CS_10_2
-
Upload
ruben-cahuana -
Category
Documents
-
view
217 -
download
0
Transcript of CS_10_2
-
7/28/2019 CS_10_2
1/2
Introduction
GO Transit, the Greater Toronto
Areas commuter rail/bus system is
currently undergoing a dramatic
expansion in service. A part of this
expansion is an improvement in rail
service between Hamilton, Ontario
and Toronto in the east. In some cases,
in order to meet the increased trafficdemands, it is necessary to add addi-
tional tracks to accommodate the
existing and future rail traffic. This is
certainly the case in the area of West
Burlington where a third track was
deemed necessary.
Problem
Near the intersection of Highway 403 and Highway 6, the existing twin tracks abut Sunfis
Pond. Sunfish Pond is an environmentally sensitive pond managed by and forming a part oBurlingtons Royal Botanical Gardens. Sunfish pond is the home to many rare aquatic specie
A problem with the new construction was that the existing geometry of the present rail line
did not provide adequate room for the 15m (50 ft) high embankment to be widened to accom
modate a third track. The main concern was stabilizing the embankment as the right of wa
was widened to protect the slope and prevent sediment migration and accumulation in Sunfis
Pond, which in turn could disturb the natural habitat and aquatic wildlife.
Solution
The solution was a combination of geosynthetic and non-geosynthetic solutions to perm
widening of the rail right of way. The non-geosynthetic solution consisted of a sheet pilretaining wall, tied back with a combination of earth anchors and a network of battered pile
The height of this wall was approximately 5 m (16.4 ft) by 180 m (590 ft) long.
Constructed above the sheet piled wall was a geosynthetic-reinforced slope with a vegetate
faade. In order to construct this slope it was necessary to cut into the existing slope. The pr
mary reinforcement specification called for Uniaxial (UX) geogrid which was installed in ho
izontal layers running from the slope face into the embankment. The vertical spacing of th
primary reinforcement layers was 1000 mm (3 ft) center to center. The secondary reinforce
ment consisted of a lighter weight geogrid. This also was installed at 1000mm (3 ft) vertica
CASE
STUDY
Volume 10
Number 2
April 2007
14649 Highway 41 NorthEvansville, Indiana 47725
812-867-66321-800-772-2040FAX 812-867-0247www.nagreen.com
Rail Transit Line Expansion withSC250 Protects Environmentally
Sensitive PondOntario GO Transit works with Burlingtons Royal Botanical Garden in Rail Line Expansion
FAC
TS
The steep railway embankment needed to be stabilized during con-
struction of a third track. Sunfish Pond (foreground) also
required protection from sediment runoff.
-
7/28/2019 CS_10_2
2/2
spacing and was vertically offset from the primary grid by
500mm (1.5 ft).
Upon completion of the 10m (32 ft) high granular embank-
ment, the 1:1 slope was covered with 150mm (6 inches) of
topsoil, and hydroseeded with a mix of grasses.
In order to protect the vegetation and topsoil from short-termerosion and also provide long-term reinforcement for the
vegetation root matrix, the decision was made to cover the
entire slope with a turf reinforcement mat (TRM). The pro-
ject engineers with the help of Armtecs Erosion Solutions
Specialists chose North American Greens SC250 because of
its proven performance. The SC250 is a composite turf reinforcement mat comprised of two heavy-duty UV sta-
bilized outer nets, a corrugated center netting incorporated with organic straw/coconut fiber mechanically bond-
ed together. This TRM provides immediate erosion control via the natural (70% straw/30% coconut) matrix,
while the three dimensional netting structure provides permanent reinforcement to the root and stems of the veg-
etation.
To ensure proper installation of the SC250, the installers followed North American Greens DOT System, a
spray-on color-coded dot pattern which indicated exact placement of fasteners. In addition, proper overlapping
of adjacent SC250 panels and trenching the material in at the top of the slope offered optimum erosion control
performance. With the use of North American Greens Erosion Control Materials Design Software (ECMDS )
the project engineers were able to select the proper TRM and offer Go Transit and the Royal Botanical Gardens
a stable, cost effective design.
Results
The selection and installation of the proper products cou-pled with good growing conditions allowed for rapid ger-
mination of the seed mix through the SC250 C-TRM, and
a great start to a fully vegetated slope. Along with provid-
ing GO Transit the means to expand the railway system
and bring more rail traffic into Ontarios Lakeshore west
corridor, the project had additional benefits for
Burlingtons Royal Botanical Gardens. While the removal
of vegetation during construction was unsightly for visi-
tors and had the potential to harm Sunfish Pond, ultimate-
ly the Gardens was pleased to have the opportunity toremove non-native plantings that had established on the
embankment and replace them with native species that
historically would have existed in the area. By re-estab-
lishing native plantings near Sunfish Pond, the Royal
Botanical Gardens was able to improve the natural habitat
surrounding the area. While the rail expansion project at Sunfish Pond was only a small part of the larger billion
dollar railway expansion project funded by the Canadian Government and Ontarios Go Transit, it offered an
example of how green engineering practices could produce a successful result for all parties involved including
Mother Nature.
North American Green SC250 C-TRM was installed as a surface
stabilizer aimed at preventing surface erosion and promoting the
reestablishment of vegetation.
After only a few months, theSC250 reinforced railway
embankment was completely
revegetated, and Sunfish Pond
was well protected from the
potential of slope erosion and
sediment runoff.