Cryomodule for Crab Cavity Tests with SPS

24
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme, Grant Agreement 284404. Cryomodule for Crab Cavity Tests with SPS Shrikant Pattalwar Accelerator Science and Technology Centre STFC Daresbury Laboratory, UK 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013, Daresbury

description

Cryomodule for Crab Cavity Tests with SPS. Shrikant Pattalwar Accelerator Science and Technology C entre STFC Daresbury Laboratory, UK. 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013, Daresbury. Acknowledgements. This presentation is on behalf of the members of the Global WP4 team . - PowerPoint PPT Presentation

Transcript of Cryomodule for Crab Cavity Tests with SPS

Page 1: Cryomodule for Crab Cavity Tests with SPS

The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme, Grant Agreement 284404.

Cryomodule for Crab Cavity Tests with SPSShrikant Pattalwar

Accelerator Science and Technology CentreSTFC Daresbury Laboratory, UK

3rd Annual Hi-Lumi Meeting Nov 11-15, 2013, Daresbury

Page 2: Cryomodule for Crab Cavity Tests with SPS

2

Acknowledgements

STFC ASTeC, Technology, University of LancasterCERN Various DepartmentsLARP ODU+SLAC, BNL, FNAL

This presentation is on behalf of the members of the Global WP4 team

Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury

Page 3: Cryomodule for Crab Cavity Tests with SPS

3

Contents • Factors Influencing Design Requirements

• Achievements so far … Concept designs for Helium Vessel and Cryomodule

• Work in Progress

• Future Plans

• Conclusion

Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury

Page 4: Cryomodule for Crab Cavity Tests with SPS

4

Requirements

• Operating Temperature • Magnetic shielding• Helium Vessel • Couplers and Interfaces• Tuner mechanism• Dynamic Heat Load• ….

1. Cavity

• Two beam pipes• Heat load due to beams• Helium Vessel Geometry • Internal Layout• ….

2. LHC

• External Geometry• Third beam pipe ( SPS

Bypass)• Coupler Orientations • Integration with

Infrastructure• Operation

3. SPS Layout

Requirements for the cryomodule are influenced by various Factors

Talk # 92 by Rama Calaga and # 95 Alex Ratti

Talk # 100 by Alick Mcpherson# 106 by Ofelia Capatina

Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury

Page 5: Cryomodule for Crab Cavity Tests with SPS

5

Requirements continued

• Cooling Capacity at various temperatures

• Cooling Processes• Ports and Interfaces• Operating modes

4. Cryogenic Services

• Mechanical Design • Safety and Pressure Relief • Volumes, pipe sizes• Methods of QC/QA

5. Regulations and directives

6. Other

• Intermediate Tests (SM18) • Assembly Procedures• Instrumentation• Cost• R&D needs Talk # 102 by Laurent Tavian Talk # 105 by Ofelia Capatina

Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury

Page 6: Cryomodule for Crab Cavity Tests with SPS

6

Helium Vessel UK 4-Rod Cavity Cavity in He Vessel Parts of the Vessel

Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury

Courtesy : Graeme Burt and Ben Hall, ULAN Saclay-II type tuner

SPS beam pipe

LHC (dummy) beam pipe

Page 7: Cryomodule for Crab Cavity Tests with SPS

7

Cryoperm magnetic shields

OVC to coupler ISO K 500 spool pieces

Tuners

2 Phase He line

Top fill LHe line

Bottom fill LHe line

Motor magnetic shield

LHe level probes

Pipework for liquid nitrogen connections

Thermometry and wiring for entire string

Fully Assembled Cavity String (4R)

Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury

Courtesy : Tom Jones (STFC)

Page 8: Cryomodule for Crab Cavity Tests with SPS

8

Helium Vessel ODU Dipole cavity BNL Double QW cavity

Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury

Courtesy : HyeKyoung Park (ODU) Courtesy : Ofelia capatina (CERN)

Page 9: Cryomodule for Crab Cavity Tests with SPS

Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury 9

Cryomodule Schematic (P&ID) Courtesy : Andy May (ASTeC)

Page 10: Cryomodule for Crab Cavity Tests with SPS

10

2150mm 800mm

1520mmCryogenics interface

Additional ports for LOM extraction/instrumentation

2mm thick MuMetal Magnetic shield

Module positioning system

1050 AluminiumThermal shield (80K) Cooling loop TBD

Cryomodule Concept

More details in - Conceptual design of a Cryomodule for Crab Cavities for HiLumi-LHC S. Pattalwar, et al, MOP 087, SRF 2013, Paris

Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury

Design features• simplifies the assembly

procedures• provides sufficient access to

internal components during assembly and after installation

• FPC is used as the main support for the cavity string.

Page 11: Cryomodule for Crab Cavity Tests with SPS

Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury 11

Compatibility with SPS InfrastructureRequirements Concept Design

Page 12: Cryomodule for Crab Cavity Tests with SPS

12

1 Clean Room Operations• Assemble cavity string • Couplers assembled at 90o

• Beam pipe closed with gate Valves

2 Outside the clean Room• Load the cavity String from Side

3 Align the string with the vacuum chamber

4. Lift and assemble with top plate of the vacuum chamber

Assembly Sequence – Proposal 1 (Side Loading)

Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury

Page 13: Cryomodule for Crab Cavity Tests with SPS

13

ISO K clamp

80K300K

Mu Metal magnetic shield (blue).

80K thermal shield (green). 20mm allocated for MLI

Final Assembly

Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury

Page 14: Cryomodule for Crab Cavity Tests with SPS

14

1 Clean room OperationsCavity, Coupler and Beam pipe

2 Outside the clean RoomMounting on the top plate

3 Outside the clean RoomAssembly of the cold parts

4 Load from the top into the vacuum chamber

Assembly Sequence – Proposal 2 (Top Loading

Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury

Courtesy : Ofelia capatina (CERN)

Page 15: Cryomodule for Crab Cavity Tests with SPS

15

Final Assembly (Top Loading )

Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury

Page 16: Cryomodule for Crab Cavity Tests with SPS

16

RF Input

Cryo services

Sliding support table

Cryomodule in SPS

Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury

Conclusion First level constraints defined by SPS layout have been successfully overcome

The design appraocah• simplifies the assembly

procedures• provides sufficient access to

internal components during assembly and after installtion

• reduces overall manufacturing cost

Page 17: Cryomodule for Crab Cavity Tests with SPS

Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury 17

Common Design Approach UK 4-Rod

US Dipole

US Double QW

Conclusion – A common design approach to accommodate all the 3 cavity designs has been successfully developed.

• External Envelope• Cryogenic Interface• Cryogenic Process• Alignment (external and Internal) • …….

Challenges – Couplers and Tuners and their locations for the three designs are different.

For illustration only

Page 18: Cryomodule for Crab Cavity Tests with SPS

18

Work In Progress

• Coupler designs for HOMs and LOMs and their integration with Infrastructure• Magnetic Shielding • Alignment • Integration with Cryogenics and heat load management• Switch over with the SPS BY-PASS or with other cryomodule• Safety , Pressure Vessel Regulations etc.• Tests at SM-18• ........................• ........................

Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury

Page 19: Cryomodule for Crab Cavity Tests with SPS

Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury 19

HL per cryomodule HL @2 K [W] HL @ 80 K

(TS) Comment

Dynamic

Deflecting mode 5.0 - Confirmed? Other Order

Modes TBD TBD

RF Coupler TBD TBD Beam Current 0.5 Tentative

Static

Radiation (cavity +Phase Sep. Cold surface + Thermal

Shield

0.2 6.8

Rescaling from LHC o W/ m2 @ cold mass

o 1.7 W/ m2 @ Thermal shield

CWT

0.557(rad) + 0.892(cond) =

1.5W x 2 = 3.0

0.625(rad) + 5.926 (cond) =

6.6W x 2 = 12.6

1 heat intercept @ 80K in the middle

Supporting System 1.0 3.3 6 tie rods/cavity

RF Coupler

0.501(rad) + 0.853(cond) =

1.4W x 2 = 2.7

0.587(rad) + 5.662 (cond) =

6.3W x2 = 12.6

1heat intercept @ 80K in the middle

Cables & Instrumentation 1.0 - Tentative

Other order modes TBD TBD Design dependent

Totals ~13.4 + TBD ~34.9 +TBD

Heat Load Budget

Page 20: Cryomodule for Crab Cavity Tests with SPS

20

Compliance with Regulations - PED

Maximum LHe volume < 100 LMaximum Operating Pressure 0.8 barG

Max He pressure0.43 barG

Max pipe diameter (ID) < 25 mm

Max Pressure 5 bar??

Category 0 for LHC Category 1 for SPS tests

CC in LHC Pmax 0.5 bar

Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury

Page 21: Cryomodule for Crab Cavity Tests with SPS

21

Manufacturing Final testsDesign Acceptance TestsQ1 (M3) Q2 (M6) Q3 (M9) Q4(M12) Q5(M15) Q6(M18) Q7 (M21) Q8 (M24) Q8 (M24) Q8 (M24)

Cavity Development and Performance tests Couplers Manufacture Tests

C1 in manufacturing

C1 Bare cavity tests

Dressed C1 test

SM-18 RF test

C2 Bare cavity tests

Dressed C2 test

Install and Commsioning at SPS

Interim FAT Final FAT

He vessel design V1 in ManufacturingCryomodule Engineering V2 in Manufacturing

Design Ancillary systemsManufacturing of Ancillary systems

Design OVC

Manufacturing of OVC

Define Instrumentation System AssemblyDevelop QA/ PED/Assembly/Test procedures

Design performance Tests Manufacturing and Assembly

Install and Commsioning

at SPS

C2 in manufacturing

Concept Design Engineering DesignManufacturing

Acceptance Tests

March 2014 Commissioning

Future Plan (Expectations)

Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury

Jan 2016

Page 22: Cryomodule for Crab Cavity Tests with SPS

22

Conclusion

1. First level constraints defined by SPS layout have been successfully overcome

2. A common design approach to accommodate any of the 3 cavity designs has been successfully developed

3. Overall design process is at an advance stage .

4. Most of the remaining issues are well understood and solutions are being worked out through collaborative efforts

5. WP4 Global collaboration is working well and advancing in a right direction

Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury

Page 23: Cryomodule for Crab Cavity Tests with SPS

Thank You

23/

Page 24: Cryomodule for Crab Cavity Tests with SPS