CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

62
CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan

Transcript of CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Page 1: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

CSIS 3600 Systems Analysis and Design

Information Systems Projects/Project Plan

Page 2: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

What is Project Management Project management is the process of planning

and controlling the development of a system within a specified timeframe at a minimum cost with the right functionality (Dennis, Wixom and Tegarden, 2002).

Project Management can be seen as a job responsibility or it can be a job in and of itself.

A Project Manager is not just a senior analyst who happens to be in charge. A project manager must apply a set of skills different from those applied by the analyst.

Page 3: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Roles of the Project Manager Scoping the project:

Project managers estimate resource requirements and formulate plans to deliver the target system.

Planning Tasks and Staffing the Project Team Once the project has begun, the project

manager becomes a supervisor. As a supervisor, the project manager directs the team's activities and evaluates progress.

Page 4: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Roles of the Project Manager continued Organizing and Scheduling the Project

Effort The project manager is responsible for

securing resources so they are available when needed.

Directing and Controlling the Project One of the most difficult and important

functions of the project manager is controlling the project. Few projects come off without problems or delays.

Page 5: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Project Management Process Initiating the Project Planning the Project Executing the Project Closing down the Project

Page 6: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

3 Steps of Project Management

Create the work plan Staff the project Control and direct the project

Page 7: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Pitfalls of Project Management

To be successful in project management, you should be aware of some of the common pitfalls that can lead to project failure: Taking shortcuts through or around the system methodology because:

Project gets behind schedule and team wants to catch up

Project is over budget and team wants to make up costs

Team members are not trained or made fully aware of the task requirements so simply miss or skip them

Page 8: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Pitfalls continued: Poor Expectations Management that results in:

Scope Creep - unexpected growth of user expectations and business requirements

Feature Creep - uncontrolled addition of technical features

Poor People Management that results in: Mythical man-month - assigning more people to the

project. There is not a linear relationship between number of people assigned to a project and time to completion.

No one in charge and no one sure of the progress of the project

Page 9: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Did you notice that many of the causes of failed projects are related?

Scope creep causes project to get behind which causes shortcuts to be taken which causes more people to be assigned to the project which causes feature creep which causes project to be way over budget and way behind schedule which causes shortcuts to be taken . . .

Page 10: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Managing Expectations

The Greatest Trait for Success is the ability to Manage Expectations

The best way to manage expectations is to Scope the Project. If you cannot scope project expectations and constraints, you cannot manage expectations. If you cannot manage expectations, your chances for success are greatly reduced.

Page 11: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Managing Expectations continued The three most important items of project

scope include: Identifying a project champion and executive

sponsor Articulation of the statement of the problem or

opportunity including project goals Identification of project constraints

Failure to achieve consensus on these dooms a project before it even starts (Whitten & Bentley, 1999)

Page 12: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Expectations Management Matrix An expectations matrix is a rule-

driven tool for assessing the dynamics of changing project parameters.

The parameters include: cost, schedule, scope and quality.

Page 13: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Expectations Management Matrix continued

Rules:You must record three X.sNo row may contain more than one X.

No column may contain more than one X.

Priorities/ Measures of Success

Max or Min

Constrain

Accept

Cost

Schedule

Scope and/or Quality

Page 14: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

EMM Example

Priorities/ Measures of Success

Max or Min

Constrain

Accept

Cost Estimated at $20 Billion

X

Schedule – Deadline December 31, 1969

X

Scope and/or Quality1. Land man on moon2. Get him back safely

X

Priority One was the ScopePriority Two was deadline (USSR was ahead in the space race)Priority Three was cost – Cost control is a priority but we may to ‘accept’ cost overruns to achieve the scope by the required deadline.

Project – Land Man on the Moon before End of Decade and before USSR

Page 15: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Why EMM During the course of an average systems

development project, priorities are not stable. Various factors such as the economy,

government, politics, etc. may change During systems analysis, unanticipated business

problems are identified or requirements modified The EMM helps to deal with expectations

management. Simple tool – but sometimes simple tools

are most effective

Page 16: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Having a Plan Success is not pre-destined A good project starts with a good plan The plan is based on the manager's

understanding of the requirements of the target system at that point in its development.

Project planning is challenging - many project plans call for unreasonably precise estimates of costs and time before a project even begins. This, and poor estimation techniques, can lead to missed deadlines and cost overruns.

Page 17: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Techniques for Developing Project Plans

Page 18: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Identification of Tasks A good place to start the development of a

plan is the SDLC and the organization’s Systems Development Methodology 

All tasks required to complete the project must be identified and then planned: How much time will be required? How many people will be needed? How much will the task cost? What tasks will be completed before other

tasks are started? Can some of the tasks overlap?

Page 19: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Statement of Work Work Breakdown Structure is a

hierarchical decomposition of the project into phases, activities and tasks. Summary Tasks – Related work units

combined together Primitive Tasks – Most basic unit of work

that will not be broken down any further Milestones – Events that signify major

accomplishments

Page 20: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Work Breakdown Structure in Outline Format

Phase (1)Activity (1.1)

Task (1.1.1)Step of the task (1.1.1.1)Step of the task (1.1.1.2)

Task (1.1.2)Step (1.1.2.1)…..

Task (1.1.3) …..Activity (1.2)…..

Phase (2)

Page 21: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Work Breakdown Structure as a Decomposition Diagram

W ork B reakd ow n S tru c tu re

S tep 1 .1 .1 .1 S tep 1 .1 .1 .2

Task 1 .1 .1

S tep 1 .1 .2 .1

Task 1 .1 .2

A c tivity 1 .1

S tep 1 .2 .1 .1

Task 1 .2 .1

S tep 1 .2 .1 .2

Task 1 .2 .2

A c tivity 1 .2Typ e t it le h e re

P h ase 1

S tep 2 .1 .1 .1

Task 2 .1 .1

A c tivity 2 .1

S tep 2 .2 .1 .1 S tep 2 .2 .1 .2

Task 2 .2 .1

A c tivity 2 .2

P h ase 2

Page 22: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Time Estimation Forward Scheduling – Establishing a

project start date and then scheduling forward from that date. Most common for IS projects.

Reverse Scheduling – Establishing a project deadline and then scheduling backwards from that date. Used when a deadline is mandatory.

Page 23: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Estimating Time Estimate system size Estimate effort required Estimate schedule time required

Page 24: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Estimating Size Lines of Code Function Points

Inputs Outputs Queries Files Program interfaces

Page 25: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Estimating Effort Function of production rates – how

much work can be done Several models have evolved from

the research – most well known is the Boehm COCOMO model

Basic formula: Effort (in person months) – 1.4 *

thousands lines of code

Page 26: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Estimate Schedule Time Historical data can be used as a

basis Sample estimation equation:

Schedule time = 3.0 * person months1/3

Page 27: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Task – Time:Expected Duration

Calculated for each primitive task There is no foolproof technique for

estimating work duration.

Page 28: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Expected Duration continued

Suggested estimation technique:1. Estimate minimum amount of time to perform the

task or the Optimistic Time (OT)2. Estimate the maximum amount of time to perform the

task of the Pessimistic Time (PT) 3. Estimate the Realistic Time or Calculate the most

likely time (MLT) as an average of the OT and PT. 4. Use weight factors (based on experience) for possible

interruptions or delays to project the resulting Expected Duration (ED)

ED = [OT + (x * MLT) + PT]/ yCommon x factor = 4Common y factor = 6

Page 29: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Examples Optimistic Time = 7 hours Pessimistic Time = 19 hours Most Likely Time = avg(OT and PT)

(7 + 19)/2 = 13 hours Expected Duration:

ED = [OT + (x * MLT) + PT]/ y [7 + (4*13) + 19]/6 = 8.67

Page 30: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

2 Primary Factors of Software Estimation SLOC (Lines of Code)

Function Points Based on the amount of functionality Advantage is more information

available early in project life cycle

Page 31: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

SLOC Determination

Difficult due to conceptual differences

Goal is to measure the amount of intellectual work needed

Page 32: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

User Function Types

External Input (Inputs) Count each unique user data or user

control input type that (i) enters the external boundary of the software system being measured and (ii) adds or changes data in a logical internal file.

External Output (Outputs) Count each unique user data or control

output type that leaves the external boundary of the software system.

Page 33: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Function Points Continued Internal Logical File (Files)

Count each major logical group of user data or control information as a logical internal file type.

External Interface Files (Interfaces) Files passed or shared between software

systems should be counted as external interface file types

External Inquiry (Queries) Count each unique input-output combination,

where an input causes and generates an immediate output, as an external inquiry type.

Page 34: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

What is COCOMO

COCOMO II is a model that allows one to estimate the cost, effort, and schedule when planning a new software development activity

The COCOMO II capability for estimation of Application Generator, System Integration, or Infrastructure development

Original COCOMO was developed by Dr. Barry Boehm in 1981

Reference: http://sunset.usc.edu/research/COCOMOII/

Page 35: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

COCOMO II Measures

In COCOMO II effort is expressed as Person Months (PM). amount of time one person spends working

on the software development project for one month (exclusive of holidays and vacations but accounts for weekends)

Person months is different from the time it will take the project to complete; this is called the development schedule.

For example, a project may be estimated to require 50 PM of effort but have a schedule of11 months.

Page 36: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

COCOMO II

Supports either SLOCOr

Function Points (Note this is true for download and

commercial versions, the Web version supports SLOC.)

Page 37: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Attributes Mode of the project:

Organic (project is from a familiar, stable, and fairly unrestrained environment)

Semidetached (project is not Organic or Embedded)

Embedded (project environment is unfamiliar, tightly constrained, and unforgiving)

Page 38: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Scale Drivers in COCOMO II

The selection of scale drivers is based on the rationale that they are a significant source of exponential variation on a project’s effort or productivity variation

Each scale driver has a range of rating levels, from Very Low to Extra High.

Page 40: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Cost Drivers

Capture characteristics that affect the effort to complete the project

ETSU program lists all options as cost drivers

Page 42: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Platform Attributes

Execution Time Constraint Main Storage Constraint Platform Volatility

Page 43: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Personnel Attributes

Analyst Capability Programmer Capability Personnel Continuity Applications Experience Platform Experience Language and Toolset

Experience

Page 44: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Project Attributes

Use of Software Tools Multisite Development Required Development

Schedule

Page 45: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Try It

Visit http://sunset.usc.edu/research/COCOMOII/

Go about ¾ of the way down and you can try it out via the Web

COSMOS – Function Point and COCOMO http://www-cs.etsu.edu/cosmos/ Use this for homework 1 question 4

Page 46: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Other Sources

Listing of Cost Estimation Software http://www.dacs.dtic.mil/

databases/url/key.hts?keycode=4:152&islowerlevel=1

Page 47: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Controlling and Directing the Project Refine estimates Match need to resources and

monitor that it happens Manage scope Manage risk Maintain quality

Page 48: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Quality Assurance A development process, methodology, and even a well-defined plan, do not ensure quality. Quality must be managed. Quality begins with establishing standards. Some internal standards in systems development include:

Standards for project deliverables such as reports and documentation

Modeling techniques Naming standards for models, objects, programs, databases, etc. Quality check-points and sign-offs at various stages of the project Technology standards such as approved graphical user interface

components and placement Testing procedures and tolerances Acceptance criteria for implementation

Page 49: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Project Tracking Tools Gantt Charts Pert Charts Understand the critical path and

slack

Page 50: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Critical Path and Slack Resource

Critical Path is a sequence of dependent project tasks that result in shortest time to project completion. It contains no slack time. Any activity delayed will cause delay in project completion.

Activities not on the critical path contain slack time. Slack time available for any task is equal to the difference between the earliest and latest completion times. Tasks with slack time can get behind schedule by an

amount less than the available slack time without having an impact on the project’s final completion date.

Page 51: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Critical Path and Slack Resource continued Understanding critical path and slack

resources are indispensable. Emphasis can be placed on the critical path, and if necessary, resources temporarily diverted from tasks with slack time to more critical ones.

Page 52: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Gantt Chart A simple horizontal bar chart that

depicts project tasks against a calendar. Bars represent detailed tasks. The length of the bar represents

duration of the task. The bar is positioned according to its

planned start and end dates.

Page 53: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Figure 3-10a -A Gantt Chart

Page 54: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Activity Progress Representation on Gantt Chart

Page 55: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Sequence of Activities Predecessor is a task that must be completed

before the start of the task in question Constraints include dependence or a task that

is dependent on the start of another task (as opposed to its completion). Other constraints might include specific date for task initialization (programmer start date, etc.)

Based on predecessors and constraints, determine activities/tasks and identify all required preceding activities. Activities may have 0, 1, or more preceding activities.

Page 56: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Project Evaluation and Review Technique (PERT) Chart PERT charts represent another view of a project

schedule that emphasizes intertask

relationships.

Page 57: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Annotated PERT Chart Rectangle contains: Task Name Task ID and Estimated

Duration Start and End dates Red indicates task is on critical

path

Page 58: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Annotated PERT Chart continued

Page 59: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

PERT including Time Completion Estimates

Note that when Te = Tl, slack time is 0. Tasks with 0 slack time are on the critical path.

Page 60: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Gantt vs PERT PERT and Gantt charting are frequently

presented as mutually exclusive tools. However, they can be used in a complementary manner.

PERT is recommended for larger projects with high intertask dependency. Gantt is recommended for simpler projects.

Gantt charts seem to be preferred in IS projects.

Most project management tools now incorporate critical path analysis.

Page 61: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Sample Base line Project Plans

Links to sample project plans are found under Lecture Notes.

Page 62: CSIS 3600 Systems Analysis and Design Information Systems Projects/Project Plan.

Quote of the WeekTop 10 Signs of IS Project Failure:

10. All software purchased is Version 1.0.9. All hardware purchased come from a discount company called Kludges

"R" Us. 8. Project manager is spotted reading PCs for Dummies 7. Application developers think Java OLE is something to be ordered at a

coffee shop. 6. Network administrators question the usefulness of an ATM system that

doesn't accept bankcards. 5. Hardware technicians try to use RAID to cure software bugs. 4. Size of database balloons reaches IWSTBTB (It Wasn't Supposed To Be

That Big) proportions. 3. Consultants revamp system architecture, which had been totally

revamped only a month ago by a different group of consultants. 2. After system is finally deployed, end users mistake their computer

mouses for foot pedals. 1. CIO is seen faxing resume.

(as published by Cahners Publishing Company, a division of Reed Elsevier Business Information, Inc.)