CS_10_2

download CS_10_2

of 2

Transcript of CS_10_2

  • 7/28/2019 CS_10_2

    1/2

    Introduction

    GO Transit, the Greater Toronto

    Areas commuter rail/bus system is

    currently undergoing a dramatic

    expansion in service. A part of this

    expansion is an improvement in rail

    service between Hamilton, Ontario

    and Toronto in the east. In some cases,

    in order to meet the increased trafficdemands, it is necessary to add addi-

    tional tracks to accommodate the

    existing and future rail traffic. This is

    certainly the case in the area of West

    Burlington where a third track was

    deemed necessary.

    Problem

    Near the intersection of Highway 403 and Highway 6, the existing twin tracks abut Sunfis

    Pond. Sunfish Pond is an environmentally sensitive pond managed by and forming a part oBurlingtons Royal Botanical Gardens. Sunfish pond is the home to many rare aquatic specie

    A problem with the new construction was that the existing geometry of the present rail line

    did not provide adequate room for the 15m (50 ft) high embankment to be widened to accom

    modate a third track. The main concern was stabilizing the embankment as the right of wa

    was widened to protect the slope and prevent sediment migration and accumulation in Sunfis

    Pond, which in turn could disturb the natural habitat and aquatic wildlife.

    Solution

    The solution was a combination of geosynthetic and non-geosynthetic solutions to perm

    widening of the rail right of way. The non-geosynthetic solution consisted of a sheet pilretaining wall, tied back with a combination of earth anchors and a network of battered pile

    The height of this wall was approximately 5 m (16.4 ft) by 180 m (590 ft) long.

    Constructed above the sheet piled wall was a geosynthetic-reinforced slope with a vegetate

    faade. In order to construct this slope it was necessary to cut into the existing slope. The pr

    mary reinforcement specification called for Uniaxial (UX) geogrid which was installed in ho

    izontal layers running from the slope face into the embankment. The vertical spacing of th

    primary reinforcement layers was 1000 mm (3 ft) center to center. The secondary reinforce

    ment consisted of a lighter weight geogrid. This also was installed at 1000mm (3 ft) vertica

    CASE

    STUDY

    Volume 10

    Number 2

    April 2007

    14649 Highway 41 NorthEvansville, Indiana 47725

    812-867-66321-800-772-2040FAX 812-867-0247www.nagreen.com

    Rail Transit Line Expansion withSC250 Protects Environmentally

    Sensitive PondOntario GO Transit works with Burlingtons Royal Botanical Garden in Rail Line Expansion

    FAC

    TS

    The steep railway embankment needed to be stabilized during con-

    struction of a third track. Sunfish Pond (foreground) also

    required protection from sediment runoff.

  • 7/28/2019 CS_10_2

    2/2

    spacing and was vertically offset from the primary grid by

    500mm (1.5 ft).

    Upon completion of the 10m (32 ft) high granular embank-

    ment, the 1:1 slope was covered with 150mm (6 inches) of

    topsoil, and hydroseeded with a mix of grasses.

    In order to protect the vegetation and topsoil from short-termerosion and also provide long-term reinforcement for the

    vegetation root matrix, the decision was made to cover the

    entire slope with a turf reinforcement mat (TRM). The pro-

    ject engineers with the help of Armtecs Erosion Solutions

    Specialists chose North American Greens SC250 because of

    its proven performance. The SC250 is a composite turf reinforcement mat comprised of two heavy-duty UV sta-

    bilized outer nets, a corrugated center netting incorporated with organic straw/coconut fiber mechanically bond-

    ed together. This TRM provides immediate erosion control via the natural (70% straw/30% coconut) matrix,

    while the three dimensional netting structure provides permanent reinforcement to the root and stems of the veg-

    etation.

    To ensure proper installation of the SC250, the installers followed North American Greens DOT System, a

    spray-on color-coded dot pattern which indicated exact placement of fasteners. In addition, proper overlapping

    of adjacent SC250 panels and trenching the material in at the top of the slope offered optimum erosion control

    performance. With the use of North American Greens Erosion Control Materials Design Software (ECMDS )

    the project engineers were able to select the proper TRM and offer Go Transit and the Royal Botanical Gardens

    a stable, cost effective design.

    Results

    The selection and installation of the proper products cou-pled with good growing conditions allowed for rapid ger-

    mination of the seed mix through the SC250 C-TRM, and

    a great start to a fully vegetated slope. Along with provid-

    ing GO Transit the means to expand the railway system

    and bring more rail traffic into Ontarios Lakeshore west

    corridor, the project had additional benefits for

    Burlingtons Royal Botanical Gardens. While the removal

    of vegetation during construction was unsightly for visi-

    tors and had the potential to harm Sunfish Pond, ultimate-

    ly the Gardens was pleased to have the opportunity toremove non-native plantings that had established on the

    embankment and replace them with native species that

    historically would have existed in the area. By re-estab-

    lishing native plantings near Sunfish Pond, the Royal

    Botanical Gardens was able to improve the natural habitat

    surrounding the area. While the rail expansion project at Sunfish Pond was only a small part of the larger billion

    dollar railway expansion project funded by the Canadian Government and Ontarios Go Transit, it offered an

    example of how green engineering practices could produce a successful result for all parties involved including

    Mother Nature.

    North American Green SC250 C-TRM was installed as a surface

    stabilizer aimed at preventing surface erosion and promoting the

    reestablishment of vegetation.

    After only a few months, theSC250 reinforced railway

    embankment was completely

    revegetated, and Sunfish Pond

    was well protected from the

    potential of slope erosion and

    sediment runoff.