWASH

is provided to clean the system with the compress air, 0.4Mpa under the controlling

of El.Control Panel.

DUAL PUMP SET

This can be supplied to give a standby pump ready piped in.

AIR COMPRESSOR

When the sewage plant is offered, the dual air compressors have been installed.

PAINTING SCHEME

Inside Outside Item Name of

component Sandblasting Painting Sandblasting Painting

1 Treatment Tank

Sa2.5 846 Epoxy tar

paint

Sa2.5 Munsell 2.5 G 7/2

2 Aeration Tank

Sa2.5 846 Epoxy tar

paint

Sa2.5 Munsell 2.5 G 7/2

3 Clarifier Tank

Sa2.5 846 Epoxy tar

paint

Sa2.5 846 Epoxy tar

paint

TYPE STC2 Marine Sewage Treatment Unit DATE

Page 9: CSSC.Nanjing Luzhou Machine Co., Ltd.maytau.ut.edu.vn/userfiles/files/STC2_STP_S1192... · CSSC.Nanjing Luzhou Machine Co., Ltd. STC2 Marine Sewage Treatment Unit Contract: 2009/W3103-2210
Page 10: CSSC.Nanjing Luzhou Machine Co., Ltd.maytau.ut.edu.vn/userfiles/files/STC2_STP_S1192... · CSSC.Nanjing Luzhou Machine Co., Ltd. STC2 Marine Sewage Treatment Unit Contract: 2009/W3103-2210
Page 11: CSSC.Nanjing Luzhou Machine Co., Ltd.maytau.ut.edu.vn/userfiles/files/STC2_STP_S1192... · CSSC.Nanjing Luzhou Machine Co., Ltd. STC2 Marine Sewage Treatment Unit Contract: 2009/W3103-2210
Page 12: CSSC.Nanjing Luzhou Machine Co., Ltd.maytau.ut.edu.vn/userfiles/files/STC2_STP_S1192... · CSSC.Nanjing Luzhou Machine Co., Ltd. STC2 Marine Sewage Treatment Unit Contract: 2009/W3103-2210
Page 13: CSSC.Nanjing Luzhou Machine Co., Ltd.maytau.ut.edu.vn/userfiles/files/STC2_STP_S1192... · CSSC.Nanjing Luzhou Machine Co., Ltd. STC2 Marine Sewage Treatment Unit Contract: 2009/W3103-2210
Page 14: CSSC.Nanjing Luzhou Machine Co., Ltd.maytau.ut.edu.vn/userfiles/files/STC2_STP_S1192... · CSSC.Nanjing Luzhou Machine Co., Ltd. STC2 Marine Sewage Treatment Unit Contract: 2009/W3103-2210
Page 15: CSSC.Nanjing Luzhou Machine Co., Ltd.maytau.ut.edu.vn/userfiles/files/STC2_STP_S1192... · CSSC.Nanjing Luzhou Machine Co., Ltd. STC2 Marine Sewage Treatment Unit Contract: 2009/W3103-2210
Page 16: CSSC.Nanjing Luzhou Machine Co., Ltd.maytau.ut.edu.vn/userfiles/files/STC2_STP_S1192... · CSSC.Nanjing Luzhou Machine Co., Ltd. STC2 Marine Sewage Treatment Unit Contract: 2009/W3103-2210
Page 17: CSSC.Nanjing Luzhou Machine Co., Ltd.maytau.ut.edu.vn/userfiles/files/STC2_STP_S1192... · CSSC.Nanjing Luzhou Machine Co., Ltd. STC2 Marine Sewage Treatment Unit Contract: 2009/W3103-2210

FINAL DRAWINGS Shanghai Shipyard Co., Ltd.

TITLE DELIVERY SCOPE AND SPARES LIST PAGE 15/16

DELIVERY SCOPE

One set of STC2 Sewage Treatment Unit including:

Compressors (DLT-10) 2sets

Discharging pump (50CPW-10-15) 1sets

Circulation pump (CR32-2-2) 1set

Membrane module (CL-7M-19K) 1set

Control box 1set

Floating Switches 2set

Valves, fittings and so on.

User requirements

TYPE STC2 Marine Sewage Treatment Unit DATE

Page 18: CSSC.Nanjing Luzhou Machine Co., Ltd.maytau.ut.edu.vn/userfiles/files/STC2_STP_S1192... · CSSC.Nanjing Luzhou Machine Co., Ltd. STC2 Marine Sewage Treatment Unit Contract: 2009/W3103-2210

FINAL DRAWINGS Shanghai Shipyard Co., Ltd.

TITLE DELIVERY SCOPE AND SPARES LIST PAGE 16/16

SPARES LIST

1. Spares for compressors

(1)Vane 1set

2. Spares for discharging pump 1set

(1)"O" Seal (20×2.6GB1235-76) 1pc

(2)"O" Seal (130×3.1GB1235-76) 1pc

(3) Mechanical seal(MN108-40 GB6556-86) 1pc

(4)Bearing(Type:6205) 1pc

3. Spares for control box 1set

(1) AC Contactor LC1-D09M7C 1pc

(2) Mid-Relay CAD-32M7C 1pc

4 *Non-return Valve H11T-16 DN25 1pc

5 *Solenoid Valve DN25 ZS-25B 1pc

6. Measuring glass of 100ml 1pc

7. Acid and alkali resistant gloves 2pairs

NOTE: ‘*’ Means that it should be installed by shipyard.

TYPE STC2 Marine Sewage Treatment Unit DATE