CSC 395 –Software Engineering
Lecture 33:
Planning & Estimation -or-
How Much for the Program using Windows
![Page 2: CSC 395 – Software Engineering Lecture 33: Planning & Estimation -or- How Much for the Program using Windows.](https://reader035.fdocuments.in/reader035/viewer/2022062421/56649d5f5503460f94a3fe68/html5/thumbnails/2.jpg)
Estimating Duration & Cost
Accurate estimations crucial Companies need to make $$$ Customers want reasonable & reliable prices
Estimates depends on many, many variables Many are unpredictable (e.g., human factors) Programmers quit or “get hit by bus” Get freak Oct. snow storm that shuts down city Programmer pairs differ in effectiveness &
productivity (up to 28x) General models impossible to create
![Page 3: CSC 395 – Software Engineering Lecture 33: Planning & Estimation -or- How Much for the Program using Windows.](https://reader035.fdocuments.in/reader035/viewer/2022062421/56649d5f5503460f94a3fe68/html5/thumbnails/3.jpg)
Planning and Process
Estimates improve as more details known Anyone confused by this point, give up
![Page 4: CSC 395 – Software Engineering Lecture 33: Planning & Estimation -or- How Much for the Program using Windows.](https://reader035.fdocuments.in/reader035/viewer/2022062421/56649d5f5503460f94a3fe68/html5/thumbnails/4.jpg)
Planning and Process
Properly engineered, estimate stays static as range shrinks
Start of requirements, estimate is $1 million Likely actual cost is in $0.25M - $4M range
After requirements, estimate stays $1 million Actual cost range shrunk to $0.5M - $2M
After analysis, estimate still $1 million But cost range reduced to $0.67M - $1.5M This is also when contract is finalized!
![Page 5: CSC 395 – Software Engineering Lecture 33: Planning & Estimation -or- How Much for the Program using Windows.](https://reader035.fdocuments.in/reader035/viewer/2022062421/56649d5f5503460f94a3fe68/html5/thumbnails/5.jpg)
Estimating Product’s End Size
Several metrics commonly relied upon Use measurable quantities for simple calculations Computed early in life cycle for use writing contracts
Includes “fudge factors” that can be tweaked Factor unique to each group and situation Tracking allows more precise estimates over time
FFP for medium-sized data processing projects Function points used in many places
![Page 6: CSC 395 – Software Engineering Lecture 33: Planning & Estimation -or- How Much for the Program using Windows.](https://reader035.fdocuments.in/reader035/viewer/2022062421/56649d5f5503460f94a3fe68/html5/thumbnails/6.jpg)
FFP Calculation
Counts files (Fi), flows (Fl), & processes (Pr) Size (S) estimated as
S = Fi + Fl + Pr Cost (C) estimated with S & efficiency factor b
C = b S
![Page 7: CSC 395 – Software Engineering Lecture 33: Planning & Estimation -or- How Much for the Program using Windows.](https://reader035.fdocuments.in/reader035/viewer/2022062421/56649d5f5503460f94a3fe68/html5/thumbnails/7.jpg)
Function Points Metric
Expressed in units of “function points” Calculated using several inputs:
Number of inputs (Inp) Number of outputs (Out) Number of Inquiries (Inq) Count of master files (Maf) Interfaces in system (Inf)
FP = 4 • Inp + 5 • Out + 4 • Inq + 10 • Maf + 7 • Inf
![Page 8: CSC 395 – Software Engineering Lecture 33: Planning & Estimation -or- How Much for the Program using Windows.](https://reader035.fdocuments.in/reader035/viewer/2022062421/56649d5f5503460f94a3fe68/html5/thumbnails/8.jpg)
Complex FP Calculation
1. Classify each of the individual components (e.g., each Inp, Out, Inq, Maf, Inf) Assign appropriate number of function points Sum is UFP (unadjusted function points)
![Page 9: CSC 395 – Software Engineering Lecture 33: Planning & Estimation -or- How Much for the Program using Windows.](https://reader035.fdocuments.in/reader035/viewer/2022062421/56649d5f5503460f94a3fe68/html5/thumbnails/9.jpg)
Complex FP Calculation
2. Compute DI (degree of influence) Sum of 14 factors ratings Each rating will be integer between
0 (“not present”) & 5 (“strong influence throughout”)
![Page 10: CSC 395 – Software Engineering Lecture 33: Planning & Estimation -or- How Much for the Program using Windows.](https://reader035.fdocuments.in/reader035/viewer/2022062421/56649d5f5503460f94a3fe68/html5/thumbnails/10.jpg)
Complex FP Calculation
3. Compute TCF (total complexity factor)
TCF = 0.65 + 0.01 DI
4. FP (number of function points) is:
FP = UFP TCF
![Page 11: CSC 395 – Software Engineering Lecture 33: Planning & Estimation -or- How Much for the Program using Windows.](https://reader035.fdocuments.in/reader035/viewer/2022062421/56649d5f5503460f94a3fe68/html5/thumbnails/11.jpg)
Analysis of Metrics
Amazingly, FP often calculated correctly Moreover, cost-per function point meaningful!
Maintenance can cause inaccuracies Major changes possible without changing Fi, Fl,
Pr, Inp, Out, Inq, Maf, Inf
![Page 12: CSC 395 – Software Engineering Lecture 33: Planning & Estimation -or- How Much for the Program using Windows.](https://reader035.fdocuments.in/reader035/viewer/2022062421/56649d5f5503460f94a3fe68/html5/thumbnails/12.jpg)
Cost Estimation Techniques
Expert judgment by analogy Compare target product to completed products Provides a WASG (wild *** scientific guess) Studies show large groups eerily accurate
Bottom-up approach Split into smaller components (e.g., classes) Estimate costs for each component
Algorithmic cost estimation models Most commonly used approach
![Page 13: CSC 395 – Software Engineering Lecture 33: Planning & Estimation -or- How Much for the Program using Windows.](https://reader035.fdocuments.in/reader035/viewer/2022062421/56649d5f5503460f94a3fe68/html5/thumbnails/13.jpg)
COCOMO
Set of estimation models developed in 1981 Updated in 1995 for modern development tools Both contain 3 models differing in complexity
Original design consists of three models: Macro-estimation model for whole product Intermediate COCOMO Micro-estimation model examining product details
![Page 14: CSC 395 – Software Engineering Lecture 33: Planning & Estimation -or- How Much for the Program using Windows.](https://reader035.fdocuments.in/reader035/viewer/2022062421/56649d5f5503460f94a3fe68/html5/thumbnails/14.jpg)
Intermediate COCOMO
Estimate product length in KDSI Estimate of 1000s of source instructions
Select development mode
Development mode determines coefficients used
Size Innovation Deadline Environment
Organic Small Little Not tight Stable
Semi-detached
Medium Medium Medium Medium
Embedded Large Greater Tight Complex interfaces
a b
Organic 3.2 1.05
Semi-detached 3.0 1.12
Embedded 2.8 1.20
![Page 15: CSC 395 – Software Engineering Lecture 33: Planning & Estimation -or- How Much for the Program using Windows.](https://reader035.fdocuments.in/reader035/viewer/2022062421/56649d5f5503460f94a3fe68/html5/thumbnails/15.jpg)
Intermediate COCOMO
Compute development (nominal) effort Effort computed as person-months
Effort = a (KDSI)b
Compute C (effort adjustment factor) Equals the product of up to 15 cost-drivers
Development time (in person-months) is:
Effort C
![Page 16: CSC 395 – Software Engineering Lecture 33: Planning & Estimation -or- How Much for the Program using Windows.](https://reader035.fdocuments.in/reader035/viewer/2022062421/56649d5f5503460f94a3fe68/html5/thumbnails/16.jpg)
COCOMO Cost Drivers
![Page 17: CSC 395 – Software Engineering Lecture 33: Planning & Estimation -or- How Much for the Program using Windows.](https://reader035.fdocuments.in/reader035/viewer/2022062421/56649d5f5503460f94a3fe68/html5/thumbnails/17.jpg)
Using COCOMO
Revision (COCOMO II) calculated similarly But much, much more complex
Estimated time then used to compute: Development costs & schedules Phase and activity distributions Maintenance costs after delivery
Ultimately based upon initial size estimate End result only as good as initial estimate
![Page 18: CSC 395 – Software Engineering Lecture 33: Planning & Estimation -or- How Much for the Program using Windows.](https://reader035.fdocuments.in/reader035/viewer/2022062421/56649d5f5503460f94a3fe68/html5/thumbnails/18.jpg)
For Next Lecture
Consider maintenance of code Ultimately where the real money is made or lost Where majority of time in project is spent But least interesting for software engineering Much determined by decisions in development